Imp. Proj. #457ACOUNCIL
KWO11VA.3, 0 o k ;
0
Originating Department Approved for Agenda Agenda Section
Ord. & Res.
Manager 1 6-25-90
Item No.
By: Dan Donahue By: 10.2
1-031i'61,41 • I I 1 • 11 1 &A.
W G I PE•• N pin ilk Mr.30 am WRIze i k , Lem wo oif 47 VER •
jUniS • MENOMIMS • Milk •vo
The City received seven bids for Improvement Project 457A on June 22, 1990.
The City Engineer will present the results on Monday evening. The apparent
low bidder was Shingobee Builders Inc. at $183•,8 (Engineer's Estimate
$180,000). / e: ? cql Kk
MOTION BY SECOND BY A n 1/0 tn - I
TO:
Review: Administration: Finance:
CITY OF NEW HOPE
RESO=ON AWARDI14G CONTRACr
FOR THE 00NSIRUCITON •
SC•NCE IN• (JSTRY PARK SITE (2WU4G
AND PAR1KING LOr IMPF4VEMENTS
(DaWVEMENT PRO= NO. 457A)
BE IT RESOLVED by the City Council of the City of New Hope as follows:
1. That bids for the construction of Improvement Project 457A were duly opened
at the New Hope City Hall, 4401 Xylon Avenue North, at 11:30 a.m. on the
22nd day of June, 1990.
2. That advertisement for bids for the construction of said improvement was
published in the New Hope-Golden Valley Post, the official newspaper of the
City, on the 30th day of May, 1990, and in the Construction Bulletin on
the 1st and 8th days of June, 1990.
t
3. It is hereby found and determined by this Council that the bid of Shingobee
Builders Inc. for the construction of said project in the amount of
$183,923.86 is the lowest responsible bid submitted for the construction of
said improvement; that Bonestroo, Rosene, Anderlik & Associates, Inc.,
Engineers for the City, have recommended to this Council the said low bid
for the award of the contract for the construction to the designated lowest
responsible bidder.
4. The Mayor and Manager are authorized and directed to enter into an
improvement contract for the construction of said nprovement in the name
of the City with the lowest responsible bidder, subject to the said
contractor furnishing a public contractor's surety bond, conditioned as
required by law.
Adopted by the City Council of the City of New Hope, Hennepin County, Minnesota,
this 22nd day of June, 1990.
Mayor
Attest:
City Clerk (J
Our File No. 3471'
SCIENCE INDUSTRY PARK GRADING
PARKING LOT -457A
NEW HOPEMN
CONTRACTORS
1. PENN CONTRACTING
2. GAMMON BROS.
48 3* ALBER CONST.
HARDRIVES, INC.
5. DAVE PERKINS CONST.
6. TALBERG LAWN & LANDSCAPE
0 7 W.B.MILLER
8. MUNN BLACKTOP
9. P. & H. WAREHOUSE SALES
cr) DRIVEWAY DESIGN, INC.
11. STENGER EXC.CO.
12. ABLE FENCE, INC.
13. NYEN EXC.INC.
14. KEVITT EXC.
15. FENC-CO INC.
G.P. LAWN SPRINKLER SERVICE
17. CROWLEY COMPANY
19.
20.
BID TIME: C.S.D.T.
BID DATE:JUME 22, 1990
TOTAL BASE BID
N6. aDl- oc
c"
Engineers Estimate $180,000
June 25, 1990
Otto G. Bonestroo, P.E.
Robert W. Rosene, P.E.
Joseph C. Anderlik, P.E.
Marvin L. Sorvala, P.E.
Ricfiard E. Turner, P.E.
James C. Olson, P.E.
Glenn R, Cook, P.E.
Thomas E. Noyes, P.E.
Robert G. Schunicht, P.E.
Susan M. Eberlin, C.P.A.
City of New Hope
4401 Xyion Avenue North
New Hope, MN 55428
Attn: Daniel Donahue
Keith A. Gordon, P.E.
Richard W. Foster, P.E.
Donald C. Burgardt, P.E.
Jerry A. Bourdon, P.E.
Mark A. Hanson, P.E.
Ted K. Field, P.E.
Michael T Rautmann, P.E.
Robert R. Pfefferle, PE.
David O. Loskota, P.E.
Thomas W. Peterson, P.E.
Michael C. Lynch, PE.
James R. Maland, P.E.
Kenneth P. Anderson, P.E.
Mark R. Rolfs, P.E.
Robert C. Russek, A.I.A.
Thomas E. Angus, P.E.
Howard A. Sanford P.E.
Daniel J. Edgerton, P.E.
Mark A. Seip, RE,
Philip J. Caswell, P.E.
Ismael Martinez, P.E.
Mark a Wallis, P.E.
Re: Science Industry Park
Site Grading & Parking Lot Improvements - Project No. 457A
Softball & Soccer Field Lighting - Project No. 457B
Our File No.'s 3471, 34120
Dear Dan:
Thomas R. Anderson, A.I.A.
Gary F Rylander, P.E.
Miles B. Jensen, P.E.
L. Phillip Gravel III, P.E.
Rene C. Plumart, A.I.A.
Agnes M. Ring, AJC.P.
Jerry D. Pertzsch, P.E.
Cecilio Olivier, PE.
Charles A. Erickson
Leo M. Pawelsky
Harlan M. Olson
Bids were received September 22, 1990 for the above projects. Listed below is
the low bid for each project compared to the engineers estimate:
No. of Bids Engineers Low Bid
Estimate
Project
457A
(Grading) 6
$180,000.00
Project
4513
(Lighting) 4
110,000.00
Low Bid Contractor
$183,923,86 Shingobee
Builders Inc.
109,467.92 Total
Construction &
Equipment Inc.
$293,295.42
As noted the engineers estimate is slightly less than the low bid amount.
Although our firm has not specifically worked with each contractor, I have
spoke with each contractor and it appears they are each more than capable of
doing the work. Total Construction & Equipment Inc. is intending to provide
the Musco Lighting System which is the preferred system by the City.
Relative to the amended permit required from the Department of Natural
Resources, it is anticipated we will receive the amended permit the week of
July 4. I have spoke with Ceil Strauss at the DNR and she does not anticipate
any difficulty.
2335 West Highway 36 9 St. Paul, Minnesota 55113 ® 612 - 636 -4600
City of New Hope
Mr. Daniel Donahue
June 25, 1990
In summary, it's recommended each project be awarded to the respective low
bidder contingent upon the amended permit from the DNR being approved. If you
have any questions please contact this office.
Yours very truly,
BONESTROO, ROSENE, ANDERLIK & ASSOCIATES, INC.
Mark Hanson
MH:lk
2
CITY OF NEW HOPE
FIVE YEAR CAPITAL IMPROVEMNET BUDGET
FUND AVAILABILITY AND NET COST
FOR PERIOD 1988 -1992
FUND /DEPARTMENT YEA
DESCRIPTION ROAD & GEN FUND TRADE IN FIN. BY
--------------- REQUESTED COST---- -
CEN,
1989 1940 1991
---- -----
___ _ -- - - " -- 1992 BRIDGE SURPLUS OR SALE OPERATIONS REPLA
FIRE _ " ----- - - --
NOSE REPLACEMENT �- ' _'_O
- 0 - - -- 5,000
1992 --- -------- -- ---- ---- ---- ---• --- -•
5,000 p ____________________ _
FIRE GEAR REPLACEMENT 1992
FIRE PAGERS 5,400 0 0 0
1942 3,883 0 5,400
0 0 3,883 ,
TOTAL FIR ,D - -- -
�- SPARTMEI[T__ - • - --- --
$819,165 $532,233 $27,433 $24,633 $201,333 $28,533 ._ -•-_ - - - --
----------•-----
PARK & RECREATION INDUSTRIAL BALLFIEID 50 $500,000 56, $O
--
1988
PAR ECREATION RESURFACE TENNIS COURTS 8 10,000 66,000 ______ __ _______
1988 10,000 00 - 0 0
PARK & RECREATION HEATER FOR NORTHWOOD SHELTER lggg 0 0 0
PARK & RECREATION PAINTSTRIPPER 3,000 3,000 p p 0 e
1988 2,500 2,500 0
PARK & RECREATION UPGRADE BALLFIELDS- SUNNYHOLLOW 1988 6,000 6,000 p 0 0 c
0 p
PARK & RECREATI * ON FLOOR SCRUBBER 0 0
PARK & RECREATION UPGRADE BLEACHERS 1988 1,000 1,000 0 0
PARK & RECREATION AGRILIME FOR HOCKEY RINKS 1988 59000 5,000 0 0 0 0
PARK & RECREATION SAND VOLLEYBALL COURTS 1988 2,000 2,Q00 0 0
0 0
1988 2,000
PARK $ RECREATION DRINKING FOUNTAIN 2,000 p 0 0 �
PARK & RECREATION 3 HANDMOWERS 1988 2,200 2,200 0 0
1988 1,800 0 0
PARK & RECREATION HANDICAPPED ASSESSIBILITY 1,800 0 0 0 0
PARK & RECREATION OUTFIELD FENCES 1988 7,200 7,200 0 0
0 0
1988 1,000
PARK & RECREATION SKATE 7IlE FOR SHELTER 1,000 p p p p � -
PARK & RECREATION PLAYGROUND EQUIPMENT 1988 3,000 3,000 0 0 0
1988 21,500 0
PARK & RECREATION ICE SWEEPING BROOMS 2 1,500 0 0 0 0 --'�
PARK & RECREATION PLAYER BENCHES 1988 1,500 1,500 0 0
1988 2,000 0 0
PARK & RECREATION JORDAN PARK 2,000 0 0 0 0
PARK R. vrrDCA- - 1988 44,000 44 nnn
CITY OF NEW HOPE
MEMORANDUM
DATE: June 18, 1990
TO: Dan Donahue, City Manager
FROM: Shari French, Parks and Recreation Director
SUBJECT: FUNDING FOR INDUSTRIAL BALLFIELD
I suggest that the following funds in the 1990-91 CIP be dedicated
to the new ballfield:
From 1990 CIP:
Carry-over from 1989 $63,000
Irrigation 18,,000
Drinking fountain 2,200
Bleachers 3,500
Traffic park 20,0D0
Ballfield complex 85,000
Sealcoat park paths 5,000
From 1991 CIP:
Bleachers 3,500
Storage bldg. 50,000
Sun shelter 25,000
Sealcoat paths 5,000
From 1990 Street Budget:
Sealcoating surplus 0,000
From 1984 CIP Sinking Fund
Interest earnings 20,000
Larry Watts has said that there is money in the 1984 CIP Sinking
Fund. This money is from interest earnings. He said that there is
over $20,000 available here.
With all the above, we come to a total of $320,200. If bids come
a little higher, I suggest that Larry be consulted again as whether
the sinking fund could cover any more of the cost, if Council is
willing to spend the money.
, Y6 °I,4
Ci�1- f���ZNT�J
Originating Department
Parks and Recreation
Shari French
By:
Approved for Agenda Agenda Section
Consent
7/23/90
Item No.
By: I / 1 6.13
RESOLUTION ADJUSTING THE 1990 -91 CAPITAL IMPROVEMENT PROGRAM
AUTHORIZING THE TRANSFER OF $102,702.50 TO SCIENCE INDUSTRY PARK
SITE GRADING AND PARKING LOT IMPROVEMENTS (IMPROVEMENT PROJECT
This resolution will enable staff to use CIP funds to fund the new
ballfields grading and parking lot improvements (457) approved at
the 6/25/90 Council meeting. Funds budgeted in the 1990 CIP for
the project total $81,125. An additional $102,702.50 is needed.
Park Increase
1990 CIP Allocation
Fountain
Traffic Park
Sealcoat Park Paths
1991 CIP Allocation
Sealcoat Park Paths
Storage Bldg. for Ballfields
Sun Shelter
Site Grading & Lot Impr. 102,702.50
$102,702.50
Decrease
$2,200.00
20,000.00
502.50
5,000.00
50,000.00
25,000.00
$102,702.50
MOTION BY 2 4 SECOND BY L`'' L( )
Review: Administration:
Finance:
RFA -001
CITY OF NEW HOPE
RESOLUTION NO. 90 -136
RESOLUTION ADJUSTING THE 1990 -91
CAPITAL IMPROVEMENT PROGRAM AUTHORIZING TRANSFER
OF $102,702.50 TO SCIENCE INDUSTRY PARK SITE GRADING
AND PARKING LOT IMPROVEMENTS (PROJECT 457A)
WHEREAS, the City Is Capital Improvement Program was established in
the 1990 City Budget for the years 1990 and 1991; and
WHEREAS, Park priorities have changed; and
WHEREAS, Bids came in higher than anticipated for the Science
Industry Park; and
WHEREAS, the Capital Improvement Fund should be amended to reflect
these changes.
NOW, THEREFORE, BE IT RESOLVED, that the 1990 -91 Capital
Improvement Budget be amended as follows:
Park Increase Decrease
1990 CIP Allocation
Fountain
Traffic Park
Sealcoat Park Paths
1991 CIP Allocation
Sealcoat Park _Paths
Storage Bldg. for Ballfields
Sun Shelter
Site Grading ,& Lot Impr.
$102,702.50
$102,702.50
$2,200.00
20,000.00
502.50:
5,000.00
50,000.00
25,000.00
$102,702.50
Adopted by the City Council of the City of New Hope, Hennepin
county, Minnesota, this 23rd day of July, 1990.
4 aLe-z'
Mayor
Attest: /,, X -
City Clerk
I
Originating Department Approved for Agenda Agenda Section
I I Consent
Parks and Recreation 10/22/90 Item No.
B Y : Shari French By: 6.8
APPROVAL OF BILL SUBMITTED BY NSP FOR PAYMENT OF COST TO CONNECT
ELECTRICAL SERVICE TO SCIENCE INDUSTRIAL BALLFIELD (PROJECT 457A) -
$1,100.00
When plans were made to build the Science Industry Park ballfields
NSP told the City that it would charge to bring service from the
street to the transformer for electrical power. The bill has been
received in the amount of $1,100.
Staff recommends payment of the bill, charging Project 457A for the
expenditure.
MOTION BY
SECOND BY
TO:
Review:
Administration:
Finance:
NORTHERN STATES POWER COMPANY
414 NICOLLET MALL
MINNEAPOLIS, MN 55401 -1927
TELEPHONE: (612) 330 -7659
CITY OF NEW HOPE
8860 EAST RESEARCH CENTER ROAD
NEW HOPE, MN 55428
101690
OCT 16, 1990
03760 - 14.38.03 -09 -00
433394
$1,100.00
DESCRIPTION
INVOICE IN CONNECTION WITH EXTEND UNDERGROUND PRIMARY CABLE FRbM
TRANSFORMER SERVING THE PUBLIC WORKS BUILDING ON INTERNATIONAL
PARKWAY; OVER TO, AND UNDER EAST RESEARCH CENTER ROAD; AND THEN
UNDERGROUND TO TRANSFORMER BY THE SHELTER BUILDING
AMOUNT DUE: $ 1,100.00
TERMS: NET
CASH -
DUE ON
RECEIPT
OF THIS INVOICE
PLEASE RETURN
A COPY
OF THIS
INVOICE
WITH YOUR PAYMENT
COUNCIL
.
@c
Originating Department Approved for Agenda Agenda Section
Parks and Recreation 1 11/26/90 1 Consent
Shari French
Item No.
By: I By: 6.4
RESOLUTION APPROVING CHANGE ORDER #1 WITH SHINGOBEE BUILDERS, INC.
FOR IMPROVEMENT PROJECT NO. 457A (SCIENCE INDUSTRY PARK GRADING AND
PARKING LOT IMPROVEMENTS) IN THE AMOUNT OF $834.43.
A change order is necessary related to the Science Industry Park
project. The additional work involved providing for additional
quick couplers at the end of each sprinkler run for the underground
watering system. This will allow the system to be cleaned through
the quick couplers rather than the last sprinkler head. The total
cost of the change order is $834.43.
Staff recommends approval.
SECOND BY - C l
Review: Administration: Finance:
t1 A
CITY OF NEW HOPE
RESOLUTION NO. 90 -212
RESOLUTION APPROVING CHANGE ORDER # 1 WITH
SHINGOBEE BUILDERS, INC. FOR SCIENCE INDUSTRY PARK
GRADING AND PARKING LOT IMPROVEMENTS
(IMPROVEMENT PROJECT 457A)
IN THE AMOUNT OF $834.43
WHEREAS, The City of New Hope authorized on June 25, 1990,
Improvement Project 457A, for the contractual sum
of $183,923.86; and
WHEREAS, Additional quick couplers at the end of each sprinkler
run were deemed necessary to complete the project in
the best possible manner, totaling $834.43.
NOW, THEREFORE, BE IT RESOLVED, that the City Council of the City
of New Hope approves change order #1 to the contract with
Shingobee Builders, Inc. in the amount of $834.43 as part
of Improvement Project #457A (Science Industry Park
Grading and Parking Lot Improvements) which brings the
total contract to $184,758.29.
Adopted by the City Council of the City of New Hope, Hennepin
County, Minnesota, this 26th day of November, 1990.
e� , a��
Mayor
Attest: ���-� -�
City Clerk
November 12, 1990
City of New Hope
4401 Xylon Avenue N.
New Hope, Minnesota 55428
Attn: Shari French
Re: Science Industry Park
Grading and Parking Lot Improvements
Project No. 457A
Our File No. 3471
Dear Shari:
Attached is Change Order No. 1 for the above project. As noted this change order provides
for additional quick couplers at the end of each sprinkler run. This will allow the system to
be cleaned through the quick couplers rather than the last sprinkler head. It was
determined after the project was bid by public works to include the additional couplers.
We recommend approval of this change order in the amount of $843.43. If you have any
questions please contact me at this office. _2
Yours very truly,
I:i
ANDERLIK c4z ASS "OCIN - FES, 1 11 , 4C.
Encl.
A. Hanson
Ah
Otto G. Bonestroo, P.E.
Keith A. Gordon, P.E.
James R. Maland, P.E.
Thomas R. Anderson, A.I.A.
Bonestroo
Robert W. Rosene, P.E.
Richard W. Foster, P.E.
Kenneth P. Anderson, P.E.
Gary P Rylander, P.E.
Joseph C. Anderlik, P.E.
Donald C. Burgardt, P.E.
Mark R. Rolfs, P.E.
Miles B. Jensen, P.E.
A"
Rosene
Marvin L. Sorvala, P.E.
Jerry A. Bourdon, P.E.
Robert C. Russek, A.I.A.
L. Phillip Gravel III, P.E.
Richard E. Turner, P.E.
Mark A. Hanson, P.E.
Thomas E. Angus, P.E.
Rene C. Plumart, A.I.A.
James C. Olson, P.E.
Ted K. Field, P.E.
Howard A. Sanford, P.E.
Agnes M. Ring, A.I.C.P.
Glenn R. Cook, P.E.
Michael T Rautmann, P.E.
Daniel J. Edgerton, PE.
Jerry D. Pertzsch, PE,
A ssociates
Thomas E. Noyes, P.E.
Robert G. Schunicht, P.E.
Robert R. Pfefferle, P.E.
David O. Loskota, P.E.
Mark A. Seip, P.E.
Philip J, Caswell, P.E.
Cedlio Olivier, P.E.
Charles A. Erickson
Susan M. Eberlin, C.P.A.
Thomas W Peterson, PE.
Ismael Martinez, P.E.
Leo M. Pawelsky
Engineers $c Architects
Michael C. Lynch, P.E.
Mark D. Wallis, PE.
Harlan M. Olson
November 12, 1990
City of New Hope
4401 Xylon Avenue N.
New Hope, Minnesota 55428
Attn: Shari French
Re: Science Industry Park
Grading and Parking Lot Improvements
Project No. 457A
Our File No. 3471
Dear Shari:
Attached is Change Order No. 1 for the above project. As noted this change order provides
for additional quick couplers at the end of each sprinkler run. This will allow the system to
be cleaned through the quick couplers rather than the last sprinkler head. It was
determined after the project was bid by public works to include the additional couplers.
We recommend approval of this change order in the amount of $843.43. If you have any
questions please contact me at this office. _2
Yours very truly,
I:i
ANDERLIK c4z ASS "OCIN - FES, 1 11 , 4C.
Encl.
A. Hanson
Ah
4401 Xylon Avenue North New Hope, Minnesota 55428 Phone: 533 -1521
November 27, 1990
Shingobee Builders
279 N. Medina Street
Loretto, MN 55357
SUBJECT: CHANGE ORDER #1 - IMPROVEMENT PROJECT 457A
SCIENCE INDUSTRY PARK GRADING AND PARKING LOT IMPROVEMENTS
Enclosed are two fully executed copies of the above- ref e renced Change Order for
your records. Please forward one copy to your bonding company.
If you have any questions, please contact me.
Sincerely,
Valerie Leone
City Clerk
enc.
cc: City Engineer
Family Styled City For Family living
COUNCIL
!� • • • •
Originating Department Approved for Agenda Agenda Section
Parks and Recreation 1 8/12/91 1 Consent
Shari French Item No.
By: BY: / 6.5
ACCEPTANCE OF IMPROVEMENT PROJECT NO. 457SCIENCE INDUSTRY PARK
GRADING AND PARKING LOT IMPROVEMENTS (VICTORY PARK) AND
AUTHORIZATION OF FINAL PAYMENT
The grading and parking lot improvements for Victory Park have been
completed (Project 457). The project was constructed by Shingobee
Builders. Mark Hanson, City Engineer, has recommended acceptance
and staff have concurred.
The project cost has been increased by $9,641.66 due to additional
storm sewer needed along the railroad tracks (130 and changing
the four foot fence along the foul lines as bid to six foot fencing
for safety.
Staff recommends acceptance and release of final payment of
$5,669.76 as soon as the IC -134 form has been submitted to the City
Clerk.
M
��
, SECOND BY 112242�
Review:
Administration:
Finance:
1.'1TIf1
July 22, 1991
City of New Hope
4401 Xylon Ave. N.
New Hope, MN 55428
Attn: Ms. Shari French
Otto G. Bonestroo, P.E.
Robert W. Rosene, P.E.
Joseph C. Anderlik, P.E.
Marvin L. Sorvala, P.E.
Richard E. Turner, P.E.
Glenn R. Cook, P.E.
Thomas E. Noyes, P.E.
Robert G. Schunicht P.E.
Susan M. Eberlin, C.P.A.
Re: Science Industry Park
Grading and Parking Lot Improvements
Project No. 457
Our File No. 3471
Dear Shari,
Keieh A. Gordon, P.E.
Richard W. Foster, P.E.
Donald C. Burgardt, P.E.
Jerry A. Bourdon, P.E.
Mark A. Hanson, PE.
Ted K. Field, PE.
Michael T Rautmann, PE.
Robert R. Pfefferle, P.E.
David O. Loskota, P.E.
Thomas W. Peterson, P.E.
Michael C. Lynch, P.E.
James R. Maland, P.E.
Kenneth P. Anderson, P.E.
Mark R. Roifs, P.E.
Robert C. Russek, A.LA.
Thomas E. Angus, P.E.
Howard A. Sanford, P.E.
Daniel J. Edgerton, P.E.
Mark A. Seip, P.E.
Philip J. Caswell, PE.
Ismael Martinez, P.E.
Mark D. Wallis, P.E.
Thomas R. Anderson, A.I.A.
Gary F. Rylandef, P.E.
Miles B. Jensen, PE.
L. Phillip Gravel III, P.E.
Rene C. Plumart, A.I.A.
Agnes M. Ring, A.I.C.P
Jerry D. Pertzsch, P.E.
Cecilio Olivier, P.E.
Robert R. Dreblow, PE.
Gary W Morien, P.E.
Karen L. Wemeri, P.E.
Keith R. Yapp, P.E.
Charles A. Erickson
Leo M. Pawelsky
Harlan M. Olson
Attached is the 7th & Final Pay Request for the above project. The final contract amount is
$194,399.95 which is 5.2% ($9,641.66) above the bid amount plus Change Order No. 1. The
added cost is due to additional storm sewer constructed along the railroad tracks (130') and
changing the 4' high fencing along the foul lines as bid to 6' high. In addition, 379 cubic yards
of additional topsoil borrow was required.
All work has been satisfactorily completed and we recommend final payment once the IC -134
Forms have been submitted. Final payment is $5,669.76. If you have any questions, please
contact this office.
Yours very truly,
Encl.
3471.cor
2335 West Highway 36 # St. Paul, Minnesota 55113 a 612- 636 -46 00
REQUEST FOR PAYMENT
DATE: Jul 15, 1991
PLACE: New hop _Minn
PROJECT:Scienc Ind Park Gradi & Park Lot Impr
PROJECT NO.:4 FILE NO.: 3471
CONTRACTOR: Sc hinaobe e Bui lders, Inc.
ADDRESS: 279 N Medina Street
L MN 55357
REQUEST FOR PAYMENT NO.: 7 & FIN AL
SUMMARY:
1. Original Contract Amount
2. Change Order - ADDITION
3. Change Order - DEDUCTION
4. Revised Contract Amount
5. Value Completed to Date
6. Material on Hand
7. Amount Earned
8. Less Retainage 0 X
FOR PERIOD:
From: Feb. 7, 1991 To: July 8, 1991
SPE CIFIED CONTRA
COMPLETION DAT
$ 834.43
9. Sub -Total
10. Less Amount Paid Previously
11. AMOUNT DUE THIS REQUEST FOR PAYMENT NO.: 7 & F
OWNER APPROVAL:
By
By
Date:
3471PR
Recommended for Approval by:
$ 183,923.86
$ _ 184,758.29
$ 194 ,399.95
$
0.00
$ _ 194
$
_
0.00
$ 194,399.95
$ 188,730.19
$ _= 5.669.76
Approved By: SHINGOBEE B UILDERS, INC.
nt " acto T
By:
PROJECT: Industry Park Gradi & Park Lot Impr
PLACE: Ne Hope, Minnesota
CONTRACTOR: S chin go bee Builders, Inc.
STATEMENT OF WORK
Contract Item
Concrete curb and gutter removal
Site grading
Select topsoil borrow, CV
27 ", Class 3, RCP
Salvage and reinstall 27" RCP apron
12 ", Class 5, RCP
12" RCP apron
Class 2 rip rap
Granular filter material
Geotextile filter material
Reconstruct existing manhole
Type II CBMH w /R3067V casting
Salvage and reinstall hydrant
3" Class 52, DIP
Fittings
3" gate valve and box
1" capped blowout with tee
Infield aggregate
Class 5, 10OX crushed
aggregate base course
2331 bituminous base course mixture
Unit
L. F.
L. S.
C. Y.
L. F.
Each
L. F.
Each
C. Y.
C. Y.
S.Y.
L. F.
Each
Each
L. F.
Lbs.
Each
Each
Ton
Unit
Price
$1.08
28,080.00
8.64
54.00
1,620.00
32.40
324.00
81.00
16.20
5.40
431.57
1,080.00
1,188.00
12.96
1.08
432.00
270.00
11.34
PAYMENT NO.: 7 & FINAL
FILE NO.: 3471
DATE: July 15 1991
Est'd Quantity
uantity To Date
110
L S
1,500
30
1
30
1
8
6
16
1.9
1
1
320
240
1
2
320
Ton 9.50 1,500
Ton 19.39 200
Page 1
116
100X
1,879
32
1
162
2
8
6
16
1
1
320
240
1
1
370.11
Amount.
To Date
$125.28
28,080.00
16,234.56
1,728.00
1,620.00
5,248.80
648.00
648.00
97.20
86.40
1,080.00
1,188.00
4,147.20
259.20
432.00
270.00
4,197.05
1,648.08 15,656.76
199.19 3,862.29
3471PR
PROJECT:Scien Industry Par Gra & Park Lot Impr
PLACE: New Hope. Minne
CONTRACTOR: Sch obee Buil Inc.
STATEMENT O WO RK
Con tract Item
2341 bituminous wear course mixture
Bituminous material for mixture
Bituminous material for tack
4" solid line, white paint
Concrete curb & gutter, Design B612
2" thick bituminous walk
4" thick concrete walk
6" thick concrete curb under fence
4' chn.lk. fence, green vinyl coated
6' chn.lk. fence, green vinyl coated
4' chn.lk. fence gate,
10' wide green vinyl coated
6' chn.lk. fence gate,
4' wide green vinyl coated
Backstop
Building
Scoreboard
Player's bench
Drinking fountain and water service
Turf irrigation system
3" rock mulch
PAYMENT NO.: 7 & FINAL
FILE NO.: 3471
DATE: J 15. 1991
Page 2
3471PR
Unit
Est'd
Quantity
Amount
Unit
Price
Quantitj
To Date
To Date
Ton
21.60
200
200.69
4,334.90
Ton
129.60
22
22.05
2,857.68
Gal.
2.16
110
120
259.20
L.F.
0.11
1,100
1,015
111.65
L.F.
7.45
1,150
1,016
7,569.20
S.F.
0.35
11,950
11,880
4,158.00
S.F.
1.30
3,200
3,261
4,239.30
S.F.
4.86
900
912
4,432.32
L.F.
11.12
440
L.F.
13.45
680
1,092
14,687.40
Each
572.40
1
1.5
858.60
Each
378.00
2
2
756.00
L.S.
3,105.00
L S
100X
3,105.00
L.S.
8,297.64
L S
100X
8,297.64
L.S.
4,708.80
L S
100X
4,708.80
Each
354.24
2
2
708.48
L.S.
2,786.40
L S
100X
2,786.40
L.S.
10,800.00
L S
100X
10,800.00
S.Y.
7.41
70
31.5
233.42
Page 2
3471PR
PROJECT:Scie Industr Park _Gradin & Park Lot Impr
PLACE: New HODe. M innesot a
CONTRACTOR: Sc hinaobe e Builder Inc.
STATEMEN OF W ORK
Unit
Contr Item Unit P rice
Marshall seedless ash Each 234.36
Black Hills spruce Each 159.84
Goldflame spirea Each 35.64
Juniper - Hughes Each 17.82
Seed w /3" existing topsoil,
PAYMENT NO.: 7 & FINAL
FILE NO.: 3471
DATE: July 15, 1991
Est'd
Quantity
Amount
(qu antity
To Date
To Date
18
16
3,749.76
4
4
639.36
4
4
142.56
3
3
53.46
mulch & fertilizer Acre 1,933.20 2
Sod with 3" existing topsoil S.Y. 1.19 18,000
Silt fence L.F. 2.16 800
TOTAL, BASE BID WORK
CHANGE O RDER NO. 1 - A QUICK COUPLERS
Quick couplers for turf
irrigation system L.S. $834.43 1
TOTAL BASE BID
TOTAL CHANGE ORDER NO. 1
TOTAL WORK COMPLETED TO DATE
2.64 5,103.65
18,000 21,420.00
900 1,944.00
$193,565.52
1
$193,565.52
834.43
$194,399.95
$834.43
Page 3
3471PR
CONTRACTOR
TOTAL BASE BID
ADDENDUM NO. 1
SCIENCE INDUSTRY PARK
SITE GRADING & PARKING LOT IMPROVEMENTS
CITY PROJECT NO. 457A
FILE NO. 3471
NEW HOPE, MINNESOTA
June 19, 1990
OPENING TIME: 11 :30 A.M., C.D.S.T_.
OPENING DATE: Friday, June 22, 1990
ADDENDUM NO. 1
PLAN SHEET 6/6
The backstop and fencing details which notes "Fencing Posts 5' Spacing
(Typical)" shall read "Fencing Posts 10' Spacing (Typical) ".
BONESTROO, ROSENE, ANDERLIK & ASSOCIATES, INC.
2335 WEST TRUNK HIGHWAY 36
ST. PAUL, MINNESOTA 55113
3471S
"M
t � r
23,000. Water Alain - Specific Requirements
General Requirements
24,000. Severs - Specific Requirements
General Requirements
Plate
1 -16
'Type II Catch Basin Manhole
Plate
1 -25
Bedding Methods for RCP, VCP,
& DIP
Plate
1 -25A
Improved Foundation for RCP,
VCP, & DIP
Plate
1 -28
Flared End Section and Trash
Guard
Plate
2 - 1A
Gate Valve & Box and Hydrant
Installation
Plate
2 -9
Concrete Thrust Blocking
Plate
4 -1
Concrete Curb and Gutter
Plate
4 -3
Pedestrian Curb Ramp
Plate
4 -9
B618 Curb & Gutter Construction
at Catch Basin
Plate
SP -60
Concrete Collar on Type II Catch
Basin
Plate
SP -89
Silt Fence Erosion Control
Soils Investigations
Supplemental Conditions of the Contract
Conditions of the Contract
r
►:
F
3471S
ADVERTISEMENT FOR BIDS
Sealed bids will be received by the City of New Hope, Minnesota in the City
Hall at 4401 Xylon Avenue N. until 11:30 A.M., C.D.S.T., on Friday, June 22,
1990, at which time they will be publicly opened and read aloud for the fur-
nishing of all labor and materials and all else necessary for the following:
SCIENCE INDUSTRY PARK - SITE GRADING a PARKING LOT IMPROVEMENTS
PROJECT NO. 457A
10,000 cu.yds. Common Excavation
LUMP SUM Irrigation for Softball & Soccer Field
LUMP SUM Backstop and Outfield Fencing for Softball Field
3,500 Sq.yds. Bituminous Surfacing
608 Lin.ft. B612 Concrete Curb
4.0 Acres Sodding and Seeding
with miscellaneous storm severs, landscaping
and correlated appurtenances.
Plans and specifications, proposal forms and contract documents may be seen at
the office of the City Clerk, New Hope, Minnesota, and at the office of
Bonestroo, Rosene, Anderlik & Associates, Inc., Consulting Engineers, 2335 W.
Trunk Highway 36, St. Paul, Mn. 55113.
Each bid shall be accompanied by a bidder's bond naming the City of New Hope
as obligee, certified check payable to the Clerk of the City of New Hope or a
cash deposit equal to at least five percent (5Z) of the amount of the bid,
which shall be forfeited to the City in the event that the bidder fails to
enter into a contract.
The City Council reserves the right to retain the deposits of the three lowest
bidders for a period not to exceed 45 days after the date and time set for the
opening of bids. No bids may be withdrawn for a period of forty-five (45)
days after the date and time set for the opening of bids.
Payment for the work will be by cash or check.
Contractors desiring a copy of the plans and specifications and proposal forms
may obtain them from the office of Bonestroo, Rosene, Anderlik & Associates,
Inc., upon payment of a deposit of $30.00. See "Information to Bidders" for
plan/specification deposit refund policy.
The city Council reserves the right to reject any and all bids, to waive
irregularities and informalities therein and further reserves the right ti
award the contract to the best interests of the City.
Daniel Donahue, Manager
City of New Hope, Minnesota
34715
a) Were a prime bidder who submitted a bona-fide bid to the owner, or
b) Submitted quotes to at least two prime bidders which are identified
with the returned plans and ,ire- ifications,
The following- Planholders need not return plans and specifications in order to
receive a refund of deposit:
a) Low prime bidder, or
b) Successful low subcontractors and suppliers who notify the
receptionist within 15 days of the bide
q�
Shingobee Builders Inc.
CONTRACTOR
$183,923.86
TOTAL BASE BID
PROPOSAL FOR
SCIENCE INDUSTRY PARK
SITE GRADING & PARKING LOT IMPROVEMENTS
CITY PROJECT NO. 457A
FILE NO. 3471
NEW HOPE, MINNESOTA
1990
OPENING TIME: 11:30 A.M. C.D.S.T.
OPENING DATE: Friday, June 22, 1990
Honorable City Council
City of New Hope
4401 Xylon Avenue North
New Hope, Minnesota 55428
Dear Council Members:
The undersigned, being familiar with your local
conditions, having made the
field inspections and investigations deemed necessary,
having studied the
plans and specifications for the work including
Addenda Nos. 1 and being
familiar with all factors and other conditions
affecting the work and cost
thereof, hereby proposes to furnish all labor,
tools, materials, skills,
equipment and all else necessary to completely
construct the project in
accordance with the plans and specifications on
file with your Clerk and
Bonestroo, Rosene, Anderlik & Associates, Inc.,
2335 W. Trunk Highway 36, St.
Paul, Minnesota 55113, as follows:
110 Lin.ft. Concrete curb and gutter removal @
One DOLLARS Eight
CENTS $ 1.08 /lin.ft. $
118.80
LUMP SUM Site grading @
Twenty -eight Thousand, Eighty DOLLARS No
CENTS LUMP SUM $
28,080.00
1,500 Cu.yds. Select topsoil borrow, CV @
Eight DOLLARS Sixty -four
CENTS $ 8.64 /cu.yd. $
12,960.00
30 Lin.ft. 27 ", Class 3, RCP @
Fifty -four DOLLARS No
CENTS $ 54.00 /lin.ft. $
1,620.00
1 Each Salvage and reinstall 27" RCP
apron @
One Thousand Six Hundred
Twenty DOLLARS No
CENTS $1,620.00 /each $
1,620.00
30 Lin.ft. 12 Class 5, RCP @
Thirty -two DOLLARS Forty
CENTS $ 32.40 / lin.ft. $
972.00
1 Each 12" RCP apron @
Three Hundred Twenty -four DOLLARS No
CENTS $ 324.00 /each $
324.00
P -1
8
Cu.yds.
Class 2 rip rap @
Eighty -one
DOLLARS No
CENTS
$ 81.00
/cu.yd. $
648.00
6
Cu.yds.
Granular filter material @
Sixteen
DOLLARS Twenty
CENTS
$ 16.20
/ cu.yd. $
97.20
16
Sq.yds.
Geotextile filter material @
Five
DOLLARS Forty
CENTS
$ 5.40 /sq.yd. $
86.40
1.9
Lin.ft.
Reconstruct existing manhole @
Four Hundred Thirty -one DOLLARS Fifty -seven
CENTS
$ 431.57
/lin.ft. $
819.98
1
Each
Type II catch basin manhole w /R3067V
casting @
One Thousand, Eighty
DOLLARS No
CENTS
$1,080.00
/each $
1,080.00
1
Each
Salvage and reinstall hydrant
@
One Thousand Eighty
-eight DOLLARS No
CENTS
$1,188.00
/each $
1,188.00
320
Lin.ft.
3 ", Class 52, DIP @
Twelve
DOLLARS Ninety -six
CENTS
$ 12.96
/lin.ft. $
4,147.20
240
Lbs.
Fittings @
One
DOLLARS Eight
CENTS
$ 1.08
/lb. $
259.20
1
Each
3 gate valve and box @
Four Hundred Thirty -two DOLLARS No
CENTS
$ 432.00
/each $
432.00
2
Each
1" capped blowout with tee @
Two Hundred Seventy
DOLLARS No
CENTS
$ 270.00
/each $
540.00
320
Ton
Infield aggregate @
Eleven
DOLLARS Thirty -four
CENTS
$ 11.34
/ton $
3,628.80
1,500
Ton
Class 5, 100X crushed aggregate base
course @
Nine
DOLLARS Fifty
CENTS
$ 9.50
/ton $
14,250.00
200
Ton
2331 bituminous base course mixture @
Nineteen
DOLLARS Thirty -nine
CENTS
$ 19.39/ton
$
3,878.00
200
Ton
2341 bituminous wear course mixture @
Twenty -one
DOLLARS Sixty
CENTS
$ 21.60
/ton $
4,320.00
22
Ton
Bituminous material for mixture @
One Hundred Twenty -nine DOLLARS Sixty
CENTS
$ 129.60
/ton $
2,851.20
110
Gals.
Bituminous material for tack @
Two
DOLLARS Sixteen
CENTS
$ 2.16 /gal.
$
237.60
1,100
Lin.ft.
4" solid line, white paint @
No
DOLLARS Eleven
CENTS
$ 0.11 /lin.ft.
$
121.00
1,150
Lin.ft.
Concrete curb and gutter, Design B612
@
Seven
DOLLARS Forty -five
CENTS
$ 7.45 /lin.ft.
$
8,567.50
P -2
11,950 Sq.ft. 2" thick bituminous walk @
No
DOLLARS Thirty_
CENTS $ 0.35 ft. $
4, 182.50
3,200 Sq.ft.
4" thick concrete walk @
On
DOLLARS Thirty
CENTS $ 1.30_/ $
4,160.0
900 Sq.ft.
6" thick concrete curb under
fence @
Four
DOLLARS Eighty -six
C $ 4. Isq.ft $
4,374.00
440 Lin.ft.
4' chain link fence, green vinyl coated @
E leven
DOLLARS Twel
CENTS $ 11.12 lin. .$
4,892.
680 Lin.ft.
6' chain link fence, green vinyl coated @
Thirte
DOLLAR Forty -five
CENTS 13.45 /lin .$ 9,146
1 Each
4' chain link fence gate (10'
wide) green vinyl coated @
Five Hundred S eventy -two DOLLARS Forty
CENT 572.40 each
572.40
2 Each
6' chain link fence gate (4'
wide) green vinyl coated @
Three Hundred Sevent DOL LAR S No
CENTS $ 3 �$
756.00
LUMP SUM
Backstop @
Three Thousa
One Hund red Five DOLLA
No CENT LUMP SUM
3105.0
LUMP SUM
Building @
Eight Thousand
Two Hundred
Ninety -se
DO Sixty-four C ENTS L UMP SUM
8
LUMP SUM
Scoreboard @
Four Thousand Seven
Hundred
_ Eight
D OLL ARS E ight y C ENTS LUM SUt L_�
4 ,708.80
2 Each
Player's bench @
Three Hundred Fifty -four DOLLARS T wenty -four
CE NUS 354.24 /e ach
708.48
LUMP SUM
Drinking fountain and water service @
Two Thousand Seven
Hundred
Eighty -six
DOLLARS Forty
CE NTS LUMP SUM $
2,786.40
LUMP SUM
Turf irrigation system @
Ten T housand Eight H DOLLARS No
CENTS LUMP SUM $ 10,800.0
70 Sq.yds.
3" rock mulch @
Seven
DOLL Forty -one
CENTS $ 7 /sq.yd. $
518.70
18 Each
Marshall seedless ash @
Two H Thirty-four DOLLARS Thirty -six
CENTS $ 234.36/each ^
4,218
4 Each
Black Hills spruce @
One Hundred Fifty - ni ne D OLLA RS Eighty - four
C 159.54Leach
6 39.36
4 Each
Goldflame spirea @
Thi rty -
DOLLARS Sixty -nine
CENZ§ 3 5.69 /each $
14
3 Each
Juniper - Hughes @
Seventeen
DOLLARS Eighty -two
CENTS $ 17.82 /each $
53.46
P -3
3471pr
2.0 Ac. Seed w /3" existing topsoil, mulch & fertilizer @
One Thousand Nine Hundred
Thirty -three DO Twenty CENTS $1,9 $ 3,866.40
18,000 Sq.yds. Sod with 3" existing topsoil @
One DOLLARS Ninetee CENT 1.19 /sq.yd. $ 21.
800 Lin.ft. Silt fence @
Two DOLLARS Sixteen CENTS 2.16 (lin.ft. 1,728.0
TOTAL BASE BID ..............................$ 183
The final amount of the contract shall be determined by multiplying the final
measured quantities of the various items actually constructed and installed by
the unit prices stated therefor, in the manner prescribed in the specifica-
tions. However, the low bidder shall be determined by adding the sums result-
ing from multiplying the quantities stated by the unit prices bid therefor.
Accompanying this bid is a bidder's bond, certified check or cash deposit in
the amount of five percent (5z) DOLLARS CENTS ($ )
which is at least five percent (5X) of the amount of my /our bid made payable
to the City of New Hope, Minnesota, and the same is subject to forfeiture in
the event of default on the part of the undersigned or failure on the part of
the undersigned to execute the prescribed contract and bond within fifteen
(15) days after its submittal to me /us.
In submitting this bid it is understood that the Owner retains the right to
reject any and all bids and to waive irregularities and informalities therein
and to award the contract to the best interests of the Owner.
In submitting this bid it is understood that payment will be by cash or check.
It is understood that bids may not be withdrawn for a period of 45 days after
the date and time set for the opening of bids. It is understood that the
Owner reserves the right to retain the certified check or bond of the three
lowest bidders as determined by the Owner for a period not to exceed 45 days
after the date set for the opening of bids.
Respectfully submitted,
279 North Medina Street
Address
Lore MN 55357
City, State & Zip Code
612 - 479 -1300
Telephone No.
(A Corporation)
Shingobe Builders I nc. (An Individual)
Name of Bidder (A Partnership)
By Gae B. Veit
Title President
Gae B. Veit
Printed Name of Signer
P -4
3471pr
1700. ADJUST MISCELLANEOUS STRUCTURES
General Requirements
1700.1. DESCRIPTION: This work shall consist of adjusting manholes, removing
and replacing frames, adjusting catch basins and gate valve boxes.
1700.2. LOCATION: The plans indicate the locations of each manhole, catch
basin and gate valve within the project. The necessary vertical adjustments
will be determined by the Engineer, and generally as indicated on the schedule
of adjustments.
The Contractor shall be responsible for the protection of all existing
structures during the course of the work. The Engineer shall assist with the
initial location of all manholes, catch basins and gate valve boxes.
The Contractor along with the Engineer and a representative of the Owner shall
inspect all manholes, catch basins and gate valve boxes prior to beginning
construction. Any foreign material found in these structures will be removed
immediately by the Owner's forces. Thereafter, the Contractor will be
responsible for removing any such foreign material which may enter the
structures during the construction period.
1700.3. CONSTRUCTION REQUIREMENTS:
1700.3.1. Adjust Manhole & Catch Basin Frames; .. Where existing frame is
within 0.10 feet of plan grade no adjustment is to be made. In such cases the
crown or gutter shall be either lowered or raised, as the case may be, to put
the street and frame at the same grade.
Where the frame must be adjusted upward the Contractor shall accomplish this
adjustment with standard concrete adjustment rings of the same size as the
cone or slab opening. Each adjusting ring shall be placed in a full mortar
bed with the frame also resting in a full mortar bed. Adjusting rings needed
to raise the casting to grade shall be incidental to the adjust item.
Where the frame is to be adjusted downward, this shall be accomplished by
removing the necessary number of adjustment rings from the structure. The
frame shall then be reset in a full mortar bed to grade.
Regardless of the direction of adjustment, no shims
allowed. The minimum thickness of all mortar joints
inch with a maximum allowable thickness of 1/2 inch. All
the joint shall be wiped clean from the inside of all
a - ranhole castings must be replaced prior to the placing
course.
iy material will be
shall be at least 1/4
excess mortar from
rings and frame. All
of the final wear
3/89-GENERAL
Copyright 1989
Bonestroo, Rosene, Anderl
& Associates, Inc. I
Care shall be taken to prevent sand, chunks of concrete or any other debris
from entering the structures.
1700.3.2. Remove and Replace Manhole and Catch Basin Frames: Where included
in the proposal or the Specific Requirements of Section 1700, the Engineer may
elect to have the Contractor remove all manhole and catch basin castings and
rings if any at the beginning of the construction work. The Contractor then
shall cover the openings with suitable steel plates and continue to construct
and compact the subbase and base courses. Prior to placing the curbing or
final wear course, the Contractor shall raise all structures to final grade
following all construction requirements outlined in 1700.3.1. drainage into
catch basins must be maintained during the time the casting is removed.. During
the same time period, the Contractor shall be responsible to keep surface water
and dirt from entering the sanitary sewer system. Adjusting rings needed to
raise the casting to grade shall be incidental to the remove and replace item.
1700.3.3. Reconstruct Manhole & Catch Basins: Where the Engineer requires, or
where it is impossible to adjust the structure with the addition or removal of
adjustment rings, reconstruction will be necessary. In such cases it will be
necessary to add or remove manhole sections. Pre-cast manhole joints shall be
rubber O-ring gasket type to match existing joint.
In absence of, the O-ring joint, older style manhole joints shall be sealed
using a material similar to Ram-Nek or equal gasket material applied in
accordance with manufacturer's recommendation.
1700.3.4. Adjust Valve Boxes: Valve boxes shall be adjusted to grade prior to
the placing of the final wear course. Thorough tamping of the material around
the valve box is required. All valve boxes are the sectional screw-threaded
adjustable type.
1700.3.5. Valve Box Extensions® Where valve boxes cannot be adjusted without
the use of extensions this item will be necessary. The contractor shall remove
the upper sections, place the necessary extension and replace the upper
section. Thorough tamping of material around the valve box is required. Valve
box extensions that fit inside the regular top section are not acceptable.
3/89-GENER&L
Copyright 1989
Bonestroo, Rosene, Anderlik
& Associates, Inc.
1700.4.4. Adjust Valve Boxes: Adjusting valve boxes will be measured by the
number of valve boxes adjusted.
1700.4.5. Valve Box Extensions: Valve box extensions shall be measured by the
lineal feet of extensions furnished and installed.
1700.5. BASIS OF PAYMENT: Payment for manhole and valve adjustments at the
contract unit price shall be payment in full for all costs incidental
o these items.
Payment shall be made based on the following schedule:
Item No. Item Unit
1700.501 Adjust Manhole & Catch Basin Frames Each
1700.502 Remove and Replace Manhole
& Catch Basin Frame Each
1700.503 Reconstruct manhole Lin.ft.
1700.504 Adjust Valve Boxes Each
1700.505 Valve Box Extensions Lin.ft.
End of Sectic1#1
1700-3 1
3/89-GENERAL
Copyright 1989
Bonestroo, Rosene, Anderlik
& Associates, Inc.
23,000. WATER MAIN
General Requirements
23,000.1. DESCRIPTION: This work shall consist of the construction of water
mains in accordance with the requirements of the Contract. Under the number-
ing system used herein number 23,000.2. - 23,000.2.G inclusive, deal with
MATERIALS; 23,000.3. - 23,000.3.L8 inclusive, deal with CONSTRUCTION REQUIRE-
MENTS; 23,000.4. - 23,000.4.1. inclusive, deal with METHOD OF MEASUREMENT AND
PAYMENT. It is intended that when the Standard Specifications do not cover
the subject matter necessary to be covered that the additional numbers in the
appropriate section may be utilized in the "Specific Requirements" and the
numerical sequence preserved.
23,000.1.A. WORK INCLUDED: The Contractor shall, unless otherwise specified,
furnish all materials, equipment, tools and labor necessary to do the work
required under his contract and unload, have and distribute all pipe, fit-
tings, valves, hydrants and accessories. The Contractor shall also excavate
the trenches and pits to the required dimensions; sheet, brace and support the
adjoining ground or structures where necessary; handle all drainage or ground
water; provide barricades, guards, and warning lights; lay and test the pipe,
fittings, valves, hydrants and accessories, backfill and consolidate the
trenches and pits; maintain the surface over the trench, remove surplus
excavated material; and clean the site of the work.
The Contractor shall also furnish all equipment, tools, labor and materials
required to rearrange sewers, conduits, ducts, pipes and other structures
encountered in the installation of the work. All the work to completely
construct the water facilities shall be done in strict accordance with the
contract documents to which these General Requirements are a part.
23,000.1.B. SPECIFICATION REFERENCE: In these General Requirements reference
is made to the Minnesota Department of Transportation Specifications which
shall mean the "Standard Specifications for Construction, 1988 Edition ", and
subsequent amendments.
23,000.2. MATERIALS: The materials used in this work shall be new and
conform to the requirements for kind and size of material specified herein or
as altered in the "Specific Requirements ", "Special Provisions" and "Proposal ".
23,000.2.A. DUCTILE IRON PIPE: All ductile iron pipe shall be in accordance
with AWWA C151 of the Class as shown on the plans, "Specific Requirements ",
and /or "Proposal ". All pipe shall be furnished with standard thickness cement
mortar lining conforming with AWWA C104. All pipe shall have push -on joints
as specified in AWWA 0111 and shall be electrically conductive.
WK111Zl7i
23000G
Copyright 1990
Bonestroo, Rosene, Anderlik
& Associates, Inc.
