IP #779
COUNCIL
REQUEST FOR ACTION
Originating Department
Approved for Agenda
Agenda Section
~
By: Guy Johnson By: L-/)--J 8.2
RESOLUTION AWARDING CONTRACT TO DMJ CORPORATION FOR THE 2005 STREET, PARK,
AND UTILITY INFRASTRUCTURE IMPROVEMENT PROJECT
(IMPROVEMENT PROJECT 779)
Public Works
May 9, 2005
Development and Plannin
Item No.
REQUESTED ACTION
Staff requests approval of a resolution awarding a contract for the 2005 Street, Park, and Utility Infrastruchue
Improvement Project 779 to the low and responsible bidder, DMJ Corporation in the amount of $384,084.25.
This price is the total of the Base Bid of $266,070.25 plus $118,014 for the Alternate 2 storm water
improvement. The engineer's estimate for the base bid, plus the alternate was $385,000.
BACKGROUND
The 2005 Infrastructure Project includes improvements to streets, utilities, and Elm Grove Park in the
Wumetka Green area of the city. The project also includes an alternate for reconstruction of the west parking
lot of St. Raphael's Church.
The sh'eet portion of the proposed project includes the consh'uction of a small cul-de-sac on Sumter A venue at
the border of the Wumetka Green Development; restoration of the Sumter A venue and 55th Avenue
u1tersection; and restoration of the u1tersection of 55th Avenue and Quebec A venue. The cul-de-sac is
necessary U1 order to maintain the separation between the Wumetka Green development and the existi11g
neighborhood, and to allow for efficient snow removal. With the necessary improvements to the city's trunk
storm water system and sanitary sewer system late last fall, the two intersections now need asphalt pavu1g
and restoration.
The proposed utility work includes improvements to the sanitary sewer system south of 55th A venue; the
construction of a dry 'water pond U1 the park, and two alternatives for storm water improvements. The
sanitary sewer system proposed 'would decrease the likelihood of the city's sanitary sewer system backing up
U1to homes, and provide the option for additional homes to be connected to the ne"v system if the need would
arise in the future.
~'~N""'d':'
/j 7;;'-
I _-4(/-r~ /{_l~ ~
SECOND BY
TO:
/
I:RFA \ PUBWORKS\ 2005\ 779 Awarding Elm Grove Contract
Request for Action
Improvement Project 779
May 9, 2005
Page 2
Staff is recommendu1g the Alternate Number 2 storm water improvement. This alternate is the construction of
a new storm water system that would collect the storm water that now flows from west to east U1 55th
A venue with the flow from the dry water pond and direct the combu1ed flow through a new storm water
pipe. The new system would flow to the north under the St. Raphael's Church west parking lot, then east in
front of the church, and then be connected to the existing Bass Lake Road storm water system east of the
church. For this alternative it would be necessary for the church to proceed with parking lot reconstruction
and for the city to obtain a utility easement from the church for future maintenance of the system. Alternate
Number 1 storm water improvement is to connect the existing storm water system in 55th A venue to the new
dry water pond, and then connect the outlet from the dry water pond to an existing storm water system that
directs all the storm water flow around the east side of St. Raphael's Church. Both alternatives require the
storage capacity realized by construction of the dry water pond in order to mitigate the overland flows and
possible flooding during very large rain events. In both alternatives the dry water pond would have a berm to
direct overflows across the church's west parku1g lot surface to Bass Lake Road.
Overall plans for the park unprovements u1clude site preparation and curbu1g for the new play equipment, an
improved trail, and landscapu1g. Replacement of the Elm Grove Park play equipment will be addressed in a
separate RF A. The proposed play equipment project would include new play equipment for two separate age
groups (two to five year old children and five to 12 year old children).
The alternate for reconstruction of the church's west parking lot would be a partnership between the church,
the developer, and the city. Staff has a meeru1g scheduled with church representatives to discuss the bid for
the parku1g lot. Based on the bid amount for reconstruction of the parku1g lot and the available funding
indicated by the church earlier, it would appear that the church would like to proceed with the improvements
to its west parking lot at this rune. At the Council meeru1g, staff will share the discussions from the meeting
with the church representatives.
Staff will also review information regarding three additional improvements; a sanitary sewer force mau1, a
water main, and a retau1u1g wall between Wuu1etka Green and St. Raphael's Church. The sanitary sewer force
maU1 and water maU1 would be u1stalled by Ryland, and the retaining wall would be a parh1ership behveen
the church and Ryland with the church's decision to proceed with the improvements to its parking lot.
FUNDING
Recommended fundu1g would be from the Winnetka Green developer, the city's storm water fw1d, the utility
fund, the park dedication fees, and St. Raphael's Church.
ATTACHMENTS
The engu1eer's memorandum, copies of the bid tabulations, the resolution ordering the project and awarding
the contract is attached.
RESOLUTION NO. 05- 67
RESOLUTION ORDERING CONSTRUCTION OF AND
AWARDING A CONTRACT FOR CONSTRUCTION
OF THE 2005 STREET, PARK AND UTILTY
INFRASTRUCTURE IMPROYEMENT PROJECT
(Improvement Project 779)
BE IT RESOL YED by the City Council of the City of New Hope as follows:
1. This Council considered and approved plans and specifications and ordered bids for
construction ofthe 2005 Street, Park and Utility Infrastructure Improvement Project No. 779 (hereafter
Project) at its meeting on March 28,2005. This action and the City staffs bid advertisement action for
the Project is hereby ratified and approved. Based on a consideration of these plans and specifications,
presentations by the City staff and City Engineer on this proj ect and this Councils own consideration
for the need for this project, this Council does hereby determine to proceed with the making of said
proposed Project, and said Project is hereby ordered
? That advertisement for bids for the construction of said Project was published in the
New Hope-Golden Valley Sun-Post, the official newspaper ofthe City, on April 7, 2005 and in The
Construction Bulletin on April 8 and April 15, 2005.
3. That bids for the construction of the Project were duly opened at the New Hope City
Hall, 4401 Xylon Avenue North, at 1:30 p.m. on April 27, 2005 as heretofore authorized by this
Council.
4. It is hereby found and determined by this Council that the bid ofD.M.J. Corporation, a
Minnesota corporation, for the construction of said Project in the amount of $384,084.25, which
includes a base bid of$266,070.25 and an alternate bid ofS 118,014.00, is the lowest responsible bid
submitted for the construction of said Project; that Bonestroo, Rosene, Anderlik & Associates, Inc.,
Engineers for the City, have recommended to this Council per their April 28, 2005 letter attached as
Exhibit A the said low bid for the award of the contract for the construction of the Proj ect to the
designated lowest responsible bid.
5. The Mayor and Manager are authorized and directed to enter into an improvement
contract for the construction of said Project in the name of the City with D.M.J. Corporation, subject
to the said contractor furnishing a public contractor's surety bond, conditioned as required by law.
Adopted by the City Council this 9th day of May, 2005.
-1-
!J!oLCZ~,
Martin E. Opem Sr., I . yor
J
Attest: /tle.UL~ /~.TYU'.--
Valerie Leone~City Clerk
P:\Attomey\Cnh Resolutions\CNH.l0030-016-reso ordering proj and awarding contract project 779.doc
-2-
~ fllA Bonestroo
e Rosene
~ Anderlik &
. \11 Associates
Engineers & Architects
2335 West Highway 36 . St. Paul, MN 551J3
Office: 651-636-4600 . Fax: 651-636-J31J
www.bonestroo.com
April 28, 2005
Honorable Mayor and City Council
City of New Hope
4401 Xylon Avenue North
New Hope, MN 55428
Re: 2005 Street, Park and Utility Infrastructure Improvement Project
File No. 000034-04159-0
Bid Results
Bids were opened for the Project stated above on Wednesday, April 27, 2005 at 1:30 P.M., C.D.S.T.
Transmitted herewith are 10 copies of the Bid Tabulation for your information and file. Copies will also
be distributed to each Bidder.
There were a total of 5 Bids. The following summarizes the results of the Bids received:
Low
#2
#3
#4
#5
Contractor
DMJ Corporation
Sunram Construction, Inc.
Midwest Asphalt Corporation
Dave Perkins Contracting, Inc.
W.E. Miller, Inc.
Bid Amount
$266,070.25
$270,557.95
$270,797.40
$275,684.00
$314,069.75
A/temate #1
$10,005.00
$12,152.00
$10,097.00
$11,472.00
$17,884.00
A/temate #2
$118,014.00
$143,542.00
$125,165.15
$134,164.00
$137,597.75
Altemate #3
$4,581.00
$10,600.00
$5,091.00
$5,325.00
$5,500.00
Alternates #1 and #2 include two different layouts for the storm sewer that would support the project
design. One of these Alternates would need to be included in the award of the project. Alternate #2 is a
more extensive option that would provide additional benefits not provided by Alternate #1. Alternate #3,
which includes a drinking fountain in the park area, was previously not recommended by Council.
Given the additional benefit of constructing Alternate #2, it is recommended that the Base Bid and
Alternate #2 be considered for the award. With this consideration, the low Bidder on the Project was DMJ
Corporation with a Total Adjusted Base Bid of $384,084.25. These Bids have been reviewed and found to
be in order. The low bid was found as follows:
Recommended Contract Award
Part - 1 Sanitary Sewer
Part - 2 Streets
Part - 3 Park Improvements
Part - 4 Parking Lot
Total Base Bid
Alternate #2 - Storm Sewer
Total Adjusted Base Bid
$ 57,830.50
$ 47,627.50
$ 29,076.00
$131.536.25
$266,070.25
$118.014.00
$384,084.25
. St. Paul, St. Cloud, Rochester, Willmar, MN · Milwaukee, WI . Chicago, IL
Affirmative Action/Equal Opportunity Employer and Employee Owned
St. Raphael' Church Parking Lot
The cost for the parking lot reconstruction portion (part 4) that is included in the Base Bid totals
$131,536.25. The parking lot design also requires the burial of the electrical service that serves the
church. This work would be completed by Xcel Energy and is not included in the City contract. The most
current estimate submitted by Xcel for this work is $11,914.15. This cost would be in addition to the bid
price, bringing the total cost of the parking lot to $143,450.40.
St. Raphael Parking Lot Reconstruction Costs
Parking Lot Construction
Burial of electrical service
Total Parking Lot Costs
$131,536.25
$ 1 1,914.15
$143,450.40
A portion of the common excavation for the parking lot is associated with the city's storm sewer
improvements. It is recommended that the design of the new parking lot improve the overland flow from
the park area out to Bass Lake Road during large rain events. To accomplish this, the parking lot was
lowered in certain areas, which increased the amount of excavation required to reconstruct the lot.
The bid unit price for common excavation for the parking lot is $11.00/CY. The estimated quantity for the
parking lot, as designed, is 3,500 CY, giving a total cost of $38,500.00 for excavation. The additional
exca~vation required for the storm se\ver improvements is approximately 60% of the total excavation, or
2,100 CY. The City contribution to the costs for this excavation would be for $23,100. Removing the
estimated $23,100 in storm sewer improvements cost from the total parking lot costs, gives a total parking
lot shared cost of $120,350.40.
Parking Lot Costs to be shared between Ryland, St.
Raphael, and City of New Hope
Total Parking Lot Costs $143,450.40
Additional Common Ex. (City $ 23.100.00
Cost only)
Total Shared Parking Lot Costs $120,350.40
Costs for the parking lot could be split between Ryland Homes, St. Raphael Church, and the City of New
Hope, as previously suggested. The recommended distribution of the costs, based on the actual bid prices,
would be as follows:
Parking Lot Cost Allocation
Entity
Ryland Homes
St. Raphael's Church
City of New Hope
Total Shared Parking Lot Costs
% of Work
20
50
30
100
Cost
$24,070.10
$60,175.20
$36.105.10
$120,350.40
A retaining wall is required along the lot line shared by the Ryland Homes property and St. Raphael's
Church. This retaining wall will be constructed under Ryland Homes' contract with the costs being split
evenly between Ryland and the Church.
The latest cost estimate for the construction of the wall is for $71,080.00. Half of this cost, $35,540.00,
would be the responsibility of the Church. This would put the costs to St Raphael's at $60,175.20 for the
parking lot and $35,540.00 for the retaining walls, totaling $95,715.20.
St. Raphael Church Project Costs
Parking Lot Reconstruction Costs
Retaining Wall Costs
Total St. Raphael Project Costs
$ 60,175.20
$ 35.540.00
$ 95,715.20
The Church has previously indicated that they are prepared to contribute between $95,000 and $100,000
towards the reconstruction of the parking lot. The costs associated with the parking lot appear to be in line
with the Church's expectations.
If the City Council wishes to award the Project to the low Bidder, then DMJ Corporation should be
awarded the Project on the Total Adjusted Bid Amount of $384,084.25.
Should you have any questions, please feel free to contact me at (651) 604-4790.
Yours very truly,
BONESTROO, ROSENE, ANDERLIK & ASSOCIATES, INC.
~~~
Vincent T. Vander Top, P.E.
Enclosures
NN NNNN ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ Z;::;: i~=~
CD CO ---l 0'>01 +:-. (..Jf\,.J-l. c: <1>
0 Ul.f>, (..Jf\.)-a.O CDCO---l 0> Ul .f>, w N ~ 0 3
"
0 ;;: :t>:t>::v OJ
0
0 ~~~W~~~~w~~wOJwnmno~Z~~~~~~~~~wn~~~~~n~~ l>' '" ::s 0 0
w -m ~-<Q -Z~ - -mcmoxo< ~ -~ -~ -~ -mo~mmmmr ~ ~lSo.l1l~
.f>, 8~~~~Q8o~~~~~~z~~m~P~0~0~0~0~~z~~~~~~~~
0 ~ Q. ~ ~ ~
.f>, zor~ ~zQ~n =mI_z~m~~~~mnmnmnmnmz~oOOO~r
..... ;;~~ a
en .f>,m ~ _ ~ nmzo . m m m m ~m <<<< -....
CD n~ ~~Qn~~w~W~mnQ~mm~m~w~w~w~wconmmmmm~~' a ~ ~ 0
0 ~m OJ~~m Onmo ~ -~~~~ ~ ~ ~ ~ =~ZnnOJoZ~W
OJ m~ ~~~m ~~ ~~r~mNm Z Z Z Z~~~ - o-~
~ ~ zcm~;;z ~~m o~rI~. ~ ~ ~ ~ ~<o oo~oQOz ~
X mz 0 OJmro~-<-x zn wOJw ~ ~ ~ >n zzcQ z~ 0
"' 00 ~~~~<~wmn~ ~IO >n> ~ ~ ~ ~~~ ~~~~~ ~ ~
~w mZwommm- m~ -oz zwz -< -< -< -<-- mmzoOJ ~ ~
<~ zg~m z~~ z ~~~ ~3~ w w w w~~ ~~oo -< co OJ
m~ Wwn~ w<~ 0 - n > > m m m m - mmcO ~ 3 c
~- ~ r> ~- w Z ~ ~ ~ ~ ~ ~ ~ z owwOJ m r
>z >~~r >~N > Q - -< -< m m m m Q ~-oc ~ ~ Q
-<0 rOW^ r 0> Z W 0 ~ ~ ~ ~ ~ ~ w _O~w m
r~~ r~ _ m z ~ I - - - - > <m_I ~ 0 (ii"
j; ~Oen I'D :;; ~ ~ z w ~ w w z ~~~ .. z 2- -0
OJ ~.
< m~ -<m ~ m 0 I ~ 0 0 0 0 ~ >~ 0: -0
m :;;< 0 -< ~ 0 0 ~ ~ ~ ~ ~ >~ .2. CD
~ -m ~ r m W W W W ~ -< ~ 0 $l
m ~~ z m m ~ ~ ~ ~ -< "0 CD
CD $l z
z z~ ~ ~ .... ~ ~ co :::J Z Q)
~ Q-< - ~ ~ ~ - S' 3
w 'R P (t)
~ '"
0
~ c ClJ 0
0.. '"
wrr ~~wm rmm m m r m r r r r m w wwm~r ::I :::J
~ww zz~~ ~~~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~-<~mw u; ClJ ~
m (fl ...
0.. (t)
OJ ~
~ "
~ III
...
:0:-
N III
01 .... ~ ~ en ~ 0 _---l ::I
~ ~O>co ~ ---l .f>, N co ~ coco a.
o ~ ~ CODO-#. ~ .f>, ~ CD N (0 0 ~ ~ 0 O(Jl~tv-1. ~ N
- 0 ~
oOJ 0
<.I> C S:C: en
<.I> <.I> "" <.I> ~ ::l ~ ;:;:
",,_en ~ "" <.I> ~ "" N "" ",,_N ;:;: c...a.
0>0 "" "" "--./ <II N <Il W ~ ~ tn <II "" "" <II 0> <IINO " (')!l; ~ a
<1100 (J1-1.-Ef)O wenen .j>. 0 --.I 0 .j>. W W w en <Il ""<IINUlO ... Q Z W
.f>,0 0 WOl.j>.O .j>.ON 0 0 0 0 en co en w 0 ~ -1.~OOO o' 0 ...
~oo OONO tnOO 0 0 0 0 0 0 0 0 0 :.,., OtnOOO "tl 0 III
UlOO ooeno 000 0 0 0 0 0 0 0 0 0 en 00000 <1> O. ~ ~
~~ s:: ...
c
o' (')
::l C
<Il ~ ..,
<II <II <.I> <II "" "" <II <.I> <.I> "" "" <.I> ~ I'D
OJ _N <Il _en ffi fA fA _-J>. 5N ~-1. -Ell ~ ~ ~ Ul W ~ "" _0> ",,_N 0 3'
~ W tn -0 Co tn "" "" "" "" ~
.j>.eno (0(0--.1--.1 (oNN ~ co ~ 0> ---l -1.W~(}lO
NOO en 0> 0>0 enen.j>. en 0 w 0 w N --.I 0 t" w COCOCOOO ...
NOO .j>.0 en 0 ---lOCO 9 0 0 0 .j>. 0 en en 0 ~ ONOOO
tnOO 0000 tnOO 0 0 0 0 0 0 0 0 OtnOOO 0
0 en <
000 0000 000 0 0 0 0 0 0 0 0 0 0 00000 <ll
- - - - - - - - - - - - 0 ~ 3
c ~ m
::l c: c: ~ m <1>
"" "" "" "" "" "" ::l ::I
~<II ~ ~ N N €A in 5..u - a. :::J u;
"" "" "" ... CD Z
OUl "" "" Co <II "" ~ W -Ol ~ tn <II "" <.I> "" Co -&'l t\.) -1. ()1 " III <ll ~ 0
""00 --.lW<.l>O N--.lO 0 0 w en en en en Ul en <.I> ~-1.O~O ... 3 ...
enoo ONCJ10 ---leno 0 0 en 0 (0 w co w 0 .j>. CJ1-2r. 0';::" 0 o' Z ..
000 00-, tn 0 000 0 0 0 0 0 0 0 0 0 tn 00000 I'D (') 0
000 oenoo 000 0 0 0 0 0 0 0 0 0 N 00000 0
::l t.)
~ ~ (') 0
0 0
... - 0
~ c: 0
$l w
<Il "" "" "" <II "" "" "" <.I> "" <.I> "" "" "" <Il "" "" o' .f>,
~w ~ €A :- .-1. {;A ~ _w "" <.I> ~ ~ ~ _CJ1 CJ1 N ..... CD N N "" <.I> "" ",,_w 6
OOUl N(OCDen ~w.j>. -N en N ~ -.,. en -.,. Co Co w CD(OCONen .::l .j>.
enoo O>CJ1CDO 0--.10 0 0 ~ 0 CJ1 N CJ1 0 CJ1 0 owocoo :J ~
000 0(000 enCJ10 0 0 en 0 ~ 0 0 en 0 en 0CJ10COO Ul
000 0000 000 0 0 0 0 0 0 0 0 0 N 00000 !"l (0
~ 0000 000 0 0 0 0 0 0 2- 0 0 0 00000 6
c (')5:m
"" <.I> <.I> "" ~ 0--'
... a. a.
"" "" ~ <II <II ~ "" N <II <II _en "tl:Eo.
co co <II "" Co "" N "" w ~ ~ Co "" <II "" "" en ""wo ~ ~ ~ ~
<II W (0 (0 w"" en wenen .j>. ~ ---l N .j>. W W w en <.I> "" "" W W 0 ...
---leno CJ1Nenen enww w 0 en 0 en CD CJ1 w Ul 0 ONWUlO o' ~-z
tnOO 0:"" COO ooe..., 0 0 0 0 <0 tn 0-, :.,., 0 ~ tne...,tnOO I'D o' ~!=l
000 0000 00CJ1 0 0 0 0 0 CJ1 CJ1 en 0 en woooo ::l "tl w
~ (ti -
::l" ::r
0 ~ '0
~ a ClJ
Gl
"" """" "" "" "" "" "" "" "" "" "" "" "" <Il g- o-
_w "" "" -1. -1. -1.-.It. ~.f:>.. ~ ffi ~ ~ ~ CJ1 W ~ 0> "" "" "" _CJ1 Q ""
"--./<0 "0 Co W Co "--./ "" "" "" (')
CD CD CD ONN .... CJ1 CJ1 CD ~ en w f;f)-20.-Jr.Q)O g' (t)
N W CD -1.~~()l Nenen ---l ~ co .j>. 0 .f>, (0 CD en CD CD(OW--.lO 4-
CJ1eno o.j>..j>.en enCJ1W N 0 .j>. 0 en N ~ CD en N CJ1CJ1.j>.00
000 0000 00:"" 0 0 0 0 ~ 0 N N 0 tn :""tnOOO 0 ~
-.
000 0000 000 0 0 0 0 0 0 en en 0 0 00000 0- s:
- - - - - - - - - C
-om ~ ~
<.I> ~ ::I III -.
"" "" "" "" "" ~ !"l < a. (ti s:
-~"" ~ "" ..... N _N ""~ I'D a.
<II C;;'
NN "" "" CJ1 "" "" "" N tn ~ -.,. "" "" <Il "" en t.9CJ10 " <1> (')
<II 0 CJ1 0'> -1. {;A 0 NCJ1CJ1 CJ1 0 N 0 en en CJ1 en 0 "" iIl""Neno ... "... (t) c;;"
enoo wCDOlO CJ1eno 0 0 CJ1 0 CJ1 0 en 0 0 N -10.010100 o' <ll z <'
000 0000 000 0 0 0 0 0 0 0 0 0 0 00000 ell ~9 (t) OJ
~ ::>
000 0000 000 0 0 0 0 0 0 0 0 0 0 00000 1il .f>,
~ ro
><
0 (') OJ
~ 0 Q
"" ;:a.
"" "" "" "" "" "" "" "" ill "" "" "" "" "" <Il "" "" ""~ ...
~_-1.(;R -1. -1. -1.-1. _N"""" ~ ..... ~ .j>. en N ..... (0 N ~ -EAf;f)~~_U1 III
ONN --""o"otn CDNN "0 CJ1 ~ Co ~ -.,. W N tn "0 -20.~-1.-l.0 a
en 0 CJ1 WCDCOO --.I --.I 0 0 0 N 0 W 0 --.I en 0 N CDNOOO
000 .j>.ooo enCJ10 0 9 CJ1 9 CJ1 0 CJ1 0 0 9 0CJ1000 ::l
000 0000 000 0 0 0 0 0 0 0 0 0 0 00000 ~
000 0000 000 0 0 0 0 0 0 0 0 0 0 00000
CD
a
-l
>
CD
C
r
~
o
Z
ClCD
s:a:
'-0.
n~
g Z
"0 0
o .
... .....
~
o
::l
C/l CD
c: -'
::l 0.
.., 0.
ll> ro
3 ..,
n Z
o !:l
::l tv
~
...
c:
g.
o'
?
5'
p
ns:CD
o -.-'
.., Co 0.
"0 :E 0.
ororo
a~~
o' ~?
::l "0 w
::r
~
5'ClCD
n ll> -.
. < 0.
roo.
"C~
~ Z
~o
~.~
n
o
~
ll>
g.
5'
~
U1(J1(J1(J1(J1(J1 (J1(J1 .l>. .l>..l>..l>..l>..l>..l>. .l>..l>. .l>. wwwwwww wWw ~~ ~ ~~ ;:;:
-.J(j){]l~WN .....0 <D co-Jen(J1.l>.W ~..... 0 <Dco-Jen(J1....w ~.....o <DCO-J en~ 3
CCCD(')::U::US:"C -l(')+>:.l>.CD(')ZS:S:>C/lC/l"C ~-lC/lCD(')~(')CDCCCC-l>C/l::UO::U::U::UCCC/lO-l"C -lC/l
::j::jommo> OO-o>::jOOZzO'U::j> ooen>cO::j::j::j~o>mcmmm::U-lm::U> 00
CCS:S:S:CD~ ~Zm. cz::uooo::Um::U ~~O~C/l::U>ccc'Uo~S:-lS:S:S:o::uo>::U -lo
~~S:~2E.... (') 'Us:-l-loo::um -l o -lZ-ls:s:s:m::u-o-lOOOOm-l~-l >0
r::u::U>->I-l-lm>Ow orz(')z~ ___.l>.mZ<m<<<s:mm~tv r-
ZZ~mmN, 'Um6-lZZ~C/lC/lOo~. ~"COOOI zzz.....oOm::ummm -l~('). "z
00 )> >-l::uIOmomm>C/lo" >. z. OOOCC)>CC(') ~C/l (')C/l >.0
ccm(')Q2::!~ ::u. m )> ~ c ::u 0 m m -l )> - )> S:::U n-> CCC--l- (,)CDCC_~r-l ::u,
C/lC/lXO-lO;o -l'U-l)>C/lC/lOOOm,z::u m-l~::UZZ C/lC/lC/l~m-lCD O::j::j-lmmO::u -l>
CC~OZCz^ Z mOO cs: zccI Zm .....~
w~m~~-lC/ls:s:cc:;;e^ -ltv~-I:_ S:~~S:CCS:I (')s:s:om(')-Im
)>m~~~ Z '~o mos:--)>o~~ C/l~zm)>Z ~mC/lz~ZO ::Uz-'U~cc::U-l 'z
~)>)>m~ 0 " "0 )>0 XXC/lmz -l~(,)o~ m~mOmO)> ~O~~::u~~~ C/l-l
::U-l-l r >)>0 ::u;:>;)>coen.fllo)>" )>~ <b
(')(')omc 0 ;o::u "000 ::u ~'U~~~ ~o(')~o~~ mcc)>~~ " ~'U
^m~ 0 ,)>)>0-1'0 3
OOZC/lC/l -l ->m o.fll 'OC/l< mmCD::u, )>OO~, Z (')C/lC/l-l::jm ::u ~m
cc~6'U .. S:(')-l C ~ ~'U~m -l )>zz rc~O)>~O cO'UOI::U 0 ::u
::U::umm)> zOm 6::UC/l::U~< ~~~::U'U ~
~C/l.$~~ "CcI ::u..... C/lC/l'US: ~
~::u~ ~ ~ (J1Qz~ oC/l~ ::U~.fllOU1~ )>~m 0 s: C/l
. .m , )>:s: <~m .-1 0 'O-l o ::u -I' -l::U z~s:;:>; m m
~-IO;:m mZZ C/l C W )>-l~< ~ o>m c Z ~
'U~~ Z s:om =6 ~ .. ~ g (')=6'Um -l ~~ "0 ~ m
m'U~ -l ::u
mC/l ~ ::Q m m -J ;:>;mm~ ..
~....::j -l "0 ::u < ...w>
cc.....m C/l m (') .....ro~
)> cc )> C/l
)>>-l" 0 -l-l-l-l,m, C/lC/lI C/l C
-l-l(')C/lC/l, ,r-l m C/l,m m, ~
ZZ~~~C/l ~~z )> OOZC/lC/l ~~)> )> ZZZZ~)>~ ~~::u )>C/l ~
, C/l
W W o!=>~ .....
WWU1~(}l ... (J1", -lo. -a. -.J tv ~ W<D w 0
WWO~(J1 0(J1-J . -J..... 00 -J <DCOO~Ol ... (J10..... (J1
0000'10-10. OOUl W O1(]1()l-lo.-lo. 00..... 0 OOOU1(Jl-lo.Q UlOOl ... ..... 0 .::!
c
<t'l <t'l <t'l <t'l <t'l <t'l ~
..... <t'l -lo.-lo. ~(j) <t'l <t'l <t'l .....
<t'l <t'l <t'l (J1 <t'l <t'l <t'l ... "...!W<t'lCotn <t'l en <t'l <t'l <t'l"" ..... ..... ""~ "
":::"(J1-lo.{I)YlO .......... U1 ..... 00-\.00 ""..... (J1 <t'l (J1~tn-lo.&lO&l <t'l<t'l~ U1 0 ""
COW-lo.-lo.NO OlCOW ~ 000100 ~0l0 W W<DWOlWOW w~o ~S ~ :!.
000000 000 0 00000 :':"00 0 0000000 tn~O . n
000000 000 0 00000 U100 0 0000000 aUla 00 ~ro
<t'l <t'l "" "" <t'l "" "" -l
..........w <t'l <t'l ~ <t'l "" <t'l <t'l "" "" ... "" b'> -€A €A €A -lo. b'> Y> "" Y> U1 ""
.?'J~--...JS>>~_--l_-lo. <D _Ol <t'l.W ..... <t'l "".W ....9' -J _-.)..0> €A <t'l ..f:1.. s:o !J1 .-lo. {;f} f.A ~ .....~..... Y>~ -JW sa.
-lo.~CJ1-"-lo.c..n -0 ...<D<D i-J CO<D.l>.CDUl en ~...en ~ ......,JCOWO'l'-J-lo.-.....! i-J.... to ~~ COW !!!.
-J<DO~OO -J 00-J W Ul-J.l>.OO ~ ~OUl ..... -J~OO<DO~ ...-J~ 00 WO
OOOUlOO Ol 00(J1 Ol OUlOOO :--l UlOO 0 OOOOUlOO ~ Ul 0 00 o -J
000000 0 000 0 00000 Ul 000 0 0000000 tnOO 00 tntn
000000 0 000 0 00000 0 000 0 0000000 000 00 00
C
<t'l <t'l b'> b'> "" S:
Ol "" -lo.-lo. WN "" b'> "" Y> <t'l
Y> <t'l "0 <t'l <t'l <t'l ... .-Jw<t'leni-J b'> -J Y> Y> "" "" w ..... w U1 "C
......"""'b'>0 ~.l>.0l 0 010-lo.UlO '" ..... 0 '" Q)(]1(j)-lo.{;AO-Ef) <t'l '" ..... en 0 €A :::!.
Ul-JCOUl~O ~-J0l 0 oocooo WOlO (J1 OlOOlUlWO(J1 w~o 00 wn
OOCOWO,O OOtn 0 oo~oo WCoO 0 tnoo,~ooo, ~<.no 00 I0ro
00-J000 000 0 00000 UlOO 0 OOOUlOOO 000 00 U1
-l
0
"" '" '" "" "" <t'l "" ~
.......... w "" "" ~ b'> <t'l "" "" "" b'> "" Ul "" <t'l -EA (;I) -Ell -lo. <t'l "" <t'l "" "" U1 '"
_~ 5J1 .-l. -€A 5JJ _Ol <D co~... ..... "" "" _....:.w_~ ..... .-lo.p>(;f) "" 5.11.CD p>.-lo. (;I) €A.-lo. .-lo. .!'J.-1J. ...... Yl co...
COUl 0 en 0:>0 "0 CoWto i-J CO<DOOl~ to Ol-J-J W (oOO'>~-.JWW ..... ~ -J "'Ul ww
(Jl""':",+;:"O'>"'""'-JO U1 OUlCO 0 -J-J~UlO Ol -JI\.)O (J1 COOUl.....<DO~ OUlOl ....0 U1CD
00(J11\.)(J10 CD OO-J 0 (J1UlOOO .l>. UlOO !=> (J100CD(J100 000 00 U1-J
0000,00 0 000, 0 000,00 10 000 0 ooo~ooo tnOO 00 ~tn
000000 0 000 0 00000 Ul 000 0 000U1000 000 00 00
C
Yl "" "" "" Yl ::l
.w "" w~ (J1W "" "" "" "" Yl -
Yl "" "" 0 Yl Yl Yl w i-Jto""to'<D Yl en "" "" "" "" ..... ..... I\.) en "C
C,..)~-lo.{A(AO 1\.).....0l <D -J...~OO Y> 1\.)..... Yl tn.p..c.o-.lr..E,A...J.{;A YlYlO ~o (fl :!.
......,-lo.~O..,.,J.O ~COo 0 U1UlWOO w.....o I\.) -J.l>.U1-JWO'" .....1\.)0 U10 wn
OWCOO,~O i.oi.oo 0 000,00 COOO 0, 0, i.OOCOOoi.o tn~O 00 Coro
U1(J1(J1-J00 000 0 00000 000 0 OUlO(J1000 0(J10 00 0
-l
0
Yl ER Yl ER "" ER "" ~
..........(J1 Yl Yl w Yl "" ER Yl Yl ER Yl Yl ~ Yl Yl €A {;A .{A -lo. "" Yl Yl U1 ER
rv(...)-'- ww ... CDER..l>. ..... -.lr.NO'1<J1W ...... sn ER Yl .:-nS:O.f.O_f'Vf,AtR_-:J.. -Yt_-J._-:.to Yl Yl ..... (J1
i-Jento""to"o ~ .....<D(J1 ..... eni-J'ototo ~ <D...0l ..... -lo.OU1tO-J-lo.-lo. (J1<Den <Den {o~
I\.).l>.-J-JOO <D en.l>.O -J WO-JOO .l>. 00..... -J CD <0 O..P..CO-lO.-J WWO 00 (Jl W
Q)CJ1tT1-'-OlO ~ 0(J10 0 -JCO.l>.OO <D 000 (J1 .,I::..-.lr.O-Jr.(Jlocn ~(Jl 0 00 ..... 0
0,0,01000 ~ 000 0 o,~ooo ~ 000 0 00010000 tnOO 00 :':"0
000(Jl00 (Jl 000 0 0(Jl000 (Jl 000 0 000(J1000 000 00 00
C
Yl "" ER ER Yl Yl ~
W ER -lo.-lo. wen Yl Yl Yl .....
Y> ER Yl "0 Yl Yl "" en tntn""tntn ER (Jl YlERER"" ..... ..... Yl ~ "
.l:lt.~-lo.'ERffiO ..... ~ en (Jl OO-lo.OO ER ..... (Jl ER Ot.p..Q')-lo.{;f)()lf,A ER ER U1 (Jl0 {I'} :!.
~.l>.01\.)1\.)0 CO(J1W 0 OOCOOO .l>.eno (J1 (J1COwcowO(J1 NNO 00 ...n
000000 000 0 00000 000 0 0000000 000 00 oro
000000 000 0 00000 000 0 0000000 000 00 0
-l
sa.
Yl Yl ER Y> ER ER "" !!!.
.......... W Yl "" W ER Yl ER "" Yl Yl Yl ER (J1 Yl Y> -Efl {I) €A -lo. Yl ER Yl Yl en Yl
.:.w .... Y' ER .-J .w 0 -J......l>. ..... (;A _-lo. 5"" _w _0') 0 _I\.) .en Yl ER .'" .co .en _w '" "" ...... ~~~~t\.) ER...... .l>. (Jl
C0010N~O Co i-Ji-J"...! to .......-J.CO(Jl()1 en 0",(J1 W <.OO'>WO-....l-lt.N -JCO'" ~ I\.) <0.",
en~O(J1OO -J 0(J1~ (J1 Ul~-JOO <D 00(J1 (J1 (J1"'0(J1<D(J10 .....00 00 eno
000000 !=> 00U1 0 0(Jl000 (J1 000 0 0000(J100 000 00 .l>. 0
000000 0 000 0 00000 0 000 0 0000000 000 00 00
000000 0 000 0 00000 0 000 0 0000000 000 00 00
o
o
o
o
w
...
o
...
.....
(J1
<D
o
OJ
-I
x
en
CD
-l
r0
CD CO coco co co coco co coco-.J -.J-.J-.J -.J-.J-.J-.J -.J-.Jmmm mm mmmmm(]l(]l z::;
c: Cl>
0 0<0 co-.Jm ()l./>.WN~O<O co-.Jm ()l./>.WN ~O{oCP-....I m()l ~WN....).Oc.oCO 3 3
0
0
0 ~~~Gq~~./>.~~~~~~~~ro~Q~~~~o~ (J)-l~G~o;~~,,~ -l~"O"O~"O./>../>.mGro~
W o~~~-<~ = = =00>0
./>. 0~-l000~~u:!00 = = =Omememmmo:r:!:j mO-lOO - .m~r
0 Q~~Z~~ZOO~~~~~Z~~~~~~~rocm ~i!~~~~~6~iTl -l~<<~<~GGZNQ
./>. ~- Z :r:-- GGGeO 0 OOOr~ ~ommromOOOG ~
()l m~~m~~O~~~~"O"O"O~<~<~<<<NG~ ;;of::~~~"O"O<':"':'~ r~~~O~C::ZZ~Gm
<0 Q G-lmr(J)~-l-l mm~m mmm~:r:> - e -I m ~ "'0 mmrmOGGmOQ
0 ~~~-IOiTlm-l-lOO~~~Z~ON Gro~-l':"':'-l "'OiTl~-lO~~~ -l ~. ZZ, Zr~~-IZ~
ro ;;o~-l-l"O-lzmmmG-I
-I -I-Imm;;O;;o OO;;o;;oOOO~Z ~ O~~O m ~;;om~~oo~ m lD
x me ~~ ~~~~~;;o;;O(J)O~;;o zezz z ",z . ;;o;;oz z -l-~~~~mrrirri<~m (5
./>.Zmmzm. ~mOJ
v; ~~ ~~~ ~~G~~~~0~~G G~I 0 ~> ~G~~I 0 .-l~(J)-I(J)-<~Orrri~
~z -1>0 G~~>~~~zm-l"O ~zO . -I -l~ O. -I
m o-l(J)~r .... "'0 ~(J) (J)mo~r (J) >
mO OZ;;o >> Zmmm "O-~ mor N > >~ ~f=m<~2m
. e ;;OI~ -IZGI~~~~rZ-l -I m . Z ~Gmmm . CD lD
G(J) ~O GIIO Z~Qo meo (J) o ~I~~O ~ ;;0 QQ Q ~m . 3 e
r r~ IorormmmoG~~ G(J);;o -l . romm~-l 2S .m.m _m~~~~65~ r
>~ ~mm ror~m~~;;o~m-l~ e"OG 0 .... (J)>;;o~ 0 Z r> ~ ~
. m(J) G;;o Q ~~ ~"O^-<~~(J)
~< ~ ~ ~m~ GG ~ ;;o~~ ;;0 ~ ~z ~ s: 0
(J)m m (J) Z ~r Z e(J) OJ<-I s: r ~r z~ "Omo(J)
()l~ m ;;0 z ~ 0 Gm ~mG (J) a ~~ G ~ o >-< oz ~~ ()l z
m ;;0 ~ ~ ~~ ~ -I~ Z~I m ;;0 ~ I m -l 0' 0-1 < 0
Z ~ I ~ ~(J) ~ ~m o~ro ~ s: ~Z ro ~ I"O ~ m e
-I "0 I ww "0 m~ -I> m "OI > m -l~ "0 ~ ~
m 0 z ~ ~ ;;0 mO ~;:o z "0 m m
-I m Z ~
6 ~ 0 ~ Z 6~ Z o -I
-Irm mmm mmmrrrr mrr ~mr r~~~r-l e
m mrrm m mm ~
z-n~ >>~ >~>-n-n-n(J) ~-n-n -<>(J) ~ ~-n-n~ ~ ~~ -n-n-n-<"z
Ul
IV .... IV
./>.-.J mN ~ -.J Wf'\..)Q) ~o 0
00 ./>.mlV -.J-.J m WIV .... ()l-.JO./>.OO
00.... ~ ~ ~ ....J.(Jl....J.(DWO->.. ~<OO ow.... IV I\.)I\.)-.,.J-J. 0> wo 0()l0000 -<
e OlD
Y> Y> Y> Y> Y> Y> Y> Y> Y> :J s:a:
Y> ()lWN IVIV~ m Y> y>.1V Y> N Y> ;;: <-Co
Y> ./>. enu,.co <0'0<0 Y>Y> Y>c .... Y> wo ./>. -.JY>Y>W Y> Y> Y> Y> Y> Y> "'0 ()~
.... Y> 0 O-.J-.J O()lom.j>.wo mNY> Y> W 0 0 wm()lW ~ ~ .... (;Af;F)-Eft~~-J. Q z
mwo 00()l OOQ-J.ONO ()l0.j>. IVOO 0 (J10()l0 (J1 (J1()l O.j>. (J1 co om ::!.
000 000 0000000 000 000 0 0000 0 00 Nt..JOOCnO (') "0 0
000 000 0000000 000 000 0 0000 0 00 ()l(J10000 <1l o .
.., ....
2'.
o'
Y> :J
Y> Y> Y> Y> ~ Y> Y> -l
Y> Y> Y> Y> Y> EA-l.-fnW....J. Y> Y> Y> Y> ~ Y> Y> Y> W {AEfl{A~W
ro g> .IV Y> (J1WIV .IV ? .~ .<0 .0 Y> _m Y>.wy> ~-J. -EA .t\:> 0 (J1....~ :"Y> .Ef} .-.. 5JJ .->.. _-"- .l'J 0
-l enu,o, '0 Y> . . . Y> Y> ~
W ./>.~.j>. <OIV<O(J1()lmo ....(J1N ()l<OO co .j>.<o.j>.W ()l~ Y> .... (J1-1o.0<OO>O
000 O-.J-.J O()loCON.j>.O mcoo> IV<OO 0 0 -.JIVCOW WIV .j>.()l comolVmo
000 OO()l 000<0000 ()l00 000 ~ 0 00()l0 mo ()l0 -.Jcooooo
000 000 0000000 000 000 0 0 0000 NO 00 a,~oooo
000 000 0000000 ~ 000 0 0 0000 ~ ~ 0()l0000
e (J) OJ
Y> Y> EI> Y> EI> Y> EI> Y> EI> Y> :J c: a:
- :J
N .j>..j>..j>. .j>. NN W Y> y>.m Y> W Y> .., Co
Y> en '0'0.0 cccY>Y>Y>c ~ EI> mco co oY>Y>m Y> Y> Y> .y) En .y} "'0 C> <1l
.... Y> (]l 000 000-.J(J1'/>'0 m ~ Y> Y>coo 0 ommo> ~ .... IV (A EA Ell (Jl ....J. -:r.. ::!. 3 ..,
-.Jwo 000 0001V()l00 om()l 1V(J10 0 om()l(J1 0 00 O()lm()lW()l(') () Z
NOo 000 0000000 000, 0,00 0 0000 0 00 wc..noo~~(f) 0
()lOa 000 0000000 000 000 0 0000 0 00 00000()l 0
:J N
-l ~
0 ..,
Y> Ei c:
Y> Y> Y> EI> .... Y> Y> - ~
Y> Y> Y> EI> Y> EI> {;A-1.E:A.f::o....J. Y> Y> Y> Y> Y> ~ Y> Y> Y> Y> W {A ffi (A -l. (,.) o'
mlVlV ./>..j>..j>. f".o.N.m..j>.y>.w ""_IV",, ~Nm IV .... .Q) wI\.) .-J. -EA .... "" (;fl~wW_N~_-l.
-to :..... a, '0'0'0 OOo-.J.j>.CDO .... CD W <0'00, ~ en o-l.-..IO'> :..,.y> ""N -.J()lm",.j>.(]l ?
00()l 000 ooolVmoo mmco 0(J10 (J1 0 C)->..(]1(D coco WO O-l.OO-"'O :;
000 000 OOoCO()lOO 0.j>.(J1 0(J10 N 0 ON (J1 (J1 00 00 (J11V0000
000 000 0000000 000 000 0 0 0000 00 00 00,0000 ~
~ 000 0000000 000 000 0 0 0000 00 ~ 000000
c ()s:m
Y> Y> "" "" EI> "" "" "" Y> S: o -. a:
m.j>.w WNN 0> "".W .!'J Y> .., Co Co
Y> ~Ot0 w-:;"rv""Y>""c Y> "" "'0 -g ~ ~
"" .j>. .... Y> wm .j>. -.,J{AffiW "" "" Y> Y> "" ""
.... EI> 0 oom ONoQ),;:"W(]l m "''''' ""W(J1 0 mm()lW ~ ....IV En .Ef) {;f} tn --lo. .-II. ::!. 9l~z
-.JIVO 000 000.j>.....1V0 -.Jaw ....()l0 0 (J1OQ)(J1 N N CD Otn-..!...J.-J..-J.(')
0,0,0 000 oooooNO o~{o ~oo 0 0000 0 00 NCoCooN~Cl> -. G:' 0
o .
000 000 00000(J10 000 ()lOa 0 0000 0 00 "'(J1000()l :J "0 ...,
-l :T
0 ~
EI> Ei
Y> Y> "" "" .... "" "" -
"" "" "" "" EI> -EA.....J.-EA~-l. "" "" "" EI> "" ~ "" "" Y> N (I){;RtA-l.N
.-..z .-J. -ER m./>.w ~ ."" .1\.) .....J. :=> -(A .?> "".w"" ........w 0 "" (J1........ <0 "" -EA .-l. ..f::o. .!" .1'\.) .w
-....J,. '0 tv ~oCn '0 . . . Y> <OEl>
o -.J .j>. W-1.f\..)(J1-.1mo ....()IN CD CJl <D (]l W ""N ()lmmOW()l
0(J10 oom oooWOl.j>.()l m<o-.J OO()l <0 0 Wf\.)-l.W 0(0 W Ol ....00l.;:..f\.)0
000 000 ooomW()lO -.J-.JW N(J10 -.J 9 001V(J1 ....m m 0 -.J0l0000
000 000 0000000 0<00 000 0 0 0000 00 00 o~oooo
~ 000 0000000 ~ 000 0 0 0000 00 00 0()l0000
C -oro
"" EI> "" "" Y> EI> "" ~ ::l c> -.
"" "" r < Co
Y> W WW W -l. -l. c.n ""Y' _N Y> III Co
0,0,0, o,o,o,y>""""c Y> EI> Y> """"",,"'0 <1l
"" -.j .... "" mo -.j co "" "" m Y> .... ""
.... Y> (J1 000 ooom.;:..wo (J1~"" ""(J10 (J1 omm(J1 -.j ()l()l (;R{A(A(Jl-Jr....J.::!. "'0'"
COIVO 000 OOOOl(O-.jO 0()l(J1 IVOO 0 0';:" NO (J1 o ()l ~()lm(J1W(]l(') III Z
00,0 000 0000000 000 000 0 0000 0 00 000000<1l ~o
000 000 0000000 000 000 0 0000 0 00 000000 ~. ~
-l
0 G
"" Ei 0
Y> "" "" .... """,,- a
"" "" Y> Y> Y> €A €A E:A ~ -l. "" "" "" ""y, ~ Y> Y, Y> Y, '" (tl-EA(AY}....J.(..J ..,
.-...{.-1. .Ef) WWW .W .<0 .-J. _~ .f\.) {;Ii 5J' "".Ny, ........ ()l ~ .... .!J1!,,_-J,.~ .(0 Y> Y> Y> N-1I.WN~O III
N-.j-.j 0,0,0, cnoco..-co-.,JO ....mw 0,<0'0 -:;,. u, momm ....m ./>.()l wwenrvwc a
0(J1()l 000 ooowco.j>.O ()lCO()l f\.)(J10 -.j 0 0.j>.-.j(J1 ()l0 ()l()l ()l-.j0000
000 000 oOON-.JOO 0()l0 000 IV 9 o co.j>. 0 ()l 0 00 0()l0000 ::l
000 000 0000000 000 000 0 0 0000 00 00 000000 ~
000 000 0000000 000 000 0 0 0000 00 00 000000
1Il
a
-;
l>
1Il
C
r
l>
-;
o
Z
OlIl
s:a:
<-0.
(')~
g Z
"C 0
o .
'" ->.
e!-
el"
::l
1Il
0.
0.
ll>
'"
z
!=>
!'oJ
(')i!:1Il
o -.-.
'" 0. 0.
"C ::l: 0.
Oll>ll>
'" tIl '"
St-z
cq~' !=>
::l "C w
:::r
~
:5"OlIl
o III _.
. < 0.
ll> 0.
"C~
~ Z
:>:'0
~. :.,.
(")
o
a
'"
III
:l
5'
~
CJ)
C
::l
'"
III
3
(")
o
::l
~
'"
c
:l
o'
::l
::I
P
z;:::
~~~~ ~~ ~~~Cll>
~~~m ~.j>. WN->'33
Ob~b~b b66~66 odO~~~~O~ ~d8~8~~~
c-;~-;~-; -;-;-;~-;-; c-;c;:o(')~(')c; ~-;oro~~~~
zl>ml>ml> l>~l>o~l> zl>zZC~Oz~ ml>O(')-;~$$:
-;r r r rrr rr -;r-;-;:ov;:o-;~ r- ~__
l>l>;:Ol>;:Ol> 1Il"C"C<"C"C l>l>~~rom"Cl>z ;:Ol>ZO zzz
zrnr~r l>~~~l>~ zrz~~~Oz~ nrPz 000
-; ::I: -; l> -; CJ);;o;:o "'"' ;:0 ;:0 -;..... -; =;:0.. ~ '::I: -; (') C C C
mcm;;om m-;-;m-;-; m zO(')~ m cm~;:o ~ww
~;:O~3~ ~.j>.W~N~ ~ ~"CO~ 5 ;:o~~~ $:~ro
l>(")l> l> 0" CJ)' , l> z~"CO . (')l>zm ~m~
-;::I:-; -; "C"C ~~ -; ~ZuZ w ::I:-;-;(') -;~~
m-m m ~~ -;~ m -;om~ . -m~ m;:om~
z z z ~~ ~~ z ~ro~6 0 zu~ ~(')83
9 9 9 z- ~l> 9 r~<u ~ 9mro rOc
w !'oJ ~ Q~ ;:0 w ~ ~ ~ !'oJ ~ ~~;:o
. . . r;:o ~ . ~ m ~ . Z 0 W
o CJ) CJ) 00 W 0 z;;o z CJ) 0 ;:o~~
;;0 -; -; -;< m ;:o;:S ~ G) -; Q -;--;
zoo m ~ z Z m 0 c ~-;~
^ ;:0;:0 $: m ^ Q ;:0 ;:0 -; (')~u
(') Z s: s: m ;:0 z S s: ~ ^~m
o ~ z G) (') ;:O.j>.W
:J \11 -I m -.:...-),
'" CJ) ~ro
l> tI)
a. $1
a. 0
ll> '" C
::I Z r mrm ~rQ -;-;::1
a. tI) ~ ~~~ ~~~ zz;::;:
(\) 3 r Vl
~ ll>
~ro tI)
50: ~ 5-
:E~ to l>
iD~ 15 u 8:
g-S;:jQ.'TJ5 (1) c; -'--'-
ll>;::;:=lIltl):J Vl ~ O~.j>. NNO
~~~~x~ ~ ~ -'-o~ oo~ ~~~
oro<CJ)~~ INO
:JO:C:;.~~~ tI)~$ Y> ;:
CPO'J(O::J~~ 3rv<- W ffi ~ ;::;:
o~~~~ ~~n 0 -.:..~-'- ~ ~ffi
:Jii)0~~ - -'0 W NN~ {flN{fl (}l.j>.":J!
a.m~roro ~g~ ~ ~~~ ~~~ ~~~
O:^wm Zll>O 0 000 .j>.oo 00ll>
roON~ ro~ 0 000 (}l00 00
~Q3~~ rn~:
:J VJ~O
.j>.~? M MM {fl
b-~ ~ = ~ ~~~~ ~ ~ ~ ~ ~ ~~ ~~~
N :> ~ ~? ~~~~ ~ .j>. ~ {fl~{fl ~ ~~{fl ~~~
~ ~ 0 0 o~om ro ~ 0 -'-N-'- 0 ~~-.:.. ~-'-~
~ ~ 0 ~W~N W ~ W N(}l~ ->. ~ow NN
~ ~ ~ om~~ 0 -.:.. -'- ~o~ ~ oo~ rn~
o 0 0 ~NO~ ~ 0 0 000 0 000 00
o 0 0 ~(}l00 0 0 0 000 0 000 00
??!P.~~~~ f{~g' ;:
(l)~~ro~8 a~~ ~ ~ ;:;:
o~~~~ Qoro m ~ffi~ ~ ~~~
::Iro. ~N (\)~3 0 ONO M->.{fl ~~::!.
a.a~.j>.O :J~(') 0 000 W~~ 000
5WN ~~o 0 000 NOO ooll>
~~-'- ~~~ 0 000 ~oo 00
tI)~.j>. Z<Ul -;
3......0 ~!l'2 ~
~z~ ~ ~ ~ ~~~~ ffi ffi ~ ~~~
.j>.o~g ~ ~ ~ ~WNrn ~ -.:.. ~ ~~ ~ ffiffi -'--'-
~- ~ ~ ~ 9~~~ ~ P ~ ffi~~ W ~~~ 99
g ~ ~ ~ ~ro~~ ~ ~ ~ ~g~ ~ ~~~ gg
. 0 !'oJ !'oJ ~O~.j>. ~ 0 0 000 N 00(}l 00
o 0 0 ~ooN ~ 0 0 000 0 000 00
o 0 0 ~oo~ 0 0 0 000 0 000 00
??~~~~~ ;:;;:u;:;; ;:
ro ro-'NN :J0a. {fl -.
CD ~__ :J.:E W -EA -69 ....
ouro~~ ~roro W ->'M~ {fl (fl{fl"C
:Jii). ww OO~ ~ ~NN (flN{fl .j>..j>.::!.
a.Ulro~~ :Jx~ ~ ~~~ ~~~ ~~o
O:f; en cD 6r '!' Ul 0 0 0 0 ~ 0 ~ m ~ ll>
ro,<;~o - ::::;'0 0 000 000 010
:J ~w s:~:r -;
~ ow Z !'!. 0
() ~ ~~ i;:R Dr
C.J1 0 -J. ~ N-Jo.-Ef7ffi -Ef) -10.-
~ ~ ~ ~ ~ ~NW~ ~ ~ ~ ~ ~ ~~ ~ffi
~ "C ~ ~? ?~~~ ~ ~ w {fl~~ ~ ~~(fl ~~
w Q 0 ~ 0 ~m~~ ~ 0 W -Jo.~~ -Jo. rorn~ ~w
tI) ~ m ~ ~O~.j>. (}l ~ ~ ~ON m O.j>.~ (}lW
_. ~ ~ ~ ~~rnm ~ ~ C.J1 oom ~ CON m~
o .... . ... ..... .. .. ..
:J g ~ g ~g~~ ~ g g ggg ~ gg~ ~~
orouo~~~~:JO C
150:ii)~2l2l5it:>~ {fl :!.
CD 5!? CD _ _ ^ W CD W -E;A f:A -
oa.u.j>..j>.~O ~ ~M~ {fl ~~"C
::Ia.~m~N,lIl ~ 0 ~......~ {fl->'M ~~~
~~~~~ro ~ 0 ~~o ~~~ ~~n
~b6Z~ ~ 0 000 000 Ooll>
Ul~~-1o. _ ~ 0 000 000 00
Oo(}l~ Ul
m~~S'2 () c;}
O' g ~ -(A En ~ Ej
w~ ~ ~ ~ ~-10.~~ -Ef) -10.-
~ ~ ~ ~ ~ ~~?~ ~ ~ ~ M{fl{fl ~ ~~{fl ~~
~. ~ ~ ~ m~~m ~ ~ g ~~~ ~ g~~ ~~
_ ~ .j>.!'oJ .j>.~0(Jl ~ ~ 0 ~OO .j>. 000 0101
o 0 0 0000 0 0 0 000 0 000 00
o 0 0 0000 0 0 0 000 0 000 00
o
o
o
o
W
.j>.
o
.j>.
~
~
~
o
CD
-;
X
Vi
ro
-;
!,.
COUNCIL
.
? 77 &r-;-U;;U1Z c/- r
Request for Action
Originating Department
Approved for Agenda
Agenda Section
Public Works
By:
Guy Johnson
By:
September 26, 2005
Consent
Item No.
6.4
Resolution approving change order no. 1 for the 2005 Street, Park, and Utility Infrastructure Project
(improvement project no. 779)
Requested Action
Staff is recommending that the Council approve Change Order No.1 to the contract with DMJ Corporation
for the 2005 Street, Park, and Utility Infrastructure Project, in the amount of $29,453.68.
Background
The original contract was $334,084.25 for the 2005 Infrastructure Project. During the project it has been
necessary to adjust some of the work and correct some issues. The contractor has requested a change order to
cover six items that required additional work.
The items are:
1.
2.
3.
4.
5.
6.
Additional storm water installation on 55th A venue
Additional work to offset the water main service to the church
Additional work and delays because of Xcel utility pole conflicts
Additional work for removal of playground equipment
Removal of temporary outlet for the new dry pond
Additional work requested by the St. Raphael's Church
Total
$9,650.35
$5,580.40
$3,410.32
$1,329.11
$1,840.00
$7,643.50
$29,453.68
Part 1 was directed by the Council to be added to the work after the original project had been bid. A new
storm water pipe was installed from the boulevard on the north side of 55th A venue to the south side of the
street and connected to an existing storm water collection system. At a future date, the new pipe could be
extended towards the backyard of 7608 55th A venue to alleviate backyard drainage issues.
Motion by
To:
cut! j
77 ().ttG
Second by ~ I lnL-i/L,
/U/J - VS ~ I / q
I:\RFA \ PUBWORKS \ 2005 \779 2005 Street, Park, Utility e.O. #I.doc
Request for Action Page 2
September 26, 2005
For part 2, the church's cast iron water service had to be offset in order allow the installation of the city's new
storm water system. Part 3 involved the delays associated with working with, and around Xcel's and Quest's
infrastructure.
Part 3 is for the many accommodations that were required from the city's contractor in order to keep the
project progressing while working with and around utility infrastructure.
Part 4 is for the removal of the existing playground equipment in Elm Grove Park. On July 25, 2005, Council
approved a change order that pulled the removal of the existing play equipment from the new playground
equipment contract (project 769) and lowered that contract amount by $1,600.
Part 5 is compensation for the removal of a temporary outlet pipe in the new dry pond. The delays by the
private utility companies delayed the start of the construction for the city's new storm water system in the
church's west parking lot. Staff requested that the developer's contractor install the temporary outlet pipe
when they completed the rough grading of the new dry pond. This allowed the storm water to flow into the
old storm water pipe around the south side of the church during rain events.
The final portion of additional work was requested by St. Raphael's Church and they will be reimbursing the
city.
Funding
Recommended frn1ding would be from the city's storm water frn1d, park dedication fees, and St. Raphael's
Church.
Attachments
The engineer's recommendation, tl1e change order, and the resolution are attached.
I:\RFA \PUBWORKS\2005\779 2005 Street, Park, Utility e.O. #1.doc
CITY OF NEW HOPE
Resolution no. 05- 119
Resolution approving change order no. 1
For the 2005 Street, Park, and Utility
Infrastructure Project
(Improvement project no. 779)
WHEREAS, the city has entered into a contract with DMJ Corporation for the
construction of the 2005 Street, Park, and Utility Infrastructure Project;
and
WHEREAS, during the course of construction, modifications to the approved plans
and specifications were needed to address existing field situations and
conditions; and
WHEREAS, to expedite the project, modifications have been made to the approved
plans and specifications to address the field situations and conditions;
and
WHEREAS, the city has received a cost proposal from DMJ Corporation to modify the
terms of the contract to address these field conditions; and
WHEREAS, the city engineer and staff have reviewed the cost proposal from DMJ
Corporation and find the cost proposal to be appropriate.
NOW THEREFORE, BE IT RESOLVED, by the City Council of the city of New Hope,
Hennepin County, Minnesota:
1. That the City Council hereby approves change order no. 1 in the amount of
$29,453.68.
Adopted by the City Council of the city of New Hope, Hennepin County, Minnesota,
this 26th day of September, 2005.
l1~eA;J;:~
Mayor ,
Attest: ~tILL
City Clerk
I:RFAIPubworks\20051779 Change Order Resolution
Memo
JL]j Bonestroo
-=- Rosene
~ Anderlik &
1 \J 1 Associates
Engineers & Architects
Project Name: 2005 Street, Park and Utility
Infrastructure Improvements
(#779)
Client: New Hope
File No: 000034-04159-0
To: Guy Johnson
Date: September 21,2005
From: Jason Quisberg
Re: Change Order #1
Remarks:
Change Order #1 consists of extra work performed by the contractor, DMJ Corporation, on the 2005 Street,
Park and Utility Infrastructure Improvements proj ect. The Change Order has been divided into six parts,
each relating to an area of work completed.
The work included in the Change Order was required to continue progress and facilitate the completion of
this project along with other current and future projects. Please see the attached Change Order for a detailed
description of each part.
