IP #938
PROJECT NO. 938
2016 Northwood Lake Project
Res. 14‐77 05/12/14 Resolution for the Bassett Creek Watershed Management Commission to obtain a
feasibility study (improvement project 938)
Res. 14‐146 11/10/14 Resolution approving the 2016 Northwood Lake improvement project feasibility study
report (improvement project no. 938)
Item 11.2 02/17/15 Discussion on Northwood Lake storm water improvements (project no. 938).
2015‐123 07/27/15 Resolution approving the preparation of plans and specifications for the 2016 Northwood
Lake improvement project (improvement project 938)
2015‐131 08/24/15 Resolution approving a cooperative construction agreement between the city of New
Hope and the Bassett Creek Watershed Management Commission for construction of
storm water improvements at Northwood Lake (improvement project No. 938); and a sub
grant agreement for the Clean Water Partnership Project Grant
2015‐185 12/14/15 Resolution approving plans and specifications and ordering advertisement for bids for
the Northwood Lake storm water improvement project (project no. 938)
2016‐36 02/22/16 Resolution approving first amendment to the cooperative agreement with Bassett Creek
Watershed Management Commission for construction of storm water improvements at
Northwood Lake (improvement project no. 938)
2016‐37 02/22/16 Resolution awarding contract to Northdale Construction Company, Inc. for construction of
public improvement project 938 (Northwood Lake Storm Water Improvement Project)
2016‐87 05/27/16 Resolution approving a change order of $12,239.13 for replacement of Sanitary Sewer on
the Northwood Lake water quality project conjunctly with the 2016 Northwood South
Infrastructure project (improvement project nos. 938 / 974)
2017‐21 2/13/17 Resolution approving change order nos. 2, 3, and 4 totaling $70,343.54 for additional
irrigation box work, temporary fencing, and common excavation offsite for the
Northwood Lake Improvements Project (Improvement Project No. 938)
2018‐27 2/12/18 Resolution approving Change Order #5 totaling $10,314.04 for additional work at storm
manhole #20 for the Northwood Lake Improvements project (Improvement Project No.
938)
2018‐28 2/12/18 Resolution approving final pay request in the amount of $32,812.12 for the Northwood
Lake Improvements project and accepting the Northwood Lake Improvements Project
No. 938