23,000.2.B. CAST IRON FITTINGS: All fittings shall be mechanical joint
unless otherwise indicated and shall be in accordance with AWWA 0110. All
fittings shall be designed for not less than 250 psi working pressure and
shall have a standard thickness cement mortar lining conforming with AWWA
C104. Ductile iron compact fittings as specified in 0153 with standard thick-
ness lining are acceptable in lieu of cast iron fittings.
23,000.2.C. RUBBER GASKETS: Rubber gaskets for mechanical joints and push-on
joints shall conform to AWWA C111 and shall be designed and manufactured to
exact dimensions to assure a liquid-tight joint. All joints shall be in-
stalled with an electrical contact through every joint.
23,000.2.D. FIRE HYDRANTS: All hydrants shall be of a uniform make. The
following information will be furnished in the "Specific Requirements": (1)
Size of valve opening; (2) Depth of trench and cover; (3) No. and size of hose
connections; (4) No. and size of steamer connections; (5) Size and type of
pipe connections; (6) Direction of opening; (7) Type of threads, hose connec-
tions; (8) Type of threads, steamer connection; (9) Shape and size of opera-
ting nut; (10) open or closed drain holes; (11) Hydrant accessories such as
flags, wrenches or drain pumps.
23,000.2.E. GATE VALVE AND BOX: Gate valves shall be bronze mounted, iron
body valves conforming with requirements of AWWA 509. All valves shall have
O-ring seals with non-rising stems and shall open to the left. Valves shall
be equipped with mechanical joint ends in accordance with AWWA 0111.
Valve boxes shall be cast iron, screw-type, adjustable for 7-1/2 foot depth of
cover. Valves and boxes shall be considered as integral units. Gate valve
boxes shall be three piece, Clow F-2450H, Mueller J-10380, or equal.
23,000.2.F. BUTTERFLY VALVE AND BOX: Butterfly valves shall be cast iron
body rubber seated, tight closure valves in accordance with AWWA 0504.
Butterfly valves shall be furnished with mechanical joint ends conforming to
AWWA 0111.
The valve operator is an integral part of the butterfly valve and shall be
constructed to operate without maintenance under ground water conditions.
Valve operators shall be manufactured by the valve manufacturer 0 and/or in
valve sizes 20 inch diameter and larger shall be equal to 90 worm gear
actuators as manufactured by Limitorque Corporation or equal for buried
service.
Valve boxes shall be cast iron and shall be two or three piece type with screw
adjustable top section for 7-1/2 foot depth of cover.
WINNHW-J
2300OG
Copyright 1990
Bonestroo, Rosene, Anderlik
& Associates, Inc.
23,000.2.G. GRANULAR MATERIALS: Materials used for improved pipe foundation
of pipe bedding shall meet the requirements of Mn/DOT Specification 3149H
Course Filter Aggregate, except that hard, durable crushed carbonate quarry
rock may also be used. The material shall have the following crushing
requirements: Not less than 50Z of the material, by weight, that is retained
on the No. 4 sieve shall have one or more crushed faces.
23,000.3. CONSTRUCTION REQUIREMENTS:
23,000.3.A. INSPECTION:
23,000.3.A1. Of Materials at Delivery Point: During the process of unload-
ing, all pipe and accessories shall be inspected by the Contractor for loss or
damage in transit.
23,000.3.A2. Field Inspection: All pipe and accessories shall be laid,
jointed, disinfected and tested for defects and leakage in the manner herein
specified.
23,000.3.A3. Disposition of Defective Material: All material found during
the progress of the work to have cracks, flaws or other defects will be
rejected by the Engineer and the Contractor shall promptly remove from the
site of the work such defective material.
23,000.3.B. CONTRACTOR'S RESPONSIBILITY FOR MATERIAL:
23,000.331. Responsibility for Material Furnished by The
Contractor shall be responsible for all material furnished by him and he shall
replace at his own expense all such material that is found to be defective in
manufacture or that has become damaged in handling after delivery by the
manufacturer. This shall include the furnishing of all material and labor
required for the replacement of installed material discovered defective prior
to the final acceptance of the work.
23,000.3.B2. Responsibility for Safe Storage: The Contractor shall be
responsible for the safe storage of material furnished by or to him and
accepted by him and intended for the work, until it has been incorporated in
the completed project.
23,000.3.C. HANDLING PIPE AND ACCESSORIES:
23,000.3.01. General: Pipe and other accessories shall, unless otherwise
directed, be unloaded at the point of delivery, hauled to and distributed at
the site of the project by the Contractor. They shall at all times be handled
with care to avoid damage.
2300OG
Copyright 1990
Bonestroo, Rosene, Anderlik
& Associates, Inc.
2300OG
Copyright ' • 1 '
Associates,
2300OG
Copyright 1990
Bonestroo, Rosene, Anderlik
& Associates, Inc.
230000
Copyright 1990
Bonestrooa Rosee, Anderlik
& Associates, Inc.
been laid, tested for defects and repaired if necessary, and the earth around
it compacted to a depth of one foot or over the top of the pipe. It shall be
the Contractor's responsibility and duty to be familiar with local and state
laws and municipal ordinances relating to this type of work and he shall
assume the responsibility for compliance therewith.
23,000.3.Ell. Manner of Piling i Excavated Material: All excavated material
shall be piled in a manner that will not, endanger the work and that will avoid
obstructing sidewalks and driveways. Gutters shall be kept clear or other
satisfactory provisions made for street drainage.
23,000.3.E12. Barricades, Guards, and Safety Provisions: To protect persons
from injury and to avoid property damage, adequate barricades, construction
signs, fences, flashers and guards as required shall be placed and maintained
during the progress of the construction work and until it is safe for traffic
to use the trenched roadway.
23,000.3.E13. Traffic and Utility Controls: Excavations for pipe laying
operations shall be conducted in a manner to cause the least interruption to
traffic. Hydrants under pressure, valve boxes, curb stop boxes, fire or
police call boxes or other utility controls shall be left unobstructed and
accessible during the construction period.
23,000.3.E14. Private Property Protection: Trees, fences, poles and all
other private property shall be protected unless their removal is authorized
and any property damage shall be satisfactorily restored by the Contractor or
adequate compensation therefore shall be the responsibility of the Contrac-
tor. Where tree trimming is required, all cut surfaces one inch or more in
diameter shall be covered with a coat of asphalt paint.
23,000.3.E15. Interruption of Water Services: No valve or other control on
the existing system shall be operated for any purpose by the Contractor with-
out approval of the Engineer and all consumers affected by such operation
shall be notified by the Contractor at least an hour before the operation and
be advised of the probable time when service will be restored.
23,000.3.E.16. Tunneling, Jacking or Excavation Other Than Open Trench:
Where pipe cannot be placed by open trench excavation, the method for placing
shall be stated in the "Specific Requirements".
23,000.3.E17. Manner of Handling Pipe and Accessories Into Trench: Proper
implements, tools and facilities satisfactory to the Engineer shall be pro-
vided and used by the Contractor for the safe and convenient prosecution of
the work.
23,000.3.E18. Inspection Before Installation: Before lowering and while
suspended, the pipe shall be carefully inspected for defects and cracks. Any
defective, damaged or unsound pipe shall be rejected.
2300OG
Copyright 1990
Bonestroo, Rosene, Anderlik
& Associates, Inc.
23,000.3.E19. Pipe Kept Clean: All foreign matter or dirt shall be removed
from the inside of the pipe before it is lowered into its position in the
trench, and it shall be kept clean by approved means during and after laying.
23,000.3.E20. Preventing Trench Water From Entering Pipe: All openings along
the line of water main shall be securely closed, as directed, and at the sus-
pension of work at any time, suitable stoppers shall be placed to prevent
earth or other substances from entering water main.
23,000.3.E21. Railroad and Highway Crossings: When any railroad or highway
is crossed, all precautionary construction measures required by the Railroad
and Highway Department shall be followed. Railroad or highway crossings shall
be jacking or tunneling and construction and permit requirements shall be as
stated in the "Specific Requirements".
23,000.3.E22. Unsuitable Conditions for Laying Pipe . No pipe shall be laid
in water or when the trench conditions are unsuitable for such work.
23,000.3.F. JOINTING: All jointing of mechanical joint pipe and push-on
joint pipe shall be in accordance with the requirements of A.W.W.A. Speci-
fication 0600.
23,000.3.F1. Preparation of Pipe Ends: Before laying the pipes, the outside
of the spigot and the inside of the bell shall be wire brushed and wiped clean
and dry. Pipe ends shall be kept clean until joints are made.
23,000.3.G. SETTING VALVES, VALVE BOXES AND FITTINGS
23,000.3.G1. General: Valves and pipe fittings shall be set and jointed to
new pipe in the manner heretofore specified for cleaning, laying and jointing
pipe.
23,000.3.G2. Setting Valves: All valves shall be set where directed by the
Engineer. Valves and boxes shall be supported on a concrete block as shown on
the detail drawings. Valve boxes shall be maintained centered and plumb over
the operating nut of the valve. Tops of the valve boxes shall be set flush
with the existing surface and shall be set so as to provide 12 inches of up-
ward adjustment. Each valve box shall be marked with a 4" x 4" timber, 6'
long set with 2 feet of the post exposed above grade.
23,000.3.H. SETTING HYDRANTS:
23,000.3.H1. Location: All hydrants shall be set where directed by the
engineer. A grade stake and location stake will be provided by the Engineer
at each hydrant. No hydrant shall be set until such a grade stake has been
placed.
PRIAMM
2300OG
Copyright 1990
Bonestroo, Rosene, Anderlik
& Associates, Inc.
23,000.3.H2. Procedure: All hydrants shall be supported on an 8 inch
concrete block or equal concrete base. Each hydrant shall be braced as shown
on the detail drawings. After each hydrant has been set, there shall be
placed around the base of the hydrant, not less than one cubic yard of gravel
or crushed rock from which all fine material has been removed. A layer of
polyethylene, minimum 4 mil, thickness, shall be carefully placed over the
rock to prevent the backfill from entering the voids in the drain rock. All
hydrants must be maintained in a plumb position during the backfilling opera-
tion.
23,000.3.I. ANCHORAGE OF BENDS, TEES AND PLUGS:
23,000.3.11. General: All bends, tees, hydrants and plugs shall be securely
braced against undisturbed soil using timbers, precast concrete block with
wooden wedges or poured in place concrete thrust blocks. Method of anchorage
must be reviewed with and approved by the Engineer prior to backfilling.
23,000.3.J.
TESTING PIPE LINES:
23,000.3.J1. Pressure During Tes ts: After the pipe has been laid and back -
filled as specified, all newly laid pipe, or any valved section of it shall,
unless otherwise specified, be subjected to hydrostatic or air pressure of 150
lbs. per square inch. The test must be conducted under the observation of the
Engineer and with his approval.
23,000.3.J2. Duration of Pressure Test: The duration of each pressure test
shall be at least two (2) hours.
23,000.3.J3. Procedure: All pipe or sections thereof shall be slowly filled
with water from a safe source if a hydrostatic test is used, and the specified
test pressure, measured at the lowest point of elevation, shall be applied by
means of a pump connected to the pipe in a satisfactory manner. The pump,
pipe connection, taps, gauges and all necessary apparatus shall be furnished
by the Contractor. Gauges and measuring devices must meet with the approval
of the Engineer. The test gauge shall be calibrated in one pound increments
and operate smoothly and accurately.
23,000.3.J4. Expelling Air Before Test: Before applying hydrostatic test
pressure, all air shall be expelled from the pipe. To accomplish this, taps
shall be made, if necessary, at points at highest elevation and afterward
tightly plugged.
23,000.3.J5. Examination Under Pressure: Any cracked or defective pipes,
fittings, valves or hydrants discovered in consequence of the pressure test
shall be removed and replaced by the Contractor with sound material in the
manner provided and the test shall be repeated until satisfactory to the Engi-
neer.
�
23000G
Copyright 1990
Bonestroo, Rosene, Anderlik
& Associates, Inc.
23,000.3.J6. Permissible Leakage: A drop in pressure over a 30 minute test
period exceeding 3 pounds shall be cause for rejection of the project. All
leaks shall be corrected and the test repeated until the pressure drop is
within the 3 pound limit.
23,000.3.J7. Conductivity:_ Conductivity shall be provided throughout the
water system by use of copper straps or approved conductive gaskets with
copper inserts. All fittings shall be mechanical joint with copper straps.
Lead tipped gaskets will not be approved for conductivity.
Copper jumper straps between sections of pipe shall be not less than 1/16" x
3/4" strap bolted to shop welded pipe straps of the same size. Bolts shall be
5/16" diameter bronze. For all locations where shop welded straps are not
available, field welds shall be made using the Cadweld method with size 32
cartridge. Each field weld shall be properly made after filing the surface of
the pipe to a clean bare metal over the entire area of the weld. Straps
bolted to mechanical joint fittings shall be not less than 1/16" x 1-1/2".
All straps shall be securely fastened and backfill placed so as to not damage
the conductivity.
Conductivity test shall be performed on all mains after they have been pres-
sure tested and are full of water at normal operating pressure. A direct
current of 350 amps at 30 volts shall be passed through the line for 4
minutes. Current flow shall be measured continuously on a suitable ammeter
and shall remain steady without interruption or excessive fluctuation through-
out the period. At the end of the 4 minute period, the current shall be
raised to 400 amps for 1 minute without fluctuation. Insufficient current or
wide fluctuations of ammeter needle shall be evidence of defective conduc-
tivity which shall be isolated, corrected and retested.
Acceptable equipment for the test shall be arc welding machines with adequate
sized cables to carry the test current without voltage drop or overheating.
Conductivity test shall be carried out in the presence of the Engineer or his
duly authorized agent. Caution shall be exercised at all times when working
with electrical equipment and wires during the conductivity test.
23,000.3.K. DISINFECTION:
2300OG
Copyright 1990
Bonestroo, Rosene, Anderlik
& Associates, Inc.
When the installation has been completed, the main shall be filled with water
at a velocity of less than 1 foot per second. This water shall remain in the
pipe for at least 24 hours. After the 24 hour retention period, the heavily
chlorinated water shall be flushed from the main until the chlorine concentra-
tion in the water leaving the main is less than 1 ppm.
Tests are required to determine chlorine residual at the end of the 24 hour
retention period and after flushing to ascertain that the heavily chlorinated
water has been removed from the pipeline. At the end of the 24 hour retention
period, the main shall contain not less than 10 ppm chlorine.
The number of tablets required per 20 foot length of pipe based on 3-k grain
available chlorine per tablet is as follows:
Diameter
4"
6"
8"
10"
12"
16"
18"
20"
24"
No. of Tablets
1
2
3
4
5
9
12
14
20
After final flushing and before the main is placed in operation, samples shall
be collected and tested to show the absence of coliform organisms. If the
initial disinfection fails to produce satisfactory bacteriological samples,
the main shall be reflushed and resampled. If further samples show the
presence of coliform organisms, then the mains shall be rechlorinated by the
continuous feed or slug method of chlorination until satisfactory results are
obtained. I
23,000.3.L. BACKFILLING, CLEANING UP AND MAINTAINING SURFACES:
23,000.3.L1. Backfilling Procedure at Pipe 2onee Granular material or other
suitable backfill material free from rocks, boulders and other unsuitable sub-
stances shall be deposited in the trench simultaneously on both sides of the
pipe for the full width of the trench to a height of at least six (6) inches
above the top of the pipe. The backfill shall be hand placed and thoroughly
compacted to fill all spaces under and adjacent to the pipe.
23000G
Copyright 1990
Bonestroo, Rosene, Anderlik
& Associates, Inc.
23,000.3.L2. Backfill Procedure Above Pipe Zone: (Tvpe "a ") Procedure Where
Settlement is Allowable: Succeeding layers of backfill may contain coarser
materials and shall be free from pieces of rock, concrete or clay lump more
than one cubic foot in volume, roots, stumps, tin cans, rubbish, frozen mate-
rials and other similar articles whose presence in the backfill would cause
excessive settlement. This type of backfilling may be accomplished above the
pipe zone by any mechanical means or otherwise, at the option of the Contrac-
tor. On traveled streets, completed backfill shall be rolled by wheel type or
crawler type equipment weighing not less than 6 tons. Surface shall be main-
tained in passable condition for traffic until date of final inspection.
Backfilling under exposed existing utilities shall be compacted to prevent
settlement and any future displacement.
23,000.3.L3. Backfilling Procedure Above Pipe Zone: (Type "b ") Succeeding
layers of backfill may contain coarser materials and shall be free from pieces
of rock, concrete or clay lump more than one cubic foot in volume, roots,
stumps, tin cans, rubbish, frozen materials and other similar articles whose
presence in the backfill could cause excessive settlement. This type of back-
filling may be compacted by puddling with hose and long pipe nozzle, or by
flooding the trench, as the backfilling is accomplished above the pipe zone by
any mechanical means or otherwise: at the option of the Contractor. It is
important that proper precautions be taken to prevent flooding Of the pipe
when flooding the trench and the Contractor shall be wholly responsible for
neglect of these precautions.
23,000.3.L4. Procedure Where No Settlement is Allowable: (Type "c ")
Succeeding layers of backfill may contain coarser materials and shall be free
from pieces of rocks, concrete or clay lump more than one -third cubic foot in
volume, roots, stumps, tin cans, rubbish, frozen materials and other similar
articles whose presence in the backfill would cause excessive settlement.
This type of backfilling shall be placed in uniform layers before compaction
of approximately 6 inches, tamped by mechanical means to the density specified
in the Specific Requirements.
23,000.3.L6. Deficiency of Backfill, By Whom Supplied: Any deficiency in the
quantity of material for backfilling the trenches or for filling depressions
caused by settlement shall be supplied by the Contractor with no extra compen-
�
23000G
Copyright 1990
Bonestroo, Rosene, Anderlik
& Associates, Inc.
sation allowed. Any settlement which occurs shall be refilled by the Contrac-
tor. Material shall be at the Contractor's expense and of a material approved
by the Engineer.
23,000.3.L7. Restoration of Surface: All surfaces shall be returned to the
original grade and contour. Any excess dirt caused by displacement due to
structures shall be removed by the Contractor to a location as designated with
no extra compensation.
23,000.3.L8. Cleaning Up: Surplus pipe line material, tools and temporary
structures shall be removed by the Contractor and all dirt and rubbish caused
by his operations and excess earth from excavations shall be hauled to a dump
provided by the Contractor and the construction site shall be left to the
satisfaction of the Engineer. Clean up operations shall be accomplished
promptly after tests are completed.
23,000.4. METHOD OF MEASUREMENT AND PAYMENT:
23,000.4.A. PIPE IN PLACE: Pipe will be paid for at the contract price per
linear foot, which shall include the cost of furnishing all pipe, rubber gas-
ket, joints and other material and of delivering, handling, laying, trenching,
bedding, backfilling, compaction, testing and all material or work necessary
to install the pipe complete in place at the depth above specified.
The length of pipe for which payment is made shall be the actual overall
length measured along the axis of the pipe without regard to intervening
valves or fittings.
All jacking shall be paid for at the contract unit price per linear foot which
shall include both the water pipe and the casing under roadway and railroad,
complete as specified previously under Section 23,000.3.E21. Payment shall be
made for the jacking length specified unless unforseen conditions require a
change in length of jacking.
23,000.4.8. CAST IRON FITTINGS: Cast iron specials will be paid for at the
contract price per pound installed, said weights to include fittings, glands,
bolts and gaskets. Payment for cast iron fittings shall be for the published
weights of mechanical joint fittings as listed in A..W.A. 0110. If ductile
iron fittings are used, the weight for payment shall be the equivalent cast
iron weight.
23,000.4.C. HYDRANTS: Hydrants will be paid for at the contract unit price
per hydrant installed complete with gravel, concrete base and bracing, but
does not include the auxiliary hydrant valve which shall be paid for under
another item of these specifications if required.
�r
23000G
Copyright 1990
Bonestroo, Rosene, Anderlik
& Associates, Inc.
23,000.4.D. GATE VALVES AND BOXES: Gate valves and boxes, including exten-
sions, will be paid for at the contract unit price per valve and box installed
for each size.
23,000.4.E. BUTTERFLY VALVES AND BOXES: Butterfly valves, operators and
boxes, including extensions, will be paid for at the contract unit per valve
and box installed for each size.
23,000.4.F. IMPROVED PIPE FOUNDATION MATERIAL: The additional granular
material required below the specified bedding shall be paid for per lineal
foot of improved pipe foundation placed for each six (6) inch thickness of
granular material placed.
23,000.4.G. ROCK EXCAVATION: If rock is encountered in the trench, such rock
excavation shall be measured by volume in cubic yards and shall be measured
from the top of the rock to a point six (6) inches below the bottom of the
pipe and twelve (12) inches from each side of the inside diameter of the
pipe. The minimum trench width of the rock excavation shall be 36 inches.
Payment shall be at the contract unit price per cubic yard.
23,000.4.H. SAND CUSHION: Granular material used for a sand cushion in areas
of rock excavation where suitable materials are not available on site shall be
paid for at the contract unit price per ton of material deposited under and
around the pipe.
23,000.4.1. SPECIAL STRUCTURES AND APPURTENANCES: Basis of payment for
special structures and appurtenances not included above shall be stated in the
"Special Provisions ", "Specific Requirements" and /or "Proposal ".
Section End of
23,000-14
23000G
Copyright 1990
Bonestroo, Rosene, Anderlik
& Associates, Inc.
24,000. SEWERS
General Requirements
24,000.1. DESCRIPTION: This work shall consist of the construction of severs
in accordance with the requirements of the Contract. Under the numbering sys-
tem used herein numbers 24,000.2 - 24,000.2.N inclusive, deal with Materials;
24,000.3 - 24,000.7.A inclusive, deal with Construction Requirements; 24,000.8
- 24,000.8.K inclusive, deal with Method of Measurement and 24,000.9 -
24,000.9.M, inclusive, deal with Basis of Payment. It is intended that when
the Standard Specifications do not cover the subject matter necessary to be
covered, additional numbers in the appropriate section may be utilized in the
Specific Requirements and the numerical sequence preserved.
24,000.1.A. WORK INCLUDED: The Contractor shall, unless specified otherwise,
furnish all materials, equipment, tools and labor necessary.to do the work re-
quired under his contract and unload, haul and distribute all pipe, castings,
fittings, manholes and accessories. The Contractor shall also excavate the
trenches and pits to the required dimensions; sheet, brace and support the ad-
joining ground or structures where necessary; handle all drainage or ground-
water; provide barricades, guards and warning lights; lay and test the pipe,
castings, fittings, manholes and accessories; backfill and consolidate the
trenches and pits; maintain the surface over the trench; remove surplus exca-
vated material; and clean the site of the work.
The Contractor shall also furnish all equipment, tools, labor and materials
required to rearrange severs, conduits, ducts, pipes or other structures en-
countered in the installation of the work. All the work to completely con-
struct the sewer facilities shall be done in strict accordance with the con-
tract documents to which these General Requirements are a part.
24,000.1.B. SPECIFICATION REFERENCE: In these General Requirements reference
is made to the Minnesota Department of Transportation Specifications which
shall mean the "Standard Specifications for Highway Construction" of the
Mn/DOT, dated January 1, 1983 and subsequent amendments.
24,000.2. MATERIALS: The materials used in this work shall be new and con-
form to t�e requirements for class, kind and size of material specified below
tr as altered or more specifically described in the "Specific Requirements",
"Special Provisions" and "Proposal".
24,000.2.A. CLAY PIPE: Clay sewer pipe and fittings shall conform to the re-
quirements of the current A.S.T.M. Specification C-700 for extra strength clay
sewer pipe. Extra strength pipe shall be used for all Vitrified Clay Sewer
Pipe on the project.
24,000.2.B. POLYVINYL CHLORIDE SEWER PIPE: Polyvinyl chloride sewer pipe and
fittings shall be produced by a continuous extrusion process using Type 1,
Grade 1 material as defined in A.S.T.M. Spec. D-1784. The design, dimensions
and wall thickness shall be in accordance with ASTM Spec. D-3034, SDR 35.
24,000-1
1/88-24000G
Copyright 1988
Bonestroo, Rosene, Anderlik
& Associates, Inc.
24,000.2.C. REINFORCED CONCRETE SEWER PIPE: The sewer pipe shall conform to
the requirements of the Standard Specifications for Reinforced Concrete Sewer
Pipe, A.S.T.M. Designation C-76 of the class designated on the plans and in the
Proposal.
24,000.2.D. CORRUGATED METAL PIPE: Corrugated metal pipe shall conform to the
Standard Specifications for Corrugated Metal Pipe Culvert of the A.A.S.H.O.
Specification M-36 with exceptions and additions as noted in Mn/DOT
Specification 3226. The kind of base metal and gauge is stated in the
"Specific Requirements". If any special coating is required, it will be stated
in the "Specific Requirements".
24,000.2.E. DUCTILE IRON PIPE: Ductile iron pipe shall conform with the re-
quirements of AWWA Standard 0151 of the class and type stated in the "Specific
Requirements". All ductile iron pipe shall have mechanical or push-on type
joints and shall have a standard thickness cement mortar lining in accordance
with AWWA Standard 0104.
Where ductile iron pipe is used as a pressure line receiving discharge.from a
pumping station, all joints shall be electrically conductive by use of copper
straps or approved conductive gaskets with copper inserts.
24,000.2.F. CAST IRON
tings shall be mechanical
fittings shall be desi
have a standard thickness
Standard C104. Ductile
are considered equal.
FITTINGS: Where ductile iron pipe is furnished, fit-
joint in accordance with AWWA Standard 0110. All
fined for 150 psi working pressure. All fittings shall
of cement mortar lining in accordance with AWWA
iron fittings in accordance with AWWA Standard C-153
24,000.2.G. JOINTS AND JOINT MATERIALS:
24,000.2.G1. Clay Pipe: Clay pipe joints shall be rubber or plastic type
compression joints in accordance with A.S.T.M. Spec. C-425. Plain-end vitri-
fied clay pipe may be used which employ Type B compression couplings in accor-
dance with ASTM Specification C594.
24,000.2.G2. Polyvinyl Chloride Pipe: Polyvinyl chloride pipe joints shall be
bell and spigot type with solvent cement applied in accordance with the
manufacturer's recommendations. Gasketed push-on type joints are considered
equal.
24,000.2.G3. Concrete Pike: Reinforced concrete pipe joints shall meet the
requirements of ASTM Specification C-361 and shall be the Bureau of Reclama-
tion Type R-4. Deformed concrete pipe shall be jointed with material similar
to Ram-Nek, Hamilton Kent, Kent Seal No. 2 or equal gasket material applied in
accordance with manufacturer's recommendations.
1/88-2400OG
Copyright 1988
Bonestroo, Rosene, Anderlik
& Associates, Inc.
MERM
1/88- 24000G
Copyright 1988
8onestroo, Rosene, Anderlik
& Associates, Inc.
6
1/88-2400OG
Copyright 1988
Bonestroo, Rosene, Anderlik
& Associates, Inc.
24,000.2.M. MORTAR MATERIALS: Mortar used for laying up concrete block or
brick manholes or used for plastering lift holes and exteriors of manholes
shall consist of Standard Portland Cement Type I, Standard Serial Designation
C-150. Lime shall conform to specifications for normal finishing hydrated
lime, A.S.T.M. Serial Designation C-6 or specifications for hydraulic hydrated
lime for structural purposes, A.S.T.M. Serial Designation C-141. Gradation
shall be subject to the approval of the Engineer.
24,000.2.N. GRANULAR MATERIALS. Granular materials used for improved pipe
foundation, special pipe bedding, or PVC pipe bedding where improved pipe
foundation is required shall meet the requirements of Mn/DOT Specification
3149H, Coarse Filter Aggregate except that hard, durable crushed carbonate
quarry rock may also be used. The material shall have the following crushing
requirements. Not less than 50Z of the material, by weight, that is retained
on the No. 4 sieve shall have one or more crushed faces.
Granular materials used for pipe bedding in rock and for PVC pipe bedding where
improved pipe foundation is not required shall meet the requirements of Mn/DOT
Specification 3149A, Granular Borrow, except that 100Z, by weight, shall pass
the 1" sieve.
24,000.3. CONSTRUCTION REQUIREMENTS:
24,000.3.A. INSPECTION:
24,000.3.A1. Of Materials at Facto All materials, whether furnished by the
Owner or by the Contractor are subject, at the discretion of the Owner, to
inspection and approval at the plant of the manufacturer.
24,000.3.A2. Of Materials at Delivery Point: During the ' process of unloading,
all pipe and accessories shall be inspected by the Contractor for loss or
damage in transit. No shipment of material shall be accepted by the Contractor
until or unless notation of any lost or damaged material shall have been made
on the bill of lading by the agent of the carrier.
24,000.3.A3. Field IngptSLi2aL All pipe and accessories shall be laid,
jointed, tested for defects and for infiltration in the manner herein speci-
fied as directed by the Engineer and subject to his approval.
24,000.3.A4. Disposition of Defective Material: All material found during the
progress • the work to have cracks, flaws or other defects will be rejected by
the Engineer and the Contractor shall promptly remove from the site of the work
such defective material.
24,000.3.Bl. ResponsibilitV for Material Furnished • Contractor: The Con-
tractor shall be responsible for all material furnished by him and he shall
replace at his own expense all such material that is found to be defective in
manufacture or that has become damaged after delivery by the manufacturer.
24,000-5
1/88-2400OG
Copyright 1988
Bonestroo, Rosene, Anderlik
& Associates, Inc.
24,000-6
1/88-24000G
Copyright 1988
Bonestroo, Rosene, Anderlik
& Associates, Inc.
24, 000.3 <B e EXCAVATION & PREPARATION OF TRENCH:
All surface water and ground water discharges shall be conducted to natural
drainage channels, drains or storm sewers.
24,000 -7
1/88 ®240000
Copyright 1988
Bonestroo, Rosene, Anderlik
& Associates, Inca
24,000.3.E3.1. Class C-1 Beddin Where Class C-1 bedding is specified or
allowed with existing materials, the trench shall have a bottom conforming to
the grade to which the pipe is to be laid. The pipe shall be laid upon sound
soil, cut true and even so that the barrel of the pipe will have bearing over
at least 50 percent of the pipe width for its entire length. Bell holes shall
be excavated to insure that the pipe rests for its entire length upon the bot-
tom of the trench. When a uniform trench bottom cannot be formed as speci-
fied, Class C-2 bedding shall be used.
The contractor may, at his option, elect to use a Class C-2 bedding in lieu of
Class C-1 bedding, without any additional compensation allowed therefor.
24,000.3.E3.2. Class C-2 Bedding: Where Class C-2 bedding is specified or
allowed, the pipe shall be bedded on granular materials meeting 24,000.2.N
specifications. The depth of bedding shall be one fourth of the outside
diameter of the pipe barrel, but not less than six inches in accordance with
the standard detail plates.
24,000.3.E3.3. Class B Bedding: Where Class B bedding is specified or
allowed, the pipe shall be bedded on granular materials meeting 24,000.2.N.
specifications. The depth of bedding shall be one fourth of the outside dia-
meter of the pipe barrel, but not less than six inches, plus one half of the
outside diameter of the pipe barrel all in accordance with the standard detail
plate.
24,000.3.E3.4. Class A jtddinga Where Class A bedding is specified or
allowed, the pipe shall be bedded in the same manner as for Class C-1 bedding
except that 2000 psi concrete shall be placed around the pipe from the bottom
of the trench to a point one half the outside diameter of the pipe barrel above
the bottom of the trench all in accordance with the Standard Detail Plate.
24,000.3.E3.5. PVC Pipe Bedding: All polyvinyl chloride sever pipe shall be
installed and bedded in accordance with ASTM specification D-2321, "Recom-
mended Practice for Underground Installation of Flexible Thermoplastic Sewer
Pipe" with granular materials meeting Specification 24,000.2.N. used for all
PVC pipe bedding. The granular materials shall be placed from a point 6" be-
low the bottom of the pipe to a point 12" above the top of the pipe.
Bedding requirements shall include mechanical compaction of sand and gravel
material surrounding the pipe to at least ninety-five (95Z) percent of maximum
density as described in ASTM Methods D698 to prevent deflection of the pipe
cross-section. Payment for such bedding and compaction operations shall be
considered incidental to the installation of the sever pipe. Where existing
soils are of non-granular nature, the Contractor shall furnish sand or gravel
material for pipe bedding as incidental to the cost of the pipe.
pzvrte�
1/88-24000G
Copyright 1988
Bonestroo, Rosene, Anderlik
& Associates, Inc.
The Owner reserves the right to measure deflection of PVC sever pipe 30 days
after placement of backfill material in the trench and at any time during the
warranty period. Deflections greater than five (5Z) percent of the inside pipe
diameter shall be considered failure of the bedding procedure and the Contrac-
tor may be required to re-excavate the trench and provide additional compaction
along the side of the sever pipe with no additional compensation for such
work. Deflection testing of PVC pipe shall be performed by the contractor with
no additional compensation allowed therefor.
24,000.3.E4. Correcting Faulty Grade: Any part of the trench excavated below
grade shall be corrected with approved material thoroughly compacted without
additional compensation to the Contractor.
24,000.3.E5. Improved Pipe Foundation: When the bottom of the trench is soft
or where in the opinion of the Engineer unsatisfactory foundation conditions
exist, the Contractor shall excavate to a depth to insure proper foundation.
The excavation shall then be brought up to pipe grade with thoroughly compacted
granular materials meeting Specification 24,000.2.N. No payment will be made
for rock installed without the knowledge or consent of the Engineer nor will
payment be made for rock installed only for devatering purposes. Payment will
be made for only the authorized granular foundation material placed under the
pipe.
It shall be the Contractor's responsibility to notify the Engineer of changing
soil conditions which may be of poor bearing capacity and when organic soils
are encountered. Where utilities are placed on unstable soils without notifi-
cation of the Engineer, the Contractor shall be responsible for all repairs and
correction of the installation without further compensation.
24,000.3.E6. Pipe Clearance in Rock: Ledge rock, boulders and large stones
shall be removed to provide a clearance of at least 6 inches below the outside
barrel of the pipe and to a clear width of 6 inches on each side of all pipe
and appurtenances for pipe 15 inches or less in diameter; for pipes larger than
15 inches, a clearance of 6 inches below and a clear width of 9 inches on each
side of outside diameter of pipe shall be provided. Adequate clearance for
properly jointing pipe laid in rock trenches shall be provided at bell holes.
24,000.3.E7. Pipe Bedding in Rock: Where rock is encountered, the space be-
tween the rock and the pipe surfaces shall be backfilled with granular materi-
als meeting specification 24,000.2.N. and thoroughly tamped. The material from
the trench excavation, other than rock, boulders, peat, silt or other un-
acceptable material, shall be considered as suitable material. No additional
compensation for placing or tamping this material shall be allowed. However,
in the event that additional material must be hauled in, the hauling of the
suitable granular material for the pipe bed shall be paid for on a weight basis
only when ordered placed by the Engineer.
24,000-9
1/88-24000G
Copyright 1988
Bonestroo, Rosene, Anderlik
& Associates, Inc.
24,000.3.E8. Solid Rock Excavation Defined: Solid rock excavation shall in-
clude such rocks as are not decomposed, weathered or shattered and which will
require blasting, barring, wedging or use of air tools for removal. Under this
classification shall be included the removal of any concrete or masonry
structures (except concrete pavement, curb, gutter and sidewalk) or boulders
exceeding one-half (1/2) cubic yard in volume that may be encountered in the
work.
24,000.3.E9. Blasting Procedure: Blasting for excavation will not proceed
until the Contractor has notified the Engineer of the necessity to do so, such
notification shall in no manner relieve the Contractor of the hazards and lia-
bility contingent in blasting operations. The hours of blasting will be fixed
by the Owner. Any damage caused by blasting shall be repaired by the Contrac-
tor at his expense. The Contractor's methods of procedure relative to blast-
ing shall conform to local and state laws and municipal ordinances.
24,000.3.E10. Bell Holes Requir Bell holes of ample dimensions shall be
dug in trenches at each joint to permit the jointing to be made properly.
24,000.3.Ell. Braced & Sheeted Trenches: The Contractor shall adequately
brace and sheet excavations wherever necessary to prevent caving or damage to
nearby property. The cost of this temporary sheeting and bracing, unless pro-
vided for otherwise, shall be considered as part of the excavation costs with-
out additional compensation to the Contractor. Trench sheeting or bracing
shall remain in place until the pipe has been laid, tested for defects and re-
paired if necessary, and the earth around it compacted to a depth of one foot
over the top of the pipe.
Sheeting, bracing, etc. placed in the "pipe zone" (that part of the trench be-
low a distance of one foot above the top of the pipe) shall not be removed
without the written permission or written order of the Engineer. Sheeting
ordered left in place by the Engineer shall be paid for at the unit price bid.
The Contractor may also leave in place, at his own expense, any sheeting or
bracing in addition to that ordered left in place by the Engineer necessary to
prevent injury or damage to persons, corporations, or property, whether public
or private, for which the Contractor under the terms of this contract is liable.
24,000.3.E12. Manner of Piling Excavated Material: All excavated material
shall be piled in a manner that will not endanger the work and that will avoid
obstructing sidewalks and driveways. Gutters shall be kept clear or other
satisfactory provisions made for street drainage.
24,000.3.E13. Maintenance of Traffic: When traffic cannot be diverted, it
will be permitted to use the highway at all times. the Contractor shall at his
own expense erect and maintain warning signs and warning barricades. The
Contractor shall at his own expense, place and maintain acceptable warning
lights and barricades to protect persons from injury and to avoid property
damage.
1/88-24000G
Copyright 1988
Bonestroo, Rosene, Anderlik
& Associates, Inc.
At all dangerous intersections, bypasses, and intercepting roads, the Contrac-
tor shall at his own expense furnish, erect and maintain such warning barri-
cades as are necessary and required by the Engineer, and he shall place and
maintain acceptable warning lights at each. It shall be the Contractor's re-
sponsibility to check and inspect all lights and barricades at all times in-
cluding Sundays and Holidays. He shall maintain the streets in a passable
condition, shall conduct his work so as to create a minimum amount of incon-
venience to traffic and shall furnish not less than two flagmen at each loca-
tion where loading or depositing of material requires the turning of the trucks
on any state highway or "main street" and where the operation of construction
equipment endangers traffic. Temporary suspension of work does not relieve the
Contractor of the responsibility outlined in the above requirements.
24,000-3.E14. Property Protection: Trees, fences, poles and all other prop-
erty shall be protected unless their removal is authorized; and any property
damaged shall be satisfactorily restored by the Contractor, or adequate
compensation therefor shall be the responsibility of the Contractor. Where
tree trimming is required, all cut surfaces one inch or more in diameter shall
be covered with a coat of asphalt paint.
24,000.3.E15. Interruption of Water Service: No valve or other control on the
existing system shall be operated for any purpose by the Contractor without
approval of the Engineer and all consumers affected by such operation shall be
notified by the Contractor at least an hour before the operation and advised of
the probable time when service will be restored.
24,000.3.E16. Tunneling, Jacking or Excavation Other Than Open Trench: Where
pipe cannot be placed by open trench excavation, the method for placing and
payment thereof shall be stated in the "Specific Requirements".
24,000.3.E17. Manner of Handling Pipe & Accessories Into Trench: Proper im-
plements, tools and facilities satisfactory to the Engineer shall be provided
and used by the Contractor for the safe and convenient prosecution of the work.
24,000.3.E18. Pipe Kept Clean: All foreign matter or dirt shall be removed
from the inside of the pipe before it is lowered into its position in the
trench, and it shall be kept clean by approved means during and after laying.
All matter entering the pipe shall be removed by the Contractor prior to ac-
ceptance with no additional compensation allowed.
24,000.3.E19. Laying the Pipe: The spigot shall be lubricated, centered in
the bell, the pipe shoved into, position and brought into true alignment; it
shall be secured there with earth carefully tamped under and on each side of
it, excepting at the bell holes. Care shall be taken to prevent dirt from en-
tering the joint space.
24,000.3.E20. Preventing Trench Water From Entering Pipe: All openings along
the line of sewer shall be securely closed, and at the suspension of work at
any time, suitable stoppers shall be placed to prevent water, earth or other
substances from entering the sewer.
24,000-11
1/88-2400OG
Copyright 1988
Bonestroo, Rosene, Anderlik
& Associates, Inc.
24,000.3.E21. M s End to Face Direction of T_qvinq: Pipe laying shall pro-
Be -as
ceed upgrade with spigot ends pointing in the direction of flow.
24,000.3.E22. Railroad & Highway C rossing: When any railroad or highway is
crossed, all precautionary construction measures required by the railroad or
highway shall be followed. Railroad or highway crossings shall be jacking or
tunneling and construction and permit requirements shall be as stated in the
"Specific Requirements".
24,000-3.E23. Unsuitable conditions LE I _Laing Pine: No pipe shall be laid in
water or when the trench conditions are unsuitable for such work.
24,000.3.E24. j2j Joints for vitrified clay and concrete pipe shall be
made by wiping the joints clean, applying the manufacturer's recommended
lubricant compound over the entire joint surface and then inserting the spigot
end into the bell with sifficient force to properly seat the pipes. Joints for
polyvinyl chloride pipe shall be made by the use of a solvent cement or pushon
rubber gaskets. All jointing procedure shall be in accordance with the
recommendations of the pipe manufacturer.
After joints are made, any superfluous material inside the pipe shall be re-
moved by means of an approved follow - 1. scraper. All joints must be water-
tight, and any leaks or defects discovered must be immediately repaired. Any
pipe which has been disturbed after being laid must be taken up, the joint
cleaned and properly relaid as directed by the Engineer.
Joints connecting cast iron pipe with concrete or clay pipes shall be made with
a concrete collar completely surrounding the joint or approved adapter.
Where a sewer line outlets to grade or where the line is terminated with a
flared end section, the Contractor shall fasten at least the last three (3)
joints together by the use of "U" bolt fasteners approved and as recommended by
the pipe manufacturers.
24,000.4. SERVICE CONNECTIONS'
24,000.4.A. WYE BRANCHES: Extra strength wye branches shall be placed at the
locations directed by the Engineer. The wye branch shall be placed so that the
wye is located at approximately a 45 angle from horizontal. Vitrified•or
other suitable plugs shall be provided for the openings. plugs shall be in-
stalled with Atlastic 77, Sonolastic Sealant or equal joint material or shall
be specifically designed for the opening to be plugged.
24,000.4.B. RISERS: Standard weight cast iron soil pipe shall be used as
risers to extend service connections to a point within 10 feet of the street
grade or as directed. Risers shall be installed in accordance with the stan-
dard service riser detail plate. Care shall be taken in backfilling so as not
to damage the.riser installation. Suitable plugs shall be provided for the
openings, properly sealed.
EMOMMM
1/88-24000G
Copyright 1988
Bonestroo, Rosene, Anderlik
& Associates, Inc.
24,000.4-C. RECORDS & LOCATION OF SERVICE CONNECTIONS: It shall be the duty
of the Contractor to keep an accurate record of service connections, as to lo-
cation, depth to top of riser, type of connection provided, etc. Location
shall be made in respect to nearest manhole center, downgrade from the ser-
vice. This record shall be turned over to the Engineer at the end of each week.
24,000.5. MANHOLES:
24,000.5.A. GENERAL: All reference to manholes shall apply equally to catch
basin structures in this section of the specifications.
24,000.5.B. EXCAVATION: Excavation shall be to a depth and size to provide
for construction of the manholes and catch basins as shown in detail on the
plans.
24,000.5.C. CONCRETE BASE: Concrete base for manhole construction shall be of
size and depth as shown on the plans. Concrete used for this purpose shall
consist of one part Portland cement, two parts of clean sharp sand and four
parts of graded coarse aggregate. Material used for this purpose shall be
subject to the approval of the Engineer. Base shall be poured on undisturbed
earth prior to setting the precast manhole sections. Precast concrete manhole
bases shall be considered equal.
24,000.5.D. WALLS: Material to be used in the walls of manholes shall be as
specified in Section 24,000.2. All external surfaces of concrete block man-
holes if permitted shall be plastered with a 1/2 inch coat of Portland cement
mortar. Mortar shall contain one part of cement to three parts of suitable
plaster sand. Lime or mortar mix shall be used in amount necessary to make a
suitable mixture for plastering purposes, but not to exceed 15Z by volume of
cement. Mortar used for laying concrete block shall consist of one part Port-
land cement to two parts of sand to which lime or mortar mix may be added not
to exceed fifteen percent (15Z) by volume of cement.
24,000.5.E. MANHOLE STEPS: Manhole steps shall be of the type as specified in
Section 24,000.2.J. Spacing shall be as shown on the detailed manhole plans,
but not greater than 16 inches in vertical alignment.
24,000.5.F. PLACING MANHOLE RINGS & COVERS: The frame or ring casting shall
be set to the designation elevation in a full mortar bed.
24,000.5.G. PLACING CATCH BASIN FRAMES & COVERS: Where catch basins are to be
placed to final grade and castings are to be installed in curbing, then the
casting and all adjusting rings shall be encased in concrete at least 4 inches
in thickness. Where curb and street work is to be done under separate contract
the casting frame shall be set in mortar only.
24,000.5.H. DROP MANHOLE INLETS: Encased drop inlets shall be constructed as
required on the plans and in accordance with the standard Drop Inlet Detail
Plate.
24,000-13
1/88-24000G
Copyright 1988
Bonestroo, Rosene, Anderlik
& Associates, Inc.
24,000.6. BACKFILLING, CLEANING UP & MAINTAINING SURFACES:
24,000.6.A. BACKFILLING PROCEDURE AT PIPE ZONE: All trenches and excavations
shall be backfilled immediately after pipe is laid therein. For backfill up tc
a level of one foot over the top of the pipe, only selected materials free froff
rock, boulders, debris or other high void content substances, shall be used.
The backfilling shall be placed completely under the pipe haunches in uniforn
layers not exceeding 4 inches in depth. Each layer shall be placed, then
carefully and uniformly tamped to eliminate the possibility of lateral
displacement and to provide uniform support completely under the pipe haunches.
The backfill material shall be moistened if necessary, tamped in 4 inch layers
and thoroughly compacted under and on each side of the pipe to provide solid
backing against the external surface of the pipe.
The installation and backfilling of polyvinyl chloride pipe shall be in accor-
dance with A.S.T.M. D-2321 with special attention given to compacting the.
backfill material around the pipe to at least 95 percent of maximum density to
a distance of one foot above the top of the pipe.
24,000.6.B. BACKFILL PROCEDURE AB " 0 ' V9 - PIPE ZONE: (Type "a") Procedure where
settlement is allowable. Succeeding layers of backfill may contain coarser
materials and shall be free from pieces of rock, concrete or clay lump more
than one cubic foot in volume, roots, stumps, tin cans, rubbish, frozen mate-
rials and other similar articles whose presence in the backfill would cause
excessive settlement. This type of backfilling may be accomplished above the
pipe zone by any mechanical means or otherwise, at the option of the Contrac-
tor. Surface shall be maintained in passable condition for traffic until date
of final inspection. Backfilling under exposed existing utilities shall be
compacted to prevent settlement and any future displacement.
24,000.6.C. BACKFILL PROCEDURE ABOVE PIPE ZONE: (Type "b") Succeeding layers
of backfill may contain coarser materials and shall be free from pieces of
rock, concrete or clay lump more than one cubic foot in volume, roots, stumps,
tin cans, rubbish, frozen materials and other similar articles whose presence
in the backfill would cause excessive settlement. This type of backfilling may
be compacted by- puddling with hose and long pipe nozzle or by flooding the
trench, as the backfilling is accomplished above the pipe zone by any mechani-
cal means or otherwise at the option of the Contractor. It is important that
proper precautions be taken to prevent flooding of the pipe when flooding the
trench, and the Contractor shall be wholly responsible for neglect of these
precautions.
24,000.6.D. PROCEDURE WHERE NO SETTLEMENT IS ALLOWABLE: (Type "c") Succeed-
ing layers backfill may contain coarser materials and shall be free from
pieces of rock, concrete or clay lump more than one cubic foot in volume,
roots, stumps, tin cans, rubbish, frozen materials and other similar articles
whose presence in the backfill would cause excessive settlement. This type of
backfilling shall be placed in uniform layers, before compaction, of approxi-
mately 6 inches, tamped by mechanical means to the density specified in the
Specific Requirements.
1/88-2400OG
Copyright 1988
Bonestroo, Rosene, Anderlik
& Associates, Inc.
24,000.6.E. PROCEDURE WHERE NO SETTLEMENT IS ALLOWABLE: (Type "d") Succeed-
ing layers of backfill shall be made of selected materials meeting require-
ments as set forth in the "Specific Requirements." This type of backfilling
shall be placed in uniform layers, before compaction, of approximately 6
inches, tamped by mechanical means to the density specified in the Specific
Requirements.
24,000.6.F. DENSITY TESTS: Density tests will be performed by an approved
soils testing firm at various locations and depths throughout the project as
directed by the Engineer. The Contractor shall cooperate fully and provide
assistance as necessary to complete these tests with no additional compensa-
tion being made to the Contractor.
All testing costs pertaining to passing tests shall be paid for by the Owner.
All testing costs pertaining to failing tests will be charged to and paid for
by the contractor.
Where areas have not been compacted sufficiently to meet specific density re-
quirements, these areas shall be excavated and recompacted until the density
requirements are met. All cost for the work associated with recompaction shall
be the Contractor's sole responsibility,
24,000.6.G. DEFICIENCY OF BACKFILL, BY WHOM SUPPLIED: Any deficiency in the
quantity of material for backfilling the trenches, or for filling depressions
caused by settlement, shall be supplied by the Contractor with no extra com-
pensation allowed. Any settlement which occurs shall be refilled by the Con-
tractor. Material shall be provided at the Contractor's expense and the mate-
rial shall be approved by the Engineer.
24,000.6.H. DISPOSAL OF EXCESS MATERIALS AND DEBRIS: Unless otherwise speci-
fied, excavated material either not suitable or not required for fill material
shall be disposed of by the Contractor outside of the right-of-way at his ex-
pense in any manner he may elect subject to the provisions of the following
paragraph.
Before dumping such materials or debris on a private or public land, the Con-
tractor must obtain from the Owner of such land written permission for such
dumping and a waiver of all claims against the Owner for any damage to such
land which may result therefrom together with all permits required by law for
such dumping. A copy of such permission, waiver of claims and permit shall be
filed with the Engineer before said disposal is made.
24,000.6.1. RESTORATION OF SURFACE: All surfaces disturbed during the con-
struction period, whether caused by actual excavation, deposition of excavated
material, or by the construction equipment, shall be returned to its original
conditions or better. Exceptions to the above, if any, or special instruc-
tions pertaining to any particular section of the project will be outlined in
the "Special Provisions."
1/88-2400OG
Copyright 1988
Bonestroo, Rosene, Anderlik
& Associates, Inc.
N3r���
24,000.6.J. CLEANING UP: Surplus pipe line material, tools and temporary
structures shall be removed by the Contractor, and all dirt, rubbish, caused by
his operations and excess earth from excavations shall be hauled to a dump
provided by the Contractor and the construction site shall be left to the sat-
isfaction of the Engineer.
Clean up and restoration shall include the replacement and restoration of all
street signs, mailboxes, posts, fences and similar items disturbed by the con-
struction described herein. Unless otherwise noted in the Special Provisions
or Proposal all items of clean -up and restorations shall be considered inci-
dental to the contract with no additional compensation allowed.
24,000.7. TESTING PIPE LINES
24,000.7.A. INFILTRATION IN SEWERS: Upon completion of the sewer construc-
tion, leakage tests shall be made to determine the amount of ground water in-
filtration into the sewers. Measurements will be made by means of 90 V -notch
weirs placed in the lines. Measurements shall be taken at all points where, in
the opinion of the Engineer, the flow of water in the sewers is greater than
the maximum allowable leakage. Teqta may be taken between individual manholes
and the infiltration in any given line shall not exceed the specified maximum
allowable rate.
The maximum allowable rate of leakage shall not exceed 100 gallons per mile per
inch diameter of pipe per day.