It is recommended that City Council approve Change Order #1 in the amount of$29,453.68. This will
increase the amount of the contract from $384,084.25 to $413,537.93.
Bonestroo, Rosene, Anderlik and Associates, Inc.
www.bonestroo.com
o St Paul Office:
2335 West Highway 36
St Paul, MN 55113
Phone: 651-636-4600
Fax: 651-636-1311
o Milwaukee Office:
12075 N. Corporate Parkway, Ste 200
Mequon, WI 53092
Phone: 262.643-9032
Fax: 262-241-4901
o Rochester Office:
1127"StreetNE
Rochester, MN 55906
Phone: 507-282-2100
Fax: 507-282-3100
o Willmar Office:
205 5th Street SW
Willmar, MN 56201
Phone: 32D-214-9557
Fax: 32D-214-9458
o St Cloud Office:
3721 23" Street S
St Cloud, MN 56301
Phone: 320-251-4553
Fax: 32D-251-6252
o Ubertyville Office:
1860 West Winchester Rd, Ste 106
Grayslake, It 60030
Phone: 847-548-6774
Fax: 847.548-6979
September 28, 2005
DMJ Corporation, Inc.
2392 Pioneer Trail
Hamel, MN 55340-0299
Subject: Change Order No. 1 - Project No. 779 (2005 street, park, and utility
infrastructure improvements)
Enclosed for your records are two fully executed copies for the above-referenced
Change Order. Please forward one copy to your bonding company. The change order
amount is $29,453.68.
This change order was approved by the New Hope City Council at its meeting of
September 26, 2005.
Sincerely,
.i} -
'/'~~.
Valerie Leone, CMC
City Clerk
Enc.
cc: Guy Johnson, Director of Public Works
Vince Vander Top, Assistant City Engineer (BRAA #34-04159)
CITY OF NEW HOPE
4401 Xylon Avenue North. New Hope, Minnesota 55428-4898. www.ci.new-hope.mn.us
City Hall: 763-531-5100. Police (non-ernergency): 763-531-5170. Public Works: 763-592-6777" TDD: 763-531-5109
City Hall Fax: 763-531-5136. Police Fax: 763-531-5174. Public Works Fax: 763-5<12-6776'
Jflj' Bonestroo
-=- Rosene
~ Anderlik &
1 \J 1 Associates
Engineers & Architects
Owner: City of New HODe, 4401 Xylon Ave. N., New Hope, MN 55428 Date July 22, 2005
Contractor: DMJ Corporation, Inc., 2392 Pioneer Trail, Hamel, MN 55340-0299
Bond Company: United Fire and Casualty Co. (IA), P. O. Box 73909, Cedar Rapids, IA 52407 Bond No: 54-152824
CHANGE ORDER NO. 1
2005 STREET, PARK AND UTILITY INFRASTRUCTURE IMPROVEMENTS
CLIENT PROJECT No.:Rff7 71
BRA FILE NO. 000034-04159-0
Description of Work
Storm Sewer Improvements
Additional storm sewer improvements were added to the project, as directed by Council, in attempt to alleviate drainage
issues on properties adjacent to the work involved in this contract. A storm sewer pipe was connected to the existing line
on the south side of 55th Avenue, via a manhole, and extended to the north side of the street and temporarily plugged. At
a later date, the pipe could be extended to the rear yards of the homes located at 7608 and 7616 55th Avenue. A structure
would be placed at the north end of the new sewer to serve as a drain to reduce storm water that collects in this area.
Water Main OtIset
During the storm sewer installation along the north side of St. Raphael's Church, the water service to the church was
found to be in conflict with the storm sewer pipe to be installed. The water service was not shown on any record plans
kept by the Church nor the City of Crystal, where the service is located. To accomodate the new storm sewer pipe, an
offset was installed in the service line, lowering the pipe by approximately two feet.
Utilitv Pole Conflict
A utility pole in the church parking lot was in conflict with the installation of the new storm sewer. Removal of this pole
and associated work pertaining to the overhead lines were not completed prior to the utility contractor installing the pipe
under the City's contract. This delay caused the contractor to: lose one hour of work time, relocate and work around a
conduit installed, and install a temporary pole to support an overhead line during the construction for protection. This
part is compensation for the time spent making these accomodations.
Plav{!round Equipment Removal
The removal of the existing play equipment in Elm Grove Park was part of a separate contract and \vas to be completed
by the contractor awarded that project. Removal of the equipment was required prior to the installation of the storm
sewer through the park. The removal ofthe equipment was not completed when the contractor for this project was at the
point where the installation of the pipe in conflict with the equipment was necessary. To avoid potential additional
charges being brought forth for the inability to complete their work; authorization was given for the contractor to remove
the play equipment so they could proceed with the sewer installation.
Temporar\' Dr\' Pond Outlet Removal
Prior to the installation of the ,storm sewer included in this project, the runoff generated by Phase II of the neighborring
redevelopment was directed overland to Elm Grove Park. The water then flowed into the existing storm sewer system via
a temporary pipe installed near the south edge of the park property. Once the storm sewer was completed, the majority of
runoff from the development could be directed into the new sewer system via an underground pipe. This allowed the
temporary pipe to be removed and all flows to be directed to the new sewer. This part represents compensation for the
removal and disposal of the pipe, buIkheading the existing structure, and constructing the embankment near the structure
in accordance with the plans.
Additional Work Requested Bv Church
St. Raphael's Church requested that additional work be completed by the contractor on the north side of the church. The
work requested was not part of the original project scope. Costs associated with the work included in this part are to be
reimbursed by the Church.
3404159CHOI.xls
No.
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
3404159CHOl.xls
Contract
Item Unit Quantity
CHANGE ORDER NO.1, STORM SE\VER IMPROVEMENTS
REMOVE BITUMINOUS PAVEMENT SY 34
REMOVE BITUMINOUS DRlVEW A Y SY 45
REMOVE CONCRETE CURB AND GUTTER LF 56
REMOVE CONCRETE DRIVEWAY PAVEMENT SY 8
SAWING BITUMINOUS PAVEMENT LF 97
4' DIAMETER STORM SEWER MH EA I
12" PVC STORM SEW'ER, SDR 26 LF 52
12" PVC PLUG EA I
B618 CONCRETE CURB AND GUTTER LF 56
6" CONCRETE DRIVEWAY PAVEMENT SF 75
AGGREGATE BASE, CLASS 5 TN 25
BITUMINOUS BASE COURSE, TYPE 31B TN 6
BITUMINOUS \\TEAR COURSE, TYPE 41A TN 4
TYPE 41 BITU!\1INOUS FOR DRlVEW A YS TN 10
SODDING, LAWN TYPE SY 50
TOTAL CHANGE ORDER NO.1, STORM SEWER IMPROVEMENTS
CHANGE ORDER NO.1, WATER MAIN OFFSET
LOW'ER WATER MAIN @ NORTH SIDE OF LS
('I.n TRCH
TOTAL CHANGE ORDER Nu. 1, W AT}..R MAIN OFFSET
CHANGE ORDER NO.1, UTILITY POLE CON'FLICT
DOVv"N TItvlE FOR POWER POLE REMOVAL LS
ADD-RELOCATE QWEST SLEEVE LS
TEMPORARY POWER POLE FOR QWEST LINE LS
TOTAL CHANGE ORDER NO.1, UTILITY POLE CONFLICT
CHANGE ORDER NO.1, PLA YGROUN'D EQUIPMENT REMOVAL
REMOVE PLA YGROU1\TD EQUIPMENT LS 1
TOTAL CHANGE ORDER NO.1, PLA YGROUN'D EQUIPMENT REMOVAL
Unit
Price
52.75
53.50
53.00
51.45
53.00
53,800.00
544.00
530.00
516.00
54.75
516.00
549.00
553.00
553.00
52.45
55,580.40
5530.32
5 I ,500.00
51,380.00
51,329.11
CHANGE ORDER NO.1, TEMPORARY DRY POl'll) OUTLET REMOVAL
REMOVE TEMPORARY CULVERT@POl'mAND LS I 51,840.00
BULKHEADIEXCA V A TE M'D REPLACE POND
EMBANKlvIENT MA TERlAL M'D COMPACT
TOTAL CHANGE ORDER NO.1, TEMPORt\RY DRY POND OUTLET REMOVAL
CHANGE ORDER NO.1, ADDITIONAL WORK REQUESTED BY CHURCH
REMOVE SHRUBS, LANDSCAPE AND DISPOSE LS 1
OFF-SITE
REMOVE CONCRETE M'D DISPOSE OFF-SITE LS
GRADE AND BACKFILL CURB AND GUTTER LS
INSTALL B612 CURB AND GUTTER WIHMTDICAP LF
ACCESS
INSTALL CONCRETE WALK SF 330 86.15
IMPORT TOPSOIL LS 5520.00
SOD LS 5500.00
F&12"-4" SLEEVE UNDER DRlVE LS I 5124.00
TOTAL CHANGE ORDER NO.1, ADDITIONAL WORK REQUESTED BY CHURCH
I
1
180
TOTAL CHANGE ORDER NO.1, STORM SEWER IMPROVEMENTS
TOTAL CHANGE ORDER NO.1, WATER MAIN OFFSET
TOT.Al CHANGE ORDER NO. I, UTILITY POLE CONFLICT
TOTAL CHANGE ORDER NO.1, PLA YGROU1\'D EQUIPMENT REMOVAL
TOT.Al CHANGE ORDER NO.1, TEMPORARY DRY POl'm OUTLET REMOVAL
TOTAL CHA.NGE ORDER NO.1, ADDITIONAL WORK REQUESTED BY CHURCH
TOTAL CHANGE ORDER NO.1:
5350.00
8520.00
5900.00
$15.00
Total
Amount
$93.50
8157.50
8168.00
811.60
$291.00
53,800.00
82,288.00
530.00
5896.00
5356.25
$400.00
8294.00
$212.00
8530.00
8122.50
59,650.35
55,580.40
55,580.40
8530.32
51,500.00
51.380.00
$3,410.32
51,329.11
51,329.11
51,840.00
51,840.00
8350.00
5520.00
5900.00
52,700.00
52,029.50
8520.00
8500.00
8124.00
57,643.50
89,650.35
55,580.40
83,410.32
51,329.11
51,840.00
57,643.50
$29,453.68
Original Contract Amount
Previous Change Orders
This Change Order
Revised Contract Amount (including this change order)
Recommended for Approval by:
BONESTROO, ROSENE, ANDERLIK & ASSOCIATES, INC.
~~
Date:
Approved by Contractor:
DMJ Corporation
'7-/7- Cl6
$384,084.25
$0.00
$29,453.68
$413,537.93
Approved by Owner:
CITY OF NEW HOPE
1Y (). L In,
tV
9-a6-C75
)
Date
Date
cc: Owner
Contractor
Bonding Company
Bonestroo & Assoc.
3404] 59CHO l.xls
COUNCIL
Request for Action
Originating Department
Public Works
Approved for Agenda
March 13, 2006
Agenda Section
Consent
By:
Guy Johnson
Item No.
By:
6.5
VL!/
Resolution accepting permanent drainage and utility easements for 2005 infrastructure improvements
(improvement no. 779)
Requested Action
Staff is recommending that the Council pass a resolution accepting easements necessary for the
maintenance and operation of drainage and utility facilities. The easements are for the following property:
7301 Bass Lake Road
Church of Saint Raphael, a Corporation
Background
To complete the water main, sanitary sewer, and storm water improvements, it was necessary to acquire
easements from a particular property. These easements were required in order to facilitate construction
and to provide for easements over the water main, sanitary sewer, and storm water pipes running along
the west side of 7301 Bass Lake Road's west parking lot, and over new storm water pipe running along the
middle of the west parking lot and along the north side of 7301 Bass Lake Road. The owner of the property
granted the city of New Hope a permanent easement on the property.
The new improvements to the storm water system, in conjunction with a dry water pond, will help mitigate
overland flows and possible flooding during very large rain events. The city's sanitary sewer force main and
water main were installed by the Winnetka Green developer.
Motion by
Second by
To:
>r
A. \.F:.Fi'i\PTJL\//C}EKS\2GU6 779 2.0U5 In.rrastructl.i.re E21st:::'lr;E:'nt:~:.d::)c
Request for Action
March 13,2006
Page 2
Funding
Funding was provided by the Wi1metka Green developer, the city's storm water fund, the utility fund, and
St. Raphael's Church.
Attachments
Copies of the permanent easements and a copy of the resolution are attached.
!: ",~ I'U!)\'\'()I?KS
\ .~',,-, .,.,
/,.;
i" ,
c:::,tru eit: rc I'.:ilscrnent5.d :;,.
City of New Hope
Resolution No. 06- 48
Resolution accepting permanent drainage and utility easements
for 2005 infrastructure improvements
(Improvement no. 779)
WHEREAS, the city has IDitiated its 2005 infrastructure improvements project 779; and,
WHEREAS, the project involves storm water and sanitary sewer improvements and requires
easements from the 7301 Bass Lake Road property; and,
WHEREAS, the owner of the property will grant the city of New Hope easements on their
property, copies of which are attached; and,
WHEREAS, the easements allow the city access to the property for the operation and
maintenance of the storm water, water, and sanitary sewer improvements; and,
WHEREAS, it would be in the city's best interest to accept the easements.
NOW, THEREFORE, BE IT RESOLVED, by the City Council of the city of New Hope,
Hennepin County, Mllmesota:
1. That the easements attached are hereby accepted.
Adopted by the City Council of the city of New Hope, Hennepin County, Minnesota this 13th
day of March, 2006.
Attest:
~{~ d~
City Clerk
'.,Pub','/urks \,2C:i}'
1:1f".i:ist:-:....:cture L::.,,::rn('j,:~ 1:.2s';.::!l'.i.tion
EASEMENT FOR CONSTRUCTION AND MAINTENANCE
OF VARIOUS PUBLIC IMPROVEl\1ENTS
. TmS INDENTlJRE is made effective as ofthe/O'day of May, 2005, between and among
the Church of Saint Raphael, a Co~-fot"'4';'r~'" (the "Grantor") and the City of New Hope, a
Minnesota municipal corporation (the "City").
WHEREAS, the Grantor is the fee owner of those certain parcels of real property located in
Hennepin County, Minnesota and legally described as follows:
Lot 4, Block 5, J.P. Riedel & Company's St. Raphael Addition
which parcels are located within the municipal limits of two Minnesota municipalities and which
parcels are collectively more commonly referred to as either 7301 Bass Lake Road, City of New
Hope or 7301 56th Avenue North, City of Crystal (collectively referred to hereafter as the
"Property"); and
WHEREAS, the City wishes to obtain various drainage and utility easements over, under
and across portions of the Property; and
WHEREAS, the Grantor is willing to grant such easements pursuant to the terms and
conditions outlined herein.
NOWWITh""ESSETH; That the Grantor in consideration of the sum of One Dollar ($1.00)
and other good and valuable consideration, the receipt and sufficiency of which is hereby
acknowledged by Grantor, does hereby grant, bargain and convey unto the City and its successors
and assigns, forever, permanent easement rights over, under and across all Easement Tracts
described below, including full and free right and authority to enter upon each and every Easement
Tract and make such use of any and all of the Easement Tracts as is reasonably necessary and
advisable in the construction, maintenance and operation of drainage and utility facilities (included
but not limited to storm sewer facilities).
The permanent easements herein granted are situated over, under and across the following
tracts ofland (collectively the "Easement Tracts" and each individually to be known as an "Easement
Tract") located in Hennepin County, Minnesota:
1. All the part of Tract A, Registered Land Survey No.1 026, according to the recorded
plat thereof, lying northerly and westerly of the following described line:
Commencing at the northeast corner of said Tract A; thence on an assumed
bearing of North 89 degrees 45 minutes 26 seconds West, along the north line
of said Tract A, a distance of33.35 feet, to the point ofbeginning of the line
to be described, thence South 00 degrees 07 minutes 02 seconds West, a
distance of 268.98 feet; thence South 45 degrees 06 minutes 47 seconds
West, a distance of 29.44 feet, thence South 88 degrees 15 minutes 23
seconds West, a distance of36.89 feet to the west line of said Tract A and
there terminating.
2. The South 10 feet of the North 38 feet of Lot 40, Auditor's Subdivision No. 226,
according to the recorded plat thereof.
3. The west 5.00 feet of the south 279.00 feet along with the area enclosed by a 10 foot
wide easement centered on the following described centerline. The centerline of said
easement begins at a point on the west line of Lot 39, Auditor's Subdivision No. 226,
according to the recorded plat thereof, 281.59 feet North of the southwest corner of
said Lot 39; thence on a assumed bearing of North 56 degrees 14 minutes 32 seconds
East a distance of 64.16 feet; thence on an assumed bearing of South 89 degrees 48
minutes 35 seconds East a distance of81.65 feet and there terminating at a point on
the east line a distance of plus or minus 38.00 feet south of the northeast comer of
said Lot 39. The sidelines of said easement are to be lengthened or shortened to
terminate at the east and west lines of said Lot 39.
4. The East 5.00 feet of the South 287.61 feet of Tract A, Auditor's Subdivision No.
226, according to the recorded plat thereof.
5. The West 10.00 feet of the North 38 feet of Lot 40, Auditor's Subdivision No. 226,
according to the recorded plat thereof
[The Remainder Of This Page Is Intentionally Left Blank; Signature Page Follows]
Church of Saint Raphael
STATE OF MINNESOTA )
) ss.
COUNTY OF )rJ-If;.JNet1',.} )
The foregoing was acknowledged before me this OJ-~ day of }'Y1 /1- Y ,2005, by
p:-,.- (V\4 r" K' J v e -!-fN"'''' and , the' and
of the Church of Saint Raphael, Grantor, on behalf of Grantor.
A/;.tJ' ;3 ~~
~~~lic ,,_ _ ~ 1" (A \ r-:./1 / 3 I
~}r-"' ...... u"'" r=Yt.,/{.J ._, 1-:;20 0
I, the undersigned, being the duly qualified and acting Clerk of the City of New Hope,
Minnesota, hereby certify that the Council of said City has duly accepted the foregoing easement.
Dated:
,2005
New Hope City
Dra ed B :
JENSEN & SONDRALL, P.A.
8525 Edinbrook Crossing, Suite 201
Brooklyn Park, l\1N 55443
(763) 424-8811
P:\Attorney\Crn.'<\Clienls\CNH'\99-1 !330\CNH99-11330-Drainage & Utility Easement-D2,doc
Church of Saint Raphael
STATE OF MINNESOTA )
) ss.
COUNTY OF l1-eNNd1~ )
The foregoing was acknowledged before me this IOH day of M ,4 Y ,2005, by
p:-y- (Y\4r K Jve.f-frV~r and , the - and
of the Church of Saint Raphael, Grantor, on behalf of Grantor.
;/~"J-;3 ~t.~
~hc CoI"-i'\.loSSIO,..l Ey/lf't,,; )-])-;;20/0
I, the undersigned, being the duly qualified and acting Clerk of the City of New Hope,
Minnesota, hereby certify that the Council of said City has duly accepted the foregoing easement.
Dated:
,2005
New Hope City Clerk
Dra ted B :
JENSEN & SONDRALL, P.A.
8525 Edinbrook Crossing, Suite 201
Brooklyn Park, l\1N 55443
(763) 424-8811
P:lAttomey\Crn.<ICliontslQ.;"H\99-113301Q.;rl99-11330-Draioage & Utility Eas=ont-D2,doc
COUNCIL
1:.t)i\.A:V2L-bt.J
Request for Action
Originating Department
Approved for Agenda
Agenda Section
Public Works
June 26,2006
Consent
Item No.
By: Guy Johnson
By:
6.6
Resolution approving change order no. 2 for the 2005 Street, Park, and Utility Infrastructure Project
(improvement project no. 779)
Requested Action
Staff is recommending that the Council approve change order no. 2 to the contract with DMJ Corporation for
the 2005 Street, Park, and Utility Infrastructure Project, in the amount of $3,018.75.
Background
Tne original contract was $384,084.25 ror the 2005 Infrastructure Project. The Council approved change order
no. 1 last September that increased the contract to $413,537.93, to allow for additional work the city and St.
Raphael's Church requested the contractor to perform.
The contractor has requested a second change order to cover three items that required additional work.
The items are:
1. Additional asphalt patching next to the city's new sidewalk
along Bass Lake Road
2. Additional work at the end of 5510 Sumter resident's driveway
3. Additional work to remove silt fence around the new dry pond
Total
$1,871.05
975.20
172. .50
$3,018.75
Part 1 was work on Bass Lake Road next to the new sidewalks that was originally to be completed by the
city's sidewalk contactor. Because DMJ Corporation's contract already had quantities for asphalt to patch Bass
Lake Road in front of St. Raphael's new west parking lot, it was more efficient and timely to have them
complete the work in front of the city's new sidewalk. This work and costs were removed from the sidewalk
project. It also allowed for the opening of both east bound lanes of Bass Lake Road to traffic sooner.
Motion by ,dU-c.l) ?.;zf:J1.J/~
To: tLettt /" I
Second by
I: \ RF A \ PUBWORKS \ 2006 \ 779 2005 Infrastructure Change Order-doc
Request for Action
June 26, 2006
Page 2
Part 2 was for additional asphalt work beyond the contract specifications at the end of a driveway at the
request of the property owner.
Part 3 was for the removal of silt fencing around a portion of the dry pond at Elm Grove Park that was
installed by the park grading contractor. With the weather and the private utility work delays in the 2005
Street, Park, and Utility Infrastructure Project, the turf was not established before the grading contractor's
project was completed. It was therefore more economical to have DMJ Corporation complete this work than
having the grading contractor return.
Funding
Recommended funding would be from the city's storm water and street infrastructure funds.
Attachments
The engineer's recommendation, the change order, and the resolution are attached.
I: \ RF A \ PUBWORKS \ 2006 \ 779 2005 Infrastructure Change Order.doc
CITY OF NEW HOPE
RESOLUTION NO. 05- 91
Resolution approving change order no. 2 for the
2005 Street, Park, and Utility Infrastructure Project
(ilnprovement project no. 779)
WHEREAS, the city has entered into a contract with DMJ Corporation for the
construction of the 2005 Street, Park, and Utility Infrastructure Project;
and
WHEREAS, during the course of construction, modifications to the approved plans
and specifications were needed to address existing field situations and
conditions; and
WHEREAS, to expedite the project, modifications have been made to the approved
plans and specifications to address the field situations and conditions;
and
WHEREAS, the city has received a cost proposal from DMJ Corporation to modify the
terms of the contract to address these field conditions; and
WHEREAS, the city engineer and staff have reviewed the cost proposal from DMJ
Corporation and find the cost proposal to be appropriate.
NOW THEREFORE, BE IT RESOLVED, by the City Council of the City of New Hope,
Hennepin County, Minnesota:
1. That the City Council hereby approves Change Order No.2 in the amount of
$3,018.75.
Adopted by the City Council of the City of New Hope, Hennepin County, Minnesota,
this 26th day of June, 2006.
"b~
Mtor Pro tern
Attest:
Ilwcn(~~u
City Clerk
I:RFA\Pubworks\2005\779 Change Order No, 2 Resolution
.11. Bonestroo
9 Rosene
"I\lI Anderfik &
.. \J. Associates
Engineers & Architects
2335 West Highway 36. St. Paul, MN 55113
Office: 651-636-4600 . Fax: 651-636-1311
, www.bonestroo.com
June 16,2006
Mr. Guy Johnson
City of New Hope
5500 International Pkwy.
New Hope, MN 55428
Re: 2005 Street, Park, and Utility Infrastructure Improvements, City Project No. 770
Change Order #2
BRAA # 000034-04159-0
Dear Guy:
Some additional work was required for the successful completion of the above project. Enclosed are four sets of
signed Change Order #2. Brief descriptions of the extra work are given below.
Some street patching was required to provide a smooth transition between the Winnetka Avenue Sidewalk project
and this project. This patching was originally intended to be part of the Sidewalk contract. Due to timing issues,
the work was eliminated from the sidewalk project and completed by DMJ under this contract. The contractor has
requested $1,871.05 to cover all expenses associated with this work.
A driveway approach on Sumter Avenue was disturbed by the construction of the turn around. In response to
requests from the resident, additional existing driveway pavement was removed and replaced with new
bituminous pavement. $975.20 has been requested to cover the costs for the additional driveway work.
Approximately 150 feet of silt fence was installed in Elm Grove Park by the contractor that completed the grading
of the park. Erosion control measures were to remain in place until the new turf was established. To simplifY the
work, DMJ removed the silt fence while on site, eliminating the need for remobilization of the grading contractor
to come in and complete the work. DMJ has requested $172.50 for the removal and disposal of the fence.
It is recommended that the City Council approve the enclosed Change Order #2 in the amount of $3,018.75. This
will increase the amount of the contract for the project from $413,537.93 to $416,556.68. Note that the total
project costs will be approximately $29,900 under budget.
Sincerely,
BONESTROO ROSENE ANDERLIK & ASSOCIATES, INC.
~~
Jason Quisberg
Enclosure
· St. Paul, St. Cloud, Rochester, MN · Milwaukee, WI · Chicago, IL
Affirmative Action/Equal Opportunity Employer and Employee Owned
JQj Bonestroo
-=- Rosene. .
"till A nderh I< &
1 \j 1 Associates
Engineers &. Architects
Owner: City of New Hope, 440 I Xylon Ave. N" New Hope, 1vrN 55428 Date June 16. 2006
Contractor: DMJ Corporation, 2392 Pioneer Trail, Hamel, MN 55340
Bond Company: United Fire and Casualty Co" p, O. Box 73909, Cedar Rapids, LA.. 52407 Bond No: 54-152824
CHANGE ORDER NO. 2
2005 STREET, PARK, AND UTILITY INFR,-\STRUCTURE IMPROVEMENTS
CLIENT PROJECT NO,770
BR,-\ FILE NO. 000034-04159-0
Description of Work
Bass Lake Road Patching
Some street patching on Bass Lake Road was required to create a smooth transition between the Winnetka Avenue Sidewalk
project and this project. TIus patching was originally to be part of the sidewalk project contract. To eliminate delay in closing
the sidewalk contract and streamline project coordination efforts, the work was completed lmder this contract.
Drivewav Improvements
In response to a resident's request, additional existing pavement on Sumter Avenue driveway \vas removed and replaced with
ne\v to create a finished product that better met the expectations of the resident. This work included removal and replacement
of additional bituminous driveway pavement.
Silt Fence Removal
Approximately 150 LF of silt fence was installed by the contractor responsible for the grading of the dry pond in Elm Grove
Park. TIle silt fence could not be removed until the turf was established, wluch did not occur until tius spring after tile
grading contractor moved out of town. To simplifY tile work, DMJ removed the fence \vlule on site. This eliminated tile need
to pay remobilization costs for the grading contractor to come back to tile site and remove the fence.
Contract
Unit
Price
Total
Amount
3
BASS L<\KE ROAD PATCHrNG
DRIVEWAY IMPROVEMENTS
SILT FENCE REMOV AI..
TOTAL CR"\NGE ORDER NO.2:
LS
LS
LS
S I ,871.05
5975,20
S 172.50
51,871.05
5975.20
53,018.75
34C4159CH02.xls
Original Contract Amount
Previous Change Orders
This Change Order
Revised Contract Amount (including this change order)
CHA1~GE IN CONTR~CT TIMES
Original Contract Times:
Substantial Completion (days or date):
Ready for final Payment (days or date):
Increase of this Change Order:
Substantial Completion (days or date):
Ready for final Payment (days or date):
Contract Time with all approved Change Orders:
Substantial Completion (days or date):
Ready for fmal Payment (days or date):
$384,084.25
$29,453.68
$3,018.75
$416,556.68
Recommended for Approval by:
BONESTROO, ROSENE, ANDERLIK & ASSOCIATES, INC.
~~
Approved by Contractor:
DlVIJ CORPORATION
Date
cc: O\vner
Contractor
Bonding Company
Bonestroo & Assoc,
3404159CH02,xls
Date:
6-/9-06
Approved by Owner:
CITY OF NEW-H1lE -
~ // \ J/
,/ I J ) I /
1/ "'\ .~./
/~XtiI-P ~ ' t~~
" - 6h?/c(
/
Date
June 28, 2006
DMJ Corporation
2392 Pioneer Trail
Hamel, MN 55340
Subject: Change Order l\lo. 2 and Final Payment
Project No. 779 (2005 Infrastructure Project)
Enclosed for your records are two fully executed copies for the above-referenced Change
Order. Please forward one copy to your bonding company. The change order for
$3,018.75 was approved by the New Hope City Council at its meeting of June 26, 2006.
Also, the final payment of $22,355.29 was approved at the June 26 meeting. Once the
city receives an approved IC-134, the check will be released. The IC-134 withholding
affidavit can be processed on-line at www.taxes.state.mn.us.
Sinc~rely" /"
, //- f:-/
',--",;--, )(:/~--},~: f?
< /.~ // / ~~.
/\,~,///~." ~
'-'" J
Valerie Leone, CMC
City Clerk
Enc.
cc: Guy Johnson, Director of Public Works
Vince Vander Top, Assistant City Engineer (BP~ #34-04159-0)
OF
4401 Xylon Avenue North <, New Hope. Minnesota 55428-4898 <V Vv\vw, ci.nevv'-hope.ml1.us
City Hall: 763-531-5100'" Police (non-emergenc:y'): 763-531-5170 <, Public Works: 763-592-6777 TDD: 763-531-5109
Cit\i Hall Fax: 763-.531-5136 ~,. Police Fax: <> Public ~\.'Vori(s Fax: 763-592-6776
COUNCIL
Request for Action
Originating Department
Approved for Agenda
Agenda Section
Public Works
June 26, 2006
Consent
Item No.
By:
Guy Johnson
By:
,
6.7
Resolution to accept the 2005 Street, Park, and Utility Infrastructure Project and approve final payment
request (ilnprovement project no. 779)
Requested Action
Staff recommends that Council approve a resolution to accept the 2005 Street, Park, and Utility Infrastructure
Improvement Project 779 and authorize final payment to DMJ Corporation in the amount of $22,355.29.
Background
The Council approved plans and specifications for the 2005 Street, Park, and Utility Infrastructure project at
its March 28, 2005, meeting and awarded a contract to DMJ Corporation in the amount of $384,084.25 on
May 9,2005.
The 2005 Infrastructure Project included ilnprovements to streets, utilities, and Elm Grove Park in the
Wilmetka Green area of the city. The project also included the construction of a dry pond, a new storm water
collection system, and the west parkIDg lot of St. Raphael's Church.
The street portion of the proposed project included the construction of a small cul-de-sac on Sumter Avenue
at the border of the Wilmetka Green Development; restoration of the Sumter A venue and 55th A venue
intersection; and restoration of the intersection of 55th Avenue and Quebec Avenue. The cul-de-sac was
necessary in order to maintain the separation between the Wilmetka Green development and the existing
neighborhood, and to allow for efficient snow removal. With the necessary improvements to the city's trunk
storm water system and sanitary sewer system in the fall of 2004, the two intersections required asphalt
paving and restoration.
Motion by
J--1z .
l /(i;-1 /1
/"-""',. 'VVJ I
~i '-){;ltll,
-
Second by
/
To:
00 9;)-
I: \ RF A \ PUBWORKS \ 2006 \ 779 2005 Infrastructure Fina!.doc
Request for Action
June 26, 2006
Page 2
The utility work included improvements to the sanitary sewer system south of 55th Avenue; the construction
of a dry water pond in the park, and storm water improvements. The sanitary sewer system improvements
completed will decrease the likelihood of the city's sanitary sewer system backing up into homes, and provide
the option for additional homes to be connected to the new system if the need would arise in the future.
The park improvements under this contract included site preparation and curbing for a new play area, an
improved trail, and landscaping. Replacement of the Elm Grove Park play equipment was addressed with a
separate project. The play equipment project included new equipment for two separate age groups of
children.
The reconstruction of the church's west parking lot was a partnership between the church, the developer, and
the city. The parking lot project allowed for the reconfiguration of the storm water collection system and for
additional parking space for the church.
Funding
DMJ Corporation's original bid for the project was $384,084.25. There were two change orders for additional
work requested by the city and the church. The change orders increased the overall contract by $32,472.43.
The net change to the original contract was an increase to $416,556.68. The final amount earned by DMJ
Corporation was $386,614.59 or 7.2% under the contract amount.
Funding was from the Wilmetka Green developer, the city's storm water fund, the utility fund, the park
dedication fees, and St. Raphael's Church.
Attachments
Attached are copies of the resolution, the engineer's memorandum recommending the acceptance of the
project, and the final pay request.
I:\RFA \PUBWORKS\ 2006\ 779 2005 Infrastructure Final.doc
City of New Hope
Resolution No. 06- 92
Resolution to accept the 2005 Street, Park,
and Utility Infrastructure Project
and to approve the final payment request
(improvement project 779)
WHEREAS, the city has entered into a contract with DMJ Corporation for the construction of
the 2005 Street, Park, and Utility Infrastructure Project; and,
WHEREAS, staff is recommending that the Council adopt a resolution to accept
improvement project 779 and approve final payment to DMJ Corporation in the
amount of $22,355.29; and,
WHEREAS, the city engineer has reported that all work has been satisfactorily completed
and recommends that final payment be made to DMJ Corporation.
NOW, THEREFORE, BE IT RESOLVED, by the City Council of the city of New Hope,
Hennepin County, Milmesota:
1. That the city COlillcil accepts the 2005 Street, Park, and Utility Infrastructure
Project from DMJ Corporation.
2. That the city manager is hereby directed to authorize the final payment of
$22,355.29 to DMJ Corporation subject to submittals of the required IC-134
forms.
Adopted by the City Council of the city of New Hope, Hennepin County, Minnesota this 26th
day of June, 2006.
'fli
Mayor Pro Tem
Attest:
j/ .v
1 {11~L:z2tnL~
City Clerk
I:RFA \Pubworks\2006\779 Final Resolution
Bonestroo
m:::::E Rosene
"I\lI Anderlik &
. ~. Associates
Engineers & Architects
12335 West Highway 36. St. Paul, MN 55113
Office: 651-636-4600 . Fax: 651-636-1311
www.bonestroo.com
June 19,2006
Mr. Guy Johnson
City of New Hope
5500 International Pkwy.
NewHope,~ 55428
Re: 2005 Street, Park, and Utility Infrastructure Improvements, City Project No. 770
Request for Final Payment
BRAA # 000034-04159-0
Dear Guy,
Enclosed fInd the signed fInal pay request for the 2005 Street, Park and Utility Infrastructure
Improvements project. All work has been completed and accepted by both the City and St. Raphael's
Church.
The fInal contract amount is for $416,556.68. Final payment is for $22,355.29, bringing the total cost to
$386,614.59 or $29,942.09 (7.2%) under budget. The majority of savings is a result of a significant
reduction in the amount of Class 5 Aggregate required due to the ability for the contractor to salvage and
reinstall existing aggregate in the street and parking lot sections.
We recommend final payment be approved in the amount of $22,355.29. Payment could be released
upon receipt of all necessary IC-134's. Please feel free to contact me at 651-604-4938 if you have any
questions.
Yours truly,
BONESTROO, ROSENE, ANDERLIK & ASSOCIATES
~~
Jason Quisberg
Enclosures
· St. Paul, St. Cloud, Rochester, MN · Milwaukee, WI · Chicago, IL
Affirmative Action/Equal Opportunity Employer and Employee Owned
I. ..- ......
.'..'.. -.........."',"'..........'....
........._...H......
:. ..' .>Bonestroo
..II~~
I'.'. '. ...AssOdate.s.
. .......
.- . .....................-.
/'. " '"', .,......;.::-:............'..........-.'.
Eli9~eer$&,A.!illit~
Owner: Ci
e, MN 55428
Date:
Re uest No:
June 19, 2006
5 AND FINAL
For Period: 12/13/2005 to 6/19/2006
Contractor: DMJ Co oration, 2392 Pioneer Trail, Hamel, MN 55340
CONTRACTOR'S REQUEST FOR PAYMENT
2005 STREET, PARK, AND UTILITY INFRASTRUCTURE IMPROVEMENTS
BRA FILE NO. 000034-04159-0
CITY PROJECT NO. 770
SUMMARY
Original Contract Amount $ 384,084.25
2 Change Order - Addition $ 32,4 72.43
3 Change Order - Deduction $ 0.00
4 Revised Contract Amount $ 416,556.68
5 Value Completed to Date $ 386,614.59
6 Material on Hand $ 0.00
7 Amount Eamed $ 386,614.59
8 Less Retainage 0% $ 0.00
9 Subtotal $ 386,614.59
10 Less Amount Paid Previously $ 364,259.30
11 liquidated damages - $ 0.00
12 AMOUNT DUE THIS REQUEST FOR PAYMENT NO. 5 AND FINAL $ 22,355.29
Recommended for Approval by
BONESTROO, ROSENE, ANDERLlK & ASSOCIATES, INC.
Y2~~
Approved by Owner:
CITY OF NEW HOPE
Specified Contract Completion Date:
September 30, 2005
Date:
3404159REQ5FINALxls
Contract Unit Current Quantity Amount
No. Item Unit Quantity Price Quantity to Date to Date
PART 1 . SANITARY SEWER:
1 MOBILIZATION LS 1 12000.00 1 $12,000.00
2 CLEAR AND GRUB TREE 2 250.00 1.3 $325.00
3 REMOVE DOGWOOD BUSH EA 4 20.00 4 $80.00
4 REMOVE BITUMINOUS DRIVEWAY SY 85 4.50 29 $130.50
5 REMOVE CONCRETE SIDEWALK SF 180 1.00 192 $192.00
6 REMOVE CONCRETE DRIVEWAY PAVEMENT SF 510 1.45 249 $361.05
7 CONNECT TO EXISTING SANITARY SEWER 8" PVC PIPI EA 1 650.00 1 $650.00
8 8" PVC SANITARY SEWER, SDR 35,8'-10' DEEP LF 185 33.00 329 $10,857.00
9 8" PVC SANITARY SEWER, SDR 35,10'-12' DEEP LF 25 35.00 $0,00
10 8" PVC SANITARY SEWER, SDR 35,12'-14' DEEP LF 40 38.00 $0.00
11 8" PVC SANITARY SEWER, SDR 35, 14'-16' DEEP LF 79 46.00 $0.00
12 4' DIAMETER SANITARY MH, 8' DEEP, INCL R-1642-B
CSTG EA 2 2500.00 2 $5,000.00
13 4' DIAMETER SANITARY MANHOLE OVERDEPTH LF 9 170.00 3 $510.00
14 CORE DRILL CONNECTION TO EXISTING MANHOLE EA 1 1100.00 1 $1,100.00
15 CONNECT TO EXISTING SEWER SERVICE EA 4 340.00 4 $1,360.00
16 BULKHEAD EXISTING SANITARY SEWER SERVICE EA 4 62.00 4 $248.00
17 8" X 4" PVC WYE, SDR 26 EA 5 250.00 5 $1,250.00
18 4" PVC, SDR 26 SERVICE PIPE LF 115 34.50 115 $3,967.50
19 SALVAGE AND REINSTALL HYDRANT AND GATE
VALVE EA 1 1700.00 1 $1,700.00
20 4" CONCRETE SIDEWALK SF 180 4.25 170 $722.50
21 AGGREGATE BASE, CLASS 5 TN 60 16.00 42,22 $675.52
22 TYPE 41 BITUMINOUS FOR DRIVEWAYS TN 18 53.00 18 $954.00
23 SALVAGE AND REINSTALL RETAINING WALL LS 1 6000.00 1 $6,000.00
24 RESTORE LANDSCAPING LS 1 600.00 1 $600.00
25 6" CONCRETE DRIVEWAY PAVEMENT SF 510 4.75 249 $1,182.75
26 SODDING, LAWN TYPE SY 1350 2.45 2365 $5,794.25
TOTAL PART 1 - SANITARY SEWER: $55,660.07
PART 2 - STREET IMPROVEMENTS:
27 TRAFFIC CONTROL LS 1 1200.00 $1,200.00
28 GEOTEXTILE CB FILTER EA 4 50.00 $0.00
29 STREET SWEEPER WITH PICK UP BROOM WITH
OPERATOR HR 16 120.00 3 $360.00
30 REMOVE BITUMINOUS PAVEMENT SY 900 2.75 975 $2,681.25
31 REMOVE BITUMINOUS DRIVEWAY SY 355 3.50 355 $1,242.50
32 REMOVE CONCRETE CURB AND GUTTER LF 240 3.00 473 $1,419.00
33 REMOVE CBMH CASTING EA 1 100.00 1 $100.00
34 SAWING BITUMINOUS PAVEMENT LF 265 3.00 287 $861.00
35 AGGREGATE BASE, CLASS 5 TN 725 16,00 160,78 $2,572.48
36 TYPE 41 BITUMINOUS FOR DRIVEWAYS TN 100 53.00 86.02 $4,559.06
37 BITUMINOUS BASE COURSE, TYPE 31B TN 180 49.00 101.34 $4,965.66
38 BITUMINOUS WEAR COURSE, TYPE 41A TN 90 53.00 90 $4,770.00
39 BITUMINOUS MATERIAL FOR TACK COAT GAL 70 3.00 $0.00
40 FURNISH AND INSTALL NEW R3067V CB CASTING,
INCL. ADJ. RINGS EA 1 650.00 1 $650.00
41 B618 CONCRETE CURB AND GUTTER LF 400 16.00 478 $7,648.00
42 SODDING, LAWN TYPE SY 500 2.45 937 $2,295.65
TOTAL PART 2 - STREET IMPROVEMENTS: $35,324.60
PART 3 - P ARK IMPROVEMENTS:
43 SITE GRADING/FINAL SHAPING LS 1 6500.00 $6,500.00
44 SPREAD SALVAGED TOPSOIL LS 1 4800.00 $4,800.00
45 AGGREGATE BASE, CLASS 5 TN 215 16.00 $0.00
46 MNDOT SEED MIX 60A AC 0.75 1300.00 0.75 $975.00
47 MNDOT SEED MIX 80A AC 0.5 1700.00 0.5 $850.00
48 NORTHWOODS MAPLE, 21/2" CAL CONTAINER STOCK EA 3 412.00 3 $1,236.00
49 BITUMINOUS WEAR COURSE, TYPE 41A, PATHWAY TN 75 53.00 75 $3,975.00
50 4" PERFORATED POLYETHYLENE PIPE LF 50 18.00 20 $360.00
51 CONCRETE PLAY AREA CURBING LF 400 16.00 248 $3,968.00
TOTAL PART 3 - PARK IMPROVEMENTS: $22,664.00
PART 4 - PARKING LOT:
52 MOBILIZATION LS 1500.00 $1,500.00
34G4159REQ5FINAL.x1s
Contract Unit Current Quantity Amount
No. Item Unit Quantity Price Quantity to Date to Date
53 REMOVE BITUMINOUS PAVEMENT SY 3550 2.00 3550 $7,100.00
54 REMOVE CONCRETE SIDEWALK SF 125 1.00 712 $712.00
55 COMMON EXCAVATION (EV) - OFFSITE CY 3500 11.00 3502 $38,522.00
56 BITUMINOUS WEAR COURSE, TYPE 41A TN 330 53.00 330 $17,490.00
57 BITUMINOUS BASE COURSE, TYPE 31B TN 330 49.00 330 $16,170.00
58 AGGREGATE BASE, CLASS 5 TN 2000 16.00 1901.85 $30,429.60
59 B612 CONCRETE CURB AND GUTTER LF 1100 10.60 1100 $11,660.00
60 CONCRETE VALLEY GUTTER SY 40 48.00 20 $960.00
61 6" CONCRETE DRIVEWAY PAVEMENT SF 600 5.00 600 $3,000.00
62 4" CONCRETE SIDEWALK SF 275 4.25 1394 $5,924.50
63 4" SOLID LINE, YELLOW PAINT LF 2350 0.25 1954 $488.50
64 PAVEMENT MESSAGE, HANDICAPPED SYMBOL - PAIN' EA 10 15.00 10 $150.00
65 PAVEMENT MESSAGE, ONLY - PAINT EA 3 15.00 3 3 $45.00
66 PAVEMENT MESSAGE, STRAIGHT ARROW - PAINT EA 8 15.00 8 8 $120.00
TOTAL PART 4 - PARKING LOT: $134,271.60
ALTERNATE NO.2-STORM SEWER (CHURCH):
72 MOBILIZATION LS 1 2000.00 1 $2,000.00
73 REMOVE MANHOLE OR CATCH BASIN EA 3 330.00 3 $990.00
74 REMOVE BITUMINOUS PAVEMENT SY 760 2,00 510 $1,020.00
75 REMOVE CONCRETE CURB AND GUTTER LF 70 4.00 70 $280.00
76 REMOVE 24" RCP STORM SEWER PIPE LF 179 20.00 179 $3,580.00
77 BULKHEAD EXISTING STRUCTURE EA 1 165.00 1 $165.00
78 REMOVE AND REPLACE MONUMENT/SIGN AND
LANDSCAPING LS 1 6000.00 1 $6,000.00
79 15" RCP STORM SEWER LF 20 32.00 20 $640.00
80 24" RCP STORM SEWER, CLASS 3 LF 263 40.00 263 $10,520.00
81 33" RCP STORM SEWER, CLASS 3 LF 649 61.00 649 $39,589.00
82 4' DIA STORM MANHOLE EA 1 1900.00 1 $1,900.00
83 4' DIA STORM CATCH BASIN MANHOLE EA 5 2050.00 5 $10,250.00
84 4.5' DIA STORM MANHOLE EA 1 2900.00 1 $2,900.00
85 4.5' DIA STORM CATCH BASIN MANHOLE EA 1 2875.00 1 $2,875.00
86 5' DIAMETER STORM SEWER MH EA 1 3570.00 2 $7,140.00
87 6' DIA STORM MANHOLE EA 1 5600.00 1 $5,600.00
88 CONNECT EX. STORM SEWER PIPE TO STRUCTURE EA 1 400.00 1 $400.00
89 SAWING BITUMINOUS PAVEMENT LF 700 3.00 60 $180.00
90 AGGREGATE BASE, CLASS 5 TN 400 16.00 $0.00
91 BITUMINOUS BASE COURSE, TYPE 31B TN 125 49.00 102.71 $5,032.79
92 BITUMINOUS WEAR COURSE, TYPE 41A TN 125 53.00 27.48 $1,456.44
93 BITUMINOUS MATERIAL FOR TACK COAT GAL 45 3.00 $0.00
94 B618 CONCRETE CURB AND GUTTER LF 70 20.00 $0.00
95 SODDING, LAWN TYPE SY 1000 2.45 1626.8 $3,985.66
TOTAL ALTERNATE NO.2 - STORM SEWER (CHURCH): $106,503.89
CHANGE ORDER NO.1
1 REMOVE BITUMINOUS PAVEMENT SY 34 2.75 34 $93.50
2 REMOVE BITUMINOUS DRIVEWAY SY 45 3.50 55.5 $194.25
3 REMOVE CONCRETE CURB AND GUTTER LF 56 3.00 56 $168.00
4 REMOVE CONCRETE DRIVEWAY PAVEMENT SY 8 1.45 $0.00
5 SAWING BITUMINOUS PAVEMENT LF 97 3.00 115 $345.00
6 4' DIAMETER STORM SEWER MH EA 1 3800.00 1 $3,800.00
7 12" PVC STORM SEWER, SDR 26 LF 52 44.00 52 $2,288.00
8 12" PVC PLUG EA 1 30.00 1 $30.00
9 B618 CONCRETE CURB AND GUTTER LF 56 16.00 56 $896.00
10 6" CONCRETE DRIVEWAY PAVEMENT SF 75 4.75 $0.00
11 AGGREGATE BASE, CLASS 5 TN 25 16.00 25 $400.00
12 BITUMINOUS BASE COURSE, TYPE 31B TN 6 49.00 6 $294.00
13 BITUMINOUS WEAR COURSE, TYPE 41A TN 4 53.00 4 $212.00
14 TYPE 41 BITUMINOUS FOR DRIVEWAYS TN 10 53.00 10 $530.00
15 SODDING, LAWN TYPE SY 50 2.45 48 $117.60
16 LOWER WATER MAIN AT NORTHSIDE OF CHURCH LS 1 5580.40 1 $5,580.40
17 DOWN TIME FOR POWER POLE REMOVAL LS 1 530.32 1 $530.32
18 ADD-RELOCATE QWEST SLEEVE LS 1 1500.00 1 $1,500,00
19 TEMPORARY POWER POLE FOR QWEST SLEEVE LS 1 1380.00 1 $1,380.00
20 REMOVE PLAYGROUND EQUIPMENT LS 1 1329.11 1 $1,329.11
3404159REQ5FINAL.x1s
Contract Unit Current Quantity Amount
No. Item Unit Quantity Price Quantity to Date to Date
21 REMOVE TEMPORARY CULVERT AT POND AND
BULKHEAD/EXCAVATE AND REPLACE POND
EMBANKMENT MATERIAL AND COMPACT LS 1840.00 $1,840.00
22 REMOVE SHRUBS AND LANDSCAPE AND DISPOSE
OF OFF-SITE LS 350.00 $350.00
23 REMOVE CONCRETE AND DISPOSE OF OFF-SITE LS 520.00 $520.00
24 GRADE AND BACKFILL CURB AND GUTTER LS 900.00 $900.00
25 INSTALL B612 CURB AND GUTTER WITH HANDICAP
ACCESS LF 180 15.00 180 $2,700.00
26 INSTALL CONCRETE WALK SF 330 6.15 330 $2,029.50
27 IMPORT TOPSOIL LS 1 520.00 1 $520.00
28 SOD LS 1 500.00 1 $500.00
29 F & I 2" - 4" SLEEVE UNDER DRIVE LS 1 124.00 1 $124.00
TOTAL CHANGE ORDER NO.1 $29,171.68
CHANGE ORDER NO.2
1 BASS LAKE ROAD PATCHING LS 1871.05 $1,871.05
2 DRIVEWAY IMPROVEMENTS LS 975.20 $975.20
3 SILT FENCE REMOVAL LS 172.50 $172.50
TOTAL CHANGE ORDER NO.2 $3,018.75
TOTAL PART 1 - SANITARY SEWER:
TOTAL PART 2 - STREET IMPROVEMENTS:
TOTAL PART 3 - PARK IMPROVEMENTS:
TOTAL PART 4 - PARKING LOT:
TOTAL ALTERNATE NO.2 - STORM SEWER (CHURCH):
TOTAL CHANGE ORDER NO.1
TOTAL CHANGE ORDER NO.2
TOTAL WORK COMPLETED TO DATE
$55,660.07
$35,324.60
$22,664.00
$134,271.60
$106,503.89
$29,171.68
$3,018.75
$386,614.59
3404159REQ5FINAL,xls
PROJECT PAYMENT STATUS
OWNER CITY OF NEW HOPE
CITY PROJECT NO. 770
BRA FILE NO. 000034-04159-0
CONTRACTOR DMJ CORPORATION
CHANGE ORDERS
No. Date
Description
Amount
1 9/19/2005 This Change Order provides for additional work on this project. $29,453.68
See Chanqe Order.
2 6/16/2006 This Change Order provides for additional work on this project. $3,018.75
See Chanqe Order.
Total Change Orders $32,472.43
PAYMENT SUMMARY
No. From
To
Payment
Retainage
Completed
1 06/01/2005 08/12/05 165,193.43 8,694.39 173,887.82
2 08/13/2005 09/07/05 82,000.56 13,010.21 260,204.20
3 09/08/2005 10/28/05 111,500.72 18,878.67 377,573.38
4 10/29/2005 12/12/05 5,564.59 19,171.54 383,430.84
5 AND FINAL 12/13/2005 06/19/06 22,355.29 386,614.59
Material on Hand
Total Payment to Date $386,614.59 Oriainal Contract $384,084.25
Retainaoe Pay No 5 AND FINAL Chanqe Orders $32,472.43
Total Amount Eamed $386,614.59 Revised Contract $416,556.68
3404 i 59REQ5FINAL.xJs
07/25/2006 Tlm 14:36 FAX 763 478 3295
DMJ CORP/KD & CO.
[4J 001
facsimile transmittal
To: Valerie Leone /Fax: 763-531-5136
From: Colleen Selly Date: 7-25-06
Re: 2005 Infrastructure Project Pages: 6
Attached are the 1C-134's for Project No. 779 (770 on Change Order).
P.O. BOX 299, HAMEL, MN 55340 / 763-478-6878 / 763-478-3295 (FAX)
07/25/2006 Tl~ 14:36 FAX 763 478 3295
DMJ CORP/KD & CO.
I4l 002
Page 1 of 1
.MINNESOTA'REVENUE
Contractor's Withholding Affidavit
Confirmation
D M J CORP
ID 3142780
Please keep this information for your records.
Submit a copy of thls page to the project owner to receive your final payment
Confirmation number
Project owner
Project number
Project begin date
Project end date
Project location
Subcontractors
122905 Tue Jul 2514:31 :56 CDT 2006
CITY OF NEW HOPE
779
July 2005
June 2006
NEW HOPE, MINNESOTA
IBES LANDSCAPING 2818571 122872
CURB MASTERS INC. 2207114 121570
NEATON BROTHERS 4990862 121231
G L CONTRACTING INC. 9401845 121129
Oi/25/2006 11m 14:3i FAX i63 4i8 3295
DMJ CORP/KD & CO.
[4J 003
hrrps:l/wwlW .mndor.slate,mn.u.<l,/wc/ilction/c.:onfirmation Print
.\~ j :'.. :'.."f ~-:~, ~ 1"/\. J~,~ ~:l ......os 1. ~r
Corrtj'J9.lctor's \JV!thhcl~ding Affidavit
C(lJ <fim.;~tion
IBES LANDSCAPING INC
ID 2818571
Please keep this Information for your records.
Submit a copy of this page to the business that hired you to receive your :f1nal payment
Confirmation number
Project owner
Project number
Project begin date
Project end date
Project location
Subcontractors
122872 Tue JuJ 25 11 :42:32 CDr 2006
CITY OF NEW HOPE
770
September 2006
October 2005
NEW HOPE STREET AND PARK
No subcontractors listed,
__..,..........." .. ......... III
07/25/2006 ~~ 14:37 FAX 763 478 3295
07/12/200b l~:~8 5513519380
DMJ CORP/KD & CO.
CURB MASTERS
M.INNESOTA.' Po.~VENUE
Contractors WithhOlding Affidavit
Confirmation
CURB MAsTaRS INCORP
10 2107114
Please keep this information for your records.
submit a copy of this page to the business that hired you to receiVe your final payment.
Confitmatron number
Project owner
Project number
Project begin date
Project end date
Project location
subcontrac1ors
121570 Wed Ju\12 12:58:17 COT 2.006
CITY OF NEW HOPE
779
August 2005
May 2006
LAKEVIEW D~lVe. MAPLE GROVE
No subcontractor.; listed.
hUPs:/Iwww..mndor.state..mn.uslwc/actionlcoofinnationPrint
14J004
PAGE 01/01
10 .-.:>- - - -
7/12/2006
DMJ CORP/KD & CO.
NEATON BROS
141 005
PAGE Ell
Page 1 or 1
Oi/25/2006 Tl~ 14:3i F.~ i63 4i8 3295
07/11/2005 1a:a0 9529553582
!
I
,
!MLNNF.SarA- REVENUE
Contractors Withholding Affidavit
Confinnation
\D 4990862
. NEA TON BROTHERS EROSION LLC
I
I PI@ase keep this infmmation for your records.
I Submit a copy oftl1is page to the business that hired you to receive your final payment
I
I Confirmation number
Project owner
Project nlJmbor
Proj~~~ ~i~d!lt~ ........ .
I. Project end date
Project location
! Subcontractors
,
I
I
I
i
I
I
I
,
r
I
,
i
I
I
!
I
I
1
t
I
1
1
I
I
!
l
i
I
I
!
~
121231 Tue Jull1 11 :07:37 COT 2006
CITY OF NEW HOPE
770
November 2005
. July 1006"-
NEW HOPE STREETS & PARK
Nn subcontractors listed.
I
!
!
I
,
[
i
!
I
f
I
I
t
i
~1:tns:/ Iwww.mndor.state.mn.us/wc/action/confirmationPrint
7/11/2006
Oi/25/2006 11m 14:3i F.~ i63 4i8 3295
Man Ju1 1U u/~ull:n7 200S 763 4[l~ 2350 P. 1
ps:/ /www.lTIndor.Slaliunn.us/wc/action/conTlrm ~tlonPnnt
DMJ CORP/KD & CO.
!4l 006
07/10/2006 07:09 AM
S\.:Io'rC'""..:i)""?i'M~ -;;C'.&,\ III m& };\b''':-\'~'''''( t$"I'
CQ ntIf'QQtQJl"C W;1;hhoidins A'ffhj{;tVE~
Confirmation
G L CONTR&.GTiNG lNC
lD 9401845
Please keep this information fer your records,
Submit a copy of this page t.o the business that hired you to receive your fjna~ payment.
Confirmation number
!::roject o\t'mer
Project nUl'nbei'
Project begin date
P!'(.~ject end date
Project locatio;li -.--..
12'1'129 Mon .Jul '10 07:06:21 CDT 2006
CITY OF NEW HOPE
as5444
July 2005
December 2005
r-:lElfrI=-IC!PE ZOOO STREET PARK UTIUTIES"
I':; ._i.-_.........~..... _&._ ......
~ .. _ ..-:-_Irr, Q-.>...1......... _Ii....... ...... I~_S...... -l .
ps:/ IWViW,lTIndor.Slate.m n. U$/wcf~r;lion !confirmatlonPrl111
Pagel 1 cf 1
Project Manual For
2005 Street, P~rk and Utility
Infrastructure Improvements
City Project NOe 779
ew Hope,
innesota
File No" 000034=04159=0
April 2005
J[JJ Bonestroo
III _ Rosene
"t\II Anderlik &
1 \J 1 Associates
Engineers & Architects
J14 Bonestroo
-=- Rosene
'11\11 Anderlik &
1 \J 1 Associates
Engineers & Architects
ADDENDUM NO.1
For
2005 STREET, PARK AND UTILITY INFRASTRUCTURE IMPROVEMENTS
CITY PROJECT NO. 779
FILE NO. 000034-04159-0
NEW HOPE, MINNESOTA
April 25, 2005
Number of Pages 13 (includes this sheet)
To:
All Planholders of Record
From:
Bonestroo, Rosene, Anderlik and Associates, Inc.
2335 West Highway 36
St. Paul, Minnesota 55113
(651) 636-4600 - General Office
(651) 604-4790- Vince Vander Top, Project Manager
The following changes, additions, and deletions are hereby made a part of the Bidding
Documents. Bidder shall acknowledge receipt of this Addendum on the Bid Form.
Failure to do so may result in rejection of the Bid.
Please ackno\vledge receipt of this Addendum by signing and faxing this page back to Bonestroo & Associates at
Fax No. (651) 636-1311 as soon as you receive it.
Company Name
Date
000034-04159-0
Al-l
ADDENDlJM NO, I
DOCUMENT 00100 - ADVERTISEMENT FOR BIDS
1. The Bid Date will be changed from 1:30 P.M., C.D.5.T., Monday, May 2, 2005 to
1:30 P.M., C.D.S.T., Wednesday, April 27, 2005.
The Bid Date is being moved up to accommodate the time period required to
obtain approval for specific parts of the Project. This approval is required prior to
the award of the Project at the May 9th Council Meeting.
DOCUMENT 00410 - BID FORM
1. A Revised Bid Form has been provided. The changes made to the Bid Form
include:
A. Mobilization Bid Items have been added to Part 4 - Parking Lot and
Alternate NO.2 - Storm Sewer (Church).
Separate Mobilization Bid Items were added to these sections to account
for the possibility of these particular parts not being awarded as part of
the Contract.
B. The pavement markings, Bid Items 63, 64, 65, and 66 (previously Bid
Items 62, 63, 64, and 65) have been changed to paint instead of epoxy.
All pavement markings will be paint. Epoxy will NOT be used for any of
the markings.
DOCUMENT 00520 - AGREEMENT FORM
1. Page 00520-1, ADD Paragraph 00520.4.02C, Part 4 - Parking Lot Completion
Date - add this Section as follows:
E. Should Part 4 be awarded, the work involved, through the installation of
the first lift of bituminous, shall be completed within 6 weeks after the
commencement of 1 of the following, whichever is earlier:
1. Alternate No.1 - Storm Sewer (Church).
2. Part 4 - Parking Lot.
The new parking lot is to be ready for use, including curb and the
bituminous base course, within 6 weeks of the initial disturbance of the
lot.
lIST Of ATTACHMENTS
1. Revised Bid Form.
END OF ADDENDUM
000034-04159-0
Al-2
ADDENDUivl NO.1
~ Bonestroo
-=- Rosene
U Anderlik &
. ~. Associates
Engineers & Architects
BIDDER:
DOCUMENT 004 I 0
REVISED BID FORM
REVISED BY ADDENDUM NO.1
2005 STREET, PARK AND UTILITY
INFRASTRUCTURE IMPROVEMENTS
CITY PROJECT NO. 779
FILE NO. 000034-04 I 59-0
NEW HOPE, tvlI},TNESOT A
2005
BID COpy
THIS BID IS SUBMITTED TO:
City of New Hope, Minnesota
4401 Xylon Avenue North
New Hope, MN 55429-4898
1.0 I The undersigned Bidder proposes and agrees if this Bid is accepted to enter into an Agreement with Owner in the form
included in the Bidding Documents to perform all work as specified or indicated in the Bidding Documents for the prices and
within the times indicated in this Bid and in accordance with the other terms and conditions of the Bidding Documents.