The Contractor shall furnish the weirs and other material and the labor for
placing the weirs in the sewers and shall assist the Engineer in making the
measurements. The Contractor shall receive no additional compensation for
making the leakage tests or corrective work necessary to reduce leakage below
the maximum allowed by the specifications.
24,000.8. METHOD OF MEASUREMENT:
24,000.8.A. TRENCH EXCAVATION: Trench excavation will be measured in linear
feet of trench according to the zone classifications specified as follows:
From 0' to 8 from 8' to 10 and in two foot increments thereafter, which are
based on the total depth of the trench to the designated grade of the pipe
invert. No deduction in depth will be made for rock encountered in the trench
above the designated grade.
Measurement will be made along the centerline of the sewer and from center to
center of all manholes, catch basins or junction fittings.
FORRM
1/88- 24000G
Copyright 1988
Bonestroo, Rosene, Anderlik
& Associates, Inc.
24,000.8.B. SOLID ROCK EXCAVATION:
trench, such rock excavation shall be me
shall be measured from the top of
outside barrel of pipe and twelve inches
pipe. The minimum trench width of
inches. For measurement purposes volume
walls for the width specified above.
If solid rock is encountered in the
asured by volume in cubic yards and
the rock to a point six inches below the
from each side of inside diameter of
the solid rock excavation shall be 36
will be computed based on vertical
24,000.8.C. SEWER PIPE WITH BEDDING: Sever pipe of each diameter and classi-
fication furnished and installed with associated pipe bedding will be measured
separately by length in linear feet. Measurement will be made along the cen-
terline of the sewer and from center to center of all manholes, catch basins or
junction fittings.
Where bends, tee manholes, flared end sections or other special shapes are in-
stalled, the length of pipe replaced by these structures shall be deducted from
the distance from center of manhole to center of manhole for pay purposes. The
special structures will be paid for as separate bid items.
24,000.8.D. SERVICE CONNECTION: Wyes and tee branches of each diameter and
classification furnished and install� vill be measured as a unit.
24,000.8.E. SERVICE RISER PIPE: Sever pipe used for service risers of each
diameter and classification furnished and installed will be measured separate-
ly by vertical length in linear feet from the centerline of the sewer to the
top of the last riser section.
24,000.8.F.
CONSTRUCTING MANHOLES: Manholes will be measured by depth of the
structure from the invert of
based on the dimensions as staked
the pipe to the top of the cover in linear feet,
by the Engineer.
24,000.8.G. CONSTRUCTING CATCH BASINS: Catch basins will be measured by the
number of catch basins completed as to shape, size, and depth according to the
plans.
24,000.8.H. ' IMPROVED PIPE FOUNDATION: Granular materials placed for improving
pipe foundation below the specified pipe bedding shall be measured by the
lineal foot of pipe placed with improved foundation in six inch depth
increments of granular material placed. As an example, if two feet of granular
material is required for improved pipe foundation under a 12" pipe installed
with C-2 bedding; six inches of material is required for Class C-2 bedding and
improved pipe foundation shall be measured as three lineal feet, six inches
deep.
24,000.8.J. DROP INLETS: Drop inlets will be measured by depth from the low-
est invert of the manhole to the invert of the pipe being served by the drop
inlet.
24,000-17
1/88-2400OG
Copyright 1988
Bonestroo, Rosene, Anderlik
& Associates, Inc.
24,000.8-K. SPECIAL STRUCTURES & APPURTENANCES: Methods of measurement for
special structures and appurtenances not included above shall be as stated in
the "Special Provisions," "Specific Requirements," and "Proposal."
24,000.9. BASIS OF PAYMENT:
24,000.9.A. TRENCH EXCAVATION & BACKFILL: Regardless of the width excavated,
sever pipe furnished and installed with bedding will be paid for at the
Contract Unit Price per linear foot of pipe falling within each of the
following depth zones as measured from the profile grade:
From 0 to V, from 8' to 10 and two foot increments thereafter.
Excavation and backfilling of trench and associated pipe bedding shall be
included in the price of sever pipe furnished and installed.
24,000.9.B. SOLID ROCK EXCAVATION: Solid rock excavation will be paid for at
the Contract Unit Price per cubic yard.
24,000.9-C. SEWER PIPE WITH BEDDING IN PLACE: Sever pipe in each diameter and
classification furnished and installed will be paid for at the Contract Price
per linear foot which shall include payment for trench excavation and
backfilling and associated pipe bedding.
24,000.9.D. DUCTILE IRON PIPE: Ductile iron pipe will be paid for at the
Contract Unit Price per linear foot for each type and diameter of, pipe fur-
nished which shall include payment for trench excavation and backfill.
24,000.9.E. WYE BRANCHES: Wye branches will be paid for at the Contract Unit
Price for each unit furnished and installed of the size specified on the Pro-
posal.
24,000.9.F. SERVICE RISER PIPE: Service riser pipe will be paid for at the
Contract Unit Price per linear foot for the vertical distance from the center-
line of the sever to the top of riser. Concrete reinforcement of the main
sever and riser pipe as described in Section 24,000.4.B. shall be considered
as incidental and will not constitute a pay item.
24,000.9.G. CONSTRUCTING MANHOLES TO DEPTH OF EIGHT FEET: Constructing of
manholes to a depth of eight (8) feet will be paid for at the Contract Unit
Price per manhole which shall include furnishing and placing the manhole frame
and cover. This section also applies to all catch basin manholes and catch
basins.
24,000.9.H. CONSTRUCTING MANHOLES TO A DEPTH GREATER THAN EIGHT FEET: Con-
structing of manholes to a depth greater than eight (8) feet will be paid for
at the Contract Unit Price per manhole plus the unit price per linear foot for
each foot of depth that is greater than eight feet. This section also applies
to all catch basin manholes and catch basins.
1/88-24000G
Copyright 1988
Bonestroo, Rosene, Anderlik
& Associates, Inc.
24,000.9.1. CONSTRUCTING CATCH BASINS: Constructing catch basins as shown on
the plans will be paid for at the Contract Unit Price per catch basin which
shall include furnishing and placing the catch basin frame and grating.
24,000.9.J. IMPROVED PIPE FOUNDATION: Authorized granular materials for
improving pipe foundation in place shall be paid for at the Contract Unit Price
per lineal foot for each six inch layer placed below pipe bedding.
24,000.9.x. SAND CUSHION: Granular material for a sand cushion in place in
rock excavation shall be paid for at the Contract Unit Price per ton.
24,000.9.L. DROP INLET PIPE: Drop inlets in place shall be paid for at the
Contract Unit Price per linear foot which shall be payment in full for the ex-
tended manhole base, encasement, drop pipe, cast iron tee, cast iron pipe and
concrete collar. Payment shall be made for sewer pipe from center to center of
all manholes as per Section 24,000.8.0. when cast iron pipe is extended for
drop inlets.
24,000.9.M. SPECIAL STRUCTURES & APPURTENANCES: Basis of payment for special
structures and appurtenances not incl- -1 above shall be stated in the "Special
Provisions," "Specific Requirement," and "Proposal ".
1/88- 24000G
Copyright 1988
Bonestroo, Rosene, Anderlik
& Associates, Inc.
24,000 -19
SUBSURFACE ' •s ! •
ATHLETIC ► LIGHT STANDARDS
INDUSTRY SCIENCE
NEW HOPE, MINNESOTA
PROJECT GME NO. 2547
INC. GME CONSULTANTS,
CONSULTING ENGINEERS
14000 21 st Ave. No./ Minneapolis, MN 55447
Rhone (612) 559 -1859 / Fax (612) 559 -0720
Dear Mr. Hanson
Following the acceptance of our proposal of May 25, 1990, we have
completed • •. c... exploration • f project. • • please
find of our • exploration and the soil report have
[yrepared. Three copies of this report have been sent to the above
address.
We appreciate the opportunity to have been of service to you for thl
project. If you have any questions regarding this report or if we c
be of further assistance to you, please •
SlnceXely,
•
WCK•smc
• . ENVIRONMENTAL
WILLIAM RE. H Jt ` ♦. * VENEMA, RE. KENNETH J, LaFOND. RE. WILLIAM O Vii. RE,
An Equal Opportunity Employer
ABOUTYOUR
More construction problems are caused by site subsurface
conditions than any other factor. As troublesome as sub-
surface problems can be, their frequency and extent have
been lessened considerably in recent years, thanks to the
Association of Soil and Foundation Engineers (ASFE).
When ASFE was founded in 1969, subsurface problems
were frequently being resolved through lawsuits. In fact,
the situation had grown to such alarming proportions that
consulting geotechnical engineers had the worst profes-
sional liability record of all design professionals. By 1980,
ASFE - member consulting soil and foundation engineers had the best
professional liability record. This dramatic turn -about can be
attributed directly to client acceptance of problem- solving
programs and materials developed by ASFE for its mem-
bers' application. This acceptance was gained because clients
perceived the ASFE approach to be in their own best interests.
Disputes benefit only those who earn their living from
others' disagreements.
The following suggestions and observations are offered to
help you reduce the geotechnical- related delays, cost -over-
runs and other costly headaches that can occur during a
construction project.
A GEOTECNICAL ENGINEERING
REPORT IS BASED ON A UNIQUE SET OF
PROJECT- SPECIFIC FACTORS
A geotechnical engineering report is based on a subsurface
exploration plan designed to incorporate a unique set of
project- specific factors. These typically include: the general
nature of the structure involved, its size and configuration;
the location of the structure on the site and its orientation;
physical concomitants such as access roads, parking lots,
and underground utilities, and the level of additional risk
which the client assumed by virtue of limitations imposed
upon the exploratory program. To help avoid costly prob-
lems, consult the geotechnical engineer to determine how
any factors which change subsequent to the date of his
report may affect his recommendations.
Unless your consulting geotechnical engineer indicates
otherwise, your geotechnical engineering report should not be used:
• When the nature of the proposed structure is
changed, for example, if an office building will be
erected instead of a parking garage, or if a refriger-
ated warehouse will be built instead of an unrefrig-
erated one;
• when the size or configuration of the proposed
structure is altered;
• when the location or orientation of the proposed
structure is modified;
• when there is a change of ownership, or
• for application to an adjacent site.
Ageotechnical engineer cannot accept responsibility for problems which
may develop if he is not consulted after factors considered in his report's
development have changed.
Site exploration identifies actual subsurface conditions
only at those points where samples are taken, when they
are taken. Data derived through sampling and subsequent
laboratory testing are extrapolated by the geotechnical
engineer who then renders an opinion about overall sub-
surface conditions, their likely reaction to proposed con-
struction activity, and appropriate foundation design. Even
under optimal circumstances actual conditions may differ
from those opined to exist, because no geotechnical en-
gineer, no matter how qualified, and no subsurface explo-
ration program, no matter how comprehensive, can reveal
what is hidden by earth, rock and time. For example, the
actual interface between materials may be far more
gradual or abrupt than the report indicates, and actual
conditions in areas not sampled may differ from predic-
tions. Nothing can be done to prevent the unanticipated, but steps can
be taken to help minimize their impact. For this reason, most
experienced owners retain their geotechnical consultant through the
construction stage, to identify variances, conduct additional
tests which may be needed, and to recommend solutions
to problems encountered on site.
• • !rr •
CHANGE
Subsurface conditions may be modified by constantly -
changing natural forces. Because a geotechnical engineer-
ing report is based on conditions which existed at the time
of subsurface exploration, construction decisions should not be
based on a geotechnical engineering report whose adequacy may have
been affected by time. Speak with the geotechnical consultant
to learn if additional tests are advisable before construc-
tion starts.
Construction operations at or adjacent to the site and
natural events such as floods, earthquakes or groundwater
fluctuations may also affect subsurface conditions and,
thus, the continuing adequacy of a geotechnical report.
The geotechnical engineer should be kept apprised of any
such events, and should be consulted to determine if
additional tests are necessary.
.>
r . , •
Costly problems can occur when other design profession-
als develop their plans based on misinterpretations of a
geotechnical engineering report. To help avoid these prob-
lems, the geotechnical engineer should be retained to work
with other appropriate design professionals to explain
relevant geotechnical findings and to review the adequacy
of their plans and specifications relative to geotechnical
issues.
REPORT
Final boring logs are developed by the geotechnical en-
gineer based upon his interpretation of field logs (assem-
bled by site personnel) and laboratory evaluation of field
samples. only final boring logs customarily are included in
geotechnical engineering reports. These logs should not under
any circumstances be redrawn for inclusion in architectural or
other design drawings, because drafters may commit errors
or omissions in the transfer process. Although photo-
graphic reproduction eliminates this problem, it does
nothing to minimize the possibility of contractors misin-
terpretating the logs during bid preparation. When this
occurs, delays, disputes and unanticipated costs are the
all -too- frequent result.
To minimize the likelihood of boring log misinterpretation,
give contractors ready access to:the complete geotechnical engineering
report. Those who do not provide such access may proceed
under the mistaken impression that simply disclaiming
responsibility for the accuracy of subsurface information
always insulates them from attendant liability. Providing
the best available information to contractors helps prevent
costly construction problems and the adversarial attitudes
which aggravate them to disproportionate scale.
. � t
Because geotechnical engineering is based extensively on
judgement and opinion, it is far less exact than other
design disciplines. This situation has resulted in wholly
unwarranted claims being lodged against geotechnical
consultants. To help prevent this problem, geotechnical
engineers have developed model clauses for use in written
transmittals. These are not exculpatory clauses designed to
foist the geotechnical engineer's liabilities onto someone
else. Rather, they are definitive clauses which identify
where the geotechnical engineer's responsibilities begin
and end. Their use helps all parties involved recognize their
individual responsibilities and take appropriate action.
Some of these definitive clauses are likely to appear in your
geotechnical engineering report, and you are encouraged
to read them closely Your geotechnical engineer will be
pleased to give full and frank answers to your questions.
Your consulting geotechnical engineer will be pleased to
discuss other techniques which can be employed to miti-
gate risk. In addition, the Association of Soil and Founda-
tion Engineers has developed a variety of materials which
may be beneficial. Contact ASFE for a complimentary copy
of its publications directory.
Published by
RPMRA SM
GM t , UL M ,
Mr. Mark. Hanson 2 June 1, 1990
I
were chosen by the Engineer. The boring locations were staked in the
f ield by the BRA survey crew; the crew also shot the boring surface
Borings 1 and 3 were drilled at the staked locations. We could no!
drive the rig directly to boring 2 we offset this boring to the top
of the slope®
The borings were drilledwith h
augers were used to advance the borings full depth. Soil samples were
in jars R reduce moisture loss, and ` i i . ` f^a to our b o for
r
examination and classification by a Geotechnical Engineer.
GME CONSULTANTS, IMF.
Mr. Mark Hanson 3 June 1. 1.990
approximate; insitu, the transition between soil types may be gradual
or abrupt in the horizontal or vertical direction.
We will retain the soil samples for this program for 30 days after the
fate of this report. If you wish to have the samples retained beyorra
this time, we ask that you please advise us; otherwise, the samples
will be discarded.
f
t
l
Mr. Mark Ranson
M . . IgF
Ell
The Soil Conservation service Map for Hennepin County, prepared in
1967, identified the site at that time as consisting mostly of marsh,
with "cut lands" to the west and the south. In our site reconnaissance
on the date of drilling, we observed that much of the marsh has been
filled in the western side and the southern parts of the site. The
G G CONSULTANTS, IN&
Mr. Mark Hanson 6 June 1, 1990
RE D RECOMMENDATIO
We understand that ten new light standards are to be constructed as
applied to the light standard foundations. Because of the height of
the standards, minor amounts
could result in visible tipping or leaning of pole.
E CONSULTANTS, INC.
Mr. Mark Hanson
P
appeared to have been seeded on the north side.
consisted of weeds and heavy grass on the south side.
June 1, 1990
In boring 1, we found 9 feet of soft great, overlying very loose silty
sand, changing to stiff silty sandy clay.
• i • 1 . •
drilling than the normal high water level, due to the drought
conditions which have persisted in the past few years® The water level
E CONSULT T% INC.
Mr. Mark Hanson 7 June 1, 1990
bottom of the cap at least -- below
protection from frost penetration.
Details on our recommendations are. presented below.
tips should be driven would vary. We anticipate that pile lengths
below existing f r .. • - i i f be • • i ,..
If a pile does not have adequate blow counts after penetrating at least
25 feet into the non-organic stiff clay, we recommend leaving it
ONIS CONSULTANTS, INC.
Mr. Mark Hanson 8 June 1, 1.990
a and retapping the pile the next day. Due to the "pile
freeze," the capacity of the pile should increase with time.
Because of the relatively stiffer upper layer of fill overlying the
organics, it is our opinion that piles driven through the soil profile
found in the borings would have adequate lateral capacity, We
recommend that the bottom of the pile caps be at least 6 feet below
Lf caissons are chosen, we recommend that straight shaft piers be used.
Where water
bearing soils or
soft
clay are encountered, t
woul e
necessary to
first drill in a
pilot
shaft with bentonite mud
and then
insert a steel casing sealed into an underlying low permeability
cohesive layer. Beyond this depth the shaft could be extended with
augers.
ONIN CONSULTANTS, INC.
Mr. Mark Hanson 10 June 1, 1990
Since groundwater was encountered in the borings, it should be
anticipated that groundwater would be encountered if caisson
foundations are used. Groundwater should not be a serious problem if
driven treated timber pile foundations •'
Although we did not encounter obstacles in our boreholes, we did
observe slabs of concrete and asphalt block and other materials
safety as well as noise, is solely that of the contractors. This
responsibility is not horn in any manner by GME Consultants, Inc.
OE CONSULTANTS, IC.
Mr. Mark Hanson 9 June 1, 1990
The lateral capacity
• caissons drilled through the soil prof ile
should be adequate for the anticipated structural loadings.
O CONSULTANT% 1 NC.
Mr. Mark Hanson 11 June
GME CONSULTANTS, INC.
Mr. Mark Hanson
W-1
M
L�Wlv *L '43
at I am a dury
GME CONSULTANTS, INC,
i E CONSULTA Ti. INC.
FFSE\
EXISTING
MARSH
B-2
896.2
PROPOSED NEW
SHORELINE
-W
EXISTING CREST
OF SLOPE
"`EXISTING
SOCCER/FOOTBALL
FIELD
SHORELINL\
*
B-1
887.9
B-3
896.7
LIGHT STANDARD
LOCATION
(TYPICAL) I
BASEBALL DIAMOND
SCALE
0 40' 80
NOTE:
BORING LOCATIONS STAKED BY BONESTROO
SOIL BORING LOCATION DIAGRAM
G CONSULTANTS, INC.
PROPOSED LIGHT STANDARDS
2083 EAST CENTER CIRCLE
SCIENCE INDUSTRY PARK
MINNEAPOLIS, MINNESOTA $5441
NEW HOPE, MINNESOTA
__U::K:Mll
WCK 254
DRILLING & SAMPLING SYMBOLS:
SL SS with Liner
otherwise noted
". ="*ux Tube --2 O.u, unless otherwise noted
PA Power Auger
DB DiomondBit - -NX:BXA%
AS Auger Sample
JS Jar Sample
VS Vane Shear
OS
Osterberg Sampler — 3^ Shelby Tube
HS
Hollow Stem Auger
VV8
Wash Sample
FT
Fish Trail
RB
Rock Bit
BS
Bulk Sample
PM
Preueunameherh*a- -insitu
Standard ^N^Penetration: Blows per foot ode14O pound hammer falling 3O inches ona2 inch O[] split spoon, except
where noted.
VVL
Water Level
VVC|
Wet Cave In
DC|
Dry Cave In
WS
While
WD
While Drilling
BCR:
Before Casing Remvoo
*CR:
After Casing Removal
AB :
After Boring
Water leve indicated on the boring the boring sd the times indicated. |n previous moi|s, the
."indicated elevations are considered reliable ground water levels. u//m determination cfground
water elevations is not possible in even several days observation, and additional evidence of ground water elevations must be
Coarse Grained o, Granular Soils have more than 50% of their dry weight retained on a #200 sieve;
boulders, cobbles, gravel or sand. Fine Grained Soils have less than 50% of their dry weight retained on a #200 sieve; they are
described as: clays or clayey silts if they are cohesive, and silts if they are non-cohesive. In addition to gradation, granular
soils are defined on the basis of their relative in-place density and fine grained soils on the basis of their strength or
consistency, and their plasticity.
Major
Component
Kwn Components Also
Percent of
Of Sample_
Size Range
Present in Sample)
D ry Weight
----Isf----
Boulders
Over in. (yOUmm)
Trace
1 --S
Cobbles
8 in. ho3in.
Little
10--19
Soft
(200mm1o75mm)
Loose
0.50— 0.99
Gravel
3in. to#4sieve
Some
28--34
Stiff
(75mm1o2mm)
Dense
2.00--3.99
Sand
#4bz#208sieve
And
35--50
Hard
(2mm80.874mm)
Extremely Dense
>8.OU
Silt
Passing #200 sieve
(0.04mm0u0.005mm)
Clay
Smaller than 0.005mm
IL
UncmwYIned
Strength, Ou,
----Isf----
Consistency
0 — 18lowsyft.
Relative Density
<0.25
Very Soft
0--3
Very Loose
0.25--049
Soft
4--9
Loose
0.50— 0.99
Medium (Firm)
10--29
Medium Dense
1.00--1.89
Stiff
30--48
Dense
2.00--3.99
Very Stiff
50--80
Very Dense
4.00--8.00
Hard
80+
Extremely Dense
>8.OU
Very Hard
GME CONSULTANTS, INC.
9'
5SS Black fine SILTY SAND, trace gravel
few thin peat seams - very loose -
wet - (SM)
13'
6SS Gray fine SILTY SAND, trace gravel
very loose - wet - (SM)
18'
7SS Brown fine SANDY CLAY WITH SILT,
trace gravel - firm to stiff -
(CL)
Boring continued on next page
*NOTE: Sampler advanced by weight
of rod and hammer
k1
0
e�
8 66
12
CONSULTANTS — ��l I I
GME 3
Geotechnical * Materials e Environmental
14000 21st lbw" No.
Minneapolis, MN 55447
LOG OF BORING 1
PROJECT
Science
Industry Park
SITE
Research Center Road
Light
Standards
New Hope,
Minnesota
CLIENT
ARCHITECT - ENGINEER
City
of
New Hope
Bonestroo Rosene Anderlik & Associates
W
UNCONFINED COMPRESSIVE STRENGTH TONS/FT 2
W
L
F
LL
—®-
Ir W
DESCRIPTION OF MATERIAL
' 2 4 5
w
a
®
WATER
w
0
m
CONTENT%
w°
a
w
4
U J
w
�
- -
STANDARD PENETRATION (BLOWS /FOOT)
n
o
20
a
f-
3
N
SURFACE ELEVATION 887,9
-®-
1 20 30 40 50
1SS
Black PEAT - very soft - moist,
wet at 6 feet - (Pt)
2SS
3
3SS
QCC
'3c
9'
5SS Black fine SILTY SAND, trace gravel
few thin peat seams - very loose -
wet - (SM)
13'
6SS Gray fine SILTY SAND, trace gravel
very loose - wet - (SM)
18'
7SS Brown fine SANDY CLAY WITH SILT,
trace gravel - firm to stiff -
(CL)
Boring continued on next page
*NOTE: Sampler advanced by weight
of rod and hammer
k1
0
e�
8 66
12
CONSULTANTS — ��l I I
GME 3
Geotechnical * Materials e Environmental
14000 21st lbw" No.
Minneapolis, MN 55447
End of boring at 40 feet
Hollow stem auger used full depth
Borehole backfilled with cuttings
*NOTE: Sampler advanced by weight
of rod and hammer
LOG OF BORING 1 (continued)
PROJECT
Science Industry Park
517E
Research Center Road
Light Standards
New Hope, Minnesota
CLIENT
ARCHITECT- ENGINEER
city
New Hope
Bonestroo Rosene Anderlik & Associates
W
INED COMPRESSIVE STRENGTH TONS/FT 2
Cr
W
LL
Uj
Z
DESCRIPTION OF MATERIAL
2 3 4 5
T s
WATER
W
>
'z
W
co
CONTENT %
Z
III
�
U
<
JU)
F
a F
w
U
Q
STANDARD PENETRATION (BLOWS /FOOT)
a
z
c1 C
t-
3
g
cc
>
Z
- -
10 20 30 40 50
Brown fine SANDY CLAY WITH SILT,
trace gravel - firm to stiff -
(CL)
A /].
11 SS
14
End of boring at 40 feet
Hollow stem auger used full depth
Borehole backfilled with cuttings
*NOTE: Sampler advanced by weight
of rod and hammer
-r
LOG OF BORING 2 (Offset to top of slope)
PROJECT
Science Industry Park
SITE
Research Center Road
Light
Standards
New Ho pe, Minnesota
CLIENT
ARCHITECT - ENGINEER
City of New Hope
Bonestroo
Rosene And erlik & Associates
L
UNCONFINED COMPRESSIVE STRENGTH TONS/FT 2
Lu
LL
- 0 -
W
DESCRIPTION OF MATERIAL
O
t 2 3 4 5
W
g
Z w
w
¢
U
t-
�
m
WATER
CONTENT %
W tL
W
Q
-' N
-J
W
Q
- -
STANDARD PENETRATION (BLOWS /FOOT)
W
N¢
Cr
SURFACE ELEVATION -896.2
N W
Z
-®-
10 20 30 40 50
1SS
6
Brown fine CLAYEY SAND, trace silt,
1
2SS
gravel - loose - damp - (SC)
8
3SS
4
4SS
8"
(Fill)
7
5SS
Brown fine SILTY SANDY CLAY, trace
5
l
gravel - firm to very soft - (CL)
5
6SS
7SS
1
23,
(Fill)
8SS
Black fibrous PEAT - firm - waist -
(Pt)
7
NA
28
9SS
Gray fine SILTY SAND, trace clay -
very loose - wet - (sM)
33
Gray fine SILTY SANDY CLAY, trace
lOS
gravel - firm to very stiff - (CL)
5
Boring continued on next page
*NOTE: Sampler advanced by weight
Geotechnical a Materials e Environmental
—
of rod and hammer
14000 21st Avenue No.
Minneapolis, MN 55447
LOG OF BORING 3
PROJECT
Science Industry Park
SITE
Research Center Road
Light
Standards
New Ho , Minnesota
CLIENT
ARCHITECT- ENGINEER
Cit
of New Ho
Bonestroo
Rosene Anderlik & Associates
r
UNCONFINED COMPRESSIVE STRENGTH TONS /FT?
LL
m
0
DESCRIPTION OF MATERIAL
3
' 2 3 4 5
tT
W
M
w d
W
t
a
m
WATER
CONTENT
LL
W
z W 0.
1--
-j
W
I-
C
W
U 5
4
STANDARD PENETRATION (BLOWS /FOOT)
®
N <
SURFACE ELEVATION 896.7
a. W
z
10 20 30 40 50
iSS
13
JIM
Brown and dark brown fine SANDY
CLAY, trace silt - very stiff to
2SS
firm - (CL)
17
3SS
8
4SS
$
9,
( Fill)
0
5SS
6
Brown fine SILTY CLAYEY SAND, trace
gravel - loose - damp - (SC -SM)
7
6SS
19
(Fill)
7SS
Black fibrous PEAT - firm - moist
-
7
(Pt)
24
8SS
Gray CLAYEY SILT, trace fine sand
-
1
very loose - moist - (ML)
29
Gray fine SILTY SANDY CLAY - very
9
soft to stiff - (CL)
1
Boring continued on next page
GME
CONSULTANTS
Geotechnical
a Materials 9 Env'Ironmental
14000 21st Avenue No.
Minneapolis, MN 55447
LOG OF BORING 3 (continued)
PROJECT
Science Industry Park
SITE Research Center Road
Light Standards
New Hope, Minnesota
CLIENT
ARCHITECT- ENGINEER
City of New Hope
Bonestroo Rosene Anderlik & Associates
W
UNCONFINED COMPRESSIVE STRENGTH TONSI
W
-®
w
M
tw9
DESCRIPTION OF MATERIAL
O
1 2 3 4 5
w Q
WATER
U.
z w
W U L
m
CONTENT %
I
I a.
a ►'
w I
`t
Q
STANDARD PENETRATION (BLOWSIFOOT)
a
g o
¢
I- °�
3
w (
¢
>
- ®-
to
to ¢
Z
10 20 30 40 50
Gray fine SILTY SANDY CLAY -
very soft to stiff - (CL)
I1SS
9
End of boring at 40 feet
Hollow stem auger used full depth
Borehole backfilled with cuttings
WATER
LEVEL
OBSERVATIONS
BORING STARTED
—
—
W.L.
23 feet
while drillin
C SULT'A e IN C.
BORING_ C 5 - -90
W.L.
j
21 feet
after drillin
Gemec . Materials . Envenmriental
14000 21st Avenue No.
RIG CME -750
DRILLER KJS
W.L.
Borin
caved at 26.5 feet
` Mmneepo6e. MN 55447
(612) 559 -1659
DRAWN
APPROVED
after auger removal
J B# 2547
SHEET
The stratification lines represent approximate boundaries
between soil types; insitu the transition may be gradual.
XASSIFICATION OF SOILS FOR ENGINEERING PURPOSES
(ASTM D 2487 and 2488)
Major divisions Group Typical names Laboratory classification criteria
symbols � I
Pt
= m
Well- graded gravels, gravel -sand
mixtures, little or no fines
Poorly graded gravels, gravel -
sand mixtures, little or no fines
Silty gravels, gravel- sand -silt
mixtures
Clayey gravels, gravel- sand -clay
mixtures
Well- graded sands, gravelly
sands, little or no fines
Poorly graded sands, gravelly
sands, little or no fines
Silty sands, sand -silt mixtures
Clayey sands, sand -clay mix-
tures
Inorganic silts and very fine
sands, rock flour, silty or clay-
ey fine sands or clayey silts
with slight plasticity
Inorganic clays of low to me-
dium plasticity, gravelly clays,
sandy clays, silty clays, lean
clays
Organic silts and organic silty x
clays of low plasticity a
0
e
u
Inorganic silts, micaceous or io
diatomaceous fine sandy or °•
silty soils, elastic silts
Inorganic clays of high plas-
ticity, fat clays
Organic clays of medium to
high plasticity, organic silts
Peat and other highly organic
soil
D 60 (D30)
N a
GW
0
Dro DroXD60
yw
m
c
o
R o
m e
Not meeting all gradation requirements for GW
0 o V a N r
y
•` N
O O
U N
and
d
GP
e:
CL
N
' N
p O
w Z
line or P.I. less than 4
Above "A" line with P.I.
s c O O c a 0
>
O ` 0 CA
c
N
°
N
d
'u
w
w o
GM
or P.I. greater than 7
u
o
N
« m
M
E
=e
td
O H
d
i m
O—
0)
3a
:: c
D60 (D30)2
A '6
Z
2
0 2 `°
at O
C
E
N
i
MH
m
c
Ln
CL
GC
c
^c
a
A a�
C.
r
N w
0.
a
.
E
io
2 y
° t
a c () a
li or P.I. less than 4
Limits plotting in hatched
c 'v a
E `m d o$
CH
c
a C L J.
is
N
a
SW
E
O
c
o a
c
N C
bols.
line or P.I. greater than 7
N
N
C
o
N
t
`
w a
W
a a
S
y
U
SP
M C
y
N
N O
U C
coZ
a
m 'o
E
SM
r m
®E
.5
LaaNi
u
N
°
g N
e
M .�
3 N a
v 'u °o
a
SC
Q
Pt
= m
Well- graded gravels, gravel -sand
mixtures, little or no fines
Poorly graded gravels, gravel -
sand mixtures, little or no fines
Silty gravels, gravel- sand -silt
mixtures
Clayey gravels, gravel- sand -clay
mixtures
Well- graded sands, gravelly
sands, little or no fines
Poorly graded sands, gravelly
sands, little or no fines
Silty sands, sand -silt mixtures
Clayey sands, sand -clay mix-
tures
Inorganic silts and very fine
sands, rock flour, silty or clay-
ey fine sands or clayey silts
with slight plasticity
Inorganic clays of low to me-
dium plasticity, gravelly clays,
sandy clays, silty clays, lean
clays
Organic silts and organic silty x
clays of low plasticity a
0
e
u
Inorganic silts, micaceous or io
diatomaceous fine sandy or °•
silty soils, elastic silts
Inorganic clays of high plas-
ticity, fat clays
Organic clays of medium to
high plasticity, organic silts
Peat and other highly organic
soil
D 60 (D30)
ML
C,=—greater than 4; C between 1 and 3
0
Dro DroXD60
°1
m
G
O1 e
e
Not meeting all gradation requirements for GW
0 o V a N r
y
m
N
N
U N
a
e:
CL
-�-
m •—
N E
line or P.I. less than 4
Above "A" line with P.I.
s c O O c a 0
between 4 and 7 are border-
°
N
line cases requiring use
h m
Atterberg limits below "A"
�o
Q
or P.I. greater than 7
o v
td
O H
OL
c
:: c
D60 (D30)2
A '6
C greater than 4; C between 1 and 3
v m =
D10 DroXDso
C y
E
N
MH
m
c
Ln
o .
�
c
^c
a
A a�
C.
r
N w
0.
a
.
E
io
° t
a c () a
li or P.I. less than 4
Limits plotting in hatched
c 'v a
E `m d o$
CH
c
a C L J.
a m
Dow '
requiring use of dual sym-
to
Nv
bols.
line or P.I. greater than 7
2
:%
OH
Pt
= m
Well- graded gravels, gravel -sand
mixtures, little or no fines
Poorly graded gravels, gravel -
sand mixtures, little or no fines
Silty gravels, gravel- sand -silt
mixtures
Clayey gravels, gravel- sand -clay
mixtures
Well- graded sands, gravelly
sands, little or no fines
Poorly graded sands, gravelly
sands, little or no fines
Silty sands, sand -silt mixtures
Clayey sands, sand -clay mix-
tures
Inorganic silts and very fine
sands, rock flour, silty or clay-
ey fine sands or clayey silts
with slight plasticity
Inorganic clays of low to me-
dium plasticity, gravelly clays,
sandy clays, silty clays, lean
clays
Organic silts and organic silty x
clays of low plasticity a
0
e
u
Inorganic silts, micaceous or io
diatomaceous fine sandy or °•
silty soils, elastic silts
Inorganic clays of high plas-
ticity, fat clays
Organic clays of medium to
high plasticity, organic silts
Peat and other highly organic
soil
10
7
4
0 10 20 30 40 50 80 70 80 90 101
Liquid Limit
Plasticity Chart
D 60 (D30)
C,=—greater than 4; C between 1 and 3
Dro DroXD60
°1
G
O1 e
a �
12 F
Not meeting all gradation requirements for GW
0 o V a N r
y
N
N
y c ( e
m OOa0
Atterber limits below "A"
g
-�-
c 3 s o E
line or P.I. less than 4
Above "A" line with P.I.
s c O O c a 0
between 4 and 7 are border-
°
N
line cases requiring use
h m
Atterberg limits below "A"
of dual symbols
w line
or P.I. greater than 7
o v
td
O H
:: c
D60 (D30)2
A '6
C greater than 4; C between 1 and 3
v m =
D10 DroXDso
C y
g C
N
w '
o .
Not meeting all gradation requirements for SW
a C •"• y U
m °
A a�
C.
0.
e 'm c
° o
Atterberg limits below "A"
° t
a c () a
li or P.I. less than 4
Limits plotting in hatched
c 'v a
E `m d o$
zone with P.I. between 4
c
a C L J.
and 7 are borderline cases
Dow '
requiring use of dual sym-
Atterberg limits below "A"
bols.
line or P.I. greater than 7
10
7
4
0 10 20 30 40 50 80 70 80 90 101
Liquid Limit
Plasticity Chart
For classification of fine-grained
grained soils.
—Atterberg Limits rr
b L. symbols
requiring use of dual
Equation of A-line:
-
-
-�-
��r��
___�_ fications
10
7
4
0 10 20 30 40 50 80 70 80 90 101
Liquid Limit
Plasticity Chart
The placement of compacted fill for support of foundations, floor slabs, pavements, or earth structures should be
carried out by an experienced excavator with the proper equipment. The excavator must be prepared to adapt his
procedures, equipment, and materials to the type of project, to weather conditions, and the structural requirements of
the architect and engineer. Methods and materials used in summer may not be applicable in winter;,fill used in dry
excavations may not be suitable in wet excavations or during periods of precipitation; proposed fill soil may require
wetting or drying for proper placement and compaction. Conditions may also vary during the course of a project or in
different areas of the site. These needs should be addressed in the project drawings and specifications.
irry
It is common to have to excavate and replace unsuitable soils below the water table for site correction. As a general
rule of prudent construction technique, we recommend that excavation /backfill below the water table not be permitted,
unless the excavation is dewatered. Numerous problems can develop when this procedure is attempted without
dewatering.
— Inability of the equipment operators and soil technicians to
observe that all unsuitable soil /materials have been removed from
the base of the excavation.
— Inability to observe and measure that proper lateral oversizing is
provided.
— Inability to prevent or correct sloughing of excavation sidewalls,
which can result in unsuitable soils trapped within the select
backfill.
— Inability of the contractor to adequately and uniformly compact
the backfill.
— Possibility of disturbance of the suitable soils at the base of the
excavation.
The dewatering methods, normally chosen at the contractor's option, should follow prudent construction practice.
Excavations in clay can often be dewatered with sump pits and pumps; this technique would not be applicable for
excavation extending into permeable granular soil, especially for depths significantly below the water table. Dewater-
ing granular soils should normally be done with well points or wells. When dewatering is needed, we strongly
recommend that the procedures be discussed at pre -bid or pre - construction meetings. The dewatering technique
chosen by the contractor should be reviewed by the architect and engineer before construction starts; it should not be
left until excavation is under way.
The selection of proper backfill materials is important when working in dewatered excavations. Even with dewatering,
the base is usually wet and the contractor must be careful not to disturb the base. We recommend that the first lifts of
backfill be a clean medium to course grain sand with less than 5% passing the #200 sieve. The use of silty sand, clayey
sand, or cohesive /semi - cohesive soils is not recommended for such situations. The excavator should be required to
submit samples of the proposed material(s) he plans to use as backfill before the fill is hauled to the site, so that it can
be tested for suitability.
INTER EARTHWORK CONSTRUCTION
Winter earthwork presents its own range of problems which must be overcome; the situation may be complicated by
the need for dewatering discussed above.
During freezing conditions, the fill used must not be frozen when delivered to the site. It also must not be allowed to
freeze during or after compaction. Since the ability to work the soil while keeping it from freezing depends in part on
the soil type, the specifications should require the contractor to submit a sample of his proposed fill before construc-
tion starts, for laboratory testing. If the soil engineer and structural engineer determine that it is not suitable, it should
be rejected. In general, silty sand, clayey sand, and cohesive /semi - cohesive soils should not be used as fill under
freezing conditions. All frozen soil of any type should be rejected for use as compacted fill.
It is important that compacted fill be protected from freezing after it is placed. The excavator should be required to
submit a plan for protecting the soil. The plan should include details on the type and amount of material (straw,
blankets, extra loose fill, topsoil, etc.) proposed for use as frost protection. The need to protect the soil from freezing is
ongoing throughout construction and applies both before and after concrete is placed, until backfilling for final frost
protection is completed. Foundations placed on frozen soil can experience heaving and significant settlement, rota-
tion, or other movement as the soil thaws. Such movement can also occur if the soil is allowed to freeze after the
concrete is placed and then allowed to thaw. The higher the percentage of fines (clay and silt, P -200 material) in the fill,
the more critical is the need for protection from freezing.
GIVIE CONSULTANTS, INC.
MOISTURE CONTROL OF FILL -
The contractor should be required to adjust the moisture content of the soil to within a narrow range near the optimum
moisture content (as defined by the applicable Proctor or AASHTO Test). In general, fill should be placed within about
2% of optimum. The need for moisture control is more critical as the percentage of fines increases. Naturally- occurring
clayey sand or cohesive /semi- cohesive soil are often much wetter than the optimum. Placing and attempting to
compact such soils to the specified density may be difficult, or not possible. Even if compacted to the specified density,
excessively wet soils may not be suitable as floor slab or pavement subgrades due to pumping Lander applied load. This
is especially true when wet cohesive /semi- cohesive soil is used as backfill in utility trenches under streets. Excessively
wet soil in thick fill sections may cause post - construction settlement beyond that estimated for fill placed at or near
(±2 %) the optimum moisture content.
An exception to this would be low permeability soil placed as a pond liner or for a dam. Such soil should usually be
placed at 2% to 4% above the optimum moisture content, to provide for a lower insitu permeability. Also, shrinking/
swelling soils (expansive clay) should be placed at about 2% to 4% above optimum moisture to reduce the possibility of
soil expansion. Clayey silt, silt, or very silty fine sand should be placed excessively dry. Such soils can undergo
post- construction consolidation upon being wetted, even if the specified density had been achieved. This is caused by
the collapse of flocculant soil particle arrangement, and can result in settlement of buildings or slabs constructed over
the soil.
Proper control of fill soil moisture is the responsibility of the excavator. The excavator should evaluate the need for
wetting or drying the soils, based either on the data in the soil report, or his own site testing. If the excavator is bringing
in off -site fill, it is also his responsibility to evaluate the moisture content of the soil, and the need for wetting or drying.
We recommend that this matter be addressed in the project specifications.
CONSTRUCTION ON COMPACTED SOIL
After the select fill has been placed, compacted, and tested, it must be maintained and protected in order to properly
support structures. The suitability of compacted fill soil can be greatly diminished if it is allowed to freeze, become
saturated while unconfined (such as in footing excavations or at the surface of slab /placement subgrade), or disturbed
by construction equipment.
The responsibility for protecting the soil, or for correcting any disturbance, should be clearly defined in the specifica-
tions. Soils which become wet and soft after compaction testing do not necessarily reflect inaccurate field density
tests. Especially with non - expansive cohesive /semi- cohesive soils, saturation when unconfined can severely reduce
the shear strength while the density remains adequate. The reduced shear strength can cause footings, floor slabs, or
pavements to settle or fail under load. We strongly recommend that all pavement subgrade be test rolled (MN /DOT
Specification 2111) immediately before paving to determine if the subgrade has not been protected and soft spots have
developed.
FLOOR SLAB SU GRADE AND UTILITY TRENCHES
This facet of construction presents special problems, especially if the slab subgrade is allowed to freeze. When the soil
thaws, it undergoes a period of temporarily lower shear strength. Floor slabs should not be cast over soil in such a
weakened or frozen condition (reference pertinent PCA and ACI publications). To do so can result in cracked and
failing slabs. The time period to heat and thaw a building may place the construction schedule and /or costs in
jeopardy. We strongly recommend that this matter be reviewed in pre -bid and pre - construction meetings.
Backfilling of utility trenches in the floor slab subgrade can be difficult. if the soil is wet, compaction to the specified
density may be difficult, or not possible. The narrowly cut trenches may preclude the use of proper compaction
equipment. With the use of small equipment in confined areas, the contractor must place the soil in thin lifts (4 to 6
inches), with the soil at the proper moisture content This work is typically carried out by contractors other than the
mass grading or earthwork contractor. We strongly recommend that the responsibility to carry out the compaction be
clearly detailed in the applicable section of the specifications, and reviewed with the appropriate contractor and
subcontractor.
GIVIE CONSULTANTS. INC.
2 slab opening for Neenah
R3067 or equal
Dimension from back of
curb
to
center of
pipe.
V
Dia.
MH —
9*
in from
Back of Curb
5"
Dia.
MH —
3'
in from
Back of Curb
6'
Dia.
MH —
T
behind
Back of Curb
7'
Dia.
MH —
9"
behind
Back of Curb
8'
Dia.
MH —
15'
behind
Back of Curb
I
I'VVII
41 4
0- w errWl
Minimum of 2 maximum of 5
concrete adjustment rings with full
bed of mortar between each and
a e collar on the outside.
7 precast reinforced concrete slatF
E
Manhole steps, Neenah R1981J or
equal, W o.c., Aluminum steps
tpproved.
-E6NQARQ-D-E�T
TYPE 11
CATCHBASIN MANHOLE
R=
1�M N
1-16.DWG
CLASS C-1
HAND SHAPED FROM
FIRM UNDISTURBED
"Bc" Denotes outside
diameter of Pipe
Barrel
w Bot(2 " KXin|mum
Anderlik a Assoc. Inc.
Consulting Engineers
St. Paul, Minnesota
Concrete
Plate No.
Compacted
BockfU|
LOAD FACTOR ig LOAD FACTOR 2.3
Compacted Backfill
/
�
Foundation
Variable
K8|n|murn = 2d + Bc f|2"
"Bc" Denotes outside
diameter of Pipe
Barrel
Anderlik S Assoc. Inc. STANDARD DETAILS
Consulting Engineers IMPROVED FOUNDATION
'
Bc
Variable
ea p
ng
" r
G
Pay Dept
|norements
6" (Typical)
-Coarse Filter
Aggregate
(&4nD{)T Spec. 3149H
Modified)
wz=M
CHWO
SIZE of PIPE Cu. Yd.
54 8i Over 16
36" to 48" 12
27" to 33" 8
24!' & Less 4
IE— Tie lost 3 joints. Use 2 tie
bolt fasteners per' joint
Installed at 60* from top or
bottom of pipe
Hand placed Rip-Rap I deep
Individual stones shall weigh not
less than 50lbs. each
Set with Grout
Size of Pipe
Bars
" H"
Bolts
Provide 3 clips to fasten Trash Guard 12" t I B"
3/, o
to
4
5/11
78
to Flared End. Hot dip galvanize 21" to 42'
1 1
6 , 1
3,4'
after fabrication. 48"to 72"
1 1 /46
IZ
I"
F
UN21='i
6 Max.
_T
Bonestroo, Rosene, STANDARD DETAILS Revisions Plate No.
An,derilk a Assoc-Inc.
Consulting Engineers FLARED END SECTION 1-28
St. Paul , Minn. AND TRASH GUARD
SIDE VIEW
Backfill to be
I Cubic Yard gravel
or crushed rock.
Cover with
polyethylene.
rock.
-1
/--- 8" Concrete block
HYDRANT INSTALLATION
Bonestroo , Rosene
Anderlik a Asso. Inc.
Consulting Engineers
St. Paul, Minn,
r4 %4" thrust
— block
6"x 6" vertical
- block
STANDARD DETAILS
GATE VALVE Ek BOX
AND HYDRANT INSTALLATM
block
Revisions Plate No.
Apr. '73
Anr. 81 2 - I A
U)
C
0
A� lb
lop
am
0
V
CONCRETE
BEDDING
MATERIAL:
BUTTRESS DIMENSIONS
PIPE
22 1 12 0 BENDS
45 BENDS
90 BENDS
SIZE
8
D,
8
D
8
D
6
5
1' -5
1' -5
2' - 1
1'-6"
8
-5"
1' -5"
2 1
1 ' - 6 ..
2' -8 .,
2-0
12"
1
3 ' - 4
2' 0
4-9
2 -6 "
16
'- 0
3 - 0
2' -0"
3
3- 0"
6'- 2
3- 6"
0'
2
E E24
3- 6
L44
2*- 8 1.
5- 6 .1
S-4"
8'-4"
4- 0"
"
3 =0"
6'-10"
3' -10"
9 1 -8 1,
5 1 -0 .1 ,
Bonestroo, Rosene,
Anderlik a Assoc., Inc.
Consulting Engineers
St. Paul, Minnesota
W
CONCRETE
0as
W(r
Ir
0(n
M 0
w
en:)
+
02
1- (r
0) cr
wtl-w
0: to
Z
co<
I
t4 o'TE I
I. DIMENSIONS IN TABLE ARE BASED ON A
WATER PRESSURE OF 150 P S 1, AND AN EARTH
RESISTANCE OF I TON PER SO. FT.
2 WOOD BLOCKING MAY BE USED IN LIEU OF
O y �N gpETE FOR 6" 8 8"10 45 BENDS AND FOR
6 8 a 12 " 0 22 1/2 0 BENDS PROVIDED AREA IN
CMN CT WITH EARTH IS SAME AS AREA SHOWI
3. DIMENSION C C C SHOULD BE LARGE
ENOUGH TO MAKE ANGLE 9- EQUAL TO OR
LARGER THAN 45
4. DIMENSION A, A A SHOULD BE AS
LARGE AS POSSIBLE WITHOUT INTERFERRING
WITH M. J. BOLTS.
5. SHAPE OF BACK OF BUTTRESS MAY
VARY AS LONG AS POUR IS AGAINST FIRM
UNDISTURBED EARTH.
Revisions I Plate No.
PLAN-45* BEND
APPROX. 1:1 SLOPE
WHERE DEPTH BLOW
PIPE EXCEEDS 6
SECTION A-A
If 6 11 Distance to variable
1/ 2 r
r
= (01 37 1/211r
slo e 3/4" er ft..
18
Distance to variable
r
= (0 1/2"r
s l o , e '3/4 er ft. 3/
1 /2/1r I
"
s i o - 3/4! r f t.,, 11 //2 r
12 I 12'
T Y P
STANDARD SECTION
B618
CONCRETE CURB 8 GUTTER
TYPE "B"
STANDARD SECTION
M.H.D. B624
CONCRETE CURB a GUTTER
TYPE
STANDARD SECTION
SURMOUNTABLE
CONCRETE CURB • GUTTER
1/Z rA r Distance to �- variable
Bituminous surface TYPE oa D"
STANDARD SECTION
Co M. H. D. B6
VII Gravel base
CONCRETE CURB
Type"A'or Type Curb
r 3/4, er 1/2" TYPE — A B, C
slope
C\J: STANDARD SECTION
DRIVEWAY
10" 1, 16 A 22 Type B
12 ' IZ'—TVDe C
Bonestroo, Rosene,
Anderlik Ek Assoc, Inc.
Consulting Engineers
St. Paul, Minnesota
STANDARD DETAILS
CONCRETE CURB B GUTTER
Revisions I Plate No.
kiff
e
Type A, B,C or D
concrete curb 8 gutter 4'- 0 _ = 4" Conc. waIR
See plots 4 -I -_ _-___--- -------------
----
i ' E I�� er. f4. �• �• f �'' .�'
o oa
Bonestr Ro sene, Revisions Plate N 0.
Anderlik a Assoc., Inc. ST ANDARD •
Consulting Engineers -3
PED EST R IAN • P,. RAMP e
St, Paul, Minnesota
conc. curb
A
B618 conc. curb
a gutter,
1 10 Min. Transition
F B616 curb Ek gutter
77;
RTr'MF=
'R�- MIIIIII
Catchbasin frame
Eh cover.
F41
I - 10'Min. Transition
F j—Top of curb
2-No.4 rebors Expansion—I
Joint
Neenah frame S cover or equal
R-3067 with Type DL grate
oo
Revisions
Bonestr Rosene
I SPECIAL DETAILS 2-19-82 JKI
Anderlik and Assoc, Inc. i
Consulting Engineers B618 CURB 8 GUTTER
St. Paul, Minn. CONSTRUCTION AT CATCH BASIN
[Oyzii
I=
Catchbosin costing
Neenah R-3067
or equal.
3" radius curb box
Min. 2, Max. 3
Conc. adjustment
rings.
®onestroo, Rose ,
Anderlik a Assoc., Inc.
Consulting Engineers
St, Paul, Minnesota
a
No. 3 re bar ( to extend
12" beyond each side
of costing ) Embedded
in conc. collar and
curb.
CONCRETE SPECIAL DETAILS
i CASTING
ON TYPE 11: CATCHBASIN
Conc. collar to encase
costing and rings.
Conc. curb mix
shall be used for
conc. collar.
0
Grout shall be placed
inside.between and
outside of conc.
adjustment rings.
Conc. or metal shims
shall be used to
level costing.
wood stakes
8' Maximum spacing
W
3:
M
D
:2
z
:2
Support post anchorage
in—situ soil
Engineering fabric. Mirafi
"Envirofenc or equal.