2.0 I Bidder accepts all of the terms and conditions of the Instructions to Bidders, including without limitation those dealing
with the disposition of Bid Security. The Bid will remain subject to acceptance for 60 days after the Bid Opening, or for such
longer period of time that Bidder may agree to in \\Titing upon request of Owner.
3.01 In submitting this Bid, Bidder represents that:
A. Bidder has examined and carefully studied the Bidding Documents, the other related data identified in the
Bidding Documents, and the following Addenda, receipt of all which is hereby acknowledged:
Addendum No.
Addendum Date
B. Bidder has visited the Project Site and become familiar with and is satisfied as to the general, local, and
Project Site conditions that may affect cost, progress, and performance of the work.
C. Bidder is familiar with and is satisfied as to all federal, state, and local Laws and Regulations that may affect
cost, progress, and performance of the work.
000034041 590BIDFORM,xls
Re,;sed By Addendum No.1
00410-I(R)
RE\1SED BID FORM
D. Bidder has carefully studied all: (I) reports of explorations and tests of subsurface conditions at or
contiguous to the Project Site and all drawings of physical conditions in or relating to existing surface or
subsurface structures at or contiguous to the Project Site (except Underground Facilities) which have been
identified in SC-4.02, and (2) reports and drawings of Hazardous Environmental Conditions that have been
identified in SC-4.06.
E. Bidder has obtained and carefully studied (or accepts the consequences for not doing so) all additional or
supplementary examinations, investigations, explorations, tests, studies, and data concerning conditions
(surface, subsurface, and Underground Facilities) at or contiguous to the Project Site which may affect cost,
progress, or performance of the work or which relate to any aspect of the means, methods, techniques,
sequences, and procedures of construction to be employed by Bidder, including applying the specific means,
methods, techniques, sequences, and procedures of construction expressly required by the Bidding
Documents to be employed by Bidder, and safety precautions and programs incident thereto.
F. Bidder does not consider that any further examinations, investigations, explorations, tests, studies, or data are
necessary for the determination of this Bid for performance of the work at the price(s) Bid and within the
times and in accordance with the other terms and conditions of the Bidding Documents.
G. Bidder is aware of the general nature of work to be performed by Owner and others at the Project Site that
relates to the work as indicated in the Bidding Documents.
H. Bidder has correlated the information known to Bidder, information and observations obtained from visits to
the Project Site, reports and drawings identified in the Bidding Documents, and all additional examinations,
investigations, explorations, tests, studies, and data with the Bidding Documents,
I. Bidder has given Engineer \vritten notice of all conflicts, errors, ambiguities, or discrepancies that Bidder
has discovered in the Bidding Documents, and the written resolution thereof by Engineer is acceptable to
Bidder.
1. The Bidding Documents are generally sufficient to indicate and convey understanding of all terms and
conditions for the performance of the work for which this Bid is submitted.
K, Bidder will submit written evidence of its authority to do business in the state where the Project is located not
later than the date of its execution of the Agreement.
4.0 I Bidder further represents that:
A. The prices in this Bid have been arrived at independently, without consultation, communication, or
agreement as to any matters relating to such prices with any other Bidder or with any competitor for the
purpose of restricting competition.
B. The prices in this Bid have not or will not be knO\vingly disclosed to any other Bidder or competitor prior to
opening of the Bids.
C. No attempt has been made or will be made by the Bidder to induce any other person or firm to submit or not
to submit a Bid for the purpose of restricting competition,
000034041590BIDFORM,xls
Re\ised By Addendum No, 1
004] 0-2(R)
REVISED BID FORM
4,02 Bidder understands that the law may require the Owner, or Engineer at the Owner's direction, to undertake an investigation
and submit an evaluation conceming Bidder's responsiveness, responsibility, and qualifications before awarding a Contract.
Bidder hereby waives any and all claims, of whatever nature, against Owner, Engineer, and their employees and agents, which
arise out of or relate to such investigation and evaluation, and statements made as a result thereof, except for statements that can
be shown by clear and convincing evidence to be intentionally false and made with actual malice. Nothing in this paragraph is
intended to restrict Bidder's rights to challenge a Contract pursuant to law.
5.01 Bidder will complete the work in accordance with the Contract Documents for the fo11owing price(s):
All specific cash a110wances are included in the price(s) set forth below and have been computed in
accordance with paragraph 11.02 of the General Conditions.
Bid Unit Prices have been computed in accordance with paragraph 11.03.B of the General Conditions
Bidder acknowledges that estimated quantities are not guaranteed, and are solely for the purpose of
comparison of Bids, and final payment for all Unit Price Bid items will be based on actual quantities
provided, determined as provided in the Contract Documents.
No. Item Units Qty Unit Price Total Price
PART 1- SANITARY SEWER:
MOBILIZA nON LS I $ $
2 CLEAR AND GRUB TREE 2$ S
, REMOVE DOGWOOD BUSH EA 4$ $
,)
4 REMOVE BITUIvIINOUS DRIVEWAY SY 85 $ S
5 REr'vIOVE CONCRETE SIDE\VALK SF 180 $ $
6 REMOVE CONCRETE DRIVEWAY SF 510 $ $
PAVEMENT
7 CONNECT TO EXISTING SANITARY EA 1 $ $
SEWER 8" PVC PIPE
8 8" PVC SANITARY SE\VER, SDR 35,8'- LF ]85 $ S
10' DEEP
9 8" PVC SANIT AR Y SEWER, SDR 35, 10'- LF 25 $ S
12' DEEP
]0 8" PVC SANITARY SEWER, SDR 35, ]2'- LF 40 $ $
14' DEEP
II 8" PVC SANITARY SEWER, SDR 35, 14'- LF 79 $ S
16' DEEP
12 4' DIAMETER SANITARY MH, 8' DEEP, EA 2 $ $
INCL R-1642-B CSTG
]3 4' DIAMETER SANITARY MANHOLE LF 9 $ S
OVERDEPTH
00003404 I 590BIDFORe"Lxls
Revised By Addendum No. I
00410-3(R)
REV1SED BID FORe"l
No. Item Units Qty Unit Price Total Price
14 CORE DRILL corn~EcTION TO EA I $ $
EXISTING ivlANHOLE
15 COl'JNECT TO EXISTING SE\VER EA 4$ $
SERVICE
16 BULKHEAD EXISTING SANITARY EA 4 $ $
SE\VER SERVICE
17 8" X 4" PVC WYE, SDR 26 EA 5 $ $
18 4" PVC, SDR 26 SERVICE PIPE LF 115 $ $
19 SAL VAGE AND REINSTALL EA I $ $
HYDRANT AND GATE VALVE
20 4" CONCRETE SIDEWALK SF 180 $ $
21 AGGREGA TE BASE, CLASS 5 TN 60 $ $
22 TYPE 41 BITUMINOUS FOR TN 18 $ $
DRNEW A YS
1" SALVAGE AND REINSTALL LS I $ $
~.)
RETAINING WALL
24 RESTORE LANDSCAPING LS 1 $ $
25 6" CONCRETE DRIVEWAY SF 510 $ $
PAVEMENT
26 SODDING, LAWN TYPE SY 1350 $ $
TOTAL PART 1 - SANITARY SEWER $
PART 2 - STREET IMPROVEMENTS:
27 TRAFFIC CONTROL LS I $ $
28 GEOTEXTILE CB FILTER EA 4$ S
29 STREET SWEEPER \vlTH PICK UP HR 16 $ S
BROOM V..,rITH OPERi\ TOR
30 REMOVE BITUMINOUS PAVEMENT SY 900 $ S
31 REMOVE BITUMINOUS DRIVEWA Y SY 355 $ $
32 REMOVE CONCRETE CURB AND LF 240 $ S
GUTTER
00 RElvlOVE CBMH CASTING EA 1 $ $
.).)
34 SA WING BITUMINOUS PA VEMENT LF 265 $ $
00003404 I 590BIDFORM,xls
Re,ised By Addendum No, I
00410-4(R)
REVISED BID FORe"l
No. Item Units Qty U nit Price Total Price
35 AGGREGA TE BASE, CLASS 5 TN 725$ $
36 TYPE 41 BITUMINOUS FOR TN 100$ $
DRIVEWA l.'S
37 BITUMINOUS BASE COURSE, TYPE TN 180 $ $
31B
38 BITUMINOUS WEAR COURSE, TYPE TN 90 $ $
41A
39 BITUMINOUS MA TERlAL FOR TACK GAL 70 $ $
COAT
40 FURNISH AND INSTALL NEW R3067V EA I $ $
CB CASTING, INCL. ADJ. RINGS
41 B618 CONCRETE CURB AND GUTTER LF 400 $ $
42 SODDING, LA \VN TYPE SY 500 $ $
TOTAL PART 2-STREET $
IMPROVEMENTS
PART 3 - PARK IMPROVEMENTS:
43 SITE GRADINGIFINAL SHA.PING LS I $ $
44 SPREAD SALVAGED TOPSOIL LS I $ $
45 AGGREGA TE BASE, CLASS 5 TN 215 $ $
46 i\fNDOT SEED MIX 60A AC 0.75 $ $
47 MNDOT SEED MIX 80A AC 0.5 $ $
48 NORTHWOODS MAPLE, 2 1/2" CAL EA 3 $ $
CONTAINER STOCK
49 BITUMINOUS WEAR COURSE, TYPE TN 75 $ $
41A, PATHWAY
50 4" PERFORATED POLYETHYLENE LF 50 $ $
PIPE
51 CONCRETE PLAY AREA CURBING LF 400 $ $
TOTAL PART 3 - PARK $
IMPROVEMENTS
000034041590BIDFORlvLxls
Revised By Addendum No. I
004] 0-5(R)
REV1SED BID FOR.\.1
No. Item Units Qty Unit Price Total Price
PART 4 - PARKING LOT:
52 MOBIUZA TION LS I S $
53 REMOVE BITUMINOUS PAVEMENT SY 3550 S S
54 REMOVE CONCRETE SIDEWALK SF 125 S S
55 COMMON EXCA VA TION (EV) - CY 3500 S S
OFFSITE
56 BITUMINOUS WEAR COURSE, TYPE TN 330 S S
41A
57 BITUMINOUS BASE COURSE, TYPE TN 330 $ $
31B
58 AGGREGA TE BASE, CLASS 5 TN 2000 S S
59 B612 CONCRETE CURB AND GUTTER LF 1100 S S
60 CONCRETE V ALLEY GUTTER SY 40 $ S
61 6" CONCRETE DRIVEWAY SF 600 S S
PAVEMENT
62 4" CONCRETE SIDEWALK SF 275 S S
63 4" SOUD LINE, YELLOW PAINT LF 2350 S S
64 PA VEMENT MESSAGE, EA 10 S S
HANDICAPPED SYMBOL - PAINT
65 PA VEMENT MESSAGE, ONLY - PAINT EA 3 S S
66 PAVEMENT MESSAGE, STRAIGHT EA 8 $ $
ARROW - PAINT
TOTAL PART 4 - PARKING LOT S
BASE BID
TOTAL PART 1 - SANITARY SEWER S
TOTALPART2-STREET S
IMPROVEMENTS
TOTAL PART 3 - PARK S
IMPROVEMENTS
TOTAL PART 4 - PARKING LOT S
TOTAL BASE BID S
00003404 1 590BlDFOR.l\Lxls
Re\ised By Addendum No, I
00410-6(R)
REY1SED BID FO~"1
No. Item Units Qty Unit Price Total Price
AL TERNA TE NO.1 - STORM SEWER
(PARK):
67 REMOVE MANHOLE OR CATCH EA I S S
BASIN
68 IS" RCP STORt\-f SE\VER LF 27$ $
69 18" RCP STORM SEV./ER LF 32 $ $
70 4' DlA STORt\1 CATCH BASIN EA 2 $ $
MANHOLE
71 CONNECT EX. STORJvf SEWER PIPE EA 2 $ $
TO STRUCTURE
TOTAL AL TERNA TE NO.1 - STORM $
SEWER (PARK)
ALTERNATE NO.2 - STORM SEWER
(CHURCH):
72 MOBILIZA TION LS I $ $
73 REMOVE MANHOLE OR CATCH EA 3 $ $
BASIN
74 REMOVE BITUMINOUS PAVEMENT SY 760 S S
75 REMOVE CONCRETE CURB AND LF 70 S S
GUTTER
76 REMOVE 24" RCP STORt\-! SE\VER LF 179 S S
PIPE
77 BULKHEAD EXISTING STRUCTURE EA 1 S S
78 REiv!OVE AND REPLACE LS I S S
MONUMENT/SIGN AND
LANDSCAPING
79 IS" RCP STORt\1 SEWER LF 20 S S
80 24" RCP STORt\-! SEWER, CLASS 3 LF 263 S S
81 33" RCP STORt\-f SEWER, CLASS 3 LF 649 S S
82 4' DlA STORtvI lv!ANHOLE EA 1 S S
83 4' DlA STORM CATCH BASIN EA 5 S S
rvIANHOLE
84 4.5' DlA STORtvI MANHOLE EA I S S
00003404 I 590BIDFORM,xIs
Rc\;sed By Addendum No, I
00410-7(R)
REVISED BID FO,,""I
No. Item Units Qty Unit Price Total Price
85 4.5' DIA STORM CATCH BASIN EA I S S
MANHOLE
86 5' DIAMETER STORIvl SEWER MH EA I S S
87 6' DL<\ STORM jyiANHOLE EA I S S
88 C01'lNECT EX. STORM SE\VER PIPE EA I S S
TO STRUCTURE
89 SA WING BITUMINOUS PAVEMENT LF 700 S S
90 AGGREGA TE BASE, CLASS 5 TN 400 S S
91 BITUMINOUS BASE COURSE, TYPE TN 125 S S
31B
92 BITUMINOUS \VEAR COURSE, TYPE TN 125 S S
41A
93 BITUMINOUS MA TERlAL FOR TACK GAL 45 S S
COAT
94 B618 CONCRETE CURB AND GUTTER LF 70 S S
95 SODDING, LAWN TYPE SY 1000 S S
TOTAL AL TERNA TE NO.2 - STORM S
SEWER (CHURCH)
AL TERNA TE NO.3 - DRINKING
FOUNTAIN:
96 1" CORPORi~ TION STOP EA 1 S S
97 1" TYPE "K" COPPER \VATER LF 50 S S
SERVICE
98 1" CURB STOP AND BOX EA 1 S S
99 FURi"lISH AND INSTALL DRINKING LS 1 S S
FOtJNTAIN
TOTAL ALTERNATE NO.3- S
DRINKING FOUNTAIN
00003404 I 590BIDFOR1\l.xls
Re\lscd By Addendum No. I
00410-8(R)
REvlSED BID FORM
6.01 Bidder agrees that the work will be Substantially Completed and completed and ready for Final Payment in
accordance with paragraph 14.07.B of the General Conditions on or before the dates or within the number of calendar days
indicated in the Agreement.
6.02 Bidder accepts the provisions of the Agreement as to liquidated damages in the event of failure to cqmplete the work
within the times specified above, which shall be stated in the Agreement.
7.01 The following documents are attached to and made a condition of this Bid:
A, Required Bid Security in the fonn of 5 percent.
8.01 The tenns used in this Bid with initial capital letters have the meanings stated in the Instructions to Bidders, the
General Conditions, and the Supplementary Conditions,
SUBMITTED on
,20_
If Bidder Is:
An Individual
Name (typed or printed):
By:
(SEAL)
(Individual's signature)
Doing business as:
Business Street Address (No P.O. Box #'s):
Phone No.:
Fax No.:
000034041 590BIDFORM,xls
Revised By Addendum No, I
00410-9(R)
RE'vlSED BID FO~\.l
A Partnership
A Corporation
00003404 I 590BlDFORM.xls
Re,;sed By Addendum No. I
Partnership Name:
(SEAL)
By:
(Signature of general partner)
Name (typed or printed):
Business Street Address (No P.O. Box #'s):
Phone No.:
Fax No,:
Corporation Name:
(SEAL)
State of Incorporation:
Type (General Business, Professional, Service, Limited Liability):
By:
(Signature)
Name (typed or printed):
Title:
Attest
(CORPORA. TE SEAL)
(Signature of Corporate Secretary)
Business Street Address (No P.O. Box #'s):
Phone No,:
Fax No.:
00410-10(R)
REVISED BID FORM
A Joint Venture
Joint Venture Name:
(SEAL)
By:
(Signature of joint venture partner)
Name (typed or printed):
Title:
Business address:
Phone No.:
Fax No.:
Joint Venturer Name:
(SEAL)
By:
(Signature)
Name (typed or printed):
Title:
Business Street Address (No P.O. Box #'s):
Phone No.:
Fax No.:
Phone and Fax Number, and Address for receipt of official communications:
(Each joint venturer must sign. The manner of signing for each individual, partnership, and corporation that is a party to
the joint venture should be in the manner indicated above),
E1\TD 0 F DOCUMENT
000034041590BIDFOIUvLxls
Re,ised By Addendum No.1
00410-11 (R)
RE\1SED BID FORe'.1
DOCUMENT 00005
PROFESSIONAL CERTIFICATIONS
I hereby certify that this report, drawing, or
specification was prepared by me or under my direct
supervision and that I am a duly Licensed Engineer
under the laws of the State of Minnesota.
~~~
Vince T. Vander Top, P.E.
Date: April 11 , 2005
Reg. No. 25770
END OF DOCUMENT
000034-04159-0
~ 2005 Bonestroo, Rosene,
Anderlik & Associates Inc.
PROFESSIONAL CERTIFICATIONS
DOCUMENT 00010
TABLE OF CONTENTS
2005 STREET, PARK AND UTILITY
INFRASTRUCTURE IMPROVEMENTS
CITY PROJECT NO. 779
FILE NO. 000034-04159-0
NEW HOPE, MINNESOTA
2005
Introductory Information
00005 Professional Certifications
00010 Table of Contents
Bidding Requirements
00100 Advertisement for Bids
00200 Instructions to Bidders
00300 Information Available to Bidders
00410 Bid Form
Contracting Requirements
00520 Agreement Form
00610 Performance Bond
00615 Payment Bond
00700 EJCDC C-700 Standard General Conditions of the Construction Contract
(Bound in back of Project Manual)
00800 Supplementary Conditions
Specifications
Division 1 - General Requirements
01100 Summary
01310 Project Management and Coordination
01400 Quality Requirements
01500 Temporary Facilities and Controls
01570 Temporary Erosion and Sediment Control
01700 Execution Requirements
000034-04159-0
~ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
00010-1
TABLE OF CONTENTS
Specifications Continued...
Division 2 - Site Construction
02225
02230
02280
02315
02318
02320
02515
02530
02535
02630
02635
02720
02740
02766
02770
02775
02870
02920
02930
Removals
Site Clearing
Adjust Miscellaneous Structures
Excavation and Fill
Subgrade Preparation
Trench Excavation and Backfill
Water Services
Sanitary Sewer
Sanitary Sewer Services
Storm Drainage
Subsurface Drainage
Aggregate Base Course
Plant Mixed Asphalt Pavement
MnDOT Combined Spec. 2350/2360
Pavement Markings
Concrete Curb and Gutter
Concrete Walks, Medians, and Driveways
Site Furnishings
Lawns and Grasses
Trees, Shrubs, and Perennial Plants
END OF DOCUMENT
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
00010-2
TABLE OF CONTENTS
DOCUMENT 00100
ADVERTISEMENT FOR BIDS
Sealed Bids will be received by the City of New Hope, Minnesota, in the City Hall at 4401 Xylon
Avenue North, until 1:30 P.M., C.D.S.T., Monday, May 2,2005, at which time they will be publicly
opened and read aloud for the furnishing of all labor, materials, and all else necessary for the
following:
2005 Street, Park and Utility Infrastructure Improvements
In general, work involves: street reconstruction, parking lot reconstruction, storm and sanitary
sewer installation, park improvements. The work consists of the following approximate
quantities:
1
430
1
885
3,400
2,000
1,200
1,200
2,000
LS Removals - Bit. Surface, Curb and Gutter, Common Ex, etc.
LF PVC Sanitary Sewer Main and Services
EA Drinking Fountain and Service
LF 24"-33" RCP Storm Sewer, with Structures
TN Aggregate Base, Class 5
TN Bituminous Mixture; Street, Parking Lot, Trail
LF Concrete Curb and Gutter; Street, Parking Lot, Play Area Curb
SY Sod
LF Parking Lot Striping
Bidders desiring a copy of the Bidding Documents may obtain them from the Issuing Office of
Bonestroo, Rosene, Anderlik & Associates, Inc., Consulting Engineers, 2335 West Highway 36, St.
Paul, MN 55113, (651) 636-4600 upon payment of a non-refundable fee of $40.00. Bidding
Documents may be seen at the office of the City of New Hope and at the Issuing Office. Bidding
Documents can also be purchased with a credit card over the internet at www.bonestroo.com.
Direct inquiries to Engineer's Project Manager, Vince Vander Top at (651) 604-4790.
Bid Security in the amount of 5 percent of the amount of the Bid must accompany each Bid in
accordance with the Instructions to Bidders.
The Owner reserves the right to retain the deposits of the 3 lowest Bidders for a period not to exceed
60 days after the date and time set for the Opening of Bids. No Bids may be withdrawn for a period
of 60 days after the date and time set for the Opening of Bids.
The Owner reserves the right to reject any and all Bids, to waive irregularities and informalities
therein, and further reserves the right to award the Contract to the best interests of the Owner.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc,
Daniel Donahue, City Manager
City of New Hope, Minnesota
ADVERTISEMENT FOR BIDS
DOCUMENT 00200
INSTRUCTIONS TO BIDDERS
ARTICLE 1- DEFINED TERMS
1.01 Terms used in these Instructions to Bidders have the meanings indicated in the General
Conditions and Supplementary Conditions. Additional terms used in these Instructions to
Bidders have the meanings indicated below:
A. Issuing Office: The office from which the Bidding Documents are to be issued and
where the Bidding procedures are to be administered.
ARTICLE 2 - COPIES OF BIDDING DOCUMENTS
2.01 Complete sets of the Bidding Documents in the number and for the non-refundable sum
stated in the Advertisement for Bids may be obtained from the Issuing Office.
2.02 Complete sets of Bidding Documents shall be used in preparing Bids; neither Owner nor
Engineer assumes any responsibility for errors or misinterpretations resulting from the use
of incomplete sets of Bidding Documents.
2.03 Owner and Engineer in making copies of Bidding Documents available on the above terms,
do so only for the purpose of obtaining Bids for the work and do not confer a license or
grant for any other use.
ARTICLE 3 - QUALIFICATIONS OF BIDDERS
3.01 To demonstrate Bidder's qualifications to perform the work within 5 days of Owner's
request, Bidder shall submit written evidence, such as financial data, previous experience,
present commitments, and such other data as may be called for below:
A. Evidence of Bidder's qualification to do business in the state where the Project is
located or covenant to obtain such qualification prior to award of Contract.
B. Evidence of genuineness of Bid and lack of collusion in conjunction therewith.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc,
00200-1
INSTRUCTIONS TO BIDDERS
ARTICLE 4 - EXAMINATION OF BIDDING DOCUMENTS, OTHER RELATED DATA,
AND PROJECT SITE
4.01 Subsurface and Physical Conditions
A. The Supplementary Conditions Identify:
1. Those reports of explorations and tests of subsurface conditions at or
contiguous to the Project Site that Engineer has used in preparing the
Bidding Documents.
2. Those drawings of physical conditions in or relating to existing surface and
subsurface structures at or contiguous to the Project Site (except
Underground Facilities) that Engineer has used in preparing the Bidding
Documents.
B. Copies of reports and drawings referenced in Paragraph 4.01.A will be made
available by Owner to any Bidder on request. Those reports and drawings are not
part of the Contract Documents, but the "technical data" contained therein upon
which Bidder is entitled to rely as provided in Paragraph 4.02 of the General
Conditions has been identified and established in Paragraph 4.02 of the
Supplementary Conditions. Bidder is responsible for any interpretation or
conclusion Bidder draws from any "technical data" or any other data,
interpretations, opinions, or information contained in such reports or shown or
indicated in such drawings.
4.02 Underground Facilities
A. Information and data shown or indicated in the Bidding Documents with respect to
existing Underground Facilities at or contiguous to the Project Site is based upon
information and data furnished to Owner and Engineer by owners of such
Underground Facilities, including Owner or others.
4.03 Hazardous Environmental Condition
A. The Supplementary Conditions identify those reports and drawings relating to a
Hazardous Environmental Condition identified at the Project Site, if any, that
Engineer has used in preparing the Bidding Documents.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
00200-2
INSTRUCTIONS TO BIDDERS
B. Copies of reports and drawings referenced in Paragraph 4.03.A will be made
available by Owner to any Bidder on request. Those reports and drawings are not
part of the Contract Documents, but the "technical data" contained therein upon
which Bidder is entitled to rely as provided in Paragraph 4.06 of the General
Conditions has been identified and established in Paragraph 4.06 of the
Supplementary Conditions. Bidder is responsible for any interpretation or
conclusion Bidder draws from any "technical data" or any other data,
interpretations, opinions, or information contained in such reports or shown or
indicated in such drawings.
4.04 Provisions concerning responsibilities for the adequacy of data furnished to prospective
Bidders with respect to subsurface conditions, other physical conditions, Underground
Facilities, and possible changes in the Bidding Documents due to differing or unanticipated
conditions appear in Paragraphs 4.02, 4.03, and 4.04 of the General Conditions. Provisions
concerning responsibilities for the adequacy of data furnished to prospective Bidders with
respect to a Hazardous Environmental Condition at the Project Site, if any, and possible
changes in the Contract Documents due to any Hazardous Environmental Condition
uncovered or revealed at the Project Site which was not shown or indicated in the Drawings
or Specifications, or identified in the Contract Documents to be within the scope of the
work appear in Paragraph 4.06 of the General Conditions.
4.05 On request, Owner will provide Bidder access to the Project Site to conduct such
examinations, investigations, explorations, tests, and studies as Bidder deems necessary for
submission of a Bid. Bidder shall fill all holes, and clean up and restore the Project Site to
its former condition upon completion of such explorations, investigations, tests, and studies.
Bidder shall comply with all applicable Laws and Regulations relative to excavation and
utility locates.
4.06 Reference is made to Article 7 of the Supplementary Conditions for the identification of the
general nature of other work that is to be performed at the Project Site by Owner or others
(such as utilities and other prime contractors) that relates to the work contemplated by these
Bidding Documents. On request, Owner will provide to each Bidder for examination
access to or copies of contract documents (other than portions thereof related to price) for
such other work.
4.07 It is the responsibility of each Bidder before submitting a Bid to:
A. examine and carefully study the Bidding Documents, the other related data
identified in the Bidding Documents, and any Addenda;
B. visit the Project Site and become familiar with and satisfy Bidder as to the general,
local, and Project Site conditions that may affect cost, progress, and performance of
the work;
C. become familiar with and satisfy Bidder as to all federal, state, and local Laws and
Regulations that may affect cost, progress, and performance of the work;
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
00200-3
INSTRUCTIONS TO BIDDERS
D. carefully study all: (1) reports of explorations and tests of subsurface conditions at
or contiguous to the Project Site and all drawings of physical conditions in or
relating to existing surface or subsurface structures at or contiguous to the Project
Site (except Underground Facilities) which have been identified in the
Supplementary Conditions as provided in Paragraph 4.02 of the General Conditions,
and (2) reports and drawings of Hazardous Environmental Conditions at the Project
Site which have been identified in the Supplementary Conditions as provided in
Paragraph 4.06 of the General Conditions;
E. obtain and carefully study (or accept consequences of not doing so) all additional or
supplementary examinations, investigations, explorations, tests, studies, and data
concerning conditions (surface, subsurface, and Underground Facilities) at or
contiguous to the Project Site which may affect cost, progress, or performance ofthe
work or which relate to any aspect of the means, methods, techniques, sequences,
and procedures of construction to be employed by Bidder, including applying any
specific means, methods, techniques, sequences, and procedures of construction
expressly required by the Bidding Documents, safety precautions, and programs
incident thereto;
F. agree at the time of submitting its Bid that no further examinations, investigations,
explorations, tests, studies, or data are necessary for the determination of its Bid for
performance ofthe work at the Price(s) Bid and within the times and in accordance
with the other terms and conditions ofthe Bidding Documents;
G. become aware of the general nature of the work to be performed by Owner and
others at the Project Site that relates to the work as indicated in the Bidding
Documents;
H. correlate the information known to Bidder, information and observations obtained
from visits to the Project Site, reports and drawings identified in the Bidding
Documents, all additional examinations, investigations, explorations, tests, studies,
and data with the Bidding Documents;
1. promptly give Engineer written notice of all conflicts, errors, ambiguities, or
discrepancies that Bidder discovers in the Bidding Documents and confirm that the
written resolution thereof by Engineer is acceptable to Bidder; and
J. determine that the Bidding Documents are generally sufficient to indicate and
convey understanding of all terms and conditions for the performance of the work.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
00200-4
INSTRUCTIONS TO BIDDERS
4.08 The submission of a Bid will constitute an incontrovertible representation by Bidder that
Bidder has complied with every requirement of this Article 4, that without exception the
Bid is premised upon performing and furnishing the work required by the Bidding
Documents, and applying any specific means, methods, techniques, sequences, and
procedures of construction that may be shown or indicated or expressly required by the
Bidding Documents, that Bidder has given Engineer written notice of all conflicts, errors,
ambiguities, and discrepancies that Bidder has discovered in the Bidding Documents and
the written resolutions thereof by Engineer are acceptable to Bidder, and that the Bidding
Documents are generally sufficient to indicate and convey understanding of all terms and
conditions for performing and furnishing the work.
ARTICLE 5 - PRE-BID CONFERENCE
5.01 There will be a pre-Bid conference held at 10:00 A.M. on Friday, April 22, 2005, at the
New Hope Public Works Facility. Attendance will not be required for Bid submittal,
however, with the complexity of the Project components and the associated coordination
that will be required, attendance is strongly encouraged.
ARTICLE 6 - PROJECT SITE AND OTHER AREAS
6.01 The Project Site is identified in the Bidding Documents. Easements for permanent
structures or permanent changes in existing facilities are to be obtained and paid for by
Owner, unless otherwise provided in the Bidding Documents. All additional lands and
access thereto required for temporary construction facilities, construction equipment, or
storage of materials and equipment to be incorporated in the work are to be obtained and
paid for by Contractor.
ARTICLE 7 - INTERPRETATIONS AND ADDENDA
7.01 All questions about the meaning or intent of the Bidding Documents are to be submitted to
Engineer in writing. Interpretations or clarifications considered necessary by Engineer in
response to such questions will be issued by Addenda mailed or delivered to all parties
recorded by Engineer as having received the Bidding Documents. Questions received less
than 10 days prior to the date for Opening of Bids may not be answered. Only questions
answered by Addenda will be binding. Oral and other interpretations or clarifications will
be without legal effect.
7.02 Addenda may be issued to clarify, correct, or change the Bidding Documents as deemed
advisable by Owner or Engineer.
ARTICLE 8 - BID SECURITY
8.01 A Bid must be accompanied by Bid Security made payable to Owner in an amount of 5
percent of Bidder's maximum Bid Price and in the form of a certified check or bank money
order, or a Bid Bond issued by a surety meeting the requirements of Paragraphs 5.01 and
5.02 of the General Conditions.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, me,
00200-5
INSTRUCTIONS TO BIDDERS
8.02 The Bid Security of the successful Bidder will be retained until such Bidder has executed
the Contract Documents, furnished the required Contract Security, and met the other
conditions of the Notice of Award, whereupon the Bid Security will be returned. If the
successful Bidder fails to execute and deliver the Contract Documents and furnish the
required Contract Security within 15 days after the Notice of Award, Owner may annul the
Notice of Award and the Bid Security of that Bidder will be forfeited. The Bid Security of
other Bidders whom Owner believes to have a reasonable chance of receiving the award
may be retained by Owner until the earlier of 7 days after the Effective Date of the
Agreement or 61 days after the Bid Opening, whereupon Bid Security furnished by such
Bidders will be returned.
8.03 Bid Security of other Bidders whom Owner believes do not have a reasonable chance of
receiving the award will be returned within 7 days after the Bid Opening.
ARTICLE 9 - CONTRACT TIMES
9.01 The number of days within which or the dates by which Milestones are to be achieved and
the work is to be Substantially Completed and ready for Final Payment are set forth in the
Agreement.
ARTICLE 10 - LIQUIDATED DAMAGES
10.01 Provisions for liquidated damages, if any, are set forth in the Agreement.
ARTICLE 11 - SUBSTITUTE AND "OR-EQUAL" ITEMS
11.01 The Contract, if awarded, will be on the basis of materials and equipment specified or
described in the Bidding Documents without consideration of possible substitute or "or-
equal" items. Whenever it is specified or described in the Bidding Documents that a
substitute or "or-equal" item of material or equipment may be furnished or used by
Contractor if acceptable to Engineer, application for such acceptance will not be considered
by Engineer until after the Effective Date of the Agreement.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
00200-6
INSTRUCTIONS TO BIDDERS
ARTICLE 12 - SUBCONTRACTORS, SUPPLIERS, AND OTHERS
12.01 If the Supplementary Conditions require the identity of certain subcontractors, suppliers,
individuals, or entities to be submitted to Owner in advance of a specified date prior to the
Effective Date of the Agreement, the apparent successful Bidder and any other Bidder so
requested, shall within 5 days after Bid Opening, submit to Owner a list of all such
subcontractors, suppliers, individuals, or entities proposed for those portions of the work for
which such identification is required. Such list shall be accompanied by an experience
statement with pertinent information regarding similar projects and other evidence of
qualification for each such subcontractor, supplier, individual, or entity if requested by
Owner. If Owner or Engineer after due investigation has reasonable objection to any
proposed subcontractor, supplier, individual, or entity, Owner may before the Notice of
Award is given request apparent successful Bidder to submit a substitute in which case
apparent successful Bidder shall submit an acceptable substitute, Bidder's Bid Price will be
increased (or decreased) by the difference in cost occasioned by such substitution and
Owner may consider such price adjustment in evaluating Bids and making the Contract
award.
12.02 If apparent successful Bidder declines to make any such substitution, Owner may award the
Contract to the next lowest Bidder that proposes to use acceptable subcontractors, suppliers,
individuals, or entities. Declining to make requested substitutions will not constitute
grounds for forfeiture of the Bid Security of any Bidder. Any subcontractor, supplier,
individual, or entity so listed and against which Owner or Engineer makes no written
objection prior to the giving of the Notice of Award, will be deemed acceptable to Owner
and Engineer subject to revocation of such acceptance after the Effective Date of the
Agreement as provided in Paragraph 6.06 ofthe General Conditions.
12.03 Contractor shall not be required to employ any subcontractor, supplier, individual, or entity
against whom Contractor has reasonable objection.
ARTICLE 13 - PREP ARATrON OF BID
13.01 The Bid Form is included with the Bidding Documents. Additional copies may be obtained
from Engineer.
13.02 All blarrks on the Bid Form shall be completed by printing in ink or by typewriter and the
Bid signed in ink. Erasures or alterations shall be initialed in ink by the person signing the
Bid Form. A Bid Unit Price shall be indicated for each Bid Item listed therein.
13.03 A Bid by a corporation shall be executed in the corporate name by the president or a vice-
president or other corporate officer accompanied by evidence of authority to sign. The
corporate seal shall be affixed and attested by the secretary or an assistant secretary. The
corporate address and state of incorporation shall be shown below the signature.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
00200-7
INSTRUCTIONS TO BIDDERS
13.04 A Bid by a partnership shall be executed in the partnership name and signed by a partner
(whose title must appear under the signature), accompanied by evidence of authority to sign.
The official address of the partnership shall be shown below the signature.
13.05 A Bid by a limited liability company shall be executed in the name of the firm by a member
and accompanied by evidence of authority to sign. The state of formation of the :firm and
the official address of the firm shall be shown below the signature.
13.06 A Bid by an individual shall show the Bidder's name and official address.
13.07 A Bid by a joint venture shall be executed by each joint venturer in the manner indicated on
the Bid Form. The official address of the joint venture shall be shown below the signature.
13 .08 All names shall be typed or printed in ink below the signatures.
13.09 The Bid shall contain an acknowledgment of receipt of all Addenda, the numbers of which
shall be filled in on the Bid Form.
13.10 The address and telephone number for communications regarding the Bid shall be shown.
13.11 The Bid shall contain evidence of Bidder's authority and qualification to do business in the
state where the Project is located or covenant to obtain such qualification prior to award of
the Contract. Bidder's State Contractor License Number, if any, shall also be shown on the
Bid Form.
13.12 Bidders shall indicate the Total Add or Deduct to the Total Base Bid for each Alternate
provided on the Bid Form.
13.13 Bidders may list proposed Substitute Items on the spaces provided on the Bid Form.
Bidders shall clearly indicate the item name, Specification Section Number, and the Total
Deduct to the Total Base Bid for each Substitute Item proposed.
13.14 Bidders shall circle the name of the Base Bid Manufacturer they will provide, if awarded the
Contract. Bidders shall circle only 1 name for each item. If the Bidder fails to circle an
item, the first item listed shall be provided.
13.15 Bidders shall identify the name of the company or subcontractor that will perform the listed
portion of the work if the Bidder is awarded the Contract.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
00200-8
INSTRUCTIONS TO BIDDERS
ARTICLE 14 - BASIS OF BID; COMPARISON OF BIDS
14.01 Bid Unit Price With Alternates
A. Bidders shall submit a Bid on a Bid Unit Price for each Bid Item of work listed in
the Bid Form and include a separate price for each Alternate described in the
Bidding Documents as provided for in the Bid Form. The price for each Alternate
will be the amount [added to] the Base Bid if Owner selects the Alternate. In the
evaluation of Bids, Owner may select any combination of Alternates or the Owner
may choose not to accept any Alternate Bids.
B. The total of all estimated prices will be the sum of the products of the estimated
quantity of each Bid Item and the corresponding Bid Unit Price. The final quantities
and Contract Price will be determined in accordance with Paragraph 11.03 of the
General Conditions.
C. Discrepancies between the multiplication of units of work and Bid Unit Prices will
be resolved in favor of the Bid Unit Prices. Discrepancies between the indicated
sum of any column of figures and the correct sum thereof will be resolved in favor
of the correct sum. Discrepancies between words and figures will be resolved in
favor of the words.
D. Bids will be compared on the basis of the "Adjusted Total Base Bid" and this
amount will be the basis for determining the lowest Bidder. The sum of the Total
Base Bid and any combination of Alternates accepted by the Owner will determine
the "Adjusted Total Base Bid." The Owner may choose to not accept any Alternate
Bids.
14.02 The Bid Price shall include such amounts as the Bidder deems proper for overhead and
profit on account of cash allowances, if any, named in the Contract Documents as provided
in Paragraph 11.02 of the General Conditions.
ARTICLE 15 - SUBMITTAL OF BID
15.01 With each copy of the Bidding Documents, a Bidder is furnished 1 separate unbound copy
of the Bid Form, and, ifrequired, the Bid Bond Form. The unbound copy of the Bid Form
is to be completed and submitted with the Bid Security.
15.02 A Bid shall be submitted no later than the date and time prescribed and at the place
indicated in the Advertisement for Bids and shall be enclosed in an opaque sealed envelope
plainly marked with the Project Title (and, if applicable, the designated portion of the
Project for which the Bid is submitted), the name and address of Bidder, and shall be
accompanied by the Bid Security and other required documents. If a Bid is sent by mail or
other delivery system, the sealed envelope containing the Bid shall be enclosed in a separate
envelope plainly marked on the outside with the notation "BID ENCLOSED." A mailed
Bid shall be addressed to Owner's office.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
00200-9
INSTRUCTIONS TO BIDDERS
ARTICLE 16 - MODIFICATION AND WITHDRAWAL OF BID
16.01 A Bid may be modified or withdrawn by an appropriate document duly executed in the
manner that a Bid must be executed and delivered to the place where Bids are to be
submitted prior to the date and time for the Opening of Bids.
16.02 Bids may be withdrawn after Bid Opening only in accordance with the law.
ARTICLE 17 - OPENING OF BIDS
17.01 Bids will be opened at the time and place indicated in the Advertisement for Bids and,
unless obviously non-responsive, read aloud publicly. A Bid Tabulation of the amounts of
the Base Bids and major Alternates, if any, will be made available to Bidders after the
Opening of Bids.
ARTICLE 18 - BIDS TO REMAIN SUBJECT TO ACCEPTANCE
18.01 All Bids will remain subject to acceptance for the period oftime stated in the Bid Form, but
Owner may, in its sole discretion, release any Bid and return the Bid Security prior to the
end of this period.
ARTICLE 19 - EVALUATION OF BIDS AND AWARD OF CONTRACT
19.01 If the Contract is awarded, award will be made on the basis of the lowest responsive,
responsible, qualified Bidder determined by the Adjusted Total Base Bid.
19.02 Owner reserves the right to reject any or all Bids, including without limitation
nonconforming, nonresponsive, unbalanced, or conditional Bids. Owner further reserves
the right to reject the Bid of any Bidder whom it finds after reasonable inquiry and
evaluation to not be responsible. Owner may also reject the Bid of any Bidder if Owner
believes that it would not be in the best interest of the Project to make an award to that
Bidder. Owner also reserves the right to waive all informalities not involving price, time, or
changes in the work and to negotiate Contract terms with the successful Bidder.
19.03 More than 1 Bid for the same work from an individual or entity under the same or different
names will not be considered. Reasonable grounds for believing that any Bidder has an
interest in more than 1 Bid for the work may be cause for disqualification ofthat Bidder and
the rejection of all Bids in which that Bidder has an interest.
19.04 In evaluating Bids, Owner will consider whether or not the Bids comply with the prescribed
requirements and such Alternates, Bid Unit Prices, and other data as may be requested in the
Bid Form or prior to the Notice of Award.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
00200-10
INSTRUCTIONS TO BIDDERS
19.05 In evaluating Bidders, Owner will consider the qualifications of Bidders and may consider
the qualifications and experience of subcontractors, suppliers, other individuals, or entities
proposed for those portions of the work for which the identity of subcontractors, suppliers,
other individuals, or entities must be submitted as provided in the Supplementary
Conditions.
19.06 Owner may conduct such investigations as Owner deems necessary to establish the
responsibility, qualifications, and financial ability of Bidders, proposed subcontractors,
suppliers, individuals, or entities to perform the work in accordance with the Contract
Documents. As a condition of its Bid, Bidder is required to waive any and all claims of
whatever nature against Owner, Engineer, and their employees and agents which arise out
of or relate to such investigations and statements made as a result thereof, except for
statements that can be shown by clear and convincing evidence to be intentionally false and
made with actual malice. This waiver is not intended to restrict Bidder's rights to challenge
a Contract award pursuant to law.
19.07 If the Contract is to be awarded, Owner will award the Contract to the Bidder whose Bid is
in the best interests of the Project.
ARTICLE 20 - CONTRACT SECURITY AND INSURANCE
20.01 Article 5 of the General Conditions, as may be modified by the Supplementary Conditions,
sets forth Owner's requirements as to Performance and Payment Bonds and Insurance.
When the successful Bidder delivers the executed Agreement to Owner, it shall be
accompanied by such bonds.
ARTICLE 21 - SIGNING OF AGREEMENT
21.01 When Owner gives a Notice of Award to the successful Bidder, it shall be accompanied by
the required number of unsigned counterparts of the Agreement with the other Contract
Documents which are identified in the Agreement as attached thereto. Within 15 days
thereafter, successful Bidder shall sign and deliver the required number of counterparts of
the Agreement and attached documents to Owner. Within 10 days thereafter, Owner shall
deliver 2 fully signed counterparts to successful Bidder with a complete set of the Drawings
with appropriate identification.
END OF DOCUMENT
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
00200-11
INSTRUCTIONS TO BIDDERS
DOCUMENT 00300
INFORMATION AVAILABLE TO BIDDERS
Portions of reports and drawings used by the Engineer in the preparation of the Bidding Documents
are attached to this document. The Technical Data is identified in the Supplementary Conditions.
Bidders are responsible for their own interpretation, verification, and use of the Technical Data
contained in these reports and drawings consistent with the General Conditions and Supplementary
Conditions. Reports, drawings, and other historical information regarding the Proj ect may be available
for Bidder's review at the Engineer's office. Schedule a viewing time with the Project Manager.
END OF DOCUMENT
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
INFORMA TION AVAIlABLE TO BIDDERS
Bonestroo Rosene Anderlik - St. Paul, MN - (651)636-1311
I~' Bonestroo
e Rosene
"till Anderlil< &
,~, Associates
Engine'" (, Architect'
BIDDER:
D iii:) ~~j)()R4T/~A)
,
DOCUMENT 00410
REVISED BID FORM
REVISED BY ADDENDUM NO.1
2005 STREET, PARK AND UTILITY
INFRASTRUCTURE IMPROVEMENTS
CITY PROJECT NO. 779
FILE NO. 000034-04159.0
NEW HOPE, MINNESOTA
2005
BID COpy
THIS BID IS SUBMITTED TO:
City of New Hope, Minnesota
440 I Xylon A venue North
New Hope, MN 55429-4898
I 01 The undersigned Bidder proposes and agrees if this Bid is accepted to enter into an Agreement with Owner in the fonn
included in the Bidding Documents to perform all work as specified or indicated in the Bidding Documents for the prices and
within the times indicated in this Bid and in accordance with the other tenns and conditions of the Bidding Documents.
2.0 I Bidder accepts all of the terms and conditions of the Instructions to Bidders, including without limitation those dealing
with the disposition of Bid Security. The Bid will remain subject to acceptance for 60 days after the Bid Opening, or for such
longer period of time that Bidder may agr ee to in writing upon request of Owner
30 J In submitting this Bid, Bidder represents that:
A Bidder has examined and cmefully studied the Bidding Documents, the other related data identified in the
Bidding Documents, and the following Addenda, receipt of all which is hereby aclmowledged:
Addendum No.
Addendum Date
!
Lj - J:)- J-coS-
B Bidder has visited the Project Site and become familiar with and is satisfied as to the general, local, and
proj ect Site conditions that may affect cost, progress, and performance of the work
C Bidder is familiar with and is satisfied as to all federal, state, and local Laws and Regulations that may affect
cost, progress, and performance of the work
00003~041590131DFOR1'1 xis
R:viscd I3y .'\dJcndum No [
00410-1 (R)
REVISED DID FORM
Bonestroo Rosene Anderlik - St. Paul, MN - (651)636-1311
D Bidder has carefully studied all: (I) reports of explorations and tests of subsurface conditions at or
contiguous to the Project Site and all drawings of physical conditions in or relating to existing surface or
subsurface structures at or contiguous to the Project Site (except Underground Facilities) which have been
identified in SCA.02, and (2) reports and drawings of Hazardous Environmental Conditions that have been
identified in SC-406,
E, Bidder has obtained and carefully studied (or accepts the consequences for not doing so) all additional or
supplementary examinations, investigations, explorations, tests, studies, and data concerning conditions
(surface, subsurface, and Underground Facilities) at or contiguous to the Project Site which may affect cost,
progress, or performance of the work or which relate to any aspect of the means, methods, techniques,
sequences, and procedures of construction to be employed by Bidder, including applying the specific means,
methods, techniques, sequences, and procedures of construction expressly required by the Bidding
Documents to be employed by Bidder, and safety precautions and programs incident thereto
F Bidder does not consider that any further examinations, investigations, explorations, tests, studies, or data are
necessary for the determination of this Bid for performance of the work at the price(s) Bid and within the
times und in accordance with the other terms and conditions of the Bidding Documents
o Bidder is aware oflhe general nature of work to be performed by Owner and others at the Project Site that
relates to the work as indicated in the Bidding Documents
H. Bidder has correlated the information knovm to Bidder, information and observations obtained fTom visits to
the Project Site, reports and drawings identified in the Bidding Documents, and all additional examinations,
investigations, explorations, tests, studies, and data with the Bidding Documents.
I. Bidder has given Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder
has discovered in the Bidding Documents, and the written resolution thereof by Engineer is acceptable to
Bidder
J, The Biddmg Documents are generally sufficient to indicate and convey understanding of all terms and
conditions for tbe per fOlmance of the work for which this Bid is submitted
J(, Bidder will submit written evidence of its authority to do business in the state where the Project is lucated nol
later than the date of its execution of the Agreement
40 I Bidder further represents that:
A The prices in this Bid have been arrived at independently, without consultation, communication, or
af:,'1eement as to any matters relating to such prices with any other Bidder or with any competitor for the
purpose of restricting competition
B The prices in this Bid have not or will not be lrnowingly disclosed to any other Bidder or competitor prior to
opening of the Bids
C No attempt has been made or will be made by the Bidder to induce any other person or firm to submit or not
to submit a Bid for the purpose of restricting competition
GOOOJ~O~1500B1DfORM ,~
Revis,d By AdOendul1l No, I
00410,2(R}
REVISED DID FORM
Bonestroo Rosene Anderlik - St. paul, MN - (651)636-1311
A Joint Venture
Joint Venture Name:
(SEAL.)
By:
(Signature of joint venture partner)
Name (typed or printed):
Title:
Business address:
Phone No:
Fax No :
Joint Venturer Name:
(SEAL)
By:
(Signature)
NJme (typed or printeci):
Title:
Business Street Address (No PO. Box #'s):
Phone No:
Fax No:
Phone and Fax Number, and Address for receipt of official communications:
(Each joint venturer must sib'T1 The munner of signing for euch individuul, pal tncrship, and COI por alion [hut is a par ly lo
the joint venture should be in the manner indicated above)
END OF DOCUMENT
U00034J4159CBIDFORM ,~
lIcviscd By Addendum No I
00410-11(R)
REVISI.:D IlID FORM
UNITED FIRE & CASUALTY COMPANY
BID BOND
KNOW ALL MEN BY THESE PRESENTS, THAT WE
DMJ Corporation
P. O. Box 299
Hamel, Minnesota 55340-0299
as Principal, hereinafter called the Principal, and the United Fire & Casualty Company, a corporation
duly organized under the laws of the State of Iowa, with Administrative Offices at P.O. Box 73909,
Cedar Rapids, IA 52407, as Surety, hereinafter called the Surety, are held and firmly bound unto
City of New Hope, Minnesota
as Obligee, hereinafter called the Obligee, in the sum of Five Percent (5%) of Amount of Bid---
for the payment of which sum well and truly to be made, the said Principal and the said Surety, bind
ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally, firmly by
these presents.
WHEREAS, the Principal has submitted a bid for
2005 Street, Park and Utility Infrastructure
City Project No. 779
Ne\v Hope, MN
NOW, THEREFORE, if the Obligee shall accept the bid of the Principal and the Principal shall enter
into a contract with the Obligee in accordance with the terms of such bid, and give such bond or bonds as
may be specified in the bidding or contract documents with good and sufficient surety for the faithful
performance of such contract and for the prompt payment of labor and material furnished in the
prosecution thereof, or in the event of the failure of the Principal to enter sllch contract and give such
bond or bonds, if the Principal shall pay to the Obligee the difference not to exceed the penalty hereof
between the amount specified in said bid and such larger amount for which the Obligee may in good faith
contract with another party to perform the work covered by said bid, then this obligation shall be null and
void, otherwise to remain in full force and effect.
Signed and sealed this May 2, 2005
(WItness)
iZ,/'J!c /. ~u-<-' ./
/ (Witness)
DMJ Corporation
(Principal)
~
:' ,"."..- ~
No Seal
A ,(Ti-tle.)..+--
. /U-"J, oUJV:J
United Fire & Casualty Company (Seal)
/~ /' ,/// _.-'i'1, / 7
~dftf C/~/ //,'~/ ///
Kurt <::.'dndblad, ~
ACKNOWLEDGMENT OF PRINCIPAL (Corporation)
STATE OF:
COUNTY OF:
On this day, May 2, 2005, before me personally come(s) !1er.}// L- !-A<-Iv~ to
me known, who, being by me duly sworn, deposes and says that he/she resides in the City of
Hamel, MN, that he/she is the J2U/,1-ld..LtL,l of the DMJ Corporation
the corporation described in and which executed the foregoing instrument; that he/she knows the
seal of the said corporation; that the seal affixed to the said instrument is such corporate seal; that
it was so affixed by the order of the Board of Directors of said corporation, and that he/she
signed his/her name thereto by like order.
I ~,
COLLEEN s. SELLYI
Notary Public-Minnesota
My COmmission Expires Jan 31, 2010
Ylu{i)lrt~(L/
Notary Public /
ACKNOWLEDGMENT OF SURETY
STATE OF: Minnesota
COUNTY OF: Ramsey
On this day, May 2 ,2005, before me personally come(s) Kurt C. Lundblad, to me
personally known, who being by me duly sworn, did say that he is the aforesaid officer or
Attorney-In-Fact of the United Fire & Casualty Company, a corporation; that the seal affixed
to the foregoing instrument is the corporate seal of said corporation, and that said instrument was
signed and sealed in behalf of said corporation by the aforesaid officer, by authority of its board
of directors; and the aforesaid officer acknowledged said instrument to be the free act and deed of
said corporation.
&4X2L,
Notary Public
"----'"7,. /
- L/~....,,,-- _'
UNITEDFIRE&qAsu4LTV.COMPANV
H()MEpFfIC[-PED;:xR RAPIDS, 19WA
CERTIFIED COPY9FPOVYEROF,ATTORNEY
(Original on file at Home Office of Company " See Certification)
.. . ..
KNOW ALL MEN BYTHESE PRESE~T~;ThqtfhelJNITEnFiRE & CASUAL TYCOMPANY,C1cOrporation duly organized and existing
under the laws of the State of lowa,and having its princfpaloffiFein Cedar Rapid9, state of Iowa, does make, constitute and appoint
'. . . ,".
D. R. DOUGHERTY, OR JACK CEDl\RL~1\Fn, OR E:}/LANGE; OR, CHRISTINBM. HANSEN, OR KURTiC. LUNDBLAD, OR
C A.HOUSH, ALL INDIVIDUALLY of SAINT PAUL MN
::.' .:,: ,",', . ::." .. :', -........ ,'," :';-'. ":;,':' .... -,". .."........ .....;. :.>. ..: -.- :..:." .. ...... :.,'.;. .,c,.,
:; ............ ..........;.:.......:.>, .::,:":-::-..:. :>:',:":;:,"-:-':: ;,:>";::.; :'-;.:::: :'<:, "::,.: _" ...... ,', c' . "'< ',: ....' .
its true and lawful Attorney(s)-in-Fact with pow"r aQd authority hereby conferred to sign, 'seal and execute in its behalfal! lawful bonds,
undertakings andother obligatory instrumentsgf similarnature~s f~llowS:Any and AU Bonds
and to bind UNITED FIRE & CASUALTY COMP,l>.NY thereby as. fully apdtothesame extentas if such instruments were signed by the
duly authorized offjceq;of UNfTEDFIRE & CASUALTY COMPANY gnd all the,?lctsof sajdAttorney, pursuanUo the authority hereby
given are hereby ratified and confirmed.
The Authority hereby granted is continuous and shall remain in fulLforce and effect until revoked by UNITED FIRE &
CASUALTY COMPANY.<i ,/> << >i>.i .....'........ ,<' 'i< ..... '. ... '... '....'.
This power of Attorney is made aQd7xecuted PlJrsuantto~nd byauthorfty oUhe following By-Law duly adopted by Board
Directors of the Company on April 18, 197;3.> d.,.,." ...'...i/..> "'<'
"'Arti"le\i-SuretyBonds andUnder1akings"
Section 2, Appointment of Attorney-in-Fact. "The President or any Vice President, anyotheroffjceroftheGompany may,
from time to time, appoint by written certificates attorneys-in-fact to act in behalf of the Company in the execution of policies of
insurance, bonds, undertakings and other obligatory instruments of like nature, The signature of any officer authorized hereby,
and theCorporateseal,maybe affixed by facsimile to any power of attorney or special power of attorney or certification of
eitherauthClrized hereby; such signature and seal, when so used, being adopted by the Company asthe original signatur~.of
such officer andthe, original seal of the, Company, to be valid andbinding upon the Companywiththesame force andeffectas
though manualfy affixed,. Such attorneys-in fact, subject to the Hmftations set forth in their respective certificates of authority ,
shall have full power to bind the Company by their signature and execution of any such instruments and to attach the seal of
the Company thereto.' The President or any Vice President, the Board of Directors or any other officer of the Company may at
any time revoke all power and authority previously given to any attorney-in-fact.
~""''' IN WITNESS WHEREOF, the UNITED FIRE & CASUALTY COMPANY has caused these presents to be signed by
~.. ~~ its vice president and its corporate seal to be hereto affixed this 8th day of January, 2004
S CCnOtATE i\'
\ SiAL iJ UNITED FIRE & CASUALTY COMPANY
..,...... ';.,~$' ~
....~._~ ,,~ /2- ~ /f
""'."....",,' By ~ L{. ~ Vice President
State onowa, County of Linn, ss:
On>8thday Of January, 2004, before me personally came Randy A. RamIo
tome known, who being by medulysworn, did depose and say; that he resides in Cedar Rapids, State oflowa; that he is aVice
President of the UNITED FIRE & CASUAL TY COMPANY, the corporation described in and which executed the above instrument; that
he knows the seal of said corporation; that the seal affixed to the said instrument is such corporate seal; that it was so affixed pursuant
to authority given by the Board of Directors of said corporation and that he signed his name thereto pursuaf} to like authority, and
acknowledges same to be the act ,/;?//i.//.'.. ..,' ..' /?} .. ,.} /_
,.. i,' 1,[,(1....., /Ic/(L ~ // t.j(~/"----
Notary PUbli<t/< ,
Mycommiss,lon ex es: ...10/26/2004
,.1.', o~'jJP~'A',,~
\z. .
, . .
~.. ... ow'"
I, the undersigned officer of the UNITED FIRE & CASUALTY COMPANY, do hereby certify that I have compared the foregoing copy of
the Power of Attorney and affidavit, and the copy of theS~ctiol1 of the by-laws of said Company as set forth in said Power of Attorney,
with the ORIGINALSON FILE IN THEHOMEOFFICEOFSAfDCOMPANY,and thatthe same are correct transcripts thereof, and of
the whole of the said originals, and thatthe said Power ofAttorl1ey has not been revoked and is now in full force and effect.
~<~"~ Intes~nY.1ereOf I hae,untosubscribedmy""n~.Ctl8and affixed the corporate seal of the said Company
~...I', '#;.,'.......,~lQ:~ this. "', day of " , '20o~:> .
S CCarDIATE I"
i -.- ~
? alAL ..,~
,.~~< . 4t~$
~.._\. "'~
. --.,&>>ti",'\
fJ--/ / t!Y7
Secretary
BOND0019 0802 01
UND3292B
Bonestroo Rosene Anderlik - st. paul, MN - (651)636-1311
402 Bidder understands that the law may require the Owner, or Engineer at the Owner's direction, to undertake an investigation
and submit an evaluation concerning Bidder's responsiveness, responsibility, and qualifications before awarding a Contract
Bidder hereby waives any and all claims, or whatever nature, against Owner, Engineer, and their employees and agents, which
arise out of or .relate to such investigation and evaluation, and statements made as a result thereof, except for statements that can
be shown by clear and convincing evidence to be intentionally false and made with actual mulice. Nothing in this paragraph is
intended to restrict l3idder's rights to challenge a Contract pursuant to law
50 I Bidder will complete the work in accordance with the Contract Documents for the following price(s):
All specific cash allowances are included in the price(s) set forth below and have been computed in
accordance with paragraph 11.02 of the General Conditions.
Bid Unit Prices have been computed in accordance with paragraph 11.03 B of the General Conditions
Bidder acknowledges that estimated quantities are not guaranteed, and are solely for the purpose of
comparison of Bids, and final payment for all Unit Price Bid items will be based on uctuai quantities
provided, determined as provided in the Contract Documents.
No. Item Units Qty Unit Price Total Price
PART 1 - SANITARY SEWER:
. '- 00.
MOBlLlZA TION LS 1 $ / ~f ceoJ $ / ~, cx::<::J" --
ou .::) ex::; J 00
2 CLEAR AND GRUB TREE 2$ ;;5'0/ - $
~ 80, C~L
.3 REMOVE DOGWOOD BUSH EA 4$ dO, - s
Li- .5"0 32'), .:)0
4 REMOVE BITUMINOUS DRJVEW A Y SY 85 S S
0"<.) ;gO.. 00
(. -"
5 REMOVE CONCRETE SIDEWAlK SF 180 $ S
I. 1f5' 73;' So
6 REMOYE CONCRETE DRlYEW A Y SF 510 $ -- S
.
PA YEMENT '-V Cft.)
7 CONNECT TO EXJSTrNG SAN!T ARY EA 1$ cpSO, - s tv ,-S-O " -'
SEWER 8" PVC PIPE 0"'..)
&0
8 8" PYC SANITARY SEWER, SDR 35, 8'- LF 185 $ ::::>3 - S t:" , 10,<;. -
) ..
10' DEEP , I
:s.s. ~ 070> r:ro
9 8" PYC SANITARY SEWER, SDR 35, ] 0'- LF 25 S S -
12' DEEP ~ , ~ -.; 0('".;1
10 8" PYC SANlT ARY SEYlER, SDR 35, 12'- LF 40 $ ,=5 s-- s II~.J CiO J ..-/
14' DEEP 00 :;:; &::{ if., i/("...J.
II 8" PVC SANITARY SEWER, SDR 35, 14'- LF 79 $ Lib_ s ) I '-' ".----
] 6' DEEP -,
cr.? V'</
12 4' DIAMETER SANITARY MH, 8' DEEP, EA 2 $ ~fScc:J,~' S 5000.- -'
/
!NCL R-1642-B CSTG Crc.J cr'....7
13 4' DIAMETER SANITARY MANHOLE LF 9 $ I 70 .' - $ !;S:SO.. --
. I
OVERDEPTH
GOOOJ~O~ 1590BIDFORM ,I;
Rt\;scu By '\UdClll11l11l No 1
00410-3(R)
REVISED IllD FORM
Bonestroo Rosene Anderlik - St. Paul, MN - (651)636-1311
No. Item Units Qty Unit Price Total Price
crt:J cv
14 CORE DRlLL CONNECTION TO EA I $ 1;/00.. - s !r I c;x::; I --
EXISTING MANHOLE ~
15 CONNECT TO EXISTING SEWER EA 4$ :3 ~OJ - $ ~.~tc,O.- C"..)
---
SERVICE arO
16 BULKHEAD EXISTING SANITARY EA 4 $ ~d' - d18~ ~
$
SEWER SERVICE
tx./ , ~ C/O
17 8" X 4" pve \\fYE, SDR 26 EA 5 S ;)50,. - $ II .'--
. ,
.. !5 ~.:5~ ' .So
,
18 4" rvc, SDR 26 SERVICE PIPE LF 115 $ $ ,3/i~77o/ -
::...~1 (;0
19 SALV AGE AND REINSTALL, EA 1$ ;,70:::7, ..-- $ 1/700,. -
HYDRANT AND GATE VALVE ' ,
/../.- .;)S"' 7 Cv~' ~.
20 4" CONCRETE SIDEWALK SF 180 $ - $
,
ifo, 0"<) ~G:10J co
21 AGGREGA TE BASE, CLASS 5 TN 60 $ - S --'
22 TYPE 41 BITUMINOUS FOR TN 18 $ 53-~ $ 7S1. ~,
DRIVEWA YS
, ~ I'rC'
2.3 SALVAGE AND REINSTALL LS 1 S c,,'/~' S (..(',000, --'
RET AfNING WALL , ,
oc.- GOO.. 00
24 RESTORE LANDSCAPING LS I $ fr:;C;Cl. - $ -
6" CONCRETE DRIVEWA Y 1-(, ,:5 dl tV';;d' S32
25 SF 510 $ - S
PAVEMENT 4/I 5"""0
26 SODDING, LA WN TYPE SY 1350 $ ()- s 3/507. -
s 57/ cY'3o- so
TOTAL PART 1 .. SANITARY SEWER :...---
!
PART 2.. STREET IMPROVEMENTS:
::-eJ ;; d 00, t<J
27 TRAFFIC CONTROL LS / dOG -. S
IS/I' -
. ,
~ V'U
28 GEOTEXTILE CB FILTER EA 4$ $0'- S CJOO,
"'.0 'r".J-O C10
29 STREET SWEEPER WITH PICK UP HR 16 $ i JO,- s /,1 J -
BROOM WITH OPERA TOR I 'I
d-' IS' :J.I ~( 7S: ~
30 REMOVE BITUMINOUS PA VEMENT SY 900 $ S
3. so (, if <( ;J.... So
31 REMOVE BITUMINOUS DRIVEWA Y SY 355 S S
,
~ <7 dO.. '~..r('/
32 REMOVE CONCRETE CURB AND LF 240 $ S -
GUTTER Cft/
~Q
.33 REMOVE CBMH CASTING EA I S ioo~- s /00----
,
~' C)-t;) 7C~ 00
34 SA \\'ING BJTUMrNOUS PA VEMENT LF 265 S ......> . - S
I.J" -
,
COOOH04159011IDFORM ,is
Rr:vised By Addendum No I
0041 Q-4(R) REVISED BID FORM
Bonestroo Rosene Anderlik - St. Paul, MN - (651)636-1311
No. Item Units Qty Unit Price Total Price
! L( · c.-u i/I (/..x5 _ ~
35 AGGREGA TE BASE, CLASS 5 TN 725 $ -' $
, I
36 TYPE41 BITUMINOUS FOR TN 100 $ <)~.~ S;3CO. CIO
$ -'
DRIVEWA YS
'-( cr . (;-0 '?; ? dO ~ U,,)
37 BITUMINOUS BASE COURSE, TYPE TN 180 S - $ -.'
JIB
38 BITUMINOUS WEAR COURSE, TYPE 53- ~, ~~770. ~,
TN 90 $ $
4IA ,
39 BITUMINOUS MATERIAL. FOR TACK 5'~ d-IO- cxJ
GAL 70 $ $ -'
COAT ocJ
- (;-rJ
40 FURNISH AND INSTAll NEW R3067Y Ell. I $ (p "Sc:;/ ~ $ (050, --
CB CASTING, INCL AD], RlNGS cO
41 B618 CONCRETE CURB AND GUTTER LF 400 $ 1(, - c:=:. $ / L{ 0 <7.' ,;..---
l {j
<:.(5' . 0. o<J
42 SODDING, LAWN TYPE SY 500 S d-.~--- s ~ J J- --'
TOTAL PART 2. STREET /-/71 (od 7.. ...)<:?
S -
IMPROVEMENTS J
PART 3 - PARK IMPROVEMENTS: " ~
'tV
43 SITE GRADING/FINAL. SHAPING LS 1$ 6. <:.,<::X::?.. $ -6.~~J --
/ '
Lf;90.~ $ L/; ~~. (.r<J
44 SPREAD SALVAGED TOPSOIL. LS i $ -
10' '-'-0 3;. if <(0, ~
45 AGGREGA TE BASE, CLASS 5 TN 215 $ - $
GCJ Cj 7$: ~
46 MNDOT SEED MIX 60A AC 075 $ t 5Q:::) J- S
, I
,...., ,?..sO, ~
47 MNDOT SEED MIX 80A AC 05$ 1/700.- $
I
48 NORTHWOODS MAPLE, 2 1/2" CAt Ell. .3 S i-f I ;).. . 6"5:- S 11 d-3~ . ~
CONT AINER STOCK .s::: ~
49 BITUMINOUS WEAR COURSE, TYPE TN 75 $ $ :J; 9 7,<).' ~
3.-
41A,PATHWAY ,
C-<.J 700. UO
50 4" PERFORATED POLYETHYLENE Lf 50 S IX". -- s -
I
PIPE (.>'Q C!Q
51 CONCRETE PLA Y AREA CURBING LF 400 S I (" ' "---." $ 41 '-100..
,
dl;,670. 00
TOTAL PART 3 - PARK S ---
IMPROVEMENTS
00003.D.1590IlIDFORM ,Is
I1.cvi5Cd 13y AdJcnuum No J
OD410-5(R)
REVISED !liD FDRM
Bonestroo Rosene Anderlik - st. Paul, MN - (651)636-1311
No.
Item
Units
Qty
Unit Price
Total Price
PART 4 - PARKING LOT:
:.0 eN
52 MOBlUZA TION LS 1 $ ~/'-<;OO.. -' $ ,~5oo J --
,;1. e::::.. o-u
53 REMOVE BITUMINOUS PA VEMENT SY 3550 $ $ 7,/00.> --
I
54 REMOVE CONCRETE SIDEWALK SF 125 $ i. a~ $ i d-S, ~
,
COMMON EXCA V A TION (EV)- ! ! (10 __10<-';00., ~
55 CY 3500 $ / ( - - $
OFFSITE c.rV ~,
56 BITUMINOUS WEAR COURSE, TYPE TN .330 S 5"3.- s i 71 LliO,
41A I I
57 BITUMINOUS BASE COURSE, TYPE TN 3,30 $ '-(1- ""'5:!- $ /~: /7CJ, ~
"IB ,
~ "3;)/ oCO. ~
58 AGGREGA TE RASE, CI,ASS.5 TN 2000 $ t:7 . --' $
.
. (,., (;7 / I; L"v 0" :/D
59 8612 CONCRETE CURB AND GUTTER LF 1100 $ ;0' --- $ --
,
';?: ~-o c ~
60 CONCRETE V ALLEY GUTTER SY 40 $ 1- .-' $ i, I ;)OJ -
/ ,
o:r<;l 3; VV
6] 6" CONCRETE DRIVEWAY SF 600 S :::)J --
$ ,C;K::.CJ j -'
PAVEMENT eN' '7:5
62 4" CONCRETE SIDEWALK SF 275 S i' - $ Ili,,<Z' '----"
I / I
a..;$- ~a,
63 4" SOLID LlNE, YELLOW PAINT LF 2350 S it $ .stf 7 . ';f---
;.,S., ~ $ ~"
64 PAVEMENT MESSAGE, EA 10 $ iSd"
. ,
HANDICAPPED SYMBOL - PAINT ~ ~.s: ~
IS- --
65 PA VEMENI MESSAGE, ONI.Y - PAINT EA .3 5> $
,
IS) .~ i (70" ~-
66 PAVEMENT MESSAGE, STRAIGHT EA 8 $ $
ARROW - PAINT dS
TOTAL PART 4 - PARKING LOT $ /51, :)~3y~
,- 'I
BASE BID -7 \iSO.Sa
TOTAL PART 1 - SANITARY SEWER S
, ~") / ~ - ~
/
TOTALPART2-STREET $ i{7: t.;) 7, SO
IMPROVEMENTS J
TOTAL PART 3 - PARK $ C)- Ii 07"" ~ &0
IMPROVEMENTS
~ C;S
TOTAL PART 4 - PARKING LOT s /3I,S..:;;?.._
"
TOT AL BASE BID $ CJt",c;.. 676 ;AS
-.
/ ..
OD003.0.1 59031DFORM ,I;
Revised By Addendum No I
00410-6(R)
REVISED DiD FORM
Bonestroo Rosene Anderlik - St. paul, MN - (651)636-1311
No. Item Units Qty Unit Price Total Price
AL TERNA TE NO.1 - STORM SEWER
(PARK): 330. ~ $
67 REMOVE MANHOLE OR CA rCH EA ] $ 33o~ '!52.,
BASIN
55 <X,/ I; if ffS.. ~
68 15" RCP STORM SEWER LF 27$ -' $
0-0 if....)
(pO. - i, 7';)0/ ---
69 IS" RCP STORM SEWER LF 32 $ S
, I .
~ :5: ~70. (.n',,/
70 4' DIA STORM CATCH BASIN EA 2 $ ;:J73S -$ ---
MANHOLE I
71 CONNECT EX, STORM SEWER PIPE ~()O.. W (:00,02.
EA 2 $ S
TO STRUCTURE
J CJ ~ Ck2 <):" 0"0
TOT AL AL TERNA TE NO.1 - STORM $
SE'\oVER (PARK) , I
AL TERNA TE NO.2 - STORM SEWER
(CHURCH): , 0,:, CJr..J
72 MOBIUZA TlON LS I $ r?1 CX::X::>' - S ~I CGC; J -
.3 -' IJ() 990, (/7...;>
73 REMOVE MANHOLE OR CATCH EA .3 $ S -'
30--
BASrN ~? 1)0
74 REMOVE BITUMINOUS PA VEMENT SY 760 $ J,r S '~d -
;,,~,-O.
75 REMOVE CONCRETE CURB AND 70 $ q, ~::;2. ;:; 8'0 , C'T,)
LF S ---
GUTTER ':X../
5; -j?C), ere/'
76 REMOVE 24" RCP STORM SEWER LF 179 $ dO, - s ---
PIPE I
co , - Q'C)
77 BULKHEAD EXISTING STRUCTURE EA 1 S __-1675- ~ s /b.:5J -
~, r1Z? -ciS
78 REMOVE AND REPLACE LS 1$ 61 G"c?() .- S _ 6fi 00::7 J :..-.- /d)'.
, ..{ -c.
MONUMENT/SIGN AND
LANDSCAPING 0'0
79 15" Rep STORM SEWER LF 20 $ 3d' s ~:> qo. 0C:>
-'
c,-.,.,; /0 J;!.b ,I
80 24" RCP STOR1v1 SEWER, CLASS .3 LF 263 $ L.(CJ J -' ~( J ~_~
s I . --- b0,-
/ r) 131\
(,:;> (. <."'0 s3~5?I'~ ~?'
81 33" RCP STORM SEWER, CLASS 3 LF 649 $ -
Co C CC7
82 4' DlA STORM MANHOLE EA IS 4QCJ- ~,/OO> -
J 70.. $
83 4' D1A STORM CATCH BASIN EA 5 S Cot/ 2:), ~ 0?,;7
C3o,,)O, -$ I< / - -"--
MANHOLE
~? .... 2 ~
84 4 5' DJA STORM MANHOLE EA I S-dr2~j- $ .?I C>O,-
GOOOJo\04159DBIDFORM ,~
Rc\iscd By ^dJcndulr. No I
00410-7(R)
REVISED DID fORM
Bonestroo Rosene Anderlik - St. Paul, MN - (651)636-1311
No. Item Units Qty Unit Price Total Price
85 '-.5' D1A STOR.M CA TCH BASIN EA ] $ d) R'7S ~$~Z$~_ ~
MANHOLE
~/,-<)70 ~ ~ $ ,~S70/ vo
86 5' DIAMEI ER STOKM SEWER MH EA I $ -
+ . .~ - 512-
87 6' DIA STORM MANHOLE EA I $ ~, ~CC?)
~! $
L(cx::?! (..~ 1001 -.rrJ
88 CONNECT EX, STORM" SEWER PIPE EA I $ $ -
TO STRUCTURE (.r</
89 SA WING BITUMINOUS PA VEMENT LF 700 $ 3/ -' $ dl/OO. ~,
,
/Lc! ~ Cr/ L{CK) J ~
90 AGGREGA IE BASE, CLASS 5 TN 400 $ $
,
Lit, Cr(}, t.rl / t?S. ~
91 BITUMINOUS BASE COURSE, TYPE TN 125 $ S
JIB
C"'3 0-0 '......)
92 BITUMINOUS WEAR COURSE, TYPE TN 125 $ --.J - $ 4/ (/;)-0; ~,
41A
5' CrO /3:5, ~
93 BITUMINOUS MATERIAL FOR TACK GAL 45 $ - $
COAT ou i t:-.o
;3-0.. ..-',.-
94 8618 CONCRETE CURB ^ND GUTTER LF 70 $ $ I, OOJ ---
. (
d' 4~ ;)/450, 0'0
95 SODDING, LA \VN TYPE SY 1000 $ ;..--0 $ ----
$ L C1-;-7::J9'. o<J
TOTAL AL TERNA TE NO.2 - STORM 155 f-@
SEWER (CHURCH) --
/1 g! 0)"1.00 !\Rf\
v
AL TERNA TE NO. .1 - DRINKING
FOUNTAIN:
"""'" 0""-'
96 I" CORPORATION STOP EA 1 s_l_7~:'__"=~ s.l'7~" -
5' .:10, $-W5<;J. ~, ~S;;
97 I" TYPE "K" COPPER \VATER LF 50 S -d .--=-
SERVICE Lf -J 7.Ct
. :J-S "'.......) ! C-o. ~
98 I" CURB STOP AND BOX EA IS / J -- s
.3 ,~~ .5 J 631. ")
99 FURJ"lISH AND INSTALL, DRINKING LS i S 1031. -- s -"
.I
FOUNT AIN s!t,S8/ -x.,.
TOTAL ALTERNATE NO.:3- "-
DRINKING FOUNTAIN j
C0003<0< 1590BIDFORI..1 .Is
Revised Oy Addendum No I
00410-S(R)
REVISED BID fORM
Bonestroo Rosene Anderlik - St. paul, MN - (651)636-1311
6.0] Bidder agrees that the work will be Substantially Completed and completed and ready for Final Payment in
accordance with paragraph 14,07 B of the Genera] Conditions on or before the dates or within the number of calendar days
indicated in the Agreement
602 Bidder accepts the provisions of the Agreement as to liquidated damages in the event of failure (0 complete the work
within the times specified above, which shall be stated in the Agreement
7,0 I The following documents are attached to and made a condition of this Bid:
A. Required Bid SecUlity in the form of 5 percent.
8 0] The terms used in this Bid with initial capital letters have the meanings stated in the Instructions to Bidders, the
General Conditions, and the Supplementary Conditions,
SUBMITTED on
11 ~(' -f rl
/-If)~j ;}"7 .
i
,20<:::)..:)
If Bidder Is:
An Individual
Name (typed or printed):
By:
(SEAL)
(Individual's signature)
Doing business as:
Business Street Address (No POBox Irs):
Phone No.:
FuxNo:
DOOOJ4'l41 S9H3lDr-ORM xis
Rc,iscu Dy l\uJcnuum No I
00410-9(R)
REVISED OlD FORM
Bonestroo Rosene Anderlik - St. Paul, MN - (651)636-1311
A Partnership
Partnership Name:
(SEAL)
By:
(Signature of general partner)
Name (typed or printed):
Business Street Address (No POBox #'s):
Phone No,:
Fax No.:
A COrDoration
Corporation Name:-D/IiS (',C;fLtJC>QA-ho;J:I)JL-.,
I
State of Incorporation: ~ i ;v/v~~
(SEAL)
..--, -
I, Service, Limited Liability): :5~ rJ2---U I C.:2/
I
By:
(SignatUl e) i
N,m, (typed 0< p.;nted), S-fJANMoAJ ~ /IG/'-Juj
V; L-L :P (L'i-r, f {) 21.)1'
Title:
Attest
t/'
(CORPORA TE SEAL)
''"''
:? \
DoX
9
Yt s:..,0L(o - 0 d- ge,
PhoneNo: 7(-5- Lf7?- 0~7 8'
'7; -, - L.J 79- ~ .:J. C;<"""
Fax No: <-",.5 I u .../C/ 1'0.../
OOGO)4041590BIDFOP~\1 xl;
Rc.....iscd By Addendum No J
00410-10(R)
REVISED BID FOfU<i
DOCUMENT 00520
AGREEMENT FORM
THIS AGREEMENT is by and between City of New Hope, Minnesota, (hereinafter called Owner) and DMJ
Corporation (hereinafter called Contractor).
Owner and Contractor, in consideration ofthe mutual covenants hereinafter set forth, agree as follows:
ARTICLE 1 - WORK
1.01 Contractor shall complete all work as specified or indicated in the Contract Documents. The work is
generally described as follows: 2005 Street, Park and Utility Infrastructure Improvements for the City of New
Hope, Minnesota.
ARTICLE 2 - THE PROJECT
2.01 The Project for which the work under the Contract Documents may be the whole or only a part is
generally described as follows: 2005 Street, Park and Utility Infrastructure Improvements Project for the City
of New Hope, Minnesota, City Project No. 779.
ARTICLE 3 - ENGINEER
3.01 The Project has been designed by Bonestroo, Rosene, Anderlik & Associates, Inc., 2335 West
Highway 36, St. Paul, MN 55113 (Engineer), who is to act as Owner's representative, assume all duties and
responsibilities, and will have the rights and authority assigned to Engineer in the Contract Documents in
connection with the completion of the work in accordance with the Contract Documents.
ARTICLE 4 - CONTRACT TIMES
4.01 Time of the Essence
A. All time limits for Milestones, if any, Substantial Completion, and completion and readiness for
Final Payment as stated in the Contract Documents are of the essence of the Contract.
4.02 Datesfor Milestones, Substantial Completion, and Final Payment
A. Specific Completion Dates are not established for each Part at this time. The complexity of this
Project requires coordination between several parties. Completion for each Part that is awarded will be
discussed as the Project progresses and determined through the coordination with other contractors (parties
involved).
B. All of the work of the Project is anticipated to be completed and ready for Final Payment in
accordance with Paragraph 14.07 of the General Conditions on or before October 28,2005.
000034-04] 59-0
@ .2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
00520-1
AGREEMENT FORM
4.03 Liquidated Damage
A. Contractor and Owner recognize that time is of the essence of this Agreement and that Owner
will suffer financial loss if the work is not completed within the times specified in Paragraph 4.02 above, plus
any extensions thereof allowed in accordance with Article 12 of the General Conditions. The parties also
recognize the delays, expense, and difficulties involved in proving in a legal or arbitration proceeding the actual
loss suffered by Owner if the work is not completed on time. Accordingly, instead of requiring any such proof,
Owner and Contractor agree that as Liquidated Damages for delay (but not as a penalty), Contractor shall pay
Owner $200 for each day that expires after the time specified in paragraph 4.02 for Milestones and Substantial
Completion until the work is Substantially Complete. After Substantial Completion, if Contractor shall neglect,
refuse, or fail to complete the remaining work within the Contract Time or any proper extension thereof granted
by Owner, Contractor shall pay Owner $200 for each day that expires after the time specified in Paragraph 4.02
for completion and readiness for Final Payment until the work is completed and ready for Final Payment.
ARTICLE 5 - CONTRACT PRICE
5.01 Owner shall pay Contractor for completion of the work in accordance with the Contract Documents an
amount in current funds as follows: For all work at the prices stated in Contractor's Bid, attached hereto as an
exhibit for an Original Contract Amount of Three Hundred Eighty-Four Thousand Eighty-Four Dollars and
Twenty-Five Cents ($384,084.25) for the Total Base Bid and Alternate No.2.
ARTICLE 6 - PAYMENT PROCEDURES
6.01 Submittal and Processing of Payments
A. Contractor shall submit Applications for Payment in accordance with Article 14 of the General
Conditions. Applications for Payment will be processed by Engineer as provided in the General Conditions.
6.02 Progress Payments; Retainage
A. Owner shall make progress payments on account of the Contract Price on the basis of
Contractor's Applications for Payment, monthly during performance of the work as provided in Paragraphs
6.02.A1 and 6.02.A2 below. All such payments will be measured by the Schedule of Values established in
Paragraph 2.07.A of the General Conditions (and in the case of Bid Unit Price work based on the number of
units completed) or, in the event there is no Schedule of Values, as provided in the General Requirements:
1. Prior to Substantial Completion, progress payments will be made in an amount equal to the
percentage indicated below, but in each case, less the aggregate of payments previously made and less
such amounts as Engineer may determine or Owner may withhold, including but not limited to liquidated
damages, in accordance with Paragraph 14.02 of the General Conditions:
a. 95 percent of work completed (with the balance being retainage).
b. 95 percent of cost of materials and equipment not incorporated in the work (with the
balance being retainage).
000034-04159-0
@.2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
00520-2
AGREEMENT FORM
2. Upon Substantial Completion, Owner shall pay an amount sufficient to increase total payments
to Contractor to 100 percent of the work completed, less such amounts as Engineer shall determine in
accordance with Paragraph 14.02.B.5 of the General Conditions and less 100 percent of Engineer's
estimate of the value of work to be completed or corrected as shown on the tentative list of items to be
completed or corrected attached to the certificate of Substantial Completion.
6.03 Final Payment
A. Upon Final Completion and acceptance of the work, in accordance with Paragraph 14.07 of the
General Conditions, Owner shall pay the remainder of the Contract Price as recommended by Engineer as
provided in said Paragraph 14.07.
ARTICLE 7 - INTEREST
7.01 All moneys not paid when due, as provided in Article 14 of the General Conditions, shall bear interest
at the maximum rate allowed by law at the place of the Project.
ARTICLE 8 - CONTRACTOR'S REPRESENTATIONS
8.01 In order to induce Owner to enter into this Agreement, Contractor makes the following
representations:
A. Contractor has examined and carefully studied the Contract Documents and the other related
data identified in the Bidding Documents.
B. Contractor has visited the Project Site and become familiar with and is satisfied as to the
general, local, and Project Site conditions that may affect cost, progress, and performance of the work.
C. Contractor is familiar with and is satisfied as to all federal, state, and local Laws and
Regulations that may affect cost, progress, and performance of the work.
D. Contractor has carefully studied all: (1) reports of explorations and tests of subsurface
conditions at or contiguous to the Project Site and all drawings of physical conditions in or relating to existing
surface or subsurface structures at or contiguous to the Project Site (except Underground Facilities) which have
been identified in the Supplementary Conditions as provided in Paragraph 4.02 of the General Conditions and
(2) reports and drawings of a Hazardous Environmental Condition, if any, at the Project Site which has been
identified in the Supplementary Conditions as provided in Paragraph 4.06 of the General Conditions.
E. Contractor has obtained and carefully studied (or assumes responsibility for having done so) all
additional or supplementary examinations, investigations, explorations, tests, studies, and data concerning
conditions (surface, subsurface, and Underground Facilities) at or contiguous to the Project Site which may
affect cost, progress, or performance of the work, or which relate to any aspect of the means, methods,
techniques, sequences, and procedures of construction to be employed by Contractor, including applying the
specific means, methods, techniques, sequences, and procedures of construction, if any, expressly required by
the Contract Documents to be employed by Contractor and safety precautions and programs incident thereto.
000034-04159-0
@.2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
00520-3
AGREEMENT FORM
F. Contractor does not consider that any further examinations, investigations, explorations, tests,
studies, or data are necessary for the performance of the work at the Contract Price, within the Contract Times,
and in accordance with the other terms and conditions of the Contract Documents.
G. Contractor is aware of the general nature of work to be performed by Owner and others at the
Project Site that relates to the work as indicated in the Contract Documents.
H. Contractor has correlated the information known to Contractor, information and observations
obtained from visits to the Project Site, reports and drawings identified in the Contract Documents, and all
additional examinations, investigations, explorations, tests, studies, and data with the Contract Documents.
I. Contractor has given Engineer written notice of all conflicts, errors, ambiguities, or
discrepancies that Contractor has discovered in the Contract Documents, and the written resolution thereof by
Engineer is acceptable to Contractor.
J. The Contract Documents are generally sufficient to indicate and convey understanding of all
terms and conditions for performance and furnishing of the work.
ARTICLE 9 - CONTRACT DOCUMENTS
9.01 Contents
A. The Contract Documents consist of the following:
1. This Agreement.
2. Performance Bond, Payment Bond, and other Bonds.
3. General Conditions.
4. Supplementary Conditions.
5. Specifications.
6. Drawings bearing the following general title: 2005 Street, Park and Utility
Infrastructure Improvements.
7. Addenda (Number One, inclusive).
8. Exhibits to this Agreement (enumerated as follows):
a. Contractor's Bid Form.
b. Documentation submitted by Contractor prior to Notice of Award.
9. The following which may be delivered or issued on or after the Effective Date of the
Agreement, and are not attached hereto:
a. Notice to Proceed.
000034-04159-0
@.2005 Bonestroo, Rosene,
Anderlik & Associates, [nc,
00520-4
AGREEMENT FORM
b. Work Change Directives.
c. Change Order(s).
B. The documents listed in Paragraph 9.01.A are attached to this Agreement (except as expressly
noted otherwise above).
C. There are no Contract Documents other than those listed above in this Article 9.
D. The Contract Documents may only be amended, modified, or supplemented as provided in
Paragraph 3.04 of the General Conditions.
ARTICLEIO-NllSCELLANEOUS
10.01 Terms
A. Terms used in this Agreement will have the meanings stated in the General Conditions and the
Supplementary Conditions.
10.02 Assignment of Contract
A. No assignment by a party hereto of any rights under or interests in the Contract will be binding
on another party hereto without the written consent of the party sought to be bound; and, specifically but
without limitation, moneys that may become due and moneys that are due may not be assigned without such
consent (except to the extent that the effect of this restriction may be limited by law), and unless specifically
stated to the contrary in any written consent to an assignment, no assignment will release or discharge the
assignor from any duty or responsibility under the Contract Documents.
10.03 Successors and Assigns
A. Owner and Contractor each binds itself, its partners, successors, assigns, and legal
representatives to the other party hereto, its partners, successors, assigns, and legal representatives in respect to
all covenants, agreements, and obligations contained in the Contract Documents.
10.04 Severability
A. Any provision or part of the Contract Documents held to be void or unenforceable under any
Law or Regulation shall be deemed stricken and all remaining provisions shall continue to be valid and binding
upon Owner and Contractor, who agree that the Contract Documents shall be reformed to replace such stricken
provision or part thereof with a valid and enforceable provision that comes as close as possible to expressing
the intention of the stricken provision.
000034-04159-0
@.2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
00520-5
AGREEMENT FORM
IN WITNESS WHEREOF, Owner and Contractor have signed this Agreement in duplicate. One (1)
counterpart each has been delivered to Owner and Contractor. All portions of the Contract Documents have
been signed or identified by Owner and Contractor or on their behalf.
This Agreement will be effective on fJ1ttA/r 9
{l
, 2005 (which is the Effective Date ofthe Agreement).
Owner:
Contractor:
Attest
y~ \()
/Z~ c.-~h/VL
-
Address for giving notices:
f'IT\/ CL'!:Qv
V~ I ~. . a-li;\
CITY OF NE\N HOPE
M4J1 XYLON AVENUE NORTH
NEW HOPE, 55428
Address for giving notices:
f) botf/Cd 9 L7
~!Ja f]~( /)1 tJ -55"3 {o <- (J ~ 7
License No.
(Where applicable)
Designated Representative:
Designated Representative:
Phone: /) &: :;5 5' 3 I - 6-- / / 1
Phone:
2; hCLf/lrl{V-\
tI P.
.
/)0 P)t)x~qC7
1 JCWl1C( : lLL/iU5S3YO -cG-q'"i
.1 f.v 3 cf7 ';( 61 0 1-
i(IJ ~ L/7 fj d-3~
r!; loyav'!
Name:
Name:
Title:
Title:
Address:
Address:
Facsimile: 7 (? 3 - 3/ - 5- I ;S G
Facsimile:
END OF DOCUMENT
000034-04159-0
@.2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
00520-6
AGREEMENT FORM
PERFORMANCE BOND
Any singular reference to Contractor, Surety, Owner, or other party shall be considered plural where applicable.
CONTRACTOR (Name and Address):
SURETY (Name and Address of Principal Place of Business):
OWNER (Name and Address):
CONTRACT
Date:
Amount:
Description (Name and Location):
BOND
Bond Number:
Date (Not earlier than Contract Date):
Amount:
Modifications to this Bond Form:
Surety and Contractor, intending to be legally bound hereby, subject to the terms printed on the reverse side hereof, do each cause
this Performance Bond to be duly executed on its behalf by its authorized officer, agent, or representative.
CONTRACTOR AS PRINCIPAL
Company:
SURETY
Signature:
Name and Title:
(Seal)
(Seal)
Surety's Name and Corporate Seal
By:
Signature and Title
(Attach Power of Attorney)
(Space is provided below for signatures of additional
parties, if required.)
Attest:
Signature and Title
CONTRACTOR AS PRINCIPAL
Company:
SURETY
Signature:
Name and Title:
(Seal)
( Seal)
Surety's Name and Corporate Seal
By:
Signature and Title
(Attach Power of Attorney)
Attest:
Signature and Title:
EJCDC No. C-610 (2002 Edition)
Originally prepared through the joint efforts of the Surety Association of America, Engineers Joint Contract Documents Committee, the Associated General
Contractors of America, and the American Institute of Architects.
00610-1
1. Contractor and Surety, jointly and severally, bind themselves, their heirs,
executors, administrators, successors, and assigns to Owner for the performance of
the Contract, which is incorporated herein by reference.
2. If Contractor performs the Contract, Surety and Contractor have no obligation
under this Bond, except to participate in conferences as provided in Paragraph 3.1.
3. If there is no Owner Default, Surety's obligation under this Bond shall arise
after:
3.1. Owner has notified Contractor and Surety, at the addresses described in
Paragraph 10 below, that Owner is considering declaring a Contractor
Default and has requested and anempted to arrange a conference with
Contractor and Surety to be held not later than 15 days after receipt of
such notice to discuss methods of performing the Contract. If Owner,
Contractor and Surety agree, Contractor shall be allowed a reasonable
time to perform the Contract, but such an agreement shall not waive
Owner's right, if any, subsequently to declare a Contractor Default; and
3.2. Owner has declared a Contractor Default and formally terminated
Contractor's right to complete the Contract. Such Contractor Default
shall not be declared earlier than 20 days after Contractor and Surety
have received notice as provided in Paragraph 3.1; and
3.3. Owner has agreed to pay the Balance of the Contract Price to:
I. Surety in accordance with the terms of the Contract;
2. Another contractor selected pursuant to Paragraph 4.3 to perform the
Contract.
4. \Vhen Owner has satisfied the conditions of Paragraph 3, Surety shall promptly
and at Surety's expense take one of the following actions:
4.1. Arrange for Contractor, with consent of Owner, to perform and
complete the Contract; or
4.2. Undertake to perform and complete the Contract itself, through its
agents or through independent contractors; or
4.3. Obtain bids or negotiated proposals from qualified contractors acceptable
to Owner for a contract for performance and completion of the Contract,
arrange for a contract to be prepared for execution by Owner and
Contractor selected with Owner's concurrence, to be secured with
performance and payment bonds executed by a qualified surety
equivalent to the bonds issued on the Contract, and pay to Owner the
amount of damages as described in Paragraph 6 in excess of the Balance
of the Contract Price incurred by Owner resulting from Contractor
Default; or
4.4. Waive its right to perform and complete, arrange for completion, or
obtain a new contractor and with reasonable promptness under the
circumstances:
1. After investigation, determine the amount for which it may be liable
to Owner and, as soon as practicable after the amount is determined,
tender payment therefor to Owner; or
2. Deny liability in whole or in part and notify Owner citing reasons
therefor.
5. If Surety does not proceed as provided in Paragraph 4 with reasonable
promptness, Surety shall be deemed to be in default on this Bond 15 days after
receipt of an additional wrinen notice from Owner to Surety demanding that Surety
perform its obligations under this Bond, and Owner shall be entitled to enforce any
remedy available to Owner. If Surety proceeds as provided in Paragraph 4.4, and
Owner refuses the payment tendered or Surety has denied liability, in whole or in
part, without further notice Owner shall be entitled to enforce any remedy available
to Owner.
6. After Owner has terminated Contractor's right to complete the Contract, and if
Surety elects to act under Paragraph 4.1,4.2, or 4.3 above, then the responsibilities
of Surety to Owner shall not be greater than those of Contractor under the Contract,
and the responsibilities of Owner to Surety shall not be greater than those of Owner
under the Contract. To a limit of the amount of this Bond, but subject to
commitment by Owner of the Balance of the Contract Price to mitigation of costs
and damages on the Contract, Surety is obligated without duplication for:
6.1. The responsibilities of Contractor for correction of defective Work and
completion of the Contract;
6.2. Additional legal, design professional, and delay costs resulting from
Contractor's Default, and resulting from the actions or failure to act of
Surety under Paragraph 4; and
6.3. Liquidated damages, or if no liquidated damages are specified in the
Contract, actual damages caused by delayed performance or non-
performance of Contractor.
7. Surety shall not be liable to Owner or others for obligations of Contractor that
are unrelated to the Contract, and the Balance of the Contract Price shall not be
reduced or set off on account of any such unrelated obligations. No right of action
shall accrue on this Bond to any person or entity other than Owner or its heirs,
executors, administrators, or successors.
8. Surety hereby waives notice of any change, including changes of time, to
Contract or to related subcontracts, purchase orders, and other obligations.
9. Any proceeding, legal or equitable, under this Bond may be instituted in any
court of competent jurisdiction in the location in which the Work or part of the
Work is located and shall be instituted within two years after Contractor Default or
within rwo years after Contractor ceased working or within two years after Surety
refuses or fails to perform its obligations under this Bond, whichever occurs first. If
the provisions of this paragraph are void or prohibited by law, the minimum period
of limitation available to sureties as a defense in the jurisdiction of the suit shall be
applicable.
10. Notice to Surety, Owner, or Contractor shall be mailed or delivered to the
address shown on the signature page.
11. When this Bond has been furnished to comply with a statutoty requirement in
the location where the Contract was to be performed, any provision in this Bond
conflicting with said statutory requirement shall be deemed deleted herefrom and
provisions conforming to such statutory requirement shall be deemed incorporated
herein. The intent is that this Bond shall be construed as a statutory bond and not as
a common law bond.
12. Definitions.
12.1 Balance of the Contract Price: The total amount payable by Owner to
Contractor under the Contract after all proper adjustments have been
made, including allowance to Contractor of any amounts received or to
be received by Owner in settlement of insurance or other Claims for
damages to which Contractor is entitled, reduced by all valid and proper
payments made to or on behalf of Contractor under the Contract.
12.2. Contract: The agreement berween Owner and Contractor identified on
the signature page, including all Contract Documents and changes
thereto.
12.3. Contractor Default: Failure of Contractor, which has neither been
remedied nor waived, to perform or otherwise to comply with the terms
of the Contract.
12.4. Owner Default: Failure of Owner, which has neither been remedied nor
waived, to pay Contractor as required by the Contract or to perform and
complete or comply with the other terms thereof.
FOR INFORMATION ONLY - Name, Address and Telephone
Surety Agency or Broker
Owner's Representative (engineer or other party)
00610-2
PAYMENT BOND
Any singular reference to Contractor, Surety, Owner, or other party shall be considered plural where applicable.
CONTRACTOR (Name and Address):
SURETY (Name and Address of Principal Place of Business):
OWNER (Name and Address):
CONTRACT
Date:
Amount:
Description (Name and Location):
BOND
Bond Number:
Date (Not earlier than Contract Date):
Amount:
Modifications to this Bond Form:
Surety and Contractor, intending to be legally bound hereby, subject to the terms printed on the reverse side hereof, do each cause
this Payment Bond to be duly executed on its behalf by its authorized officer, agent, or representative.
CONTRACTOR AS PRINCIPAL
Company:
SURETY
Signature:
Name and Title:
(Seal)
(Seal)
Surety's Name and Corporate Seal
By:
Signature and Title
(Attach Power of Attorney)
(Space is provided below for signatures of additional
parties, if required.)
Attest:
Signature and Title
CONTRACTOR AS PRINCIPAL
Company:
SURETY
Signature:
Name and Title:
(Seal)
(Seal)
Surety's Name and Corporate Seal
By:
Signature and Title
(Attach Power of Attorney)
Attest:
Signature and Title:
EJCDC No. C-615 (2002 Edition)
Originally prepared through the joint efforts of the Surety Association of America, Engineers Joint Contract Documents Committee, the Associated
General Contractors of America, the American Institute of Architects, the American Subcontractors Association, and the Associated Specialty Contractors.
00615-1
1. Contractor and Surety, jointly and severally, bind themselves, their heirs,
executors, administrators, successors, and assigns to Owner to pay for labor,
materials, and equipment furnished by Oaimants for use in the performance of
the Contract, which is incorporated herein by reference.
2. With respect to Owner, this obligation shall be null and void if Contractor:
2.1. Promptly makes payment, directly or indirectly, for all sums due
Claimants, and
2.2. Defends, indemnifies, and holds harmless Owner from all claims,
demands, liens, or suits alleging non-payment by Contractor by any
person or entity who furnished labor, materials, or equipment for use
in the performance of the Contract, provided Owner has promptly
notified Contractor and Surety (at the addresses described in
Paragraph 12) of any claims, demands, liens, or suits and tendered
defense of such claims, demands, liens, or suits to Contractor and
Surety, and provided there is no Owner Default.
3. With respect to Claimants, this obligation shall be null and void if
Contractor promptly makes payment, directly or indirectly, for all sums due.
4. Surety shall have no obligation to Claimants under this Bond until:
4.1. Claimants who are employed by or have a direct contract with
Contractor have given notice to Surety (at the addresses described in
Paragraph 12) and sent a copy, or notice thereof, to Owner, stating
that a claim is being made under this Bond and, with substantial
accuracy, the amount of the claim.
4.2. Claimants who do not have a direct contract with Contractor:
1. Have furnished written notice to Contractor and sent a copy, or
notice thereof, to Owner, within 90 days after having last
performed labor or last furnished materials or equipment included
in the claim stating, with substantial accuracy, the amount of the
claim and the name of the party to whom the materials or
equipment were furnished or supplied, or for whom the labor was
done or performed; and
2. Have either received a rejection in whole or in part from
Contractor, or not received within 30 days of furnishing the above
notice any communication from Contractor by which Contractor
had indicated the claim will be paid directly or indirectly; and
3. Not having been paid within the above 30 days, have sent a
written notice to Surety and sent a copy, or notice thereof, to
Owner, stating that a claim is being made under this Bond and
enclosing a copy of the previous written notice furnished to
Contractor.
:>. If a notice by a Claimant required by Paragraph 4 is provided by Owner to
Contractor or to Surety, that is sufficient compliance.
6. When a Claimant has satisfied the conditions of Paragraph 4, the Surety
shall promptly and at Surety's expense take the following actions:
6.1. Send an answer to that Claimant, with a copy to Owner, within 45
days after receipt of the claim, stating the amounts that are undisputed
and the basis for challenging any amounts that are disputed.
6.2. Payor arrange for payment of any undisputed amounts.
7. Surety's total obligation shall not exceed the amount of this Bond, and the
amount of this Bond shall be credited for any payments made in good faith by
Surety .
8. Amounts owed by Owner to Contractor under the Contract shall be used for
the performance of the Contract and to satisfy claims, if any, under any
performance bond. By Contractor furnishing and Owner accepting this Bond,
they agree that all funds earned by Contractor in the performance of the
Contract are dedicated to satisfy obligations of Contractor and Surety under
this Bond, subject to Owner's priority to use the funds for the completion of
the Work.
9. Surety shall not be liable to Owner, Claimants, or others for obligations of
Contractor that are unrelated to the Contract. Owner shall not be liable for
payment of any costs or expenses of any Claimant under this Bond, and shall
have under this Bond no obligations to make payments to, give notices on
behalf of, or otherwise have obligations to Claimants under this Bond.
10. Surety hereby waives notice of any change, including changes of time, to
the Contract or to related Subcontracts, purchase orders and other obligations.
11. No suit or action shall be commenced by a Oaimant under this Bond other
than in a court of competent jurisdiction in the location in which the Work or
part of the Work is located or after the expiration of one year from the date (1)
on which the Claimant gave the notice required by Paragraph 4.1 or Paragraph
4.2.3, or (2) on which the last labor or service was performed by anyone or
the last materials or equipment were furnished by anyone under the
ConstrUction Contract, whichever of (1) or (2) first occurs. If the provisions
of this paragraph are void or prohibited by law, the minimum period of
limitation available to sureties as a defense in the jurisdiction of the suit shall
be applicable.
12. Notice to Surety, Owner, or Contractor shall be mailed or delivered to the
addresses shown on the signature page. Actual receipt of notice by Surety,
Owner, or Contractor, however accomplished, shall be sufficient compliance
as of the date received at the address shown on the signature page.
13. When this Bond has been furnished to comply with a statutory requirement
in the location where the Contract was to be performed, any provision in this
Bond conflicting with said statutory requirement shall be deemed deleted
here from and provisions conforming to such statutory requirement shall be
deemed incorporated herein. The intent is that this Bond shall be construed as
a statutory Bond and not as a common law bond.
14. Upon request of any person or entity appearing to be a potential
beneficiary of this Bond, Contractor shall promptly furnish a copy of this Bond
or shall permit a copy to be made.
15. DEFINITIONS
15.1. Claimant: An individual or entity having a direct contract with
Contractor, or with a first-tier subcontractor of Contractor, to furnish
labor, materials, or equipment for use in the performance of the
Contract. The intent of this Bond shall be to include without
limitation in the terms "labor, materials or equipment" that part of
water, gas, power, light, heat, oil, gasoline, telephone service, or
rental equipment used in the Contract, architectural and engineering
services required for performance of the Work of Contractor and
Contractor's Subcontractors, and all other items for which a
mechanic's lien may be asserted in the jurisdiction where the labor,
materials, or equipment were furnished.
15.2. Contract: The agreement between Owner and Contractor identified on
the signature page, including all Contract Documents and changes
thereto.
15.3. Owner Default: Failure of Owner, which has neither been remedied
nor waived, to pay Contractor as required by the Contract or to
perform and complete or comply with the other terms thereof.
FOR lNFORl\'lATION ONLY - Name, Address and Telephone
Surety Agency or Broker:
Owner's Representative (engineer or other party):
00615-2
DOCUMENT 00800
SUPPLEMENTARY CONDITIONS
These Supplementary Conditions amend or supplement the Standard General Conditions of the
Construction Contract (No. C-700, 2002 Edition) and other provisions of the Contract Documents
as indicated below. All provisions, which are not so amended or supplemented, remain in full
force and effect.
The terms used in these Supplementary Conditions have the meanings stated in the General
Conditions. Additional terms used in these Supplementary Conditions have the meanings stated
below, which are applicable to both the singular and plural thereof.
ARTICLE 1 - DEFIN1TIONS AND TERMINOLOGY
SC-1.02
Add the following new paragraph immediately after Paragraph 1.02.F:
G. The Specifications are written in imperative mood and streamlined form. This
imperative language is directed to the Contractor, unless specifically noted otherwise. The words
"shall be" are included by inference where a colon (:) is used within sentences or phrases.
ARTICLE 2 - PRELIMINARY MATTERS
SC 2.02.A Amend the first sentence of Paragraph 2.02.A by striking out the word "ten" and
inserting the word "five."
ARTICLE 4 - AVAILABILITY OF LANDS: SUBSURFACE AND PHYSICAL CONDITIONS,
REFERENCE POINTS
SC-4.02
Delete 4.02.A and 4.02.B in their entirety and insert the following:
A. No reports of explorations or tests of subsurface conditions at or contiguous to the
Project Site are known to the Owner or Engineer.
ARTICLE 5 - BONDS AND INSURANCE
SC-5.01
Add the following new paragraph immediately after Paragraph 5.01.C:
D. Separate Performance and Payment Bonds should be submitted utilizing EJCDC
Form C-610 and C-615 (2002 Editions), or a similar bond form if approved by Owner.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
00800-1
SUPPLEMENTARY CONDITIONS
SC-5.03.B
Delete Paragraph 5.03.B in its entirety and insert the following:
B. Failure of Owner to demand such certificates or other evidence of full compliance
with these insurance requirements or failure of Owner to identify a deficiency from evidence
provided, shall not be construed as a waiver of Contractor's obligation to maintain such insurance.
C. By requiring such insurance and insurance limits herein, Owner does not represent
that coverage and limits will necessarily be adequate to protect Contractor and such coverage and
limits shall not be deemed as a limitation on Contractor's liability under the indemnities granted to
Owner in the Contract Documents.
SC-5.04
Add the following new paragraph immediately after Paragraph 5.04.B:
C. The limits of liability for the insurance required by Paragraph 5.04 of the General
Conditions shall provide coverage for not less than the following amounts or greater where
required by Laws and Regulations:
1. Worker's Compensation Insurance
Coverage A - Statutory
Coverage B - $500,000
$500,000
$500,000
Each Accident
Disease - Policy Limit
Disease - Each Employee
2. Commercial General Liability
$1,000,000 General Aggregate
$1,000,000 Products/Completed Operations Aggregate
$1,000,000 Each Occurrence
$1,000,000 Personal Injury
3. Comprehensive Automobile Liability
$1,000,000 Combined Single Limit - Bodily injury and property
damage. All owned, non-owned, and hired vehicles.
4. Umbrella Excess Liability
$1,000,000
$1,000,000
Each Occurrence
Aggregate
Umbrella excess liability shall be a combined single limit which shall provide
excess liability insurance over Commercial General Liability, Comprehensive
Automobile Liability, and Employers Liability.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
00800-2
SUPPLEMENTARY CONDITIONS
5. The following persons or entities shall be included as additional insured on the
Commercial Liability, Comprehensive Automobile Liability, and Umbrella Excess
Liability. Tills coverage shall be primary and noncontributory:
Owner.
Engineer.
SC-5.06.A
Amend the fIrst sentence of Paragraph 5.06.A to read:
A. Contractor shall purchase and maintain during the entire construction period, a
Builders Risk Property Insurance Policy in the amount of the full replacement cost of the entire
work at the Project Site. The insurance policy shall comply with the provisions of Paragraph
5.06.A1 through 5.06.A7. A minimum deductible of $1,000 each claim shall apply to tills
insurance and the risk of loss of the applicable deductible shall be born by Contractor,
subcontractor, or others suffering such loss. In addition, the provisions of Paragraphs 5.07, 5.09,
and 5.10 shall apply with the exception that Contractor shall act as fIduciary for the insureds, as
their interest may appear and adjust the loss with the insurance company.
SC-5.06.A
Add the following new item immediately after Item 5.06.A7:
8. The Builder's Risk Insurance required herein shall apply to projects
involving construction of structures and buildings only. The requirements of this Section
shall be waived on projects involving only underground utilities, grading, street
improvements, and similar construction work but any damage or loss to property shall be
at the sole responsibility of Contractor until fInal acceptance of the work.
ARTICLE 6 - CONTRACTOR'S RESPONSIBILITIES
SC-6.08.A Amend the first sentence of Paragraph 6.08.A by replacing the words "the
Supplementary Conditions" with the words "Division 1 - General Requirements."
SC-6.19.A
Delete the words "representation of' in the second sentence.
ARTICLE 10 - CHANGES IN THE WORK; CLAIMS
SC-10.05.B Amend the first sentence of Paragraph 10.05.B by replacing the words "30 days"
with the words "10 days." Amend the third sentence of Paragraph 10.05.B by replacing the words
"60 days" with the words "30 days."
ARTICLE 13 - TESTS AND INSPECTIONS; CORRECTION, REMOVAL OR ACCEPTANCE
OF DEFECTIVE WORK
SC-13.07.A Amend the fIrst sentence of Paragraph 13.07.A by striking out the words "one
year" and inserting the word "two years."
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
00800-3
SUPPLEMENTARY CONDITIONS
ARTICLE 14-PAYMENTS TO CONTRACTOR AND COJvfPLETION
SC-14.02.B5 Add the following new item immediately after Item 14.02.B5d:
e. Contractor's failure to make acceptable submittals in accordance with the
accepted schedules.
ARTICLE 16 - DISPUTE RESOLUTION
SC-16.01
Delete Paragraph 16.01.C in its entirety and insert the following in its place:
C. If the claim is not resolved by mediation, Engineer's action under Paragraph 10.05.C or a
denial pursuant to Paragraphs 10.05.C3 or 10.05.D shall become final and binding 30 days after
termination of the mediation, unless within that time period Owner or Contractor:
1. elects in writing to demand arbitration of the claim, pursuant to Paragraph SC-16.02,
or
2. agrees with the other party to submit the claim to another dispute resolution process.
SC-16.01.D Add the following new paragraph immediately after Paragraph SC-16.01.C:
D. Notwithstanding any applicable statue of limitations, a party giving notice under
Paragraph SC-16.01.Cl shall commence an action on the claim within 1 year of giving such
notice, and within the period of any applicable statute of limitation or repose. Failure to do so
shall result in the claim being time-barred and Engineer's action or denial shall become final and
binding.
SC-16.02 Add the following new paragraph immediately after Paragraph 16.01:
SC-16.02 Arbitration
A. All claims or counterclaims, disputes, or other matters in question between Owner
and Contractor arising out of or relating to the Contract Documents or the breach thereof (except
for claims which have been waived by the making or acceptance of Final Payment as provided by
Paragraph 14.09), including but not limited to those not resolved under the provisions of
Paragraphs SC-16.01.A and 16.01.B, but not including any claim in excess of $100,000, will be
decided by arbitration in accordance with the Construction Industry Dispute Resolutions
Procedures of the American Arbitration Association then in effect, subject to the conditions and
limitations of this Paragraph SC-16.02. This agreement to arbitrate and any other agreement or
consent to arbitrate entered into will be specifically enforceable under the prevailing law of any
court having jurisdiction.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
00800-4
SUPPLEMENTARY CONDITIONS
B. The demand for arbitration will be filed in writing with the other party to the
Contract and with the selected arbitrator or arbitration provider and a copy will be sent to Engineer
for information. The demand for arbitration will be made within the 30 day period specified in
Paragraph SC-16.01.C, and in all other cases within a reasonable time after the claim or
counterclaim, dispute, or other matter in question has arisen, and in no event shall any such
demand be made after the date when institution of legal or equitable proceedings based on such
claim or other dispute or matter in question would be barred by the- applicable statue of
limitations.
C. No arbitration arising out of or relating to the Contract Documents shall include by
consolidation, joinder, or in any other manner any other individual or entity (including Engineer,
and Engineer's consultants and the officers, directors, partners, agents, employees, or consultants
of any of them) who is not a party to this Contract, unless:
1. in inclusions of such other individual or entity is necessary if complete relief is
to be afforded among those who are already parties to the arbitration; and
2. such other individual or entity is substantially involved in a question of law or
fact which is common to those who are already parties to the arbitration and which will
arise in such proceedings.
D. The award rendered by the arbitrator(s) shall be consistent with the agreement of the
parties, in writing, and include: (i) a concise breakdown of the award; (ii) a written explanation of
the award specifically citing the Contract Documents provisions deemed applicable and relied on
in making the award.
E. The award will be fina1. Judgment may be entered upon it in any court having
jurisdiction thereof, and it will not be subject to modification or appeal, subject to provisions of
the Controlling Law relating to vacating or modifying an arbitral award.
F. The fees and expenses of the arbitrators and any arbitration service shall be shared
equally by Owner and Contractor.
END OF DOCUMENT
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
00800-5
SUPPLEMENTARY CONDITIONS
Performance Bond
Bond No. 54-152824
Any singular reference to Contractor, Surety, Owner or other party shall be considered plural where applicable,
CONTRACTOR (Name and Address):
DMJ Corporation
2392 Pioneer Trail
Hamel, MN 55340-0299
OWNER (Name and Address):
City of New Hope
City Hall
New Hope, MN
CONTRACT
Date: May 12, 2005
Amount: $384,084.25
Description (Name and Location): 2005 Street, Park and Utility Infrastructure Improvements Project
New Hope, Minnesota
SURETY (Name and Address of Principal Place of Business):
United Fire and Casualty Company
P. O. Box 73909
Cedar Rapids, IA 52407
BOND
Date (Not earlier than Contract Date): May 12,2005
Amount: $384,084.25
Modifications to this Bond Form: Noue
Surety and Contractor, intending to be legally bound hereby, subject to the terms printed on the reverse side hereof, do each cause this
Performance Bond to be duly executed on its behalf by its authorized officer, agent or representative.
CONTRACTOR AS PRINCIPAL
Company: (No Seal)
DMJ Corporation
Signature: // /
Name and T~ j, tL-r I ~/L/7, /?/U!...$/'dCl1-f:-
SURETY
Company: (Corp. Seal)
United ~.an casnal~Comp.ny
Signa~~~~~~
./ ././
Name Title: Jack Cedarleaf II, Att~rn9"'ln-fact
(A ch Power of Attorney) V
(8 pace is provided below for signatures of additional parties, if required.)
CONTRACTOR AS PRINCIPAL
Company:
(Corp. Seal)
SURETY
Company:
(Corp. Seal)
Signature:
Name and Title:
Signature:
Name and Title:
EJCDC No. 19l0-28-A (2002 Edition)
Originally prepared through the joint efforts of the Surety Association of America, Engineers Joint Contract Documents Committee, the Associated General Contractors of
America, and the American Institute of Architects.
1. The CONTRACTOR and the Surety, jointly and severally, bind themselves, their
heirs, executors, administrators, successors and assigns to the Owner for the
performance of the Contract, which is incorporated herein by reference.
2. If the CONTRACTOR performs the Contract, the Surety and the
CONTRACTOR have no obligation under this Bond, except to participate in
conferences as provided in paragraph 3.1.
3. If there is no OWNER Default, the Surety's obligation under this Bond shall arise
after:
3.1. The OWNER has notified the CONTRACTOR and the Surety at the
addresses described in paragraph 10 below, that the OWNER is considering
declaring a CONTRACTOR Default and has requested and attempted to arrange a
conference with the CONTRACTOR and the Surety to be held not later than fifteen
days after receipt of such notice to discuss methods of performing the Contract If
the OWNER, the CONTRACTOR and the Surety agree, the CONTRACTOR shall
be allowed a reasonable time to perform the Contract, but such an agreement shall
not waive the OWNER's right, if any, subsequently to declare a CONTRACTOR
Default; and
3.2. The OWNER has declared a CONTRACTOR Default and formally
terminated the CONTRACTOR's right to complete the Contract. Such
CONTRACTOR Default shall not be declared earlier than twenty days after the
CONTRACTOR and the Surety have received notice as provided in paragraph 3.1;
and
3.3. The OWNER has agreed to pay the Balance of the Contract Price to:
3.3.1. The Surety in accordance with the terms of the Contract;
3.3.2. Another contractor selected pursuant to paragraph 4.3 to
perform the Contract.
4. When the OWNER has satisfied the conditions of paragraph 3, the Surety shall
promptly and at the Surety's expense take one of the following actions:
4.1. Arrange for the CONTRACTOR, with consent of the OWNER, to
perform and complete the Contract; or
4.2. Undertake to perform and complete the Contract itself, through its agents
or through independent contractors; or
4.3. Obtain bids or negotiated proposals from qualified contractors acceptable
to the OWNER for a contract for performance and completion of the Contract,
arrange for a contract to be prepared for execution by the OWNER and the
contractor selected with the OWNER's concurrence, to be secured with performance
and payment bonds executed by a qualified surety equivalent to the Bonds issued on
the Contract, and pay to the OWNER the amount of damages as described in
paragraph 6 in excess of the Balance of the Contract Price incurred by the OWNER
resulting from the CONTRACTOR Default; or
4.4. Waive its right to perform and complete, arrange for completion, or
obtain a new contractor and with reasonable promptness under the circumstances;
4.4.1. After investigation, determine the amount for which it may be
liable to the OWNER and, as soon as practicable after the amount is determined,
tender payment therefore to the OWNER; or
4.4.2. Deny liability in whole or in part and notify the OWNER
citing reasons therefor.
5. If the Surety does not proceed as provided in paragraph 4 with reasonable
promptoess, the Surety shall be deemed to be in default on this Bond fifteen days
after receipt of an additional written notice from the OWNER to the Surety
demanding that the Surety perform' its obligations under this Bond, and the OWNER
shall be entitled to enforce any remedy available to the OWNER. If the SURETY
proceeds as provided in paragraph 4.4, and the OWNER refuses the payment
tendered or the Surety has denied pliability, in whole or in part, without further
notice the OWNER shall be entitled to enforce any remedy available to the OWNER.
6. After the OWNER has terminated the CONTRACTOR's right to complete the
Contract, and if the Surety elects to act under paragraph 4.1, 4.2, or 4.3 above, then
the responsibilities of the Surety to the OWNER shall not be greater than those of the
CONTRACTOR under the Contract, and the responsibilities of the OWNER to the
Surety shall not be greater than those of the OWNER under the Contract. To a limit
of the amount of this Bond, but subject to commitment by the OWNER of the
Balance of the Contract Price to mitigation of costs and damages on the Contract, the
Surety is obligated without duplication for:
6.1. The responsibilities of the CONTRACTOR for correction of defective
Work and completion of the Contract;
6.2. Additional legal, design professional and delay costs resulting from the
CONTRACTOR's Default, and resulting from the actions or failure to act of the
Surety under paragraph 4; and
6.3. Liquidated damages, or if no liquidated damages are specified in the
Contract, actual damages caused by delayed performance or non-performance of the
CONTRACTOR.
7. The Surety shall not be liable to the OWNER or others for obligations of the
CONTRACTOR that are unrelated to the Contract, and the Balance of the Contract
Price shall not be reduced or set off on account of any such unrelated obligations.
No right of action shall accrue on this Bond to any person or entity other than the
OWNER or its heirs, executors, administrators, or successors.
8. The Surety hereby waives notice of any change, including changes of time, to the
Contract or to related subcontracts, purchase orders and other obligations.
9. Any proceeding, legal or equitable, under this Bond may be instituted in any court
of competent jurisdiction in the location in which the Work or part of the Work is
located and shall be instituted within two years after CONTRACTOR Default or
within two years after the CONTRACTOR ceased working or within two years after
the Surety refuses or fails to perform its obligations under this Bond, whichever
occurs first. If the provisions of this paragraph are void or prohibited by law, the
minimum period of limitation available to sureties as a defense in the jurisdiction of
the suit shall be applicable.