Fabric anchorage trench
Backfill trench with
tamped natural soil
In
.N2t_%- Attach fabric to
support posts with
lath and staples
63vag 1 11 T. - n - I big 0 W
r "Ic - s - t — R — evision.-
may, 19190
SUPPLEMENTAL CONDITIONS OF THE CONTRACT
3.1. AWARD OF CONTRACT
The award of the project shall be made to the lowest responsible bidder based
on the lowest base bid amount. The Owner reserves the right to retain all
bids for 45 days prior to awarding the Contract.
8.14. ONE -YEAR CORRECTION PERIOD
The correction period is herewith revised to two years.
OUT -OF -STATE CONTRACTOR SURETY DEPOSIT
When an out -of -state Contractor enters into a contract that exceeds
$100,000.00, the Contractor must file Form SD -E, Exemption from Surety
Deposits for Out -of- State Contractors, with the Minnesota Department of
Revenue. If the Contractor is exempt from the surety deposit requirements, he
shall provide the Owner with a copy of the form showing the Revenue Department
certification. If the Contractor is not exempt, the Owner will withhold an
additional eight (8) percent of each payment made to the Contractor and
forward those funds to the Minnesota Department of Revenue. Forms and
information can be obtained by calling (612) 296 -6181 or (toll free)
1 -800- 657 -3777.
CERTIFICATE OF COMPLIANCE WITH MINNESOTA STATUES 290.92 & 290.97
Upon completion of the project and prior to final payment, the Contractor and
all subcontractors shall complete Minnesota Department of Revenue Form _IC -134,
revised September, 1989. This form, Withholding Affidavit for Contractors,
must be stamped and dated by the Department of Revenue and forwarded to the
Owner. Contractors can obtain copies of this form from the Owner or from the
Minnesota Department of Revenue, Mail Station 4450, St. Paul, MN 55416 or by
calling (612) 296 -6181.
3471S
Copyright 1990
Bonestroo, Rosene, Anderlik
& Associates, Inc.
STATE OF MINNESOTA
County of- jjgmPI j ss.
On this---------- - - - - -- 2 nd , _ day of JX
John P. Martinsen A. D. 19-9.Q, before me appeared
-------------- ---- "--- •------------ - -. -__ __ _ -_ - - - -. -, to me personally known, who, being by me duly sworn, did say
that he is the Agent and Attorney -in -Fact of the UNIVERSAL SURETY COMPANY, a corporation
organized and existing under the laws of the State of Nebraska; that the seal affixed to the foregoing
instrument is the corporate seal of said corporation; that said instrument was signed and sealed in be-
half of said corporation by authority of its Board of Directors; and said ------
Mar
acknowledged sai nstrument to be the free act and deed of aid car o
RACNt! THoh,lg*
- - - - -- ---- - - - - --
My Commission ptr Y��w. -, -ice Notary P lic__
,,� - - - - -- County, Minn.
LINCOLN, NEBRASKA
POWER OF ATTORNEY
1 J�,I1 4JA I� Thew Vrrsrnts:
That the UNIVERSAL SURETY CONIPAM , a corporation of the State of Nebraska, having its principal office in the City of Lincoln, Nebraska, pursuant to the
following By -Law, which was adopted by the Board of Directors of the said Company on July 23, 1981, to -wit:
"Article V- Section 6. RESIDENT OFFICERS AND ATTORNEYS -IN -FACT. The President or any Vice- President, acting with any Secretary or Assistant Secretary.
shall have the authority to appoint Resident Vice- Presidents and Attorneys -In -Fact, with the power and authority to sign, execute, acknowledge and deliver on its
behalf, as Surety: Any and all undertakings of suretyship and to affix thereto the corporate seal of the corporation. The President or any Vice- President, acting with
any Secretary or Assistant Secretary, shall also have the authority to remove and revoke the authority of any such appointee at any time."
does hereby make, constitute and appoint
Richard W. Dunphy or Bruce N. Telander or John P. Martinsen or R. W. Frank or
R. Scott Egginton or Donald R. Olson or Dennis J. Linder or Linda K. French or
Gary S. Soderberg, Minneapolis, Minnesota
its true and lawful Attorney(s) -In -Fact, to make, execute, seal and deliver for and on its behalf, as Surety:
Any and all undertakings of suretyship
And the execution of such bonds or undertakings in pursuance of these presents, shall be as binding upon said Company, as fully and amply, to all intents and
purposes, as if they had been duly executed and acknowledged by the regularly elected officers of the Company at its offices in Lincoln, Nebraska, in their own
persons.
The following Resolution was adopted at the Regular Meeting of the Board of Directors of the Universal Surety Company, held on July 23, 1981:
"RESOLVED. That the signatures of officers of the Company and the seal of the Company may be affixed by facsimile to any Power of Attorney executed in
accordance with Article V- Section 6 of the Company By -Laws; and that any such Power of Attorney bearing such facsimile signatures, including the facsimile
signature of a certifying Assistant Secretary and facsimile seal shall be valid and binding upon the Company with respect to any bond, undertaking or contract of
suretyship to which it is attached."
All authority hereby conferred shall remain in full force and effect until terminated by the Company.
IN WITNESS WHEREOF, UNIVERSAL SURETY COMPANY has caused these presents to be signed by its Vice- President and its corporate seal to be hereunto
affixed this 24th day of June , 1g 88
UNIVERSAL SURETY COMPANY yV AETy
�
0RP3VTE
Secretary B y
Vice-President
State of Nebraska
ss.
County of Lancaster)
On this 24th day of June 19 88 before me personally came Robert L. Privett to
me known, who being by me duly sworn, did depose and say that (s)he resides in the County of Lancaster, State of Nebraska; that (s)he is the Vice- President of the
UNIVERSAL SURETY COMPANY, the corporation described in and which executed the above instrument; that (s)he knows the seal of the said corporation; that the
seal affixed to the said instrument is such corporate seal; that it was so affixed by order of the Board of Directors of said corporation; that (s)he signed (his) (her)
name by like order; and that By -Law, Article V- Section 6, adopted by the Board of Directors of said Company, referred to in the preceding instrument, is now in force.
Gerald 0. liens
GENERAL NOTARIAL
i\`� BEAL
;(
STATE OF NEBRASKA
My Commission Expires 8 -22 -89 Notary Public r
l Thomas A. Tallman Assistant Secretary of UNIVERSAL SURETY COMPANY, do hereby certify that the above and
foregoing is a true and correct copy of a Power of Attorney executed by said UNIVERSAL SURETY COMPANY, which is still in full force and effect.
Signed and sealed at the City of Lincoln, Nebraska this 2nd, day of July 19 9 0 ,
cVPET
4 O 9
/ 41�� >� COBP E
As
SE 1 ,
stant Secretary „�e ^`�
ME AND ADDRESS OF AGENCY:
FOSTER
200 W. 8DWY. P.O. BOX 188
MONTICELLO. Mt
Immmo
ME AND ADDRESS OF lNSUREDv
SHINGOBEE BUILDERS INC,
P. 0. BOX 6
LORETTO, NN
55357
COMPANIES AFFORDING COVERAGE:
COMPANY K CIGNA QS 00
COMPANY Bf AUTO OWNERS INS CC)
COMPANY Q STATE FUND MUTUAL
COMPANY D:
COMPANY E:
LIMITS
OF LIABILITY
MP TYPE
POLICY NUMBER IN THOUSANDS
(000)
TTER OF INSURANCE EFFECTIVE/EXPIRATION DATE
A GENERAL LIABILITY
MFCD!6131167
X COMMERCIAL GENERAL
03/20/90 TO 03/20/91
LIABILITY
GENERAL AGGREGATE:
$ 1,000
CLAIMS MADE X OCCURRENCE
PRODUCTS CONP/OPS AGG:
$ 1000
X OWNERS & CONTRACTORS
PROTECTIVE
PERSONAL & ADVERTISING INJURY!
$
500
EACH OCCURRENCE:
$
50 1 01
FIRE DAMAGE (ANY I FIFW
$
51f)
MEDICAL EXPENSE (ANY I PERSON):
$
5
AUTOMOBILE LIABILITY
MFCD!6131167
X ANY AUTO
03/20/90 TO 03/20/91 CSL:
$
500
ALL OWNED AUTOS
Bl-
SCHEDULED AUTOS
EACH PERSON)
HIRED AUTOS
NON-OWNED AUTOS
BI:
GARAGE LIABILITY
EACH ACCIDENT)
PROPERTY DAMAGE:
,ORD CERTIFICATE OF INSURANCE PAGE 2
LIMITS OF LIABILITY
�Mp TYPE POLICY NUMBER IN TT- (000)
I 'i
T E/Ey. F
7TER OF INSURANCE EFFECT-V AT ION DATE E
11.4 EA. OCCU-IR'. /AGGREG4AT�-
B EXCESS LIABILITY
OTHER THAN
UMBRELLA FORM
WORKERS COMPENSATION
AND
EMPLOYERS' LIABILITY
862 6 8 ,-,f7, 8
000 $ 3 0 0
04/01/910 TO 04
EACH ACCIDENT:
DISEASE POLICY LIMIT:
DISEASE EACH EMPLOYEE- $
IN
SCRIPTION OF OPERATIONS/LTIOCATIONS/VEHICLES/SPECIAL ITEMS:
P I T C I Y - M I T F"' I ES T 1. 0 A C"! D E N'T" D I S F" AS E
Li 1�, j, 11
MBRELLA TWO 'IFOLICTE'S C)NE FIC)R SHT B fl� T D E 13, S5 @ 3 C) 0 -, 0 0
I I N C� 13 E - - 11 ' T - -7
8-322f AND Ot, FOR ' BERT FIENC�E, T 1,
NC
00 - T 1,1 Ir Q
'U "' 0 e) -ID -8 3 611 7 5
I I I V - -L
-- CANCELLATION
V.04
___ .® 0
CERTIFICATE HOLDER
Bonestroo Rosene
Anderlik & Associated Engineers
2335 W, Hwy 36
St. Paul, Mn 55113
(File # 3471)
City Of New Hope, Owners
4401 Xylon Ave. Norht
New Hope, Mn 55428
DATE ISDSUED- 071/iD'5/90
, ALA X jRii'ZED REP.i.!ES , -7ef7i-
amrsup. INSURANCE BINDER
ISSUE DATE (MM/DD/YY)
THIS BINDER |SA TEMPORARY INSURANCE CONTRACT,
SUBJECT TD THE CONDITIONS SHOWN ON THE REVERSE
0FTHIS FORK4_
_SIDE
iUCER
COMPANY BINDER NO.
�
Cigna Ins.
Foster-Franzen-Carlson
EXPIRATION
DATE E'^~^'E TIME DATE TIME
200 W. Broadway P0 BOX 188
mw x 12:01 AM
Monticello, MN 55362
' ` '- l_._' 1pM-L��- L-_LNOON
THIS BINDER IS ISSUED TO EXTEND COVERAGE IN THE ABOVE NAMED
$
COMPANY PER EXPIRING POLICY NO:
' 000«onE
DESC OF ~'~---'-'---P--Y (In Loc
--- --- — - ---- -
eBuilders
o �hi0g0bS9 Builders Inc. I
~
Risk - Completed
l. Contractors, City of New H0D8 owner
Value Form
le8trU0 R03eDe ADderllk & Assoc., Architects
OWNER'S & CONTRACTOR'S PROT.
) Shi0g0he8 Builders
EACH OCCURRENCE
� North Medina Street '
~~
`retO, Mn 55357
`--~~�-- -
TYPE OF INSURANCE
COVERAGEIFORMS
AMOUNT DEDUCTIBLE COINSUR.
IERTY CAUSES OF LOSS
BASIC BROAD X SPEC,
"All Risk" Completed Value Form
Perils
$8,300 $250
100%
:RAL LIABILITY
GENERAL AGGREGATE
$
COMMERCIAL GENERAL LIABILITY
PROD, — COMPIOPS AGGREGATE
$
CLAIMS MADE OCCUR
PERSONAL & ADVTSNG. INJURY
$
OWNER'S & CONTRACTOR'S PROT.
EACH OCCURRENCE
$
FIRE DAMAGE (Any one fire)
$
RETRO DATE FOR CLAIMS MADE:
MED. EXPENSE (Any one person)
$
ALL VEHICLES SCHEDULED VEHICLES
CSL $
LIABILI
NONIOwNED
mnso
GARAGE
PHYSICAL DAMAGE
COLLISION DED.
ALL VEHICLES SCHEDULED VEHICLE�
SS LIABILITY
UMBRELLA �° �
OTHER THAN UMBRELLA FORM nErno DATE FOR CLAIMS MADE
STATED AMOUN
OTHER
EACH AGGREGATE SELF-INSURED
OCCURRENCE RETENTION
WORKER'S COMPENSATIO
AND
EMPLOYER'S LIABILITY
STATUTORY
$ (EACH ACCIDENT)
$ (DISEASE-POLICY LIMIT)
)VeriDg: 1 story frame storage shed in the C0UrSe
Of construction situated at 8900 Research
Center Road, New Hope, Minn
ACV
MORTGAGEE ADDITIONAL INSURED
LOSS PAYEE
" m�LOAN en
CONDITIONS
ORD 75 (2185)
2�3E w
S`1
$$��@@yv� @@ ,rvsp�
g RECE IVEo fS
N �� ENV
IVALTH
SPECIFICATIONS
FOR THE CONSTRUCTION OF THE
••� 11 v �,.• .
• I •• V . ...
BERNARD HERMAN ARCHITECTS, INC.
4825 OLSON MEMORIAL HIGHWAY,SUITE 234
MINNEAPOLIS, MINNESOTA 55422
612/545 -1253
I Co IZO U 6"1 V k
I hereby certify that this plan,
specification, or report was prepared by
me or under my direct supervision and that
I am a duly Regist red Professional
Archi un a S of the State of
Mi ota .
NeT'ffar'd Herman, AL -
Date: October 31, 1989 Reg. No.: 7893
TABLE OF CONTENTS
TITLE SHEET & CERTIFICATE
TABLE [FCONTENTS
SCHEDULE 0RDRAWINGS
DIVISION A - BIDDING INFORMATION NO. OF PAGES
A-01 - Advertisement for Bids 2
A-02 - Instructions to Bidders G
A-03 - Bid Form - General Construction 3
B-01 - Agreement 1
B-02 - Bond Form 1
DIVISION C - CONTRACT CONDITIONS
C-01 - General Conditions 1
C-02 - Supplementary Conditions 8
0101
- Summary of the Work
l
0IO2
- Work Schedule
1
8110
- Description of Bide & Alternates
1
0113
- Construction Permits
1
8120
- Project Meetings
. 1
0130
- Submittals Required
1
0140
- Quality Control
1
0150
- Temporary Facilities
3
0160
- Materials and Equipment
1
0170
- Project Close-out
1
0180
- Technical Specification Format
2
0180
- Miscellaneous Requirements
3
DIVISION 02 - 8ITBW]RK
0201 - Subsurface Exploration
1
0211 - Demolition
2
0220 - Excavation and Backfill
4
0280 - Iauudnosplog
2
DIVISION 03 - CONCRETE
0320 - Concrete Reinforcement
2
0330 - Cast in Place Concrete
4
DIVISION 04 - MASONRY
0401 - Masonry Construction
5
DIVISION 05 - METALS
0518 - Structural Steel
2
0550 - Miscellaneous Metals
1
DIVISION 06 - CARPENTRY
0810 - Rough Carpentry
3
0819 - gom3 Trusses
4
Table of Contents-01
im: ywgreoe �aypikvg W
16MARIJ I k k It
0753 - Elastic Sheet Roofing & Membrane Flashings 3
0760 - Flashing and Sheet Metal 2
0761 - Preformed Metal Roofing, Fascia and Soffit System 3
0 - Unit Skylights 1
0790 - Sealants 2
1111VA1612 • 1 1: i i • • 1 i; ; ��, 1 11
0811 - Hollow Metal Doors & Frames (Welded Type.) 3
0840 - Aluminum Entrances and Storefronts
0852 - Aluminum Windows
0870 - Finish Hardware 3
0880 - Glass and Glazing 2
DIVISION 09 - FINISHES
0925 - Gypsum Drywall
0930 - Ceramic Tile
0970 - Special Flooring
0990 - Painting and Decorating
In &TA 155 BE
1016 - Metal Toilet Partitions 2
1020 - Louvers and Vents 1
1050 - Lookers and Basket Racks 1
1052 - Fire Protection Specialties 1
1080 - Toilet and Bath Accessories I
DIVISION 11 -
(Does not apply)
DIVISION 12 - FURNISHINGS
(Does not apply)
DIVISION 13 - SPECIAL CONSTRUCTION
(Does not apply)
DIVISION 14 - CONVEYING SYSTEMS
(Does not apply)
DIVISION 15 - MECHANICAL
15010 - General Provisions b
10505 - Basic Materials and Methods 5
15060 - Pipe and Pipe Fitting 3
15200 - Water Supply System 2
15450 - Plumbing Fixtures 1
15800 - Ventilation 3
Table of Contents-02
V i 0 D •
16010
- Electrical General Provisions
4
16100
- Electrical Basic Materials and Methods
6
16400
- Electrical Services and Distribution System
3
16500
- Lighting
2
16700
- Telephone Raceway System
2
16750
- Paging Backgroun
3
16800 -
Electrical Power /Heating Equipment
3
1 • • i •_ •i•►YY�I►Mi.�
• • I1:
S � i S•
Table of Contents -03
SCHEDULE OF DRAWINGS
F.-It y lwY
Al SITE PLAN
A2 BATHHOUSE FLOOR PLAN
A3 EQUIPMENT BUILDING FLOOR PLAN
A4 BATHHOUSE ELEVATIONSS
A5 EQUIPMENT BUILDING ELEVATIONS & SECTIONS
A6 BUILDING SECTIONS & INTERIOR ELEVATIONS
A7 BUILDING DETAILS
i:_
S1 FOOTING & FOUNDATION PLAN
S2 SECTIONS & DETAILS
S3 EQUIPMENT BUILDING FOOTING & FOUNDATION PLAN
MECHANICAL
M1 BATHHOUSE - MECHANICAL WORK
M2 BATHHOUSE - RISERS & DETAILS
M3 EQUIPMENT BUILDING - MECHANICAL WORK
W/I�iIY.•f
E1 BATHHOUSE - ELECTRICAL
E2 EQUIPMENT BUILDING - ELECTRICAL
A-01 E- E - BIDS
1.0 PROJECT: Swimming Pool Bathhouse & Equipment
Building, New Hope, Minnesota.
2.0 OWNER: City of New Hope
4401 Xylon Avenue North
New Hope, Minnesota 55428
3.0 BIDS DUE: Sealed Proposals will be recieved at the
indicated address until 2:00 PM on
Thursday, November 16, 1989. Shortly
thereafter the proposals will be opened
and publicly read aloud.
4.0 PLACE DUE: New Hope City Hall
Office of City Manager
4401 Xylon Avenue North
New Hope, Minnesota 55428
Attention: Mr. Dan Donahue
5.0 TYPE OF BIDDING, AND
CLASSES OF WORK: The Owner will accept proposals from
contractors for a single prime contract to
include:
General, Mechanical and Electrical
Construction.
6.0 AVAILABILITY OF
DOCUMENTS: Drawings and specifications are on file at
the office of Bernard Herman Architects,
Inc., New Hope City Hall, the St. Paul
Builders Exchange, the Minneapolis
Builders Exchange and F.W. Dodge Corp.
7.0 DOCUMENTS DEPOSIT: Two sets of documents will be available to
bidders. Documents may be obtained from
the architect upon a deposit of $35.00 per
set. The deposit is refundable upon
return of documents, in good condition, to
the architect's office within fifteen days
after bidding. Failure to submit a bid or
to return documents, as indicated, will
result in forfeiture of deposit.
8.0 DOCUMENTS PURCHASE: Persons requiring documents other than as
described above, may purchase them. There
will be no refunds on purchased items.
Each bidder is solely responsible for
selection of appropriate drawing sheets
and completeness of his bid. Each request
must be in writing or by phone and made to
the Architect.
A -01 -01
A- 01 1 11' 11 111 •• B IDS
8.0 DOCUMENTS PURCHASE: (continued)
Bidders from outside the Metropolitian
area can request plans and they will be
sent US Mail upon receipt of plan deposit
plus shipping and handling charges.
9.0 BID SECURITY: Each bid shall be accompanied by a
certified check or cashiers check made
payable to the City of New Hope, or a
corporate surety bond by a surety company
duly authorized to do business in the
State of Minnesota, in the sum of not less
than 5% of the total amount of the bid,
which is submitted as a bid security
conditioned upon the bidder's entering
into a contract with the City of New Hope
in accordance with the terms of the bid.
It is agreed that said bid security will
constitute liquidated damages, and not a
penalty, for the failure or refusal of the
successful bidder to enter into a contract,
in accordance with this proposal.
10.0 QUALIFICAITON STATEMENT: Each bidder will be required to submit
with the bid, a Contractor's Qualification
Statement, AIA Document A305.
11.0 PRIOR APPROVAL: This contract has a 3 day prior approval
clause for product substitutions.
END OF SECTION A -01
A- 019108
BHA10 -89
A -01 -02
A -02 - INSTRUCTIONS TO BIDDERS
1.0 DEFINITIONS:
1.1 All definitions set forth in the General Conditions of the Contract
for Construction, AIA Document A201, are applicable to these
Instructions to Bidders.
1.2 Bidding documents include Advertisement or Invitation to Bid,
Instructions to Bidders, and the proposed Contract Documents
including any Addenda issued prior to receipt of bids.
1.3 Addenda are written or graphic instruments issued prior to the
execution of the Contract which modify or interpret the bidding
documents, including Drawings and Specifications, by additions,
deletions, clarifications, or corrections. Addenda will become a
part of the Contract Documents when the Construction Contract is
executed.
2.0 BIDDERS REPRESENTATION:
2.1 Each bidder, by submitting his bid, represents that he has read and
understands the bidding documents and also any and all subcontractors
he intends to use has carefully and thoroughly reviewed the drawings,
specifications, and other construction contract documents and have
found them complete and free from ambiguities and sufficient for the
purpose intended. If this was not the case, they have followed the
procedure as outlined in 4.0 hereinafter.
2.2 Each bidder, by submitting his bid, represents that he has carefully
examined the site of the work and that from his own investigations he
has satisfied himself as to the nature and location of the work and
the character, quality, quantities of materials and difficulties to
be encountered, the kind and extend of equipment and other facilities
needed for the performance of the work, the general and local
conditions, and other items which may, in any way, affect the work or
its performance.
2.3 Each bidder, by submitting his bid, represents that he intends to
perform this Contract within the prescribed time period allocated for
this work.
3.0 QUALIFICATION OF BIDDERS:
3.1 The bidder and all workmen, employees and subcontractors - he intends
to use are skilled and experienced in the type of construction
represented by the construction contract documents bid upon.
3.2 Each bidder shall submit to the Owner a properly executed
Contractor's Qualification Statement, AIA Document A305, with the
Proposal Form.
A -02 -01
A -02 - INSTRUCTIONS TO BIDDERS
4.0 EXAMINATION OF BIDDING DOCUMENTS:
4.1 Each bidder shall examine the bidding documents carefully and, not
later than three days prior to the date for receipt of bids, shall
make written request to the Architect for interpretation or
correction of any ambiguity, inconsistency, or error therein which he
may discover. Any interpretation or correction will be issued as an
Addendum by the Architect. Only a written interpretation or
correction by Addendum shall be binding. Neither the bidder nor any
of his employees, agents, intended suppliers, or subcontractors shall
rely upon any verbal representations, allegedly authorized or
unauthorized from the owner, his employees, or agents including
architect, engineers, or consultants, in assembling the bid figure.
5.0 SLMSTITTMONS .
5.1 Each bidder represents that his bid is based upon the material and
equipment described in the bidding documents.
5.2 No substitution will be considered unless written request has been
submitted to the Architect for approval at least three days prior to
the date for receipt of bids unless otherwise indicated. Each such
request shall include a complete description of the proposed
substitution, the name of the material or equipment for which it is
to be substituted, drawings, cuts, performance and test data, and any
other data or information necessary for a complete evaluation. All
requests must have a stamped, self addressed return envelope, and be
made in duplicate. If the Architect approves any proposed
substitution, such approval may be set forth in the Addendum. Final
approval of substitute material will not occur until shop drawings
and/or samples have been submitted and approved by the Architect
after contract award.
6.0 BIDDING PROCEDtk .
6.1 All bids must be prepared on copies of the forms provided in the
specification and submitted in accordance with the Instructions to
Bidders.
6.2 A11 bids must be submitted in duplicate, and it shall be the
responsibility of each bidder to reproduce such forms for actual use.
The form bound with the specifications are reproduction masters and
any copy of the specifications from which said forms have been
removed shall be considered a mutilated copy. All proposals must be
legibly written in ink with all amounts given both in words and
figures where so indicated. Proposals shall be strictly in
accordance with the prescribed form. Any modifications thereof,
deviations or omissions therefrom may be considered sufficient cause
for rejection. Proposals carrying riders or qualifications to the
bid as submitted may be rejected as irregular. Where there is a
difference between the amounts shown in words and figures, the amount
in words shall prevail.
A -02 -02
A -02 - INSTRUCTIONS TO BIDDERS
6.0 BIDDING PROCEDURES: (continued)
6.3 A bid is invalid if it has not been deposited at the designated
location prior to the time and date for receipt of bids indicated in
the Advertisement or Invitation to Bid, or prior to any extension
thereof issued to the bidders.
6.4 Unless otherwise provided in any supplement to these Instructions to
the Bidders, no bidder shall modify, withdraw, or cancel his bid or
any part thereof for 30 days after the time designated for the
receipt of bids in the Advertisement or Invitation to Bid.
6.5 Prior to the receipt of bids, Addenda may be mailed or delivered to
each person or firm recorded by the Architect as having received the
bidding documents, and will be available for inspection wherever the
bidding documents are kept available for that purpose. Addenda
issued after receipt of bids will be mailed or delivered only to the
selected bidder. All addenda issued prior to the time of bidding
shall be covered in the proposal and will become a part of the
Contract. State the numbers of addenda included on the proposal
form.
6.6 Erasures or other changes in the bids must be explained or noted over
the signature of the bidder.
6.7 The bidder shall state in his proposal the number of calendar days
from the date of signing Contract that will be required to complete
the project.
6.8 The bidder shall refer to the Advertisement or Invitation to Bid
(Section A -01) for Bid Security requirements.
6.9 Each copy of the proposal must be signed in ink by the bidder.
6.10 Bids which are not signed by individuals making them should have
attached thereto a Power of Attorney evidencing authority to sign the
bid in the name of the person for whom it is signed.
6.11 Bids which are signed for a co- partnership should be signed by all of
the co- partners or by an Attorney -in -Fact. If signed by an
Attorney -in -Fact, there should be attached to the bid, a Power of
Attorney evidencing authority to sign the bid.
6.12 Bids which are signed for a corporation should have the correct
corporate name thereof signed in handwriting or in typewriting and
the signature of the President or other authorized officer of the
corporation should be manually printed or typewritten below the
corporate name following the word "By If such a
bid is manually signed by an official other than the President of the
Corporation, a certified copy of a resolution of the Board of
Directors evidencing authority of such official to sign the bid
should be attached to it.
A -02 -03
A -02 - INSTRUCTIONS TO BIDDERS
6.0 BIDDING pRocEDURES : ( continued )
6.13 If bids are signed by any other legal entity, authority of the person
signing for such legal entity should be attached to the bid.
6.14 Submit proposal and other required
envelope, plainly identified as:
Proposal for (Contract Work)
(Name of Project)
(Name of Owner)
(Address of Owner)
(Bidder's Name and Address)
data in an opaque, sealed
If submitted by mail, the proposal envelope shall be enclosed in
another envelope addressed for mailing. Submit proposals at the time
and place shown on the Advertisement or Invitation to Bid (Section
A -01).
7.0 F&JECTION OF BIDS:
7.1 The bidder acknowledges the right of the Owner to reject any or all
bids and to waive any informality or irregularity in any bid
received. In addition, the bidder recognizes the right of the Owner
to reject a bid if the bidder has failed to furnish any required bid
security, or to submit the data required by the bidding documents, or
if the bid is in any way incomplete or irregular.
8.0 SUBMISSION OF POST BID INFTION:
8.1 Upon request by the Architect, the selected bidder shall, within
seven days thereof, submit the following:
8.1.1 A statement of costs for each major item of work included in the
bid.
8.1.2 A designation of the work to be performed by the bidder with his own
forces.
8.1.3 A list of the subcontractors or other person or organizations
(including those who are to furnish materials or equipment
fabricated to a special design) proposed for such portions of the
work as may be designated, the names of the subcontractors proposed
for the principal portions of the work. The bidder will be required
to establish to the satisfaction of the architect and the owner, the
reliability and responsibility of the proposed subcontractors to
furnish and perform the work described in the sections of the
specifications pertaining to such proposed subcontractors'
respective trades. Prior to the award of the contract, the
architect will notify the bidder in writing if either the owner or
the architect, after due investigation, has a reasonable and
substantial objection to any person or organization on such list. If
the owner or architect has a reasonable and substantial objection to
any person or organization, the bidder may, at his option withdraw
his bid without forfeiture of bid security. If the bidder submits
an acceptable substitute with an increase in his bid price to cover
the difference in cost occasioned by such substitution, the Owner
may, at his discretion, accept the increased bid price or he may
disqualify the bidder. Subcontractors and other persons and
organizations proposed by the bidder and accepted by the owner and
A -02 -04
A-02 - INSTRUCTIONS T BIDDER
8.0 SLMMISSION OF POST- -BID DOOMATION: (continued)
8.1.3 (continued)
architect must be used on the work for which they were proposed and
accepted. The Subcontractors shall not be changed except with the
written approval of the owner and the architect.
9.0 CONTRACT AWARD:
9.1 For the purpose of preliminary consideration, the apparent "Low
Bidder" will be determined by the amount of the base bid. Award of
Contract may include full consideration of unit prices, alternates,
and completion time. The architect will issue notification of award
and draw up and approve the Owner /Contractor Agreement. The owner
reserves the right to make contract award to the firm that he finds
to his (the owner's) best advantage, including consideration of any
or all alternates.
10.0 PERFORMANCE BOND AND LABOR AND MATERIAL PAYMENT BOND:
10.1 The owner shall have the right, prior to the execution of the
contract, to require the bidder to furnish bonds covering the
faithful performance of the contract and the payment of all
obligations arising thereunder in such form and amount as the owner
may prescribe and with such sureties secured through the bidder's
usual sources as may be agreeable to the parties. If such bonds are
stipulated in the bidding documents, the premiums shall be paid by
the bidder; if required subsequent to submission of bids, the cost
shall be reimbursed by the owner. The bidder shall deliver the
required bonds to the owner not later than the date of execution of
the contract, or if the work is commenced prior thereto in response
to a letter of intent, the bidder shall, prior to commencement of
the work, submit evidence satisfactory to the owner that such bonds
will be issued.
10.2 The bidder shall require the Attorney -in -Fact who executed the
required bonds on behalf of the surety to affix thereto a certified
and current copy of his Power of Attorney indicating the monetary
limit of such power.
EM OF SECTION A -02
A- 029108
BHA10 -89
A -02 -05
A -03 - BID FORM - PROPOSAL FOR CONTRACT WORK
1.0 The attached Bid Form, available from the Owner or Architect, shall
be used for submittal of all proposals for contract work. Each
bidder shall complete the form in its entirety and shall submit all
information required. In submitting the bid, it is understood that
the City of New Hope reserves the right to reject any and all bids.
It is further agreed that the bid may not be withdrawn for a period
of thirty days after date of filing same.
1.1 As a requirement of the.bid, a bid bond or corporate surety bond
shall be submitted with the proposal.
END OF SECTION A-03
A- 039018
BHA10 -89
A -03 -01
New Hope City Hall
4401 Xylon Avenue North
New Hope, Minnesota
Gentlemen:
10 -31 -89
(1) The undersigned, being familiar with the existing and local
conditions affecting the cost of the work and with the Contract
Documents, including Instructions to Bidders, Proposal Form, General
and Supplemental Conditions, .Drawings and Specifications and Addenda
numbers as prepared by Bernard Herman
Architects, Inc., and in accordance with the provisions thereof,
hereby proposes to furnish all labor, materials, equipment,
insurance, taxes, transporation and means necessary for and
incidental to:
Complete construction including General, Mechanical and Electrical
Construction.
Base bid is for the sum of:
Dollars ($ )
Consisting of Name of Subcontractor
($ ) for General Construction
($ ) for Mechanical Construction
($ ) for Electrical Construction
(2) In submitting this bid, it is understood that the right is reserved
by City of New Hope to reject any and all bids and that it is agreed
that this bid may not be withdrawn for a period of thirty (30) days
after date of bid opening.
(3) Each bid shall be accompanied by a certified check or cashiers check,
made payable to City of New Hope or a corporate surety bond of a
surety company duly authorized to do business in the State of
Minnesota, in the sum of not less than five (5) percent of the total
amount of the bid, which is submitted as a bid security conditioned
upon the bidder's entering into a contract with City of New Hope in
accordance with terms of the bid. It is agreed that said bid
security of the successful bidder will constitute liquidated damages,
and not a penalty, for the failure of the bidder to enter into
contract in accordance with this proposal.
(4) Each bid shall be accompaned by a properly executed Contractor's
Qualification Statement, AIA Document A305.
(5) All addenda shall become part of the bid and the work, and shall be
submitted with the bid. The Contractor shall insert the addenda
numbers in the space provided where indicated on the first page of
the Proposal.
(6) A bid shall be rejected if it contains any alteration or erasure,
unless alteration or erasure is corrected as herein provided. An
alteration or erasure may be crossed out and the correction thereof
printed in ink or typewritten adjacent thereto and initialed in ink
by the person signing the bid.
(7) We propose to complete the work in accordance with the Contract
Documents within calendar days from execution of the
Contract.
(8) If a corporation, what is the state of incorporation:
(9) If a partnership, state full name of all co- partners:
Official Address
Date
Firm Name
By
Title
By;
Title
1 i �I' i• ' � i' � !!' 91�i Iii
1.0 The AIA Standard Form Documents will be used as the agreement form
between Owner and Contractor. The following form is the one to be
used.
AIA A101 - StiDul.ated Sum
Copies of the above forms are on file at the office of the architect and
may be reviewed during normal working hours, Monday through Friday, or as
included following this Section.
END OF SECTION B-01
B- 019108
BHA10 -89
B -01 -01
1.0 PE F OINANCE BOND
1.1 Performance Bond and a Labor and Material payment Bond will be
required in the amount of 100 percent of the Contract Sum, executed
on AIA Document A311 Performance Bond and Labor and Material payment
Bond. These bonds are not required as a condition of bidding but
will be required as a condition of the contract award.
� d1 � • : 1
: ms
� .•
B -02 -01
1.0 A.I.A. Form:
The "General Conditions of the Contract for Construction," American
Institute of Architects Document A201, 1976 Edition, hereinafter
referred to as the "A.I.A. General Conditions," are hereby made a
part of this specification whether or not it is bound herein. The
AIA General Conditions may be examined at the office of the
Architect. The AIA General Conditions including Supplementary
Conditions (Section C-02) shall become a part of this contract and
shall apply to all contractors and subcontractors.
2.0 TABLE OF ARTICLES:
For the convenience of the contractors, the "Table of Articles" of
the AIA General Conditions is listed below:
1. Contract Documents
2. Architect
3. Owner
4. Contractor
5. Subcontractors
6. Work by Owner or Separate Contractors
7. Miscellaneous Provisions
8. Time
9. Payments and Completion
10. Protection of Persons and Property
11. Insurance
12. Change in the Work
13. Uncovering and Correction of Work
14. Termination of the Contract
C-019108
BHAIO-89
C-01-01
C -02 - SUPPLEMENTARY CONDITIONS
GENERAL
. The Articles contained in the Supplementary Conditions of the
Contract may amend, modify, supersede, void or supplement the
Articles of the General Conditions of the Contract for
Construction, AIA Document A201, 1976 Edition, and when
applicable, and if used, AIA Document A201 /SC (latest edition).
The Supplementary conditions shall take precedence over the
provisions of the General Conditions. Where any part of an
article of General Conditions is not so amended, modified,
superseded or voided by a provision of the Supplementary
Conditions, such part shall remain in effect.
ARTICLE 1. CONTRACT DOCUMENTS:
1.1.1 Amend as follows:
The Contract Documents include bidding documents; including the
advertisement for bid, instructions to bidders, samples of forms,
the Contractor's bids, and any addenda thereto.
1.2.5 Add the following:
The general character and scope of the Work is shown by the
drawings. Where a portion of the Work is fully drawn and the
remainder is merely indicated, the portion fully drawn shall apply
to all similar parts of the Work.
1.2.6 Add the following:
Where specifications are abbreviated type, they indicate complete
sentences in the same manner as when a note occurs in the
drawings. Omissions of words such as "the Contract shall" and "as
shown on the drawings" are intentional. The words "shall" or
"shall be" are to be supplied by inference. The term "provide"
shall mean "furnish and install in place ".
1.2.7 Add the following:
Where a number is listed in the specifications (as for gauges,
weights, temperatures, amount of time, etc.) the number shall be
interpreted as that or better.
ARTICLE 2. ARCHITECT`
2.1.2 Add the following:
"The architect shall assist the owner in preparation of bidding
information, bid forms, conditions of the contract, the agreement
between owner and the contractor, and the procedure of determining
insurance requirements. The owner, after review, shall have final
approval for these items."
2.2.4 Add the following:
The architect will not be responsible for the acts or omissions of
the owner.
C -02 -01
• • i� �• •
ARTICLE 2. ARCHITECT: (continued)
2.2.14 Change to read:
"The architect will review or take other appropriate action upon
contractor's submittals such as shop drawings, product data and
samples, but only for conformance with the design concept of the
work and with the information given in the contract documents.
Such action shall be taken with reasonable promptness so as to
cause no delay. The architect's review of a specific item shall
not indicate approval of an assembly of which the item is a
component.
2.2.16 Change to read:
"The architect, through field observations, will determine the
dates of substantial completion and final completion, will receive
and forward to the owner for the owner's review written warranties
and related documents required by the contract and assembled by
the contractor and will issue a final certificate for payment upon
compliance with the requirements of paragraph 9.9.
2.2.20 Add the following:
Whenever an article or material is defined by describing a
proprietary product, or by using the name of a manufacturer, the
term, "or equal ", if not inserted, shall be understood as
establishing minimum standards as to the type, function, standard
of design, durability, efficiency and quality desired and shall
not be construed so as to exclude other manufacturers' products or
comparable quality, design and efficiency.
Makes and models of items which the Contractor alleges to be equal
to the makes and models of items named in the specification, shall
be subject to written approval by the Architect and /or Engineer.
The use of substitute items will not be permitted without the
approval of the State and the Architect and /or Engineer. All
requests for substitution shall be in writing and approved by the
Architect and /or Engineer. The Contractor shall not be relieved
from the responsibility of furnishing articles or materials equal
in quality, design, and efficiency to those specified because of
the approval of such substitute items by the Architect and /or
Engineer. The Architects and /or Engineers approval or rejection
of a proposed substitute may be based on any of the previous
considerations, and his decision, which may or may not express
reasons for rejection, shall be final. Requests for substitutions
shall originate with and be submitted by the Contractor, not a
subcontractor. The material or equipment shall be sufficiently
described to enable the Architect and /or Engineer to easily
identify the salient features.
ARTICLE 3. OWNER:
3.2.2 Amend this paragraph to delete the requirement that the City of
New Hope (Owner) provide a legal description of the site.
C -02 -02
C-02 - SUPPLEMENTARY CONDITIONS
rft M
4.2.2 Add the following:
On all drawings, figures take precedence over measurements by
scale, and any scaling is done at the Contractor's own risk. The
Architect shall decide on any questions that may arise regarding
the meaning and intent of the Drawings and Specifications. Should
any drawings or figures have been omitted which are necessary to a
clear understanding of the Work or should any error appear in
either, or discrepancies be found between the Drawings and
Specifications, it shall be the duty of the Contractor to notify
the Architect of such omissions, errors, or discrepancies, and in
no case proceed in uncertainity. Should any mistakes arise in
consequence of such neglect on the part of the Contractor to
notify the Architect, he must correct them at his own expense.
Before ordering any material or doing any work, the Contractor
shall verify all measurements of the Project for his particular
class of Work and shall be responsible for the correctness of
same. No extra charge or compensation will be allowed to the
Contractor on account of differences between actual dimensions and
the measurements shown by the Drawings. Any noticeable
discrepancy in the respect shall be reported to the Architect
immediately for his consideration and decision. All the component
part of the Work shall be carefully checked and laid out in order
that the structure as a whole shall conform to the intent of the
Drawings.
Failure to examine the project building and the site and the
contract drawings and to become familiar with the existing
conditions shall not constitute cause for complaint or claim for
extra payment. Accept project site as it exists. Site will be
available to Contractor upon receipt of Architect/Engineer's
written notice to proceed, unless otherwise indicated in these
documents. Care, custody, and control of the site or premises is
vested in Contractor during the term of operations under the
Contract, subject to the rights of the Owner, unless noted
otherwise.
Each Contractor shall give full protection to the buildings and
occupants. He shall replace or repair, at his own expense all
damage to existing buildings, sidewalks, curbs, drives, lawns,
plants, trees and shrubbery arising from his construction work,
from whatever cause.
4.4.3 Add the following:
Workmanship and Materials.
A. No trade shall commence Work until conditions are right or
conditions are right for carrying out the work properly and
surfaces to be covered are suitable.
B. Manufacturer's printed instructions covering details of
installation shall be followed where not in conflict with
these specifications. If there is a conflict, notify the
architect and obtain his approval before proceeding.
C. Completed work shall be left plumb, level, true to line or
I plane, anchored securely in place free from damage.
C-02-03
i 2 - SUPPLEMENTARY CONDITI.C
ARTICLE 4. CONTRACICR: (continued)
4.4.3 Workmanship & Materials (continued)
D. Unless otherwise called for, all pieces of material shall be a
stock size as is in conformity with standard good practice of
the trade.
E. Except where in conflict with these specifications, current
manufacturer's printed specifications of herein specified
proprietary products are made part of these specifications.
4.7.1 Add the following:
Except in those municipalities which provide State- approved
electrical inspection, all installation of electrical wiring shall
be inspected by the State Board of Electricity. Allowance shall
be made in the bid and contract for the cost of such inspection.
Fees for such inspection will be charged in accordance with the
rules and regulations of the State Board of Electricity. Evidence
of payment of fees shall be provided by the Contractor with his
Request for Payment.
4.12.6 Change to read:
"The contractor shall not be relieved of responsibility for any
deviation from the requirements of the contract documents by the
architect's review of shop drawings, product data or samples under
subparagraph 2.2.14 unless the contractor has specifically
informed the architect in writing of such deviation at the time of
submission and the architect has given approval to the specific
deviation. The contractor shall not be relieved from
responsibility for errors or omissions in the shop drawings,
product data or samples by the architect's review thereof."
4.12.9 Add the following:
Submit to the architect shop drawings; including fabrication,
erection, layout and setting drawings and other such drawings as
may be required under various sections of the specifications,
until final approval is obtained. The Contractor is responsible
for obtaining and distributing required prints of shop drawings to
his subcontractors. Material drawings shall be made from
transparencies which carry the architect's appropriate stamp.
Mechanical and Electrical fixture brochures and catalog cuts shall
be submitted to the engineers in six copies and shall show
dimensions, performance characteristics and capacities, wiring
diagrams and controls, schedules, and other pertinent information
as required. Where printed materials describe more than one
product or model, clearly identify which is to be furnished.
4.12.10 Add the following:
Manufacturer's Instructions: Where any item of Work is required
by specifications to be furnished, installed, or performed in
accordance with a specified product manufacturer's instructions,
contractor shall procure and distribute the necessary copies of
such instructions to all concerned parties.
C -02 -04
C-02 S - 1 11PLRENTARY CONDITTO
ARTICLE 4. CONTRACTOR: (continued)
4.14.1 Delete this paragraph in its entirety and substitute the
following:
Contractor shall do all cutting, fitting or patching of his work
that may be required to make its several parts come together
properly and fit it to receive or be received by work of
Subcontractors, shown upon, or reasonably implied by drawings and
specifications for the completed structure, and he shall make good
after them as Architect /Engineer may direct. Any cost caused by
defective or ill -timed work shall be borne by party responsible
therefore. Contractor shall not endanger any work by cutting,
excavating, or otherwise altering the work and shall not. cut or
alter the work of any other Contractor. Contractor will leave all
necessary holes in walls, chases, etc., required for any of the
mechanical work or electrical work, provided these are accurately
located before the execution of the work by the Mechanical or
Electrical Subcontractors. Cutting-required by Subcontractors and
not shown on the general plans shall be done by General
Contractor. General Contractor shall pay all costs for such work.
Any patching and repal_ring of the finished work made necessary for
cutting in this Contract will be done by the General Contractor.
Any injury to the structural members of the building caused by the
Contractor or by those in his employ shall be made good at the
Contractor's expense.
No supplement.
ARTICLE 6. W ORK BY OWNER OR BY SEPARATE CONTRACTORS
No supplement.
ARTICLE 7. MISCELLANEOUS PROVISIONS:
No supplement.
ARTICLE 8. TIME
8.1.3 Change to read'
The date of substantial completion of the work of designated
portion thereof is the date when construction is sufficiently
complete, in accordance with the contract documents, so that the
owner can occupy or utilize the work or designated portion thereof
for the use for which it is intended. Minor corrective work and
the replacement of defective work or materials, and the adjustment
of control apparatus will not delay the determination that the
contract is substantially complete.
8.3.5 Add the following:
The following will not be considered justification for extension
of time unless due to one of the causes stated within this
Article.
A. Delay caused by subcontractors or suppliers, except if the
supplier goes out of business and another supplier cannot be
found in time to meet schedule.
B. Shortage of workmen.
C -02 -05
SUPPLEMENTARY-CONDITIONS
ARTICLE 9. PAYMENTS AND COMPLETION: (continued)
9.3.4 Add: Progress payments shall be made on or about the 10th day of
each month upon application, in the amount of 90% of the work
completed and materials described under 9.3.2 on the first $200
thousand of a contract and 95% of the remaining amount of the
contract.
M-
No supplement.
ARTICLE 11. INSURANCE:
11.1.2 Replace the text with: This insurance shall be written for not
less than the following limits of liability:
1. Contractor's Comprehensive General & Liability Insurance:
a. Bodily injury:
$250 thousand - each occurrence
$500 thousand - aggregate
b. Property Damage (broad form):
$100 thousand - each occurrence
$200 thousand - aggregate
2. Contractor's Contingent Liability:
a. Bodily injury:
$250 thousand - each occurrence
$500 thousand - aggregate
b. Property Damage:
$100 thousand - each occurrence
$200 thousand - aggregate
3. Automobile Insurance, covering all owned, non-owned, and hired
vehicles:
a. Bodily injury:
$250 thousand
$500 thousand
- each occurrence
- aggregate
b. Property Damage:
$100 thousand - each occurrence
4. Workmen's Compensation: Statutory
5. Contractor's Public Liability (broad form) to cover provisions
of 4.18:
a. Bodily injury:
$250 thousand - each occurrence
$500 thousand - aggregate
b. Property Damage:
$100 thousand - each occurrence
$200 thousand - aggregate
C-02-06
C-02 - CONDITIONS
ARTICLE 11. INSURANCE: (continued)
11. 1. 2 (continued)
6. Completed operations insurance:
a. Bodily injury:
$250 thousand - each occurrence
$500 thousand - each occurrence
b. Property Damage
$100 thousand - each occurrence
$200 thousand - aggregate
7. Umbrella Policy to cover excess liability:
a. Bodily injury and property damage combined:
$1 million
Approval of the Insurance by the Owner shall not relieve or
decrease the liability of the Contractor hereunder. It is to be
understood that the Owner and the Architect do not in any way
represent that the insurance or the limits of insurance specified
in these articles are sufficient or adequate to protect the
Contractor's interests or liabilities, but are merely minimums.
Comprehensive general and automobile liability policy form or
policies shall be written by the same insurer who shall be a
company licensed in the state where the same work is located at
the time the policy is issued. XCU property damage exclusions
shall be eliminated in all oases where made applicable by the
liability insurance classifications. Completed operation
insurance shall remain in effect for not less than one (1) year
after substantial completion of the project.
11.1.4 Change or read:
Prior to award, the Contractor shall file a complete "package" of
two Certificates of Insurance signed by the Insurer or two
Certified Copies of all insurance policies with Architect, who
will then file one of the copy packages with owner. Each
Certificate of Insurance shall be accompanied by a notarized Power
of Attorney evidencing the authority of the agent to act on behalf
of the company. None of the insurance required hereunder shall be
cancelled, changed or allowed to lapse until the contract has been
completed and the work accepted. In the event of cancellation,
change or expiration, thirty (30) days' notice shall be given the
Owner and all other insured parties by the insurance company or
companies validated by an authorized representative of the
insurer. Each policy of insurance shall contain the clause, "In
the event of cancellation or expiration of the policy or of any
change in the policy of any nature, thirty (30) days' advance
written notice will be sent to the Owner and the Architect". No
work under the contract will be started until all insurance
certificates or policies have been filed and approved, nor shall
any progress payment become due and payable until such certificate
or policies have been filed.
WMAIM
C -02 - supPLIIMENTARY CONDITIONS
ARTICLE 11. INSURANCE: (continued)
11.3 Property Insurance
Clauses 11.3.1, 11.3.4 and 11.3.5 are deleted, and the following
clauses substituted and added to Article 11, Part 3:
11.3.1 The Contractor shall purchase and maintain property insurance upon
the entire work at the site to the full insurance value thereof.
This insurance shall include the interests of the Owner, the
Contractor, subcontractors and sub - subcontractors in the work and
shall insure against the perils of Fire, Extended Coverage,
Vandalism and Malicious Mischief. This insurance shall be written
on a Builders' Risk Completed Value form.
11.3.4 The Contractor shall file two Certificates of Insurance signed by
the insurer or two Certified Copies of all policies with the
Architect before an exposure to loss may occur.
11.3.5 The Contractor may, at his option, include other special insurance
in the property insurance policy. The cost of such other special
insurance shall be borne by the Contractor.
11.3.9 Add the following:
In the event of loss, deductibles, if any, shall be paid by the
Contractor.
ARTICLE 12. CHANGES IN THE WORK:
12.1.6 Add the following:
The owner or architects are not responsible to give Notice of
Change Orders to the Surety (if any).
ARTICLE 13. UNCOVERING AND CORRECTION OF WORK:
13.2.1 Add the following:
"The corrective work shall conform in all aspects with the
original intent of the contract documents."
13.2.2 Add the following:
Guarantess, special guarantees and any other guarantees required
by the Contract Documents shall not exclude or otherwise limit the
Owner's possible remedies at law and shall not be construed as a
waiver by the Owner of any other remedy.
ARTICLE 14. TERMINATION OF THE CONTRACT:
No supplement.
END OF SECTION C-02
i • 1
C 1 .
1 is
0101 - SUMMARY OF WORK
1.0 LOCATION OF SITE:
1.1 The site is located at Civic Center Park, 44th and Xylon Avenue
North, New Hope, Minnesota.
2.0 GENERAL DESCRIPTION OF TTIE WORK:
2.1 The following is a general description of the work required for the
building construction and site work for the project named on the
Title Page, hereinafter specified and shown on the drawings:
Construct two buildings consisting of a Swimming Pool Bathhouse and a
Pool Equipment/Storage Building. Both buildings shall be slab on
grade with brick and block backup walls, wood trusses and metal roof.
Existing W Heaters (2), soap dispensers (8), and drinking fountains
(2) from the existing bathhouse shall be removed and re-installed in
the new building.