10. Notice to the Surety, the OWNER or the CONTRACTOR shall be mailed or
delivered to the address shown on the signature page.
11. When this Bond has been furnished to comply with a statutory or other legal
requirement in the location where the Contract was be performed, any provision in
this Bond conflicting with said statutory or legal requirement shall be deemed
deleted here from and provisions conforming to such statutory or other legal
requirement shall be deemed incorporated herein. The intent is that this Bond shall
be construed as a statutory bond and not as a common law bond.
12. Definitions.
12.1 Balance of the Contract Price: The total amount payable by the
OWNER to the CONTRACTOR under the Contract after all proper adjustments
have been made, including allowance to the CONTRACTOR of any amounts
received or to be received by the OWNER in settlement of insurance or other Claims
for damages to which the CONTRACTOR is entitled, reduced by all valid and
proper payments made to or on behalf of the CONTRACTOR under the Contract.
12.2. Contract: The agreement between the OWNER and the
CONTRACTOR identified on the signature page, including all Contract Documents
and changes thereto.
12.3. CONTRACTOR Default: Failure of the CONTRACTOR, which has
neither been remedied nor waived, to perform or otherwise to comply with the terms
of the Contract.
12.4. OWNER Default: Failure of the OWNER, which has neither been
remedied nor waived, to pay the CONTRACTOR as required by the Contract or to
perform and complete or comply with the other terms thereof.
Payment Bond
Bond No. 54-152824
Any singular reference to Contractor, Surety, Owner or other party shall be considered plural where applicable.
CONTRACTOR (Name and Address):
DMJ Corporation
2392 Pioneer Trail
Hamel, MN 55340-0299
OWNER (Name and Address):
City of New Hope
City Hall
New Hope, MN
CONTRACT
Date: May 12, 2005
Amount: $384,084.25
Description (Name and Location):
SURETY (Name and Address of Principal Place of Business):
United Fire and Casualty Company
P. O. Box 73909
Cedar Rapids, IA 52407
2005 Street, Park and Utility Infrastructure Improvements Project
New Hope, Minnesota
BOND
Date (Not earlier than Contract Date): May 12, 2005
Amount: $384,084.25
Modifications to this Bond Form: None
Surety and Contractor, intending to be legally bound hereby, subject to the terms printed on the reverse side hereof, do each cause this
Performance Bond to be duly executed on its behalf by its authorized officer, agent or representative.
CONTRACTOR AS PRINCIPAL
Company:
DMJ Corporation
(No Seal)
SURETY
Company: (Corp. Seal)
United Fire and Casualty Com~?ny d /
Signatu~~
N am~ it1e~ Jack CedarleafII, Attoro. e~~in;::fae{ -
(Apach Power of Attorney) Y
Signature'"
Name and Title:
'0-" ~i-/'71 !;:u,sl'de,tt-
(Space is provided below for signatures of additional parties, if required.)
CONTRACTOR AS PRINCIPAL
Company:
(Corp. Seal)
SURETY
Company:
(Corp. Seal)
Signature:
Name and Title:
Signature:
Name and Title:
EJCDC No. 19l0-28-B (2002 .Edition)
Originally prepared through the joint efforts of the Surety Association of America, Engineers Joint Contract Documents Committee, the Associated General Contractors of
America, the American Institute of Architects, the American Subcontractors Association, and the Associated Specialty Contractors.
1. The CONTRACTOR and the Surety, jointly and severally, bind themselves, their
heirs, executors, administrators, successors and assigns to the OWNER to pay for
labor, materials and equipment furnished for use in the performance of the Contract,
which is incorporated herein by reference.
2. With respect to the OWNER, this obligation shall be null and void if the
CONTRACTOR:
2.1. Promptly makes payment, directly or indirectly, for all sums due Claimants,
and
2.2. Defends, indemnifies and holds harmless the OWNER from all claims,
demands, liens or suits by any person or entity who furnished labor, materials or
equipment for use in the performance of the Contract, provided the OWNER has
promptly notified the CONTRACTOR and the Surety (at the addresses described in
paragraph 12) of any claims, demands, liens or suits and tendered defense of such
claims, demands, liens or suits to the CONTRACTOR and the Surety, and provided
there is no OWNER Default.
3. With respect to Claimants, this obligation shall be null and void if the
CONTRACTOR promptly makes payment, directly or indirectly, for all sums due.
4. The Surety shall have no obligation to Claimants under this Bond until:
4.1. Claimants who are employed by or have a direct contract with the
CONTRACTOR have given notice to the Surety (at the addresses described in
paragraph 12) and sent a copy, or notice thereof, to the OWNER, stating that a claim
is being made under this Bond and, with substantial accuracy, the amount of the
claim.
4.2. Claimants who do not have a direct contract with the CONTRACTOR:
1. Have furnished written notice to the CONTRACTOR and sent a
copy, or notice thereof, to the OWNER, within 90 days after having last performed
labor or last furnished materials or equipment included in the claim stating, with
substantial accuracy, the amount of the claim and the name of the party to whom the
materials were furnished or supplied or for whom the labor was done or performed;
and
2. Have either received a rejection in whole or in part from the
CONTRACTOR, or not received within the 30 days of furnishing the above notice
any communication from the CONTRACTOR by which the CONTRACTOR had
indicated the claim will be paid directly or indirectly; and
3. Not having been paid within the above 30 days, have sent a
written notice to the Surety and sent a copy, or notice thereof, to the OWNER,
stating that a claim is being made under this Bond and enclosing a copy of the
previous written notice fumished to the CONTRACTOR.
5. If a notice required by paragraph 4 is given by the OWNER to the
CONTRACTOR or to the Surety, that is sufficient compliance.
6. When the Claimant has satisfied the conditions of paragraph 4, the Surety shall
promptly and at the Surety's expense take the following actions:
6.1. Send an answer to the Claimant, with a copy to the OWNER, within 45
days after receipt of the claim, stating the amounts that are undisputed and the basis
for challenging any amounts that are disputed.
6.2. Payor arrange for payment of any undisputed amounts.
7. The Surety's total obligation shall not exceed the amount of this Bond, and the
amount of this Bond shall be credited for any payments made in good faith by the
Surety.
8. Amounts owed by the OWNER to the CONTRACTOR under the Contract shall
be used for the performance of the Contract and to satisfY claims, if any, under any
Performance Bond. By the CONTRACTOR furnishing and the OWNER accepting
this Bond, they agree that all funds eamed by the CONTRACTOR in the
performance of the Contract are dedicated to satisfY obligations of the
CONTRACTOR and the Surety under this Bond, subject to the OWNER's priority to
use the funds for the completion of the Work.
9. The Surety shall not be liable to the OWNER, Claimants or others for obligations
of the CONTRACTOR that are unrelated to the Contract. The OWNER shall not be
liable for payment of any costs or expenses of any Claimant under this Bond, and
shall have under this Bond no obligations to make payments to, give notices on
behalf of, or otherwise have obligations to Claimants under this Bond.
10. The Surety hereby waives notice of any change, including changes of time, to
the Contract or to related Subcontracts, purchase orders and other obligations.
II. No suit or action shall be commenced by a Claimant under this Bond other than
in a court of competent jurisdiction in the location in which the Work or part of the
Work is located or after the expiration of one year from the date (I) on which the
Claimant gave the notice required by paragraph 4.1 or paragraph 4.2.3, or (2) on
which the last labor or service was performed by anyone or the last materials or
equipment were furnished by anyone under the Construction Contract, whichever of
(1) or (2) first occurs. If the provisions of this paragraph are void or prohibited by
law, the minimum period of limitation available to sureties as a defense in the
jurisdiction of the suit shall be applicable.
12. Notice to the Surety, the OWNER or the CONTRACTOR shall be mailed or
delivered to the addresses shown on the signature page. Actual receipt of notice by
Surety, the OWNER or the CONTRACTOR, however accomplished, shall be
sufficient compliance as of the date received at the address shown on the signature
page.
13. When this Bond has been furnished to comply with a statutory or other legal
requirement in the location where the Contract was to be performed, any provision in
this Bond conflicting with said statutory or legal requirement shall be deemed
deleted herefrom and provisions conforming to such statutory Qr other legal
requirement shall be deemed incorporated herein. The intent is, that this Bond shall
be construed as a statutory Bond and not as a common law bond.
14. Upon request of any person or entity appearing to be a potential beneficiary of
this Bond, the CONTRACTOR shall promptly fumish a copy of this Bond or shall
permit a copy to be made.
15. DEFINITIONS
15.1. Claimant: An individual or entity having a direct contract with the
CONTRACTOR or with a Subcontractor of the CONTRACTOR to furnish labor,
materials or equipment for use in the performance of the Contract. The intent of this
Bond shall be to include without limitation in the terms "labor, materials or
equipment" that part of water, gas, power, light, heat, oil, gasoline, telephone service
or rental equipment used in the Contract, architectural and engineering services
required for performance of the Work of the CONTRACTOR and the
CONTRACTOR's Subcontractors, and all other items for which a mechanic's lien
may be asserted in the jurisdiction where the labor, materials or equipment were
furnished.
15.2. Contract: The agreement between the OWNER and the CONTRACTOR
identified on the signature page, including all Contract Documents and changes
thereto.
15.3. OWNER Default: Failure of the OWNER, which has neither been
remedied nor waived, to pay the CONTRACTOR as required by the Contract or to
perform and complete or comply with the other terms thereof.
ACKNOWLEDGMENT OF PRINCIPAL (Corporation)
STATE OF:
COUNTY OF:
On this day, May 12,2005, before me personally come(s) Au/r' L l4\-.lJ.-J to
me known, who, being by me duly sW9rn, deposes and says that he/she resides in the City of
Hamel, MN, that he/she is the P./UJ-')/cUiG(- of the DMJ Corporation
the corporation described in and which executed the foregoing instrument; that he/she knows the
seal of the said corporation; that the seal affixed to the said instrument is such corporate seal; that
it was so affixed by the order of the Board of Directors of said corporation, and that he/she
signed his/her name thereto by like order.
lEEN s. SEllyl
<>tal)' Public-Minnesota I
"""Ion c"'""res Jan 31,2010."
Wr1 Comm- '"'^"" ~
/ '
L - ./ /
~'~/"''''''''i '" rei..../.... ".[./;;...1 ...'
/ /i i - '. . %.?/ . j/
L/ ~.(t(~X9't;d/k
Notary Public
V
ACKNOWLEDGMENT OF SURETY
STATE OF: Minnesota
COUNTY OF: Ramsey
On this day, May 12, 2005, before me personally come(s) Jack CedarleafII, to me
personally known, who being by me duly sworn, did say that he is the aforesaid officer or
Attorney-In-Fact of the United Fire & Casualty Company, a corporation; that the seal affixed
to the foregoing instrument is the corporate seal of said corporation, and that said instrument was
signed and sealed in behalf of said corporation by the aforesaid officer, by authority of its board
of directors; and the aforesaid officer acknowledged said instrument to be the free act and deed of
said corporation.
(Z~
Notary Public
UNITED FIRE & CASUALTY COMPANY
HOME OFFICE - CEDAR RAPIDS, IOWA
CERTIFIED COPY OF POWER OF ATTORNEY
(Original on file at Home Office of Company- See Certification )
KNOW ALL MEN BY THESE PRESENTS, That the UNITED FIRE & CASUAL TYCOMPANY,a corporation duly organized and existing
under the laws of the State of Iowa, and having its principal office in Cedar Rapids, State of Iowa, does make, constitute and appoint
D. R. DOUGHERTY, OR JACK CEDARLEAF II, OR E. LANGE, OR, CHRISTINE M. HANSEN, OR KURT C. LUNDBLAD, OR
C. A. HOUSH, ALL INDIVIDUALLY of SAINT PAUL MN
its true and laWfulAttorney(s )-in-Fact with power and authority hereby conferred to sign, seal and execute in its behalf all laWful bonds,
undertakings and other obligatory instruments of similar nature as follows: Any andAHBonds
and to bind UNITED FIRE & CASUALTY COMPANY therebyas fully and tothesame extent as if such ipstruments were signed by the
duly authorized officers of UNtTED FIRE & CASUALTY COMPANY and all the acts of said Attorney, pursuantto the authority hereby
given are hereby ratified and confirmed.
The Authority hereby granted is continuous and shall remain in full force and effect until revoked by UNITED FIRE &
CASUALyY COMPANY.
This power of Attorney is made and executed pursuant to and by authority ofthefollowingBy-Lawduly adopted by Board of
Directors of the Company on April 18, 1973.
"Article V - Surety Bonds and Undertakings"
Section 2, Appointment of Attorney-in-Fact. 'The President or any Vice President, or any other officer ofthe Company may,
from time to time, appoint by written certificates attorneys-in-fact to act in behalf of the Company in the execution of policies of
insurance, bonds, undertakings and other obligatory instruments of like nature. The signature of any officer authorized hereby,
and the Corporate seal, maybe affixed by facsimile to any power of attorney or special power of attorney or certification of
either authorized hereby; such signature and seal, when so used, being adopted by the Company as the original signature of
such officer andthe. original seal of the Company, to be valid and binding upon the Company with the same force and effect as
though manually affixed. Such attorneys-in fact, subject to the limitations set forth in their respective certificates of authority
shall have full power to bind the Company by their signature and execution of any such instruments and to attach the seal of
the Company thereto. The President or any Vice President, the Board of Directors or any other officer of the Company may at
any time revoke all power and authority previously given to any attorney-in-fact.
. ~,,~ IN WITNESS WHEREOF, the UNITED FIRE & CASUALTY COMPANY has caused these presents to be signed by
it~"'~" its vice president and its corporate seal to be hereto affixed this 8th day of January, 2004
~~~!~'~l
-.:> lUlL 1:::
~' ~;:
~ ~,~
ik......~"\\\~
--....,
State of Iowa, County of Linn, ss:
UNITED FIRE & CASUALTY COMPANY
By ~ (j ~
Vice President
On 8th day of January, 2004, before me personally came Randy A. Ramlo
to me known, who being by me duly sworn, did depose and say; that he resides in Cedar Rapids, State of Iowa; that hejs a Vice
President of the UNITED FIRE & CASUAL TY COMPANY, the corporation described in and which executed the above instrument; that
he knows the seal of said corporation; that the seal affixed to the said instrument is such corporate seal; that it was so affixed pursuant
to authority given by the Board of Directors of said corporation and that he signed his name thereto pursual} to like authority, and
acknowledges same to be the act and deed of said corporation. ... l..l/J.....y'. ... .VI... '. /i 3' .7 .. ..C
./ i ((. G ... 6./. c>.<t..:.z // t ..26.../ "----
:, . ~.At
'1 ":jot... Notary Publici
<:> ..
; ~ ~ My commiSSion expo es: 10/26/2004
~. ow
I, the undersigned officer of the UNITED FIRE & CASUALTY COMPANY, do hereby certify that I have compared the foregoing copy of
the Power of Attorney and affidavit, and the copy of the Section of the by-laws of said Company as set forth in said Power of Attorney,
with the ORIGINALS ON FILE IN THE HOME OFFICE OF SAID COMPANY, and that the same are correct transcripts thereof, and of
the whole of the said originals, and that the said Power of Attorney has not been revoked and is now in full force and effect.
~<~/->. In testimo.qy whereof I hav~unto subscribed my na~d affixed the corporate seal of the said Company
~#~ ~~~ this I.~ day of ~,L/ 20 t') ,) .
~ 001'0141'111 I I
i _...., I I
-.:> SIAL ..,$ f2
..~ ~~$ 1k
~.,,'=~,\..\" ~ / t/ J~ Secretary
BOND0019 0802 01
UND3292B
United Fire Group
Fidelity & Surety Department
POLICYHOLDER DISCLOSURE
NOTICE OF TERRORISM INSURANCE COVERAGE
SURETY BONDS
You should know that, effective November 26, 2002, any losses sustained by the surety
caused by certified acts of terrorism would be partially reimbursed to the surety by the
United States under a formula established by federal law. Under this formula, the United
States pays 90% of covered terrorism losses exceeding the statutorily established deductible
paid by the surety providing the coverage. The portion of your bond premium that is attrib-
utable to coverage for acts of terrorism is $ 0.00. Before any charges are added for terror-
ism coverage in future surety products you purchase, you will be able to make a coverage
election for a then specified premium charge.
The existence of the federal terrorism insurance program does not affect the obligations you
assume in the indemnity agreement.
HOME OFFICE: 118 Second Ave. SE, PO Box 73909, Cedar Rapids, IA 52407-3909 Phone: 319-399-5700 FAX: 319-399-5425
UND.3290b (3-03)
ACOBQ CERTIFICATE OF LIABILITY INSURANCE I DATE (MMICD/YYYY)
05/12/2005
PRODUCER (651) 488-6666 FAX (651)488-9932 THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION
Cedarleaf, Cedarleaf & Cedarleaf, Inc. ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE
HOLDER. THIS CERTIFICATE DOES NOT AMEND,EXTEND OR
360 W. Larpenteur Ave. ALTER THE COVERAGE AFFORDED BY THE POLICIES BELOW.
P. O. Box 64717
St. Paul, MN 55164 INSURERS AFFORDING COVERAGE NAIC#
INSURED DMJ Corporat i on; SKH Aspha It, LLC INSURER A: Continental Western Ins. Co. 9637
2392 Pioneer Trai I INSURER B:
P. O. Box 299 Ct. INSURER C:
Hamel, MN 55340-0299 INSURER D:
INSURER E:
COVERAGES
THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD INDICATED. NOTWITHSTANDING
ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS CERTIFICATE MAY BE ISSUED OR
MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS, EXCLUSIONS AND CONDITIONS OF SUCH
POLICIES. AGGREGATE LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS.
I~?~ ~9,ll.'~ TYPE OF INSURANCE POLICY NUMBER POLICY EFFECTIVE POLICY EXPIRATION LIMITS
GENERAL LIABILITY CWP2396148 11/01/2004 11/01/2005 EACH OCCURRENCE $ .1,000,000
X COMMERCIAL GENERAL LIABILITY DAMAGE TO RENTED $ 50,00C
c-- =:J CLAIMS MADE [8] OCCUR
MED EXP {Anyone perl on} $ 5,000
I--
A PERSONAL & ADV INJURY $ 1,000,000
GENERAL AGGREGATE $ 2,000,000
GEN'L AGGREGATE LIMIT APPLIES PER: PRODUCTS - COMPJOP AGG $ 2,000,000
II fXl PRO. nLOC
POLICY X JECT
AUTOMOBILE LIABILITY CWP2396148 11/01/2004 11/01/2005 COMBINEO SINGLE LIMIT
")( ANY AUTO $
(Ee accidant) 1,000,000
I--
ALL OWNED AUTOS BODILY INJURY
I-- $
SCHEDULED AUTOS (Per perlon)
A -
HIRED AUTOS BOOIL Y INJURY
- (Per accidant) $
NON-OWNED AUTOS
-
- PROPERTY DAMAGE $
(Per accidant)
GARAGE LIABILITY AUTO ONLY. EA ACCIDENT $
==1 ANY AUTO OTHER THAN EA ACC $
AUTO ONLY: AGG S
EXCESSIUMBRELLA LIABILITY CU2416549 11/01/2004 11/01/2005 EACH OCCURRENCE $ 3,000,000
[8] OCCUR D CLAIMS MADE AGGREGATE $ 3,000,000
A s
~ OEOUCTIBLE $
X RETENTION S 10,OOC S
WORKERS COMPENSATION AND WC2396147 11/01/2004 11/01/2005 X I ~~T~J~'" I 10J~'
EMPLOYERS' LIABILITY E.L EACH ACCIOENT $ 100,000
A ANY PROPRIETORlPARTNERlEXECUTIVE
OFFICERlMEMBER EXCLUDED? E.L. OISEASE. EA EMPLOYEE S 500,000
if yes. describe under E.L DISEASE - POLICY LIMIT $ 100,000
SPECIAL PROVISIONS below
OTHER
::>~ESCRIPTlON OF OPERATIONS J LOCATIONS J VEHICLES J EXCLUSIONS ADDED BY ENDORSEMENT J SPECIAL PROVISIONS -
roject: City Project #779 ; Fi Ie 00034-04159-0; 2005 Street Park & Uti I ity Improvements.
he City of New Hope and Bonestroo Rosene Ander I ik & Associates are additional insureds, within
he scope of the insured's operations on General Liabi I ity & Umbrella pol icies.
CERTIFICATE HOLDER CANCELLATION
SHOULD ANY OF THE ABOVE DESCRIBED POLlC!ES BE CANCELLED BEFORE THE
EXPIRATION DATE THEREOF, THE ISSUING INSURER WILL ENDEAVOR TO MAIL
City of New Hope ~ DAYS WRITTEN NOTICE TO THE CERTIFICATE HOLDER NAMED TO THE LEFT,
c/o Bonestroo Rosene Ander I ik BUT FAILURE TO MAIL SUCH NOTICE SHALL IMPOSE NO OBLIGATION OR LIABILITY
2335 W. Highway 36 OF ANY KIND UPON THE INSURER, ITS AGENTS OR REPRESENTATIVES.
St. Paul, MN 55113 AUTHORIZED REPRESENTATIVE ~
John Pribnow/SP
ACORD 25 (2001/08)
@ACORDCORPORATION 1988
SECTION 01100
SUMMARY
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. Basic description of the Project and work restrictions.
1.02 SUMMARY OF WORK
A. Project Name: 2005 Street, Park and Utility Infrastructure Improvements for the
City of New Hope, Minnesota, City Project No. 779.
B. Description of Work: Installation of sanitary sewer and services and storm sewer,
the construction and/or restoration of street sections, construction of bituminous
trails and play area curb in an adjoining park, and the reconstruction of an existing
parking lot.
C. This Project will be completed simultaneously with other projects at the same
location. These other projects include additional City projects, as well as work to
be performed by a neighboring developer's contractor.
D. The other City project includes the installation of play equipment and sodding in
the park area. It is anticipated that this work will take place in the latter part of this
Contract.
E. The developer of the property to the west of the church property, Ryland Homes,
is responsible for some work that will overlap the work of this Contract. At this
time, the work to be completed includes:
1. Rough grading in the park area. This work includes the rough grading of
the dry pond and berm in the park area and stockpiling of topsoil. This
work is scheduled to be completed prior to the start of work for this
Contract.
2. Installation of water main and force main on the west side of the church
property. It's anticipated that this work will be completed late May.
3. Installation of storm sewer connecting the development system to the
system installed as part of this Project. The completion of this work will
be dictated by the installation of the sewer under this Contract.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
01100-1
SUMMARY
4. Retaining wall construction along the west property line of the church.
This should be completed after installation of the developer's force main,
water main, and storm sewer, and prior to the construction of the new
parking lot.
5. Seeding and planting in the park area. This includes the seeding mixtures
and trees shown on the Drawings. This work is to be completed after the
final grading, re-spreading of topsoil, and trail construction is completed
under this Contract.
F. In the event that the Alternate No.2 storm sewer is constructed and the parking lot
reconstruction is awarded, the quantities involving the restoration of the existing
lot will be adjusted with no adjustment to the Bid Unit Price.
G. Extensive coordination will be required for successful completion of these
Projects. The coordination requirements will increase or decrease dependant on
which parts are awarded to this Contract.
H. The Owner reserves the right to award or reject any or all of the parts listed on the
Bid Form. No adjustment will be made to Bid Unit Prices to those parts that are
awarded.
1.03 COMPLETION DATES
A. Substantial Completion: Set forth in the Agreement.
B. Final Completion: Set forth in the Agreement.
1.04 LIQUIDATED DAMAGES
A. Provisions for liquidated damages, if any, are set forth in the Agreement.
1.05 WORK RESTRICTIONS
A. Use of Project Site:
1. Location of construction facilities, staging areas, product stockpiles,
material storage, and temporary construction should be reviewed with the
Engineer and shall be removed upon completion of work.
2. Contractor responsible for snow removal and disposal from the Owner's
property if necessary to maintain access and working space during
construction.
3. Keep existing driveways and entrances clear and available to the public
and to the Owner.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, lnc.
01100-2
SUMMARY
4. If additional space is needed, obtain and pay for such space off Project
Site.
B. Access to Project Site:
1. Access to the Project areas shall be via Winnetka Avenue North (CSAR
156) to 53rd Avenue North to Sumter Avenue.
2. If the parking lot reconstruction is awarded, the church property may be
accessed directly from Bass Lake Road (County Road 10).
3. Review any proposed alternate routes with the Engineer.
C. Other Work at Project Site:
1. The wrecking of an overhead power line and relocation of a utility pole is
anticipated.
2. See the notes above under the Summary of Work for more information
regarding other work that may take place on the Project Site.
PART 2 - PRODUCTS
Not Used
PART 3 - EXECUTION
3.01 MEASUREMENT AND PAYMENT
A. All work and costs ofthis Section shall be incidental to the Project and included
in the TOTAL BASE BID.
END OF SECTION
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
01100-3
SUMMARY
SECTION 01310
PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. General requirements for overall Project coordination.
1.02 UTILITIES
A. Notify Gopher State One Call before starting construction in a given area requesting
utility locates in the Project Site.
B. Project Utility Sources: Coordinate work with the following utility owners. The
following utilities are known to be on the Project Site and are shown on the Drawings
in a general way:
1. Water: Owner.
2. Sanitary Sewer: Owner.
3. Storm Sewer: Owner.
4. Electric: Xcel Energy, Gregory S. Plumedahl, 8701 Monticello Lane, Maple
Grove, MN 55369; ph: 763-493-1670; fax: 763-493-1501.
5. Gas: Reliant Energy, Cherie Monson, P.O. Box 1165, Minneapolis, MN
55440-1165; ph: 612-321-5435; fax: 763-321-5480.
6. Telephone: Qwest, Carrie Oster, 9700 Schmidt Lake Road, R.m 155,
Plymouth, MN 55442; ph: 763-531-8997; fax: 763-536-5098.
7. Cable TV: Comcast, Doug Zahn, 1238 Grey Fox Road, Arden Hills, MN
55112-6930; ph: 651-493-5316; fax: 651-493-5116.
C. Owner requires 48 hour notice for all utility interruptions.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
01310-1
PROJECT MANAGEMENT AND
COORDINATION
1.03 PERMITS
A. Comply with the stipulations of the following permits, which have been applied for
and will be furnished by the Owner:
1. MPCA StormW:'!:ter Discharges Associated With Construction Activities
NPDES General Permit.
B. Apply for, obtain, and comply with other permits, licenses, and approvals which may
be required for the Proj ect.
1.04 SURVEYING AND CONSTRUCTION OBSERVATION
A. Provide Engineer and Resident Proj ect Representative a minimum of 48 hours notice
in advance of the need for establishing lines, grades, measurements, grade checks, and
observation of work.
B. Engineer will furnish a Resident Proj ect Representative consistent with Paragraph 9.10
of the Supplementary Conditions.
1.05 PROJECT MEETINGS
A. Administrative Requirements:
1. Proj ect Superintendent or persons designated by the Contractor to attend and
participate in the Project meetings shall have all required authority to commit
the Contractor to solutions agreed upon in the Project meetings.
2. Engineer will set the time, sites, and prepare the agenda for the meetings.
3. Engineer will prepare meeting minutes and distribute 1 copy to Contractor.
Notify Engineer of inaccuracies or discrepancies in the meeting minutes within
5 calendar days of receipt of the minutes.
4. The attendance and cooperation of subcontractors and suppliers may be
required.
B. Preconstruction Conference:
1. Provisions for the Preconstruction Conference are set forth in the General
Conditions.
2. Requirements for preconstruction submittals are set forth in the General
Conditions.
000034-04159-0
i!:i 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
01310-2
PROJECT MANAGEMENT AND
COORDINATION
C. Progress Meeting Procedures:
1. Engineer will schedule construction progress meetings throughout the duration
of the Project to assess the progress of the work, identify and discuss Project
related issues, and discuss near-term construction activities.
1.06 CONSTRUCTION SCHEDULING
A. Sequencing and Scheduling:
1. Contracts for other work within the Project limits will be awarded and
construction activities will take place at the same time as the work is
completed under this Contract.
2. If Alternate No.2 is accepted, the installation of the storm sewer that passes
through the existing church parking lot will need to be coordinated with the
installation of water main and force main (to be completed by others).
3. The installation ofthe Phase 1 portion of the Play Area Curbing and all work
required to be completed prior to curb installation will need to be coordinated
with the installation ofthe play equipment (to be completed by others).
4. Coordination between contractors will be required. Coordinate schedules and
activities through the Project Engineer.
1.07 SUBMITTALS
A. Submit a minimum of 4 copies of shop drawings, plus the quantity of copies the
Contractor wants returned.
PART 2 - PRODUCTS
Not Used
PART 3 - EXECUTION
3,01 MEASUREMENT AND PAYMENT
A. All work and costs ofthis Section shall be incidental to the Proj ect and included in the
TOTAL BASE BID.
END OF SECTION
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
01310-3
PROJECT MANAGEMENT AND
COORDINATION
SECTION 01400
QUALITY REQUIREMENTS
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. Information required for conformance to regulatory requirements.
B. Quality assurance.
C. Procedures to measure and report the quality and performance of the work.
1.02 REFERENCE STANDARDS
A. Whenever reference is made to the Minnesota Department of Transportation
Specifications, such reference shall mean "Standard Specifications for Construction,"
2000 Edition (MnDOT Spec.) and all subsequent revisions and supplements. The
word "Engineer" is understood to refer to the Engineer for the Owner.
1.03 SUBMITTALS
A. Prior to start of work, submit testing laboratory name for various specified tests for
approval by Engineer.
B. Submit copies of laboratory test results or analysis.
C. Manufacturer's certificates of quality control or performance.
1.04 WORKMANSHIP
A. Comply with industry standards of the region, except where more restrictive
tolerances or specified requirements indicate more rigid standards or more precise
workmanship.
1.05 TESTS AND INSPECTIONS
A. Conform to the requirements of Article 13 of the General Conditions, except as
modified herein.
B. Notify Engineer 48 hours prior to expected time for operations requiring tests and
inspections.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
01400-1
QUALITY REQUIREMENTS
C. Provide incidental labor and facilities to obtain and handle samples at Project Site or
source, transport samples to laboratory, facilitate tests and inspections for storing and
curing of test samples.
1.06 LABORATORY REPORTS
A. After each inspection and test, submit 3 copies of Laboratory Report to Engineer.
B. Include: Date issued, Project Title and number, name of inspector, date and time of
sampling or inspection, identification of product and Specifications Section, location
in the Project, type of inspection or test, date of test, results oftests, and conformance
with Contract Documents.
1.07 LABORATORY RESPONSIBILITIES
A. Test samples and perform field tests.
B. Provide qualified personnel. Cooperate with Engineer and Contractor in performance
of services.
C. Ascertain compliance with the requirements of the Contract Documents.
D. When requested by Engineer, provide interpretation oftest results.
1.08 Lll'v1ITS ON TESTING LABORATORY AUTHORITY
A. Laboratory may not release, revoke, alter, or enlarge on requirements of Contract
Documents.
B. Laboratory may not approve or accept any portion of the work.
C. Laboratory may not assume any duties of Contractor.
D. Laboratory has no authority to stop work.
1.09 MANUFACTURER'S CERTIFICATES
A. If requested by Engineer, submit manufacturer's certificate with shop drawings
certifying that products meet or exceed specified requirements executed by
responsible officer.
1.10 MANUFACTURER'S FIELD SERVICES
A. Provide qualified representative to observe field conditions; conditions of surfaces
and installation; quality of workmanship; start-up of equipment; and test, adjust, and
balance of equipment.
000034-04159-0
@ 2005 BonestroQ, Rosene,
Anderlik & Associates, Inc.
01400-2
QUALITY REQUIREMENTS
PART 2 - PRODUCTS
Not Used
PART 3 - EXECUTION
3.01 MEASUREMENT AND PAYMENT
A. All work and costs of this Section shall be incidental to the Project and included in
the TOTAL BASE BID.
END OF SECTION
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
01400-3
QUALITY REQUIREMENTS
SECTION 01500
TEMPORARY FACILITIES AND CONTROLS
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. Temporary utilities and miscellaneous temporary facilities required during
construction.
1.02 REFERENCES
A. Minnesota Department of Transportation "Standard Specifications for Construction,"
2000 Edition (MnDOT Spec.),
B. The Minnesota Manual on Uniform Traffic Control Devices (MMUTCD), including
the Field Manual on Temporary Traffic Control Zone Layouts - Latest edition.
1.03 SUBMITTALS
A. Submit Traffic Management and Control Plan. Plan shall include the following
information:
1. Haul and access routes.
2. Traffic control measures.
3. Permits or applications required by local authorities.
4. Temporary facilities required.
PART 2 - PRODUCTS
Not Used
PART 3 - EXECUTION
3.01 MOBILIZATION
A. Move personnel, equipment, materials, and all other items required to complete the
work at the Project Site.
B. Establish Contractor offices, building, or other facilities necessary for work on the
Project.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
01500-1
TEMPORARY FACILITIES
At'ill CONTROLS
C. Temporarily hold or relocate utilities and any miscellaneous structures, such as signs,
power poles, guy wires, and mailboxes disturbed.
3.02 SIGNS, MAILBOXES, ETC. REMOVAL AND REPLACEMENT
A. Remove, store carefully, and replace all non-City or County owned signs, posts, etc.
that may be within the Project Site as directed by Engineer.
3.03 TEMPORARY UTILITIES
A. Provide and maintain all temporary facilities, utilities, and controls as long as needed
for the safe and proper completion of the work. Remove all temporary facilities,
utilities, and controls as rapidly as progress will permit or as directed by Engineer.
B. Temporary Water for Construction:
1. Obtain water for construction from locations designated by the Owner.
3.04 CONSTRUCTION FACILITIES
A. Sanitary Facilities:
1. Comply with all governing regulations, including safety and health codes for
sanitary fixtures and facilities.
2. Provide self-contained toilet units, or water and sewer connected temporary
toilet facilities consistent with governing regulations. Contractor may not use
Owner's toilet facilities.
3. Provide and maintain adequate supply of toilet tissue, paper towels, paper
cups, and similar disposable materials appropriate for each facility. Provide
appropriate covered waste containers for used material.
3.05 TEMPORARY CONSTRUCTION
A. Pumping and Dewatering:
1. Provide draining, pumping, dewatering, and cleaning operations necessary to
complete the work.
2. Provide all necessary pumping to remove all surface water and groundwater
from structures as required for the work. Provide erosion control measures for
discharge of water.
3. Protect Project Site and adjacent property to avoid damage.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
01500-2
TEMPORARYFAC~ITffiS
AND CONTROLS
3.06 TRAFFIC CONTROL
A. Provide and maintain all traffic control devices needed to guide, warn, control, and
protect traffic throughout the Project Site. All traffic control devices and other
protective measures shall conform to MMUTCD.
B. Remove traffic control devices at the conclusion of the work.
C. Flaggers are required to protect construction vehicles during unloading or
construction materials. Conform to the requirements of the MJ\.1UTCD, the Flagging
Handbook included in the Field Manual for Temporary Traffic Control Zone Layouts,
and the following: while on duty flaggers shall wear hard hats and reflectorized
florescent orange rests; and flaggers shall be fully clothed when on duty with shirt or
blouse, slacks or trouser, and sturdy shoes.
D. Field Quality Control:
1. Daily inspect and insure that all traffic control devices required by the
construction are in accordance with the MMUTCD. Any discrepancy between
the actual devices in use and the required devices shall be immediately
rectified.
2. Furnish names, addresses, and phone numbers of at least 3 individuals
responsible for the placement and maintenance of traffic control devices. At
least 1 of these individuals shall be "on call" 24 hours per day, 7 days per
week during the time any traffic control devices furnished and installed by the
Contractor are in place.
3. Provide access for emergency vehicles and busses to all residences at all
times.
4. Respond to any request from the Engineer to improve or correct the usage of
traffic control devices on or related to this Proj ect within 1 hour ofthe time of
notification.
5. Keep all traffic control signs and devices in a legible condition. This shall
include but not be limited to removing grime and dust deposited on any
device by traffic, natural causes, or when requested by Engineer.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
01500-3
TEMPORARY FACILITIES
AND CONTROLS
V'
3.07 TE11PORARY BARRIERS AND ENCLOSURES
A. Temporary Barriers:
1. Provide temporary covers, enclosures, markers, and barriers as necessary to
protect work.
2. Damage to the Project Site caused by removal of temporary fencing,
including postholes, shall be promptly repaired by Contractor. During
removal at no time shall the work remain unattended if a dangerous condition
exists because of incomplete removal or Project Site repairing.
B. Temporary Fence:
1. Install as necessary to protect work.
2. Maintain and repair fence throughout the duration of the Project.
3. Provide Owner and Engineer with keys or combinations to any locks that may
be used to secure fencing gates.
3.08 MEASUREMENT AND PAYMENT
A. A Bid Item has been provided for Mobilization. Measurement is Lump Sum. This
will be considered payment in full for all work and costs of this Bid Item:
1. Partial payment of the Lump Sum Bid Item "Mobilization" will be made
using a percentage based on the following:
Cumulative Percent of
Mobilization Item Paid
First Partial Payment
Percent of original contract amount earned - 25
Percent of original contract amount earned - 50
Percent of original contract amount earned - 100
50
70
90
100
B. Dewatering: All costs related to pumping and dewatering as specified above will be
considered incidental to the Project.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
01500-4
TEMPORARY FACILITIES
Al\!D CONTROLS
C. A Bid Item has been provided for Traffic Control. Measurement is by the Lump
Sum. This will be considered payment in full for all work and costs ofthis Bid Item,
including removal:
1. Partial payment of the Lump Sum Bid Item "Traffic Control" will be made
using a percentage based on the following:
Cumulative Percent of
Traffic Control Item Paid
First Partial Payment
Percent of original contract amount earned - 25
Percent of original contract amount earned - 50
Percent of original contract amount earned - 100
50
70
90
100
D. All other work and costs of this Section shall be incidental to the Project and
included in the TOTAL BASE BID.
END OF SECTION
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
01500-5
TEMPORARY FACILITIES
AND CONTROLS
SECTION 01570
TEMPORARY EROSION AND SEDIMENT CONTROL
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. Temporary measures to control soil erosion and sedimentation.
1.02 RELATED SECTIONS
A. Section 02315 - Excavation and Fill.
B. Section 02920 - Lawns and Grasses.
1.03 REFERENCES
A. Minnesota Department of Transportation "Standard Specifications for Construction,"
2000 Edition (MnDOT Spec.):
1. 1803 - Prosecution of Work.
2. 2573 - Temporary Erosion Control.
3. 3733 - Geotextile.
4. 3886 - Silt Fence.
5. Special Provisions S-25.
6. Special Provisions S-250.
1.04 PERMITS
A. General:
1. This Proj ect disturbs 1 or more acres of total land area, submit a completed
application form for the MPCA's General Storm Water Permit for
Construction Activity and the appropriate fees to the MPCA. Also, submit a
copy of the completed, signed, and dated application form to Owner.
Authorization to begin grading under the NPDES Permit is automatically
granted 48 hours after the permit application has been submitted to the
MPCA.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
TEMPORARY
EROSION AND SEDIMENT CONTROL
01570-1
1.05 SEQUENCING AND SCHEDULING
A. Conform to MnDOT Spec. 1803.5:
1. Submit for approval the plan of operations for accomplishing temporary and
permanent erosion control.
2. All temporary erosion control measures to be installed prior to any grading
activities.
3. Permanent erosion control measures are to be installed when deemed
appropriate during the grading process.
4. If the Contractor fails to install erosion or sediment measures, the Engineer
may withhold payment from related work until the control measures are
undertaken by the Contractor:
a. When the Contractor fails to conduct the quality control program,
doesn't conduct the inspection required in the NPDES permit, or fails
to take action ordered by the Engineer to remedy erosion or sediment
control problems, the Engineer shall issue a Written Order to the
Contractor,
b. The Contractor shall respond within 24 hours with sufficient
personnel, equipment, materials, and conduct the required work or be
subject to a $500.00 per calendar day deduction for noncompliance.
B. Contractor is responsible for the establishment of permanent turf in accordance with
Section 02920 - Lawns and Grasses to prevent excessive soil erosion.
PART 2 - PRODUCTS
2.01 SILT FENCE
A. Machine Sliced Silt Fence:
1. Geotextile Fabric: Monofilament/Monofilament Geotextile conforming to
MnDOT Spec. 3886.2A, Machine Sliced:
a. Width: Minimum 36 inches.
2. Posts: Standard steel T -posts with welded plate weighing not less than 1.33
pound per lineal foot. Minimum length 60 inches. Minimum embedment is
24 inches below ground surface with a maximum:
a. Post spacing of 6 feet.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
TEMPORARY
EROSION AND SEDIMENT CONTROL
01570-2
2.02 TEMPORARY CONSTRUCTION ENTRANCE
A. Rock Construction Entrance:
1. 3 inch size (minimum) washed river rock.
2. Geotextile: Conform to MnDOT Spec. 3733, Type 4.
2.03 STORM DRAIN INLET PROTECTION
A. Curb inlet protection device:
1. Geotextile Catch Basin Filter.
B. Non-street inlet protection:
1. Geotextile Box.
PART 3 - EXECUTION
3.01 GENERAL
A. Conform to MnDOT Spec. 2573.3:
1. Minimize the amount of disturbed land that is susceptible to erosion.
2. Install the appropriate temporary erosion and sediment structural controls
measures in accordance with approved sequence of construction. Clearing
and grubbing operations shall be so scheduled and performed so that grading
operations and permanent erosion control features can follow immediately
thereafter.
3. The surface area of erodible earth material exposed at 1 time by clearing and
grubbing, by excavating, by fill, or by borrow shall not exceed 1/3 of the
Project length without written approval of the Engineer.
4. Only disturb, clear, or grade areas necessary for construction. Delineate areas
not to be disturbed:
a. Exclude vehicles and construction equipment from these areas to
preserve natural vegetation.
5. Maintain and preserve riparian and naturally vegetated buffer strips along
water courses.
000034-04159-0
(Q 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
TEMPORARY
EROSION AND SEDIMENT CONTROL
01570-3
3.02 INSTALLATION
A. Silt Fence: Conform to MnDOT Spec. 2573.3B3:
1. Silt fences shall be installed in the locations shown on the Drawings, using
the machine sliced installation method.
2. If the silt fence is longer than 600 feet, it shall be constructed in separate
independent units with each unit having a length less than 600 feet. All
splices shall be avoided whenever possible:
a. If necessary, splices will be made at an opposing fence post and
according to the manufacturer's specifications.
B. Temporary Rock Construction Entrance:
1. Rock construction entrance shall be installed in locations shown on the
Drawings.
2. Rock construction entrance shall be constructed before grading begins on the
Project Site.
3. Inspect rock construction entrance daily for mud accumulation,
3.03 MAINTENANCE
A. Conform to MnDOT Spec. 2573.3D, and as follows:
1. Contractor is responsible for inspection, maintenance, and repair of any
washouts or accumulations of sediment that occur as a result of the grading or
construction. Restoration consists of grade repair, turfre-establishment, and
street sweeping of mud and debris tracked from the Project Site.
2. Inspection of all erosion control items will take place immediately after each
runoff event and at least daily during prolonged rainfall. Any required repairs
shall be made immediately.
3, Upon final acceptance of the Proj ect and establishment of permanent erosion
control measures, the Contractor shall remove all temporary erosion control
measures.
B. Sediment Removal: Conform to MnDOT Spec. 2573.3E and Special Provision
S-25:
1.
If an erosion control device has been reduced in capacity by 30 percent or
more, the Contractor shall restore such features to their original condition.
TEMPORARY
EROSION AND SEDIMENT CONTROL
000034-04159-0
<Q 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
01570-4
C. Mobilization, Emergency Erosion Control: Conform to MnDOT Spec. 2573.3H,
Special Provision S-250, or as modified below:
1. Routine temporary erosion control measures are not considered to be part of
Emergency Mobilization Erosion Control.
D. Control dust blowing and movement on Project Site and roads as directed by
Engineer to prevent exposure of soil surfaces, to reduce on and offsite damage, to
prevent health hazards, and to improve traffic safety:
1. Dust control measures will be considered incidental.
E. Acceptance of Work: Conform to MnDOT Spec. 2573.3C.
3.04 MEASUREMENT AND PAYMENT
A. Bid Items have been provided for temporary measures to control soil erosion and
sedimentation. Payment at the Bid Unit Price will be considered compensation in full
for all work necessary to complete the Bid Item in full, including installation,
maintenance, sediment removal, repairs, and removals.
B. Measurement will be based upon the units as listed below for Bid Items removed,
abandoned, or salvaged complete as specified. No measurement will be made of any
removals that are not required. The actual quantity installed multiplied by the
appropriate Bid Unit Price will be compensation in full for all work and costs ofthe
following Bid Items. 80 percent partial payment will be made upon installation and
20 percent payment will be made upon removal and restoration:
1. Machine Sliced Silt Fence: Measurement will be along the base ofthe fence,
from outside to outside of the end posts for each section offence.
2. Temporary Rock Construction Entrance: Measurement will be by weight or
loose volume (vehicular measure).
3. Geotextile CB Filter: Measurement will be by each.
4. Drain Inlet Protection: Measurement will be by each.
C. All other work and costs of this Section shall be incidental to the Project and
included in the TOTAL BASE BID.
END OF SECTION
000034-04159-0
(Q 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
TEMPORARY
EROSION AND SEDIMENT CONTROL
01570-5
SECTION 01700
EXECUTION REQUIREMENTS
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. Requirements for overall execution of the work and closeout of the Contract for Final
Payment.
1.02 SUBMITTALS
A. Submit the following items consistent with the Conditions of the Contract and
Division 1 - General Requirements Sections:
1. Record Documents, Written Notification of Substantial Completion,
Executed Certificate of Substantial Completion, Written Notification of Final
Completion, Spare Parts, Operation and Maintenance Manuals, instructions,
schedules, warranties, guarantees, Bonds, certificates, certificates of
inspection, and other documents.
2. Final Application for Payment, including accompanying documentation
IC-134 Form.
PART 2 - PRODUCTS
Not Used
PART 3 - EXECUTION
3.01 EXAMINATION
A. Acceptance of Conditions: By commencing work, Contractor construes acceptance
of the adjacent work as satisfactory to receive subsequent work.
B. Existing Conditions: Before commencing work, inspect work completed by others
that is adjacent to work. If adjacent conditions prevent completion of work,
Contractor will not commence work until the conditions are corrected.
C. Inspect each product immediately prior to installation. Remove damaged products
from Project Site.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
01700-1
EXECUTION REQUIREMENTS
3.02 GENERAL INSTALLATION REQUIREMENTS
A. Comply with the manufacturer's instructions for installation of manufactured
products to the extent that these instructions are applicable and more explicit or more
stringent than requirements indicated in the Contract Documents.
B. Secure work true to line and level, within recognized industry tolerances, with
anchorage devices designed and sized to withstand stresses, vibration, and rocking.
Allow for expansion and movement of building.
C. Install each element of work during weather conditions and Project status to ensure
coordination of the work. Isolate each element of work from incompatible work as
necessary to prevent deterioration.
D. Record installation details and prepare Record Documents consistent with the
General Conditions.
3.03 PROJECT SITE MAINTENANCE
A. Maintain stockpiles, excavations, access roads, and all other work areas free from
dust. Employ dust abatement techniques whenever a dust nuisance or hazard occurs,
or as directed by Engineer. Comply with local ordinances.
B. Protect hazardous work areas and hazardous material storage areas.
C. Protect trees unless specifically indicated on Drawings.
D. Clean access roads and haul routes with mechanical street sweeper.
E. If Contractor fails to maintain Project Site, Engineer will provide Written Notice of
Contractor's defective work. Contractor will be given 12 hours from the Notice to
clean Project Site. After the 12 hour period, Owner may correct the defective work
consistent with Article 13.09 of the Conditions of the Contract.
3.04 CLEANING AND PROTECTION
A. Clean and protect work in progress and adjoining work during handling and
installation. Apply protective covering on installed work where it is required to
ensure freedom from damage or deterioration.
B. Clean and perform maintenance as frequently as necessary throughout construction
period. Adjust and lubricate operable components to ensure operability without
damage effects.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
01700-2
EXECUTION REQUIREMENTS
3.05 CERTIFICATE OF COMPLIANCE WITH MINNESOTA STATUTES 290.92 & 290.97
A. Upon completion of the Project and prior to Final Payment, the Contractor and all
subcontractors shall complete Minnesota Department of Revenue Revised Form
IC-134. This form, Affidavit for Obtaining Final Settlement of Contract with the
State of Minnesota and any of its Political or Governmental Subdivisions, is to be
signed by a Department of Revenue representative and forwarded to the Owner.
Copies of this form can be obtained by writing to the Minnesota Department of
Revenue, Forms Section, Mail Station 1173, St. Paul, MN 55146-1173 or by
calling (651) 296-4444.
3.06 MEASUREMENT AND PAYMENT
A. A Bid Item has been provided for Street Sweeper with Pick Up Broom with Operator,
Measurement will be by the units of hours.
B. All other work and costs of this Section shall be incidental to the Project and
included in the TOTAL BASE BID.
END OF SECTION
000034-04159-0
<<::i 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
01700-3
EXECUTION REQUIREMENTS
SECTION 02225
REMOVALS
PART 1- GENERAL
1.01 SECTION INCLUDES
A. Complete or partial removal and disposal or salvage of at grade, above grade, and
below grade structures and miscellaneous items.
1.02 RELATED SECTIONS
A. Section 02315 - Excavation and Fill.
1.03 REFERENCES
A. Minnesota Department of Transportation "Standard Specifications for Construction,"
2000 Edition (MnDOT Spec.):
1. 2104 - Removing Pavement and Miscellaneous Structures.
1.04 DEFINITIONS
A. Remove: To take away or eliminate from the Project Site by aJ1ymethod selected by
the Contractor, including disposal of material.
B. Salvage: To dismantle, disassemble, or remove carefully without damage so the item
can be re-assembled, replaced, or reused in a workable condition equal to that
existing before removal.
C. Abandon: To fill, bulkhead, or close off pipes and structures so that no settlement or
flow can occur.
1.05 REGULATORY REQUIREMENTS
A. Conform to MnDOT Spec. 2104.3C, with the following modifications:
1. All materials designated for removal shall be disposed of outside the Proj ect
Site at locations to be selected by the Contractor,
2. All materials designated for salvage shall be stockpiled or temporary stored
on sites to be provided by the Contractor.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02225-1
REMOVALS
1.06 SCHEDULING
A. Prior to starting work, submit for review by the Engineer and approval by the Owner,
a schedule showing the commencement, order, and completion dates of the various
parts of this work.
B. Fill holes or depressions resulting from removal or salvage immediately.
C. Provide temporary surface restoration for traffic continuity where removal or salvage
operations are completed within streets, driveways, or parking lots.
PART 2 - PRODUCTS
Not Used
PART 3 - EXECUTION
3.01 GENERAL
A. Dispose of all items removed, except for those items identified to be salvaged or
recycled. Said disposal shall be in accordance with all laws, regulations, statutes, etc.
B. Perform removal work without damage to adj acent retained work. Where such work
is damaged, the Contractor shall patch, repair, or otherwise restore same to its
original condition at no expense to the Owner.
C. Remove debris from the work area as often as necessary, but not less than at least
once at the end of each workday. Debris shall be placed in approved containers to
prevent the spread of dust and dirt.
D. Execute the work in a careful and orderly manner with the least possible disturbance
to the public and occupants of buildings.
E. Fill holes resulting from removals consistent with Section 02315 - Excavation and
Fill.
3.02 EXAMINATION
A. Meet with owners of signs to determine requirements for salvage, storage, and
replacement.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02225-2
REMOVALS
3.03 PROTECTION
A. Take all necessary precautions to adequately protect personnel, and public and
private property in the areas of work. All Project Site fencing shall be in place prior
to the start of any removal work.
B. All street signs, traffic control signs, guy wires, mailboxes, posts, wood fence, etc.
which may interfere with construction shall be removed, stored safely, and replaced.
C. Approved barriers or warning signs shall be provided as necessary.
D. Provide and maintain temporary protection of existing structures designated to
remain where removal work is being done, connections made, materials handled, or
equipment moved.
E. Do not close or obstruct walkways or roadways. Do not store or place materials in
passageways or other means of egress. Conduct operations with minimum traffic
interference.
F. Take reasonable precautions to limit damage to existing turf. Avoid disturbance to
any material beyond the limits required for new construction.
G. Holes or depressions created by removals shall not be left open for more than 1 day.
Any hole within 10 feet of sidewalks shall be filled, suitably marked, or covered
immediately.
3.04 SAWING PAVEMENT
A. Concrete Pavement: Saw along the removal line to a depth of 1/3 ofthe thickness of
the concrete prior to breaking off the pavement.
B. Bituminous Pavement: Saw along the removal line to a minimum depth of3 inches
prior to breaking off the pavement.
C. Pavement that must be sawn a second time due to lack of protection or poor quality
of the first cut will not be compensated a second time.
3.05 REMOVE BITUMINOUS PAVEMENT, PATH, DRlVEWAY
A. Remove in accordance with MnDOT Spec. 2104.3B, except as modified below.
B. Sawcut bituminous pavement at the removal limits prior to that removal (incidental
to removal on paths and driveways), unless otherwise approved by the Engineer.
C. Prior to restoring trench areas, the edges of the trench shall be trimmed back to a
vertical face on a straight line which is parallel with the centerline of the trench.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02225-3
REMOVALS
3.06 REMOVE CURB AND GUTTER
A. Sawcut at removal limits (incidental to curb removal).
B. Concrete Curb and Concrete Curb and Gutter: Do not disturb any material beyond the
limits required to form for new construction (assumed 12 inches maximum from the
back of new work and 6 inches beyond the edge of new driveways).
C. Bituminous Curb: Bituminous curb is to be removed with the pavement. No
additional compensation will be made for the curb removal.
3.07 REMOVE CONCRETE SURFACING
A. Work includes sidewalks and driveways.
B, Sawcut concrete surfacing prior to removal (incidental).
C. Remove concrete in such a manner that the remaining surfacing is not damaged.
D. When removing existing sidewalks, the Contractor shall not disturb any material
beyond the limits required for new construction (assumed as 6 inches maximum
beyond and 8 inches maximum below existing grade).
E. When removing existing driveways, the Contractor shall not disturb any material
beyond the limits required to form for new construction (assumed 12 inches
maximum from the back of new work and 6 inches beyond the edge of new
driveways).
F. Prior to restoring trench areas, the edges of the trench shall be trimmed back to a
vertical face on a straight line which is parallel with the centerline of the trench.
3.08 REMOVE BITUMINOUS SURFACING
A. Work includes pathways and driveways.
B. Sawcut bituminous surfacing to full depth at the limits of partial removal prior to that
removal, unless otherwise approved by the Engineer.
C. Remove bituminous in such a manner that the remaining surfacing is not damaged.
D. Prior to restoring trench areas, the edges of the trench shall be trimmed back to a
vertical face on a straight line which is parallel with the centerline of the trench.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02225-4
REMOVALS
E. When removing existing pathways and driveways, the Contractor shall not disturb
any material beyond the limits required to form for new construction (assumed 12
inches maximum from the back of new work and 6 inches beyond the edge of new
driveways).
3.09 REMOVE MANHOLES AND CATCHBASINS
A. Remove entire structure, including casting, structure, and base slab.
3.10 REMOVE CATCHBASIN MANHOLE CASTING
A. Remove casting and adjustment rings and dispose of off-site.
3.11 REMOVE SECTIONS OF EXISTING PIPE
A. Pipes to be removed shall be removed and disposed of off site. Trench is to be
compacted in accordance with Section 02320 - Trench Excavation and Backfill.
3.12 REMOVE RETAINING WALL
A. Remove wall in its entirety (by others), including footings and tiebacks.
B. Dispose of materials offsite at a predetermined location.
3.13 REMOVE LIGHT POLE
A. Remove pole and light fixture (by others) and dispose of off-site.
B. Remove or coordinate removal with private utility, overhead power line serving the
light.
3,14 SALVAGEANDREINSTALL
A. Signs:
1. In no case shall a traffic sign or street sign be removed or disturbed by
Contractor without prior notification being given to Engineer and then only
after satisfactory arrangements have been made for a temporary installation or
its disposition:
a. Street identification signage shall be maintained at all times due to its
importance to the 911 Emergency Response System.
2. Remove and salvage all posts, A-frame angle brackets, stringers, as well as
the nuts, bolts, and washers.
000034-04159-0
(Q 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02225-5
REMOVALS
3. Exercise reasonable care against damage to in-place signs during storage and
installation.
4. Remove signs damaged during construction and replace with new signs.
B. Mailboxes:
1. Remove and salvage existing mailboxes that interfere with the work or whose
access is restricted by the construction activities.
2. Place at temporary locations as directed by Engineer.
3. Removal, temporary re-installation, and replacement shall occur such that
mail delivery is not interrupted.
4. Reinstall in locations as shown on Drawings or as directed by Engineer.
5. Mailboxes, posts, and appurtenances damaged during construction shall be
replaced with new at no charge to Owner.
C. Fences:
1. Salvage and store fence and post material where they are in conflict with the
work.
2. After completion of work, reinstall fence to the condition existing prior to
removal.
3. Install temporary snow fence or similar barrier at the end of the working day
while the permanent fence is removed.
D. Retaining Wall:
1. Salvage and store retaining wall materials where they are in conflict with the
work.
2. After completion of work, reinstall retaining wall to the condition existing, or
better, prior to removal.
3.15 SALVAGE AND DELIVER TO OWNER
A. Park Bench (By Others):
1. Remove benches and deliver to New Hope Public Works Facility,
000034-04159-0
(Q 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02225-6
REMOVALS
B. Basketball Post, Hoop, and Backboard (By Others):
1. Remove and deliver to New Hope Public Works Facility.
3.16 FIELD QUALITY CONTROL
A. Salvaged items to be reinstalled shall be ofthe same shape, dimension, location, and
quality of the original item prior to construction.
B. Items damaged during removal or salvaging operations shall be replaced with new
material of equal type and quality of the damaged item when it was new.
3.17 DISPOSING OF MATERIAL
A. Dispose of all materials outside of the Project Site at disposal location selected by
Contractor in compliance with state and local regulations. Burying of material and
debris is not allowed within the Project Site.
3.18 MEASUREMENT AND PAYMENT
A. Bid Items have been provided for removal items. Payment at the Bid Unit Price will
be considered compensation in full for all work necessary to complete the Bid Item in
full, including removal, salvage, storage, disposal, and reinstallation.
B. Measurement will be based upon the units as listed below for items removed,
abandoned, or salvaged complete as specified. No measurement will be made of any
removals that are not required. The actual quantity removed multiplied by the
appropriate Bid Unit Price will be compensation in full for all work and costs of the
following Bid Items:
1. Sawing Bituminous Pavement: Per lineal foot along the saw cut line as
staked.
2. Remove Bituminous Pavement: Per square yard without regard to thickness,
including any integral bituminous curb.
3. Remove Concrete Sidewalk: Per square foot without regard to thickness.
4. Remove Concrete Driveway Pavement: Per square foot without regard to
thickness.
5. Remove Bituminous Driveway: Per square yard without regard to thickness.
6. Remove Concrete Curb and Gutter: Per lineal foot ofthe type specified.
7. Remove CBMH Casting: Per each.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02225-7
REMOVALS
8. Remove Manhole or Catch Basin: Per each.
9. Remove Pipe: Per lineal foot ofthe type specified, measured from center of
junction fittings, catch basins, or manholes.
10. Remove and Replace Monument/Sign/Landscaping: Measurement will be
Lump Sum. Payment at the Bid Unit Price will considered compensation in
full for all work necessary to complete the Bid Item, including:
a. Temporary relocation of the monument/sign to a location where it
will not interfere with vehicular or pedestrian traffic.
b. Temporary transplanting of shrubs surrounding the monument.
c. Salvage of any landscape materials (edging, cover material, etc.).
d. Moving the monument back to the original location.
e. Transplanting of shrubs back to original, permanent locations.
f. Reinstallation oflandscaping materials.
11. Salvage and reinstall signs and mailboxes will be incidental.
C. A Bid Item has been provided for Salvage and Reinstall Hydrant and Gate Valve.
Measurement will be by each salvaged and reinstalled. Payment at the Bid Unit Price
will be considered compensation in full for all work necessary to complete the Bid
Item.
D. A Bid Item has been provided for Salvage and Reinstall Retaining Wall.
Measurement will be by lump sum. Payment at the Bid Unit Price will be considered
compensation in full for all work necessary to complete the Bid Item.
E. All other work and costs of this Section shall be incidental to the Project and
included in the TOTAL BASE BID.
END OF SECTION
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02225-8
REMOVALS
SECTION 02230
SITE CLEARING
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. Removal and trimming of vegetation and trees, and stripping and stockpiling of
sod and topsoil.
1.02 RELATED SECTIONS
A. Section 02315 - Excavation and Fill.
1.03 REFERENCES
A. Minnesota Department of Transportation "Standard Specifications for
Construction," 2000 Edition (MnDOT Spec.):
1. 2101 - Clearing and Grubbing.
2. 2571 - Plant Installation.
1.04 DEFINITIONS
A. Brush: All bushes, shrubs, and other vegetation that can be cut with a brush scythe
or mowing machine, including small isolated trees having a diameter of 4 inches
or less at a point 2 feet above the ground surface.
B. Clearing: Cutting, removing, and disposing of trees, shrubs, bushes, windfalls,
and other vegetation in the designated areas.
C. Grubbing: in the designated areas.
D. Tree Trimming/Pruning: Cutting broken, damaged, or obstructing branches and
installing wound dressing.
E. Remove: Removing and disposing of branches, roots, and other remains.
1.05 PROJECT/SITE CONDITIONS
A. Protect specimen trees close to work that are designated to remain, but may be
damaged by work.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02230-1
SITE CLEARlNG
1.06 SEQUENCING AND SCHEDULING
A. Complete before or sufficiently ahead of on-going rough grading, excavation,
backfill, and compacting for utilities.
B. Install temporary erosion control measures prior to work of this Section.
PART 2 - PRODUCTS
2.01 WOUND DRESSING
A. Asphalt base tree paint.
B. Other acceptable materials per Engineer's approval.
PART 3 - EXECUTION
3.01 GENERAL
A. Review removals in the field with the Engineer prior to doing work.
B. Assume multiple mobilizations for the work of this Section.
C. Stockpile soil to eliminate contamination with other onsite materials.
3.02 CLEARING AND GRUBBING
A. Clearing Trees: Cut off, remove, and dispose of trees and brush in the areas
designated as a clearing operation. When grubbing is not required, the point of cut
off shall be 6 inches above the ground.
B. Clearing Brush: Cut even with the ground surface.
C. Grubbing: Remove brush, stumps, roots, and other remains to a minimum depth
of 6 inches below sub grade for all proposed sections,
D. All depressions resulting from the grubbing operations shall be backfilled in
accordance with Section 02315 - Excavation and Fill.
3.03 TRIMMING AND PRUNING
A. As directed by the Engineer, trim trees that are to be saved but interfere with the
proposed construction. Paint all cuts with wound dressing.
000034-04159-0
~ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02230-2
SITE CLEARING
3.04 STRIPPING
A. After clearing and grubbing have been completed, strip sod and topsoil to a line 2
feet outside of areas to be occupied by structures, walks, roadways, areas to be
excavated or filled, and other areas shown.
B. Stockpile sufficient topsoil to re-spread at a uniform depth of 4 inches to all
disturbed areas identified for seeding or sodding:
1. Do not strip within the drip line (branch spread) of trees identified to
remam.
3.05 DISPOSAL
A. Dispose of all cleared and grubbed material and debris outside the right-of-way at
a location selected by the Contractor, except for trees and logs to be salvaged.
B. Disposal site should be a properly designated landfill area as determined by
appropriate governmental agencies or lands under direct control of the Contractor.
C. Stripped materials not used for embankments shall be disposed off Project Site.
D. On site burial of any debris is not permitted.
3.06 PROTECTION
A. Conduct operations so as not to damage surrounding private property.
B. Protect trees intended to be saved from injury or defacement during operations:
1. Restrict widths of utility trenches.
2. Provide protective bracing, sheeting, or box to insure safe work conditions
as incidental to Contract.
C. Exercise care to keep salvaged material as clean as possible during operations.
D. Install temporary fencing at the construction limits and drip lines of trees to be
protected prior to any construction activities in order to protect vegetation.
3.07 MEASUREMENT AND PAYMENT
A. A Bid Item has been provided for Remove Dogwood Bush. Measurement will be
by physical count of each bush remove. Payment will constitute compensation in
full for all removal, disposal work, and costs.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02230-3
SITE CLEARING
B. A Bid Item has been provided for Clear and Grub. Measurement will be by
physical count of each tree cleared and grubbed having a diameter of more than 4
inches at a point 24 inches above the ground surface. Payment will constitute
compensation in full for all removal, disposal work, and costs.
C. Sod Removal: This work is considered incidental to the other work of the
Contract.
D. Windfal1/Deadfall Removal: This work shall be incidental to the Project with no
direct compensation.
E. Brush Removal: This work shall be incidental to the Project.
F. Stripping and Stockpiling of Soil: This work shall be considered incidental to
other work in the Contract.
G. All other work and costs of this Section shall be incidental to the Project and
included in the TOTAL BASE BID.
END OF SECTION
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02230-4
SITE CLEARING
SECTION 02280
ADmST MISCELLANEOUS STRUCTURES
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. Adjustment of utility structures.
1.02 RELATED SECTIONS
A. Section 02530 - Sanitary Sewer.
B. Section 02630 - Storm Drainage.
C. Section 02740 - Plant Mixed Asphalt Pavement.
1.03 REFERENCES
A. American Society of Testing and Materials (ASTM):
1. A48 - Specification for Gray Iron Casting.
2. C6 - Specification for Normal Finishing Hydrating Lime (Mortar).
3. C141 - Specification for Hydraulic Hydrated Lime for Structural Purposes
(Mortar).
4. C150 - Specification for Portland Cement (Concrete RingslMortar).
1.04 SEQUENCING AND SCHEDULING
A. Contractor, Engineer, and Owner shall inspect all existing structures prior to
beginning construction.
B. Owner will remove any foreign material found in the existing structures prior to
construction. Contractor is responsible for removing any foreign material that enters
the structures during construction,
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02280-1
ADJUST MISCELLANEOUS STRUCTURES
PART 2 - PRODUCTS
2.01 ADmSTING RING
A. Concrete:
1. Size to match cone or opening in top slab.
2. Concrete Compressive Strength: Minimum 3000 psi.
3. Reinforcing: Single hoop 8 gauge steel wire.
4. Thickness: Minimum 2 inches, maximum 6 inches.
2.02 ADHESION MATERIALS
A. Mortar:
1. Standard Portland Cement: Type I, ASTM C150.
2. Normal Finishing Hydrated Lime: ASTM C6.
3. Hydraulic Hydrated Lime for Structural Purposes: ASTM C141.
4. Mix Proportions: 1 part cement to 3 parts mortar sand; lime may be added to
mixture: maximum amount 15 percent by volume.
2.03 CASTINGS
A. Manhole, Catch Basin Frames, and Covers:
1. Requirement: ASTM A48.
2. Material: Class 35 cast iron. Best grade. Free from injurious defects and
flaws.
3. Finish: Coal tar pitch varnish.
4. Finish Preparation: Sandblast.
5. Machine cover and frame contact surface for non-rocking protection.
000034-04159-0
(Q 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02280-2
ADJUST MISCELLANEOUS STRUCTURES
6. Type and Style: NEENAH R1642, Type "B" Lid, or approved equal, for
sanitary and storm sewer manholes, and NEENAH R3067, Type "V" Grate,
or approved equal, for storm sewer catch basin manholes and catch basins.
Covers without grate openings stamped with "SANTI AR Y SEWER" or
"STORM SEWER" as appropriate. Use 2 inch letters.
PART 3 - EXECUTION
3.01 GENERAL
A. The necessary vertical alignment will be determined by the Engineer and generally as
indicated on the schedule of adjustments.
B. Where existing frame is within 0,10 feet of grade, no adjustment is to be made.
C. The frame shall be raised or lowered to match the street or gutter.
D. Protect existing structures from damage.
E. Prevent sand, concrete, or any other debris from entering the structures.
3.02 PREPARATION
A. Call utility owners to field mark their utility locations.
B. Contractor to verify exact location of existing utilities.
3.03 ADmST FRAME AND RING CASTING
. A. Remove all dirt, debris, dust, and other deleterious material from surface prior to
placement of first adjusting ring.
B. Concrete Adjusting Ring:
1. Mortar on top and bottom surfaces of all concrete adjusting rings; between
surface oftop slab or cone and bottom ring; between surface oftop ring and
casting; on entire surface of area of ring with no gaps:
a. Mortar Thickness: 1/4 to 1/2 inch.
2. No shims of any material allowed.
3. Required cross slope of casting to be achieved by varying thickness of mortar.
4. Do not plaster the inside surface of rings.
000034-04159-0
<Q 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02280-3
ADJUST MISCELLANEOUS STRUCTURES
5. Wipe clean all excess mortar from the joints inside all rings and frame.
6. Remove all mortar spills from the structure.
7. Minimum of2, maximum of6 adjusting rings allowed.
8. Use a 6 inch ring where applicable.
3.04 REMOVE EXISTING AND PLACE NEW MANHOLE AND CATCH BASIN FRAME
A. Remove and dispose of frame and casting as indicated on the Drawings.
B. Place new adjustment rings conforming to Section 3.03 - Adjust Frame and Ring
Casting.
C. Install new frame and casting.
D. Patch road to match existing pavement section.
E. Dispose of removed material off Project Site.
3.05 FIELD QUALITY CONTROL
A. For adjustments made within bituminous surfaced areas, any settlements of the
bituminous surface greater than 3/8 inch below the rim of the adjustment structure
will require removal and replacement ofthe bituminous surfacing at the Contractor's
expense.
B. Secure manholes and structures immediately after completion or before suspension of
operations at the end of working day with castings or suitable alternative device.
C. Adjust Manholes and Catch Basin Frames 1/8 inch to 3/8 inch below grade prior to
placing the final wear course. Thorough tamping of the material around manhole and
catch basin frames is required. Where existing frame is within 0.10 feet of grade, no
adjustment is to be made. In such cases the crown or gutter shall be either lowered or
raised, as the case may be, to put the street and frame at the same grade.
D. Adjust frame upward with standard concrete adjustment rings ofthe same size as the
cone or slab opening. Place each adjustment ring and frame in a full mortar bed.
Adjusting rings needed to raise the casting to grade shall be incidental to the
adjustment pay item.
E. Adjust frame downward by removing the necessary number of adjustment rings from
the structure and resetting the frame in a full mortar bed to grade.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik& Associates, Inc.
02280-4
ADJUST MISCELLANEOUS STRUCTURES
F. Regardless of the direction of adjustment, no shims of any material will be allowed.
The minimum thickness of all mortar joints shall be at least 1/4 inch with a
maximum allowable thickness of 1/2 inch. All excess mortar from the joint shall be
wiped clean from the inside of all rings and frame. All manhole castings must be
replaced prior to the placing of the final wear course.
G. Adjust valve boxes to 1/8 inch to 3/8 inch below grade prior to placing the final wear
course. Thorough tamping of the material around the valve box is required. All
valve boxes are the sectional screw-threaded adjustable type.
3.06 MEASUREMENT AND PAYMENT
A. Adjusting Manhole Frame and Ring Casting: Adjustment of the manhole frame and
ring castings in this Contract are considered incidental to the installation of the
manhole.
B. Adjust Catch Basin Frame and Ring Casting: Adjustment of the catch basin frame
and ring castings in this Contract are considered incidental to the installation ofthe
catch basin.
C. Furnish and Install New Casting: A Bid Item has been provided for Furnish and
Install New R3067V CB Casting, Including Adjustment Rings. Measurement will be
by each casting with adjustment rings furnished and installed.
D. All other work and costs of this Section shall be incidental to the Project and
included in the TOTAL BASE BID.
END OF SECTION
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, lnc.
02280-5
ADJUST MISCELLANEOUS STRUCTURES
SECTION 02315
EXCAVATION AND FILL
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. Excavation and fill for roadways, foundations, channels, ponds, and other areas.
1.02 RELATED SECTIONS
A. Section 02225 - Removals.
B. Section 02230 - Site Clearing.
C. Section 02318 - Sub grade Preparation.
D. Section 02320 - Trench Excavation and Backfill.
1.03 REFERENCES
A. Minnesota Department of Transportation "Standard Specifications for
Construction," 2000 Edition (MnDOT Spec.):
1. 2105 - Excavation and Embankment.
2. 3149 - Granular Material.
1.04 SUBMITTALS
A. Submit the following items:
1. Gradation tests for borrow materials.
1.05 DEFINITIONS
A. The definitions of the different classifications of excavation and borrow material
shall conform to MnDOT Spec. 2105.2, or as modified herein:
1. Common Excavation: In locations where the design cross section is in a
cut section, common excavation shall be classified as all excavation above
the grading grade. In areas where the design cross section is in a fill
section, common excavation shall consist of excavation below topsoil
stripping.
000034-04159-0
<<:> 2005 Bonestroo, Rosene,
AnderJik & Associates, Inc.
02315-1
EXCA V A TION AND FILL
1.06 QUALITY ASSURANCE
A. Assist testing laboratory by excavating for density tests. Assist testing laboratory
with obtaining material samples.
1.07 SEQUENCING AND SCHEDULING
A. For the park area, rough grading, including excavation and import of any borrow
materials required, will be performed by others.
B. Perform excavation as soon as possible after sewer and water construction.
C. Complete sub grade for streets, driveways, walks, and parking lots immediately
after trench backfill and compaction.
D. Complete finish grading of turf areas within 5 calendar days after backfill.
PART 2 - PRODUCTS
2.0 1 MATERIALS
A. Salvaged Aggregate:
1. Conform to MnDOT Spec. 3149.2C1.
PART 3 - EXECUTION
3.01 GENERAL
A. Conform to MnDOT Spec. 2105.3A, or modified herein:
1. Establish traffic control prior to excavations.
2. Establish the specified erosion control devices according to Section 01570
- Temporary Erosion and Sediment Control prior to all excavations.
3. Notify utility companies of progress schedule so they can accomplish
relocations, removals, and holding of lines.
4. Perform removals consistent with Section 02225 - Removals.
5. Strip topsoil consistent with Section 02230 - Site Clearing.
000034-04159-0
C9 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02315-2
EXCAVATION AL'1D FILL
3:02 PREP ARATION OF EMBANKMENT
A. Conform to MnDOT Spec. 2105 .3B, or as modified herein:
1. Engineer's approval is required of all areas where preparation work has
been performed prior to the placement of the embankment or fill material.
2. Where embankment is to be constructed over swamp, marsh, or other
locations where the foundation material is unstable, the foundation shall
be excavated to remove all or part of the unstable material.
3.03 EXCAVATION OPERATIONS
A. Conform to MnDOT Spec. 2105 .3C, or as modified herein:
1. Perform excavations to the alignment, cross section, and grade as shown
on the Drawings and staked by the Engineer.
2. Excavation of unstable material below grade shall be done under the
direction of the Engineer as the subsurface conditions are disclosed.
3. Remove muck excavation material by utilizing a backhoe so as to
minimize disruption to the bottom of the excavation.
4. Notify Engineer immediately of any large boulders or ledge rocks
encountered so proper measurement or profile can be made for pay
quantities.
5. No solid rock will be allowed within 12 inches of the subgrade.
6. Provide and maintain temporary drainage facilities until permanent
facilities are completed.
7. After the roadway excavation is complete and prior to backfilling
operations, notify the Engineer 24 hours in advance so all excavation areas
can be cross-sectioned to determine quantities.
8. Cut, fill, and grade Project Site to elevations and contours shown on the
Drawings with allowances for pavements, topsoil, and structures.
3.04 DISPOSITION OF EXCAVATED MATERIAL
A. Conform to MnDOT Spec. 2IOS.3D, or as modified herein:
1. Strip topsoil consistent with Section 02230 - Site Clearing.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02315-3
EXCA V A TION AND FILL
3.05 PLACING EMBANKMENTS
A. Conform to MnDOT Spec. 2105 .3E, or as modified herein:
1. Topsoil placement shall conform to Section 02920 - Lawns and Grasses.
3.06 COMPACTING EMBANKMENTS
A. Conform to MnDOT Spec. 2l05.3F, or as modified herein:
1. Compaction required for embankment materials shall conform to the
Specified Density Method with the testing location and rates being
determined by the Engineer.
3.07 FINISH OPERATIONS
A. Conform to MnDOT Spec. 2105.3G, or as modified herein:
1. Finish grading of sub grade prior to placement of an aggregate base course
shall conform to the following tolerances:
a. Not vary by more than 0.05 feet above or below the prescribed
elevation at any point where a measurement is made.
2. Finish grading of granular material for sub grade prior to placement of an
aggregate base course shall conform to the following tolerances:
a. Not vary by more than 0.10 feet above or below the prescribed
elevation at any point where a measurement is made.
3. Grading of the soils beneath the proposed topsoil shall be reviewed and
approved by the Engineer prior to the start of the topsoil placement.
3.08 MEASUREMENT AND PAYMENT
A. A Bid Item has been provided for Common Excavation. Measurement will be by
volume of material in its original position, based on cross sections performed by
the Engineer, and computed by the average end area method using the original
and final cross sections. The Common Excavation Bid Item includes excavation
and disposal of excavated material off-site.
B. Rough grading in the park area is to be performed by others.
C. All other work and costs ofthis Section shall be incidental to the Project and
included in the TOTAL BASE BID.
END OF SECTION
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02315-4
EXCA V AnoN AND FILL
SECTION 02318
SUBGRADE PREPARATION
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. Grading, shaping, and compacting sub grade prior to placing a base or surface
course.
1.02 RELATED SECTIONS
A. Section 02315 - Excavation and Fill.
1.03 REFERENCES
A. Minnesota .Department of Transportation "Standard Specifications for
Construction," 2000 Edition (MnDOT Spec.):
1. 2105 - Excavation and Embankment.
2. 2111 - Test Rolling.
1.04 SEQUENCING AND SCHEDULING
A. Sub grade preparation shall be performed prior to placement of the aggregate
backfill material if excavation and rough grading of sub grade is not performed
under this Contract.
B. Subgrade preparation shall be performed prior to placement of the concrete curb
and gutter.
C. Complete subgrade for streets, driveways, walks, and parking lots immediately
after installation of pipe as part of trench backfill and compaction.
PART 2 - PRODUCTS
Not Used
PART 3 - EXECUTION
3.01 GENERAL
A. Sub grade preparations shall be performed to produce the required density, grade,
and cross-section.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02318-1
SUBGRADE PREPARATION
3.02 PREPARATION
A. Inspection of subgrade by test rolling conforming to MnDOT Spec. 2111, or as
modified herein:
1. The equipment used for test rolling shall be a Tandom Truck with a gross
weight of 45,000 pounds.
2. The road bed will be considered unstable if yielding and rutting is greater
than 1-112 inch.
3.03 CO:MPACTION
A. Conform to MnDOT Spec. 2105.3F1, or as modified herein:
1. For the Specified Density Method, the Engineer will sample and test the
soils to determine the Maximum Density and Optimum Moisture.
2. Density and moisture tests will be taken on the compacted sub grade at the
location and testing rates designated by the Engineer. Nuclear density
testing shall be considered an approved method.
3.04 FINISH OPERATIONS
A. Sub grade tolerance shall conform to MnDOT Spec. 2105.3G, or as modified
below:
1. Not vary by more than 0.05 feet above or below the prescribed elevation at
any 1 point where a measurement is made.
3.05 MEASUREMENT AND PAYMENT
A. A Bid Item has been provided for Site GradinglFina1 Shaping. Measurement will
be by Lump Sum.
B. Payment at the Bid Unit Price shall include all costs related to performing the
work in accordance with these Specifications, including shaping, grading,
compacting, tolerancing, and test rolling.
C. A Bid Item has been provided for Spread Salvaged Topsoil. Measurement will be
by Lump Sum. Payment will be made for the spreading of the salvaged topsoil
(by others) uniformly with a minimum depth of 4 inches, over the entire park
area.
D. All other work and costs of this Section shall be incidental to the Project and
included in the TOTAL BASE BID.
END OF SECTION
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02318-2
SUB GRADE PREP ARA IrON
SECTION 02320
TRENCH EXCAVATION AND BACKFILL
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. Trenching requirements for underground piping and appurtenances, including
requirements for excavation, backfill, and compaction.
1.02 RELATED SECTIONS
A. Section 02230 - Site Clearing.
1.03 REFERENCES
A. Minnesota Department of Transportation "Standard Specifications for
Construction," 2000 Edition (MnDOT Spec.):
1. 2105 - Excavation and Embankment.
2. 3149 - Granular Material.
B. American Society of Testing Materials (ASTM):
1. D2321 - Recommended Practice for Underground Installation of Flexible
Thermoplastic Sewer Pipe.
1.04 SUBMITTALS
A. Provide the following submittals:
1. Product Data:
a. Each Borrow Material:
1) Name and location of source.
2) Results of gradation tests.
000034-04159-0
~ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02320-1
TRENCH EXCA VA TION
AND BACKFILL
1.05 DEFINITIONS
A. Bedding: The soil material adjacent to the pipe which makes contact with the pipe
foundation, walls of the trench, and upper level of backfill. The purpose of
bedding is to secure the pipe to true line and grade, and to provide structural
support to the pipe barrel.
B. Foundation: Soil material beneath the pipe bedding.
C. Improved Pipe Foundation: Foundation provided by importing material from
sources outside the Project Site. Required when foundation is soft or unstable.
D. Course Filter Aggregate: Free draining mineral product used around draintile
pIpe.
E. Pipe Zone: That part of the trench below a distance of 1 foot above the top of the
pIpe.
1.06 SEQUENCING AND SCHEDULING
A. Uncover utilities and verify both horizontal and vertical alignments sufficiently in
advance of construction to permit adjustments in the work. Determine location of
existing utilities and identify conflicts before excavating trench for pipe
installation.
B, Notify Gopher State One Call before starting construction In a gIVen area,
requesting utility locations in the field.
C. Provide continuance of flow of existing sewer and other facilities.
D. Backfill and compact all trench excavations promptly after the pipe is laid.
1.07 WARRANTY
A. Trench settlements that occur during the correction period and are greater than
1 inch as measured by a 10 foot straight edge will be repaired in a manner
acceptable to the Owner at the Contractor's expense.
000034-04159-0
<<::i 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02320-2
TRENCH EXCA V A TION
At'lD BACKFILL
PART 2 - PRODUCTS
2.01 PIPE BEDDING MATERIAL
A. Polyvinyl Chloride (PVC) Pipe and High Density Polyethylene (HDPE) Pipe:
1. Comply with MnDOT Spec. 3149.2B1 for granular borrow:
a. No onsite granular material encountered during construction may
be used.
b. 1 inch maximum aggregate size.
B. Ductile Iron Pipe (DIP) and Reinforced Concrete Pipe (RCP):
1. Class C-1 Bedding:
a. Undisturbed soil.
2.02 IMPROVED PIPE FOUNDATION MATERIAL
A. Comply with MnDOT Spec. 3149.2H Modified:
1. Crushing Requirements: At least 50 percent of the material by weight
retained on the No.4 sieve shall have 1 or more crushed faces.
2.03 COARSE FILTER AGGREGATE MATERIAL
A. Comply with MnDOT Spec. 3149.2H.
2.04 SAND CUSHION MATERIAL
A. Comply with MnDOT Spec. 3149.2B1 for Granular Borrow:
1. No onsite granular material encountered during construction may be used.
2. 1 inch maximum aggregate size.
2.05 BACKFILL MATERIAL
A. Suitable materials selected from the excavated materials to the extent available
and practical.
B. Suitable materials are mineral soils free of rubbish, trees, stumps, branches,
debris, frozen soil, oversize stone, concrete and bituminous chunks, and other
similar unsuitable material.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02320-3
TRENCH EXCAVATION
AND BACKFILL
PART 3 - EXECUTION
3.01 EXAMINATION
A. Prior to construction, inspect existing utility structures and surface features, and
document condition.
B. Re-inspect foundation soils ifrain fall or snow has occurred after initial inspection
but prior to placing pipe and bedding.
3.02 PREPARATION
A. Notify Utility Owners to field mark their utility locations.
B. Protect as necessary surface features, such as utility poles, trees, structures,
pavement, etc., that are not designated on the Drawings to be removed.
C. Notify utility companies of progress schedule so they can accomplish any
necessary relocations and removals that they have agreed to relocate, remove, or
support.
D. Implement traffic control.
E. Complete temporary removal or relocation of surface features, such as fences,
shrubs, signs, and mailboxes.
F. Strip off existing topsoil within trench excavation limits and stockpile. Separate
vegetative strippings from salvageable topsoil and dispose of appropriately.
G. Crossing Under Existing Utility Lines:
1. Use extreme care when excavating in the vicinity of underground utility
lines to avoid damage to protective coatings or surfaces.
2. Where possible and as authorized by the utility, temporarily remove the
utility line, install the new pipe, and reinstall the utility line.
3. Where existing line cannot be removed or is not feasible to remove,
securely support, excavate under, backfill under and around the utility line
to 100 Percent Standard Proctor Density.
4. Report and repair damaged lines prior to backfilling trench.
000034-04159-0
~ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02320-4
TRENCH EXCA V A IION
AND BACKFILL
3.03 CONSTRUCTION
A. Trench Excavation:
1. Excavate trench to alignment and grade shown on the Drawings.
2. The trench width at the surface may vary and depends on the depth of
trench and nature of the excavated material encountered. However, it shall
be of ample width to permit the pipe to be laid and jointed properly and
the backfill to be placed and compacted properly.
3. Correct any part of the trench that is inadvertently excavated below grade
with approved material compacted to 100 Percent Standard Proctor
Density.
4. Brace, shore, or sheet trench and provide drainage. Comply with
applicable State Regulations relating to industrial safety to a safe angle of
repose. Angle of repose may be no less than that required by the Accident
Prevention Division of the State Industrial Commission or the
requirements of the Occupational Safety and Health Act (OSHA),
whichever is most restrictive.
5. Pile all excavated material in a manner that will not endanger the work or
obstruct sidewalks, driveways, gutters, etc.
6. Segregate soils in the excavated material that are not suitable for trench
backfill and dispose of in a manner that is consistent with the requirements
specified herein under "Backfill Above Pipe Zone."
7. Dispose of excess excavated materials off of right-of-ways and easements
in a suitable site selected by the Contractor.
8. Haul materials, other than natural soil materials that are suitable as backfill
material, to an approved landfill as directed by the Engineer.
B. Water Control:
1. Dewater the ground as necessary to excavate the trench and install the
pipe. All pipe and structures shall be laid in a dry condition prior to
backfill. Maintain groundwater level a minimum of 1 foot below the pipe
invert. Measure the rate of flow from dewatering pumps at the beginning
of the dewatering operation(s) and once per week thereafter. Keep a daily
log of hours pumped.
000034-04159-D
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, lnc.
02320-5
TRENCH EXCA VA TION
AND BACKFILL
C. Trench Bottom:
1. Excavate to a sufficient depth to insure adequate foundation when the
bottom of the trench is soft or where in the opinion of the Engineer
unsatisfactory foundation conditions exist. Bring excavation up to pipe
grade with thoroughly compacted granular materials meeting the
requirements of Improved Pipe Foundation Material.
2. Provide temporary support, remove, relocate, or reconstruct eXlstmg
utilities located within the trench excavation. Utility shall designate
method employed. Use particular care and provide compacted fill or other
stable support for utility crossings to prevent detrimental displacement,
rupture, or failure.
3. Excavate to expose existing utilities that cross in close proximity to the
planned pipe line to determine the utilities' exact location sufficiently
ahead of pipe installation to plan for the avoidance of grade conflict.
Measure to determine the utilities' location relative to the planned pipe line
location. A deviation from the alignment, grade, and location to avoid
conflict may be ordered by the Engineer.
4. In locations where rock affects the pipe foundation, excavate the trench 6
to 12 inches below the pipe and place sand cushion material up to the
proposed invert elevation. The remainder of the trench up to the top of
rock elevation shall be backfilled with granular backfill material meeting
the requirements of Part 2.05.B of this Section:
a. Sand Cushion: The removal and disposal of the unsuitable material
within the trench and below the invert elevation, and the
replacement up to invert elevation with the appropriate bedding
material.
b. Granular Backfill: The removal and disposal of unsuitable material
within the trench, above the invert elevation, and replacement up to
the surface with appropriate backfill material. No additional
compensation will be allowed for wider or deeper trenches in rock
excavations.
c. For PVC and HDPE Pipe, the sand cushion shall be placed to 1
foot above the pipe and shall be paid as pipe bedding. The
remainder of the trench up to the top of the rock shall be backfilled
with granular backfill material.
5. Improved Pipe Foundation: When unsatisfactory foundation conditions
exist, excavate to a depth consisting of solid materials. Fill to pipe grade
with thoroughly compacted granular materials meeting the requirements of
Improved Pipe Foundation Material.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Ander1ik & Associates, Inc.
02320-6
TRENCH EXCA V A TION
Ai"lD BACKFILL
3.04 PIPE BEDDING
A. Polyvinyl Chloride Sewer Pipe: Bed pipe in accordance with ASTM D232 1.
B. Reinforced Concrete Pipe: Bed pipe in accordance with Class C-1 Bedding.
C. Use only selected materials free from rock, boulders, debris, or other high void
content substances to a level 1 foot above the top of pipe. Remove ledge rock,
boulders, and large stones to provide at least 6 inch clearance from pipe.
D. Dig bell holes of ample dimension at each joint such that the pipe barrel rests
continuously on the bedding.
3.05 BACKFILL WITHIN PIPE
A. Backfill immediately after pipe is laid. Restrain pipe as necessary to prevent their
movement during backfill operations.
B. Place material completely under pipe haunches in uniform layers not exceeding 4
inches in depth.
3.06 BACKFILL ABOVE PIPE ZONE
A. Use suitable materials meeting the requirements of Backfill Material.
B. Place in uniform depth layers not to exceed 12 inches before compaction.
Complete the compaction of each layer before placing material for the succeeding
layer.
C. Compact each layer by mechanical means until it meets the requirements of
MnDOT Spec. 2105.3F1 "Specified Density Method." Trenches shall be
compacted to a minimum of 95 percent, except to 100 percent in the upper 3 feet.
D. The method and means of placement and type of compaction equipment used is at
the discretion of the Contractor. However, all portions of the trench backfill must
meet minimum specified compaction requirements.
E. Any deficiency in quantity of backfill material (caused by shrinkage or
settlement) shall be supplied at no additional cost to the Owner.
F. Excavated material not suitable or required for backfill shall be disposed of
outside of the Project Site.
000034-04159-0
~ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02320-7
TRENCH EXCA V A TION
AND BACKFILL
3.07 RESTRlCTED TRENCH WIDTH
A. Restrict width of trench to conform to construction limits indicated on the
Drawings and where directed by the Engineer to prevent damage to specimen
trees or adjacent structures.
B. A trench box is to be used for the installation of the sanitary sewer main and
services to minimize disturbance to surrounding landscaping, driveways, turf, etc.
3.08 FIELD QUALITY CONTROL
A. Density Tests: To be performed by an approved soils testing firm at various
locations and depths throughout the Project Site as directed by the Engineer. The
Contractor shall cooperate fully and provide assistance as necessary to complete
these tests.
B. Failed density test areas shall be excavated and re-compacted until the density
requirements are met.
3.09 MEASUREMENT AND PAYMENT
A. Trench Excavation: Excavation and backfilling of trench and associated pipe
bedding shall be included in the price of pipe provided.
B. Pipe Bedding: Considered incidental and shall be included in the price of pipe
furnished and installed.
C. Temporary Bracing and Sheeting: Considered part of the excavation costs with no
additional compensation to Contractor, unless provided for otherwise.
D. Density Tests:
1. Passing Tests: All costs paid by Owner.
2. Failing Tests: All costs charged to and paid by the Contractor.
E. Dewatering: No explicit, direct payment is made for this work. Include the costs
in the Bid Unit Prices for the pipe or structure installed.
F. All other work and costs of this Section shall be incidental to the Project and
included in the TOTAL BASE BID.
END OF SECTION
000034-04159-0
<<d 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02320-8
TRENCH EXCA V A TION
AND BACKFILL
SECTION 02515
WATER SERVICES
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. Construction of water service pipe, corporation stops, curb stops and boxes, and
all appurtenances.
1.02 RELATED SECTIONS
A. Section 02320 - Trench Excavation and Backfill.
1.03 REFERENCES
A. American Society of Testing and Materials (ASTM):
1. B88 - Class K Copper Water Service Pipe.
1.04 SEQUENCING AND SCHEDULING
A. Install water service after rough grading is complete to ensure adequate cover.
PART 2 - PRODUCTS
2.01 SERVICE PIPE
A. Copper Water Tube: Seamless, Type K water tube conforming to ASTM B88:
1. Fittings shall be designed for working pressures up to 150 psig. Fittings
used in service lines shall be designed for connection to the service line
by threads, brazing, compression, and/or flaring.
2.02 CORPORATION STOP
A. Approved Manufacturers:
1. Mueller, Minneapolis Pattern H-15000.
2. Ford Type F600.
3. Hayes No. 5200.
4. McDonald No. 4701.
000034-04159-0
~ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02515-1
WATER SERVICES
B. Threaded for use with copper service pipe.
C. Threaded on inlet end with standard corporation cock thread.
2.03 CURB STOP
A. Approved Manufacturers:
1. Curb Stops 1 Inch and Smaller:
a. Mueller Oriseal, Minneapolis Pattern H-15151.
b. Ford No. B22.
c. Hayes No. 5155.
d. McDonald No. 4714.
B. Proper connection type for inlet and outlet.
C. Full opening through the valve body with no smaller restriction allowed.
2.04 CURB BOX
A. Approved Manufacturers:
1. Mueller, Minneapolis Pattern H-10388.
2. Hayes: Conforming to Paragraph 2.03.A1a-d.
3. McDonald: Conforming to Paragraph 2.03.A1a-d.
B. Adjustable in height from 78 inches to 90 inches.
C. Stationary rods.
D. 1-114 inch upper section.
E. Mueller, Minneapolis pattern base.
2.05 TRANSITION FITTINGS
A. Polycam steel transition fittings shall conform to A WW A C901.
000034-04159-0
<9 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02515-2
WATER SERVICES
PART 3 -EXECUTION
3.01 INSTALLATION
A. Governing Code: Minnesota Plumbing Code and any local ordinances that may
apply.
B. Preparation: Conform to Section 02320 - Trench Excavation and Backfill.
C. New service shall be connected at the locations shown on the Drawings or as
directed by the Engineer.
D. Water Service Line:
1. Terminate water service as shown on Drawings or as directed by the
Engineer.
E. Corporation Stop:
1. Tap into main only when water main is under pressure.
2. Support corporation with 1/2 cubic yard 1-1/2 inch stabilization rock.
F. Curb Box:
1. Support on full size pre-cast segmental manhole block.
2. Place in a vertical position.
3. Install to finished grade.
G. All trenches shall be backfilled and compacted in accordance to Section 02320 -
Trench Excavation and Backfill.
3,02 FIELD QUALITY CONTROL
A. Do not backfill trench until the service has been inspected and approved by the
Engineer.
3.03 PROTECTION
A. Mark Each Curb Box:
1. Solid 4 inch x 4 inch wood post extending 4 feet above grade.
2. Metal fence post extending 4 feet above grade.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02515-3
WATER SERVICES
3.04 MEASUREMENT AND PAYMENT
A. Water Service Line: Measurement by linear foot of each size and type of pipe
measured along the axis of the pipe, from centerline of the water main to
termination as shown on the Drawings with no regard to intervening fittings.
Payment at the Bid Unit Price per foot shall include cost of all pipe, fittings,
laying, excavation, backfilling, and testing:
1. Placement and compaction of the aggregate material around the
corporation stop and gooseneck is incidental to the service line.
2. Supplying and installing wooden markers or fence a post is incidental to
the service line.
B. Corporation Stop: By physical count of each type installed.
C. Curb Stop and Box: By physical count of each type installed.
D. Material, placement, compaction, and removal of excess trench material to be
included in the Bid Unit Price for Water Service Line.
E. All other work and costs of this Section shall be incidental to the Project and
included in the TOTAL BASE BID.
END OF SECTION
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02515-4
WATER SERVICES
SECTION 02530
SANITARY SEWER
PART 1- GENERAL
1.01 SECTION INCLUDES
A. Sanitary sewer gravity pipe, manholes, fittings, and miscellaneous appurtenances.
1.02 RELATED SECTIONS
A. Section 02225 - Removals.
B. Section 02280 - Adjust Miscellaneous Structures.
C. Section 02320 - Trench Excavation and Backfill.
D. Section 02535 - Sanitary Sewer Services.
1.03 REFERENCES
A. American Society of Testing and Materials (ASTM):
1. A48 - Specification for Gray Iron Castings.
2. A615 - Specification for Deformed and Plain Billet-Steel Bars for Concrete
Reinforcement.
3. C150 - Specification for Portland Cement.
4. C206 - Specification for Finishing Hydrated Lime.
5. C478 - Specification for Precast Reinforced Concrete Manhole Sections.
6. Dl784 - Specification for Rigid Poly (Vinyl Chloride) (PVC) Compounds
and Chlorinated Poly (Vinyl Chloride) (PVC) Compounds.
7. D3034 - Specification for Type PSM Poly (Vinyl Chloride) (PVC) Sewer
Pipe and Fittings.
8. D3212 - Specification for Joints for Drain and Sewer Plastic Pipes Using
Flexible Elastomeric Seals.
9. F477 - Specification for Elastomeric Seals (Gaskets) for Joining Plastic Pipe.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02530-1
SANITARY SEWER
B. Minnesota Department of Transportation "Standard Specifications for Construction,"
2000 Edition (MnDOT Spec.):
1. 3760 - Insulation Board (polystyrene).
1.04 PROJECT SITE CONDITIONS
A. Sanitary sewer lines are shown on the Drawings in a general way. Contractor should
anticipate minor variations in both horizontal and vertical directions in locating
existing system.
1.05 SUBMITTALS
A. Conform to Section 01310 - Proj ect Management and Coordination.
B. Shop Drawings: Indicating information for fabrication and installation of manholes.
C. Manufacture's Certification of Compliance:
1. Precast structures fabrication and installation.
2. Certification of compliance for each diameter and class of pipe.
3. Gray iron castings.
1.06 SEQUENCING AND SCHEDULING
A. Do not pursue work causing shut off of utility services (gas, water, electric,
telephone, TV, etc.) to consumers until the utility owner is contacted and all
consumers are notified of the shut-off schedule.
B. Verify vertical and horizontal location of sanitary sewers sufficiently in advance of
installing new pipe to determine the extent of conflict, if any.
C. Successfully complete required inspections and testing before restoration of surface.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02530-2
Sfu~ITARY SEWER
PART 2 - PRODUCTS
2.01 MATERIALS
A. Concrete Materials:
1. Standard Portland Cement Type 1, clean washed sand, crushed rock, and
gravel free from deleterious materials for monolithic concrete manholes and
all manhole bases.
2. Portland Cement: Comply with the requirements of ASTM C150.
3. Design Mix: Subject to the approval of the Engineer. Use proper water-
cement ratio to obtain (4000 psi) in 28 days.
B. Mortar Materials:
1. Cement: Type 1 Standard Portland Cement conforming to ASTM C150.
2. Lime: Normal fInishing hydrated lime meeting requirements of ASTM C206.
3. Mix Proportions:
a. 1 part cement to 3 parts of suitable plaster sand for mortar used for
plastering the exterior walls of block manholes, catch basins,
adjusting rings, and lift holes. Use lime or mortar mix in the amount
necessary to make a suitable mixture for plastering purposes, but not
to exceed 15 percent by volume.
b. 1 part Portland cement to 2 parts of sand to which lime or mortar mix
may be added but not to exceed 15 percent by volume for mortar used
for laying concrete block.
4. Reinforcing Steel: Comply with the requirements ofASTMA615, Grade 60.
2.02 MANHOLES
A. Precast concrete sections conforming to ASTM C478.
B. Joints: Rubber o-ring gasket type, or approved equal.
C. Structure Bases:
1. Pre-cast integral with bottom section of manhole.
2. Pre-cast invert.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02530-3
SANITARY SEWER
D. Manhole Steps: Reinforced polypropylene plastic steps with No.2 deformed grade
steel rod:
E. Pipe Connections:
1. All manholes shall be fabricated with pipe openings consisting of a rubber
boot and stainless steel band to seal off the joint from allowing dirt, ground
water, or other objectionable material from entering. These materials shall be
installed with the fabrication on all new manholes.
2.03 MANHOLE FRAMES AND COVERS
A. Requirement: ASTM A48, Class 35C.
B. Finish: Coal tar pitch varnish.
C. Finish Preparation: Sandblast.
D. Machine cover and frame contact surface for non-rocking protection.
E. Type and Style: As shown on Drawings.
F. Covers with 2 concealed pick holes of approved design.
G. Weight: Minimum of380 lbs.
2.04 PIPE MATERIAL
A. PSM Poly (Vinyl Chloride) (PVC) Plastic Pipe and Fittings (4 Inch Through 15 Inch
Diameter):
1. General: Pipe and fittings conform to ASTM D3034.
2. Materials: PVC plastics having a minimum Cell Classification of 12454B,
12454C, or 13364B as defined in ASTM Dl784, Pipe materials shall have a
minimum hydrostatic design stress of2,000 psi as certified by the Plastic Pipe
Institute. Additives and fillers, including but not limited to stabilizers,
antioxidants, lubricants, colorants, etc., shall not exceed 20 parts by weight
per 100 ofPVC resin in the compound.
3. Design: Integral wall bell and spigot j oint, and a minimum wall thickness
conforming to SDR 35 and/or SDR 26.
000034-04159-0
<9 2005 Bonestroo, Rosene,
Anderlik & Associates, lnc.
02530-4
SANITARY SEWER
4. Joints: Conform to ASTM D3212. Push-on type only with the bell-end
grooved to receive a gasket. Elastomeric Seal (Gasket): A basic polymer of
synthetic rubber conforming to ASTM F477. Natural rubber gaskets will not
be accepted.
5. Marking: Each pipe shall be identified with the name ofthe manufacturer, or
trademark and code, nominal pipe size in inches, the PVC cell classification,
and "Specification D3034."
2.05 INSULATION
A. Conform to the requirements of MnDOT Spec. 3760 for Polystyrene Insulation
Board.
PART 3 - EXECUTION
3.01 PREPARATION
A. Excavation and Preparation of Trench: Conform to Section 02320 - Trench
Excavation and Backfill.
B. The use of a trench box for the installation along Quebec Avenue North will be
required to minimize disturbance to existing surface features.
C. By-Pass Pumping: Contractor shall be responsible for all items required to maintain
sewer flows during construction of the new sanitary sewer line. All work and costs
for this are considered incidental to the Project, unless otherwise specified.
3.02 INSTALLATION
A. Connect to Existing System:
1. Connect to Existing Structure:
a. Connect to existing structure at location shown on the Drawings.
b. Core the hole in the structure, trimming the pipe flush with the
structure, trimming the pipe flush with the pipe to seal it within the
wall.
c. Reconstruct manhole bench/invert if required.
d. Make repairs to the structure.
000034-04159-0
(Q 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02530-5
SANITARY SEWER
2. Connect to End of Existing Pipe (Stub):
a. Locate and expose end of existing stub.
b. Remove existing plug and connect to pipe.
B. Pipe Installation:
1. Excavation and Preparation of Trench: Conform to Section 02320 - Trench
Excavation and Backfill.
2. Lay and maintain pipe and appurtenances to the alignment, grade, and
location shown on the Drawings and/or staked in the field. No deviation from
the Drawing and/or staked alignment, grade, or location is allowed, unless
approved by the Engineer. Deviation from grade in excess of 0.05 percent
may be cause for removal and relaying pipe at the Contractor's expense.
3. General Pipe Installation Procedure: Use joint lubricant in accordance to
manufacturer's instructions. Lubricate joint, center spigot in bell, push spigot
home, bring pipe to proper line and grade, and secure pipe in place by
properly bedding.
4. Lay pipe upgrade with spigot ends pointing in the direction of flow.
5. Plug all openings to the installed pipe with suitable stoppers to prevent water,
dirt, and debris from entering the sewer.
6. Remove all foreign matter or dirt from interior of each pipe length as the
work progresses. Keep the bell and spigot clean during and after installation.
Take care to prevent dirt from entering the joint space. Remove any
superfluous material from inside the pipe after pipe installation by means of
an approved follower or scraper.
7. All joints must be watertight. Repair any leaks discovered.
C. Installing Structures and Appurtenances:
1. Furnish and install structures in accordance with Detail Plates as shown on
the Drawings.
2. Place precast integral base section on compacted sub grade.
3. Set precast concrete sections plumb with a 1/4 maximum out of plumb
tolerance allowed.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, lnc.
02530-6
SANITARY SEWER
4. Install short precast section (maximum 16 inch height) immediately below
the eccentric cone or precast top slab.
5. Position vertical wall of the eccentric cone on the downstream side.
6. Steps:
a. Locate over downstream pipe, except for pipe 24 inches in diameter
or greater. Then place where most appropriate to provide the most
suitable access.
b. Secure and neatly mortar in place 15 inches on center spacing.
7. Install Rings and Adjust Structure: Conform to Section 02280 - Adjust
Miscellaneous Structures.
8. Neatly mortar lift holes.
9. All pipes entering the manhole must be cut with a power saw to provide a
clean, smooth pipe surface.
D. Installation of Insulation:
1. Insulation is to be placed wherever sanitary sewer line comes within 3
feet of any storm structure or line, or within 5 feet of the ground surface.
3.03 PROTECTION
A. Plug all entrances and openings to the system promptly and before suspension of
operations at the end of working day.
B. Secure manholes and structures immediately after completion or before suspension of
operations at the end of working day with casting or suitable alternative device.
C. Mark structure susceptible to being hit by construction or vehicular traffic.
3.04 FIELD QUALITY CONTROL
A. Scope:
1. Provide all labor, materials, and equipment to perform tests.
2. Engineer to observe and verify all tests and to visually inspect the final work
for compliance.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02530-7
SANITARY SEWER
B. Cleanup:
1. Clean pipe and all structures:
a. If newly installed mains and structures are kept clean during
construction, cleaning will not be required.
b. If newly installed mains and/or structures become dirty due to
negligence of the Contractor, cleaning will be performed at the sole
expense of the Contractor.
2. The bailing or flushing method of cleaning pipe is acceptable only if adequate
provisions, acceptable to the Engineer, for keeping dirt and debris out ofthe
existing sewer system or ponds are employed. Jetting may be required.
3. Complete prior to final inspection for acceptance.
C. Tests and Inspections:
1. Commence test procedures only when pipe and structures are clean and free
of dirt, water, or other foreign matter, and for buried pipe, trench has been
backfilled.
2. Lamping: Engineer will verify installation for true line and grade, joints are
home, no broken or deflective pipes exist, the installed pipe is structurally
sound, and that the structures conform to the specified requirements.
3. Deflection Testing: Required for all flexible pipe (CCF, PVC, and HDPE).
Deflection testing shall be conducted at least 30 days after the pipe has been
backfilled to the desired finish grade. Deflection testing shall be done in the
presence of the Engineer:
a. Pipe Diameters Through 24 Inches: Deflections shall be determined
by pulling mandrel through the sewer main.
b. Mandrel Requirements: The mandrel shall have a minimum diameter
equal to 95 percent ofthe average internal diameter ofthe pipe. The 5
percent deflection allowance shall include both deflection occurring
after burial and deformation which occurs as a result of the
manufacturing process, shipping, and pipe storage:
1) The Average Internal Diameter shall be determined as
specified below:
a) Average Internal Diameter = (Average Outside
Diameter) minus 2 x (Minimum Pipe Wall
Thickness).
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02530-8
SANITARY SEWER
000034-04159-0
(Q 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
b) The Average Outside Diameter will be computed as
the average of 16 Project Site field measurements of
the pipe prior to installation. 4 outside diameter
measurements will be made on each of 4 lengths of
the particular diameter pipe to be tested.
Measurements shall be made by the Contractor in the
presence of the Engineer.
c) No adjustments to the average internal diameter will
be allowed for out-of-roundness, diameter variation,
or thickness variation due to manufacture, shipping,
and handling.
2) Mandrel shall be constructed of rigid steel, be non-adjustable,
and have an odd number of legs (9 legs minimum). Its
effective length shall not be less than its nominal diameter.
3) Deflection Template/Bar Requirements:
a) The circular template diameter (or rigid bar length)
shall be equal to the average internal diameter as
determined in Articles 3.4.C. 2.
b) Circular templates shall be constructed of rigid
materials and be non-adjustable.
c) Rigid bars shall have a 1 inch diameter circular
section, be constructed of steel, and be non-adjustable.
c. Owner reserves the right to measure the deflection of all flexible pipe
at any time during the correction period. Deflections greater than
5 percent of the inside diameter of the pipe shall be considered
failure. Contractor may be required to re-excavate the trench, re-
compact the backfill material, and restore the surface with no
additional compensation for such work.
02530-9
SANITARY SEWER
4. Low Pressure Air Test:
a. Must meet criteria set forth in ASTM C924 and ASTM F1417.
b. Pipe shall be cleaned but may be wetted. Pneumatic balls shall be
used to plug the ends at manholes. Low-pressure air shall be
introduced into plugged line until the internal air pressure reaches
4.0 psig greater than the average back pressure of any groundwater
pressure that may submerge the pipe. At least 2 minutes shall be
allowed for the pressure to stabilize before readings are taken and the
timing started. During this time, check all plugs with soap solution to
detect plug leakage. If any plugs are found to leak, air shall be bled
off, the plugs shall be retightened, and the air shall be reintroduced
into the line.
c. The sewer line under test will be accepted as having passed the air
test, ifthe pressure does not drop more than 0.6 psig in less time than
1/2 minute per inch in diameter of the pipe being tested. The
minimum starting pressure is 3.6 psig.
3.05 MEASUREMENT AND PAYMENT
A. Bid Items have been provided for Sanitary Sewer Pipe. Measurement will be based
upon units of lineal feet for each size and type for furnishing and installing pipe
complete in place as specified, including excavation, backfilling, and compaction.
Pipe will be measured from centerline to centerline of manholes or to the connection
point of the existing pipe:
1. PVC pipe bedding will be paid in accordance with Section 02320 - Trench
Excavation and Backfill.
2. Improved pipe foundation material, if necessary, shall be per Section 02320
- Trench Excavation and Backfill.
B. A Bid Item has been provided for 4 Foot Diameter Sanitary Sewer Manhole.
Measurement will be per each manhole. Payment will include the manhole, manhole
frame and casting, and adjusting rings in place as specified on the Drawings.
C. A Bid Item has been provided for Core Drill Connection to Existing Manhole,
Measurement shall be on the basis of each and shall be considered to include all
excavation, labor, materials, and equipment necessary make the required connection,
including core drilling and reconstructing bench/invert.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02530-10
SANITARY SEWER
D. A Bid Item has been provided for Connect to Existing Sanitary Sewer Pipe.
Measurement shall be on the basis of each and shall be considered to include all
excavation, labor, materials, and equipment necessary to make the required
connection, including removal of existing plug.
E. All other work and costs of this Section shall be incidental to the Project and
included in the TOTAL BASE BID.
END OF SECTION
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02530-11
SANITARY SEWER
SECTION 02535
SANlTARY SEWER SERVICES
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. Sanitary sewer service pipe replacement and all appurtenances,
1.02 RELATED SECTIONS
A. Section 02320 - Trench Excavation and Backfill.
B. Section 02530 - Sanitary Sewer.
1.03 REFERENCES
A. American Society of Testing Materials (ASTM):
1. D 1784 - Specification for Rigid Poly (Vinyl Chloride) (PVC) Compounds
and Chlorinated Poly (Vinyl Chloride) (PVC) Compounds.
1.04 SYSTEM DESCRIPTION
A. This work shall consist of the construction of sanitary sewer services in accordance
with the requirements ofthe Contract.
B. It is the intent ofthese Specifications to require the same quality of work be received
on the house services in the way of grade and alignment, and shall be required on the
main lines and laterals.
1.05 SUBMITTALS
A. Submit to Engineer for each service: Depth of service record, location of connection,
and length of service lines.
1.06 PROJECT SITE CONDITIONS
A. Verify sanitary sewer service locations prior to the start of any construction. Existing
service locations are taken from record plans and have not been confirmed.
1.07 SEQUENCING AND SCHEDULING
A. Install sanitary sewer and all pipe deeper than the services prior to the installation of
the services.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02535-1
SANITARY SEWER SERVICES
PART 2 - PRODUCTS
2.01 MANUFACTURED UNITS
A. PSM Poly (Vinyl Chloride) (PVC) Plastic Pipe and Fittings (4 Inch Through 15 Inch
Diameter):
1. General: Pipe and fittings conform to ASTM D3034.
2. Materials: PVC plastics having a minimum Cell Classification of 12454B,
12454C, or 13364B as defined in ASTM D1784. Pipe materials shall have a
minimum hydrostatic design stress of2,000 psi as certified by the Plastic Pipe
Institute. Additives and fillers, including but not limited to stabilizers,
antioxidants, lubricants, colorants, etc., shall not exceed 20 parts by weight
per 100 ofPVC resin in the compound. Certification of resin compounding
shall be provided by the pipe manufacturer prior to shipment to the Project
Site.
3. Design: Integral wall bell and spigot joint and a minimum wall thickness
conforming to SDR 26 and as shown on the Drawings.
4. Joints: Conform to ASTM D3212. Joints shall be push-on type only with the
bell-end grooved to receive a gasket. Elastomeric seal (gasket) shall have a
basic polymer of synthetic rubber conforming to ASTM F477. Natural
rubber gaskets will not be accepted.
5. Marking: Each pipe shall be identified with the name of the manufacturer or
trademark and code, nominal pipe size in inches, the PVC cell classification,
and "Specification D3034."
2.02 BEDDING MATERIAL
A. See Section 02320 - Trench Excavation and Backfill.
PART 3 - EXECUTION
3.01 INSTALLATION
A. Governing Code: Minnesota Plumbing Code and any local ordinances which may
apply.
B. Minimum 1/4 inch per foot grade, unless otherwise directed by the Engineer.
C. PVC Pipe and Fittings:
1. Similar to main line sanitary sewer pipe installation.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02535-2
SANITARY SEWER SERVICES
D. Proposed service line locations are shown on the Drawings.
E. Record Actual Depth and Station at End of Service:
1. Exercise care in determining the depth.
2. The depth recording is incorporated into the ''Record Drawings" and becomes
a permanent part of City Records.
3.02 FIELD QUALITY CONTROL
A. Do not backfill trench until the service has been inspected and approved by the
Engineer.
3.03 PROTECTION
A. Mark location of new service connection with a wooden 2 inch x 2 inch x "variable"
marker.
3.04 MEASUREMENT AND PAYMENT
A. A Bid Item has been provided for 4 Inch PVC, SDR 26 Service Pipe. Measurement
will be by linear foot of each size and type of pipe installed as measured along the
axis ofthe pipe with no regard to intervening fittings. Payment at the Bid Unit Price
shall be compensation in full for all work and costs, including excavation, pipe,
bedding, backfill, and trench compaction.
B. A Bid Item has been provided for Connect to Existing Sewer Service. Measurement
and Payment will be per Each connection made, including any fittings required.
C. A Bid Item has been provided for Bulkhead Existing Sanitary Sewer Service,
Measurement and Payment will be per each service pipe bulkheaded with non-shrink
concrete grout.
D. All other work and costs of this Section shall be incidental to the Project and
included in the TOTAL BASE BID.
END OF SECTION
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02535-3
SANITARY SEWER SERVICES
SECTION 02630
STORM DRAINAGE
PART 1- GENERAL
1.01 SECTION INCLUDES
A. Storm sewer pIpe, manholes, catch basins, fittings, and miscellaneous
appurtenances.
1.02 RELATED SECTIONS
A. Section 01570 - Temporary Erosion and Sediment Control.
B. Section 02280 - Adjust Miscellaneous Structures,
C. Section 02315 - Excavation and Fill.
D. Section 02320 - Trench Excavation and Backfill.
E. Section 02635 - Subsurface Drainage.
F. Section 02720 - Aggregate Base Course.
G. Section 02770 - Concrete Curb and Gutter.
1.03 REFERENCES
A. American Society of Testing and Materials (ASTM):
1. A48 - Specification for Gray Iron Castings.
2. C76 - Specification for Reinforced Concrete Culvert, Drain, and Sewer
Pipe.
3. C139 - Specification for Concrete Masonry Units for Construction of
Catch Basins and Manholes.
4. C150 - Specification for Portland Cement.
5. C206 - Specification for Finishing Hydrated Lime.
6. C361 - Specification for Reinforced Concrete Low Head Pressure Pipe.
7. C443 - Specification for Joints for Circular Concrete Sewer and Pipe,
Using Rubber Gaskets.
000034-04159-0
<<:i 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02630-1
STORM DRAINAGE
8. C478 - Specification for Precast Reinforced Concrete Manhole Sections.
B. Minnesota Department of Transportation "Standard Specifications for
Construction," 2000 Edition (MnDOT Spec.):
1. 2511 - Rip Rap.
2. 3601 - Rip Rap Materials.
3. 3733 - Geotextiles.
1.04 SEQUENCING AND SCHEDULING
A. Do not pursue work-causing shut off of utility service (gas, water, electric,
telephone, TV, etc.) to consumers until the utility owner is contacted and all
consumers are notified of the shut-off schedule.
B. Successfully complete required inspections and tests before commencement of
Aggregate Base Course - Section 02720 and Concrete Curb and Gutter - Section
02770.
1.05 SUBMITTALS
A. Conform to Section 01310 - Proj ect Management and Coordination.
B. Shop Drawings:
1. All storm sewer structures.
C. Manufacturer's Certificate of Compliance for:
1. Gray iron castings.
2. Precast manhole sections.
3. Rip rap.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik '& Associates, Inc.
02630-2
STOR.1"vf DRAINAGE
PART 2 - PRODUCTS
2.01 MATERIALS
A. Mortar Materials:
1. Cement: Use Type 1 Standard Portland Cement conforming to ASTM
C150.
2. Lime: Use normal finishing hydrated lime meeting the requirements of
ASTM C206.
3. Mix Proportions:
a. One (1) part cement to 3 parts of suitable plaster sand for mortar
used for plastering the exterior walls of block manholes and catch
basins, adjusting rings, and lift holes. Use lime or mortar mix in
the amount necessary to make a suitable mixture for plastering
purposes, but not to exceed 15 percent by volume.
b. One (1) part Portland cement to 2 parts of sand to which lime or
mortar mix may be added, but not to exceed 15 percent by volume
for mortar used for laying concrete block.
2.02 STORM MANHOLE AND CATCH BASIN FRAMES AND COVERS
A. General:
1. Requirement: ASTM A48.
2. Material: Class 35 cast iron. Best grade. Free from injurious defects and
flaws.
3. Type and Style: As shown on Drawing. Covers without grate openings
shall be stamped "STORM SEWER."
4. Covers with 2 concealed pick holes of approved design.
5. Weight: Minimum of380 lbs.
2.03 STORM MANHOLES AND CATCH BASINS
A. General:
1. Requirements: ASTM C478, details on the Drawings.
2. Diameter and special requirements are shown on the Drawings.
000034-04159-0
~ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02630-3
STORM DRAINAGE
3. Structures shall be of precast concrete.
4. Manhole Joints: Rubber o-ring gasket type meeting ASTM C443.
5. Structure bases shall be pre-cast.
6. Manhole Steps: Reinforced polypropylene plastic steps with No. 2
deformed grade steel rod.
2.04 PIPE MATERIALS
A. Reinforced Concrete (RCP) Pipe and Fittings:
1. General Requirement: ASTM C76, Wall B with circular reinforcing.
2. Materials: Conform to the requirements of ASTM C76, Wall B with
circular reinforcing. O-ring gaskets shall be synthetic rubber, circular
reinforcing in cross-section, and shall conform to ASTM C361.
3. Pipe Joints: Bell and spigot ASTM C361.
4. Pipe Class: As shown on the Drawings.
5. Marking: Each pipe shall be identified with the name of the manufacturer
trade name or trademark and code, identification of plant, date of
manufacture, and the pipe class and specification design.
2.05 RIP RAP
A. General Requirement: Conform to MnDOT Spec. 2511:
1. Riprap Materials: Conform to MnDOT Spec. 3601.
2. Granular Filter: Conform to MnDOT Spec. 3601.
3. Geotextile Filter: Conform to MnDOT Spec. 3733.
4. Grout: Conform to MnDOT Spec. 2461.
000034-04159-0
i!:l 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02630-4
STORM DRAINAGE
PART 3 - EXECUTION
3.01 PREPARATION
A. Trench Excavation and Backfill shall conform to Section 02320 - Trench
Excavation and Backfill.
B. By-Pass Pumping: Contractor responsible for all items required to maintain sewer
flows during construction ofthe new storm sewer. All work and costs for by-pass
pumping is considered incidental to the Proj ect, unless otherwise specified.
3.02 INSTALLATION
A. Connect Existing Pipe to Structure:
1. Connect existing pipes to new structures at locations shown on the
Drawings.
2. Remove sections of pipe as necessary to install new structure.
a. Take care not to damage existing pipe.
b. Any segment of pipe damaged by Contractor shall be replaced with
new materials at no expense to the Proj ect.
3. Reinstall pipe sections, connecting to new structure.
4. Use a new standard bell and spigot joint with rubber o-ring gasket if
existing is damaged during removal or reinstallation.