2.2 Unless otherwise specified, the contractor shall supply, labor
transportation, materials, apparatus, fuel, energy, light,
scaffolding, and tools necessary for the entire proper and final
completion of his work; and shall install, maintain, and remove all
equipment of the construction and other utensils or items, and be
responsible for the safe, proper, and lawful construction,
maintenance, and use of same; and shall construct in the best and
most workmanlike manner, a complete project including everything
properly incidental thereto as shown on the plans, stated in
specifications or reasonably implied therefrom, all in accordance
with the Contract Documents.
2.3 The total work of this Bid Package is to include the following
divisons of work:
A. General Construction
B. Electrical Construction
C. Mechanical Construction
3.0 CONTRACT LTNITS:
3.1 The contract limits for this project are shown on the Site Plan and
will be verified by the Owner prior to start of construction.
IND OF SECTION 0101
0101-01
0102 - WORK SCHEDULE
1.0 TIME OF CCMPLMON:
1.1 The contractor shall commence work within the shortest time possible
after receipt of executed copy of contract and notification to
proceed. A letter of intent will be issued within 5 days of receipt
of bids to accelerate the process to begin construction. The
Bathhouse must be completed and operational by May 1, 1990.
2.0 PROJECT SCHEDULE FOR TIM OF COMPLMON:
2.1 After award of contract, the Owner and Contractor may establish a
formal schedule for completion of the work based upon the bidders,
proposed number of days to complete the work.
3.0 SEQUENCING OF WORK:
3.1 The contractors shall sequence their work as required to accommodate
reasonable convenience of the owner.
3.2 Temporary dust barriers, approved by the architect, shall be provided
when required to carry out the work of the contract documents or by
the architect.
3.3 In all cases, security of the building and site must be maiitained
during all of construction.
0=1 :
IM6
0102-01
0110 - DESCRIFrION OF BIDS AND ALTERNATES
1 • • i Iiti
1.1 The cost of the project shall be for all work as indicated in the
specifications and /or shown and detailed on the drawings for a single
Prime Contract including:
A. General Construction
B. Mechanical Construction
C. Electrical Construction
2.0 ALTERNATE PRICES:
2.1 The bid proposal form contains the alternates listed below. The
contractor, in submitting a proposal for an alternate, shall include
all costs for labor, materials, equipment, services, overhead and
profit for each item as described in this section.
2.2 Alternates may be accepted at the discretion of the Owner.
i • IS
R.M.1 :•
0110 -01
0113 - CONSTRUCTION M MLTS
1.0 BUILDING CONSTRUCTION PERMIT
1.1 The General Contractor shall arrange and pay for the general
construction permit for the project, if required.
1.2 The cost of the permit shall be included in the contractor's bid
amount.
2.0 ADDITIONAL PO MM:
2.1 All other prime contractors and individual subcontractors shall pay
for any and all additional permits, licenses, inspections and fees
required for the proper execution and completion of his particular
portion of the work, including any sewer access charges and /or water
access charges.
END OF SECTION 0113
01138019
BHA10 -89
0113 -01
0120 - PROJECT MEETINGS
1.0 REVIEW MEETDIGS:
1.1 The architect may elect to hold progress meetings, at his discretion,
with this contractor and/or other contractors to review the progress
and status of the project. Each contractor shall designate personnel
completely familiar and responsible for the project to attend these
meetings.
FIN NIARTWITPIC
0120-01
r �Dll � I
1.0 GENERAL:
1.1 The following list of submittals has been prepared for the
convenience of the Contractor and may not be a complete listing. The
Owner and/or Architect will provide or indicate the appropriate forms
that shall be used for specific submittals.
2. PRIOR 110 AWARD:
2.1 List of subcontractors and/or suppliers and manufacturers 4 copies
2.2 Contractor's Qualification Statement 1 copy
4XIM WN Co IL00KO-41 WN Vol 14 V
3.1 Performance/Labor and Material Bond 4 copies
3.2 Certificate of Insurance 4 copies
3.3 Additional submittals as may be required by the contract
documents or requested by the Owner or Architect 4 copies
4.0 WITHIN SEVEN DAYS AFTER CONTRACT EXECUTION:
4.1 Detailed cost breakdown on application for payment form,
breakdown to be in accordance with divisions of
specifications and shall separate labor and material 4 copies
4.2 Name of project superintendent 4 copies
4.3 Additional submittals as may be required by the contract
documents or requested by the Owner or Architect 4 copies
1 . V"(91AMECAIN011116
5.1
Application and Certificate for Payment 4
copies
5.2
Partial lien waivers if requested
4
copies
6.0
AS WCRK PROGRESSES:
Contractor's
Affidavit of Payment of Debts & Claims
6.1
Shop drawings and samples:
One reproducible transparency
Contractor's
Affidavit of Release of Liens
and 2 prints for drawings
and
7.5
Lien Waivers from all subcontractors and materials
6 copies of other submittals
6.2
Instructions
2
copies
6.3
Manuals
2
copies
6.4
Guarantees
2
copies
6.5
Test Results
2
copies
6.6
Additional submittals as may be required
by the contract
documents.
7.1
Application and Certificate for Payment
4 copies
7.2
Consent of
Surety Company to Final Payment
4
copies
7.3
Contractor's
Affidavit of Payment of Debts & Claims
4
copies
7.4
Contractor's
Affidavit of Release of Liens
4
copies
7.5
Lien Waivers from all subcontractors and materials
suppliers,
"Standard Form"
4
copies
7.6
Additional
submittals as may be required by the Owner or
Architect.
V It
NAM
0130-01
0140 - QUALITY CONTROL
1.0 MANUFACTURER'S DIREMONS .
1.1 Apply, install, connect, and erect manufactured items or materials
according to the recommendations of the manufacturer when such
recommendations are not in conflict with the contract documents.
Where they are in conflict, the contractor shall notify the
architect. If the contractor proceeds without notifying the
architect, then the contractor shall assume total responsibility for
the installation.
1.2 Furnish to the architect, on request, copies of manufacturer's
recommendations. Secure approval of recommendations before
proceeding with work.
1.3 Keep at the site not less than one copy, in good condition, of
manufacturer's recommendations, or directions, pertaining to work at
the site. Inform involved personnel of requirements and availability
of manufacturer's recommendations.
2.0 TESTING:
2.1 The contractor shall retain and pay the expense of a testing
laboratory, with prior approval by the architect, to perform
specified testing.
2.2 The contractor shall, at his expense, furnish samples for such tests
and when required to, cost of transportation to the testing
laboratory.
2.3 Materials shall be tested as specified and in the quantity specified.
2.4 When a number of tests are specified, the architect shall select the
locations.
2.5 When test results are inconclusive or indicate non - compliance with
standards, additional testing will be provided, at no cost to the
owner, until compliance is obtained.
2.6 Copies of all tests shall be sent to the contractor, applicable
subcontractor, and architect by the testing agency.
2.7 The architect may, at times, request additional testing.
2.8 Inspection and testing shall in no way relieve the contractor or
supplier from responsibility in furnishing materials and workmanship
in accordance with the plans and specifications.
3.0 REJECTED MATERIALS'
3..1 Rejected materials tested to non - compliance or of obvious
non - compliance with the specifications as judged by the architect
shall be immediately removed and the proper or correct materials
installed.
END OF SECTION 0140
01409108
BHA10 -89
0140 -01
0150 - TEMPORARY FACILITIES
1.0 TEMPORARY OFFICES:
1.1 The general contractor shall provide a temporary office on the site.
The office shall contain a desk or table of sufficient size to hold
the construction drawings and shall be properly heated and lighted.
1.2 When the building is substantially enclosed, these offices may be
moved indoors, upon approval of architect to designated rooms.
2.0 TEMPORARY TELEPHONES:
2.1 The general contractor shall install a temporary phone in his
office. This phone shall b * e for the use of the architect, engineers,
and owner for calls relative to this project. Other contractors may
use this telephone but shall reimburse the general contractor for
the cost of their calls.
3.0 CONSTMJCTION WATER:
3.1 Water for construction purposes is available at the existing fire
station building or City Hall which shall be furnished by the Owner
at no cost to the Contractor. Another option is to connect to the
fire hydrant west of the Concessions Building which shall include a
cold weather box as part of the connection. Connections, piping or
hoses, as may be required, shall be the responsiblity of the
Contractor. Location of connection shall be as directed by the City
of New Hope.
4.0 DRINKING WATER:
4.1 Drinking water shall be provided by the General Contractor, in
containers for the use of his employees and subcontractors.
5.0 TEMPORARY LIGIT AND POWER:
5.1 Electrical power is available at the site within the Concession
Building and shall be furnished by the Owner at no cost to the
Contractor. Temporary lighting systems if required shall be
furnished and installed by the Contractor.
6.0 TEMPORARY SANITARY FACILITIES:
6.1 Temporary toilet facilities at the site shall be the responsibility
of the Contractor.
7.0 TEMPORARY HEAT AND ENCLOSURES:
7.1 The General Contractor shall provide temporary heat as necessary to
complete the work of the contract. Costs for energy use shall be
paid by the General Contractor.
8.0 TRASH REMOVAL AND CLEANING•
8.1 The general contractor shall be responsible for providing trash
receptacles. Each contractor is responsible for collecting and
depositing his debris in the collection facilities.
8.2 The general contractor shall be responsible for the removal of
debris from the jobsite at regular intervals. Trash and debris
should not be allowed to accumulate.
0150-01
0150 - TEMPORARY FACILITIES
8.0 TRASH IaMVAL AND CLEANING: (continued)
8.3 All contractors and subcontractors shall collect and remove from the
jobsite their own liquid waste requiring special handling for
disposal.
8.4 All contractors and subcontractors shall keep all work areas,
passageways, and stairs in and around the project free from debris
resulting from his work at all times.
8.5 All contractors and subcontractors shall protect equipment and
finishes at the jobsite from damages resulting from work under their
control. All cleaning required as a result of failure to protect
equipment and finishes, and for removal of protective covers, shall
be the responsibility of the contractors and subcontractors at
fault.
9.0 FIRE PROTEMON:
9.1 The general contractor shall provide general temporary fire
protection. Permanently installed fire protection equipment may be
used for temporary fire protection during construction.
10.0 ACCESS:
10.1 One specific vehicle access or delivery location from the street
onto site will be designated by the City of New Hope, for sole
construction use by the Contractor.
11.0 SHEDS AND STORAGE:
11.1 Each contractor shall provide suitable and sufficient enclosed and
covered spaces, with raised floors, to protect his own materials and
equipment subject to damage by weather or construction work, and
provide sheds to suitably store materials and equipment needing only
limited protection.
11.2 The general contractor shall allocate and designate storage areas
and working spaces for various trades.
12.0 FENCING AND SECURITY
12.1 The general contractor shall be responsible for overall security
including buildings and pool area. Construction area shall be
secured by the Contractor with an orange wire mesh fence, minimum of
36" high, at the end of each day.
12.2 The responsible contractor shall cover trenches and holes when not
in use and erect barriers at changes in plane steeper than 45
degrees and more than three feet in height, and provide and maintain
flashing warning lights and signs as necessary to prevent damage or
injury. Keep warning lights operational from dusk to dawn.
12.3 Protect window and door openings with boarding by method approved by
architect until the addition is enclosed and weather tight and do
not remove until new windows or adequate temporary enclosures at
window openings and outside doors can be secured.
0150 -02
0150 - TEMPORARY FACILITIES
12.0 FENCING AND SECURITY: (continued)
12.4 Debris and dust shall not be permitted to accumulate and must be
removed from site at frequent intervals.
12.5 Provide dust barriers to avoid spread of debris and dust into
existing spaces occupied by owner when remodeling of existing
building or other work of this project is being done.
13.0 SHORING, SHOUING, BRACING, ETC.:
13.1 All temporary shoring, sheeting, and /or bracing required for the
removal of existing work or for the installation of new work shall
be included in this contract and must be done in accordance with the
direction and to the entire satisfaction of the architect, but each
contractor must assume all responsibility for this work and make
good any damage caused by improper supports or failure of shoring in
any respect. When the permanent supports are completed, all shoring
shall be removed by the contractor who installed same.
13.2 This contract shall also include all necessary cutting and patching
of masonry concrete, plaster, wood, steel, etc. as may be required
for the installation of shoring and supports.
END OF SECTION 0150
1 �• It
_.
S•
0150 -03
1 .1 � �i• 1 9� ICI
1.0 DELIVERY AND STORAGE
1.1 Schedule deliveries and unloading to prevent traffic congestion,
blocking of access, and interference with work. Arrange deliveries
to avoid larger accumulations than can be suitably stored at site.
1.2 Pack, handle, and protect materials to prevent damage during loading,
delivering, and storing.
1.3 Materials and equipment may be stored on the premises, in a manner
that will prevent damage to materials or structure, and that will
prevent injury to persons. Locations of storage shall be subject to
approval by the City of New Hope.
1.4 Store cementitious materials in dry, weathertight, ventilated spaces.
Store ferrous materials to prevent contact with ground and to avoid
rusting and damage from weather.
1.5 Damaged or defective materials, no matter in what stage of
completion, may be rejected by the architect and shall be removed
from the premises at once, at no additional cost to the Owner.
END OF SECTION 0160
01609108
BHA10 -89
0160 -01
0170 - PROJECT CLOSEOUT
1.0 OPERATING INS°IRUMONS AND MANUALS:
1.1 The contractor shall deliver to the owner two copies of neatly edited
looseleaf manuals for all operating equipment incorporated into the
work. The manuals shall contain the following information when
applicable.
1.1.1 - Complete operating instructions and recommendations as to the
fuel of product to be used.
1.1.2 - Cleaning instructions including recommended cleaning
materials.
1.1.3 - Complete lubrication data and schedules.
1.1.4 - Maintenance data, repair and schedules.
1.1.5 - Parts list with numbers, recommended parts of stock and
nearest parts depot and service organization.
1.1.6 - Assembly drawings, wiring diagrams, and mechanical diagrams.
1.2 Arrange with owner an appointment to give physical demonostration and
oral instructions for proper operation and maintenance of machines
and equipment.
2.0 CLEAN UP:
2.1 The general contractor shall, upon completion of work and prior to
owner move -in at substantial completion, thoroughly clean the
building. Foreign matter is to be removed from all surfaces with
appropriate solvents or cleaners. All ceiling tile and grid shall be
free of smudges, fingerprints, or other damage or soil. All new
windows and existing windows where work was done shall be washed on
both interior and exterior surfaces. All carpeting shall be
thoroughly vacuumed and other floors treated as specified and swept
and mopped. All woodwork and cabinets shall be dusted.
2.2 Refer to Section 0180.
3.0 AS BUILT DRAWINGS:
3.1 Contractor shall maintain one complete set of drawings on the site at
all times and mark all field changes and deviations in red pencil.
3.2 The owner will supply one set of transparencies of the drawings at
the time of substantial completion and the contractor shall transfer
all information and submit to the architect /engineer for approval
prior to final acceptance.
END OF SECTION 0170
01709108
BHA10 -89
0170 -01
0180 - TECHNICAL SPECIFICATION FORMAT
1.0 CONDENSED SPECIFICATIONS:
In an attempt to be brief and concise, much of the repetitive
wording of the specification has been eliminated and is contained in
this section by reference. The individual specification sections;
have a format that is the same as below, augment those below,
indicate if they apply, are required, or to what extent are
modified.
1.1 CONDITIONS:
Each and every specification section is bound by the Conditions of
Division A, B, C, and 01.
PART 1 GENERAL: .
1.01 Scope - The extent of work of this section shall be to provide
and /or install as noted; all labor, materials, equipment, and
services necessary for and reasonably incidental to providing and /or
installing, as noted the items mentioned in the section title
together with other related items as indicated on the drawings and
specified herein.
1.02 Alternate Bids - The owner requests an alternate bid or bids related
to the work of this section. Refer to Section 0110.
1.03 Unit Prices - The owner requests a unit price for the possible
addition or deletion of work related to the work of this section.
1.04 Shop Drawings - Refer to General and Supplementary Conditions for
submission method and quantities.
1.05 Samples - For sample requirements, refer to Article 4.13.2 of the
General Conditions and as modified by the Supplementary Conditions.
If a mock -up sample is required, it shall be an area of 4' -0" x
4' -0" of each material finish, or color. The architect will allow
mock -up's to become part of the permanent construction if they
affect the aesthetics of future use of the building or item.
Unapproved mock -ups will be torn down or otherwise removed
immediately.
1.06 Guarantee - The time shall be as described and designated in
Division "C" but in no case shall be less than 1 year. However, 'if
certain items have not been installed as of the time of substantial
completion, then the guarantee period for these items shall begin at
the time of installation. In the case of owner use and occupancy of
a portion of the work prior to completion of the entire project, the
guarantee period of said portion of work shall commence upon the
date of the certificate of substantial completion for the portion
involved. The contractor shall notify the architect in writing of
any error, inconsistency, omission or discrepancy in the contract
documents or of any actions of the owner or the owner's agents that
could invalidate this warranty.
0180 -01
0180 - TECHNICAL SPECIFICATION FORMAT
PART 1 GENERAL: (continued)
1.07 Standards - Reference in the specifications to known standards, such
as codes, specifications, etc., promulgated by professional or
technical associations, institutes, and societies, are intended to
mean the latest edition of each such applicable standard adopted and
published as of the date of the advertisement to bid on this project
except where otherwise specifically indicated. Each such standard
referred to shall be considered a part of the specifications to the
same extent as if reproduced therein in full. Contact Architect for
identification, if required.
1.08 Testing - Provide number and type indicated. Sample preparation or
size as recommended by testing laboratory. Refer to Section 0140 -
Quality Control for testing specifications.
1.09 Include List - It is the responsibility of the contractor to
establish the extent of work required of each section in order to
complete the product. However, on occasion a list is provided for
the convenience of the contractor to expedite bidding. The list is
not intended to be complete.
1.10 Do Not Include List - On occasion, and for the convenience of the
contractor, a list of items included in other sections of the
specifications, by others or the owner, is included.
1.11 standards of Quali - When manufacturers are mentioned in this
paragraph, it shall mean that they have been judged to be able to
equal the standard of quality of the manufacturers' products
mentioned in the materials list of Part 2 - Products. If no
manufacturer is listed in the materials list of Part 2, each of the
manufacturers listed in 1.11 are acceptable to produce the product
to its specified performance. The architect shall be the judge of
which manufacturers' products are equal to those specified in Part
2.
1.12 Clean Up - During construction, clean up shall be "broom finish".
For final clean up., see 0170-2.0.
i .
FIMM11415.•-•
0180-02
0190 - MISCELLANFOVS REQUIRE ENM
1.0 LAYOUT OF BUR DING:
1.1 The general contractor shall employ an experienced and competent
civil engineer to establish a permanent benchmark to which easy
access may be had during the progress of the work and to determine
all lines and grades. Keep on the job at all times, a complete
level and transit and keep same in good working condition to allow
the architect unrestricted use of same at all times if desired.
2.0 BSI GLASS:
2.1 The general contractor is responsible for all damaged, broken, or
scratched glass until final acceptance of the project, and at
completion, he shall replace, at his own expense, all such glass.
Glass broken or damaged by others will be replaced by the contractor
and cost paid for by the responsible party.
3.0 WORK NOT IN CONTRACT:
3.1 Items indicated on the drawings as "NIC ", or noted "Not in Contract"
are shown for convenience only and are not part of the contract.
Work denoted as above may be done prior to, during, or later than
the term of work for this contract.
3.2 Refer to Contract Documents to determine extent of work under this
contract incidental to work denoted as above including, but not
limited to, cutting, patching, fitting, and connecting.
3.3 The owner may undertake or award other contracts for additional
work, and the contractor shall fully cooperate with such other
contractors and owner's employees and carefully fit his own work to
such additional work as may be directed by the architect. The
contractor shall not commit or permit any act which will interfere
with the performance of work by any other contractor or owner's
employee.
3.4 Under no circumstances shall any work related to removal of asbestos
be included in this contract. It shall be the responsibility of the
owner to arrange for asbestos removal. It shall be expected that
completion of the work, by the owner, will occur prior to the
Contractor having access to any areas affected by asbestos removal.
The Contractor shall coordinate with the owner when access shall be
possible so as not to delay the work of this Contract.
4.0 CUTTING AND PATCHING:
4.1 Where new work abuts existing work to remain, and damage is incurred
to the existing surfaces or objects, the contractor responsible
shall restore the damaged surfaces to their original condition
without expense to owner.
4.2 Any cutting that may be required shall be done by the individual
trades requiring same, but cutting shall be done under the
supervision of the Prime Contractor. All patching shall be the
responsibility of the contractor performing the cutting.
4.3 Any new paths worn in the lawn areas outside the contract limits or
defined construction area, by changed pedestrian traffic due to the
construction barricades and fences, will be repaired by the owner
after completion of the work.
0190 -01
• r r a• - a �r. rMi
5.0 SALVAGE OR REMCYVAL:
5.1 Materials from site not required for re -use or storage, shall become
the property of the contractor and shall be removed promptly from
site. The owner, however, shall have the right of first refusal of
removed items.
5.2 Materials noted on the drawings to be reused, if applicable, shall
be approved before incorporating in the work. Contract amount shall
include cleaning, conditioning, and installing items or materials to
be reused.
5.3 Materials indicated to be retained or stored for the owner shall be
removed without damage and placed in the designated area noted on
the drawings. Such area shall be properly protected to prevent
dirt, damage, or markings of the area.
6.0 INTERRUPTION OF SERVICES
6.1 Utility services shall be interrupted only with the approval of the
Architect and Owner and shall be coordinated with the owner's
activities.
7.0 VISITATION OF SITE:
7.1 It shall be the responsibility of all contractors to visit the site
and familiarize himself with existing conditions before attempting
to formulate a bid.
8.0 DAMAGE TO EXISTING:
8.1 Each contractor shall be responsible for protection of existing
surfaces, fixtures, hardware, ductwork, conduit, or any other items
indicated in the Contract Documents to remain as existing or to be
refinished or otherwise reused. Any damage which may occur to the
above must be repaired and /or replaced to correct said damage, to
the satisfaction of the architect.
9.0 CLARIFICATION OF DEFINITIONS:
9.1 The following definitions are provided for specification
clarification: The Contractor - A Prime Contractor for the project.
This Contractor, or this Subcontractor - The Subcontractor for a
particular trade or type of work, as contracted to the Contractor.
10.0
10.1 Dimensions indicated on the drawings are based upon the original
drawings for the existing buildings and /or typical dimensions taken
in the field. Before ordering any material or doing any work, each
contractor shall verify all measurements at the building and shall
be responsible for the correctness of same. No extra charge or
compensation will be allowed due to differences between actual
dimensions and the measurements indicated on the drawings;
differences which are found, shall be submitted to the architect for
consideration before proceeding with the work.
0190 -02
0190 - MISCELLANEOUS
11.0 SHOP DRAWD4GS:
11.1 The Contractor shall submit (1) reproducible transparency and (2.)
print of drawings, and (6) copies of other data to the Architect for
review. Shop drawings shall be submitted sufficiently in advance of
construction of the product being reviewed to allow ample time for
checking, correcting, resubmittal and rechecking.
11.2 All shop drawings must be reviewed by the Prime Contractor prior to
sending to the Architect and shall bear the Contractor's stamp as
evidence that they have been reviewed by, and consequently approved
by, the Contractor. They must, be signed and stamped, with all
corrections noted. Review by the architect is only for conformance
with the design concept of the project and does not relieve the
contractor of the responsibility of conforming with the Contract
Documents. Any changes made in the dimensions or quantities are
done only as an aid to the Contractor to indicate possible
conflicts. The Contractor has final responsibility for dimensions
and quantities, fabrications, techniques of construction and
coordination of the work with all other trades.
0190-03
WIM V W-116i Do DON
1.0 GENERAL:
1.1 Soil investigation work for the building area involved in the work of
this contract have been performed and are available for review and
inspection at the office of the architect. The Bidders shall be
responsible to familiarize themselves with the content of the Soil
Investigation Report.
END OF SECTION 0201
02019108
BHA10-89
0201-01
0211 - DEMOLITION
REFERENCE: Refer to Section 0180 for explanation of abbreviated
specification format.
WN-lumm"Ralim
1.01 Scope - Provide and execute.
1.02 Alternate Bids - See 0110.
1.03 Unit Prices - Not applicable.
1.04 Shop Drawings - Not applicable.
1.05 Samples - Not applicable.
1.06 Guarantee - Per contract conditions.
1.07 Standards - Not applicable.
1.08 Testing - Not applicable.
1.09 Include List - As shown on drawings or as required to complete the
Work:
A. Concrete pool deck, as required.
B. Concrete curbs and sidewalks, as required.
C. Bituminous paving, as required.
D. Cyclone fence.
E. Storm drain system within construction limits, including catch
basins and piping. Refer to Mechanical.
1.10 Do Not Include List Mechanical or electrical demolition.
1.11 Standards of Quality Not applicable.
1.12 Clean Up - Per contract conditions.
TART 2 PRODUCTS:
2.01 Materials - All materials noted for demolition shall be removed in a
neat and workmanlike manner so as to facilitate the new construction
through simple and neat connection detail.
PART 3 EXECUTION:
3.01 Demolition
A. Items noted for retention shall be stored on the site in a manner
which will protect them until reuse or turning over to owner is
performed.
B. The contractor shall examine the drawings and existing site
condition to determine extent of demolition work required.
C. Accomplish all demolition of existing construction as requij:ed for
the accomplishment of work under the contract. Care shall be
Laken to assure that the existing construction to remain in place
is not damaged.
D. Materials not required for reuse shall become the property of the
contractor that removed them and shall be removed promptly from
the site. The owner, however, shall have the right of first
refusal.
E. Materials noted on the drawings and/or specified or chosen for
retention shall be removed by this contractor from the work area
and delivered to a designated storage location at the building
site.
F. All structures to be removed shall be removed completely from the
site, only after the owner has been consulted and has given his
approval to the demolition schedule.
0211-01
0211 - DEMOLITION
PART 3 EXMMON: (continued)
3.01 Demolition (continued)
G. All existing concrete foundations, footings, curbs and paving
shown to be removed, shall be removed completely from the site.
All subsequent excavations of existing material shall be
backfilled with suitable fill as required.
END OF SECTION 0211
02119108
BHA10-89
0211-02
0220 - EXCAVATION AND BACKFILL
REFERENCE: Refer_ to Section 0180 for explanation of abbreviated
specification format.
1.01 Scope - Provide and install.
1.02 Alternate Bids - See 0110.
1.03 Unit Prices - See 1.17 Bidding, this section.
1.04 Shop Drawings - Not required.
1.05 Samples - Not required.
1.06 Guarantee - Per contract conditions.
1.07 Standards - See testing.
1.08 Testing
A. The contractor shall employ and pay for an independent testing
laboratory, approved by the architect, to make all tests required
herein.
1. Maximum dry density at optimum moisture content in accordance
with ASTM D 1557 for each type of soil to be used for-
compacted fill.
a. Provide 1 compaction test every 75' at all interior and
exterior bearing walls.
b. Provide 1 compaction test per 2500 sq. ft. under floor
slabs.
c. Provide 1 compaction test per 5000 sq. ft. under
bituminous paving.
B. If compaction is found to be unsatisfactory, this contractor shall
have the laboratory make the necessary number number of extra
in -place field dry density tests to determine the extent of
re- compaction work required and shall perform whatever
re- compaction is then necessary.
1.09 Include List - All excavation, backfill and engineered fill for
buildings, slab base, bituminous paving removal, protection of
excavation from freezing.
1.10 Do Not Include - Bituminous base.
1.11 Standard of Quality - See testing.
1.12 Clean Up - Per contract conditions.
1.13 Site Visitation - This contractor shall visit the site to determine
the existing conditions under which he will be obliged to operate and
the extent of the site preparation work in accordance with
Instructions to Bidders.
1.14 Existing Service Lines and Utility Structures
A. Existing service lines and utilities, which are to remain in
service, shall be protected from damage, and supported if
necessary. When such service lines or utilities are not shown on
the drawings are encountered within excavated areas, notify the
architect. Contract amount shall be adjusted for additional work.
(However, verify location of existing utility lines as noted on
drawings.)
1.15 Soil Investigation - Section 0201.
1.16 Bidding
Base Bid - Bid as per drawings assuming a soil bearing capacity of
2000 # /SF.
0220 -01
0220 - EXCAVATION AND BACKFILL
2.01 Materials - Fill material shall be obtained from excavations on the
site, provided this material meets the following requirements and is
approved. Additional fill material, if required, shall be obtained
from borrow pits off the site approved by the architect. All fill
material shall be free of organic or frozen material, debris or
stones having a diameter larger than 6 ".
A. Compacted Fill Supporting Footings shall be well graded material,
such as sand or gravel, tested and approved by the testing
laboratory.
B. Compacted Fill Supporting Exterior and Interior Building Sla
shall be granular material, friable earth or clays of low
plasticity tested by the testing laboratory and approved by the
architect. The native sandy soils, type SP can be used for this
fill.
C. Compacted Fill Against Exterior Face of Foundation and areas of
general grading shall be suitable fill as found on site.
3.01 Clearing
A. Clear all areas as required for new work.
B. Before removing topsoil, scrape or rake area to remove roots,
loose materials, rocks, and weeds. Debris, stones larger than
four inches, or excessive amounts of subsoil not permitted in
stripped topsoil. Follow recommended excavation criteria as
called out in Soils Engineering Report. See Soils Report, Section
0201.
C. Remove topsoil to its entire depth in spaces indicating grading
changes, storage areas, and spaces to have structures, drives,
walks and paving.
D. Store topsoil on site in neat piles.
3.02 Excavating
A. Excavate within building area, and beyond for working space, to
depths required. Prepare surface level to within one inch
elevations indicated.
B. Excavation shall be sufficiently made so that all footings bear on
virgin soil. If the contractor is in doubt of bearing capacity of
the soil at the bottom of the footings or other work, he shall ask
the architect for further instruction. Failing to do so he shall
be responsible for any damage due to settlement.
C. Excavate to a minimum of six inches below bottoms of slabs,
minimum of six inches below finish grade for planting and lawn,
and to bottom of sub -grade for paved area.
D. Provide lights and barricades around all excavations as may be
required by all laws or ordinances or consideration of general
safety.
E. Control the grading in vicinity of excavated areas so as to
prevent water from running into or standing in excavated areas or
damaging other structures.
0220 -02
0220 - EXCAVATION AND BACKFILL
PART 3 EXECMION: (continued)
3.02 Excavating (continued)
F. Provide all labor and equipment to maintain dry conditions in
excavation at all times until backfilling is completed or
permanent drainage is in operation.
G. All footing, building slab, and paved area subgrades shall be
approved by the architect.
H. Unauthorized Excavation - If approved subgrade is encountered at
the elevations shown on the drawings and the contractor excavates
to a greater depth, the architect may direct the contractor to
extend the footings and foundation walls or piers to the lower
elevation, or place properly placed and tested compacted granular
fill to the specified elevations without additional payment.
I. Authorized Additional Excavation - If approved subgrade is not
encountered at the elevations shown on the drawings, the architect
may direct the contractor to excavate to a greater depth and
ba.ckfill with properly placed and tested compacted fill. Payment
for such additional work shall be in accordance with the
established unit prices of the contract.
J. All excess excavated material not needed or suitable for fill, is
to be removed from site. -
K. All rocks of more than 6" in diameter are to be removed from site
in same manner as of above. Larger boulders of 4' in diameter and
larger will be retained and used by owner for landscaping.
3.03 Filling and Compacting
A. Remove debris from excavations before backfilling, and backfill
both sides of foundation wall at the same time.
B. Grades shall be uniform levels or slopes between points where
elevations are given or between such points and existing grades.
Abrupt changes in slopes shall be rounded.
C. Place compacted fill material in horizontal layers not exceeding
8" in thickness. Placement shall start in the deepest area and
progress approximately parallel to the finished grade.
D. No compacted fill material shall be placed in free water, or
frozen ground, or on surfaces which have not been tested and
approved by the architect.
E. Soils shall be undisturbed below bottom of footing grade. A large
vibratory roller shall be used to surface compact the upper 2 feet
of soil below bottom of footing grade to 98% Standard Proctor
density (ASTM D- 698 -78). Compact fill under building slabs to 95%
of Standard Proctor density. Against exterior walls to 90%
Standard Proctor density. Under bituminous paving to 95% of
Standard Proctor density.
F. Perform the tests specified as directed by the architect and
obtain the architect's approval before proceeding with the next
layer is started.
0220 -03
0220 - EXCAVATION AND BACEFILL
PART 3 EXECUTION: (continued)
3.03 Filling and Compacting (continued)
G. Do not compact material when the moisture varies more than 2% from
the optimum moisture content. A uniform moisture content will be
required throughout the layers of fill material. Wetting or
drying manipulation shall be required if necessary to accomplish
this. Suspend compaction operations when, in the architect's
opinion, satisfactory results cannot be obtained because of rain
or other unsatisfactory conditions.
3.04 Site Grading
A. Do all cutting, filling, compaction of fills and rough grading
required to bring the entire project area, outside of buildings to
subgrade before any other work begins.
1. For surfaced areas such as lawn, roadways, parking areas,
service courts, steps and walks to underside of the respective
surfacing or base course, as fixed by the finished grades
therefore.
B. Finish rough grading to that ordinarily obtainable by use of
bladegrader or scraper.
C. Slope rough graded surfaces to drain surface water away from
excavations and structures, minimum slope one inch in four feet.
D. Any settlement or washing that occurs prior to acceptance of the
work, shall be repaired, and grades re- established to the required
elevations and slopes.
E. Fill to required subgrade levels any areas where settlement
occurs. Where subgrade for paving abuts existing paved areas,
provide and maintain tapered fill of gravel or other suitable
material.
3.05 Base Fill
A. Immediately below slabs on grade, furnish and place a 6" clean
granular fill.
B. Roll and compact base fill.
3.06 In all cases, follow recommendations of Soils Engineering Foundation
investigation. Any discrepancy between Soils Engineering Report and
architect excavation and backfill specification shall be brought to
the attention of the architect prior to the work in question being
done.
END OF SECTION 0220
1 1. 1:
• .
0220 -04
0280 - LANDSCAPING
REFERENCE: Refer to Section 0180 for explanation of abbreviated
specification form.
WMA
1.01 Scope - Provide and install.
1.02 Alternate Bids - See 0110.
1.03 Unit Prices - Not required.
1.04 Shop Drawings - Not required.
1.05 Samples - Not required.
1.06 Guarantee - Required until end of maintenance period.
1.07 Standards - AAM.
1.08 Testing - Not required.
1.09 Include List - Sodding and final smoothing of topsoil, planting of
shrubs, trees, and rock border around buildings.
1.10 Do Not Include List - Preparation of subgrade, spreading of topsoil.
1.11 Standards of Quality - Not applicable.
1.12 Clean Up - Per contract conditions.
... ••,iI
2.01 Materials
A. Topsoil is furnished and installed under 0220.
B. Fertilizer, certified commercial containing 10 -6 -4
(Nitrogen- Phosphate - Potash).
2.02 Sod.
A. Sod shall be nursery quality, free of noxious grasses and weeds,
such as, but not limited to quack grass, crab grass, etc., and
shall have dense growth, be well rooted, with at least 70%
Kentucky Bluegrass. Submit source of sod and sod description to
architect for approval. Sod shall be a minimum of 18" wide by 24"
long, with not less than 1 1/2" to 3/4" soil on the roots.
3.01 Sod
A. Lawn areas constructed in spring after April 25 shall be covered
with a 1" loose layer of clean wheat or oat straw. Straw shall be
kept wet until a catch of grass is established. After which this
contractor shall remove loose straw from site.
3.02 Watering
A. Water grass as necessary to maintain healthy plants. All areas
not maintained properly must be replaced by contractor. All
watering should be done in the afternoon or at night. The surface
layer of soil must be kept damp by frequent light watering with a
fine _spray during the germination period after seeding or
vegetative planting and until the young plants are rooted firmly.
0280 -01
0280 IANDSCAP
PART 3 EXECUTION: (continued)
3.03 Maintenance Period
A. Maintain seeded lawn for a minimum period of 60 days after
substantial completion or date of lawn completion, whichever is
longer, by watering, weeding, and mowing. After this period, lawn
will be maintained by owner.
3.04 Clean Up
A. Upon completion of all construction, this subcontractor shall
clean up any debris, stones, etc., from planted and paved areas,
in a neat and acceptable condition meeting the approval of the
architect.
END OF SECTION 0280
1 :1• it
C# 1 1
0320 - CONCRETE REINFORCEMENT
REFERENCE: Refer to Section 0180 for explanation of abbreviated
specification format.
1.01 Soo - Provide and install.
1.02 Alternate Bids - See 0110.
1.03 Unit Prices - Not applicable.
1.04 Shop Drawings - Required.
1.05 Samples - Not required.
1.06 Guarantee - Per contract condition.
1.07 Standards - ACI 318-71, ACI 315-65, CRSI, ACI 301-66.
1.08 Testing - Not required.
1.09 Include List
A. Welded wire fabric in all exterior slabs and walks.
B. Reinforcing bars in concrete.
C. Reinforcing bars in masonry.
1.10 Do Not Include List - Not applicable.
1.11 Clean Up - Per contra conditions.
1.12 Clarification - All relative notes on structural drawings shall have
precedence over this section.
a , 4 & I •
2.01 Materials
A. Reinforcing bars: New billet - steel bars, ASTM A615, Grade 60
(except grade 40 for ties), domestic manufacturer.
B. Welded wire fabric: ASTM A185 of wire gauge and mesh size a shown
on the drawings or required. Domestic manufacturer.
C. Accessories: Properly sized chairs, spacers, boltsters, etc.
Provide plasti-coated accessories at slabs and beam that are
exposed below.
2.02 Miscellaneous Fabrication
A. All bars over #2 size shall be deformed bars.
B. Where reinforcing bars are continuous, lap bars 24 diameters at
splices unless otherwise shown. Non-continuous ends of top bars
in beams and slabs shall terminate in a standard hook unless
otherwise shown.
C. Furnish temperature steel for all concrete slabs in accordance
with ACI code, unless otherwise shown.
D. All bars with hooks and/or 90 degree bends shall be bent to a
radius as prescribed by ACI 318-71. Provide comer bars at all
comers and intersections.
0320-01
KEENER
3.01 Placing
A. Place, support, and tie reinforcing to prevent displacement.
Reinforcing shall be cleaned of oil, grease, scale, rust or other
coatings which will impair the bond.
B. Reinforcing shall not be welded nor shall accessories of any kind
be welded to reinforcing bars, unless approved by the architect.
C. Bar supports or legs only which came in contact with forms for
concrete exposed to view in the finished structure shall have
plastic coated legs or shall be made of plastic. All bars shall
be tied to prevent displacement during concreting.
D. Welded wire fabric shall be lapped not less than the spacing of
the cross wires plus two inches.
3.02 Bond Beam & Masonry Lintel Reinforcing
A. Provide two No. 5 bars, unless otherwise noted, set on chairs
complete with corner bars as required.
B. In general, lintels in non-bearing walls at openings up to 5'-4"
wide shall be reinforced masonry lintels with a minimum of 8"
bearing at each end and reinforced with two #5 bars.
END OF SECTION 0320
a=- �
1
0320-02
0330 - CAST IN PLACE CONCRETE
REFERENCE: Refer to Section 0180 for explanation of abbreviated
specification format.
1.01 Scope - Provide and install.
1.02 Alternate Bids - See 0110.
1.03 Unit Price - None.
1.04 Shop Drawings - None.
1.05 Samples - Not required.
1.06 Guarantee - ACI 301-66 and ACI 302-69. The following portion of this
Section 0330 contains requirements and information related to the
above standards. In case of conflict between the above standards and
this section, the requirements stated herein shall govern.
1.08 Testing - Required. 1 compression test for each days pour.
1.09 Do Not Include List - Granular basefill and epoxy flooring..
1.10 Include List
A. Setting anchor bolts, setting plates, or other steel members
embedded in concrete as indicated on architectural drawings.
B. Grouting, including base plates, etc.
C. Concrete footing, flooring, aprons, benches and counters, and 6"
curbs for lockers.
D. Floor vapor barrier.
E. Installation of reinforcing.
F. Formwork.
G. Floor safe.
1.11 Weather Protection - Provide adequate protection from weather, �o
facilitate continued construction project.
1.12 Coordination - Coordinate activity with other trades to provide
containment of all items required by the project documents such as
handicap showers and floor tile.
1.13 Clean Up - Required.
1.14 Structural Clarification - All relative notes on structural drawings
shall have precedence over this section.
PART 2 PRODUCTS:
2.01 Materials - Materials must conform to the following specifications:
A. Portland Cement - ASTM C150-71.
B. Air Entraining Admixtures - ASTM C-260.
C. Aggregate - ASTM D-98.
1. Coarse aggregate shall be size 467 (1 1/2" max. size) for
footings and slabs on grade of 6" or greater thickness.
2. Coarse aggregate shall be size 1 (3/4" max. size) for all other
concrete except as otherwise noted.
3. Coarse aggregate at topping - 1/2" max. size.
4. Exposed aggregate - 3/8" to 3/4" smooth round stone. No
crushed stone allowed. Do not use aggregate containing any
iron.
D. Water - Clean, fresh, and potable.
0330-01
0330 - CAST IN PLACE CONCRETE
PART 2 PRODUCTS: (continued)
2.01 Materials (continued
E. Premolded expansion joint filler - 1/2" x slab depth, Homex 300.
F. Curing Compound - ASTM C309-58, Type 11, 100% resin-based, with
fugitive dye. Use compound with white dye in hot, dry weather.
(Exterior walks and curbs only.)
G. Shrinkage Compensating Portland Cement - (Chem-Comp.) Penn-Dixie
or approved equal.
H. Non-shrink grout - "5-Star", "Por-Rok".
T. Vapor Barrier - 4 mil polyethelene.
J. Forms
1. Not exposed to view - wool 3/4" No. 2 common lumber or panel
forms.
2. Exposed interior non-finished surfaces - moisture resistanL
plywood, 5/8" minimum, large sheets with inconspicuous joints.
3. Exposed finished surfaces and exposed exterior - moisture
resistant plastic coated plywood, 5/8" minimum, large sheets
with inconspicuous joints.
4. Stoop formwork that remains in place shall be of uril-reated
plywood and lumber, such as; Spruce, Pine or other white woo is
to facilitate fast deterioration.
K. Sealer - Sonneborn "Kure -n-Seal" or approved equal.
L. Concrete patching - Tamms Floorstone or Floorstone/Lastex. Install
with Tamms FCP Liquid Bond.
M. Floor Safe - Rectangular floor safe, AMSEC 'Model 6131500,
distributed by Armor Security Co., Minneapolis., to be installed
in Manager's Office (12-3/4" x 14-1/2" x 10-3/4").
2.02 Proportioning
A. Concrete shall be working stress type, normal weight, of strengths
as shown on structural drawings.
B. All exterior concrete shall be air entrained concrete. The ail
content shall be as follows for the maximum size coarse aggregate
used:
5% to 8% for 3/4" coarse aggregate
4% to 7% for I" coarse aggregate
3% to 6% for 1 1/2" coarse aggregate
C. High early strength concrete is not required, but may be used
pending approval.
D. Tests shall yield an average minimum 28 day strength 15% greater
than required.
E. Concrete with horizontal average minimum 28 day strength 15%
greater than required.
F. Concrete with horizontal surfaces exposed to weather shall have a
minimum cement content in legs per cubic - yard of 6 for no
plasticizing admixture and 5 1/2 with plasticizing admixture.
Maximum water shall be six gallons per bag.
G. Slump shall be within the following limits:
Vertical surfaces - 5" maximum, 3" minimum
Slabs - 4" maximum, 2" minimum
H. Exposed aggregate concrete shall contain 2 fl, oz. per 100 lb. of
cement of Plastiment Retarding Densifier by Sika or equal and be
air entrained to 3% to 6%.
I. Precast topping - 3,000 psi.
0330-02
0330 - CAST IN PLACE CONCRETE
a . *
3.01 Mixing - Batch mixing at site will not be allowed unless approval is
obtained. Approval must be obtained from architect.
3.02 Flatwork
A. All slabs-on-grade (interior and exterior) shall be placed over a
base fill specified in Section 0220, compacted and dampened (but
not wet) just prior to placing concrete.
B. Construction joints shall conform to Section 704 of ACI 318 and
shall not exceed the following maximum spacings:
1. Slabs on grade without intermediate control joints - maximum
spacing 30'-0". (Locate joints under partitions)
2. Slabs on grade with intermediate control joints - no limit.
C. Control joints - shall not exceed the following maximum spacings:
1. Slabs on grade - 25' with maximum area bound by control joints
of 625 sq.ft.
D. Depths of control joints shall be as shown on drawings.
E. Expansion joints - (Slab-on-grade) shall be provided at all
locations indicated on drawings, at walls, steps, where shown, and
where new work adjoins exterior walls, slabs, and bituminous
surfaces. 60'-0" on center maximum at exterior walks
F. Unless otherwise shown, all slabs on grade shall be G" thick.
G. Except as otherwise noted, slabs shall have a minimum of three
steel trowelings, an approved power disc float machine or rollers
not over 24" long and weighing not less than 200 pounds may be
used as directed by architect. Slabs to be smooth finish with no
variations.
H. Concrete benches and counters may be pre-cast or poured subject to
approval of the Architect.
3.03 Bar Clearance - Clearance between reinforcing and earth or forms
shall be as follows:
Footings 3"
Slabs (structural) 3/4"
BeLuns & Columns (stirrups or ties) 1 1/2"
Slabs on grade - approximate center of slab
3.04 Curing
A. All horizontal interior slab surfaces shall receive curing/sealing
compound as specified.
B. In cold weather, (below 40 degrees F) the materials, including
forms, shall have been heated to between 70 degrees and 80 degrees
before depositing and a heated enclosure provided, with
temperature maintained within enclosures of 70 degrees F. for 2
days or 50 degrees F. for 5 days.
3.05 Finishes
A. Unless otherwise noted, slabs shall be light broom finish.
Counters and benches shall be smooth or rubbed finish.
3.06 Tolerances
A. Class A tolerances shall be:
1. 1/16" above or below the line in 10"0".
2. 1/32" above or below the line in W-O".
0330-03
0330 - CAST IN PLACE CONCRETE
PART 3 EXECUTION: (continued)
3.07 Vapor Barrier
A. Install under all interior slabs.
END OF SECTION 0330
03309108
BHA10 -89
0330 -04
0401 - MASONRY CONSTRUCTION
REFERENCE: Refer to Section 0180 for explanation of abbreviated
specification format.
�1 Us
1.01 Scon - Provide and install.
1.02 Alternate Bids - See 0110.
1.03 Unit Price - None.
1.04 Shop Drawings - None.
1.05 Samples - None
1.06 Guarantee - Per contract condition.
1.0 Standards - ASTTM, NCMA. SCPI.
1.08 Testing - Not required.
1.09 Include List
A. Cold weather protection as required.
B. Joint reinforcing.
C. Installation of embedded items such as steel reinforcing, well
plates, and anchors.
D. Concrete for bond beams in accordance with Section 0320 and 0330.
F. Loose lintel installation.
F. Brick veneer ties.
1.10 Do Not Include List
A. Sealant.
1.11 Standards of Qualit - Not applicable.
1.12 Clean Up - Per contract conditions.
1.13 Environmental Conditions
A. Provide for heating and protecting in cold weather. Do not use
frozen or ice-covered materials.
B. Do not lay masonry when temperature is expected to fall below 35
degrees F. Provide ample enclosures and heat for continuatiori of
work without interruptions from weather except for days of rain
and high winds. Keep masonry moist in hot weather, until mortar
has cured.
C. Cover tops of walls at end of day's work. Protect finished
concrete blockwork from damage.
D. Conform to the recommended hot and cold weather masonry practices
of the Structural Clay Products Institute.
1.14 Scaffolding - This contractor shall furnish, maintain, and move as
required all scaffolding he may require for the installation of his
work.
1.15 Codes - Meet requirements of U.B.C.
1.16 Structural Clarification - All relative notes on structural
shall have precedence over this section.
PART 2 PRODUCTS:
2.01 Materials
A. Hollow load-bearing stone aggregate concrete block AST'l C-90-70
grade N, Type I of approved manufacturer, cured 30 (lays before
delivery.
B. Face Brick Allowance - Brick shall be 3-5/8" x 3-5/8" x 11-5/8"
with an allowance of $650.00/1000 F.O.B. jobsite. Basic brick
color shall match existing Concession Building.
C. Portland Cement: ASTM C-150, Type 1.
0401-01
0401 - MASONRY CONSTRUCTION
PART 2 PRODUCTS: (continued)
D. Masonry Cement: ASTM C -91, Type M or N.
E. Hydrated Lime ASTM -207, Type S or Type N, double hydrated.
F. Sand; ASTM C- 144 -70, natural, 100% sieve, 5" (min.) retained on
#16 sieve, 30% (max.) pass 450 sieve.
G. Water: Free from matter that could impair suitability for use in
mortar.
H. Cleaning Agent: Sure -Kleen or approved equal, type of cleaner to
be approved by architect.
I. Concrete Corefill: 1 Portland, 2 1/2" fine sand, 2 pea gravel.
J. Non- shrink Grout: "5- Star ", "Por -Rok ", or approved equal.
K. Control Joint Strip: Carter Waters Regular Block Joint, Dur -O -Wall
Rapid Control Joint - Regular, A -A Wire Products Co. Tite -Wall,
Hohmann & Bernard Type QSB -4, Vinylex Regular, or approved equal.
L. Bituminous plastic cement: conforming to Federal Spec. SS- C- 153C.,
Type 1.
M. Joint reinforcing: See structural notes.
N. Control joint strip: Carters Waters Regular Block Joint,
Dur -o -Wall Rapids Control Joint - Regular, A -A Wire Products Co.
Tite -Wall, Hohmann & Bernard QSB -4, Vinylex Regular, or approved
equal.
0. Brick veneer ties -
P. Exterior masonry walls should be filled with poured styrofoam
beads, masonry fill insulation.
2.02 Mortar Measurement and Mixing
A. All mortar shall be mixed utilizing masonry cement of the
appropriate strength. Masonry cement shall be mixed as recommended
by the manufacturer for the mortar type.
B. Measurement of materials: The method of measuring materials for
the mortar used shall be by either volume or weight, and such that
the specified preparations can be controlled and accurately
maintained. Measurement of sand by shovel will not be permitted.
C. Mixing mortars: All cementitious material shall be. mixed for at
least 3 minutes and not more than 5 minutes in a mechanical batch
mixer with the maximum amount of water to produce a workable
consistency.
D. Retempering: Mortars that have stiffened because of evaporation of
water from the mortar shall be retempered by adding water as
frequently as needed to restore the required workable consistency.
Mortars shall be used and placed in final position within 2 1/2
hours after initial mixing.
E. Colored mortar to be job mixed. Follow manufacturers instructions
completely when adding pigments to mortar.
2.03 Use of Mortar Types
A. Type M Mortar - shall be used for all masonry, below.
B. Type N Mortar - shall be used for all other masonry.
3.01 Laying Block
A. Lay block plumb, level, or true to a line.
B. Finish flush joints that will not remain exposed. Use concave
tooled joints for work that will remain exposed. Tool vertical
joints first. Use joints approximately 3/8" wide.
0401 -02
0401 - MASONRY CONSTRUCTION
PART 3 EXECUTION: (continued)
3.01 Laying Block (continued)
C. Dampen block and concrete brick on mortar faces only, in hot
weather, immediately before laying. Lay block without units
carrying surface water.
D. Lay hollow block in full mortar bed on shell surface and at ends.
Lay concrete brick and solid block in full mortar bed with head
and edge joints completely filled.
E. Block work shall be running bond unless otherwise noted.
F. Provide reinforced concrete block lintels at all door, window, and
duct openings where other lintels are not provided.
G. Furnish solids and special shapes at jambs and corners. Make all
cuts with a.masonry saw. No broken units shall be exposed in
finish work.
H. At control joints, insert control joint strip and premolded joint
fillers to provide a 3/4" deep rake joint on both sides of wall
for other's sealant.
I. Fill void of bond beam and reinforced lintels with 3,000 psi
concrete unless noted otherwise, mixed according to Section 0330,
which shall apply to this section by reference.
J. Install joint reinforcing and ties at spacings shown on structural
drawings for the various wall constructions. All ties and
reinforcing shall be embedded fully in mortar.
K. Install all embedded items required by the drawings and
specifications.
L. Control joint where shown on exterior elevations.
3.02 Laving Brick
A. General: Do not install cracked, broken, or chipped masonry units
exceeding ASTM allowances.
1. Use masonry saws to cut and fit exposed units.
2. Lay brick plumb, true to line, and with level courses
accurately spaced within allowable tolerances.
3. Do not furrow bed joints.
4. Stop off horizontal run by racking back in each course;
toothing is not permitted.
5. Adjust units to final position while mortar is soft and
plastic.
6. If units are displaced after mortar has stiffened, remove,
clean joints and units of mortar, and relay with fresh mortar.
7. When joining fresh masonry to set or partially set masonry:
a. Remove loose brick and mortar.
b. Clean and lightly wet exposed surface of set masonry prior
to laying fresh masonry.
8. All brick work to be laid with running bond.
9. NOT USED.
10. Dampen brick, in hot weather, immediately before laying. Do
not use brick carrying surface water.
11. Block back -up shall be laid simultaneously with the brick
facing.
12. Lay out courses to minimize cutting and to avoid jumping bond.
13. Install accessories, and built -in items, as work progresses.
Install loose lintels in full bed of mortar. Fill voids of
metal frames with mortar.
0401 -03
0401 - MASONRY CONSTRUCTION
PART 3 EXEQITION: (continued)
3.02 Laying Brick (continued)
A. (continued)
14. Keep cavity walls clean. Slightly bevel mortar bed to incline
toward cavity.
15. Install joint reinforcing and wall ties at spacings previously
indicated in specifications.
16. The interior surface of single wythe masonry mortar shall be
cleaned as required.
a. Protection of work
1. Protect sills, ledges, and offsets from mortar drippings
or other damage during construction.
2. Remove misplaced mortar or grout immediately.
3. Protect face materials against staining.
4. Protect the door jambs and corners from damage during
construction.
b. Mortar beds
1. Lay brick with full mortar coverage on horizontal and
vertical joints in all courses.
2. Provide sufficient mortar on ends of brick to fill head
joints.
3. Rock closures into place with head joints thrown against
two adjacent bricks in place.
4. Do not pound corners or jambs to fit stretcher units
after setting in place.
5. Where adjustments to corners or jambs must be made after
mortar has started to set, remove mortar and replace
with fresh mortar.
c. Mortar joints
1. Nominal thickness: 3/8"
2. Construct uniform joints.
3. Shove vertical joints tight.
4. Tool concave joints in exposed surfaces when thumbprint
hard using jointing tool.
5. Flush cut all joints not tooled.
3.03 Reinforcing, Fill, and Bearing
A. Place specified masonry reinforcing in all block. Embed
reinforcing completely in mortar, lap eight inches minimum.
B. Reinforcing for bond beams to be provided by others, but installed
by this contractor. Fill bond beams and vertical reinforce block
cores with not less than 3,000 PSI concrete. Meet applicable
requirements specified for concrete work.
C. When steel lintels are not detailed, use masonry lintels. For
masonry lintels, use block bond beam with 3,000 PSI concrete and
reinforced as indicated. Case and cure lintels as specified for
lintels with not less than two No. 5 bars.
3.04 Pointing and Cleaning
A. Cut out defective joints and holes in exposed masonry and repoint
with mortar.
B. Dry brush masonry surface after mortar has set at end of each
day's work and after final pointing.
0401 -04
0401 - MASONRY CONSTRUCTION
PART 3 EXECUTION: (continued)
3.04 Pointing and Cleaning (continued)
C. Apply cleaning agent to sample wall area of 20 sq.ft. (sq.m) in
location acceptable to the architect /engineer, if cleaning by
water does not produce satisfactory results.
1. Do not proceed with cleaning until sample area is acceptable to
architect /engineer.
2. Follow manufacturer's recommendations.
3. Thoroughly wet surface of masonry on which no green
efflorescence appears before using cleaning agent.
3.04 Pointing and Cleaning (continued)
C. 4. Scrub with acceptable cleaning agent.
5. Immediately rinse with clear water.
6. Work small sections at a time.
7. Work from top to bottom.
8. Protect sash, metal lintels, and other materials which may
corrode when masonry is cleaned with acid solution.
D. Leave work area and surrounding surfaces clean and free of mortar
spots, droppings, and broken masonry.
END OF SECTION 0401
04019108
BHA10 -89
0401 -05
0510 - STRUCTURAL STEEL
REFERENCE: Refer to Section 0180 for explanation of abbreviated
specification format.
1.01 Scope - Provide and install.
1.02 Alternate Bids - See 0110.
1.03 Unit Prices - None.
1.04 Shop Drawings - Required.
1.05 Samples - None.
1.06 Guarantee - Per contract conditions.
1.07 Standards - AISC, AWS.
1.08 Testing - Not required.
1.09 Do Not Include List - Grouting under plates or setting of plates,
loose steel angles for brick lintel.
1.10 Include List -
A. Anchor bolts, installed by 0330 or 0401.
B. Setting plates and bearing plates.
C. Beams, columns, base plates and other items shown on drawings.
1.11 Structural Clarification - All relative notes on structural drawings
shall have precedence over this section.
0, 1 Wit I
2.01 Materials
A. Structural Steel: Beams and angles - ASTM A36; Pipes - ASTM A53,
Type E or S, Grade B ; Tubes - ASTM A500, Grade B.
B. Bolts: ASTM A325.
C. Primer: Federal Specifications TT- P -86a, Type II or approved
equal.
D. Welding Electrodes: ASTM A223 E70xx.
2.02 Fabrication
A. All wall bearing beams shall have wall anchors, except as
otherwise shown, and stud anchor bolts as shown for all blocking.
B. Beam connection according to Uniform Load constants as given in
the AISC manual unless noted on drawings or reactions are noted on
the drawings in which case such reactions shall be provided -for.
Shop connections may be welded or bolted.
C. Standard welded framed beam connections of equal value that
conform to the AISC Manual may be substituted for riveted or
bolted connections, subject to approval. All bolts shall be 3/4"
diameter bolts.
D. Punch or drill for temporary field connections and for attachments
of work by other trades.
E. Where indicated on the drawings, A -325 bolts shall be used for
field connections. Two bolts minimum.
F. All steel shall be thoroughly cleaned, all rust and mill scale
removed and shall receive one shop coat of paint, except areas
within 2" of field welds. Unpainted areas left to preserve shop
marks will not be permitted.
0510 -01
0510 - STRUCTURAL STEEL
PART 2 PRODUCTS: (continued)
2.02 Fabrication (continued)
G. Access to places where materials for this contract are being
fabricated or produced shall be provided to the architect for the
purpose of inspection.
H. Substitutions of sections or modifications of details shall be
made only when approved, and at no additional cost to the owner.
I. All beam web copes shall be made to a radius of 1" (minimum).
PART 3 EXECMON
3.01 Erection
A. The contractor shall be responsible for the accurate setting and
leveling of all bearing plates and setting plates. Bearing and
setting plates shall be leveled on steel wedges or shims or as
otherwise detailed and then grouted in place.
B. Flame cutting of steel on site not permitted except with specific
approval.
C. This contractor alone shall be responsible for the correct fitting
of all structural members and for elevation and alignment of the
finished structure.
D. Steel to be encased in concrete shall not be painted. All interior
exposed steel shall receive one field coat of paint when noted on
the drawings.
E. All lintels bearing on masonry shall have a minimum of 8" bearing
at each end, with a minimum of three courses of brick or concrete
filled concrete block two courses high and 16" in length under
bearing ends, unless otherwise noted on drawings or details.
F. All welding shall be as required by code and appropriate standards
and done by qualified welder. Recently certified by A.W.S.
3.02 Cleaning
A. Remove soil, stain, and extraneous materials caused by structural
steel work, from adjacent surfaces.
B. Remove foreign matter and clean structural steel to satisfactory
conditions to receive specified finish.
C. Remove and replace items that cannot be satisfactorily cleaned.
3.03 Painting
A. All items shall be painted on shop coat of paint as herein
specified. Furnish to job a sufficient quantity of the same paint
for field touch -up of field welds, abrasions, etc.
0510 -02
0550 - MISCELLANEOUS METALS
REFERENCE: Refer to Section 0180 for explanation of abbreviated
specification format.
.. •
.4 flD
1.01 Sco pe - Provide.
1.02 Alternate Bids - See 0110.
1.03 Unit Prices - None required.
1.04 Shop Drawings - Required.
1.05 Samples- None required.
1.06 Guarantee - Per contract conditions.
1.07 Standards - AISC, AWS.
1.08 Testing - None required.
1.09 Include List -
A. Anchors and inserts related to this section.
B. Loose lintels installed by 0401.
C. Clip angles.
D. Standard steel pipe railings.
1.10 Do Not Include List
1.11 Standards of Qualit - Not applicable.
1.12 Clean up - Per contract conditions.
j•lu %
2.01 Materials
A. Steel - All steel shall be ASTM A36 steel unless otherwise noted
on the drawings.
B. Galvanized steel - ASTM A446-69 and latest standards of American
Hot Galvanizers Association.
C. Bolts - ASTM A307, latest edition.
D. Paint - Federal Specification TT-P-86a, Type II, or approved
equal.
E. Welding electrodes - ASTM A223E 70xx.
2.02 Fabrication
A. Fabricate all items in accordance with the drawings and
specifications and approved shop drawings.
B. All metal shall be thoroughly cleaned, all rust and scale removed,
and shall receive one shop coat of specified paint.
3.01 Erection - All miscellaneous metal shall be neatly and accurately set
as shown on the drawings.
0610 - ROUGH CARPENTRY
REFERENCE: Refer to Section 0180 for explanation of abbreviated
specification format.
9-A .14 M Wei
1.01 Scope - Provide and install.
1.02 Alternate Bids - See 0110.
1.03 Unit Prices - None.
1.04 Shop Drawings - None required.
1.05 Samples None.
1.06 Guarantee - Per contract conditions.
1.07 Standards and Codes
A. Lumber grading rules and wood species to be in conformance with
Voluntary Product Standard PS 20-70 grading rules of the following
associations apply to materials furnished under this section.
1. Northeastern Lumber Manufacturer's Associati6n, Inc. (NELKA)
2. Southern Pine Inspection Bureau (SPIB)
3. West Coast Lumber Inspection Bureau (WCLIB)
4. Western Wood Products Association (WWPA)
5. Redwood Inspection Service (RIS)
6. Northern Hardwood and Pine Manufacturer's Association (NTII7-
B. Plywood Grading Rules
1. Softwood Plywood - Construction and Industrial: Product
Standard PS 1-66.
2. Hardwood Plywood - Product Standard PS 51-71.
C. Grade Marks - Identify all lumber and plywood by official grade
mark.
1. Lumber - grade stamp to contain symbol of grading agency; mill
number or name; grade or lumber; species or species grouping or
combination designation; rules under which graded, if
applicable; and condition of seasoning at time of manufacture,
a. S-MMN: - Unseasoned—
b. S-Dry: Maximum of 19% moisture content.
c. MC-15 or XD: Maximum of 15% moisture content.
d. Dense.
2. Softwood Plywood: Appropriate grade trademark of the
Plywood Association.
a. Type, grade, class, and identification index.
b. Inspection and testing agency mark.
3. Hardwood Plywood: Appropriate grade mark of
inspection, testing, or grading.
D. Requirements of Regulatory Agencies:
1. Span tables: National Forest Products Association
2. Working stresses: Softwood Lumber, National
Specification, National Forest Products Association.
1.08 Testing - None.
1.09 Do Not Include - not applicable.
1-10 Include List
A. Blocking and bracing.
B. Roof curbs not provided by mechanical.
C. Roof blocking.
D. Wood deck.
E. Plastic laminate cabinet and countertop.
-American
qualified
Design
0610-01
0610 - ROUGH CARPENTRY
PART 1 GENERAL: (continued)
1.11 Clean Up - Required.
1.12 Structural Clarification - All relative notes on structural drawings
shall have precedence over this section.
PART 2 PRODUCTS:
2. Lumber
A. Dimensions
1. Specified lumber dimensions are nominal.
2. Actual dimensions conform to industry standards established by
the American Lumber Standards Conuilittee and the Rules Wri ting
Agencies.
B. Moisture content: Unseasoned or 19% maximum at time of permanent
closing in of building
; or structure, for lumber 2 inch or less
nominal thickness.
C. Surfacing: Surface four sides (S4S), unless specified otherwise.
D. Framing lumber: See structural notes. Hem-Fir. No. 2 or better.
2.02 Wood Blocking and Plates in contact with Concrete or Masonry: sh�.
be wolmanized lumber C.C.A. preservative and having a retention of
preservative of .40 lbs. per cubic foot of wood or equal.
2.03 Roof Blocking: shall be wolmanized lumber C.C.A. preservative and
having a retention of preservative of .40 Ibs. per cubic foot of wo,')d
or equal.
2.04 Rough Hardware: All exterior hardirare
galvanized or cadmium plated.
A. Bolts: (Anchor bolts)
1. FS FF-B-575 C.
2. FS FF-B-584 D.
B. Nuts: FS FF-N-836 C.
C. Expansion shields: FS FF-B 561 C.
D. Lag screws and bolts: FS FF-B-561C.
E. Toggle bolts: FS FF-B-588C.
F. Wood screws: FS FF-S-111C.
G. Nails and staples: FS FF-N-105B.
exposed to weather shall be
2.05 Metal Framing Accessories:
A. Strap Anchors 16 ga. -galvanized.
B. Framing Angles 18 ga. galvanized.
2.06 Roof Deck: Shall be 2" x 6" nominal tongue and groove solid wood
decking, #2 and better SPF. Place random controlled lay-up.
2.07 Roof Sheathing (Equipment Building): Shall be 5/8" C-D exterior
plywood. APA rated panels 30/12.
2.08 Plastic Laminate Cabinet: Shall be custom built in accordance t,;itla
AWI standards 400 casework with high pressure laminate finish. All
exposed surfaces shall be'1/32" plastic laminate. Provide inside
backer sheet.
0610-02
0610 - ROUGH CARPENTRY
3.01 Conditions of Surfaces - Verify that surfaces to receive rough
carpentry materials are prepared to exact grade and dimension.
3.02 Roof Blocking - shall be reviewed with the roofing contractor Lind
shall be installed to the requirements of his standard specifications
and guarantee and at a minimum shall be firmly anchored to deck or
perimeter so as to resist a lateral force of '15 pounds per lineal
foot.
END OF SECTION 0610
06109108
BHA10-89
0610-03
0619 - WOOD TRUSSES
REFERENCE: Refer to Section 0180 for explanation of abbreviated
specification format.
1.01 Sco - Provide.
1.02 Alternate Bids - See 0110.
1.03 Unit Prices - None.
1.04 Shop Drawings and Engineering Drawings -
A. This contractor shall be responsible for all truss and secondary
member designs which shall bear the name and seal and/or
registered number and state of registry of a Minnesota Licensed
Professional Engineer.
B. Truss designs shall contain the following data:
1. Design and fabrication data.
2. Metal connectors: Nominal sizes and locations of connectors at
all joints.
3. Lumber specifications.
4. Species and stress grade of lumber to be used as members.
5. Design loadings of trusses and allowable stress increase.
6. Force analysis or bar forces in each member.
Truss bearing supports: Sizes and location.
8. Camber.
9. Permanent bracing and/or bridging: as required to prevent
compression buckling of individual truss members only.
10.Handling and erection instructions.
C. Copies 'of the truss designs and/or shop drawings shall be
submitted to the architect for approval prior to the fabrication
of any components.
1.05 Samples - None.
1.06 Guarantee - Per contract conditions.
1.07 Standards and Codes
A. Lumber grading rules and wood species to be in conformance with
Voluntary Product Standard PS 20-70 grading rules of the following
associations apply to materials furnished under this section:
1. Northeastern Lumber Manufacturers Association, Inc. (NWLMA)
2. Southern Pine Inspection Bureau (SPIB)
3. West Coast Lumber Inspection Bureau (WCLIB)
4. Western Wood Products Association (WWPA)
5. Redwood Inspections Service (RIS)
6. Northern Hardwood and Pine Manufacturer's Association (NHPMA)
B. Grade marks: Identify all lumber by official grade mark.
1. Lumber: Grade stamp to contain symbol of grading agency; mill
number or name; grade of lumber; species or species grouping or
combination designation; rules under which graded, if
applicable; and condition of seasoning at time of manufacture.
a. S-GYN: Unseasoned.
b. S-Dry; Maximum of 19% moisture content.
c. MC-15 or RD: Maximum of 15% moisture content.
d. Dense.
C. Requirements of Regulatory Agencies:
1. Span tables: National Forest Products Association.
2. Working stresses: Softwood lumber, National Design
Specification, National Forest Products Association.
0619-01
0619 - WOOD TRUSSES
PART 1 GEgERAL: (continued)
1.07 Standards and Codes (continued)
D. The design and fabrication criteria of all wood trusses shall meet
with "National Design Specifications for Stress Grade Lumber and
its Fastenings" by National Forest Products Association (Latest
Revision); "Timber Construction Standards" by American Institute
of Timber Construction (Latest Revision); and "Design
Specifications for Light Metal Plate Connected Wood Trusses" by
Truss Plate Institute (Latest Revision), the same as if those
specifications and all their references were set out in full
herein.
E. All design shall be in conformance with current State and Local
Codes.
1.08 Testing - None.
1.10 Do Not Include List - Installation by 0610.
1.09 Include List - All roof trusses including the furnishing of all
materials, equipment and labor necessary for the prefabrication,
delivery and permanent setting of the wood trusses. Also include all
miscellaneous parts such as: blocking, bridging, temporary and
permanent bracing and all related items of hardware, metal hangers,
anchors and special metal shapes deemed by the structural engineer
and the truss design engineer to be necessary for the proper
prefabrication, erection, assembly, supporting and anchoring of the
wood trusses.
1.11 Clean Up - Required per contract conditions.
1.12 Product Delivery, Storage, and Handling
A. Immediately upon delivery to job site, place materials in area
protected from weather.
B. Store materials a minimum of 6" above ground on framework or
blocking and cover with protective waterproof covering providing
for adequate air circulation or air ventilation.
C. Do not store seasoned materials in wet or damp portions of the
building.
1.13 Standards of Quali - See 1.07 above.
2.01 Open Web Trusses Base Bid - All trusses referred to in this section
of the specifications shall be gang-nail Fink wood trusses, or
approved equal.
A. Lumber:
1. All lumber used for truss members shall conform to the
published as set out in the official grading rules of the
appropriate lumber association or as.listed in the reference
specifications; except that, whenever this specification, notes
on the plans, or truss engineering designs calls for lumber
which exceeds the minimum set forth therein, the specifications
plans, and/or truss engineering designs shall be applicable,
and information stated or shown in one shall be applicable the
same as if in all of them.
2. The moisture content of all lumber shall be within the proper
limits, as stated in the reference specifications, but shall
not, in any case, exceed 19% nor be less than 7% at the time of
fabrication.
0619-02
0619 - WOOD TRUSSES
PART 2 PRODUCTS: (continued)
2.01 Open Web Trusses Base Bid - (continued)
A. Lumber (continued)
3. All lumber shall conform to the species and fully recognized
nominal sizes shown on the plans or truss engineering designs.
All members shall be cut from lumber which bears the proper
grade mark stamp of a recognized grading agency association or
licenses lumber inspection agency. No lumber shall be used
which does not appear to conform to the proper dimensions
and/or grade.
B. Connectors:
1. All truss connector plates shall be manufactured from only
prime commercial quality galvanized sheet steel of no less than
20 gauge thickness which has a minimum yield of 33,000 psi., -
and a minimum ultimate tensile strength of 48,000 psi. The
corrosion resistant coating shall be 1.25oz. per square foot
commercial class hot dipped galvanized before stamping.
2. All metal connectors shall be gang-nail connectors, and shall
be stamped "gang-nail". The connectors shall have a series of
nail like projections which are designed to separate the fibers
of the wood into which they are pressed, in accordance with
accepted nailing practices.
3. Where field connections of truss sub-assemblies are necessary,
the connections shall be in accordance with the details shown
on the truss design drawings, approved by a professional
engineer and the architect.
C. Fabrication:
1. All trusses and other roof structural components shall be
fabricated in a properly equipped manufacturing facility. They
shall be manufactured by experienced workmen, using precision
cutting and truss fabrication equipment, under the direct
supervision of a qualified foreman. All trusses shall be
fabricated under strict rules of inspection and quality control
as the local code may require, open to the inspection of the
architect or his representative at all times.
2. All truss members shall be accurately cut to length, angle and
be true to line to assure tight joints for finished truss.
3. All truss members and connector plates shall be properly placed
in special jigs and the members tightly clamped in place,
remaining in that position until the connector plates have been
pressed into the lumber simultaneously on both sides of the
joints.
4. Camber shall be built into the trusses, as noted on the
engineering truss designs, by properly positioning the members
in the fabricating jig.
5. Top and bottom chords shall be 2 x 6.
3.01 Conditions of Surfaces - Verify that surfaces to receive rough
carpentry materials are prepared to exact grades and dimensions.
0619-03
0619 - WOOD TRUSSES
PART 3 EXE=ION: (continued)
3.02 Installation:
A. Trusses:
1. Fabricated trusses and sub-assemblies shall be handled with
care so that they are not subject to damage. If the trusses are
to be stock-piled or stored prior to erection, they shall be
set in vertical positions, resting upon temporary bearing
supports and braced so that they will be subjected to no
unusual bending or tipping over.
2. All truss members shall be accurately cut to keep horizontal of
the trusses to a minimum.
3. The permanent structural cross-bracing to ensure the overall
rigidity of the roof system shall be in accordance with the
architectural plans of the building structure.
4. Proper erection bracing shall be installed to hold the trusses
true and plumb and in safe condition until permanent truss
bracing and bridging can be solidly nailed in place to form a
structurally sound roof framing system. All erection and
permanent bracing shall be installed and all components
permanently fastened before the application of any loads.
5. Field erection of !he trusses, including items such as proper
handling, safety precautions, temporary bracing to prevent
topping or dominoing of the trusses during erection, and any
other safeguards or procedures consistent with good workmanship
and good building erection practices, shall be the
responsibility of the general contractor and/or the erection
contractor.
6. Framing anchors and/or truss hangers shall be provided by the
contractor in accordance with the architectural plans.
7. During the entire construction period, all contractors shall
provide means for adequate distribution of concentrated loads
so that the carrying capacity of any one truss and/or component
is not exceeded.
0619-04
0753 - ELASTIC SHEET ROOFING, INSULATION & MEMBRANE FLASHINGS
REFERENCE: Refer to -Section 0180 for explanation of abbreviated
specification format.
1.01 Sco pe - Provide and install.
1.02 Alternate Bids - See 0110.
1.03 Unit Prices - Not required.
1.04 Shop Drawings - Not required.
1.05 Samples -
A. Manufacturer's Literature: Materials description and installation
instructions for system.
B._ Shop Drawings: Details of the conditions encountered on project
bearing statement that details have been prepared, or reviewed,
and approved by the manufacturer's technical staff.
C. Samples: 10-lbs. aggregate ballast.
D. Test Reports: Independent testing laboratories reports stating
compliance with Federal Specifications for each type rigid
polyisocyanurate insulation. Test reports shall be dated wiUn1r)
six months of the product manufacture date.
1.06 Guarantee - Ten (10) year written manufacturer's warranty covering
materials and workmanship.
1.07 Standards - Per contract condition, ASTTM Specifications, Federal
Specifications.
1.08 Testing - Not required.
1.09 Include List -
A. Roofing membrane (adhesive applied)
B. Roof insulation
C. Installation inspection
D. Membrane flashing at perimeter, curbs and penetrations.
1.10 Do Not Include List - Roof blocking (except as noted on drawings),
sheet metal flashing (unless proposed as voluntary alternate).
1.11 Standard of Quality - Firestone, Carlisle, Goodyear, Diversate
General.
1.12 Clean Up - Per contract conditions.
2.01 Manufacturer - Roofing materials shall be by Firestone Industrial
Products Company or approved equal.
2.02 Materials
A. Membrane: Firestone Rubberguard .045" E.P.D.M. (Ethylene Propylene
Diene Monomer).
B. Flashings: .060" thick Firestone Formflash Membrane.
C. 1/2" high pressure recovery board over tapered insulation.
D. Insulation: Expanded polystyrene on flat roof only. Tapered
1/8"/ft., minimum 1" thick at roof edge, maximum 4" thick at,
center of building.
E. Bonding adhesive, splicing cement, lap sealant, water cutoff
mastic, pipe seals, night sealant and pourable sealer - all
manufactured by Firestone Industrial Products Company.
0753-01
0753 - ELASTIC S= ROOFING, INSULATION & MEMBRANE FLASHINGS
3.01 Stored Material: Materials shall not be stored on the site until a
reasonable time before the application of the roofing items. Storage
of roofing materials must be in a dry place. Proper protection for
all materials must be furnished by the contractor. Roofing materials
and roofing insulation must be stored between 60 degrees F. and 80
degrees F. on pallets or wood members and not in contact with the
roof or ground.
3.02 Surface Preparation: The entire area to be roofed shall be inspected.
by the roofing contractor to determine that it is free from debris,
possesses required blocking and is free from other gross
irregularities.
Contractor shall notify the architect in writing of any and all
defects in the receiving surfaces, and work shall not proceed until
such defects have been corrected. Proceeding with installation is
evidence of surface acceptability.
3.03 Protection:
A. Any conditions created by this contractor which shall create a
hazard to the building or it's contents, shall be remedied by Lhe
providing of temporary protection to the interior and exterior of
the building. Such protection shall meet approval. In raisin--
materials alongside finished wall surfaces, protect adjoining
walls with tarpaulins to prevent damage. Roofing contractor shall
be responsible for cleaning soiled surfaces clue to the --
negligence as required.
B. Water cut-offs shall be made by extending the membrane beyond the
insulation and setting the end of the membrane in 12" of Firestone
Night Sealant.
3.04 Installation:
A. Roof Membrane - Roofing and flashing shall only be applied by
factory trained and approved roofing contractors familia'r with the
product and applied in strict compliance with the manufacturer's
instructions. Material shall be homogeneous one-piece loosely laid
roof membrane. Seams shall be made by lapping the membrane a
minimum of three inches, for continuity and integrity, and sealed
with sealant. All seams must be sealed the same- working day.
B. Membrane Flashing - Flashing shall be installed at all vertical
surfaces, roof interruptions and penetrations in accordance with
the manufacturer's currently published drawings and consistent
with job conditions. Extend base flashing up vertical surfaces
not less than 3", except as shown otherwise on the drawings.
3.05 Curb Insulation
A. Apply 3/4" or thicker insulation to mechanical equipment ,,trait
curbs and to other curbs where insulation is not provided with the
unit.
3.06 Adjusting and Cleaning
A. Inspect all work - thoroughly and make corrections iiiimediaLely.
07153-02
0753-- ELASTIC S= ROOFING, INSULATION & MEMBRANE FLASHINGS
PART 3 EXECUTION: (continued)
3.07 Protection
A. The installer shall advise other contractors of recommended
protection for roofing so that the work will be without damage or
deterioration (except for normal weathering) at the time of
acceptance.
END OF SECTION 0753
07539108
BHA10-89
0753-03
0760 - FLASHING AND SHEET METAL
REFERENCE: Refer to Section 0180 for explanation of abbreviated
specification format.
PART 1 GENERAL:
1.01 Scope - Provide and install.
1.02 Alternate Bids - See 0110.
1.03 Unit Prices - Not required.
1.04 Shop Drawings - Not required.
1.05 Samples - Not required.
1.06 Guarantee - 2 years.
1.07 Standards - AISC, AISI.
1.08 Testing - None required.
1.09 Include List -
A. Gravel stops.
B. Metal flashings, reglets and counter flashing.
C. Sealants associated with flashing.
D. Scuppers.
1.10 Do Not Include List - Not applicable.
1.11 Standards of Quality - Colorklad, Foremost, Pac- Clad.
PART 2 PRODUCTS:
2.01 Materials
A. Colorklad flashing to be as manufactured by Vincent Brass and
aluminum, 24 ga. All readily visible items shall be Colorklad,
such as - fascia, scuppers, gravel stops, counterflashing and all
accessories associated with these items shall match.
B. Galvanized steel - ASTM A526 -71, 24 ga. (typical) or as noted.
(Only at unexposed locations.)
C. Solder - ASTM B32 -80, alloy grade 58, 50% tin, 50% lead.
D. Flux - FS O- F -506C, Type I.
E. Asphaltic base paint - FS TT-C -494, Type II.
F. Plastic cement - FS SS- C -153G, Type I.
G. Metal primer - FS TT-P -641, Type II, Moore's Ironclad Galvanized
Primer.
H. Sealant - 707 Butyl Sealant by Protective Treatments, Inc. or
equal.
2.02 Fabrication
A. Fabricate gravel stop, coping and all other flashing sections in
lengths as required for joints at 10' -0" o.c. with 1/2" joints
with 6" splice plates, profile as indicated on the drawings.
B. Fabricate flashing section up to 10' in one piece. For sections
over 10', use sheets as large as are practicable. Fold exposed
edges back, not less than 3/8" and flatten.
C. Form 45 degree drip at bottom of gravel stop, nested over a
continuous hook strip of galvanized steel on building exterior.
D. Fabricate miscellaneous sheet metal items as noted and detailed on
drawings.
0760 -01
0760 - FLASHING AND Sl= METAL
PART 3 EXECUTION:
3.01 Flashing
A. Install flashing as indicated and as necessary to obtain
weathertight conditions.
B. Lap ends not less than four inches, set in plastic cement. Flash
continuously around internal and external comer. Extend flashings
not less than eight inches up onto vertical surfaces unless
otherwise shown.
C. Extend counterflashings into sawed masonry joints at least 1 1/2".
Secure with lead plugs and point with sealant.
D. Install flashings around curbs on all roof top equipment, if not
supplied with equipment.
3.02 Gravel Stops
A. Flash as indicated and as necessary to obtain weathertight
condition.
B. Flash continuously around internal and external corners.
3.03 Protections
A. Where sheet metal abuts or members into adjacent dissimilar
materials, the juncture shall be executed in a manner t17--1t will
prevent electrolysis between the materials.
B. Protect metals from corrosion when embedded in, or in contact
with, other materials.
3.04 Miscellaneous Sheet Metal
A. Install all miscellaneous sheet metal items as shown on the
drawings. When items are exposed, workmanship shall be of the
highest quality.
END OF SECTION 0760
07609108
BHA10-89
0760-02
0761 - PREFORMED METAL ROOFING, FASCIA AND SOFFIT SYSTEM
REFERENCE: Refer to Section 0180 for explanation of abbreviated
specification format.
1.01 Scop - Provide and install.
1.02 Alternate Bid - See 0110.
1.03 Unit Price - Not required.
1.04 Shop Drawing - Required.
1.05 Samples - 2 sets - 3" x 6" samples of prefinisbed sheet metal for
color selection.
1.06 Guarantee -
A. 2 year weather tightness warranty from applicator.
B. 20 year finish guarantee from manufacturer.
1.07 Standards - Per contract conditions.
1.08 Testing - Not required.
1.09 Include List -
A. Preformed metal fascia, roof and soffit panels.
B. Structural hat channel framing system.
C. Sealant associated with system.
D. Flashing associated with preformed metal roof, fascia and soffit
panels.
E. All accessories, attaching devices, and trim pieces (color matched
where exposed to view) required or shown to provide a weather
tight system.
1.10 Do Not Include -
A. Interior steel stud system, structural light gauge metal joists
and studs.
B. Metal roof edge flashing.
1.11 Standards of Qualit - ColorKlad, PAC-CLAD, AEP/SPAN.
1.12 Clean Up - Required.
2.01 Manufacturer - Sheet metal fascia, roof and soffit materials shall be
manufactured by ColorKlad or approved equal.
2.02 Design of Preformed Metal Fascia, Roof and Soffit Panel'Svstem
A. This contractor shall be responsible for the design of all, metal
panel installations including all supports, components, and
fasteners noted on the drawings or specified by this section.
System shall be designed to resist applicable building code 1,;ind
and uplift forces for the spans and points of achievement. System
shall be designed to accommodate thermal movement.
2.03 Materials
A. Prefinished Sheet Metal:
Galvanized carbon
steel sheets,
21
gauge, Kynar finish. One
pre-formed pan system.
Standing seam
Lit
18" o.c. with double hem
standing seam cap.
Color shall
be
selected from manufacturers standard finshes
and protected
by
plastic film.
B. Sealant shall comply with
NAM�T SS-la-68.
01161-01
0761 -
PREFORMED METAL ROOFING, FASCIA AND SOFFIT SYSTEM
PART 2
PRODUCTS: (continued)
2.03 Materials (continued)
C.
Flashing shall be shop formed as shown on details
and on shop
drawings to provide weather tightness from sheets or
roll material
to match quality and color of preformed panels.
D.
Framing: Galvanized steel hat channels, 24 gauge,
spacing as
required to meet design and code requirements.
E.
Provide color matched fasteners where fasteners are
exposed to
view.
F.
Provide color matched touch-up paint.
G.
Miscellaneous supports: As necessary to secure metal
panels to
building structure.
H.
Bituminous Paint: Aspha-1t emulsion, ASTIM D 1187-66
(1910),
Type A.
I.
Felt paper, 30#, and red resin paper over felt.
PART 3
MCUTION:
3.01 Inspection
A. This contractor will be responsible for inspecting the surfaces to
which the systems will be attached to insure that proper support
structure has been provided by others in accordance with -he
construction documents. Any discrepancies should be brought to
the attention of the architect prior to the start of inst 'allin-g
work. By proceeding with the installation of the panel system,
this contractor accepts the job site conditions.
3.02 Preparation
A. Coordinate the work with other work f(
items which make up the entire
weatherproofing or waterproofing. It
be permanently watertight, and not
manufacturer's published limitations.
Dr the correct sequencing of
membrane or system r) f
is required that the system
deteriorate in excess of
3.03 Installation
A. This contractor shall take proper precautions when installing roof
soffit, and fascia systems to protect work already in place to
maintain weather tight conditions.
B. Install roof and soffit panels as detailed.
C. Fasten panels to subframing with concealed fasteners as
recommended by manufacturer. Surface exposed fasteners should be
utilized only when concealed fastening is impossible. Surface
fasteners should be as small as possible with minimal exposed
heads.
D. Install all flashings, closures, and trims required.
F. Install work with lines and corners of exposed units true and
accurate. Form exposed faces flat and free of buckles, excessive
waves and avoidable tool marks, considering the temper and
reflectivity of the metal. Provide uniform, neat seams.
F. Protect metal surfaces which are to be in contact with dissimilar
metals, with a coat of bituminous paint specified to prevent,
galvanic or corrosive action. Coating shall riot-, extend onto
exposed surfaces.
G. At completion of work, remove all scrap material from building stn(
site.
07 61 -02
0761 - PREFORMED METAL ROOFING, FASCIA AND SOFFIT SYSTEM
PART 3 EXMJITION: (continued)
3.03 Installation (continued)
H. Remove protective plastic film immediately after installation of
prefinished flashings and miscellaneous fabrications.
I. Remove all flux, scraps and dirt immediately. Excess flux shall
be neutralized with a 5 to 10 percent solution of washing soda and
surface drenched with clean water.
J. Field touch-up marred or abraded surfaces with paint provided.
1. Replace sections of flashiri-O or trim, which exhibit abrasions
on the face of surfaces exposed to view from finished grade.
END OF SECTION 0761
07619108
BH-Alo-89
0761-03
0782 - UNIT SKYLIGHTS
REFERENCE: Refer to Section 0180 for explanation of abbreviated
specification format.
PART 1 COS[qII.:
1.01 Scope - Provide and install.
1.02 Alternate Bid - See 0110.
1.03 Unit Price - Not required.
1.04 Shop Drawing - Required.
1.05 Samples - Not required.
1.06 Guarantee - 1 year.
1.07 Standards - ASTM ' AAMA.
1.08 Testing - Not required.
1.09 Standards of Quality - Wasco, APC, Dur-Red, Naturalite.
2.01 Materials
A. Skylights to be PALM continuous Ridgelite Model No. 530 by
Hillsdale Industries, Inc. or equal. This acrylic sealed single
dome shall be clear with a 6063-T5 extruded altuninum curb frzm
and dome elevating leg with support gasket and retaining fr,-Urie.
B. Refer to Drawings for size and location.
3.01 Installation - as per manufacturer's recommendations.
A. Install on top of wood curb in continuous sealant 'bed.
B. Secure with 1/4" toggle bolts or attachment screws as per
manufacturer's instructions.
END OF SECTION 0782
07829108
BHAIO-89
0782-01
0790 - SEALANTS
REFERENCE: Refer to Section 0180 for explanation of abbreviated
specification format.
1.01 Scope - Provide and install.
1.02 Alternate Bids - See 0110.
1.03 Unit Prices - None required.
1.04 Shop Drawings - None required.
1.05 Samples - Not required.
1.06 Guarantee - Per contract conditions.
1.07 Standards - Per contract conditions.
1.08 Testing - None required.
1.09 Include List
A. Joints around exterior doors.
B. Joints around any item recessed or set into masonry or concrete.
E. Joints at control and expansion joints.
G. Joints required to provide a water and weather tight construction.
1.10 Do Not Include List
A. Sealants associated with membrane roofing and flashing.
1.11 Standard of Quality
A. Parr, Inc.
B. Dow Corning.
1.12 Clean Up - Per contract conditions.
... •'•0�
2.01 Materials
A. Exterior sealant - exposure beads to be Mono by Tremco.
B. Interior sealant - exposure beads to be Mono by Tremco.
C. Back -up - Tremco joint backing (round profile) by Tremco
Manufacturing Co.
D. Sealant primer - as recommended by manufacturer of sealant, when
required.
E. Color by architect.
F. Fireproof sealant - Flameseal Fire Stop Putty by Nelson Electric.
G. Acoustical Sealant - Tremco or United States Gypsum.
3.01 Preparation
A. Examine all surfaces that are to be caulked. Report unsatisfactory
conditions and do not proceed until correction has been properly
made.
B. Properly prepare joints and surfaces to receive sealant compound.
Mask or protect as necessary to prevent smearing of adjacent
surfaces.
C. Remove dust, moisture, rust, grease, glaze, and loose materials
that could interfere with adhesion of compound.
D. Rake joints as necessary to obtain minimum of 1/4" for sealant.
Maintain sealant width of not more than one inch.
0790 - SEALANTS
PART 3 EXECUTION: (continued)
3.02 Installing
A. Pack joints more than 3/4" deep, and joints not properly backed,
with back-up to within 3/4" of adjacent surfaces.
B. Prime surfaces if recommended for best adhesion and apply compound
with sufficient pressure to completely below face of adjacent
sides of the joint. Sealant joints to be completely weathertight
and securely adhered at both sides.
C. Complete joint sealant before finish painting is started. Remove
any smeared sealant and clean adjacent surfaces with proper
solvent cleaner.
D. Do not apply sealant when surrounding temperature is below 40
degrees F. or when excessive moisture is present.
E. Provide anti-tack agent over beads if required for dust free
surfaces.
F. Seal air tight all penetrations of fire area separation walls,
tenant party walls, and tenant/corridor walls.
END OF SECTION 0790
07909108
BHA10-89
MUM
0811 - HOLLOW METAL DOORS AND FRAMES (WELDED TYPE)
REFERENCE: Refer to Section 0180 for explanation of abbreviated
specification format.
1.01 So - Provide and install.
1.02 Alternate Bids - See 0110.
1.03 Unit Prices - None required.
1.04 Shop Drawings - Required.
1.05 Samples - None required.
1.06 Guarantee - Per contract conditions.
1.07 Standards - ANSI.
1.08 Testi - None required.
1.09 Include List - See plan and details.
1.10 Do Not Include List Glass & glazing.
1.11 Standards of Qualit Pioneer Industries, Trussbilt,
Mesker, Kewanee, Steelcraft, Curries.
1.12 Clean Up - Per contract conditions.
1.13 Co-operation - Co-operate with other contractors
provisions for hardware and other related items.
Glewwe Metals,
to provide
a. . SO
2.01 Basic Material
A. Sheet steel for frames shall
steel.
B. Sheet steel for doors shall
steel.
be hot rolled prime quality caps on
be cold rolled stretcher level sheet
2.02 Frames and Doors
A. All hollow metal frames and doors are to be stock or custom made.
B. Frames 16 ga. (welded type)
C. Doors 18 ga.
D. Hollow metal frames are to be of sizes and configurations shown on
the drawings.
E. Provide frame reinforcing shown as required, integral with frames.
2.03 Fabrication
A. Metal Frames
1. Hollow metal door frames, as shown on the drawings shall be
formed of gauges as specified for exterior or interior
locations.
2. The frames shall be mortised, reinforced, drilled and tapped
for all mortise hardware except that the drilling tapping for
surface door closers and door closer brackets shall be done in
the field by the contractor.
3. Furnish three (3) gum rubber bumpers for single frames, two
(2) for pairs, equal to Glynn Johnson's GJ64.
4. Provide steel hinges reinforcements 3/16" x 1 1/2" x 9" long.
Hinge and strike plate cutouts to be protected with pressed
steel cover boxes spotwelded to the back of the frames behind
these mortises.
0811-01
PART 2 PRODUCTS: (continued)
2.03 Fabrication (continued)
A. Metal Frames (continued)
5. Provide 12 gauge x 14" steel one piece channel reinforcing in
head frame for closers and 3/16" x 1 1/2" x 4 steel
reinforcing at lock strikes.
6. Frames shall be neatly mitered at corners and continuously
fully welded and ground smooth for an invisible joint.
7. Provide angle clips at bottom of all frames with punched holes
for securing the frames to floor construction. Also provide 16
gauge spreader channel at bottom of all frames to avoid
twisting of frames in shipment.
8. Provide appropriate wall anchors as detailed, with a minimum
of four (4) anchors per jamb for frames up to V-V high,
adding extra anchor for each additional 16" or fraction
thereof. Anchors to suit wall and/or U.L. label 'conditions,
with masonry anchors 16 gauge corrugated type, 10" long.
9. All materials, after a thorough cleaning, shall be given one
coat of baked-on red oxide prime covering inside as well as
outside surfaces.
10. All hardware items shall be installed at the job site by the
contractor. Hardware provisions to be made from templates,
furnished by the finish hardware supplier.
11. All material shall be pre-assembled at the factory in the
largest size units permitted by shipping restrictions for
minimum assembly of related parts in field.
12. Should field splicing be required it shall be made by
qualified personnel of he manufacturer and shall be done to
the satisfaction of the architect.
B. Metal Doors
1. Hollow metal full flUsh doors except as otherwise noted (and
transom panels where indicated), shall be a 1-3/4" thickness
constructed of 16 gauge, full cold rolled, stretcher level
sheet steel, spotwelded to a truss-shaped or rigid steel
channel core vertically 6" o.c. and insulated with 8 pound
density mineral wool.
2. Doors shall be mortised and reinforced for hardware furnished
under finished hardware section of the specification.
Reinforcements for hinges, locks, closers, etc. shall be the
manufacturer's standard.
3. Reinforce doors for surface items such as semi-concealed
closers, brackets, surface holders, door stops, etc. Drilling
and tapping of these surface items to be done in the field by
general contractor.
4. Doors shall be flat and true with a flatness tolerance of
1/16" in all directions, including diagonal. Doors shall be
furnished with 1/8" bevel on edges.
0811-02
0811 - HOLLOW METAL DOORS AND FRAMES (WELDED TYPE)
PART 2 PRODUCTS: (continued)
2.03 Fabrication (continued)
B. Metal Doors (continued)
5. All doors, etc. shall be thoroughly cleaned of rust, grease,
and other impurities and all welds shall be ground smooth.
Metallic tiller shall be ground smooth. Metallic filler shall
be applied where necessary to fill construction joints and
ground to a smooth surface. Manufacturer's standard prime coat
shall be applied, with interior surfaces of exterior doors
primed before fabrication. Exterior doors shall be constructed
in such a manner that the top and bottom are flat and sealed.
2.04 Protection - Paint on doors and frames shall be thoroughly dry and
delivered to project in sturdy crating and stored in a manner to
avoid cracking before installation. After installation, protect from
abrasions and other damage until acceptance of the building.
PART 3 EXECUTION:
3.01 Installation
A. Examine surfaces and openings that are to receive metal doors or
frames. Report unsatisfactory conditions and do not proceed until
corrections have been made.
B. Where doors are indicated to open against an intersecting wall,
and scheduled to receive a surface mounted, standard exposed
closer with a regular arm, the jamb of frame shall be set not less
than 6" from face of wall.
C. Provide temporary wood spreaders at mid-height of all door frames
and cased opening frames while masonry walls are being
constructed. Spreader shall be out to fit frame at head of frame.
Leave all spreaders in place until mortar sets. Check frequently
to insure that frame is plumb and level. Fill all door frames in
masonry solidly with grout, as the work progresses, including head
frame.
I M a n C I O
0811-03
0840
- ALUMINUM ENTRANCES AND STOREFRONTS
REFERENCE: Refer to Section 0180 for explanation of
abbreviated
specification format.
PART
I GENERAL:
1.01
Sc - Provide and install.
1.02
Alternate Bid - See 0110.
1.03
Unit Price -_None None required.
1.04
Shop Drawing - Required.
1.05
Samples - None required.
1.06
Guarantee - Required - 2 years.
1.07
Standards - AA, AAMA, NAAMM.
1.08
Testing - None required.
1.09
Include List -
A. Sealant associated with aluminum doors and frames, amd
storefront.
B. Hardware as scheduled below.
C. Coordination with the general contractor for
closers,
weatherstripping, and thresholds, etc.
D. Installation of Glass and Glazing by Aluminum
Storefront
Contractor (Refer to 0880).
E. Aluminum Louvers by Aluminum Storefront Contractor
(Refev to
1020).
1.10
Do Not Include - Cylinder locks (by Owner).
1.11
Standards of Qualit - Kawneer Mfg., Inc.
PART 2 PRODUCTS:
2.01
Materials
A. All aluminum doors, entrance frames and window frames shall be
extruded from 6063 T5 alloy.
B. Finish to be #40 dark bronze.
C. Sealant to be Mono by Tremco or approved product as recommended by
manufacturer.
2.02 Doors
A. Medium Stile "350" doors with 1/4" aluminum panel (.050 skin both.
sides), as shown on the drawings.
B. All exterior doors shall have surface applied threshold
weatherstripping.
2.03 Entrance Frames and Fixed Aluminum Windows
A. 1-3/4" x 4 1/2", Kawneer 450, Tri-fab, for entrance frame systems
as shown and detailed on the drawings.
B. Door frames shall be pile weatherstripped on all door edges.
C. Furnish thresholds for all door openings.
2.04 Hardware - US26D finish
A. Manufacturer's standard door hardware package including but not
necessarily limited to push, CS-9 pull, 1-1/2 pr hinges each door,
provision of cut-out for cylinder dead lock, LCN 4040 closer with
hold open, flush bolts, threshold, etc. 'Refer to drawings
regarding special threshold for door E-101, Equipment Building.
0840 - ALUMINUM ENTRANCES AND STOREFRONTS
a • .
3.01 Aluminum Door - Main frame assembly and hardware shall be installed
according to manufacturer's recommendations, and anchored securely at
jambs, head and sidelite sills. Seal with specified sealant per
manufacturer's recommendations to form watertight joint between frame
and surrounding construction.
3.02 Protection and Cleaning - After installation, metal surfaces of the
walls, windows, panels, and entrance shall be cleaned on both
interior and exterior of all mortar, plaster, paint, and other
contaminants. After being cleaned, all work shall be protected
against damage until it is accepted by the architect.
� / • • m
I . 1 i
0852 - ALUMINUM WINDOWS
REF=CE: Refer to Section 0180 for explanation of abbreviated
specification format.
PART 1 GENERAL:
1.01 Sco pe - Provide and install.
1.02 Alternate Bid - None.
1.03 Unit Price - None required.
1.04 Shop Drawing - Required.
1.05 Samples - None required.
1.06 Guarantee - 1 year.
1.07 Standards - ANSI, A*11A.
1.08 Testing - Required. Data to be submitted with shop drawings.
1.09 Include List - Glazing.
1.10 Do Not Include - Sealant.
1.11 Standards of Qualit - Acorn.
1.1.2 Clean Up - Does not apply.
UM 9 F
2.01 Materials
A. Windows shall be thereto -break fixed, electro-static paint bronze
finish, double -hung 2500-A2 Series, as manufactured by Acorn
Building Products or approved equal.
B. Sizes shall be as shown on drawings.
C. Furnish with screens at exterior windows.
D. Furnish windows with clear insulating glazing, installed.
5/8" or 7/8" as is standard for manufacturer.
E. Furnish with or without nailing flanges as required by the
details.
PART 3 EXECUTION:
3.01 Fabrication
A. Windows and doors are to be fabricated in accordance �,�ith
manufacturer's standard specification.
B. Factory glaze in vinyl glazing channel,
3.02 Installation
A. Install plumb and level, secure and weatherti-ght in accordance
with manufacturer's recommendations. Windows to be placed as
shown on the drawings and secured with or without nailing flanges
as required.
END OF SECTION 0852
08529108
BHA10-89
0852-01
0870 - FINISH HARDWARE
REFERENCE: Refer to Section 0180 for explanation of abbreviated
specification format.
1.01 Scope - Provide and install.
1.02 Alternate Bids - See 0110.
1.03 Unit Prices - None required.
1.04 Shop Drawings - Required. Furnish complete hardware schedule showing
all manufacturers' number, function, and finish of all hardware
furnished to the architect for review. Furnish keying schedule after
1.05
1.06
1.0 - 1
1.08
1.09
1.10
1.11
1.12
1.13
1.14
determination of requirements.
Samples - Not required.
Guarantee - One year.
Standards - Federal Specification FF-H-106A,
101.
Testing - Not required.
Include List - Interior doors only,
Do Not Include List Exterior aluminum door
Standards of Quality See Part 2.
Clean Up - Per contract documents.
UL, DIM, NTT)A 80, NFP-A
hardware.
Packaging of Materials - Hardware shall be properly wrapped in
separate packages, complete with all trim, screws, and fasLerdng
devices, for each and every door, and distinctly labeled and nurtibere(3.
for each opening. A typewritten schedule shall accompany each
shipment in conformance with the approved and filed schedule
submitted by the contractor. Provide information for proper hardware
positioning of each type of assembly with the typewritten schedule.
Delivery of Materials - All hardware shall be delivered from the
factory, to offices of the subcontractor designated to install same,
or to the job site for installation by the General Contractor.
Templates will be required for all hardware applied to hollow metal
doors and frames.
1.15 Quality Control - Workmanship and finish of all hardware shall be
free from all blemishes and defects. All defective pieces shall be
rejected, even if they may be set in place before the defect is
discovered. Defective products shall be removed and new pieces-
substituted in their place by this contractor without extra cost to
the owner, including labor to remove and replace the various items.
'fl-ie correct number of screws and/or fasteners, in proper size,
finish, and material corresponding with the hardware to be fastened,
shall be furnished with each piece of hardware. Furnish products of
only one manufacturer for each type of hardware, where possible.
6, .
2.01 Materials
A. Furnish and install finish hardware as specified for the
allowances listed below:
Hollow metal doors - $250.00 per. opening.
0870-01
0870 - FINISH HARDWARE
PART 2 PRODUCTS: (continued)
2.01 Materials (continued)
B. The manufacturers listed below are approved for use. Finishes
shall be as indicated.