5. If butt connection must be made, and approved by Engineer, construct
concrete collar around joint. Collar shall be minimum 12 inches thick in
all locations and extend a minimum of 12 inches each way of the joint.
B. Pipe Installation:
1. Lay and maintain pipe appurtenances to the alignment, grade, 'and location
shown on the Drawings and/or staked in the field. No deviation from the
Drawing and/or staked alignment, grade, or location is allowed, unless
approved by Engineer. Deviation from grade in excess of 0.05 percent
may be cause for removal and relaying pipe at the Contractor's expense.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02630-5
STORL\1 DRAINAGE
2. General Pipe Installation Procedures:
a. Wipe joints clean; apply the manufacturer's recommended
lubricant compound over the entire joint surface; center spigot in
bell and push spigot home; take care to prevent dirt from entering
the joint space; bring pipe to proper line and grade, and secure pipe
in place by properly bedding.
3. Lay pipe upgrade with spigot ends pointing in the direction of flow.
4. All joints must be watertight.
5. Remove all foreign matter or dirt from inside the pipe. Keep the bell and
spigot clean during and after installation. Take care to prevent dirt from
entering the joint space. Remove any superfluous material from inside the
pipe after pipe installation by means of an approved follower or scraper.
6. Where cut-ins make it impossible to construct bell and spigot joints or
when dissimilar pipe materials are joined, a reinforced concrete collar
shall be placed completely surrounding the joint or the connection shall be
made by using an approved adapter.
7. Any pipe which has been disturbed after being laid must be taken up, the
joint cleaned, and properly relaid as directed by the Engineer.
C. Structures and Appurtenances Installation:
1. Furnish and install structures in accordance with the Drawings.
2. Excavate to depth and size as shown in the Drawings.
3. Pour inverts shaped to the half section of equivalent size pipe conforming
to the inlet and outlet pipe so as to allow for a free, uninterrupted flow
with all surfaces sloping to the flow line.
4. Preformed inverts not allowed where pipe grades are 2 percent or greater,
unless design grade is built through the manhole.
5. All concrete pipes entering manholes must be cut with a concrete saw.
6. Steps:
a. Locate on the downstream side, except for pipe 24 inches in
diameter or greater. Then place where most appropriate to provide
the most suitable access.
b. Secure and neatly mortar in place 15 inches on center spacing.
000034-04159-0
~ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02630-6
STORM DRAINAGE
7. Position vertical wall of the eccentric cone on the downstream side.
8. On structures with a build that contains more than 1 barrel section, the
section immediately below the precast top slab shall be maximum 16 inch
height.
9. Lift holes neatly mortared up.
10. Install Adjustment Rings and Adjust Casting: Conforming to Section
02280 - Adjust Miscellaneous Structures.
D. Construct Manhole Over Existing Pipe:
1. Construct manhole over existing pipe at locations shown on the Drawings.
2. Saw cut existing pipe to fit flush with inside wall of new structure.
3. Seal any openings in manhole.
E. Riprap:
1. General: Conform to MnDOT Spec. 2511.
F. Bulkhead Structure:
1. Bulkhead opening in structure at locations shown on Drawings with brick,
non-shrink concrete grout, or concrete block masonry 8 inches thick.
2. Precast concrete plugs may be used in lieu of bulkhead. Plug must fit
snugly into pipe opening and be watertight.
3.03 FIELD QUALITY CONTROL
A. Scope:
1. All pipeline testing is considered incidental to the Bid cost of the pipe.
2. Engineer to observe and verify that all tests and visual inspections have
been completed prior to final acceptance.
B. Cleaning:
1. Consists of Cleaning the Pipe and Structures:
a. If newly installed mains and structures are kept clean during
construction, cleaning will not be required.
000034-04159-0
(Q 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02630-7
STORM DRAINAGE
b. If newly installed mains and/or structures become dirty due to
negligence of the Contractor, cleaning will be performed at the
sole expense of the Contractor.
2. The bailing or flushing method of cleaning pipe is acceptable only if
adequate provisions acceptable to Engineer for keeping dirt and debris out
of the existing sewer system are employed. Jetting may be required.
3. Complete prior to fmal inspection for acceptance.
C. Required Tests and Inspections:
1. Infiltration:
a. To determine the amount of ground water infiltration into sewers.
b. Test waived if no visible infiltration is observed during the
lamping inspection.
c. Measurement made by means of 90 degree v-notch weirs placed in
the lines as directed by the Engineer.
d. Measurements taken at the points where in the Engineer's opinion
the flow of water in the sewer is greater than the maximum
allowable leakage.
e. Maximum Allowable Rate of Leakage: Not more than 100 gallons
per mile per inch diameter per day.
f. Tests may be taken between individual manholes and the
infiltration in any given line must not exceed the specified
maximum allowable rate.
g. Method of Measurement: Measurement of time for a
predetermined volume of flow to occur.
2. Lamping:
a. Verify installation is to true line and grade,
b. Verify installed pipe is structurally sound.
c. Verify there are no broken or deflective pipe.
d. Verify that joints are all home.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02630-8
STORM DRAINAGE
e. Verify structures conform to specified requirements.
3.04 PROTECTION
A. Plug all entrances and openings to the system promptly and before suspension of
operations at the end of working day.
B. Secure manholes and structures immediately after completion or before
suspension of operations at the end of working day with castings or suitable
alternative device.
C. Mark all structures to avoid being hit by construction or vehicular traffic.
D. Mark each plug location with 4 inch x 4 inch timbers to above grade to aid in
marking the future connection.
E. Establish erosion control measures as per Section 01570 - Temporary Erosion
and Sediment ControL
3.05 MEASUREMENT AND PAYMENT
A. Bid Items have been provided for Storm Sewer Pipe. Measurement will be based
upon units of lineal feet for each size, type, and class of pipe furnished and
installed complete in place as specified, including excavation, backfilling, and
compaction. Pipe will be measured from centerline of structure to centerline of
structure:
1. Pipe bedding will be paid in accordance with Section 02320 - Trench
Excavation and BackfilL
2. Improved pipe foundation material, if necessary, shall be per Section
02320 - Trench Excavation and BackfilL
B. Bid Items have been provided for Storm Catch Basin, Storm Catch Basin
Manhole and Storm Manhole. Measurement will be based upon units of each,
according to type and size for furnishing and installing structures complete,
including casting frame and cover, and adjusting rings in place as specified.
C, A Bid Item has been provided for Connect Existing Storm Sewer Pipe to
Structure. Measurement shall be per each connection made. Payment will include
all costs related to making the connection, including removal and reinstallation of
existing pipe, and construction of concrete collar if necessary.
D. A Bid Item has been provided for Bulkhead Existing Structure. Measurement will
be per each bulkhead installed. Payment will include all costs related to
bulkheading or plugging the structure as described in this Section.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02630-9
STORM DRAINAGE
E. All other work and costs of this Section shall be incidental to the Project and
included in the TOTAL BASE BID.
END OF SECTION
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02630-10
STORM DRAINAGE
SECTION 02635
SUBSURFACEDRAJNAGE
PART I-GENERAL
1.01 SECTION INCLUDES
A. Drain tile.
1.02 RELATED SECTIONS
A. Section 02320 - Trench Excavation and Backfill.
B. Section 02630 - Storm Drainage.
1.03 REFERENCES
A. American Society of Testing and Materials (ASTM):
1. D1248 - Polyethylene Plastics Molding and Extrusion Materials.
B. American Association of State Highway and Transportation Officials (AASHTO):
1. M252 - Corrugated Polyethylene Drainage Tubing (3 Inch to 10 inch).
C. Minnesota Department of Transportation "Standard Specifications for
Construction," 2000 Edition (MnDOT Spec.):
1. 3149 - Granular Material.
2. 3733 - Geotextiles.
P ART 2 - PRODUCTS
2.01 POLYETHYLENE PIPE
A. General Requirements: High-density polyethylene corrugated exterior/smooth
interior pipe meeting AASHTO M252.
B. Material: Meet ASTM D1248, Type III, Category 4, Grade P33, Class C.
C. Coupling bands shall cover at least 1 full corrugation on each section of pipe. Pipe
fittings shall conform to AASHTO M252.
D. Perforated wall.
000034-04159-0
(Q 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02635-1
SUBSURFACE DRAINAGE
E. Geotextile Wrap of Fabric: Non-woven, spun-bonded polypropylene, or spun-
bonded nylon.
2.02 BEDDING MATERIAL
A. Granular Borrow meeting MnDOT Spec. 3149 .2B 1 Modified:
1. One hundred (100) percent passing by weight the 1 inch sieve.
2. Furnished by Contractor from a location located off the Project Site.
3. No onsite granular material encountered during construction may be used.
2.03 PIPE DRAIN AGGREGATE
A. Course Filter Aggregate conforming to MnDOT Spec. 3149.2H.
2.04 GEOTEXTILE
A. Geotextile Wrap shall conform to MnDOT Spec. 3733, Type 1.
PART 3 -EXECUTION
3.01 GENERAL
A. The location and alignment of the subsurface drains and outlets are shown in a
general manner on the Drawings. Exact location and alignment to be determined
by the Engineer.
3.02 DRAIN TILE INSTALLATION
A. Construct at locations and elevations determined by Engineer or as shown on the
Drawings.
B. Pipe Bedding: Drain pipe aggregate.
C. Grade: Unless otherwise specified or shown on the Drawings, the grade of pipes
shall not be flatter than 1 in 250.
E. Plug upstream end of the drain pipe.
F. Sections of the drain pipe shall be firmly joined.
G. If perforated drain pipe is used, the pipe shall be placed so that the perforations
are in the position indicated on the Drawings or designated by the Engineer.
H. Compaction: Conform to Section 02320 - Trench Excavation and Backfill.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02635-2
SUBSURFACE DRAINAGE
I. Flushing: After installation has been completed, pipes shall be flushed with
sufficient water to remove material that has entered the pipes during construction.
3.03 FIELD QUALITY CONTROL
A. Do not backfill trench until the pipe has been inspected and approved by the
Engineer.
3.04 MEASUREMENT AND PAYMENT
A. A Bid Item has been provided for 4 Inch Perforated Polyethylene Pipe Drain Tile.
Measurement will be by linear feet of pipe along its axis with no regard to
intervening fittings. Payment shall include geotextile, aggregate, and fittings.
B. Supplying and installing required markers at ends shall be considered incidental
to the drain tile installation.
C. All other work and costs of this Section shall be incidental to the Project and
included in the TOTAL BASE BID.
END OF SECTION
000034-04159-0
@ 2005 Bonestroo, Rosene,
AnderJik & Associates, Inc.
02635-3
SUBSURFACE DRAINAGE
SECTION 02720
AGGREGATE BASE COURSE
PART 1- GENERAL
1.01 SECTION INCLUDES
A. Requirements for aggregate base course on a prepared sub grade.
1.02 RELATED SECTIONS
A. Section 02318 - Sub grade Preparation.
B. Section 02740 - Plant Mixed Asphalt Pavement.
1.03 REFERENCES
A. Minnesota Department of Transportation "Standard Specifications for Construction,"
2000 Edition (MnDOT Spec.):
1. 2211 - Aggregate Base.
2. 3138 - Aggregate for Surface and Base Courses.
1.04 SUBMITTAL
A. Submit gradation report on sample of aggregate base to be used.
1.05 SEQUENCING AND SCHEDULING
A. Construct aggregate base only after all of the following have been completed:
1. Subgrade has been corrected for instability problems and successfully passed
a test rolling test performed by the Contractor and witnessed by the Engineer.
2. Subgrade has been checked for conformance to line and grade tolerances
(stringline) .
PART 2 - PRODUCTS
2.01 MATERIALS
A. Aggregate Base: Conform to MnDOT Spec. 3138, Class 5 aggregate.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02720-1
AGGREGA IE BASE COURSE
PART 3 - EXECUTION
3.01 PREPARATION
A. Prepare the sub grade in accordance with Section 02318 - Subgrade Preparation.
B. Subgrade to be completed and approved by the Engineer prior to installation of
aggregate base.
3.02 CONSTRUCTION REQUIREMENTS
A. Conform to MnDOT Spec. 2211.3:
1. Compact by mechanical means to 100 Percent Standard Proctor Density.
2. Install aggregate base in accordance with details on Drawings.
3. Deliver weight tickets to Engineer daily.
3.03 FIELD QUALITY CONTROL
A. The Owner shall have an independent testing laboratory sample the aggregate base
materials, determine the moisture/density relationships and gradation, and perform
field moisture/density tests at locations determined by Engineer.
B. Line and Grade Tolerance: The final aggregate base surface will be checked for
conformance to specified tolerances by the "stringline" method prior to approval to
pave the surface. Grade shall be::t 0.03 feet of grade.
3.04 PROTECTION
A. Protect aggregate base until it is covered by surface pavement.
B. Keep aggregate base free of ruts and irregularities until covered by surface paving.
C. Place water on aggregate base for dust cOhtrol as required to eliminate nuisance
conditions for adjacent properties.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02720-2
AGGREGA IE BASE COURSE
3.05 MEASUREMENT AND PAYMENT
A. A Bid Item has been provided for Aggregate Base, Class 5. Measurement will be by
the ton of material compacted in place as determined from weight tickets delivered
to the Engineer:
1. If the aggregate base course material is being wasted or placed excessively
thick, the Owner reserves the right to deduct quantities that are in excess of
Drawing thickness. Said quantities shall be based on material weighing 110
pounds per square yard of area per inch of thickness.
B. All other work and costs of this Section shall be incidental to the Project and
included in the TOTAL BASE BID.
END OF SECTION
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02720-3
AGGREGAIEBASECOURSE
SECTION 02740
PLANT MIXED ASPHALT PAVEMENT
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. Hot plant mixed asphalt-aggregate mixtures for weanng and non-wearmg
pavement courses.
B. Bituminous tack coat.
1.02 RELATED SECTIONS
A. Section 02280 - Adjust Miscellaneous Structures.
B. Section 02720 - Aggregate Base Course.
C. Section 02770 - Concrete Curb and Gutter.
1.03 REFERENCES
A. Minnesota Department of Transportation "Standard Specifications for
Construction," 2000 Edition (MnDOT Spec.):
1. Attached version of Specification 2360 Plant Mixed Asphalt Pavement
(Combined 2360/2350 (GyratorylMarshall Design) Specification).
2. 2357 - Bituminous Tack Coat.
3. 2535 - Bituminous Curb.
1.04 SUBMITTALS
A. Submit mixture design report to the Engineer. Conform to MnDOT Spec.
2360.3E and 2360.4F, and Division 1 - General Requirements.
B. Contractors shall submit mix design report for all projects, regardless of the size
of the project.
C. Contractor shall submit Q/C results in accordance with MnDOT Spec. 2360.4F.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02740-1
PLANT MIXED ASPHALT PAVEMENT
1.05 SEQUENCING AND SCHEDULING
A. Aggregate base and concrete curb and gutter to be completed and approved by the
Engineer prior to placement of bituminous surfaces.
B. The Contractor shall provide a 48 hour notice for scheduling and noticing of the
residents prior to paving operations.
C. Adjust structures prior to placement of bituminous wearing course as specified in
Section 02280 - Adjust Miscellaneous Structures.
D. Bituminous cores for testing shall be taken 12 to 48 hours after paving operations.
PART 2 - PRODUCTS
2.01 MATERIALS
A. Mixture Designation: Conform to MnDOT 2360.1, except as modified in the
typical section Detail Drawing and Bid Form.
B. Conform to MnDOT Section 2360.2, except as modified herein:
1. Scrap Asphalt Shingles (2360.2A2h) are not allowed in wearing course
pavements.
2. Waste Incinerator Ash (WIA) (2360.2A2j) will not be allowed in either
bituminous wear or non-wear course pavements.
C. Bituminous Tack Coat:
1. Bituminous Material: Conform to MnDOT Spec. 3151:
a. Emulsified Asphalt, Cationic, CSS-l or CSS-2.
D. Asphalt Binder Material: Conform to MnDOT Spec. 2360.2G and as identified in
the Mix Designation.
E. Mixture Design: Conform to MnDOT Spec. 2360.3.
000034-04159-0
@ 2005 Bonestroo, Rosene,
AnderJik & Associates, Inc.
02740-2
PLANT MIXED ASPHALT PAVEMENT
F. Mixture Quality Management (Quality Control/Quality Assurance): Conform to
MnDOT Spec. 2360.4, except as modified herein:
1. Quality Control Testing: The Contractor will be allowed to provide
historical testing data from the previous 3 days of production for each
mixture type to meet the Production Sampling and Testing Rates indicated
in Table 2360.4-E for Course Aggregate Angularity and Fine Aggregate
Angularity. The Contractor will be allowed to provide historical testing
data from the previous 10 days of contractor production for each mixture
type to meet the Production Sampling and Testing Rates indicated in
Table 2360.4-E for TSR, Aggregate Specific Gravity, and Asphalt Binder
Content.
2. Quality Assurance testing will be completed at the discretion of the
Engineer, testing rates will not exceed Table 2360.4-D and 2360.4-E:
a. A verification sample will be taken by the Engineer. The
Contractor will be required to use the verification companion
sample as part of the QC testing program.
PART 3 -EXECUTION
3.01 GENERAL - CONFORM TO MNDOT SECTION 2360.5 CONSTRUCTION
REQUIREMENTS, EXCEPT AS MODIFIED HEREIN
A. The Contractor to review the proposed paving sequence with the Engineer prior to
placement of each bituminous course (lift).
B. The Proposed Sequence Shall Address The: Longitudinal seams, compaction,
traffic control, hauling routes, and placement of pavement markings.
C. Preparation of Bituminous Non Wear Course:
1. Final clean up of the bituminous surface with the use of a power pickup
broom and front end loader
2. Adjustment of structures as specified In Section 02280 - Adjustment
Miscellaneous Structures.
D. Joints:
1. Where new construction meets existing bituminous surfacing, the existing
surface shall be uniformly milled or saw-cut straight, and bituminous tack
coat applied prior to placement of each bituminous course (lift).
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02740-3
PLANT MIXED ASPHALT PAVEMENT
3.02 RESTRICTIONS
A. Conform to MnDOT Section 2360.5B, except as modified herein:
1. All street surfaces checked and approved by the Engineer prior to paving.
2. Existing bituminous surfaces must be dry prior and during placement of
any bituminous pavements.
3. Wearing course shall not be placed when the air temperature in the shade
and away from artificial heat is 500 or less, unless otherwise approved by
the Engineer.
3.03 EQUIPMENT
A. Conform to MnDOT Section 2360.5C.
3.04 TREATMENT OF SURFACE
A. Bituminous Tack coat shall conform to MnDOT Spec. 2357, except as modified
herein.
B. Restrictions:
1. The tack coat shall not be applied when the road surface is wet or when
the weather conditions are unsuitable.
2. The area for tack coat application shall be limited as directed by the
Engineer.
3. The Contractor shall have sole responsibility of claims of tack coat on
personal property due lack of notification or signage of the area being tack
coated.
C. Equipment:
1. Conform to MnDOT Spec. 2321.3C1.
D. Road Surface Preparation:
1. Conform to MnDOT Spec. 2357.3C.
E. Application:
1. At a uniform rate conforming to MnDOT Spec. 2357.3Dl, but not greater
than 0.05 gallon per square yard.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02740-4
PLAt'lT MIXED ASPHALT PAVEMENT
2. Along the front edge of the concrete curb and gutter and existing
pavement, prior to placement of bituminous base.
3.05 PAVEMENTDENSITY
A. Conform to MnDOT Section 2360.6, except as modified herein:
1. Pathways, Dn.veways, Small Parking Lots, Leveling Courses, and
Patching shall conform to Section 2360.6C - Ordinary Compaction
Method.
2. All other Pavement Density shall conform to Section 2360.6B -
Maximum Density Method.
3. Modify Table 2360.6-B2a Lot Determination as indicated below:
Daily Production (Tons) Lots
200 to 1000 1
1001 to 2000 2
2001 to 3600 3
3601 to 5000 4
5001 + 6
Daily production 0 to 200 tons is at the discretion of the Engineer.
4. Modify Table 2360.6-B4 "Payment Schedule for Maximum Density" as
indicated below. This modification is intended to eliminate incentive
payments for pavement density:
Percent of Max Specific Gravity (2) Percent of Max Specific Gravity (2)
SP Wear (~100 mm [4 inches] from SP Non-Wear (>100 mm [4 inches] from Percent
Surface) Surface) Payment
All MY & LV , SP Shld (4% Void) SP Shoulders (3% Void)
93.6 and above 94.6 and above 100 (3)
93.1 to 93.5 94.1 to 94.5 100 (3)
92.0 to 93.0 93.0 to 94.0 100
91.0 to 91.9 92.0 to 92.9 98
90.5 to 90.9 91.5 to 91.9 95
90.0 to 90.4 91.0 to 91.4 91
89.5 to 89.9 90.5 to 90.9 85
89.0 to 89.4 90.0 to 90.4 70
Less than 89.0 (4) Less than 90.0 (4)
Table 2360.6-B4
Payment Schedule for Maximum Density
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02740-5
PLANT MIXED ASPHALT PAVEMENT
B. Vibrating steel drum roller and a pneumatic tired roller employed in conjunction
with each other during compaction of all wear courses.
3.06 THICKNESS AND SURFACE SMOOTHNESS REQUIREMENTS
A. Conform to MnDOT Section 2360.7, except as modified herein:
1. Delete Section 2360.7C Pavement Smoothness.
B. Structure Adjustment - Conform to Section 02280 - Adjust Miscellaneous
Structures for tolerances.
3.07 MEASUREMENT AND PAYMENT
A. Method of measurement and payment shall conform to MnDOT Section 2360.8,
except as modified herein.
B. A Bid Item has been provided for bituminous material for Tack Coat:
1. Measured by volume in gallons at 600 F.
2. Payment for bituminous material used for Tack Coat includes
compensation in full for all costs incidental to the fumishing and
application at the Bid Unit Price per gallon.
3. Cleaning of all debris and dirt from the previous bituminous surfaces prior
to placement of Tack Coat is included in the Bid Unit Price for Tack Coat.
4. Payment for tacking exposed edges of existing bituminous surfaces and
concrete curb and gutter in conjunction with base course placement is
considered incidental to the placement of the base course.
C. Bid Items have been provided for different types of Bituminous Mixtures.
1. Measured by the weight in tons of material placed and accepted for each
specified Bid Item as stated in the Bid Form. Payment shall be made in
accordance with the acceptance and payment schedules provided in the
MnDOT Combined 2360/2350 (GyratorylMarshall Design) Specification.
2. The Bid Unit Price includes both the bituminous course mixture and
asphalt binder material.
3. Partial payment will not exceed 70 percent of the total calculated payment
until the required testing and product documentation is received and found
to be acceptable to the Engineer.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02740-6
PLANT MIXED ASPHALT PAVEMENT
D. Preparation of Bituminous Base: Measurement and Payment shall be made as
stated in the Bid Form and shall include the following:
1. Final clean up of the bituminous base course with a power pickup broom.
2. Final adjustment of the structures to conform to Section 02280 - Adjust
Miscellaneous Structures.
E. All other work and costs of this Section shall be incidental to the Project and
included in the TOTAL BASE BID.
END OF SECTION
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02740-7
PLANT MIXED ASPHALT PAVEMENT
(2360) PLANT MIXED ASPHALT PAVEMENT
Combined 2360/2350 (Gyratory/JVlarshalI Design) Specification
December 1, 2004
This Specification requires the Contractor to provide a mix that complies with all of the design,
production, and placement requirements of the specification. The Department Owner does not make any guaranty
or warranty, either express or implied, that compliance with one part of this specification guarantees that the
Contractor will meet the other aspects of the specification.
2360.1
All Sections titled 2360 also apply to 2350.
DESCRIPTION
This work consists of the construction of one or more pavement courses of hot plant mixed
asphalt-aggregate mixture on the approved prepared foundation, base course or existing surface in accordance with
the specifications and in conformity with the lines, grades, thiclmesses and typical cross sections shown on the plans
or established by the Engineer. Mixture design will be either 2360 or 2350 (gyratory or Marshall) as described in
the Special Provisions Drawings through the rnL'{ture designation.
A
(4)
Mixture Designations
Mixture designations for asphalt rnL'{tures contain the following information:
(1)
The fIrst two letters indicate the mixture design type:
SP = Gyratory Mixture Design
LV = Marshall Mixture Design - Low Volume, 50 blow
MV = Marshall Mixture Design - Medium Volume, 50 blow
SM = Gyratory Mixture Design for Stone Matrix Asphalt (SMA)
(2)
The third and fourth letters indicate the course:
WE = Wearing and Shoulder Weating Course
NW = N on- W eating Course
(3)
The fIfth letter or number indicates the maximum aggregate size*:
A or 4 = 12.5rnrn [1/2 inch], SP 9.5
B or 3 = 19.0rnrn [3/4 inch], SP 12.5
Cor 2 = 25.0rnrn [1 inch], SP 19.0
5 = 9.5rnrn [3/8 inch], (Marshall design only)
E = See provision for SM.A. design
* Letter is used in gyratory designation; number is used in Marshall designation
For Gyratory Design:
The sixth digit indicates the Traffic Level (ESAL's x 106)
The requirements for gyratory mixtures in this specification are based on the 20-year design traffic
level of the Project expressed in Equivalent Single .Axle Loads (ESAL's). The five traffic levels
are sho\VTI below in Table 2360.l-A.
2360/2350 Combined Specification
December 1, 2004
Traffic Level 20 Year Design ESAL's (1 x 106 ESAL's)
21 <1
32 1 to < 3
4 3 to < 10
5 10 to < 30
6 SMA
Table 2360.1-A
Traffic Levels
1 -- (AADT ~ 2300)
2 -- (2300< AADT <6000)
For Marshall Design:
The sixth and seventh digit indicate the Marshall design blows:
50 blow design for both LV and MY mixtures
(5) The last two digits indicate the air void requirement:
40 = 4.0% for SP and SM Wear mixtures
35 = 3.5% for J:vIV Wear and Non-Wear
30 = 3.0% for LV Wear and Non-Wear and SP Non-Wear and Shoulder
(6) The letter at the end of the mixture designation identifies the asphalt binder grade:
A = PG 52-34
B = PG 58-28
C = PG 58-34
D = PG 58-40
E = PG 64-28
F = PG 64-34
G = PG 64-40
H = PG 70-28
1= PG 70-34
L = PG 64-22
Ex: Gyratory Mi'i:ture Designation -- SPWEB540E (Design Type, Lift, Agg Size, Traffic Level, Voids, Binder)
Ex: Marshall Mixture Designation - L VWE35030B (Mix Type, Lift, Agg Size, Marshall blows, Voids, Binder)
Ex: SMA Mixture Designation -- SMWEE640H (Design Type, Lift, Agg Size, Traffic Level, Voids, Binder)
B
Minimum Lift thickness
Minimum paving lift thickness will be based on maximum aggregate size:
Aggregate Size A, 4*; B, 3*:
Aggregate Size 5*:
Aggregate Size C, 2* (for non-wear only):
* Marshall designation
Minimum Lift thickness = 40 mrn [1 Yz inch]
Minimum Lift thickness = 20 mrn [3/4 inch]
Minimum Lift thickness = 65 mrn [2 Yz inch]
2360.2
MATERIALS
A
Aggregate
Al
General
The aggregate shall consist of sound, durable particles of gravel and sand, crushed stone and sand,
or combinations thereof. It shall be free of objectionable matter such as metal, glass, wood, plastic, brick, rubber,
and any other material having similar characteristics. Coarse aggregate shall be free from coatings of clay and silt to
the satisfaction of the Engineer.
Page 2 of 48
2360/2350 Combined Specification
December 1,2004
The Contractor shall not compensate for the lack offmes by adding soil materials such as clay,
loam, or silt. Overburden shall not be blended into the asphalt aggregate.
Each different material (source, class, kind, or size) shall be fed at a uniform rate from its storage
unit. An individual source, class, type, or size of material shall not be stockpile blended with another source, class,
type or size of material.
A2
Classification
The aggregate shall conform to one of the following classifications. The class of aggregate to be
used shall be the Contractor's option unless otherwise specified in the Contract.
A2a
Class A
Class A aggregate shall consist of crushed igneous bedrock (specifically; basalt, gabbro, granite,
rhyolite, diorite and andosite) and rock from the Sioux Quartzite Formation. Other igneous or metamorphic rock
may be used with specific approval of the Engineer. Class A materials may contain no more than 4.0% non-Class A
aggregate. This recognizes the fact that some quarries may contain small pockets of non-Class A material within
that source. Intentional blending or addition of non-Class A material is strictly prohibited!
A2b
Class B
Class B aggregate shall consist of crushed rock from all other bedrock sources such as carbonate
and metamorphic rocks. (gneiss or schist)
A2c
Class C
Class C aggregate shall consist of natural or partly crushed natural gravel obtained from a natural
gravel deposit.
A2d
Class D
Class D aggregate shall consist of 100 percent crushed natural gravel. The crushed gravel shall be
produced from material retained on a square mesh sieve having an opening at least twice as large as the
Specification permits for the maximum size of the aggregate in the composite asphalt mixture. The amount of
carryover (material fmer than) the selected screen shall not exceed ten percent.
A2e
Class E
Class E aggregate shall consist of a mixture of any two or more of the above classes of approved
aggregate (A, B, and D). The use of Class E aggregate, as well as the relative proportions of the different
constituent aggregates, shall be subject to the approval of the Engineer. The relative proportions of the constituent
aggregates shall be accurately controlled either by the use of a blending belt approved by the Engineer prior to
production or by separately weighing each aggregate during batching operations.
A2f
Steel Slag
Steel slag may not exceed 25 percent of the mass of the total aggregate. Stockpiles will be
accepted for use if the total expansion, determined by ASTM D4792, is less than 0.50%.
A2g
Taconite Tailings (TT)
Taconite tailings shall be obtained from ore that is mined westerly of a north-south line located
east of Biwabik, Mn (R15W-R16W); except that taconite tailings from ore mine.d in southwestern Wisconsin will
also be permitted for use.
Page 3 of 48
2360/2350 Combined Specification
December 1, 2004
Approved taconite tailing sources are on file with the Department Bituminous Engineer.
A2h
Scrap Asphalt Shingles
Scrap asphalt shingles may be included in both wear and non-wear courses to a maximum of 5
percent of the total weight of mixture. Only scrap asphalt shingles from manufacturing waste are suitable. The
percentage of scrap shingles used will be considered part of the maximum allowable RAP percentage. Refer to
Section 2360.2 G1 to select a virgin asphalt binder grade (use requirements for> 20% RAP, regardless of total
RAP/shingle percentage). Scrap Shingle Specifications are on file in the Bituminous Office.
A2i
Crushed Concrete and Salvaged Aggregate
Crushed concrete is allowed as an aggregate source for up to 50 percent of the aggregate in
non-wear mixtures. Crushed concrete is not allowed in wearing courses.
Salvaged aggregate is allowed as an aggregate source for up to 100 percent of the aggregate in
wear and non-wear mixtures. All salvaged aggregate shall be stockpiled uniformly to limit variation in mixture
properties. Salvaged aggregates shall meet quality and crushing requirements as specified herein.
A2j
Sewage Sludge Ash (SSA)
Sewage sludge ash is allowed as an aggregate source in both wear and non-wear courses to a
maximum of 5 percent of the total weight of mixture. Only SSA that meets the Tier II hazard evaluation criteria as
approved by .Mn/DOT's Office of Environmental Services, Environmental Analysis Section, will be allowed for use
in the mixture.
Approved waste incinerator ash sources are on file with the Department Bituminous Engineer.
A3
Recycled Asphaltic Pavement Materials (RAP)
The combined RAP and virgin aggregate shall meet the composite fine aggregate angularity or
calculated crushed requirements (both coarse and fine aggregate) for the mixture being produced (calculated crushed
allowed for Marshall design only). RAP containing any objectionable material, i.e., road tar, metal, glass, \vood,
plastic, brick, fabric, or any other objectionable material having similar characteristics will not be permitted for use
in the asphalt pavement mixture.
Asphalt binder content in the RAP shall be determined according to Mn/DOT Lab Manual Method
1851 or 1852.
B
Manufactured Crushed Fines (-4 material)
All Class A, B, D, and E material that passes the 4.75 mrn [#4] screen will be considered as
crushed fmes.
Manufactured Crushed Fines (-4 material) from Class C Aggregate. Produce manufactured
crushed fmes (-4 material) from a gravel source by passing the gravel over a selected screen, 9.5 mrn [3/8 inch] or
larger, prior to mechanical crushing. The material which passes the 9.5 mrn [3/8 inch] screen shall not be
incorporated into the manufactured crushed fines but may be used as it qualifies for natural sand. The amount of
carryover (material fmer than) the selected screen shall not exceed ten percent.
The material retained on the 9.5 rnrn [3/8 inch] screen shall be crushed. The material that passes
the 4.75 mrn [#4] screen, after crushing, will be considered as 100% crushed fines. Material retained on the
4.75 mrn [#4] screen after crushing will not be counted as +4 crushing until tested.
Page 4 of 48
2360/2350 Combined Specification
December 1, 2004
C
Quality Requirements
Cl
Los An gel es Ratti er Test ..................... .............. ....................... ..................... .......... .A.ASHT 0 T96
The Los Angeles Rattler loss on the coarse aggregate fraction (material retained on the 4.75 rom
[#4] sieve shall not exceed 40 percent for any individual source used within the mix. An aggregate proportion
which passes the 4.75 rom [#4] sieve and exceeds 40 percent LAR loss on the coarse aggregate fraction is prohibited
from use in the mixture.
C2
Soundness (Magnesium Sulfate) ............................................................................AASHTO TI04
The magnesium sulfate soundness loss at 5 cycles on the coarse aggregate fraction (material
retained on the 4.75 mID [#4]) shall not exceed the following for any individual source used within the mix: *
a) No more than 14 % loss on the 19 mID [3/4 inch] to 12.5 mID [1/2 inch] and larger fractions.
b) No more than 18% loss on the 12.5 mID [1/2 inch] to 9.5 mID [3/8 inch] fraction.
c) No more than 23% loss on the 9.5 mID [3/8 inchJ to 4.75 mID [#4J fraction.
d) No more than 18% for the composite loss. (Applies only if all three size fractions are tested).
* 1) If the composite requirement is met but one or more individual components do not, the source may
be accepted if no individual component is more than 110% of the requirement for that component.
2) If each individual component requirement is met but the composite does not, the source may be
accepted if the composite is no greater than 110% of the requirement.
An aggregate proportion which passes the 4.75 mID [#4] sieve and exceeds the requirements listed
above on the coarse aggregate fraction is prohibited from use in the mixture.
C3
Spall Materials and Lumps ...........................................................MnlDOT Laboratory Manual
Spall is defmed as shale, iron oxide, unsound cherts, pyrite, highly weathered and/or soft phyllite
and argillite (may be scratched with a brass pencil), and other materials having similar characteristics.
Lumps are defmed as loosely bonded aggregations and clayey masses. If the percent of lumps
measured in the stockpile or cold feed exceed the values listed below, asphalt production shall cease and compliance
shall be determined by dry batching. This procedure may be repeated at any time at the discretion of the Engineer.
Maximum limits for Spall and lumps, expressed as percentages by mass, are listed in
Table 2360.3-B2a.
C4
Insoluble Resi d ue T est ....................................................................NInlDOT Laboratory NIan ual
If Class B carbonate material is used in the mix, the minus 0.075 mID [#200] sieve size portion of
the insoluble residue shall not exceed 10 percent.
D
Aggregate Restrictions
Class B carbonate aggregate restrictions are specified in Table 2360.3-B2a.
E
Gradation Requirement
The coarse and fine aggregate shall be combined in such proportions to produce an asphalt
mixture meeting all of the requirements defmed in this specification and shall conform to the gradation as defmed in
Table 2360.2-E. Gradation testing shall be conducted in accordance with AASHTO T-11 (-0.075 mID [-#200J wash)
and T-27.
Page 5 of 48
2360/2350 Combined Specification
December 1, 2004
Table 2360.2-E
Aggregate Gradation Broad Bands
(% passing of total washed lJradation)
Sieve Size A or 4 * B or 3* Cor 2* 5* E
(mm [inch]) (SMA)
25.0 [1 inch] 100 See SIvfA Provisions
19.0 [3/4 inch] 100(1) 85-100
12.5 [1/2 inch] 100( ) 85-100 45-90
9.5 [3/8 inch] 85-100 35-90 - 100
4.75 [#4] 25-90 20-80 20-75 65-95
2.36 [#8] 20-70 15-65 15-60 45-80
0.075 [#200] 2.0-7.0 2.0-7.0 2.0-7.0 2.0-7.0
*Marshall Designation
With the approval of the Engineer, the gradation broadband for the maximum aggregate size may be reduced to 97%
passing for mixtures containing RAP, when the oversize material is suspected to come from the RAP source. The
virgin material must remain 100% passing the maximum aggregate sieve size.
F
Additives
An additive is any material added to an asphalt mixture or material, such as mineral filler,
hydrated lime, asphalt additives, anti-strip, and similar products that do not have a specific pay item. When a
Contract requires additives, compensation is included with the pay items for the appropriate mixture. If the
Engineer directs the Contractor to incorporate additives, the compensation will be as Extra Work, at the unit price
specified in the proposal. The Department Owner \vill not compensate the Contractor for additives incorporated at
the Contractor's option.
Additives \vill not be incorporated into the mixture \vithout approval of the Department
Bituminous Engineer. Anti-foaming agents shall be added to asphalt cement at the manufacturer's recommended
dosage rate. Mineral filler and hydrated lime may be added in a quantity not to exceed 5 percent and 2 percent,
respectively, of the total mass of the aggregate. The combination of mineral filler and hydrated lime shall not
exceed 5 percent of the total mass of aggregate. The Engineer \vill approve or disapprove methods for addition of
additives.
F1
Min er a I Fill er ............................................................................................................................ 3145
F2
H Y d rated Lime........ .......................................... ........................................................................ 3145
Hydrated lime used in asphalt mixtures shall meet the requirements of ASTM C977 and have a
maximum of eight percent unhydrated oxides (as received basis). The method of introducing and mixing the
hydrated lime and aggregate shall be subject to approval by the Engineer prior to beginning mixture production.
F3
Liquid Anti-Stripping Additive
When a liquid anti-strip additive is added to the asphalt binder, blending shall be completed before
the asphalt binder is mixed with the aggregate. Liquid anti-strip additives that alter the asphalt binder, such that it
fails to meet the Performance Grade (PG) requirements, shall not be used. Liquid anti-strip may be added by the
supplier at the refInery or by the Contractor at the plant site. The company/supplier adding the additive shall be
responsible for testing the binder/additive blend to ensure compliance with the AASHTO M 320, Standard
Specification for Performance Graded Asphalt Binder. No paving will be allowed until the asphalt binder/additive
blend has been tested and results show that binder/additive blend properties meet the criteria in Section 2360.2G.
The testing shall be done in accordance with a Mn/DOT approved Asphalt Binder QC Plan. Requirements for the
Asphalt Binder QC Plan are on file in the Bituminous Office.
Page 6 of 48
2360/2350 Combined Specification
December 1, 2004
The following requirements for H:N1A mixture and asphalt binder must also be met when liquid
anti-strip is added at the H:N1A plant site.
F4
G
Mixture ReQuirements at Desig;n:
1) The Contractor must design the mixture with the same asphalt binder that will be supplied to the
plant site. (Both Laboratory Mixture Design (Option 1) and Modified Mixture Design (Option 2).
2) The Contractor must provide documentation with either design option that includes Tensile
Strength Ratio results with the liquid anti-strip dosed at the optimal rate. Documentation must
include verification the binder/additive blend meets AASHTO M 320 at the optimal dose rate.
Contractor Production Testing; ReQuirements for Asphalt Binder/LiQuid Anti-Strip Blend:
1) The Contractor shall, on a daily basis, sample and test the asphalt binder/anti-strip blend. Testing
of the blend can be by viscosity, penetration, or dynamic shear rheometer (DSR). When a
polymer modified asphalt binder is specified, the Contractor shall use the DSR as the daily QC
test.
2) The Contractor shall, on a weekly basis, send the Engineer and Mn/DOT Chemical Laboratory
Director a weekly QC report summarizing the results of the daily testing as required in number 1.
3) The Contractor shall, on a bi-weekly basis, test the binder/anti-strip blend to ensure compliance
with the AASHTO M 320, Standard Specification for Performance Graded Asphalt Binder
(minimum 1/project). Test results shall be sent to the Engineer and Mn/DOT Chemical
Laboratory Director.
4) In addition to the sampling requirements listed above, the Contractor shall obtain asphalt
binder/anti-strip blend field verification samples according to 2360.4 E12.
LiQuid Anti-Strip Additive Metering; Svstem:
1)
The metering system shall include a liquid anti-strip flow meter in addition to an anti-strip pump.
The flow meter shall be connected to the liquid anti-strip supply to measure and display only the
anti-strip being fed to the asphalt binder.
The meter readout shall be positioned for convenient observation.
There shall be a means provided for comparing the flow meter readout with the calculated output
of the anti-strip pump. See number 7.
The system shall display in units ofliters [gallons] to the nearest liter [gallon] or in units of metric
tons [tons] to the nearest 0.001 metric tons [0.001 tons], the accumulated anti-strip quantity being
delivered to the mixer unit.
The system shall be calibrated and adjusted to maintain an accuracy of:t one percent error.
Calibration shall be required for each plant set-up prior to production of mixture.
The Engineer may require, on a daily basis, the Contractor "stick" the anti-strip tank at the end of
j}e days production to verify anti-strip usage quantities.
The system shall provide for a convenient method for sampling the binder/anti-strip after blending
has occurred.
Alternative blending and metering systems must be pre-approved by the Engineer
2)
3)
4)
5)
6)
7)
8)
9)
C oa ting and Anti-Stripping Additive ......................................................................................3161
Asphal t Binder lYla terial ......................................................................................AASHTO lYI 320
Asphalt binder material shall meet the requirements ofPG asphalt binder testing tolerances,
sampling rates, testing procedures, and acceptance criteria based on the most current Mn/DOT Technical
Memorandum, titled "Inspection, Sampling, and Acceptance of Bituminous Materials." The PG asphalt binder
cannot be modified with air blowing procedures unless the Department Bituminous Engineer approves it. The
Contractor shall not use petroleum distillates such as fuel oil, diesel fuel or other fuels in the asphalt tanks. A
statement shall be provided by the supplier for recommended laboratory mixing and compaction temperatures and
field maximum mixing and compaction temperatures.
Page 7 of 48
2360/2350 Combined Specification
December 1, 2004
Gl
Asphalt Binder Selection Criteria for All Mixtures with RAP
Overlay Specified PG Asphalt Virgin Asphalt Binder Grade to be used with RAP
Binder Grade < 20% RAP > 20% RAP
64-22 64-22 64-28
Other PG Grades No grade adjustment No grade adjustment
New Construction (1) Specified PG Asphalt Virgin Asphalt Binder Grade to be used with RAP
Binder Grade :$; 20% RAP > 20% RAP
52-34 52-34 Not allowed *
58-28 58-28 58-28
58-34 58-34 Not allowed *
64-28 64-28 64-28
64-34 64-34 Not allowed *
Other PG Grades No grade adjustment Not allowed *
*
When approved by the Engineer, the virgin asphalt binder grade can be selected by using the blending chart
procedure on file in the Bituminous Office. Mn/DOT may take production samples for
information/verification of compliance with a specified asphalt binder grade.
Includes cold inplace recycle, reclaiming, and reconstruction.
(1)
2360.3
MIXTURE DESIGN
A
Mixture Design General
The asphalt mix may be designed using one of the following two Contractor trial mix design
options. Review of mixture designs will be performed in the District Materials Laboratory lab where the Project is
located. The addition of aggregates and materials not included in the original mixture submittal is prohibited.
It is the Contractor's responsibility to design a Marshall mixture in accordance with the most
current AASHTO T-245, the Asphalt Institute's Mix Design Methods for Asphalt Concrete MS-2, and the Mn/DOT
Laboratory Manual such that it meets the requirements of this specification.
For Marshall design, the design air void content of the mixture is dependent on the mixture type,
regardless of the location in the pavement structure. Design air void content for LV and MV mixtures is 3.0% and
3.5%, respectively.
It is the Contractor's responsibility to design a gyratory mixture in accordance with the most
current AASHTO T -312, the Asphalt Institute's Superpave Mi.x Design Manual SP-2 (2-hour short term aging
period is used for volumetric), and the :N1n/DOT Laboratory Manual such that it meets the requirements of this
specification.
For gyratory design, the design air void content of the mixture at design shall be 4.0% at the
design number of gyrations (Ndesign) for mixtures placed in the upper 100 mID [4 inches] of the finished surface. The
design air void content of the mixture at design shall be 3.0% at the design number of gyrations (Ndesign) for mixtures
placed at depths more than 100 rnm [4 inches] from the surface and on all (wear and nonwear) shoulders that do not
carry traffic. If less than 25% of a layer is within 100 mID [4 inches] of the surface, the layer may be considered to
be below 100 mID [4 inches] for mix design purposes (non-wear).
Page 8 of 48
2360/2350 Combined Specification
December 1,2004
v
Design Air oid Requirement for Gyratory Mixtures
SP Wear SP Non-wear SP Shoulder**
Location from ~ 100 mID [4 inch]* > 100 mID [4 inch]* All Wear and
surface Non-Wear
Air Voids 4.0% 3.0% 3.0%
* If less than 25% of a layer is within 100 mID [4 inches] of the surface, the layer may be
considered to be below 100 mID [4 inches] for mix design Purp9ses-,-
** Shoulders that do not carry traffic.
B
Laboratory Mixture Design (Option 1)
Test results and documentation as described in Section 2360.3C shall be submitted with the
materials described below for consideration by the Department Bituminous Engineer or District Materials Engineer
to verify compliance with these specifications and to issue a Mixture Design Report.
Bl
Aggregate sample
At least 15 working days prior to the start of asphalt production, the Contractor shall submit to the
Department Bituminous Engineer or the District Materials Engineer a 35 kg [80 pound] sample of representative
aggregate retained on the 4.75 mID sieve [#4] and a 15 kg [35 pound] sample of material passing the 4.75 mID sieve
[#4J for quality testing. The Contractor shall provide 24 hour notice of intent to sample aggregates. These samples
will be tested for quality of each source, class, type, and size of virgin and non-asphaltic salvage aggregate source
used in the mix design. The Contractor shall retain a companion sample of equal size until a Mixture Design Report
is issued. Quality requirements are defmed in Section 2360.2C.
Aggregates that require the magnesium sulfate soundness test shall be submitted to the
Department Bituminous Engineer or District Materials Engineer at least 30 calendar days prior to the start of asphalt
production. Dispute resolution procedures for aggregate qualities are on file in the Bituminous Office.
B2
Mixture sample
At least 7 working days prior to the start of asphalt production, the Contractor shall submit in
writing a proposed Job ML'\. Formula (JMF) for each combination of aggregates to the Department Bituminous
Engineer or District Materials Engineer for review. A Level II Quality Management mix designer must sign the
proposed JMF. For each JMF submitted, the Contractor shall include test data to demonstrate conformance to
mixture properties as specified in Table's 2360.3-B2b and 2360.3-B2c. The proposed JMF shall be submitted on
forms approved by the Department. In addition, the Contractor shall submit an uncompacted mixture sample plus
briquettes compacted at the optimum asphalt content and required compactive effort conforming to the JMF for
laboratory examination and evaluation. Mixture sample size and number of compacted briquettes are as follows:
1 lxture am e eQUlrements
Item Gyratorv Design Marshall Design
Un-compacted Mixture Sample Size 30 Kg [75 pounds] 18 Kg [40 pounds]
Number of compacted briquettes 2 3
Table 2360.3-B2
M' SIR
B2a
Mixture Aggregate Requirements
The aggregate fractions shall be sized, graded, and combined in such proportions that the resulting
mixture will meet the requirements listed in Section 2360.2-E and Table 2360.3-B2a shown below.
Page 9 of 48
2360/2350 Combined Specification
December 1,2004
Table 2360.3-B2a
M'rt A t R t
1 I ure \.ggrega e eQUlremen s
Traffic Traffic Traffic Traffic SMA
Aggregate Blend Property Level 2& LV Level 3 & MV Level 4 Level 5 T. Level 6
20 year Design ESAL' s <1 million 1 - 3 million 3 - 10 10 - 30 See SMA
million million Provisions
Coarse Aggregate Angularity
(ASTM D5821) 30/- 55/- 85 / 80 95 / 90
(one face / two face), %- Wear -
(one face / two face), %- NonWear 30/- 55/- 60/ - 80/75
Fine Aggregate Angularity (FAA)
(AASHTO T304, Method A) %- Wear 40(2) 4il) 44 45 -
%-Non-Wear 40(2) 40(1) 40 40
Flat and Elongated Particles, maxl~) % 10 10 10
by weight, (ASTM D 4791) - (3:1 ratio) (3:1 ratio) (3:1 ratio) -
Clay Content(2) (AASHTO T 176) - - 45 45 -
Total Spall in fraction retained on the 5.0 2.5 1.0 1.0 -
4.75mm [#4] sieve
Maximum Spall Content in Total 5.0 5.0 1.0 1.0 -
Sample
Maximum Percent Lumps in fraction 0.5 0.5 0.5 0.5 -
retained on the 4.75mm [#4] sieve
Class B Carbonate Restrictions
Maximum% -4.75mrn [-#4]
Final Lift!All other Lifts 100/100 100/1 00 80/80 50/80 -
Maximum% +4.75mrn [+#4]
Final Lift! All other Lifts 100/1 00 100/100 50/1 00 0/100 -
Gvratorv
Max. allowable RAP percentage 30/40 30/30 30/30 30/30
Wear / Non Wear
Marshall
Max. allowable RAP percentage 30/40 30/30
Wear /Non Wear
(1) F or Marshall design, the Contractor may determine -4 crushing by either FAA of uncompacted voids or
calculation of crush from the composite blend. The choice must be made prior to start of production.
Manufactured crushed fInes requirement is 25%. RAP sand will be considered 50% crushed if the
angularity index equals or exceeds 40, and 100% crushed if the angularity index equals or exceeds 45.
(2) Not applicable under Marshall design.
B2b Mixture Requirements
Mixture evaluation will be based on the trial mix tests and the corresponding requirements listed
in Table 2360.3-B2b and Table 2360.3-B2c.
Page 10 of 48
2360/2350 Combined Specification
December 1, 2004
1 I ure eqUlrements
Traffic Level Traffic Level Traffic Level Traffic Level SMA
2 3 4 5 T. Level 6
20 year Design ESAL's < 1 million I - 3 million 3 - 10 million 10 - 30 See S1-'IA
million Provisions
Gyratory Mixture Requirements
Gyrations for N initial 6 7 8 8 -
Gyrations for Ndesil!ll 40 60 90 100 -
Gyrations for Nma:dmum 60 90 140 160 -
Air Voids, % -- Wear 4.0 4.0 4.0 4.0
Air Voids, % -- Non-Wear & All 3.0 3.0 3.0 3.0 -
Shoulder
% Gmm at Ninitial- Wear - :s; 91.5 :s; 90.5 :s; 90.0
% Gmm at Ninitial- Non-Wear & - :s; 92.5 :s; 91.5 :s; 91.0
All Shoulder
% Grrun at Nmaximum- Wear :s; 98.0 :s; 98.0 :s; 98.0 :s; 98.0 -
% Gmm at N maximum- Non Wear & :s; 99.0 :s; 99.0 :s; 99.0 :s; 99.0 -
All Shoulder
Tensile Strength Ratio \1), min% 75\2) 75\-) 80\J) 80\J) -
Fines/Effective Asphalt 0.6 - 1.2 0.6 - 1.2 0.6 - 1.2 0.6 - 1.2 -
VFA, % -- Wear 65 - 78 65 - 78 65 - 76 65 - 76
Non-Wear & All Shoulder 70 - 83 70 - 83 70 - 82 70 - 82
Marshall Mixture Requirements LV MY
Marshall Blows 50 50 - - -
Air Voids, % 3.0 3.5 - - -
Tensile Strength Ratio \1), min% 70\4) 70\4)
Stability, minimum N [Ib f] 5000 [1125] 6000 [1350]
Fines/Effective Asphalt Wear 0.6 - 1.30 0.6 - 1.30
Non-Wear 0.6-1.40 0.6-1.40 - - -
Table 2360.3-B2b
M'xt R
(1) See Section 2360.4 E9. Use 150mm [6 inch] specimens for gyratory and 100mm [4 inch] specimens for
Marshall design.
(2) Mn/DOT Min~ = 65, (3) Mn/DOT Min = 70, (4) Mn/DOT Min = 60
B2c VlVIA Criteria
The voids in mineral aggregate (VMA) of the mixture at design and during production shall meet
the minimum criteria as shown in Table 2360.3-B2c at the specified compaction level. VMA shall be calculated
according to the procedures outlined in Asphalt Institutes SP-2 or MS-2 manual. VMA is a design and
acceptance/process control requirement.
01 S In 1 Inera ;gregate 1 - I lxture eqUlremen s
Gradation Fine Mixture VMA Coarse Mixture VMA
% Pass 2.36 mm [#8] Minimum % Pass 2.36 mm [#8] Minimum
A or 4* >47 15.0** :S;47 14.5*
B or 3 * > 39 . 14.0 :s; 39 13.5
C or 2* > 35 13.0 :s; 35 12.5
5* ----- 15.0** ----- -----
E See SMA Provisions
V'd' M'
Table 2360.3-B2c
I A (VMA) M'
R
t
*Marshall designation.
**For LV 4 and LV 5 mixes lower VMA requirements by 0.5%
Page 11 of48
2360/2350 Combined Specification
December 1, 2004
B3
Tensile Strength Ratio sample
Mixture or briquettes that represent the mixture at optimum asphalt content, shall be submitted at
least 7 days prior to actual production for verification of moisture sensitivity retained tensile strength ratio (TSR).
Material submitted for TSR verification may be tested for maximum specific gravity Gmm compliance in addition to
TSR results. Failure to meet the Gnun tolerance will result in rejection of the submitted mix design. A new mix
design submittal will be required and will be subject to provisions described in Section 2360.3C. One of
the following options may be used to verify that the tensile strength ratio (TSR) meets the requirements in
Table 2360.3-B2b.
Option A) The Contractor will batch material at the design proportions including optimum asphalt.
Immediately (before curing) split the sample and allow samples to cool to room temperature. Submit 35 kg
[77 pounds] of mixture to the District Materials Laboratory for curing and test verification. Both groups will use a
two (2) hour cure time C:t 15 minutes) at 1440C [2900F] and follow procedures in ASTM D 4867-92, Iv1n!DOT
modified as defmed in the MnlDOT Laboratory Manual.
Option B) The Contractor batches, cures (as indicated in option A), compacts, and submits
briquettes and uncompacted mixture as specified below.
o
Marshall Desi n
8,200 g
9
6.0 - 8.0%
B4
Aggregate Specific Gravity .....................................AASHTO T84 and T85, Mn/DOT Modified
The Contractor shall determine the specific gravity of all aggregate used in the mixture.
c
Documentation
Each proposed JMF submitted for review under Section 2360.3B and 2360.3D shall include the
following documentation and test results.
(1) The name(s) of the individual(s) responsible for the Quality Control of the mixture during
production.
(2) The low projects number on which the mixture will be used.
(3) The percentage in units of 1 percent (except the 0.075 mm sieve [#200] in units of 0.1 percent) of
aggregate passing each of the specified sieves for each aggregate to be incorporated into the
mixture. The gradation of aggregate from salvaged asphaltic material shall be derived from the
material after the residual asphalt has been extracted.
(4) The source and description of the materials to be used. The aggregate pit or quarry source
number. The proportion of each material (in percent of total aggregate).
(5) The composite gradation based on (3) and (4) above. Note: Include virgin composite gradation
based on (4) and (5) above for mix.tures containing RAP.
(6) The bulk (dry) and apparent specific gravities and water absorption (by % weight of dry
aggregate) of both coarse and fine aggregate, for each product used in the mixture (including
RAP). Use AASHTO T-84 and T-85 Mn/DOT modified as defmed in the Mn/DOT Laboratory
Manual. The tolerance allowed between the Contractor's and the Department's specific gravities
are Gsb (individual) = 0.040 [+4 A1'ID -4] and Gsb (combined) = 0.020.
(7) The composite gradation plotted on a FHW A 0.45 power chart. (Federal form PR-1115)
Page 12 of 48
2360/2350 Combined Specification
December 1, 2004
(8) For mixtures containing RAP include extracted asphalt binder content of the RAP with no
retention factor included.
(9) The percentage (in units of 0.1 percent) and PG grade of asphalt binder material to be added,
based upon the total mass of the mixture.
(10) When using laboratory mixture design Option 1 (2360.3B) or Option 2 (2360.3D), include the
following:
(a) A minimum of three different asphalt binder contents (minimum 0.4 percent between
each point), with at least one point at, one above and one below the optimum asphalt
binder percentage.
(b) The maximum specific gravity at each asphalt binder content. The theoretical maximum
specific gravity used for percent air voids determination shall be calculated based on the
average ofthe effective specific gravities measured by a minimum of two maximum
specific gravity tests at the asphalt contents above and below the expected optimum
asphalt binder content.
(c) The test results for the individual and average bulk specific gravity, density, and heights,
of at least two specimens at each asphalt binder content. For Marshall design include the
test results for the individual and average bulk specific gravity, density, height, stability,
and flow of at least three specimens at each asphalt binder content.
(d) The percent air voids in the mixture at each asphalt binder content.
(e) The percent Voids in Mineral Aggregate (VMA) at each asphalt binder content.
(f) The fInes to Effective Asphalt (F/A) ratio calculated to the nearest 0.1 percent.
(g) TSR results at the optimum asphalt binder content.
(h) Graphs showing air voids, voids in the mineral aggregate, Gmb, Grnm and unit weight vs.
percent asphalt binder content for each of the three asphalt binder contents submitted
with trial mix.
(11) Optional Add-Rock/Add-Sand Provisions
lfthe Contractor chooses to use the add-material option to augment the submitted JMF, the
Contractor shall provide samples of the aggregate for quality analysis in accordance with Section
2360.3B 1. The Contractor shall provide mix design data for two additional design points per
add-material. One point shall show a proportional adjustment to the submitted JMF that includes
5 percent, by mass, add-material at the JMF optimum asphalt percent. The second point shall
show a proportional adjustment to the submitted nvIF that includes 10 percent, by mass,
add-material at the nvlF optimum asphalt percent. The following information will be reported for
each of these two points:
(a) The maximum specific gravity (average of two tests).
(b) The test results for the individual and average bulk specific gravity, density, and height of
at least two specimens at the optimum asphalt binder content. For Marshall design
include the test results for the individual and average bulk specific gravity, density,
height, stability, and flow of at least three specimens at the optimum asphalt binder
content.
(c) The percent air voids in the mixture for each point.
(d) The Fines to Effective Asphalt ratio calculated to the nearest 0.1 of a percent.
(e) Coarse and Fine Aggregate crushing counts
Up to two add-materials will be allowed per mix design submittal. Aggregate quality and mix
characteristics are required for each proposed add-material and shall be submitted at the time of
the original trial rni'i: submittal. No mixture sample or briquettes are required for these two
additional points.
Page 13 of 48
2360/2350 Combined Specification
December 1, 2004
Additional Documentation For:
Gyratory Design
(G 1) The test results from the composite aggregate blend at the proposed JMF proportions
indicating compliance with Coarse Aggregate Angularity, Fine Aggregate Angularity,
and Flat and Elongated as shown in Table 2360.3-B2a.
(G2) The design traffic level and the initial, design, and maximum number of gyrations Ninitial,
Ndesign, and Nmaximum'
(G3) The temperature ranges the mixture is intended to be discharged from the plant and
compacted at the roadway shall be provided by the asphalt binder supplier. Temperatures
to be included are, laboratory mixing and compaction temperature ranges and maximum
field mixing and compaction temperatures.
(G4) Evidence that the completed mixture will conform to all specified physical requirements
as follows:
Design air Voids (Va), VMA, VF A, TSR, F / Ae (Fines to effective asphalt ratio),
Densification %Gmm at Ninitiah Ndesign, and NMaximum'
(G5) Labeled gyratory densification tables and curves, generated from the gyratory compactor,
for all points used in the mixture submittal.
Marshall Design
(M 1) The test results from the composite aggregate blend at the proposed JMF proportions
indicating compliance with fine aggregate angularity uncompacted voids as shown in
Table 2360.3-B2a. Or calculated -4.75 rom [-#4] crushing from the composite blend of
the proposed JMF. Selection of either FAA or -4.75 mID [-#4] crushing shall be made at
the time of mix design submittal. This selection will dictate the choice of method used
for detennination of compliance and acceptance for the duration of time the Mixture
Design Report is in force. RAP sand will be considered 50% crushed if the angularity
index equals or exceeds 40, and 100% crushed if the angularity index equals or exceeds
45.