ITEM MANUFACTURER FINISH
Butt Hinges McKinney, Stanley, Hager Exterior-US32D
Interior-US26D
Locks Schlage, Yale, Corbin, Russwin US26D
Closers Norton, Yale, Dorma Aluminum
Protective Plates Quality, Brookline, Cipco, US32D
Hiawatha
Thresholds, Reese, Pemko, National Guard Aluminum
Jamb Gaskets
2.02 Butt Hinges
A. (2) hinges per leaf for openings through 60" high. Add (1) hinge
per leaf for each 30" or fraction in height.
B. Standard weight for exterior outswing entrance doors.
C. Size: 4 1/2" X 4 1/2" for 1 3/4" thick doors.
2.03 Locks
A. Cylinder locks shall be furnished by the Owner. Cut-outs shall be
provided by this Contractor.
2.04 Closers
A. Determine closer size and mounting method in accordance with
manufacturer's recommendations. Mount on interior side of
exterior doors.
2.05 Protective Plates
A. Furnish 16 ga., .050 plates as follows:
2" less than width of door and 10" high or as shown on drawings.
2.06 Keying
A. Change key and masterh all lock cylinders as directed by the
Owner to their existing system. Manufacturer to maintain key
serial number records.
B. Furnish two change keys for each look and three masterk for
each masterkey set.
C. Ship masterkeys to Owner via registered mail.
D. Hardware supplier shall prepare proposed keying schedule for
approval.
2.07 General Description
A. Lever handle locksets with lock one side only will be selected
for Storage Room Doors, Manager's Office and Janitor's Closet.
B. Owner uses "Best" locking and keying system which should be
considered herein.
0,
•
L
3.01 Installation - Install hardware in accordance with manufacturer's
recommendations and instructions.
08710-02
0870 - FINISH HARDWARE
PART 3 EXECUTION: (continued)
3.02 Mounting Heights - Install hardware at mounting heights conforming to
the recommended mounting locations of the Builders' Hardware
Manufacturers Association.
PART 4 SCHEDULE:
4.01 Hardware Schedule
A. The hardware supplier shall provide a schedule for review by the
Architect & Owner. Verification of quantities shall be the
responsibility of the Contractor.
B. For metal doors, provide; butt hinges, locksets, closers,
protective plates and other hardware as required or specified
herein.
C. All hardware shall be provided with appropriate fasteners,
brackets, roses, fillers, extensions, or other items necessary for
the appropriate installation and attachment to the materials onto
and/or into which it is installed.
END OF SECTION 0870
i US i 2
0870 -03
0880 - GLASS AND GLAZING
REFERENCE: Refer to Section 0180 for explanation of abbreviated
specification format.
PART I GENERAL:
1.01 Sco pe - Provide and install.
1.02 Alternate Bids - See 0110.
1.03 Unit Prices - Not required.
1.04 Shop Drawings - Not required.
1.05 Samples - Not required.
1.06 Guarantee - I year.
1.07 Standards - Per contract conditions.
1.08 Testing - Not required.
1.09 Include List - Glazing of doors, windows, fixed interior window, by
Aluminum Storefront Contractor.
1.10 Do Not Include List Not applicable.
1.11 Standards of Qualit ASG Industries, Inc.
1.12 Clean Up - Required.
1.13 Handling and Protection
A. Handle glazing materials to avoid injury to persons and to avoid
damage to materials or to work in place. Satisfactorily repair or
remove and replace work that has been damaged.
B. All shall not be approved until substantial completion.
C. Protect glass from scratching, breaking, or other injury while
storing, during installation, and until work is completed.
1.14 Measurements - All sizes of glass shall be taken from the actual
frames. Sizes shown on the drawings are approximate, to be used for
estimating only.
PART 2 PRODLLM:
2.01 Materials
A. 1/4" tempered obscure by PPG or equal.
B. Glazing
1. Neoprene setting and spacer blocks..
2. Extruded polybuthene tape sealant such as Parflex Tape by Parr,
Inc., or Tremco 440 by Tremco Co.
3. Sealant - Mono by Tremco Manufacturing Co., or Uni-Par-Seal by
Parr, Inc.
4. Glazing compound - Tremco "Tremco, Tremglaze" or approved
equal, olco-resinous compound.
C. Laminated safety glass may be substituted for tempered subject to
approval of the architect..
2.02 Glazing size and location - Refer to drawings for openings to be
glazed and the glass to be used.
PART 3 EXECUTION:
3.01 Installation
A. Set all glazing in the best possible manner and in such a way that
there will be equal bearing the entire width of the pane.
B. All glazing setting blocks, spacers, tape, etc. shall be set in
accordance with the manufacturer's recommendations.
af-2-011 "I
0880 - GLASS AND GLAZING
PART 3 EZEION: (continued)
3.01 Installation (continued)
C. Thoroughly clean all contact surfaces of sash, stops, reglets, and
glass edges of dirt, dust, oil and other foreign matter before
starting glazing.
D. No glazing shall be done when the air temperature is less than 40
degrees F. nor when frost, ice or moisture is on the glazing
surfaces.
E. Provide a seal bead of sealant in bottom corners of all wood frame
to insure against leaks.
F. At the completion of the work of the section, this contractor
shall remove from the building and premises all rubbish and
accumulated matters of whatever nature not caused by other trades
and shall leave work in a clean, orderly, acceptable condition.
G. Install temporary coverings necessary to prevent damage to
finished surfaces during construction.
DI 10 OWN • to ii
1 2•
•221 1
0925 - GYPSUM DRYWALL
REFERENCE: Refer to Section 0180 for explanation of abbreviated
specification format.
1.01 Scope - Provide and install.
1.02 Alternate Bids -See 0110.
1.03 Unit Price - Not required.
1.04 Shop Drawings - Not required.
1.05 Samples - Required for drywall and ceiling texture.
1.06 Guarantee - Per contract conditions.
1.07 Standards - The reference to United States Gypsum Company products or
standards in this specification shall be taken as intending to mean
and specify the products or standards described, or any other equal
thereto in quality, finish, and durability, and equally as
serviceable for the purpose for which it is or they are intended; and
this quality shall be determined by the architect and he alone shall
be the sole judge as to what material or services will be accepted.
Other products shall meet requirements and recommendations of
applicable portions of standards listed:
A. American Society for Testing and Materials - ASTM
B. Federal Specifications - FS
C. Painting and Decorating Contractors of America - PDCA
1.08 Testing - Not required.
1.09 Include List
A. Drywall adhesive.
B. Coordination with 0610 regarding wood blocking.
1.10 Do Not Include List -
A. Painting specified in 0990.
B. Wood framing.
1.11 Protection - This contractor shall protect adjacent ceiling, wall,
and floor finish materials in place prior to the installation of
drywall and shall properly clean or replace all such materials
damaged by his neglect. This contractor shall protect his texturing
and provide the necessary touch-up prior to final completion. This
contractor shall provide all scaffolding, staging, lay drop cloths,
etc. necessary for proper execution of his work.
1.12 Clean Up - Required.
9 , . &
2.01 Materials - The following materials herein specified are manufactured
by United States Gypsum Co., unless otherwise indicated.
A. Ceilings
1. 5/8" type 'X' Gypsum Board.
2. Apply 1 layer to 2 x framing spaced at 16" o.c.
0925-01
0925 - GYPSUM DRYWALL
PART 3 EXECUTION:
3.01 Wallboard Erection
A. Gypsum wallboard to be applied as required by Testing Agency
rating.
B. Wallboard shall be applied with type 'W' drywall screws spaced in
accordance with USG recommendations. When required, insulation
shall be installed prior to erection. Screws shall be staggered
on adjoining edges.
C. Fasten gypsum board beginning at the center and work towards the
outer edges. Hold the board firmly against the supports while
fastenings. Locate fasteners opposite each other on adjacent ends
and edges. Fasteners at edge of boards shall be located 3/8" to
1/2" to the edge.
D. Openings for electrical devices, piping, grilles, and registers
shall be accurately located and neatly made to closely fit the
devices and be completely covered by plates and escutcheons.
E. Coordinate installation and finishing of gypsum board with work of
other trades. If requested, provide early installation and taping
of gypsum board.
F. Panel attachment -Roof /Ceiling - Attach face layer parallel with
framing. Stagger fact layer joints 10" minimum from base layer
joints. Face layer to be screw attached 12" o.c.
3.02 Joint Treatment
A. All joint compounds shall be USG or equal, premixed or mixed in
strict accordance with manufacturer's recommendations.
B. Taping
1. All purpose compound shall be applied in a thin uniform layer
to all joints and angles to be reinforced. Reinforcing tape
shall be applied immediately, centered over the joint and
sealed into the compound. Sufficient compound, approximately
1/64" to 1/32" must remain under the tape to provide proper
bond. A skim coat shall immediately follow tape embedment but
not to function as a fill or second coat. Tape shall be
properly folded and embedded in the angles to provide a true
angle.- The tape or embedding coat must be thoroughly dry prior
to application of the fill coat.
2. All purpose compound shall be applied over the embedding coat,
filling the board taper flush with the surface. The fill coat
shall cover the tape and feather out slightly beyond the tape.
On joints with no taper, the fill coat shall cover the tape and
feather out at least 4" on either side of the tape. No fill
coat is necessary on interior angle. The fill coat shall be
thoroughly dry prior to application of the finish coat. Taping
compound need only have hardness.
0925 -02
0925 - GYPSUM DRYWALL SYSTEM AND SPRAYING
PART 3 EXECiP1'ION: (continued)
3.02 Joint Treatment (continued)
B. Taping (continued)
3. Topping compound or all purpose compound shall be spread evenly
over and extended slightly beyond the fill coat on all joints
and feathered to a smooth uniform finish. Over tapered edges,
the finished joint shall not protrude beyond the plane of the
surface. All taped angles shall receive a finish coat to cover
the tape and taping compound, providing a true angle. Where
necessary, sanding shall occur between coats and following the
final application of compound to protrude a smooth surface
ready for decoration.
C. A taping or all purpose type compound shall be applied as the
first coat to all fastener depressions. This shall be followed by
a minimum of 2 additional coats of topping or all purpose
compound, leaving all depressions level with the plane of the
surface.
D. All corners and edges, durabead, and control joint shall be
concealed by at least two coats of USG all purpose compound. When
completed, the compound shall extend 8" to 10" from edge of
exposed metal nosing. Compound shall be finished as above.
END OF SECTION 0925
09259108
BHA10 -89
0925 -03
0930 - CERAMIC TILE
REFERENCE: Refer to Section 0180 for explanation of abbreviated
specification format.
1.01 Sco pe - Provide and install.
1.02 Alternate Bid - See 0110.
1.03 Unit Price - None required.
1.04 Shop Drawing - None required.
1.05 Samples - Provide color samples.
1.06 Guarantee - Per contract conditions.
1.07 Standards - ANSI, TCA. (Current Handbook)
1.08 Testing - None required.
1.09 Include List - Ceramic tile floors, base and walls.
1.10 Do Not Include - Does not apply.
1.11 Standards of Qualit - Romany Spartan., American Olean, Winburn.
1.12 Clean Up - Per contract conditions.
2.01 Material (based on American Olean Tile Co.)
A. Floor - Ceramic mosaics shall be 2" x 2", price group 3.
B. Base - Ceramic mosaics coved to match floor, 5" high total.
C. Walls - 4 1/4" x 4 1/4" matt glazed tile.
D. Grout - Hydroment joint filler.
E. Color as selected by owner.
F. Provide matching trim pieces as required.
3.01 Installation
A. Floor tile and trim TCA F113.
B. Base, interior walls TCA W243, 244.
C. Slope floors to drains, true to plane.
D. Expansion joints - provide expansion joints as recommended by the
manufacturer.
E. Any deviations depressions, ridges, humps, etc. or other defects
that would prevent a satisfactory installation of ceramic tile
true to intended plane shall be filled with Floorstone, or
Sonnocrete, sanded down or otherwise leveled to proper plane,
ready to receive new tile installation.
F. Accurately cut tile to fit around pipes, fixtures, etc., and grind
cut edges before installing.
G. Joints between the shall be uniform in width (approximately 1/16"
wide) with the joints open for the full depth (thickness) of the
tile.
H. Install grout in accordance with the manufacturer's
recommendations, wiping away excess or smeared grout from the tile
surface before it starts to set.
I. Use care in grouting tile to avoid smearing grout over face of
tile. Apply wax to ceramic the face before grouting with fascia
sealer grout.
0930-01
0930 - CERAMIC TILE
PART 3 EXECLNION: (continued)
3.01 Installation (continued)
J. Damp cure portland cement and sand grout for a minimum of three
days using polyethylene.film and wetting tile thoroughly on the
second day.
K. Any inferior workmanship, cracked tile, poorly pointed joints,
shall be replaced or corrected as directed by the architect.
3.02 Cleaning
A. Ceramic tile surfaces shall be cleaned in accordance with the
latest recommendations of the "Tile Manufacturer's Association,
Inc." and/or the "Ceramic Tile Council."
END OF SECTION 0930
09309108
BHA10-89
0930-02
0970 - SPECIAL FLOORING
REFERENCE: Refer to Section 0180 for explanation of abbreviated
specification format.
1.01 Scope - Provide and install.
1.02 Alternate Bids - See 0110.
1.03 Unit Price - Not required.
1.04 Shop Drawi - Not required.
1.05 Samples - Required to select colors.
1.06 Guarantee Per contract conditions.
1.07 Standards
A. Manufacturer's verification of flame spread 25 maximum and 125
maximum smoke developing for other areas will be required prior to
signing of con
1.08 Testing - Not required.
1.09 Include List - As specified below.
1.10 Do Not Include List -
1.11 Standard of Qualit - See spec. below.
1.12 Clean Up - Required.
1.13 Protection - Install necessary covering for surfaces that may have
traffic during construction period.
lvms &
2.01 Materials
A. Ceram-tex Epoxy Broadcast Granular Flooring as manufactured by
Ceram-Traz Corporation, Osseo, Minnesota.
B. Primer shall be as recommended by the manufacturer of the epoxy
base granular quartz flooring.
C. Epoxy base granular quartz flooring shall be epoxy based material
mixed to a mortar consistency with quartz granules seeded in the
mix. Floor shall be a non-slip surface for wet foot traffic.
Texture of floor is subject to approval of the Architect.
D. Sealer shall consist of an over-coat of clear epoxy.
3.01 Installation
A. If concrete floor surfaces are irregular, rough, or has low spots,
they shall be resurfaced to a level, smooth, finish with a
latex-type underla3,ment similar to Armstrong 5 -170 Flormastic or
approved equal.
B. General: Comply with manufacturer's instructions for the
particular conditions of application. If printed instructions are
not available or do not apply to the project conditions, consult
the manufacturer's technical representative for specific
recommendations before proceeding with the work.
C. Preparation of substrate shall be in accordance with
manufacturer's recommendations.
1. Broom or vacuum all substrate surfaces prior to application of
any epoxy base granular quartz flooring.
2. Moisture content of concrete substrate, building air
temperature and relative humidity must be within limits
recommended by manufacturer.
0970 -01
0970 - SPECIAL FLOORING
PART 3 EXECUTION: (continued)
3.01 Installation (continued)
D. Primer: Primer shall be applied to all substrate surfaces and
shall be applied in accordance with manufacturer's
recommendations.
E. Epoxy base granular quartz flooring shall be trowel applied over
primer in accordance with manufacturer's recommendations, and
shall be applied to not less than 1/8" thickness.
F. Sealer: After epoxy base flooring has cured, apply sealer coat in
strict accordance with manufacturer's recommendations.
G. Protection: After application, protect all epoxy base flooring
and cove base from damage by use of heavy Kraft paper or other
covering.
H. Finishing: After completion of the project and just prior to the
final inspection of the work, thoroughly clean all epoxy base
flooring and cove and leave in perfect condition.
END OF SECTION 0970
09709108
BHA10 -89
1• / i
0990 - PAINTING AND DECORATING
REFERENCE: Refer to Section 0180 for explanation - of abbreviated
specification format.
1.01 Scope - Provide and install.
1.02 Alternate Bids - See 0110.
1.03 Unit Prices - None required.
1.04 Shop Drawings - None required.
1.05 Samples - None.
1.06 Guarantee - Per contract conditions.
1.07 Standards - ASTM, FS, PDCA, SSPC, ASA.
1.08 Testing - None.
1.09 Include List -
A. Interior hollow metal and metal clad doors.
B. Gypsum board ceilings as scheduled.
C. Steel lintels and beams.
D. Wood deck and trusses.
E. All unfinished wood in finished spaces.
F. All miscellaneous metal items.
G. Preparation of surfaces to be painted or finished under this
section.
H. Paint all exterior mounted equipment whether or not factory
finished, aluminum or galvanized, including items furnished by
mechanical and electrical.
I. Paint galvanized metal in finished spaces.
J. Paint exposed surfaces of interior mechanical and electrical
equipment and material, whether or not factory finished, occurring
in finished spaces or adjacent to finished surfaces, including
grills, registers, piping, piping, conduit, panels, and cabinets.
K. Touch up of marred and minor damaged prefinished items.
1.10 Do Not Include -
A. Prefinished doors and trim.
B. All items specified as prefinished.
C. Interior concrete block walls, wood
Equipment Building.
D. Special flooring.
1.11 Standards of Qualit - Benjamin Moore
Glidden (G), Olympic (0), and O'Brien
1.12 Clean Up - Per contract conditions.
trusses, and plywood deck in
(B/M), Pratt & Lambert (P &L),
(O-B).
2.01 Manufacture - Basic product selections are based on Benjamin Moore
Products, unless otherwise noted.
2.02 Materials
A. Materials shall conform to the
standards as listed below.
1. Basic paint materials: Benjamin
2. Raw Linseed Oil: ASTM D234.
3. Boiled Linseed Oil: ASTM D260.
4. Turpentine: ASTM D13.
5. Mineral Spirits: ASTM D235.
6. Orange Shellac: ASTM D237.
latest adopted or tentative
Moore (B/M).
0990-01
0990 - PAINTING AND DECORATING
PART 2 PRODUCTS: (continued)
2.02 Materials (continued)
A. (continued)
7. Drier: ASTM D600.
8. White Lead: ASTM D81.
9. Red Lead: ASTM D83.
10. Putty: FS TT-P-79a, Type 1.
11. Stain and varnish basic materials: Pratt & Lambert.
12. Tinting colors: by manufacturer of basic materials.
2.03 Mixing and Colors:
A. Use factory mixed colors, shades, and tints except as indicated.
Job mixing permitted only with specific approval.
B. All colors will be picked from color chips. If the contractor
uses a different manufacturer or a different type of paint, he
shall be responsible for adjusting the tint to compensate and to
match the approved color chip. If the substrate is such that it
affects the finish color, the contractor shall be responsible for
adjusting the tint to compensate and to match the approved color
chip.
C. A maximum of 15 colors may be utilized.
PART 3 EXECUTION'
3.01 Surface Condition Examine all surfaces to receive finish. Report
any unsatisfactory condition to architect and do not proceed until
corrections are made or assume responsibility.
3.02 Preparation
A. All spaces shall be broom clean before painting is started, and
all surfaces to be painted shall be dry. Temperature of spaces [ri
the building where painting is being done or where it is drying
shall be maintained above 50 degrees.
B. Before painting, all dust, dirt, plaster, grease, and other
extravenous matter which would affect the finished work shall be
removed. Foreign matter on surfaces left by other trades will be
removed by others.
C. The contractor shall properly prepare all new surfaces before
painting by cutting, stopping, filling, light sanding before all
coats, and final dusting with clean tack cloth to insure a smooth
and uniform surface without variation of gloss, suction, or other
blemish. Knots, pith or sapwood shall be treated with shellac and
all nail holes, cracks, open joints and other defects shall be
puttied.
3.03 Priming
A. Where metal is pre-primed and is scheduled for painting, clean,
sand, and spot prime any areas requiring same. Primer to be as
required for metal type.
B. Prime all material as required by manufacturer of finish material.
0990 - PAINTING AND DECORATING
PART 3 EXECUrION: (continued)
3.04 Painting and Finishing
A. All paintings and finishing shall be carefully done and left
perfect. No paint spots shall be left on glass, hardware,
plumbing trim, fixtures, valves, etc., or other finished work.
All workmanship shall be of the very best, with all materials
evenly spread and smoothly flowed on without runs, skips,
blemishes, or sagging of materials and without brush marks or
debris covered marks.
B. All surfaces shall be sanded lightly with #00 sandpaper between
coats.
C. No painting shall be done under conditions unsuitable for
producing a good finish nor while plastering or other "wet" work
is in progress.
D. Wall. surfaces that will be concealed by millwork or casework shall
be finished before the cabinets are installed and similar to other
similar wall surfaces in same room.
E. Coats as specified are intended to cover surfaces perfectly; if
surfaces are not covered, further coats shall be applied at no
extra cost.
F. All brushes shall be clean and maintained in good condition.
G. Allow at least 24 hours between coats unless special paints or
coatings require more or less drying time as recommended by
manufacturer.
3.05 Protection of Work
A. The contractor shall furnish and lay drop cloths in all areas
where painting is being done to protect floors and other work from
damage during the prosecution of his work.
B. Where it becomes necessary in order to execute his work, the
painter shall remove temporary coverings, receptacle and switch
plates, and replace same in a proper manner when uncovered
surfaces have been completed. In case these coverings cannot be
replaced, the painter shall protect the work in some other manner.
All materials used in the building shall be stored where directed
by the architect.
C. Refrain from smoking while working and at all times limit smoking
in restricted areas, such as in storage space for paint products.
D. Store all paint materials in metal covered containers and all
brushes, rollers, paint thinners, etc., shall be stored in covered
metal containers. Used rags shall be removed from the building
each night.
3.06 Schedule of Finishes
A. Exterior and interior miscellaneous metal: thoroughly clean. One
coat B/M Ironclad Retardo Rust Inhibitive Paint. Two coats of B /iyI
Moorglo Enamel.
B. Interior hollow metal frames and doors, other ferrous metal items,
spot prime. Two coats of B/M Satin Impervo.
0990 -03
0990 - PAINTING AND DECORATING
PART 3 EXECUTION: (continued)
3.06 Schedule of Finishes (continued)
C. Piping and Ductwork (in finished spaces)
1. Galvanized: One coat B/M Ironclad Galvanized Metal Primer.
One coat B/M Satin Impervo.
D. Gypsum Board Ceiling - One coat B/M Latex Primer and one coat B/M
semi-gloss enamel.
E. Wood Deck - One coat Moorewood Semi-transparent stain, #081.
F. Interior concrete block - Moorcraft Block Filler 4173 and two
coats Moorcraft Waterborn Acrylic Epoxy Enamel, #279, and
Waterborn Catalyst #2 7 18.
G. Wood Trusses - One coat Moorewood solid color stain, #080.
0 0
0990-04
1016 - METAL TOILET PARTITIONS
REFERENCE: Refer to Section 0180 for explanation of abbreviated
specification format.
• • • � •
1.01 Scope - Provide.
1.02 Alternate Bid - See 0110.
1.03 Unit Price - None.
1.04 Shop Drawing - Required.
1.05 Samples - Required for color.
1.06 Guarantee - One year.
1.07 Standards - Per contract conditions.
1.08 Testing - Not required.
1.09 Include List - As shown on drawings.
1.10 Do Not Include - Not applicable.
1.11 Standards of Quality - See below.
1.12 Clean Up - Required.
• . • :,
2.01 Materials -
A. Furnish floor supported, overhead braced, toilet partitions,
shower compartment partitions, dressing cubicles, and wall hung
bracket supported urinal partitions. Partitions shall be as
manufactured by; Accurate Partitions Division of USG, Capitol
Partitions, Inc., Global Steel Products Corp., Sanymetal Products
Co., Inc., or approved equal. Doors: 24" X 58" X 1" thick,
inswinging typical, and 34" wide outswinging for handicapped where
shown. Urinal screen shall be 18" X 42" X 1" thick.
B. Finish shall be baked enamel on clean sheet steel surfaces. Color
shall be as selected from manufacturer's standard colors.
C. Shower Compartments and Privacy Cubicles shall be Presidential
Series Showers, for physically handicapped, as manufactured by
Capitol Partitions, Inc., or approved equal. All walls shall be
1" thick, material impervious to water. All corner connections
shall be made by means of continuous aluminum corner section.
Field caulk as required. Headrail shall be annodized aluminum
with integral shower curtain track.
D. Receptor shall be pre -cast one piece terrazzo 6" high, made of
white cement with black and white marble chips. Receptor
shoulders shall be rabbeted to receive panels. Brass drain shall
be cast integrally and shall provide for a caulked lead
connection, not less than 1" deep to a 2" pipe and have removable
stainless steel stainer plate.
E. Benches shall be solid Poly Pro as manufactured by Capital
Partions, Inc., or approved equal. Benches to have full radius
edges, 10" wide x 1 -1/4" thick.
1016 -01
1016 - METAL TOILET PARTITIONS
PART 3 INSTALLATION:
3.01 Installation
A. Coordinate for blocking and rough openings.
B. Install per manufacturers recommendations.
C. Provide all clips and mounting brackets as required for
installation.
END OF SECTION 1016
a ! : _
i •
1016 -02
D&M'l I I#Jkvj CIL' I ��
REFERENCE: Refer to Section 0180 for explanation of abbreviated
specification format.
1.01 Scope - Provide and install.
1.02 Alternate Bid - See 0110.
1.03 Unit Price - None.
1.04 Shop Drawing - Required.
1.05 Samples - Not required.
1.06 Guarantee - Per contract conditions.
1.07 Standards - Pei contract conditions.
1.08 Testing - Not required.
1.09 Include List - Where indicated on drawings by AlUlPinium Storefront
Contractor.
1.10 Do Not Include - All items covered. by Mechanical.
1.11 Standards of Quality - Airline Products Co., The Airolite Co., Arroi,
United, American Warming and Ventilating Co., Ruskin.
1.12 Clean Up - Per contract conditions.
2.01 Materials -
A. Furnish horizontal adjustable aluminum blade louvers, Model T663,
size as indicated on the drawings as manufactured by Airolite or
approved equal. Louver shall be 4" deep, 45 degree blade angle,
5" centers (blade spacing), chain operated, baked enamel finish.
B. Provide all required fasteners.
PART 3 INSTALLATION:
3.01 Installation -
A. Install per manufacturer's recommendations in aluminum frFune
system.
B. Coordinate setting of louver with other trades. Set plumb, level
and in proper alignment with adjacent work. Use concealed
anchorages wherever possible.
END OF SECTION 1020
10209108
BHA10-89
1020-01
��C,E.: Refer to Section 0I80 for explanation of abbreviated
specification format.
PART 1 GENERAL:
1.01 Scog - Provide.
1,02 Alternate Bid - See 0110.
1.03 Unit Price - None,
1,84 Shop Drawing - Required.
1.05 Samples - Not required,
1.06 Guarantee - Per contract conditions.
1,07 Standards - Per contract conditions.
1.08 Testing - Not required.
1.08 Include List - Where indicated on drawings.
1.10 Do Not Include - Installation by 8810.
1.11 Standards of Qualit - Peucu & American Locker.
1.12 Clean - Per contract conditions.
2.01 Materials -
A. Public lookers shall be Vanguard Staourd, #6233V, double tier
lockers, as manufactured by Peoco or approved equal. Pro,iGe
built-in grooved key lock for each looker.
B. Staff lockers shall be Invincible Athletic Locker, single tier
lookers, 46113A Cully ventilated, as manufactured by Peoco or
approved equal, for padlocks,
C. Basket Racks ahuII be #65930, 40''YJx 13-3/16'`D z 79"B, with 32
basket capacity, as manufactured by Peuuo, or approved equal (16
required). Provide number plates on the Racks from 001 to 512.
D. Baskets shall be #09646 8, S"W x 13''D x 8"B, as manufactured by
Peoco, or approved equal (512 required). Provide number plates on
the Baskets from 001 to 512. Baskets shall be chrome plated
finish.
PART 3 INSTALLATION:
3.01 Installation - By 0610,
A. Install per manufacturer's recommendations.
B. Install lockers on poured concrete base.
C. Install basket racks bolted together in each Basket Room as
follows:
l. Two groups of two racks fastened end to end.
2. One group of four racks fastened end to end and aide by side.
END OF SECTION 1050
10509108
DIB\18-80
IO50-01
1052 - FIRE PPMECTION SPECIALTIES
REFERENCE: Refer to Section 0180 for explanation of abbreviated
specification format.
PART 1 GENERAL:
1.01 Scope - Provide and install.
1.02 Alternate Bid - See 0110,
1.03 Unit Price - Not required.
1,04 Shop Drawing - Required.
1.85 Sampl - Not required..
1.06 {uarand e - One year.
1.07 Standards - NIFPA 10, UL approved.
1.08 Testing - Not required.
1.09 Include List - Required inspection and maintenance tagging.
1.10 Do Not Include - Does not apply.
1.11 Standard of Qualit - Larueu/e and J. L. Industries.
1,12 Clean - Not required.
2.01 Materials - Iarseo's - Extinguisher and Mounting Bracket.
A. Extinguisher - MP10 (44-60B:C) 10 pounds.
B. Bracket Model B-2 3tazxdaux}
PART 3 EXECUTION:
3.01 Install in locations shown oudrawings. (One in each 6oiIdiog).
Provide all necessary fasteners, nnobors, etc. required for
installation and install in accordance with oatiuCucturcr'a
recommendations.
END OF SECTION 1052
10529108
1O52-81
1080 - TOILET AND BATH ACCESSORIES
REFERENCE: Refer to Section 0180 for explanation of abbreviated
specification format.
• . • 91 � •.
1.01 Sco - Provide and install.
1.02 Alternate Bid - See 0110.
1.03 Unit Price - None.
1.04 Shop Drawing - Catalog cuts and installation of drawings.
1.05 Samples - Not required.
1.06 Guarantee - Per contract conditions.
1.07 Standards - Per contract conditions.
1.08 Testing - Not required.
1.09 Include List -
A. As scheduled below or shown on drawings.
B. Compact baby changing station.
1.10 Do Not Include - None.
1.11 Standards of Quality - Bradley.
1.12 Clean Up - Does not apply.
2.01 Materials - Bradley product numbers are indicated.
A. Furnish the following for toilet room 110:
1. Mirror, frameless #430 bright annealed stainless steel,
16" x 20 ", with 1/4" masonite backing.
2. Grab bars, #040 and #001, 24 ".
3. Soap dispenser. Provide one new wall mounted dispenser for
each two lays to match existing dispensers to be removed from
existing Bathhouse and reused in Shower Rooms.
4. Toilet tissue holder, #522.
5. Handicapped shower seat (shower room), 18 "W x 15- 1 /2 "D, #U934T
as manufactured by AJ Washroom Accessories.
6. Compact Baby Changing Station, koala Bear Flare, as manufactured
by JBL Industries, Inc., Vadnais Heights, Minnesota.
7. Chrome towel hooks, B -677 polished stainless steel, Bobrick or
approved equal (20 thus).
•_U -►4-_ K_r_ _ •
3.01 Installation
A. Coordinate with 0610 for blocking and rough openings.
B. Install per manufacturers recommendations.
C. Provide all clips and mounting brackets as required for
installation.
D. Install mirrors with appropriate mounting screws to suit
individual field conditions as per manufacturer's recommendations.
END OF SECTION 1080
10809108
BHA10 -89
1080 -01
BATHHOUSE NEW HOPE, MINNESOTA 10/31/89
DIVISION 15 - MECHANICAL
SECTION 15010 GENERAL PROVISIONS
1... CONDITI.ON.S. OF- THE - CONTRACT
1.1 The Conditions of the Contract (General, Supplementary
and other conditions), and the General Require
(Section of Division 1) are hereby made a part of this
Section.
1.2 The Articles contained in this section may delete.
modify, or add to the provisions of the Conditions of
the Contract and shall take precedence over the
Conditions of the Contract.
2.0 GENERAL
2.1 The work under this section of the snecifications
consists of f urnishing all labor, ecTuipmen t and
materials necessary for and reasonably i to the
complete installation of the Mechanical Systems as
herein described and indicated on. the drawings.
including such minor details not specifically mentioned
or shown as may be necessary to complete the syste'7•'.
ready for successful operation and subject to the terms
and conditions of the contract. All work under this
division shall be done in accordance with the best
- modern practice, using first crrade equipment and
material new and previously unused, unless specifically
indicated otherwise.
2.2 The drawings are diagrammatic in nature and not intended
to show exact locations. Contractor shall coordinate
installation with other documents and on-site
conditions.
2 .3 It is the intent of the Plans and Specifications to forr
a Guide for a complete installation. Everything
necessary for the completion and successful operation of
the work, whether or not herein definitely specified or
indicated on the drawings, shall be furnished ara
installed as well as faithfully as if so specified or
indicated without additional cost to the Owner.
Mechanical Contractor shall verify all dimensions and
lengths prior to installation.
2.4 Wherever a question exists as to exact intention of the
documents, obtain instructions from the A/E before
nroceedinq with the work. Should the drawings disagree
in themselves or with the specifications, the better
quality or greater quantity of work or materials shall
be provided as determined by the Engineer.
MECHANICAL GENERAL PROVISIONS 15010 - 1
BATHHOUSE NEW HOPE, MINNESOTA 10/31/89
3.0 ELECTRICAL WORK
3.1 All line voltage power wiring (120 volts or higher) will
be furnished, installed and connected by the Electrical
Contractor under Division 16. This Contractor shall
provide the Electrical Contractor with factory wiring
diagrams of mechanical equipment furnished under
Division 15.
3.2 All electrical components, wiring, and devices furnished
under Division 15 shall conform to the latest revision
of the NEC and to Division 16 of this specification.
This Contractor shall be responsible for furnishing such
equipment and components to operate on the voltaae
characteristics as specified under the electrical
division.
4.0 CODES, FEES AND PERMITS
4.1 Comply with the requirements of the State and Local
codes. Secure all permits and licenses requirecl fL'c the
installation of this work, and pay all fees incidental
thereto including water and sewer hook up charges,
deposits and sewer availability charges (SAC).
4.2 Furnish equipment and supplies that meet the following
Standards:
Laws of the State
Plumbing Codes of the State.
Local Ordinances and Regulations.
National Board of Fire Underwriters (TTFPr'
Testina Code of the American Societv of
Mechanical Engineers (A"SME).
State Enerav Code.
American Society for Testing Materials (AASTI-1).
HUD - Minimum Property Standards.
Uniform Building Code.
Am
erican Society of Heating, Refrigeration, Air
Conditioning Engineers (AISHRAE).
Occupational Safety and Health 'Act (OSHA).
5.0 PAVEMENT, SIDEWALK, SOD AND LANDSCAPING REPLACEHENT
5.1 The Mechanical Contractor shall be responsible for the
replacement of existing sod, street pavement, curbs,
sidewalks or other situations removed or danlaqed by hi-t;
in the course of the Mechanical Work, not scheduled for
replacement under the Contract.
6. SPECIAL A"I.T CONDITIONS
6.1 Each bidder shall examine the site and fa--riliarize
himself with all the existing conditions and limitations
MECHA'Al"TICAL GENERAL PROVISIONS 15010 - 2
BATHHOUSE NEW HOPE, MINNESOTA 10/31/39
before subyr-ittina a proposal. I extras will be allowed
because of the Contractor's misunderstanding as to the
amount of work involved or his lack of knowledge of any
existina condition with the work.
0 MATERIALS _S,U.B�STITUTTOITS.
7.1 Where any equipment or materials are specifically named,
the Contractor shall base his proposal on that item. The
Contractor may, at his option, list on a separate sheet
alternate items, subject to the conditions stated
herein, along with specific identification of the ite-,,Il -
as to the specification paragraph, and charaes in this
proposed project price. On major pieces of equipment
acceptable alternate manufacturers have been listed as
equal from which Contractor may choose for his alternate
prices. The list shall be submitted with. and 1 1:)ecore
part of, the Contractors proposal.
7.2 The Owner with A/E approval may select items sun-pliv-d by
any manufacturer listed, and the Contractor aarees to
furnish and install such items as selected for a
contract price equal to the bid price stated adjusted by
the difference between the sum of the installed oric�:s
for all specified items - and the sun of the installed
prices for the items selected by the owner.
7.3 Where any equipment or materials is referred to by the*�
trade name, or other specific manner, followed by the
clause, "or approved equal", it is understood to refer
to the grade or quality required uired and is not intended to
eliminate other equally desirable equipment or
materials, which would meet the requirements of the
specifications and approval of the Engineer. Approval of
such material is subject to submitted shoe drawincrs.
7.4 This Contractor shall pay, provide, install and be
responsible for extra materials required by himself or
any other trade due to this Contractor's USEE-1- of
alternate approved equipment which has installation
requirements different than the specified equipment.
This Contractor shall pay other trades for any eortra
work they are involved in due to this substitution of
equipment. He shall also be responsible and shall pay
for any re-desian work associated with the installation
requirements of the substituted equipment, orovidinQ
either revised drawincrs or sketches prepared by him or
the Engineer. All re- design work shall be approved by
the Engineer.
8.0 WARRANTY /GUAR ANTEE
8.1 The Contractor shall assume resnonsibilitv for anv
defects which may develop in any part of his work caused
MECHAFICAAL GENERAL PROVISIONS 15010 - 3
BATHHOUSE NEW HOPE, MINNESOTA 10/31/89
by faulty workmanship, material or equipment, and aarees
to replace, repair, or alter, at his expense, may such
faulty workmanship, material, or equipment that has been
brought to his attention during a neriod of one (1) year
from the date of the final certificate of navment.
,-cceptance of the work shall not waive this auarantee.
8.2 Defects of any kind due to faulty work or materials
appearing during the above mentioned period must be
immediately made good by the Contractor at his own
expense to the entire satisfaction of the Owner and
Enaineer. Such reconstruction and repairs shall include
all damage to the finish or furnishings of the building_
resulting from the original defect or repairs thereto.
8.3 This guarantee shall not apply to darn.aaes occurrina
after final accentance and due to wind, fire, violence,
abuse or carelessness of other Contractors or tl'
employees or the agents of the Owner.
8.4 This guarantee shall not apply where other auarantees
for greater lengths of time are specifically called for.
9.0 SHOP DRAWINGS
9.1 The Contractor shall provide a minimum of seven (7) sets
of approved, stamped and bound collated shop dra.winus
for all systems and equipment furnished under This
Division or as indicated otherwise in the indivi6
sections of the specifications. Two sets of sho-)
drawings will be retained by the A'Architect/Enaineer
after final approval.
9.2 The shop drawings shall be properly labeled as to
contractor, project, subject, manufacturer's nain.e, etc.,
with catalog numbers, features, dimensions, etc.,
clearly indicated and pointed out.
10.0 CORRELATION OF WORK
10.1 Consult the Drawinas and Specifications of electrical
and other trades for correlating information and layout
work so that it will not interfere with other trades.
Verify all dimensions and conditions, i.e., finished
ceiling heights, footinas and foundation elevations.
bearn, depths, etc., with the architectural and structural
drawings. If conflicts occur such that resolution is not
possible by the affected trades on the job, notify the
Architect/Engineer so that the proper changes can be
made to avoid extra cost to the Owner. Where work must
be replaced due to failure of the Contractor to verify
the conditions existing on the job or due to failure to
coordinate with other trades in a timely manner, such
replacement must be accomplished by this Contractor at.
MECHANICAL GENERAL PROVISIONS 15010 - a
BATHHOUSE NEW HOPE, MINNESOTA 10/31/89
no extra cost to the Owner. This shall apply to shoe
fabricated work as well as to work fabricated in place.
11.0 EOUIPMENT AND MATERIALS
11.1 Pinina and duct connections to equipment shown on
Drawinas are typical for the style and - ..model of a
particular manufacturer. Changes in piping, ductwork
connections, pump impellers, and electrical to suit
actual installed types shall be made with no additional
cost to the Owner.
12.0 PROTECTION
12.1 Protect all openings and all equipment where set, by
coverina to prevent obstruction to pipes, breal -acre,
misuse or disfigurement of equipment. Immediately cover
all openings in equipment upon uncratina or receipt at
the job site until permanent connection is made.
12.2 The Contractor is resnonsible for anv damaai� to the
plumbing Pines or fixtures and shall keen clean all
materials installed by him until acceptance of the
entire building by the Owner.
13.0 MANNER.11OF.. RUNIT,.INGI-I PIPING ---AND --I DUCTWORK
13.1 All pipina and ductwork shall be run in the most direct.,
straiaht and mechanical manner and everywhere nroPeT
crraded. Offsets in vertical pipe will be allowed only
when unavoidable. All pipe connections shall be so Made
as to allow for perfect freedom of move of the
pipina during expansion without sprincrina.
13.2 Coordinate work with that of all other trades, properly
crrounina piping with other pipes. Run pipes as srovTn
the drawings, but the Engineer reserves the t i t r o
make slight changes in runs to avoid interf�rerc- r
other work or structural conditions without extra charcre
by the Contractor. Coordinate location of pipes and
their hanaer points with other trades such that the
maximum weight imposed on any one bar Joist sha n
exceed 25 lb per lineal foot of bar joist.
END OF SECTION
MECH J,TT("L GEJ%TERAL PROVISIONS 15010 - 5
1.1 General Provisions (Section 15010) are hereby made a
part of this Section.
2.0 CONCRETE FOUNDATIONS AND PADS
2.1 All concrete foundations, pads and pits Will be
provided by the Division 15 Contractor, and shall be
responsible for the proper size and death inc-ludina all
necessary anchor bolts, tie plates, etc.
3.0 PAINTING
3.1 This Contractor shall also be res for the
touch -up painting of all ecruipment provided under this
Division. Any equipment or annaratus (71a - T e d'
scratched, or defaced during shipment or installat .
shall be touched-up with kits of the proper color
furnished by the equipment manufacturer.
4.0 CLEANING 'ND FINISHING
4.1 After all tests have been made and accepted, the
Mechanical Contractor shall cro over the whole lob and
clean fixtures, pipes, fittings and other eal-iii)7nen" C
installed by him, leaving the entire area in a clear
and complete working order.
5.0 CUTTING "ND PATCHING
All cutting of existing conditions and all patchinci
required to install any portion of this work or to
correct defects in work shall be the resnonsibilitv of
this Contractor. Patching will be don .a- in a rna n n, r 1: c
match existing construction,
5.2 All cutting and patching shall be carefully done under
the direction of the A/E. Damage caused throucTh neal-ect
of this clause shall be made good by this Contractor.
6. INSTRUCTION MANUALS
6.1 Upon substantial completion of this project, Droject, and before
final acceptance, this Contractor shall furnish to the
Owner two (2) copies of a complete manual fl-111V
describing the construction, installation, operation,
and maintenance of each piece of equipment and system
installed under this contract. Each manual shall be
bound in a looseleaf binder with a plastic leather
11ECHANICAL BASIC MATERIALS AND METHODS 15050 - 1
BATHHOUSE
10/31/89
the front indicatincf
1. Mechanical operation and Maintenance Instructions
and Parts List.
2. Project Name.
3. Date.
A. Contractor's Name, Address, and Telephone Number.
The manuals shall consist of sections tabbed and
labeled according to systems, and shall include wiring
diaarams, valve charts, control diagrams, shop
drawincrs, spare parts lists, and manufacturer's
oneration and maintenance manuals with -names and
telephone numbers of parts suppliers.
7.0 EXCAVATING AND BACKFILLING
-, � :M_ .... . -------
7.1 All excavating and backfillincr for 'underground pinina
shall be done by this Contractor. All work shall be
carefully protected from injury due to frost, water or
other causes, and any work shall be promni:lv
and properly repaired.
7.2 After underaround work has been inspected and annroved,
the work shall be covered with frost-free earth around
piping and sand thoroughly tamped and compacted.
7.3 All backfill up to the top of piping shall be fr of
rocks and shall be tamped around the pipe. Rack-F' - 11 ul:
to two (2) feet of cover over the nine shall be nlace�
by hand and tamped, being careful not to disturb the
pine. Backfill from a point two (2) feet above the top
of the pipe to grade shall be placed in - maxin-nium... 12
layers and compacted to a density equivalent of 95*
oroctor density. Density tests shall big made in
sufficient number that the compaction meets the
requirements of these specifications.
/8 T
8.1 All plumbing work shall be inspected, tested and
approved as required by the Local and State Plunbina
Inspector, and Department of Health. Test shall be made
in the presence of the proper inspector or their duly
authorized representative and he shall furnish the
Engineer with a certificate.
UNIONS
9.1 On inlet and outlet of all anparatus or equipment
having screwed and/or soldered connections, 2" and
smaller.
MECHANICAL BASIC MATERIALS AND 14ETHODS 15050 - 2
BATHHOUSE NEW HOPE , MINUESOTA 10/31/89
9.2 Malleable iron unions with ground joint brass to iron
seat, ANSI 150 lb, black or cralvanized, Grinnell 46
Stockham, 694.
10.0 DIELECTRIC UNIONS
10.1 Where dissimilar metal piping materials come in
contact, except for the use of valves, isolate from
each other with dielectric couplings. Lines 1-1/2" and
smaller shall have universal insulating unions type
2000 series, style No. 3 and 4. Lines 2" and larger
shall have insulatina flanges, and larger lines shall
have insulating flanges having one brass component and
one steel component as manufactured by Service
Engineers, Inc., Fort Worth, Texas.
11.0 N I PP LE S
11.1 Nipples shall conform to the requirements of U.S.
Department of Commerce Commercial Standard CS-5 - "Pine
Nipples7 Brass, (onner, Steel and Wroucht Iron". Use
nipples from packages which bear manufacturer's label
or tag reading: "Guaranteed Pine Nipples Confor-i-Ino to
CS-5 Made From New Pipe" or other words to this
effect.
11.2 Make nipples of same material and weight as nine where-
on used.
11.3 Floor, wall and ceiling plates for lincoveri:- pips
through finished area shall be provided, except within
closed cabinet work. Plates shall be chrome plated and
have raised edges to accommodate extended sleeves.
12.0 STRAINERS
12.1 Install strainers where indicated on the olans.
Strainer shall be Y—pattern type, cast iron or
semi -steel (bronze when installed on conner or brass
pipe), pressure rated for intended service. Strainers
shall have standard brass screen, crasketed machin 6
flanaed cap with threaded blowdown opening, valved to
the nearest floor drain. Strainers shall be scr,zwed for
sizes 2" and smaller and flanaed for 2-1/2" and laraer.
Strainer to have mini-mum effective strainina ratio four_
to one. Strainer shall be by Mueller, C.M. Bailev,
Arm.strona.
1 3... Q B 7 A C K F L-10 W - I PREVENTION
13.1 Provide safety devices such as vacuu-m breakers and
backflow prevention valves as required by code to
prevent contamination of drinking water sunply system.
MECHANICAL BASIC MATERIALS AND METHODS 15050 - 3
BATHHOUSE NEW HOPE , MINNESOTA 10/ 31 / 8 9
14.0 VALVES
14.1 Furnish and install all valves indicated on the
drawings and as required to sectionalize control
valves. individual aroups of risers; and n 1 umnb i n a
fixtures. All valves shall be concealed T,-Then in
finished room areas, and shall be located in an
accessible position through access panels furnished by
the General Contractor.
14.2 The valves shall be Gate, Globe, Check or Plucr Type as
.indicated with brass bodies, bronze trim, and designed
for a working pressure of 125 lbs. per square inch.
Valves 2" and under shall have brass or bronze bodies
with sweat fitting ends. Gate valves shall have rising
stems. Globe valves shall have rising stems.
14.3 These valves shall be Crane, Nibco-Scott or Hammond
with the name, size and manufacturer's na_r.e clearly
stamped on each valve.
15.0 ROOF JACKET
15.1 Vent stacks from sewer, soil, waste and drain pines
shall be extended at least 12" above the roof, and
shall be encased in galvanized iron frost -proof
- jackets, Moore or equal, each having an air space of at
least 1" between the outside surface of the pine and
the inside surface of the frost jacket. The top of the
frost jacket shall be desianed so as to permit the
insertion therein of a testing plug of such form that
it can be readily seen until removed; and said nlua
shall be removed at once, after a final inspection has
been made and anoroved by the Engineer. The vent pipe
shall be cast iron where same passes through roof slab.
The minimum size of any vent passing throijah the roof
shall be 2".
16.0 PIPE HANGERS AND SUPPORTS
16.1 This Contractor shall furnish and install all nine
hangers and supports as required to install all lines
under his contract. The hangers shall be of proper
strength and placed on the correct centers to support
the lines with no saaaina. Any additional steel
members required to run the pipes where indicated on
the drawinas shall be furnished and installed by this
Contractor.
17.0 FLOOR, WALL, _AND CIE I L I1 -PLAT-E.S.
17.1 Where uncovered, exposed pines pass through walls or
floors of finished rooms, they shall be fitted with
wall or floor plates. wherever projecting sleeves
MECHANICAL BASIC MATERIALS AND METHODS 15050 - 4
BATHHOUSE NEW HOPE , MINNESOTA. 10/31/89
occur, the Mates shall have a raised hood desian to
cover the sleeves.
18.0 CLEANOUTS
.18.1 Full sized brass screw plua cleanout plugs shall be
furnished and installed at the foot of all soil waste
stacks and at all points where shown on drawings and
where necessary to permit the entire drainage system to
be rodded out easily. Provide cleanouts at every turn
in the sink wastes. Cleanouts appearing in finished
floors shall be with polished N.B. Cover and shall
finish flush with the finished floor. Cleanouts in
walls shall be covered with a flush relate with center
screw, with C.G. cover. Soil and waste piping run in
the earth under the floor slab shall have cleanouts of
double eighth bends and finish flush with floors. All
cleanouts must be in accessible positions and not over
50 feet apart.
19.0 FLOOR
All floor drains provided under this contract shall be
of Josam, J.R. Smith, Zurn, or Wade Manufacture and
shall be of type, material and construction indicated.
Provide lead flashing for all drains in structural
slabs above grade.
19.2 Floor drain shall be Josam #30602-A cast iron body
with integral trap and Nickoloy strainer.
20.0 HOS-El" BI-IB
20.1 Furnish and install Josam, Woodford, or "41urn 3/4" brass
non-freeze similar to Josam #71150 outside hose faucets
where shown on the drawings. Set sill cocks
approximately 2'-0" above grade unless directed
otherwise. Conceal supply lines where nossibl_r and
-provide drain cock for each faucet. The Contractor
shall notify Owner as to what drain valves shall be
shut and lines drained to prevent freezing.
END OF SECTION
MECHANICAL BASIC MATERIALS AND METHODS 15050 - 5
BATHHOUSE NEW HOPE, MINNESOTA 10/31/89
DIVISION 15 - MECHANICAL
SECTION 15060 PIPE AND PIPE FITTING
CONDITIONS OF THE CONTRACT
1.1 Refer to Section 15010 Mechanical General Provisions
and Section 15050 Mechanical Basic Materials and
Methods.
GENERAL
2.1 All pipes shall be run with proper grades to provide
for easy draining. They must be thoroughly reamed and
cleaned before installation. Pipes run overhead shall
be placed as close to the ceilings as possible to
maintain proper headroom and to present a neat
appearance, all consistent with the correct pitching of
pipes. Piping shall be run as shown on the drawings.
Except for piping run in equipment rooms, all piping
shall .-)e concealed unless specifically indicated other
wise on the drawings.
2.2 Consult manufacturer's data and the large scale details
of rooms containina plumbing fixtures on the
Architectural drawings before roughing -in piping. Plug
or cap pipina immediately after installation. Minimum
size of all water piping shall be 1/2" except for short
stubs immediately at fixtures. Armaflex pipe insulation
shall be used where piping passes through fram-els.
2.3 All screw threads must be tapered and proportioned in
accordance with the regulations formally adopted by the
manufacturers of wrought iron pipe and boiler fittings.
All threads must be cut true and sharp and threaded
joints shall be put together and made tight with
graphite.
2.4 Pipe welding shall comply with the provisions of the
latest revision of the applicable code, -whether ASME
Boiler Construction Code, ANSI Code for Pressure
Piping, or such state or local requirements as may
supersede codes mentioned above.
PIPE & FITTING SCHEDULE ACCORDING TO TYPE OF SERVICE
3.1 Water Underground
Pipe - 2-1/2" and smaller - Type,/K,coipper with flared
water works type fitting.
Pipe - 3" and larger - Class 150 cast iron cement
lined, ASA specification A21.4
Fittings - Class 250 pipe.
Joints - Mechanical joint with lead tipped rubber
PIPE AND PIPE FITTINGS 15060 - 1
BATHHOUSE NEW HOPE, MINNESOTA 10/31/89
or push on joints with conductive rubber gaskets
or outside strapping
3.2 Domestic cold water and hot water above around
(inside building)
Pipe - Type L hard temper copper pipe.
Fittinas - 1" and smaller - cast bronze solder type
or wrought solder type.
Fittings - 1-1/4" and larger - wrought solder type.
Solder - 95/5 for all domestic water piping.
The use of galvanized steel pipe for 3" and larger
is optional.
Pipe - 3" and larger schedule #40 galvanized steel
pipe.
Fittings - 3" and larger standard galvanized malleable.
3.3 Sanitary Waste, Sewer, Underaround _(Inside
BuijALncr)
Pipe - Service weight cast iron soil pipe.
Fittings - Service weight cast iron soil pipe.
Joiy.ts - Lead and Oakum or Tyseal Neoprene Gasket.
3.4 Sanitary Sewer Underaround (0 ' d - e utsi -- Buil ' di '- n - q
Pipe - 12" or less standard strength vitrified clay
sewerpipe ASTM-C13, or service weight cast iron.
Pipe and fittings - over 12" - extra strength
vitrified clay sewer pipe ASTM C-200.
Joints - Hot pour type or Tyseal Neoprene Gasket.
The use of PVC plastic pipe and fittings shall be
approved if allowed by the local codes having
jurisdiction. PVC pipes and fittings shall not be
used in suspended ceiling air plenums.
3.5 Waste,__Vent and Sewer Above Ground.
Pipe - Schedule #40 galvanized steel.
Fittings - Black cast iron drainage fittings.
The use of hubless cast iron pipe with hubless
fiftinas and stainless steel clamps installed and
supported as per manufacturer's recommendation in lieu
of specified galvanized steel is approved. The use of
PVC plastic pipe and fittings shall be approved if
allowed by the local codes having jurisdiction. PVC
pipes and fittings shall not be used in suspended
ceiling air plenums.
3.6 Gas (Inside Building).
Pipe - Black steel schedule #40.
Fittings - Exposed pipe up thru 2" - 150# black
malleable screwed fittinas, or welded fittings.
Fittings - 2-1/2" and larger, concealed piping and
tunnel piping - standard weight welded fittings.
3.7 Gas (outside Building)
Pipe - Black steel schedule #40 coated and wrapped
PIPE AND PIPE FITTINGS 15060 - 2
BATHHOUSE NEW HOPE, MINNESOTA 10/31/89
with "Sc.otch wrap".
Fittings - Standard weight welding fittings coated
and wrapped.
4.0 PIPE INSULATION
4.1 Insulate all hot and cold water pipes with fiberglass
insulation according to the following schedule:
Insulation Thickness
Pipe Size 1-1/4" 1- 1/2 " -2" 2 -1/2"
Cold Water 1/2" 3/
Hot Water below
150 dearees F. 1/2" 111 1-1/2"
Hot water above
l
150 degrees F. l it it 1-1/2" Z'
END OF SECTION
PIPE AND PIPE FITTINGS 15060 - 3
BATHHOUSE NEW HOPE, MINNESOTA 10/31/89
DIVISION 15 - MECHANICAL
S-EC'1TI-ON-.'-' 210-01 WATER SUPPLY SYSTEM
1-1,110 CONDITI.ONS.10,F...--THIE. COITTR CT
1.1 Refer to Section 15010 Mechanical General Provisions
and Section 15050 Mechanical Basic Materials and
Methods.
2.0 SCOPE
2.1 This Section includes all labor, ecruip skills and
tools necessary to furnish and install the water supply
system.
2.2 Pipes, valves, fittings, equipment, pipe hangers and
supports as required by any and all eauinment indicated
in these Specifications and Drawings.
3.0 SHOCK ABSORBER AND AIR CHAMBERS
3.1 Hot and cold water supply pipes serving all fixtures
shall terminate with an approved air chamber or shock
absorber to suppress water hammer. Air chamber shall be
type, sized and located as required by state or 1.)c
plumbing codes.
3.2 Shock absorbers shall be by Zurn, Josam, Wade or
approved equal.
4.0 VACUUM BREAKERS AND AIR GAPS
4.1 Water supply connection to fixtures or eaui which
have submerged inlet or inlets which are below the
spill line of the fixture or equipment. s 1), a I - ". ' r, e
provided with an an vacuum breaker device or air
gap arrangement as required by code.
5.0 GAS WATER HEATER
5.1 Remove and relocate two (2) existing water heaters in
the existing bath house and re-install the same two (2)
water heaters in the new bath house. Reuse the existing
hot and cold water manifolds connected to both water
heaters, also re-use existing 3-way mixers as shown in
the plan. Piping pincr connection of the relocated water
heaters to be the same as it was connected in the
existing bath house.
.0 STERILIZATION OF WATER -PIPTNG
6.1 Upon completion of the new domestic cold and hot
WATER SUPPLY SYSTEM 15200 - 1
BATHHOUSE NEW HOPE. MINNESC)TA 10/31./S9
water systems, and in accordance with the State
Plumbina Code, this Contractor shall sterilize these
systems with chlorine before they are placed in
operation. The amount of chlorine applied shall be such
as to provide a dosage of not less than 50 parts per
million. Following a contact period of not less than 24
hours, the heavily chlorinated water should be flushed.
from the system with clean water until the residual
chlorine content is not greater than 0.2 parts per
million. All valves in water lines being_ sterilized
shall be opened and closed several times durini the
eight hour period.
6.2 All sterilization work shall be oerforred in a manner
and with methods such as to meet the approval of the-�
State Board of Health.
END OF SECTION
WATER SUPPLY SYSTEM 15200 - 2
BATHHOUSE NEW HOPE, MINNESOTA 10/31/29
DIVISION 15 - MECHANICAL
SECTION 1 1-5- 4 5-0 PLU,MB ING - F - IXTURES
1.0 CONDITIONS OF THE CONTRACT
1.1 Refer to Section 15010 Mechanical General Provisions
and Section 15050 Mechanical Basic Materials and
Methods.
2 1-.1-01 SC-Qlp-E'
2.1 This Section includes all labor, eauipmient, skills and
tools necessary to furnish and install the olumbina
fixtures, trim., miscellaneous brassware. etc.
3.0 MANUFACTURERS
3.1 Plunbina fixtures and tri as manu 1 ) , 7
American Standard, Crane, Kohler, Eljer, Chicaao
Faucet, Oasis, Haws, Halsey-Tavlor, Moen, Delta, Elkay
are approved equal.
4.0 PLUMBING FIXTURE SCHEDULE
4.1 Refer to the Plumbinq Fixture Schedule on the Drawinas
for Models and descriptions of all plumbincr fixtures.
END OF SECTION
PLUMBING FIXTURES 15450 - 1
BATHHOUSE NEW HOPE, MINNESOTA 10/31/89
DIVISION 15 - MECHANICAL
SECTION 15800 VENTILATION
1.0 CONDITIONS OF THE CONTRACT
1.1 Refer to Section 15010 Mechanical General Provisions
and Section 15050 Mechanical Basic Materials and
Methods.
2.0 GENERAL
2.1 The system as specified shall include all ductwork,
registers dampers, exhaust fans and equipment herein
specified, mentioned or shown on the drawings and shall
be furnished and installed in place, connected up, and
ready for normal operation.
3.0 TESTING & ADJUSTING THE VENTILATION SYSTEMS
3.1 Adjustment shall be done by properly setting all
dampers to obtain the required air flow as shown on the
drwgs. Any additional dampers which may be required to
get proper air supply and quantity, shall be furnished
by this Contractor at no expense to the Owner.
4.0 DUCTWORK
4.1 All sheet metal ductwork shall be constructed of
galvanized sheet steel of the best grade "Wheeling"
brand, heavily galvanized and of gauge indicated
below.
WIDTH IN INCHES GAUGE
0 12
#26
13 30
#24
31 60
#22
61 84
#20
Equipment housing
#16
Reinforcing shall be in accordance with SMACNA low
pressure duct.
4.2 All ductwork must be made practically air tight. The
Architect/Engineer reserves the right to order any open
seams that may be present made tight by soldering and
riveting. Ducts shall be sufficiently braced to
prevent vibration or sagging. All panels over 10" wide-
or deep shall be cross-broken for strength. The
Architect/Engineer reserves the right to order
additional bracing if he deems it necessary. All
vertical ducts or risers shall be self-supporting and
shall be complete in themselves. No single partitions
VENTILATION 15800 - 1
BATHHOUSE NEW HOPE, MINNESOTA 10/31/89
between ducts will be allowed.
4.3 All major horizontal ducts shall be rigidly and
securely supported in an approved manner with trapeze
hangers formed of rods and angle iron under ducts on no
greater than 4'-0" centers. The upper ends of hangers
shall be securely fastened by an approved method.
Hangers fastened to masonry construction shall be
anchored with Phillips or Ackerman-Johnson shields, or
approved equal. Furnish and install all structural
steel supports required for ducts, fan units, etc.
4.4 All ductwork shall be run substantially as shown on the
drawings with bends and curves of easy radius. Where
possible, the inside radius shall not be less than the
width of the duct.
4.5 Changes in size throughout shall be of perfect
rectangular cross-section. The Architect /Engineer
reserves the right to make minor changes in run of
certain ducts without extra cost to the Owner if
necessary to avoid unforeseen structural or other
interference.
4.6 All fastening and hardware for galvanized ductwork and
sheet metal work shall be cadmium plated; and screws,
bolts, fastenings, etc., shall not penetrate duct.
5.0 DUCT INSULATION
5.1 All insulation work under this contract shall be done
by personnel familiar with this class or work. All
insulation work shall present a neat and workmanlike
appearance. The lining shall be attached by means of an
adhesive-mopped on to cover the entire metal surface.
Exhaust ductwork a distance (3') from the roof
opening shall be externally wrapped with one inch (1")
thick blanket foil faced insulation.
EXTERNAL BLANKET DUCT INSULATION
A. Johns-Manville, R-6, 1-1/2" thick, FSK Facing,
1-2" Tab.
B. Owens-Corning, ED 75, 1-1/2" thick, FRK-25, 1-2"
Tab.
C. Certain-Teed/St. Gobain, Type IV, thick,
FKS, 1-2" Tab.
EXTERNAL RIGID FIBERGLASS BOARD INSULATION
A. Certain-Teed/St. Gobain, 1" thick, 3 lb. density
Fiberglass Board, 1B-300 ASJ.
B. Owens-Corning, 1" thick, 3 lb. density
Fiberglass Board ASJ.
VENTILATION 15800 - 2
BATHHOUSE NEW HOPE, MINNESOTA 10/31/89
C. Johns-Manville, 1" thick, 3 lb. density
Fiberglass Board 814 APJ.
5.2 Duct Liner
1" thick, 3 lb. density coated fiberglass insulation,
adhere, with coated side toward air stream, to all
interior sides of the duct with a minimum 50% coverage
of fire-resistant insulation bonding adhesive per
manufacturer's recommendation. Adhesive shall
completely cover the sheet metal at each end of each
section of duct work and each butt end of insulation.
When duct width idth exceeds 12" or height exceeds 24",
further secure the liner to. these surfaces with
mechanical fasteners at 16" O.C.
Adhesive shall be equal to 3M-EC 1128.
Mechanical fasteners shall be Graham Welding pins or
Cherry Rivets or equal.
Duct sizes shown on plans are inside dimensions and
duct shall be increased to give same free area.
Where duct work is acoustically lined, it does not have
to be thermal covered.
6 DUCT ACCESSORIES
6.1 Gravity Backdraft Dampers
Furnish and install backdraft dampers where indicated
on the drawings. Dampers shall be Air Balance, or
approved equal, made with steel frame and 26 gauge
stiffened aluminum blades. Damper blades shall be
steel with Oilite or bronze bearings. Damper blades
shall have neoprene trim. Blades shall be securely
linked together so they will operate simultaneously.
7.0 GRILLES, REGISTERS, DIFFUSERS
7.1 Grilles, registers and diffusers to be Hart & Cooley,
of the type and size shown in the schedule on the plan.
Barber-Colman and Krueger are approved equal.
8.0 EXHAUST FANS
8.1 Exhaust fans shall be by Greenheck or Acme, of the type
and size req. as shown on the plans. Exhaust fan shall
be provided with back draft damper. Duct of exhaust
fan shall be insulated 3' from exterior wall or roof.
END OF SECTION
VENTILATION 15800 - 3
BATHHOUSE NEW HOPE, MINNESOTA 10/31/89
DIVISION 16 - ELECTRICAL
SECTION - 1601
1.0 GENERAL
ELECTRICAL GENERIL PROVISIONS
1.1 The Conditions of the Contract (General, Supplementary
and other Conditions), and the General Requirements
(Section of Division 1) are hereby made a part of this
Section.
1.2 The Articles contained in this Section may delete,
modify, or add to the Provisions of the Conditions of
the Contract and shall take precedence over the
Conditions of the Contract.
CODES, FEES AND PERMITS
2.1 The complete electrical installation shall conformn to
all of the requirements of the National Electrical Code
and all a<)plicable state and local regulations and
ordinances.
2.2 All service charges, fees, permits, licenses, etc.,
required in connection with the work of this Division,
shall be secured by and paid for by this Contractor.
3.0 PAVEMENT, SIDEWALK, SOD AND LANDSCAPING REPLACEMENT
3.1 The Electrical Contractor shall be responsible for the
replacement of existing sod, street pavement, curbs.
sidewalks or other situations removed or damaged by him
in the course of the Electrical Work, not scheduled for
replacement under the Contract.
4.0 SPECIAL AND LOCAL CONDITIONS
4.1 Each bidder shall examine the site and familiarize
himself with all the existing conditions and
limitations before submitting a proposal. No extras
will be allowed because of the Contractor's
misunderstanding as to the amount of work involved or
his lack of knowledge of any existincr condition in
connection with the work.
5.0 DRAWINGS AND SPECIFICATIONS
5.1 These specifications and corresponding drawings are
intended to form a complete set of plans for the
electrical work of this project and neither shall be
considered complete without the other. Where an item is
mentioned in one and not in the other, it shall be
considered binding to this contract as though mentioned
in both.
ELECTRICAL GENERAL PROVISIONS 16010 - 1
BATHHOUSE NEW HOPE, MINNESOTA 10/31/89
5.2 Where a question exists as to exact intention of the
documents, obtain instructions from the Architect/
Engineer (A/E) before proceeding with the work. Should
the drawinas disaaree in themselves or with the
specifications, the better quality or greater quantity
of work or materials shall be provided as determined by
the Engineer, whose decision shall be final.
6.0 MATERIAL
6.1 When any material, device or equipment is followed by
"or equal", no prior approval will be required.
Approval of such substitution is subject to submittal
of shop drawings.
6.2 When any material, device or equipment is specifically
named without either the tern., "or equal", or "or
approved equal", and no alternate product is listed. i
substitution will be allowed, except where a specific
Alternate bid is recruested in Section 16001 Base and
Alternate Bids, or in any subsequent addendum.
6.3 Contractor may submit voluntary alternate bids with his
proposal to substitute material or equipment not
otherwise specified. Include sufficient information for
Engineer's evaluation and comparison to the specified
material or equipment.
6.4 The A/E will make recommendations reaardinc all
alternate bids to the Owner for his acceptance or
rejection.
6.5 When any material, device or equipment is followed by
"or approved -equal", Contractor must obtain prior
approval for any proposed substitution, by submitting a
written request for approval, together with sufficient
catalog and size information to show the equipment is
comparable, to the Engineer five (5) working days
before the hour of submission of Bids. All reauests
will be studied by the A/E who will issue an addendum
noting all prior approvals. All approvals are based on
.general design and performance of equipment and final
approval is subject to submittal of shop drawings.
6.6 No material, device or equipment shall be used by the
Contractor in preparing his bid unless it was specif-
ically specified without substitution; was specified as
"or equal", has received "prior approval", or was
included in an alternate bid accepted by the owner,
following the procedure specified above. If no
alternate bid is accepted by the Owner, the specified
equipment shall be furnished.
ELECTRICAL GENERAL PROVISIONS 16010 - 2
BATHHOUSE NEW HOPE, MINNESOTA 10/31/89
6.7 This Contractor shall pay, provide, install and be
responsible for extra materials required by himself or
any other trade due to this Contractor's use of
alternate approved equipment which has installation
requirements different than the specified equipment.
6.8 Final approval of certain materials and equipment will
be based on the manufacturer's shop drawings. The
Engineer's approval of shop drawings for substitute
materials shall not relieve the Contractor from
responsibility for deviations from the drawings or
specifications unless he has, in writing, called the-
Engineer's attention to such deviation at the time of
submission nor shall it relieve him of responsibility
for error in the drawings.
7.0 SHOP DRAWINGS
7.1 The Contractor shall provide seven (7) sets of bound
and collated shop drawings for all systems and
equipment furnished under this Division or as indicated
otherwise in the individual sections of the
specifications.
7.2 The shop drawings shall be properly labeled as to
Contractor, project, subject, manufacturer's name,
etc., with catalog numbers, features, dimensions, etc.,
clearly indicated and pointed out.
8.0 TEMPORARY LIGHT, POWER, HEAT, TOILET AND WATER
8.1 Refer to Division 1, Special Conditions, of these-
Specifications for requirements.
9.0 WORKMANSHIP
9.1 All work shall be performed in a neat and work
manner by personnel experienced and skilled in the
electrical trade.
10.0 CORRELATION OF WORK
10.1 Consult the Drawings and Specifications of mechanical
and other trades for correlating information and layout
work so that it will not interfere with other trades.
Verify all footings and foundation elevations, beam
depths, etc., with the Architectural and Structural
Drawings. If conflicts occur such that resolution is
not possible by the affected trades on the job, notify
the Architect /Engineer so that the proper changes can
be made to avoid extra cost to the Owner. Where work
must be replaced due to failure of the Contractor to
verify the conditions existing on the job or due to
failure to coordinate with other trades in a timely
ELECTRICAL GENERAL PROVISIONS 16010 - 3
BATHHOUSE NEW HOPE, MINNESOTA 10/31/89
manner, such replacement must be accomplished by this
Contractor at no extra cost to the Owner. This shall
apply to shop fabricated work as well as to work
fabricated in place.
11.0 AS BUILT DRAWINGS
11.1 Contractor shall maintain one complete set of drawings
on the site at all times and mark all field chances and
deviations in red pencil."
12.0 GUARANTEE
12.1 The Contractor shall assume responsibility for any
defects which may develops in any part of his work
caused by faulty workmanship, material or equipment,
and agrees to replace, repair, or alter at his own
expense, any such faulty workmanship, material, or
equipment that has been brought to his attention during
a period of one year from the date of the final
certificate of payment. Acceptance of the work shall
not waive this guarantee.
END OF SECTION
ELECTRICAL GENERAL PROVISIONS 16010 - 4
BATHHOUSE NEW HOPE, MINNESOTA 10/311
DIVISION 16 - ELECTRICAL
SECTION 16100 ELECTRICAL BASIC MATERIALS AND 1111ETHODS
1.0 COND1IT.IPN.S
1.1 General Provisions (Section 16010) are hereby made a
part of this Section.
2.0 SCOPE
2.1 This Section includes all labor, materials, equip
skills and tools necessary to install the basic
materials of the electrical system. The work of this
Section includes, but is not limited to the following:
A. Raceways and Fittings
B. Junction and Outlet Boxes
C. Hangers & Supports
D. Wire and Cable
E. Wiring Devices
3.0 CONCRETE FOUNDATIONS
3.1 Foundations, anchor bolts, arout, shims, etc., required
for properly placina any equipment furnished and
installed under this Division, shall be provided by
this Contractor unless specifically stated otherwise in
the specifications or on the drawinas. Concrete shall
conform to requirements of Division 3.
4.0 PAINTING
4.1 Paintincr shall be by others except where soecifier'"
otherwise. All items shall be left clean and in
paintable condition, except that this Contractor shall
refinish and restore to its oriainal condition all
electrical equipment which has sustained da-,rarie to th
Manufacturer's prime or finish coat(s) of naint or
enamel.
5.0 CLEANING
5.1 This Contractor shall clean all debris, surplus
materials, etc., resulting from this work or oneration.
He shall cro over the whole job cleaning fixture-s.
panelbcards and other equipment installed by him
leaving the job and equipment in a clean and
first-rate condition.
6.0 CUTTING, P AND SEALING
6.1 The General Contractor will provide openings, chases
and clearances in new construction where necessary to
ELECTRICAL BASIC MATERIALS AND METHODS 16100 - 1
BATHHOUSE NEW HOPE, MINNESOTA 10/311/89
accommodate this work. It shall be the responsibility
of this Contractor to notify him in time of location
and required sizes of all openinas, etc., so as to
cause him no delay.
6.2 All cutting of existing cond
electrical work shall be by
craftsmen skilled in their
fittings, and re Holes
floors must be drilled without
around holes.
iticns required by t he
this Contractor, usina
trades for cutting:
required to be cut in
excessive breaking out
6.3 Seal off all conduit oveninas through fire rated slats.
walls and ceilings using UL anDroved mat---r 4 als and
methods to maintain a fire ratinas. Seal equipment
or components exposed to the weather and nak�-
watertight and insect proof.
7.0 MAINTENANCE BROCHURE
7.1 The Electrical Contractor shall prepare two
complete maintenance brochures which shall cover all
electrical systems and equipment furnished or installe-"'
by him for this project.
7.2 Data shall be placed in 8-1/2" x 11" heavy duty
three -ring binders. Data shall include a title Page
complete table of contents, approved shop drawinas
maintenance instructions, catalog brochure information
and replacement parts list.
8.0 WIRING METHODS
8.1 All conductors shall be installed in metal race'-ways,
with adequate means for expansion. The building has no
heating system and inside temperatures will be -20
decrees fahrenheit during the winter.
8.2 Raceways shall be concealed in the wall corstrucr-icn
and below the concrete slabs. Raceways installed above
the 96" high internal walls shall be neatly installed
on the truss members and run parallel to or at right
angles to the trusses and walls. Use standoff tv'!:e
supports so that all exposed raceways can be painted,
(by others), and will not trap moisture.
8.3 Install drain tiles at low points for any run that
could otherwise trap moisture.
8.4 All raceways in the existing pool equipment room shall
be exposed.
9.0 MATERI AND EQUIPMENT
ELECTRICAL BASIC MATERIALS AND METHODS 16100 - 2
BATHHOUSE NET4 HOPE, MINNESOTA 10/31/89
9.1 All materials and equipment ruipment shall be listed by
Underwriter's Laboratories, Inc., except where no
standards have been established for the particular
material or equipment specified, and shall bear the
U.L. Label.
10.0 RACEWAYS AND FITTINGS
10.1 Raceways shall be rigid metal (RMC), intermediate metal
(IMC),electrical metallic tubina (EMT), flexible metal
(FMC), flexible nonmetallic conduit (FNC). or rigid
plastic (RPC) as manufactured by Republic, Jones &
Laughlin, Youngstown, Gedney, Carlon, Can-Tex,
Electroflex, or equal.
10.2 Fittings shall be of construction similar to the
particular raceway, weathertight as required. Fittin
shall be set-screw or compression type. indentor tvne
fittinas are not acceptable. In addition to conduit
manufacturers, fittings shall be as manufactured by
O.Z., Raco, Efcor, Recral, Pyle-National Crouse-Hinds,
or equal.
10.3 Conduit installation shall conform to the followina
reauirements:
A. Neat and orderly, perpendicular or parallel
with building construction.
B. Supported with non-corrosive metallic straps,
clamps, or hangers.
C. Coordinate routing with other trades. Conduit
location is secondary to mechanical and aeneral
construction elements of buildina.
D. Concealed in all finished areas unless explicitly
noted otherwise.
E. Flexible metal conduit shall be used for conn-
ections to all fixed appliances, motors. trans-
formers, and All other vibrating equipj-.1enT:.
Flexible metal conduit shall also be used for
connections to recessed light fixtures and other
branch circuit wiring as required for special
an
F. Use expansion fittings at expansion joints and
where temperature chanaes cause excess exnansion.
G. All conduit exposed to weather or in direct con-
tact with concrete shall be RMC or IMC.
H. All conduit concealed in or below concrete slab
on crrade, or in masonry constriction within 24"
of final grade shall be RMC, IMC or RPC.
I. Aluminum conduit shall not be nermitted.
J. Provide all trenching and backfill required,
including surface restoration.
1 JU.N�CTI-ON.-. AND -,OUTLET - "BOXES
,
ELECTRICAL BASIC MATERIALS AND METHODS 16100 - 3
BATHHOUSE NEW HOPE, MINNESOTA 10/31/89
.1 Boxes shall be of craivani zed code aalicre steel as
manufactured by Appleton, Steel City, Raco, or equal,
and as follows:
A. Minimum size 4 inch square or octagon by
1-1/2 inches deep.
B. Mud, plaster or extension rings as required.
C. Concealed except where explicitly noted
otherwise.
D. Locations coordinated with other trades.
E. Supported independent of conduit system.
F. Offset back-to-back boxes a minimum of 6".
G. Type FS or FD for surface exterior applications.
H. Masonry boxes sized to match bricks.
I. Metal boxes used with metal raceway.
J. Floor boxes - dual level concrete tight Class 2.
11.2
Hountina heiahts shall be as follows (Nominal):
DEVICE
FINISHED
AREA Receptacles
Exterior Receptacles
24 11
Light Switches
52"
Telephone Outlets
A. Desk type
12"
B. Wall type
66?f
Motor Starters
66
Thermostats
66"
Push Buttons
52"
Clock Outlets
7 1 -6 t v
UNFINISHED AR FA
12" 52"
24"
52"
1 2 1-.1 0
MULTI-OUTLET ASSEMBLIES
52 11
66"
66
66 11
52"
as noted
12.1 Assemblies shall be complete with all adapters,
feed-in devices and elbows required for a complete
installation, installed in accordance with Article 352
and 353 of the IJEC, as follows:
Type - A1 Single receptacles ore-wired on a single
20 amp circuit - Wiremold type 20G.
Typ2l-A-21- Same as type Al, except duplex recept-
acles - Wiremold type 20DG.
Typ.e.B_1. Single receptacles pre-wired on (2)
20 amp circuits - Wiremold type 20GA.
Typel.-P1 Same as type Bl, except duplex around-
ing type receptacles - Wiremold type
20DGA.
The drawinas indicate the spacing of the outlets (in
inches), i.e. A2-60, B1-30, etc.
ELECTRICAL BASIC MATERIALS AND METHODS
16100 - al
BATHHOUSE
_13.10 CONDUCTORS
NEW HOPE, MINNESOTA
13.1 Aluminum conductors are expressly forbidden.
10/31/89
13.2 Conductors shall be soft drawn copper as manufactured
by American, G.E., Cyprus, Cornish, National Electric,
Rockbestoes, Pirelli, or equal to meet IPCEnA
Specifications. Conductors shall conform to the
followina:
A. No. 12 minimum size, except for controls.
B. Stranded for No. 8 and larger.
C. Color coded. Colored wire for branch circuits
and field marked for feeders.
D. Feeder splices shall utilize hydraulic comp-
ression connectors - Burndy, Ampact Taps, T & B.
E. Branch splices shall utilize "Scotchlock" conn-
ectors.
F. Minimum conductor insulation shall be 600 volt
type THHIXT for size #8 A.W.G. and smaller and
type THW, THW11, THHN or XHHW for #6 and laraer
chanae as req. for high ambient temperatures.
1 4-.0. WIRING
14.1 Devices shall be commercial grade as manufactured by
Leviton; equivalent devices by Pass & Sey-moure, G.E. '
Sylvania, Hubbell and Arrow-Hart, or approved equal aS
follows:
A. Ivory color with smooth nylon plates. Round corner
galvanized plates for surface installation, in
service spaces. Stainless steel plates shall be
used in food preparation areas.
B. Toggle type switches, 15 amp, 120/277 volt #5501-
2.
C. Duplex receptacles, 15 amp (20 as noted) 12 volt.
3-wire grounding type #5014.
D. Pilot-switch combinations with neon pilot in
toggle #57501.
E. Clock outlets, 15 amp, 125 volts. Leviton #5261CH.
F. Wet location covers for weatherproof devices.
Heavy duty Bell Electric.
G. GFI receptacles 20 amp, 125 volt, and 5 MA trip
ratina where required by code. Leviton #6199.
Use feed thru type where downstream receptacles
need GFI protection.
H. Dimmer switches - Lutron NOVA Series with separate
de-buzzing coils for Edison Base larins larger than
150 watts.
I. Special receptacles shall be as follows:
(Dryer) (Rance)
ELECTRICAL BASIC MATERIALS AND METHODS 16100 - 5
BATHHOUSE NEW HOPE, NINNESOTA 10/31/89
120-208V 20 AMP 30 AMP 50 Allp
3-wire non NEMA 10-20R 10-30F 10-50R
aroundincr type Hubbell #6810 #9350 #796"
208/240V NEMA 6-20R 6-30R 6_50R
I-phase,3-wire Hubbell #5461 #9330 #9367
120/240 volt NEMA 14-20R 14-30R 14-50R
1-phase,4-wire Hubbell #3410 #9430 #9450
15.0 INSTALLATION AND WORKMANSHIP
15.1 All work shall be installed by skilled mechanics in a
neat and workmanlike manner and shall be an by
the A/E before final acceptance by the Owner. n
sufficiently larae work force shall be emploved at all
times, and shall be provided with the tools and
equipment required to insure progress of the work of
this Contractor at a rate comparable with the overall
job proaress.
15.2 The conduit system shall be concealed in the buildina
construction in all finished areas of the building
except where specifically noted otherwise. Conduits
for equipment, panelboards, wireways, etc., shall be
run exposed in equipment room and unfinished areas.
1 1 6. - 0 IDENTIFICATI
16.1 Provide black and white laminated plastic enaraved
nameplates with 3/16" minimum height characters for:
A. All circuit protective devices located in service
equipment, main distribution switchboari, main
distribution panelboards, and meter centers, etc.
B. Each panelboard, dry-type transformer, and m,
control center (M.C.C.).
C. Each switch or device built into control panels.
16.2 Provide 1/4" orange flexible plastic tape, I)y,-no
Industries, or equal, havina 1/8" embossed leaends for
individually mounted fused switches, disconnect
switches, motor starters, relays, time clocks, and
other control devices.
END OF SECTION
ELECTRICAL BASIC MATERIALS AND METHODS 16100 - 6
BATHHOUSE NEW HOPE, MINNESOTA 101/31/89
DIVISION 16 - ELECTRICAL
SECTION 16400 ELECTRICAL SERVICE AND DISTRIBUTION SYSTEM
1 COIN-PITIP-US
1.1 Refer to Section 16010 Electrical General Provisions
and Section 16100 Electrical Basic Materials and
Methods.
2.0 ELECTRIC SERVICE PROVISIONS
2.1 Furnish and install a new 120/208 volt 3 phase, 4 wire,
secondary electric service from a new nad mounted
transformer to replace the existina 120/240 volt
3-phase, 4 wire, open delta service from the existing
pole mounted transformer as shown on the drawings and
as specified herein.
2.2 The Local Power Utility Company (LPU Co.) will furnish
and install the concrete pad and the pad—mounted
transformer as well as all primary cables, and all
final connection. Utility company will provide and
install transformer crroundincr and will provide meters
and current transformers for installation and
connection by this Contractor.
2.3 Contractor shall initiate the request for service in a
timely manner.
2.4 Contractor shall furnish and install the followina:
A. Secondary service feeder from transformer to the
main disconnect(s) and metering equipment.
B. Main fused switch(es) and/or distribution
switchboard and fuses.
C. All service around connections.
D. Meter sockets to meet the Utility Company
requirements.
E. Installation and connection of all direct readin(-,
meters, CT cabinets, current transformers, - meters
and test switches.
3.0 GF I OU - ND I NG - - S Y STEMS
3.1 Service entrance equipment, current transforre-rs. mater
sockets, transformer cabinets, panelboards, metal
raceway systems, neutral service conductor and all
other permanently installed electrical equipment shall
be solidly arounded in accordance with the National
Electrical Code to form a continuous, permanent and
effective crrounding system.
ELECTRICAL SERVICE AND DISTRIBUTION SYSTEM 16400 - 1
BATHHOUSE NEW HOPE, MINNESOTA 10/31/39
3.2 The around bus built into the new main fused switch,
shall serve as the building electrical system service
aroundina point. Connect from same to the existina
service grounding conductor. Size per NEC Tab-L--
#250-94 and provide an "additional electrode" per
#250-81. existing bonding jumpers around water meter,
and around fault relay to remain. Where the bare
around wire is subject to physical damage, install wire
in a rigid steel conduit.
3.3 The continuity of the grounding system shall be
maintained throughout the entire raceway, cabinet and
equipment enclosure system. Ground bushings and _Jumpers
shall be used wherever normal conduit termination does
not insure continuity. Where non-metallic conduit is
used for distribution, a properly sized insulated
grounding conductor shall be run in the conduit, and
shall be properly bonded to equipment at each end of
run. Conduit size shall be increased as needed. 1
parts of liahtina fixtures shall be bonded to conduit
system with green ground wire. Plug strip shall
positively arounded to conduit system. Non-self
grounding receptacles shall be grounded to outlet.bo_-,
with around piatail. Where switchboards, panellboards or
meter centers consist of several sections, Daint sj
be scraped off at points of bolting to insure grounding
continuity.
4.0 MAIN FUSIBLE CLASS T SWITCH -250 VOLT
4.1 Provide a main fusible disconnect switch at the
location shown on the drawing and as specified herein,
4.2 Main switch to be 250 volt, normal duty, multi-pole.
with solid neutral assembly suitable for use as
service entrance ecruinment when bonded to the main
aroundina electrode. all switches shall be UL listed 'to
withstand a 100,000 amp R14S symmetrical short circuit
when compete with Class T rejection type fuses, have a
voidable cover interlock and a NEMA 1 enclosure.
4.3 Provide hinged cover wireway or raceway to connect to
the existina main 400 amp circuit breaker and around
fault relay which shall remain. Main switch shall be
clearly and permanently identified.
4.4 Provide spare fuses per Article 16400.7.
5_.0 P A N EL B 1 0 " 1 : 1 RD S-
5.1 Contractor shall furnish and install branch circuit
panelboards of indicated construction, complete with
all breakers and accessories required for a complete
ELECTRICAL SERVICE AND DISTRIBUTION SYSTEM 16400 - 2
BATHHOUSE NEW HOPE, MINNESOTA 10/31/89
installation.
5.2 Branch circuit panelboards shall be type 00 Load
Centers as manufactured by Square D, G.E., ITE,
Westinahouse, Sylvania, Crouse Hinds, Cutler - Hammer, or
approved equal.
5.3 All other panels shall be equal to Square D, NOO as
indicated on the drawings.
5.4 Circuit breakers shall be thermal magnetic, blues -on
tvDe with a minimum rating of 10,000 A.I.C. full size
breakers only. Multiple breakers. shall be common
type.
6.0 DISCONNECT SWITCHES
6.1 Switches to be normal duty fusible type, and by sa-ne
manufacturer as panels, as follows:
6.2 600 or 250 volt rated, multi-pole, with solid n;=utra!
where required.
6.3 Fusible with quick-make and quick-break operation.
horsepower rated, with voidable door interlock,
6.4 NEMA enclosure type as reauired by application.
6.5 Mount with ton at 78", or as noted.
7.0 FUSES
7.1 Fuses shall be as manufactured by Buss Gould-
Shawmut or approved equal. Provide 10% spare fuses of
each size and tv
END OF SECTION
ELECTRICAL SERVICE AND DISTRIBUTION SYSTEM 16400 - 3
BATHHOUSE NEW HOPE, MINNESOTA 10/31/89
DIVISION 16 - ELECTRICAL
SECTION 16500 LIGHTING
1.0 CONDITIONS
1.1 Refer to Section 16010 Electrical General Provisions
and Section 16100 Electrical Basic Materials and
Methods.
2.0 LAMPS
2.1 Lamps shall be installed in all lighting fixtures
unless specifically noted otherwise.
2.2 Lamps shall be as manufactured by G.E., Sylvania,
Phillips, or approved equal, as follows, except where
noted otherwise.
2.3 Incandescent lamps shall be inside frosted.
2.4 Fluorescent lamps shall be standard output, rapid start
or slimline, warm white, except where noted otherwise.
2.5 Twin Tube Compact fluorescent (PL) lamps shall be
manufactured by Sylvania, G.E. or Philips.
2.6 High output (800 M.A.) fluorescent lamps shall be Wari-
Lite Deluxe energy saver type.
2.7 Mercury vapor lamps (MV) shall be "Warmtone" type with
mogul base.
2.8 Metal halide lamps (MH) shall be the clear type with
mogul base, manufactured by Sylvania, or Phillips.
2.9 High pressure sodium lamps (HPS) shall be clear type,
except where noted otherwise. The lamp and ballast
voltage shall be the highest available where a
particular size lamp is manufactured in more than one
voltage rating.
2.10 Low pressure sodium lamps (LPS) shall be manufactured
by G.E., Thorn, or Phillips.
3.0 BALLASTS
3.1 Furnish and install ballasts in all fluorescent and
"H.I.D." lighting fixtures and assemblies, manufactured
by Advance, Universal, Jefferson, General Electric, or
equal.
3.2 Fluorescent ballasts shall be Class "P", high power
factor, "CMB" certified, "A" sound rating. All 2-lamp,
LIGHTING 16500 - 1
BATHHOUSE NEW HOPE, MINNESOTA 10/31/89
425/430 M.A. ballasts shall be of the energy saver
type, Advance Mark III or equivalent.
3.3 Contractor shall verify the ballast voltage.of all
fluorescent and "H.I.D." lighting fixtures to match the
branch circuit voltage prior to ordering fixtures.
3.4 Ballasts for all H.I.D. lamps shall be constant
wattage, auto-transformer type, except where reactor or
other type is specifically noted. Ballasts for metal
halide lamps shall be lead-peak type.
4.0 LIGHTING FIXTURES
4.1 Contractor shall furnish and install light fixtures as
indicated on the plans, complete with lamps And
accessories necessary for a complete installation.
The Contractor, the fixture supplier and fixture
manufacturer shall be fully informed of the contents
of each fixture description and are cautioned that
the catalog nunbers only d o not necessarily include
all components or features required.
4.2 Where a fixture allowance of a specific amount is
indicated, it shall refer to the Contractor's actual
invoiced cost without mark-up for overhead and profit.
4.3 All fixtures shall be firmly supported by structural
members of the building. In areas without suspended
ceilings, where truss construction is used, fixtures
shall be mounted from the trusses. Where trusses are
not located directly above the fixtures, support same
with wooded members of sufficient strength set between
the trusses and nailed or screwed firmly in place.
Equal means of support shall be installed from wood
joists, purlins, etc., where applicable. Support all
fixtures and chandeliers which weigh in excess of 50
pounds directly from structure and not from suspended
ceiling, or add #12 support wires to the ceiling as
required to adequately support the fixtures.
4.4 All fluorescent fixtures in rows shall be hung level
and in straight lines with fixtures butted tightly, and
pendants spaced to meet fixture mfr's. specifications.
Use jack chains only where specifically noted.
5.0 LIGHTING CONTROL SYSTEM
5.1 Provide photocell, time clock and/or relays as
indicated on the drawings. -
END OF SECTION
LIGHTING 16500 - 2
BATHHOUSE NEW HOPE, MINNESOTA
DIVISION 16 - ELECTRICAL
SECTION 16700 TELEPHONE RACEWAY SYSTEM
1.0 CONDITIONS
10/31/89
1.1 Refer to Section 16010 Electrical General Provisions
and Section 16100 Electrical Basic Materials and
Methods.
2.0 TELEPHONE SERVICE PROVISIONS
2.1 Provide 1-1/4" RPC conduit(s) stubbed out of buildina
24" below grade and capped where shown on the drawings
for Public Telephone Utility Company's (PTU Co-'s)
direct burial underground cable. Stub up 12" AFF at the
Main Telephone Terminal(s) MTT(S).
2.2 Provide arounding conductor to main electrical service
aroundina point with size to meet PTU Co.
requirements.
2.3 Coordinate the timing of PTU Co's cable installation
with the site work and keep them informed as to the
progress of the work.
3.0 TELEPHONE TERMINAL CABINETS
3.1 This Contractor shall provide 1/2" thick 24" wide x
48" high plywood backboard for main terminal (MTT).
4.0 TELEPHONE OUTLETS
4.1 The telephone wall outlets on stud walls or concrete
walls will have a 4" x 4" x 2" outlet box with. a
horizontal split cover plate with a 7/8" diameter hole
in the center complete with vinyl arom-ni.et. Plates shall
match the receptacle plates in the area.
4.2 Telephone outlets shall not be placed in a back-to-back
oosition, but shall be seoarated bv a mini-mum of 12
inches horizontally.
5.0 TELEPHONE CONDUITS
5.1 Provide empty conduit with bushings for multiple
telephone outlets as follows:
A. One outlet
B. Two outlets
C. Three outlets
3/4" diameter
1" diameter
1-1/4" diameter
TELEPHONE RACEWAY SYSTEM 16700 -1
BATHHOUSE NEW HOPE, MINNESOTA 10/31/219
5.2 Conduits shall be run to the main telephone te-ernminal,
or shall be stubbed out of the wall above accessible
suspended ceilinas, or into the unfinished service
space just below the roof or floor.
5.3 Furnishing of telephone instruments, cable, jacks, etc.
will be by others.
END OF SECTION
TELEPHONE RACEWAY SYSTEM 16700 -22
BATHHOUSE NEW HOPE, MINNESOTA 10/31/89
SECTION 16750
1.0 CONDITIONS
PAGING/BACKGROUND MUSIC SYSTEM
1.1 Refer to Section 16010 Electrical General Provisions and
Section 16100 Electrical Basic Materials and Methods.
2.0 SCOPE
2.1 This Section includes all materials, equipment, labor, skills
and tools required to furnish and install a complete Paging/
Background Music system throughout the building and the
outdoor pool area as specified herein and as shown on the
drawings.
3.0 GENERAL
3.1 System shall include back boxes and wiring for a complete and
satisfactorily operating single zone system consisting of
microphone, speakers, cable, volume controls, and amplifier.
3.2 The system shall distribute signal from an available music
source arranged by Owner and paging via a paging microphone
to be located in the managers office and at the cashiers
area.
3.3 Activating the paging shall mute the music.
4.0 PERFORMANCE - TECHNICAL REQUIREMENTS
4.1 The system shall be free of noticeable distortion, clipping,
hum, buzz, hiss and other undesired signals when operated at
required levels.
4.2 Constant voltage loudspeaker distribution shall be 70 volt
unless specifically indicated otherwise.
4.3 The total loudspeaker (in watts) of any amplifier shall not
be greater than 80 percent of the amplifiers continuous sine
wave output rating, as measured at 400 Hertz, i.e. - the
loudspeaker load impedance shall be at least 1.25 times the
amplifiers nominal output impedance.
5.0 SUBMITTALS
5.1 Contractor and system supplier shall produce a wiring diagram
for the complete system.
5.2 Contractor shall furnish complete shop drawing package for
this system. This submittal shall consist of, but not be
limited to:
A. A material list showing quantity, manufacturer, type,
and description of each item being furnished.
PAGING/BACKGROUND MUSIC SYSTEM 16750 - 1
BATHHOUSE NEW HOPE, MINNESOTA 10/31/89
WSJ
6.1
6.2
B. Product data sheets for each item being furnished,
including type of cable.
EQUIPMENT
Equipment shall be as follows - or approved equal.
The amplification equipment shall be mounted on a wall shelf
located in the managers office size to hold the amplifier.
Provide a flush receptacle in the wall 6" above the shelf.
6.3 The amplifier shall be Dukane Model 1A1660 or approved equal,
60 watt RMS output, with less than 1% distortion between 20
and 20,000 Hz., 20 to 20,000 Hz. frequency response, 25 and
70 volt output. The amplifier shall be complete with #2A32
dual input module and protective devices to protect against
overload or short circuit, and shall be mounted on the
shelf.
6.4 Microphona shall be DuKane Model 7A766 - Desk type (2 req.).
6.5 Bathhouse speakers shall be Dukane #5A607, flush mounted in
wall as high as possible, mounted in a #145-226 back box with
a #6A342 steel grille attached with tamperproof screws.
Provide 10'0" cable with wall mike receptacle and matching
plug.
6.6 Exterior horns shall be Dukane #5A31. Mount (1) horn on (1)
existing pool light pole at 20+ feet above grade and (2)
horns on building where shown.
6.7 Volume controls to be Dukane Model 9A1550A locate in basket
rooms.
6.8 Microphone input cable shall be West Penn 290 in conduit.
6.9 Loudspeaker cable shall be West Penn #223 installed in
conduit.
7.0 INSTALLATION
7.1 Contractor shall furnish and install all conduit, junction
and outlet boxes, wiring, etc., as required to provide a
complete system.
7.2 Contractor shall identify and tag all cables with permanent
type markers to denote location served.
7.3 All splices shall be made in an approved manner and shall be
located only in junction boxes and other identifiable and
accessible points.
No splices are permitted in conduits or raceways. When
PAGING/BACKGROUND MUSIC SYSTEM 16750 - 2
BATHHOUSE NEW HOPE, MINNESOTA 10/31/89
splicing shielded cables, continuity and isolation of the
shield shall be maintained throughout the circuit.
7.4 Microphone lines (or any signal line carrying levels of less
than 10 millivolts) shall be installed without splices.
7.5 Microphone lines and program lines shall not be routed near
loudspeaker or power lines.
7.6 Internal loudspeakers shall be tapped at 2 watts and external
horns at 4.0 watts, unless specifically indicated otherwise.
8.0 TESTS AND ADJUSTMENTS
8.1 Upon completion of the installation phase the system supplier
shall thoroughly test and adjust the system to insure proper
operation.
8.2 The supplier shall measure the impedance of the amplifiers
connected load after all units are installed and taps
properly set. These measurements shall be made with proper
test equipment using a 400 Hertz sine wave signal. The
results of these measurements shall be recorded for inclusion
in the as-built manuals. Where required, appropriate
correction(s) and adjustments shall be made.
9.0 MANUALS
9.1 The Contractor shall furnish two (2) complete as-built
manuals as specified in Section 16100 which shall contain the
following:
A. As-built system function block diagrams.
B. Operating and maintenance manuals.
C. Name, address and phone number of the responsible
service organization.
END OF SECTION
PAGING/BACKGROUND MUSIC SYSTEM 16150 - 3
BATHHOUSE NEW HOPE, /MINNESOTA 10/31/
DIVISION 16 - ELECTRICAL
SECT I 1,6.8,0_0
1 _._ 0 CONDITIONS�
ELECTRIC POWER/HEATING EQUIPMENT
1.1 Refer to Section 16010 Electrical General Provisions
and Section 16100 Electrical Basic Materials and
Methods.
2,0 1 SCOPE
2.1 This Section includes all labor, - materials, equiprent,
skills, and tools necessary to install the electric
service to all motors, electrical poT ectuipment,
and controls. The work of this section includes, but
is not limited to, the following:
A. All HVAAC System motors and equipment.
B. All electrical powered equipment furnished under
other sections or divisions of the specifications,
or by others.
C. Control wiring.
D. Manual motor starters.
3.0
3.1
4.0
4.1
5.0
5.1
RELATED I WORK
The following related work is specified under other
Sections or Divisions of this Specification.
A. HVAC and mechanical system equipment is specified
under Division 15.
B. Non-mechanical electrically powered equipment is
specified in Division 2 thru 14.
SHOP DRAWINGS
Provide shop drawings for all types and sizrvs of
motor control equipment furnished under this section
and used on the project.
MANUFA
Manufacturers shall be as specified below, or anorovea
equal. Requests for approval of other manufacturers
shall be made as specified in Section 16010.
ELECTRICAL POWER /HE EQUIPMENT 16800 - 1
BATHHOUSE NEW HOPE, MINNESOTA 10/31/89
6.0 POWER WIRING
6.1 All motors
divisions
otherwise.
to control
install no
shall test
will be furnished and installed under other
of this specification, unless noted
With the exception of motors factory wired
apparatus, the electrical contractor shall
wer wiring for and connect all motors and
same for direction and rotation.
6.2 All motor and equipment ruipment disconnect switches shall be
provided and installed by this Contractor unless noted
or snecified otherwise and shall be non-fused type,
unless specifically noted to be complete with fuses.
Non-fused disconnect switches may be used for roof-top
HVA' units if feeder is protected by an overcurrent
protective device in panel and where approved by thl-:--
local inspector. Switch size may be reduced to 115 of
full load current rating.
6.3 Power wiring is defined as all wiring associated with a
, motor or other item of equipment that carries the same
line current as the motor or equipment. Thus, the
wirina to the main controls of a maanetic starter,
relay or manual starter and from the starter to the
motor. terminals is "Power wiring" and part of this
Contractor's work. All equipment power wirina shall he
provided and installed by this Contractor.
7. CONTROL, WI.,RIING.
7.1 Control devices and wirina shall be defined as "the
devices and wirina associated with a motor or system of
several motors or other equipment, that does not carry
the full load current of the motor or equipment ".
Control wiring may be either line voltage or at some
lesser voltage.
7.2 This Contractor shall furnish and install only those
control devices and control wirina shown on the
drawings and for proper operation of the equipment.
8.0 MANUAL MOTOR STARTERS
8.1 This Contractor shall furnish and install manual motor
starters where shown on the drawings and as specified
herein. Starters shall be Square D, Class 2510
complete with thermal overload elements sized by this
Contractor using the actual motor nameplate data.
8.2 Starters shall be Type FG-1 where surface mounted on
unfinished walls or located at the motor. Provide Type
FS-1 where recessed into finished walls. All -manual
starters located remote from the motor shall have a
built-in pilot light No. FG-1P or FS-1P.
ELECTRICAL POWER /HEATING EQUIPMENT 16800 - 2
BATHHOUSE NEW HOPE, MINNESOTA 10/31/89
Special manual starters such as 2 -pole,
two-speed type, reversing, etc., shall be as specified
on the drawinas. Contractor shall verify the exact
type of reversina or two-speed motor to be suppiie6
before orderincr the manual starters.
8.4 Equivalent equipment manufactured by W_astinqhouse.
ITE, General Electric, Allen Bradley, F.P.1, or
Cutler-Hammer is approved.
END OF SECTION
ELECTRICAL POWER/HEATING EOUIP14EIJT 16800 - 3
November 10, 1989
ADDENDUM NO. 1
Bernard Herman Architects, Inc.
4825 Olson Memorial Highway, Suite 230
Minneapolis, Minnesota 55422
City of New Hope
Swimming Pool Bathhouse and
Equipment Building
- N , ....... . ...
13
This Addendum shall be made a part of the contract documents.
Bidders shall include the work described herein as part of the
Base Bid and insert the Addendum Number in the space provided on
the Proposal Form.
SPECIFICATIONS
Section 0101 - Summary of Work
Item 2.0, General Description of the Work
Delete the phrase "soap dispensers (8)" from third paragraph.
Section 0211 - Demolition
Part I General - Item 1.09, Include List
Add the following item:
F. Trees
Section 0280 - Landscaping
Part I General - Item 1.09, Include list
Substitute "Redwood Chips" in place of rock border, and add
"Landscape Fabric" and "Valley View Edging" to the list of
items.
Part 2 Products
2.03 Landscape Fabric
A. Furnish and install Wheeler Landscape Fabric in all
planting areas and at new trees, installed according
to manufacturer's recommendations.
2.04 Wood Chips
A. Furnish and install redwood chips or bark, 2"+
size, installed at a depth of 3" at all planting
areas and border around buildings.