D
Modified Mixture Design (Option 2)
Test results and documentation as described in Section 2360.3C shall be submitted to the
Department Bituminous Engineer or the District Materials Engineer to verify compliance with mix design
requirements and issue a Mix Design Report. Mixture submittal is not required. The Contractor may use this option
if all of the following conditions are met:
a) The aggregates in the proposed Mix Design Report have been used, in part, in other Mix Design
Reports. Additionally, the aggregates must have been previously tested for and meet all applicable
quality requirements in the current construction season.
b) The Level II mix designer submitting the mixture design must have a minimum of 2 years
experience in mixture design.
c) The Contractor and his representatives cannot have violated the requirements of 1512
Unacceptable and Unauthorized Work relating to mixture design or mixture production within the
last 12 month period.
Page 14 of 48
2360/2350 Combined Specification
December 1, 2004
Dl
JMF Submittal
At least 2 working days prior to the start of asphalt production, the Contractor shall submit in
writing a proposed Job Mix Formula (nvIF) for each combination of aggregates to the Department Bituminous
Engineer or District Materials Engineer for review. A Levelll Quality Management mix designer must sign this
proposed JMF. For each JMF submitted, the Contractor shall include documentation as outlined in Section 2360.3C
to demonstrate conformance to mixture properties as specified in Table 2360.3-B2b and 2360.3-B2c. The proposed
JMF shall be submitted on forms approved by the Department.
D2
Initial Production Test Verification
At the start of production, the testing frequency for the first 1,800 metric tons [2,000 tons] of each
mix type shall be as specified in Table 2360A-D.
All mixture placed on ~,'fn'DOT the Owner's projects shall meet the specified quality indicators
and required field density. Failure to do so will result in reduced payment or removal and replacement with
acceptable material.
The Department Owner shall take a mix verification sample within the first four samples at the
start of production of each mix type.
D3
Tensile Strength Ratio sample
See Section 2360AE9
D4
Marshall Stability (Marshall Design Only)
On the first day of production, for each different mix design, at the same time the verification
sample is obtained, an additional sample shall be obtained for Department Owner evaluation of Marshall stability.
This sample may be tested at the discretion of the District ~,{aterials Engineer Engineer. The Contractor is not
required to test stability on production mixture.
If the Marshall stability fails to meet the minimum requirements as listed in Table 2360.3-B2c the
Contractor shall stop production immediately. The Contractor will be required to submit a revised mix design, with
bituminous mixture at optimum asphalt content, to the District Materials Laboratory. If the mixture meets the
minimum stability requirement production may be resumed.
If the stability fails the second time, the Mix Design Report will be revoked. The Contractor will
then be required to submit a new mix design according to Laboratory Mixture Design 2360.3B, Option 1. A new
ML"'\: Design Report will be issued upon successful verification of the new mixture design submittal.
E
Mixture Design Report
A Mixture Design Report consists of the JMF (Job Mix Formula). The nvIF includes composite
gradation, aggregate component proportions, asphalt binder content of the mixture, design air voids, Voids in
Mineral Aggregate, and aggregate bulk specific gravity values. JMF limits will be shown for gradation control
sieves, percent asphalt binder content, air voids, and VMA. Issuance of a Mixture Design Report confums the
mixture has been reviewed for and meets volumetric properties only. No guaranty or warranty, either express or
implied, is made regarding placement and compaction of the mixture
A Department reviewed Mixture Design Report is required for all paving except for small
quantities of material provided under Section 2360.5H. All submitted materials must meet aggregate and mixture
design requirements before a Mixture Design Report is issued. The Department will review two trial mix designs
per mix type designated in the plan, per Contract at no cost to the Contractor. Additional mix designs will be
verified at a cost of $2000 per design, payable to the Commissioner of Transportation.
Page 15 of 48
2360/2350 Combined Specification
December 1, 2004
For city, county, and other agency projects, the Contractor shall provide to the District Materials
Laboratory a complete Project proposal including addenda, supplemental agreements, change orders, and any Plan
sheets (including typical sections) that affect the mix design. The Department will not start the verification process
without this information.
2360.4
lVIIXTURE QUALITY M.Al~AGEMENT (Quality Control/Quality Assurance)
A
Quality Control (QC)
The Contractor shall provide and maintain a quality control program for HMA production. A
quality control program is defmed as all activities, including mix design, process control inspection, sampling and
testing, and necessary adjustments in the process that are related to the production of a hot mix asphalt (HMA)
pavement which meets the requirements of the specifications.
Al
Contractor Certified Plant HlVIA
Ala
Certification Procedure
The Contractor shall:
(1)
(2)
Complete application form and request for plant inspection.
Provide a site map of stockpile locations.
(3)
Pass plant and testing facility inspection by having the Plant Inspector and Bituminous Plant
Authorized Agent complete and sign the Asphalt Plant Inspection Report (TP 02142-02, TP
02143-02). By signing the Asphalt Plant Inspection Report, the HMA plant authorized agent
agrees to calibrate and maintain all plant and laboratory equipment within allowable tolerances set
forth in these specifications, Standard Specifications for Construction, and the Mn/DOT
Bituminous Manual.
(4)
Obtain a Mixture Design Report prior to production.
Alb
Maintaining Certification
To maintain certification, the plant must produce, test, and document all certified plant asphalt
mixtures in accordance with the above requirements on a continuous basis. Continuous basis means all asphalt
mixtures supplied from a certified plant to any Department project 'with 2360 asphalt mixtures must be sampled and
tested in accordance with 2360 requirements and the Schedule of Materials Control.
The Contractor shall assure the plant certification procedure is performed annually after winter
suspension and before producing material for a Project. In addition, a fIrst-day sampling and testing frequency rate
as stated in Table 2360A-D shall be followed.
The Contractor shall recertify a plant when it is moved to a new location or a previously occupied
location.
Alc
Revocation of Plant CertifIcation
The Department Construction Engineer may revoke certification of an asphalt plant when
requirements are not being met or records are falsified. The Department may revoke the Technician CertifIcation
for the individual involved.
The Department Bituminous Engineer and Department Contract Administrator will maintain a list
of companies who have had their asphalt plant certification revoked.
Page 16 of 48
2360/2350 Combined Specification
December 1, 2004
B
Quality Assurance (QA)
The Department Owner will perform QA testing as part of the acceptance process. The Engineer
is responsible for QA testing, records, and acceptance. The Engineer will accomplish the QA process by:
(1)
(2)
(3)
(4)
(5)
(6)
(7)
Conducting Quality assurance and verification sampling and testing.
Observing sampling and tests performed by the QC personnel.
Taking additional samples at any time and any location during production.
Monitoring the required QC summary sheets and control charts.
Verifying calibration of laboratory testing equipment.
Communicating :.1:n'DOT Owner test results to the Contractor's QC personnel in a timely manner.
Ensuring Independent Assurance Sampling and testing requirements are met.
C
Contractor's Quality Control
Cl
Personnel Requirements
Along with the proposed mix design data, the Contractor shall submit to the Engineer an
organizational chart listing the names and phone numbers of individuals and alternates responsible for mix design,
process control administration, and inspection. The Contractor shall also post a current organizational chart and if
required by the Engineer, post a daily roster of individuals performing QC testing in the Contractor's test facility.
The Contractor's quality control organization or private testing firm shall have Certified
Technicians who have met the requirements on file with the Department's Technical Certification program.
Individuals performing process control testing must be certified as a Level I Bituminous Quality Management (QM)
Tester. Individuals performing mix design calculations or mix design adjustments must be certified as Level II
Bituminous QM Mix Designer. The Contractor shall have a Certified Level II Bituminous QM Mix Designer
available to make any necessary process adjustments. The Contractor shall have a minimum of one person per
paving operation certified as a Level II Bituminous Street Inspector.
C2
Laboratory Requirements:
The Contractor shall furnish and maintain a laboratory at the plant site or other site as approved by
the Engineer. The laboratory shall be furnished with the necessary equipment and supplies for performing
Contractor quality control testing. The laboratory equipment shall meet the requirements listed in Section 400 of the
MnlDOT Bituminous Manual and these specifications, including having extraction capabilities. The laboratory shall
be calibrated, and operational prior to the beginning of production. In addition to the requirements listed above, the
laboratory shall be equipped with a telephone for use by the Contractor or the Engineer. A fax machine and copy
machine shall be available for use by the Contractor or the Engineer at the laboratory site. The laboratory shall also
include a computer and printer. The computer shall have the following minimum requirements: 1) Intel based with
either Celeron or Pentium IV processor with a minimum processor speed of 1.8 :tvIHZ. 2) CD writer with CD/RW
capability and a minimum write speed of 16x. 3) Windows 2000 or Windows XP with Microsoft Excel version 97
or newer. The printer must be able to print control charts.
The Engineer shall be allowed to inspect measuring and testing devices to confirm both calibration
and condition. The Contractor shall calibrate and correlate all testing equipment in accordance with the latest
version of the MnlDOT Bituminous Manual.
D
Sampling and Testing
The Contractor shall ensure that all QC samples are taken at random locations. Random number
generation and determination of random sample location shall be consistent with the Mn/DOT Bituminous Manual
Section 5-693.7 Table A or Section 5 of ASTM D3665. The Engineer may approve alternate methods of random
number generation.
Page 17 of 48
2360/2350 Combined Specification
December 1, 2004
The tests for mixture properties shall be conducted on representative portions of the mix, quartered
from a larger sample of mixture taken from behind the paver, or when approved by the Engineer, an alternate
sampling location. The procedure for truck box sampling, an alternate sampling location, is on fIle in the
Bituminous Office. When an alternate sampling location is approved and used by the Contractor, the daily
verification sample must still be taken from behind the paver.
The Contractor shall obtain a sample of at least 25 kg [55 pounds]. This sample may be either
split in the field or transported to the test facility by a method to retain heat to facilitate sample quartering
procedures. The Contractor shall store and retain mixture bulk samples and companion samples for the Department
Engineer for a period of7 working days. The Contractor shall maintain these split samples in containers labeled
with companion numbers. The Contractor shall perform QC sampling and testing according to the following
schedule.
Determine the planned tonnage for each mixture to be produced during the production day.
Divide the planned production by 1000. Round the number to the next higher whole number. This number will be
the number of production tests required for that mixture. Required production tests are listed in Table 2360A-E.
Split the planned production into even increments and select sample locations as described above. If actual tonnage
exceeds planned tonnage additional tests may be required. During production, mixture volumetric property tests
will not be required when mix production is less than 270 metric tons [300 tons]. However, production tests will be
required when the accumulative tonnage on successive days exceeds 270 metric tons [300 tons].
At the start of production, the testing frequency for the fIrst 1800 metric tons [2,000 tons] of each
mix type shall be as follows:
ro uc IOn ar - Jp es ng a es
Production Test Testine: Rates Test Reference Section
Bulk Specific Gravity I test per 450 metric tons [500 tons] AASHTO T312,T166 Mn/DOT 2360.4E2
modified
Maximum Soecific Gravity I test per 450 metric tons r500 tons AASHTO T209 MnlDOT modified 2360.4E3
Air Voids (calculated) 1 test per 450 metric tons [500 tons AASHTO T269, T312 2360.4E4
Asphalt Content I test per 450 metric tons r 500 tons Bit & Lab Manual 2360.4EI
VMA (Calculated) I test per 450 metric tons [500 tons) AI MS 2 & SP 2 2360.4E5
Gradation I test per 900 metric tons r 1 000 tons 1 AASHTO Ill, T27, T30Mn/DOT modified 2360.4E6
Coarse Aggregate Angularity 1 test per 900 metric tons [1000 tons] ASTM D5821 236D.4E7
Fine Aggregate Angularity 1 test per 900 metric tons [1000 tons] AASHTO T304, Method A 2360.4E8
(FAAil)
Table 2360.4-D
P d f St t U T ti R t
(1) Marshall design allows -4.75mrn [-#4] manufactured crushed filles calculation per Mn/DOT Bituminous Manual
E
Production Tests
When more than one Mn/DOT approved test procedure is available, the Contractor shall select,
with the approval of the Engineer, one method at the beginning of the Project and use that method for the entire
Project. The Contractor and Engineer may agree to change test procedures during the construction of the Project.
Page 18 of 48
2360/2350 Combined Specification
December 1, 2004
Table 2360.4-E
Production Sampling and Testing Rates
Production Test Samolingrresting Rates Test Reference Section
Bulk Specific Gravity Divide the planned production by 1000. Round the AASHTO T312, T245 Tl66 2360.4E2
number to the next higher whole number. MnJDOT mod
Maximum Specific " AASHTO T209 MnJDOT 2360.4E3
Gravity modified
Air Voids (calculated) " AASHTO T269, TI12 2360.4E4
Asphalt Content " Bit & Lab Manual 2360.4El
VMA (Calculated) " Al MS 2 & SP 2 2360.4E5
Gradation 1 gradation per 1,800 metric tons [2,000 tons], or AASHTO Tll, T27, 2360.4E6
portion thereof (minimum of one per day) TIOMnJDOT modified
Coarse Aggregate 2 tests/day for a minimum of 2 days, then 1 per day if ASTM D5821
Angularity CAA is met. rfCAA >8% of requirement, 1 sample/day 2360.4E7
but test lIweek.
Fine Aggregate 2 tests/day for a minimum of 2 days, then 1 per day if AASHTO T304, Method A
Angularity (F AA)(I) FAA is met. If FAA >5% of requirement, I sample/day 2360.4E8
but test lIweek.
TSR 1 st sample at 5,000 tons or by second day of production, ASTIvl D4867 MnlDOT 2360AE9
then sample at everY 18,000 metric tons r20,000 tonsl modified
Aggregate Specific 1 per 9,000 metric tons [10,000 tons] AASHTO T84 & T85, 2360.4EI0
Gravity MnlDOT modified
Mixture Moisture Daily unless exempted by Engineer MnlDOT 5-693.950 2360AEII
Content
Asphalt Binder Sample 1 st load (each grade) then 1 per 1,000,000 liter MnlDOT 5-693.920 2360.4E12
f250,000 gallon-sample size 1 Quart.l
(1) Marshall design allows -4.75rnrn [-#4] manufactured crushed fmes calculation per Mn/DOT Bituminous Manual
(a)
(b)
(c)
(d)
Asphalt Binder Content
Spot Check (Virgin only)....................................................................Mn/DOT Bituminous Manual
Incinerator Oven (1) ........................................................ Mn/DOT Laboratory Manual Method 1853
Chemical Extraction ........................................lv1n/DOT Laboratory Manual Method 1851 or 1852
Meter Method (Virgin only) ................................................................Mn/DOT Bituminous Manual
El
(1) Incinerator Oven may not be used when the percentage of Class B material exceeds 50%
within the composite blend, unless a correction factor is determined by the Contractor
and approved by the District Materials Engineer.
E2
Marshall Bulk Specific Gravity, Gmb (3 specimens).....AASHTO T166, Mn/DOT Modified, or
E2a
Gyratory Bulk Specific Gravity, Gmb (2 specimens) ................................ AASHTO T312, T166,
MnlDOT Modified
E3
Maximum Specific Gravity, Gmm.........................................AASHTO T209, MnlDOT Modified
E4
Air Voids - Individual and Isolated (calculation)......................................AASHTO T269, T312
Isolated air voids are calculated using the maximum mixture specific gravity and the
corresponding bulk specific gravity from a single test. Individual air voids are calculated from the ma.'(irnum
specific gravity moving average and the bulk specific gravity from that single test.
For gyratory design, compaction shall be conducted to Nmaximum and calculations for %Gmm at
Ninitial and Ndesign shall be determined by applying the calculated correction factor as described in the Asphalt
Institute SP 2 manual.
Page 19 of 48
2360/2350 Combined Specification
December 1, 2004
Production control for % Gmm at Ninitial and Nmaximum shall not exceed the limit sho\VU in Table
2360.3-B2b by more than 1.0 %. Mixture produced beyond these limits, as measured by the moving average offour
tests, may result in a cancellation of the Mix Design Report. A new mix design and submittal that satisfies these
specification criteria may be required.
E5
Voids Mineral Aggregate (Vl\'IA) (calculation) ............................. Asphalt Institute MS-2, SP-2
E6
Gradation - Blended Aggregate..........AASHTO T-ll, T-27, and T-30 (all MnJDOT modified)
Testing to determine the blended aggregate gradation shall be determined every 1800 metric tons
[2,000 tons], or portion thereof (minimum of one per day), on samples taken at the same time as the required
mixture sample for a given increment.
All gradations require a - 0.075 mm [-#200] wash.
(a)
Virgin Aggregate Mixtures - Drum or Screenless Plants
Belt Samples or extracted production samples.
All Other Mixtures:
1. Hot Bins - Drybatch (Optional)
2. Incinerator Oven Mn/DOT Laboratory Manual Method 1853 (Optional) except
samples that contain over 50% class B. (1)
Extraction I'v1n/DOT Laboratory Manual Method 1851 or 1852 (Optional)
....
;).
(b)
(1) Incinerator Oven may not be used when the percentage of Class B
material exceeds 50% within the composite blend, unless a correction
factor is determined by the Contractor and approved by the District
Materials Engineer.
E7
Coarse Aggr ega te An gul ari ty ................................................................................... ASTl\rl D5821
CAA test results shall meet the minimum percent fractured faces as sho\VU in Table 2360.3-B2a.
ASTM D-5821 shall be used to determine coarse aggregate angularity on the composite blend from aggregates used
in production of hot mix asphalt. Mixtures that contain virgin aggregates may be tested from composite belt
samples. Mixtures that contain RAY must be tested from extracted aggregates taken from standard production
samples. The percentage of fractured faces of the composite aggregate blend less than 100% shall be tested at the
following rates:
(1) Perform two tests per day for each mixture blend for a minimum of two days and then one per day
if the test samples meet CAA requirements.
(2) IfCAA crushing test results exceed 8 percent of the requirement, take one sample per day and
perform one test per week.
CAA results must be reported on the test summary sheet. Mixture placed and represented by
results below the minimum requirement, as sho\VU in Table 2360.3-B2a, will be subject to reduced payment as
outlined in Table 2360.4-13. Tonnage subjected to reduced payment shall be calculated as the tons placed from the
sample point of the failing test until the sampling point when the test result is back Viithin specifications.
E8
Fine Aggregate A.ngularity ......................................................................ASTlVl C1252 lVlethod A
FAA test results shall meet the minimum criteria sho\VU in Table 2360.3-B2a. ASTM C1252
Method A shall be used to determine fine aggregate angularity on the composite blend from aggregates used in
production ofHl'vIA. Mixtures that contain virgin aggregates may be tested from composite belt samples. Mixtures
that contain RAP must be tested from extracted aggregates taken from standard production samples. The percentage
of uncompacted voids from the composite aggregate blend shall be tested at the following rates.
Page 20 of 48
2360/2350 Combined Specification
December 1, 2004
(1) Perform two tests per day for each mixture blend for a minimum of two days and then one per day
if the test samples meet FAA requirements.
(2) If FAA test results exceed 5 percent of the requirement, take one sample per day and perform one
test per week.
FAA results must be reported on the test summary sheet. Mixture placed and represented by results below the
minimums, as shown in Table 2360.3-B2a, will be subject to reduced payment as outlined in Table 2360A-L3.
Tonnage is subjected to reduced payment shall be calculated as the tons placed from the sample point of the failing
test until the sampling point when the test result is back within specifications.
E8a
- 4.75 mm [-#4] Manufactured Crushed Fines ......................................... (calculation) Mn/DOT
Bituminous Manual
Under Marshall design, when the -4.75 mm [-#4] crushing is calculated, adjustments in target
values from the composite blend must be made at the end of each days paving. If the target quantity (percent of
-4.75 mm [-#4] to be crushed) changes due to mixture proportion or composite gradation change, a new target
shall be established for the next days paving.
E9
Field Tensile Strength Ratio (TSR) .........................................ASTM D4867 Mn/DOT Modified
A TSR sample shall be obtained within the [lIst 4,500 metric tons [5,000 tons] ofH1\tlA produced
or by the second day of production, whichever comes [lIst, to verify tensile strength ratio (TSR). These samples
may be tested at the discretion of the District :Materials Engineer Owner. If the M:aterials Engineer Owner requires
the samples to be tested, both the Contractor and the Department Engineer will be required to test these samples
within 72 hours after it is sampled. Sample size shall be 50 kg [110 pound] minimum and split in half to provide a
sample for the Department Engineer and the Contractor. The Department Engineer companion of this split shall be
labeled with the date, time, Project number and approximate cumulative tonnage to date. The Department Owner
companion shall be given to the Department Owners Street Inspector or Plant Monitor immediately or delivered to
the District ~.1aterials Engineer within 24 hours of sampling, as specified by the Engineer. Mixture samples shall be
taken from behind the paver unless the Engineer approves an alternate sampling location. Specimen size shall be
100 mm [4 inch] for Marshall mix design and 150 mm [6 inch] for gyratory design The Contractor may test the
sample at a permanent lab site or a field lab site.
Additional HIvlA mixture samples for TSR evaluation shall be sampled at a rate of 1 per 18,000
metric tons [20,000 tons] increments for all mixtures produced on the Project. These samples may be tested at the
discretion of the District ~1aterials Engineer Owner. If the ~.1aterials Engineer Owner requires the samples to be
tested, both the Contractor and the Department Engineer will be required to test these samples.
Minimum acceptable TSR values for production are shown in Table 2360A-E9. The Contractor
shall stop production immediately if minimum TSR requirements are not met. The Contractor will not be allowed to
resume production until anti-strip has been added to the asphalt binder. Determination of who is responsible for the
cost of the anti-strip is based on ~.1nI])OT O\Vner and Contractor TSR values as outlined in Tables 2360AE9A,
2360AE9B, and 2360AE9C. "Vhen ~.1nI])OT the Owner is responsible for the cost of the anti-strip, payment will be
made only for the cost of the anti-strip for mixtures placed on that project. ~1nI])OT The Owner will not reimburse
the Contractor for any delay costs associated with making changes related to this testing.
Table 2360.4-E9
Mixture Type- - Minimum TSR
LVandMV Gyratory Traffic Level 2-3 Traffic Level 4-5
~1n/DOT ),fuI])OT ~1nI])OT
Contractor Owner Contractor O\"'mer Contractor Owner
70% 60% 75% 65% 80% 70%
Page 21 of48
2360/2350 Combined Specification
December 1, 2004
Table 2360.4-E9A
LV and MV Contractor TSR
Mixtures >70 <70
~1n/DOT ~60 NA ~'f:n/DOT
Owner Owner
TSR <60 Contractor Contractor
Table 2360.4-E9B
Gyratory Level Contractor TSR
2-3 >75 <75
~'fn/DOT ~65 NA Mn/DOT
Owner Owner
TSR <65 Contractor Contractor
Table 2360.4-E9C
Gyratory Level 4-5 Contractor TSR
>80 <80
;:'iln'DOT ~70 NA ~'ln'DOT
Owner Owner
TSR <70 Contractor Contractor
Another sample shall be taken and tested within the fIrst 450 metric tons [500 tons] after
production resumes. rfthe re-test fails to meet the minimum specified value the Contractor shall stop production
immediately. Production cannot resume until the Contractor has discussed, with the Engineer, a proposal for
resolving the problem. The Contractor shall not operate below the specified minimum TSR on a continuing basis.
A continuing basis shall be defIned as 2 or more successive tests failing the TSR requirements.
The following conditions will automatically require a sample to be taken and tested:
1. A proportion change of more than 10 percent (from the currently produced mixture) for a single
stockpile aggregate.
2. The discretion of the Engineer.
Dispute resolution proe<::dures for TSR are on file in the Bituminous Office.
E10
Aggregate Specific Gravity (Gsb) ........................... AASHTO T84 and T85, Mn/DOT modified
Samples of all aggregate stockpiles shall be collected on each aggregate used in the production
mixture, at a rate of one sample per 9,000 metric tons [10,000 tons] mixture produced. These samples shall be taken
at random as directed by the Engineer. These representative stockpile samples shall be 40 kg [90 pounds] of each
aggregate component. Each sample shall be split in half to provide a sample for the Department Owner and the
Contractor. The Department Owner companion shall be labeled with date, time, Project number and approximate
cumulative tonnage to date.
The Department OVvller's companion shall be given to the Department Owner's Street Inspector or
Plant Monitor immediately or delivered to the District ~,1aterials Engineer within 48 hours of sampling, as specified
by the Engineer. These samples may be tested. Tested samples will be compared to the Contractor's values on the
Mix Design Report. rfthe results deviate beyond the tolerance specified in Table 2360.4-M, the dispute resolution
procedure on file in the Bituminous Office will be utilized. Any mixture placed following notification of new
specific gravity values Vvil1 be based upon Department results unless proven incorrect. The Contractor shall be
notified when new specific gravity values become available and what impact this will have on the calculated VMA.
Page 22 of 48
2360/2350 Combined Specification
December 1, 2004
Ell
Moisture Con tent .................. ............... ........... ............... .......... ........................ Mn/D 0 T 5-693.950
Provide a mixture with a moisture content not greater than 0.3 percent. The moisture content in
the mixture shall be measured behind the paver or alternate approved sampling method on fIle in the Bituminous
Office. Sampling and testing shall be conducted by the Contractor on a daily basis unless exempted by the
Engineer. Sampling and testing is suggested when rain on stockpiles exceed more than 5 mID [0.2 inch] in a 24 hour
period. The sample shall be stored in an airtight container. Microwave testing is prohibited.
HMA that exceeds 0.3% moisture content is unacceptable. The Contractor shall take appropriate
action to remove excess water from the mixture. This action may include reducing the production rate, mixing
stockpile aggregates prior to placement into the feed bins, and use of covered stockpiles.
El2
Asphalt Binder Samples
The Contractor shall sample the fIrst shipment of each type of asphalt binder, then sample at a rate
of one per 1,000,000 liters [250,000 gallons]; sample size shall be 1.0L [1 quart]. All samples shall be taken in
accordance with the Mn/DOT Bituminous Manual 5-693.920. Sampling shall be conducted by Contractor and
monitored by the Inspector. Promptly submit the sample to the Department Materials Laboratory in Maplewood.
The Contractor shall record sample information on Asphalt Sample Identification Card.
F
Documentation (Records)
The Contractor shall maintain documentation, including test summary sheets and control charts,
on an ongoing basis. The Contractor shall also maintain a fIle of gyratory specimen heights for all gyratory
compacted samples and test worksheets. Reports, records, and diaries developed during the progress of construction
activities for the Project, shall be fIled as directed by the Engineer and will become the property of the Department
Owner. The Contractor shall:
(1) Number test results in accordance with standard Department procedures and record on forms
approved/supplied by the Department.
(2) Facsimile all production test results on test summary sheets to the District ~,1i1terials Laboratory
Ene:ineer's Street Inspector and to other sites as requested by the Engineer, by 11 AM of the day
following production.
(2a) Include the following production test results and mixture information on the Department approved
test summary sheet.
1. Percent passing on sieves listed in Table 2360.2-E
2. Coarse and fine aggregate crushing.
3. Ma.ximum specific gravity (Gmrn}
4. Bulk specific gravity (Gmb).
5. Percent asphalt binder content (Pb).
6. Calculated production air voids (Va)' Gyratory design shall also include %Gmrn at Ninitial,
%Gmrn at Ndesign , and % Gmrn at Nmaximum
7. Calculated voids in mineral aggregate (V1vIA).
8. Composite aggregate specific gravity (Gsb) reflecting current proportions.
9. Aggregate proportions in use at the time of sampling.
10. Tons where sampled.
11 Cumulative tons.
11a. Tons Represented by Test.
12. Fines to effective asphalt ratio (F/Ae).
13. Signature Line for ~,ln/DOT Engineer and Contractor Representative.
14. Mixture Moisture Content.
15. l\1nIDOT Owner verification sample test result.
Page 23 of 48
(2b)
(3)
(4)
(5)
(6)
(6a)
(7)
(8)
G
2360/2350 Combined Specification
December 1, 2004
Submit copies of all failing test results to the Engineer on a daily basis.
Provide the Engineer with asphalt manifests ofBOL's (Bill of Lad ding) on a daily basis.
Provide a daily plant diary to include a description of QC actions taken (adjustment of cold feed
percentages, changes in JMFs, etc.) include all changes or adjustments on the test summary sheets.
Provide weekly truck scale spot checks (as requested bv Emcineer).
Provide a Department approved accounting system for all mixes and provide a daily and final
Project summary of material quantities and types.
Provide a final hardcopy summary of all quality control test summary sheets and control charts at
completion of bituminous operations on the Project to the Engineer. Because Certified Plant test
data often represents test data for multiple projects, it may be necessary to make duplicate copies
of the data for each project. The Contractor shall also submit a diskette of the quality control
summary sheets, control charts and density worksheets to the Bituminous Engineer.
Furnish an automated weigh scale and computer generated weigh ticket. The ticket shall indicate
project number, mix designation (including binder grade), Mixture Design Report#, truck
identification and tare, net mass, date and time of loading. Any deviations from the minimum
information to be provided on the computer generated weigh ticket must be approved by the
Engineer in writing.
Charts and records for a mixture produced at one plant site shall be continued from contract to
contract.
Documentation (Control Charts)
The following data shall be recorded on the standardized control charts if requested bv the
Engineer, all control charts, and summary sheets shall be computer generated using software approved by the
Engineer. Software is available from the MnlDOT Bituminous Office at
www.mrr.dot.state.mn.us/pavement/bituminous/bituminous . asp.
(1) Blended aggregate gradation, include sieves shoWTI in Table 2360.2-E for specified mixture.
(2) Percent asphalt binder content (Pb)
(3) Maximum specific gravity (GmrrJ
(4) Production air voids (Va)
(5) VMA
Individual test results shall be plotted for each test point. A solid line shall connect individual
points. The moving average for each test variable shall be plotted starting with the fourth test. A dashed line shall
connect the moving average points. The Department's OWTIer's quality assurance and verification test results shall
be plotted with asterisks. Specification JMF limits shall be indicated on the control charts using a dotted line. The
Engineer may waive the plotting of control charts.
H
JlVIF Limits
The production air voids and VMA are based upon the minimum specified requirements as shown
in Tables 2360.3-B2b and 2360.3B2c. Gradations and asphalt binder content limits are based upon the current
Department reviewed Mixture Design Report. Gradation control sieves include each sieve shown in
Table 2360.2-E. The mixture production targets are listed on the Mixture Design Report. J1vfF limits are the target
plus or minus the limits shown in Table 2360A-H. JMF limits are used as the criteria for acceptance of materials
based on the moving average. A moving average is the average of the last four test results.
Page 24 of 48
2360/2350 Combined Specification
December 1, 2004
Table 2360.4-H
JMF Limits (N=4)
Item JMF Limits
VMA,% - 0.3
Production Air Voids, % -'- 1.0
Asphalt Binder Content, % -0.4
Sieve - % Passing*
25, 19, 12.5,9.5,4.75 mrn [1 inch, 3/4 inch, 1/2 inch, 3/8 inch, #4J x7
2.36 mrn [#8] x6
0.075 mrn [#200] x2.0
*.ITvIF limits are not allowed outside the broadband requirements in Table 2360.2-E.
I
JMF Bands
JMF Bands are defmed as the area between the target, as identified on the Mixture Design Report,
and the .ITvIF limits.
J
JIVIF Adjustment
The Contractor shall begin mixture production with the materials (gradation, asphalt content, and
aggregate proportions) closely conforming to the reviewed Mixture Design Report. Closely conforming shall be
defmed as aggregate proportions within 5 percent of the design proportions (1) and other mixture parameters within
the JMF limits in Table 2360.4-H. This requirement may be waived if the Contractor provides the District Materials
Laboratory with prior documented production data showing how production affects the mixture properties or if the
Contractor provides the District Materials Laboratory with a written justification or explanation of material changes
since the original mixture submittal.
(1) The Contractor shall begin mixture production using all aggregate proportions included on the Mixture Design Report unless
the aggregate proportion is shown as 0 percent.
If, during production, the Contractor determines from results of QC tests that adjustments to the
mix design are necessary to acbieve the specified properties, the following provisions shall apply. No adjustments
are allowed using aggregates or materials not part of the original mix design.
The Contractor shall make a request for a JMF adjustment to the Department Bituminous Engineer
or District Materials Engineer. The requested change will be reviewed for the Department by a Certified Level II
Bituminous QM Mix Designer. If the request meets the design requirements in Tables 2360.3-B2a and 2360.3-B2b,
a revised Mixture Design Report shall be issued. Each trial mixture design submittal as described in Section
2360.3A may have three JMF adjustments per mixture per project without charge. Additional JMF adjustments
requested must be accompanied with a $500 fee per each additional JMF adjustment, payable to the Commissioner
of Transportation.
If a .ITvIF change is requested for the 0.075 mrn [#200] sieve, the Fines to Effective Asphalt Ratio
shall be determined on the moving average from the previous four gradation tests conducted during actual
production. The adjusted .ITvIF shall be within the mixture specification gradation design broadbands shov,n in
Section 2360.2E. Should a redesign of the mixture become necessary, a new JMF shall be submitted. The JMF
asphalt content may only be reduced if the production VMA meets or exceeds the minimum VMA requirement for
the mixture being produced.
Adjustments will be made as a result of an interactive process between the Contractor, Engineer,
and District Materials Engineer. Consecutive requests for JMF adjustments, without production data, are not
allowed. The calculation of the moving average shall continue after the .ITvIF has been approved.
Page 25 of 48
2360/2350 Combined Specification
December 1,2004
J1
JMF Adjustment for Proportion Change> 10%
If a J1vIF adjustment is requested for a proportion change exceeding 10% (from the currently
produced mixture) for a single stockpile aggregate, supporting production test data from a minimum of four tests run
at an accelerated testing rate of 1 test per 450 metric tons [500 tons] must be included with the request for
adjustment. In addition to the requirements listed above, acceptable verification and approval of the requested J1vIF
will be based on individual and moving average test results. Individual test results must be within twice the
requested J1vIF limits for percent asphalt binder, production air voids, and VMA. Individual gradation must be
within twice the requested J1vIF bands. The moving average values must be within the control limits of Table
236004-H . The calculation of the moving average shall continue after the change in proportions.
If the mixture meets the specified quality indicators, the request for J1vIF adjustment will be signed
by the District Materials Laboratory and considered effective from the point the proportion change was made.
Failure to meet the quality indicators will result in reduced payment or removal and replacement with acceptable
material. Consecutive requests for J1vIF adjustments without production data is not allowed.
K
Corrective Action - Percent Asphalt Binder Content, VlVL\, and Gradation and Production
Air Voids
When the moving average values trend toward the J1vIF limits, the Contractor shall take corrective
action. The corrective action taken shall be documented on summary sheets and, if applicable, a request for J1vIF
adjustment shall be submitted to the District Materials Engineer for review and approval. All tests shall be part of
the project files and shall be included in the moving average calculations. The Contractor shall notify the Engineer
whenever the moving average values exceed the J1vIF limits.
L
Failing Materials
The detennination of price adjustments for failing materials will be based on the criteria outlined
in this Section. Material acceptance is based on individual and moving average test results. Isolated test results are
used for acceptance of air voids at the start of mixture production. Generally, individual test results which are more
than twice the J1vIF bands are considered failing. Moving average test results are considered failing when they
exceed the JNfF limits.
If the moving average values exceed the JNIF limits, the Contractor shall stop production and
make adjustments. The Contractor shall restart production only after notifying the Engineer of the adjustments that
have been made. Testing shall resume at the accelerated rates and for the tests listed in Table 236004-D for the next
1800 metric tons [2,000 tons] of mixture produced. The calculation of the moving average shall continue after the
stop in production.
Mixture produced where the moving average of four exceeds the JNfF limits shall be considered
unsatisfactory and subject to requirements of Section 236004L4, L5, L6, and L 7. Individual test failures are
discussed in Section 236004L1, L2, and L3.
When the total production of a mixture type for the entire project requires less than four tests, a
moving average will be established based on the tests taken. Acceptance of material will be consistent with the
criteria outlined in Section 236004L and will be based on the following modifications to the J1vIF limits: For two
tests, establish the new J1vIF limits by multiplying the J1vIF limits listed in Table 236004-H by 1041; for three tests,
establish the new J1vIF limits by multiplying the J1vIF limits listed in Table 236004-H by 1.15. For moving average
gradation, the modified JNfF limit cannot exceed the broadband requirements in Table 2360.2-E.
When the Contractor's testing data fails to meet specified tolerances as listed in Table 236004-M,
quality assurance/verification data shall be used in place of the Contractor's data to determine the appropriate
payment factor.
Page 26 of 48
2360/2350 Combined Specification
December 1, 2004
Ll
Isolated Failures at Mixture Start-Up - Production Air Voids
At the start-up of mixture production, before a moving average of four can be established the fIrst
three (3) isolated test results for production air voids will be used for acceptance. Isolated production air voids are
calculated by using the maximum mixture specific gravity and the corresponding bulk specific gravity from that
single test. After four (4) samples have been tested and a moving average of four can be established, acceptance
will be based on individual and moving average production air voids.
If, at the start of production, any of the first three (3) isolated test results for production air voids
exceeds twice the JMF bands from the target listed on the Mixture Design Report, the material is considered
unsatisfactory or unacceptable. Reduced payment as outlined in Table 2360.4-L3 shall apply to all tonnage placed
from the sample point of the failing test until the sample point when the isolated test result is back within twice the
JMF bands. When the failure occurs at the fIrst test, after the start of production, the tonnage subjected to reduce
payment shall be calculated as described above and shall include the tonnage from the start of production.
When isolated air voids are less than 1.0% or greater than 7.0% the Engineer will decide whether
the mixture is subject to removal and replacement or reduced payment. If the mixture is to be removed and
replaced, the Contractor at his expense will perform the work. To better defme the area to be removed and replaced
the Engineer may require the Contractor to test inplace mixture. This may include testing mixture placed prior to
the failing test result. Reduced payment will be 50 percent of the Contract bid price.
L2
Individual Failure at Mixture Start-Up - VMA
At the start-up of mixture production, before a moving average of four can be established, the first
three (3) individual test results for VMA will be used for acceptance. After 4 samples have been tested and a
moving average of four can be established, acceptance will be based on individual and moving average VMA.
If, at the start of production, any of the fIrst three (3) individual Vl'vIA test results exceeds twice
the JMF bands from the target listed on the Mixture Design Report, the material is considered unsatisfactory or
unacceptable. Reduced payment as outlined in Table 2360.4-13 shall apply to all tonnage placed from the sample
point of the failing test until the sample point when the test results are back within tvvice the JMF limits. When the
failure occurs at the fIrst test, after the start of production, the tonnage subjected to reduce payment shall be
calculated as described above and shall include the tonnage from the start of production.
L3
Individual Failure - Gradation, Percent Asphalt Binder, Production Air Voids, and VMA
Item Pay Factor (I)
Gradation 95 %
Coarse and Fine Aggregate Crushing 90%
Vl'vIA 85 %
Asphalt Binder Content 85 %
Production Air Voids (individual (-) and isolated (-,~ 70%
Table 2360.4-L3
Reduced Payment Schedule for Individual Test Results
(1) Lowest Pay Factor applies when there are multiple reductions on a single test.
(2) Individual air voids are calculated using the moving average maximum specific gravity and the
bulk specifIc gravity from that single test.
(3) Isolated air voids are calculated from the maximum specific gravity and the bulk specific gravity
from that single test. Isolated void test results are used for acceptance only for the fIrst 3 tests
after mixture production start-up.
If the individual gradation test exceeds hvice the JMF bands from the target listed on the Mixture
Design Report the material is considered unsatisfactory or unacceptable. Reduced payment as outlined in Table
2360.4-13 shall apply to all tonnage represented by the individual test.
Page 27 of 48
2360/2350 Combined Specification
December 1, 2004
If the individual tests for percent asphalt binder content, production air voids, or VMA exceeds
twice the JMF bands from the target listed on the Mix Design Report the material is considered unsatisfactory or
unacceptable. Reduced payment as outlined in Table 2360A-L3 shall apply to all tonnage placed from the sample
point of the failing test until the sample point when the test result is back within twice the JMF limits. When the
failure occurs at the first test after the start of daily production, tonnage subjected to reduced payment shall be
calculated as described above and shall include the tonnage from the start of production that day.
When individual air voids are less than 1.0% or greater than 7.0% the Engineer will decide
whether the mixture is subject to removal and replacement or reduced payment. If the mixture is to be removed and
replaced, the Contractor at his expense will perform the work. To better defme the area to be removed and replaced
the Engineer may require the Contractor to test inplace mixture. This may include testing mixture placed prior to
the failing test result. Reduced payment will be 50 percent of the Contract bid price.
L4
Moving Average Failure at Mixture Start-Up - Production Air Voids
When a moving average failure occurs within any of the first 3 moving average results after
mixture start-up (tests 4,5,6), the mixture will be considered acceptable if the individual air void, corresponding to
the moving average failure is within the JMF limits. If the individual air void is not within the JMP limit, the
mixture will be considered unacceptable and the Engineer will decide whether the mixture is subject to removal and
replacement or reduced payment. The Engineer may waive the penalty if the isolated air void corresponding to the
individual air void is within the JMF limit. If the mixture is to be removed and replaced, the Contractor at his
expense will perform the work. Reduced payment will be 50 percent of the Contract bid price. Tonnage subjected
to replacement or reduced payment shall be calculated as the tons placed from the sample point of the failing
moving average result and corresponding individual air void beyond the JMF limit to the sampling point when the
individual test result is back within the JMF limit.
L5
Moving Average Failure at Mixture Start-Up - VMA
When a moving average failure occurs within any of the fIrst 3 moving average results after
mixture start-up (tests 4,5,6), the mixture will be considered acceptable if the individual VMA, corresponding to
the moving average failure is within the JMF limits. If the individual VMA is not within the JMF limit, the mixture
will be considered unacceptable and the Engineer will decide whether the mixture is subject to removal and
replacement or reduced payment. If the mixture is to be removed and replaced, the Contractor at his expense will
perform the work. Reduced payment will be 75 percent of the Contract bid price. Tonnage subjected to
replacement or reduced payment shall be calculated as the tons placed from the sample point of the failing moving
average result and corresponding individual VMA beyond the JMP limit to the sampling point when the individual
test result is back within the JMF limit.
L6
Moving Average Failure - Production Air Voids
A moving average production air void failure occurs when the individual production air void
moving average of four exceeds the TIvIF limit. This mixture is considered unacceptable and the Engineer will
decide whether the mixture is subject to removal and replacement or reduced payment. If the mixture is to be
removed and replaced, the Contractor at his expense will perform the work. Reduced payment will be 50 percent of
the Contract bid price. Tonnage subjected to replacement or reduced payment shall be calculated as the tons placed
from the sample point of all individual test results beyond the TIvIF limits which contributed to the moving average
value that exceeded the JMF limit to the sampling point when the individual test result is back within the TIvIF limits.
When the failure occurs at the fIrst test after the start of daily production, tonnage subjected to reduced payment
shall include the tonnage from the start of production that day.
Page 28 of 48
2360/2350 Combined Specification
December 1, 2004
e uce aymen c e u e or ovmg Average est esults
Item Pay Factor (I)
Gradation 75 %(J)
Coarse and Fine Aggregate Crushing NA (individual failures only)
VN1A (-) 75 %
Asphalt Binder Content 75 %
Production Air V oids(~) 50%
R d dP
Table 2360.4-L6
tShdlt M
T R
(1)
(2)
(3)
Lowest Pay Factor applies when there are multiple reductions on a single test.
See criteria for mixture production start-up
Excluding the 0.075 rnrn [#200] sieve, use 95% pay factor iffailure is within aggregate gradation
broadband, Table 2360.2-E.
L7
Moving Average Failure - Percent Asphalt Binder Content, VNIA, and Gradation
F or mixture properties including asphalt binder content, VMA, and gradation, where the moving
average of four exceeds the JMF limits, the mixture is considered unacceptable and the Engineer will decide
whether the mixture is subject to removal and replacement or reduced payment. If the mixture is to be removed and
replaced, the Contractor at his expense will perform the work. Reduced payment will be 75 percent of the Contract
bid price. Tonnage subjected to replacement or reduced payment shall be calculated as the tons placed from the
sample point of all individual test results beyond the JJ\tIF limits which contributed to the moving average value that
exceeded the JMF limit, to the sampling point when the individual test result is back within the JMF limits. When
the failure occurs at the fIrst test after the start of daily production, tonnage subjected to reduced payment shall
include the tonnage from the start of production that day.
L8
Coarse and Fine Aggregate Crushing Failure
If any test result for Coarse Aggregate Angularity, Fine Aggregate Angularity or -4.75rnrn [- #4]
calculated crushing fail to meet minimum requirements in Table 2360.3-B2a, all material placed is subject to
reduced payment as outlined in Table 2360A-L3. Tonnage subjected to reduced payment shall be calculated as the
tons placed from the sample point of the failing test until the sampling point when the test result is back within
specifications. When the failure occurs at the fIrst test after the start of daily production, tonnage subjected to
reduced payment shall include the tonnage from the start of production that day.
M
Quality Assurance
The Engineer will periodically witness the sampling and testing being performed by the
Contractor. If the Engineer observes that the sampling and quality controJ tests are not being performed in
accordance with the applicable test procedures, the Engineer may stop production until corrective action is taken.
The Engineer will notify the Contractor of observed deficiencies promptly, both verbally and in writing.
The Engineer may obtain additional samples, at any time, to determine quality levels. These
additional samples or verification samples are described in Section 2360AN. For mixture, the Contractor shall test
their portion immediately.
All testing and data analysis shall be performed by the CertifIed Level I Bituminous Quality
Management (QM) Technician. Certification shall be in accordance with the Mn/DOT Technical Certification
Program. The Department shall post a chart giving the names and telephone numbers for the personnel responsible
for the Quality assurance program.
The Engineer shall calibrate and correlate all laboratory testing equipment in accordance with the
latest version of the Mn/DOT Bituminous Manual.
Page 29 of 48
2360/2350 Combined Specification
December 1, 2004
Table 2360.4-M
Allowable Differences (Tolerances) Between Contractor and Mn/DOT Owner Test Results*
Item Allowable Difference
Mixture Bulk Specific Gravity (Gmb) 0.030
Mixture Maximum Specific Gravity (Gmm) 0.019
VMA (Calculated) 1.2
Fine Aggregate Angularity, uncornpacted voids (U) % 1
Coarse Aggregate Angularity, % fractured faces (%P) 15
Aggregate Individual Bulk Specific Gravity (+4.75mrn [+ #4]) 0.040
Aggregate Individual Bulk Specific Gravity (-4.75mrn [- #4]) 0.040
Aggregate combined blend Specific Gravity (Gsb) 0.020
Tensile Strength Ratio (TSR) % See Table 2360.3-B2b
Asphalt Binder Content
Meter Method, % 0.2
Spot Check Method, % 0.2
Chemical Extraction Methods, % 0.4
Incinerator Oven, % 0.3
Chemical vs. Meter, Spot Check, or Incinerator methods 0.4
Incinerator Oven vs. Spot Check 0.4
Gradation Sieve % passing:
25.0, 19.0, 12.5,9.5 mrn [1 inch, 3/4 inch, 1/2 inch, 3/8 inch] 6
4.75 mm [#4] 5
2.36 mm [#8] 4
0.075 mm [#200] 2.0
*Test tolerances listed are for single test comparisons.
N
Verification Testing
A verification sample is a sample, which is sampled and tested by :.1n'DOT the Owner to assure
compliance of the Contractor's Quality Control program. A verification companion is a companion sample, to
:.1n'DOT's the Owner's verification sample, provided to the Contractor. The Contractor is required to test and use
this verification companion sample as part of the QC program. The verification companion sample will replace the
next scheduled QC sample. It is recommended enough material be sampled to accommodate retesting should the
samples fail to meet requirements as described below.
Verification testing shall be performed on at least one set of production tests Section 2360.4E,
excluding sections E9, E10, Ell, and E12, on a daily basis per mix type. The verification companion sample will be
used to verify the requirements of Tables 2360.2-E, 2360.3-B2a, 2360.3-B2b, and 2360.3-B2c and will be compared
to the Verification sample for compliance with allowable tolerances as specified in Table 2360.4-M. These include
the mixture properties of Gmm (mixture max gravity), Gmb (mixture bulk gravity), asphalt binder content, VMA
(calculated), Coarse and Fine Aggregate crushing, and gradation. For Coarse and Fine Aggregate crushing that
meets the requirements of Section 2360.4E7 and 2360AE8 the one test per week shall be performed on a verification
companion. These do not include the aggregate bulk specific gravity Gsb, fines to effective asphalt, or the tensile
strength ratio (TSR). Asphalt binder content and gradation must be determined by either extraction method
2360.4E1b or 2360AE1c. Asphalt content from the verification test result must be used to determine VMA.
The Department's Owner's verification test results will be available to the Contractor within 2
working days from the time the sample is delivered to the District Laboratory Engineer for Gmmmixture max
gravity, Gmb mixture bulk gravity, air voids (calculated), asphalt binder content, VMA (calculated). Gradation and
crushing results will be provided to the Contractor within 3 :Nfn/DOT working days. Once the verification test
results are available, they will be included on the test summary sheet. These results and those from the Contractor's
verification companion will be compared for allowable tolerances as specified in Table 2360.4-M. If the tolerances
are met, the verification process is complete.
Page 30 of 48
2360/2350 Combined Specification
December 1,2004
If the tolerances between Department Owner and Contractor are not met, retests of the material
shall be conducted by the Departmont Owner. If the retests fail to meet tolerances, the Department's Owner's
verification test results will be substituted for the Contractor's results in the QC program and used for acceptance.
Only those parameters out of tolerance will be substituted and, if applicable, volumetric properties will be
recalculated (1).
When tolerances from the verification sample retests are not met, an investigation will begin
immediately to determine the cause of the difference. Testing equipment, procedures, worksheets, gyratory
specimen height sheets, and personnel will be reviewed to determine the source of the problem The ~
Materials Engineer may also require a hot-cold comparison of mixture properties be performed. The procedure for
hot-cold comparisons is as follows:
The hot-cold comparison sample will be split into three representative portions. The Engineer will
observe the Contractor testing the sample. One part shall be compacted immediately while still
hot (additional heating maybe required to raise the temperature of the sample to compaction
temperature). The second and third part will be allowed to cool to air temperature. The
Contractor will retain the second part and the third part will be transported to the District :.'1aterials
Laboratory Engineer. On the same day and at approximately the same time the Contractor and the
District :.'Iaterials Laboratory Engineer will heat their samples to compaction temperature and
compact them. From this information a calibration factor will be developed to compare the
specific gravity of the hot compacted samples to reheated compacted samples. Each test will
involve a minimum of three Marshall specimens or two gyratory specimens. This test may be
repeated at the discretion of the Contractor or the District ~Materials Engineer.
Note: Care must be taken when reheating samples for mixture properties analysis tests. Mix samples
should be reheated to 700C [1600F] to allow splitting of the sample into representative fractions
for the various tests. Overheating of the mixture portions to be tested for maximum specific
gravity (Rice Test) may result in additional asphalt being absorbed in the aggregate.
The Department Owner will test the previously collected QA samples until they meet the
tolerances or the remaining samples are all tested. Once these samples are tested, the department Owner will test
QA samples subsequent to the verification sample until tolerances are met. Acceptance will be based on QC data
with substitution of Department Ovmer test results for those parameters out of tolerance (1). If reestablishment of
test result tolerances is not achieved within 48 hours, the Contractor shall cease mixture production and placement
until the problem is resolved.
(1) If, through analysis of data, it is determined there is a bias in the test results, the Engineer will determine
which results are appropriate and shall govern. Methods to analyze data for determination of bias are on
file in the Bituminous Office.
2360.5 CONSTRUCTION REQUIREMENTS
A General
The following construction requirements provide for the construction of all courses. When
construction is under traffic, the requirements ofMn/DOT 2221.3D \vill apply.
B
Restrictions
In general, no work within the roadway will be permitted in the spring until seasonal load
restrictions on roads in the vicinity have been removed. However, work within the roadbed may be permitted before
that time if, in the opinion of the Engineer, it can be done without damage to the subgrade. fu\1A shall not be placed
when, in the opinion of the Engineer, the weather or roadbed conditions are unfavorable.
Page 31 of 48
2360/2350 Combined Specification
December 1, 2004
No asphalt pavement wearing course (final wearing course if multiple wearing courses) shall be
placed after October 15th in that part of the state north of an east-west line between Browns Valley and Holyoke,
nor after November 1st south of that line. The Engineer may waive these restrictions when;
(1) The asphalt mixture is not being placed on the traveled portion of the roadway, or
(2) The roadway involved will not be open to traffic during the following winter, or
(3) The Engineer directs in writing the mixture be placed.
The Contractor shall not use petroleum distillates such as kerosene and fuel oil to prevent adhesion
of asphalt mixtures in pavement hoppers, truck beds, or on the contact surfaces of the compaction equipment.
Anti-adhesive agent must meet the criteria for "Effect on Asphalt" as described in the most recent Asphalt Release
Agent Report on file in MnlDOT's Office of Environmental Services and the Bituminous Office.
C
Equipment
Cl
Asphalt Mixing Plants
CIa
Requirement for All Plants
The Contractor shall test and calibrate all scales according to lVIn/DOT 1901, except as otherwise
designated by the Contract.
Cla(l)
Equipment for the Preparation of the Aggregate
Add mineral filler to the mixture using a storage silo equipped with a device to ensure a constant
and uniform feed.
Cla(2)
Equipment for the Preparation of Asphalt Material
Tanks for storage of asphalt material at the plant shall be equipped to heat the material and
maintain the material at the required temperatures. The discharge end of the circulating line shall be below the
surface of the asphalt material. Provide agitation for modified asphalt, when used, ifrecommended by the supplier.
An outage table or chart and measuring stick shall be provided for each storage or working tank.
Tanks shall be equipped with provisions for taking of asphalt binder material samples. After delivery of asphalt
binder material to the Project, the Contractor shall not heat the material above 1750C [350oF]. For modified asphalt,
the maximum storage temperature shall not exceed the recommendation of the asphalt supplier.
Cla(3)
Asphalt Binder Control
\Vhen asphalt binder material is proportioned by volume, the plant shall be equipped with either a
working tank or a metering system for determining asphalt binder content of the mixture.
The working tank shall have a capacity between 3 800 L [1,000 gallons] and 7 600 L
[2,000 gallons]. The working tank shall be calibrated and supplied with a calibrated measuring stick. The tank may
be connected to a mixing unit and used only during spot check operations, but it shall be available at all times. Any
feedback shall be returned to the working tank during spot check operations.
Page 32 of 48
2360/2350 Combined Specification
December 1,2004
The metering system shall consist of at least one approved asphalt binder flow meter in addition to
the asphalt binder pump. The flow meter shall be connected to the asphalt binder supply to measure and display
only the asphalt binder being fed to the mixer unit. The meter readout shall be positioned for convenient
observation. Means shall be provided for comparing the flow meter readout with the calculated output of the asphalt
binder pump. In addition, the system shall display in liters [gallons] or to the nearest 0.001 metric tons [0.001 tons],
the accumulated asphalt binder quantity being delivered to the mixer unit. The system shall be calibrated and
adjusted to maintain an accuracy of:t one percent error. This calibration shall be required for each plant set-up prior
to production of mixture.
C1a(4)
Dryer: The aggregate shall be free of unburned fuel.
C1a(5)
Thermometric Equipment:
The plant shall be equipped with a sufficient number of thermometric instruments to ensure
temperature control of the aggregate and the asphalt binder material.
C1a(6)
Pollution Controls
C1a(6)(a)
Po 11 u ti 0 n.............................................................................................................................. ....... 1717
C1a(7)
Surge and Storage Bins
The plant may include facilities to store hot asphalt mixture for coordinating the rate of production
with the paving operations. Storage of the hot mixture will be permitted for a period not to exceed 18 hours,
provided the following requirements are met:
(a)
Hot mix storage facilities shall be designed and operated to prevent segregation of the mix,
drainage of the asphalt from the mix, and to prevent excessive cooling or overheating of the
mixture.
(b)
The temperature of the mixture at time of discharge from the storage facility shall be within a
tolerance of 50C [90F] of the temperature when discharged from the silo or mixer.
C2
Placement and Hauling Equipment
All equipment shall be serviced away from the paving site to prevent contamination of the
mixture. Units that drip fuel, oil, or grease shall be removed from the paved surface until such leakage is corrected.
C2a
Asphalt Pavers
Asphalt pavers shall be self-contained, power-propelled units, with an operational vibratory
screed, capable of spreading and finishing courses of asphalt plant mix material in widths applicable to the specified
typical sections and thiclmesses, indicated in the Contract.
The screed or strike-off assembly shall produce a fInished surface of the required evenness and
texture without tearing, shoving, or gouging. For mainline paving, screed extensions and auger extensions are
required if the paving width on either side of the paver is greater than the basic screed unless otherwise directed by
the Engineer. Strike-off only extension assemblies are not allowed for mainline wearing course paving, unless
directed by the Engineer.
Automatic screed control by means of an erected string line shall only be required when stated in
the Contract.
All pavers shall be equipped with an approved automatic screed control. The automatic controls
shall include a system of sensor-operated devices, which follow reference lines, or surfaces on one or both sides of
the paver as required. The speed of the paver shall be adjusted to produce the best results.
Page 33 of 48
2360/2350 Combined Specification
December 1, 2004
All mixtures shall be spread without segregation to the cross sections shown in the plans. In
general, leveling layers shall be spread by the method producing the best results as approved by the Engineer. The
objective is to secure a smooth base of uniform grade and cross section so that subsequent courses will be uniform in
thickness. The leveling layer may be spread with a properly equipped paver or, when approved by the Engineer, a
motor grader equipped with a leveling device, or with other means for controlling the surface elevation of the
leveling layer.
All mixtures shall be spread, to the fullest extent practicable, by an asphalt paver. When approved
by the Engineer, mixtures may be spread by a motor grader in areas that are inaccessible to a paver such as on
driveway entrances, irregular areas, short isolated areas or when the quantity of mixture makes it impractical to
place with a paver.
On shoulder surfacing and uniform width widening, when the placement width is too narrow for a
paver, the mixture in each course shall be spread with an approved mechanical device.
The placement of each course shall be completed over the full width of the section under
construction on each day's run unless otherwise directed by the Engineer.
C2b
Trucks
Trucks for hauling asphalt mixtures shall have tight, clean, and smooth beds. Mixture shall not be
allowed to adhere to the truck beds. Adherence may be prevented by spraying the truck bed with an anti-adhesive
agent in accordance with Section 2360.5B. Each truck shall be equipped with a cover of canvas or other suitable
material to protect the mixture from weather. The cover shall extend at least 300 mID [1 foot] over the sides and be
attached to tie-downs unless the truck is furnished with a mechanical or automated covering system, which prevents
airflow underneath by stretching the cover tightly on the top of or inside the sideboards. The cover shall be used
when directed by the Engineer.
C2c
Motor Graders
Motor graders shall be self-propelled and have pneumatic-tires with a tread depth of 13 mID
[112 inch] or less. They shall be equipped with a blade not less than 3 m [10 feet] in length and shall have a
wheelbase of not less than 4.5 m [15 feet].
D
Treatment of the Surface
Dl
Tack Coat
An asphalt tack coat shall be applied to existing asphalt and concrete surfaces, and to the surface
of each course or lift constructed, except for the final course or lift, according to Mn/DOT 2357. Emulsified asphalt
tack coats shall be allowed to break, as indicated by a color change from browll to black, before a subsequent lift is
placed.
The contact surfaces of all fixed structures and the edge of the in-place mixture in all courses at
transverse joints and longitudinal joints shall be given a uniform but not excessive coating ofliquid asphalt or
emulsified asphalt before placing the adjoining mixture.
E
Compaction Operations
After being spread, each course shall be compacted to the required density. The rollers shall, as
practicable, be operated continuously so all areas are thoroughly compacted to the required density. When not
operating, the rollers shall not stand on the uncompacted mixture or newly rolled pavement having a surface
temperature exceeding 600C [1400F]. Rolling with steel-wheeled rollers shall be discontinued if it produces
excessive crushing or pulverizing of the aggregate or displacement of the mixture.
Page 34 of 48
2360/2350 Combined Specification
December 1, 2004
To prevent adhesion of the mixture to the steel roller wheels, the contact surfaces of the wheels
shall be kept properly moistened using water or a water solution containing small quantities of a detergent or other
approved material.
To secure a true surface, variations such as depressions or high areas, which may develop during
rolling operations, and lean, fat or segregated areas shall be corrected by removing and replacing the material in the
defective area. All such corrections shall be accomplished as directed by the Engineer at no expense to the
Department Owner.
When mixtures are spread by a motor grader, pneumatic-tired rollers shall compact the mixture
simultaneously with the spreading operation.
F
Construction Joints
Joints shall be thoroughly compacted to produce a neat, tightly bonded joint that meets surface
tolerances. Both transverse and longitudinal joints are subject to density requirements as outlined in Section 2360.6
Pavement Density.
Fl
Transverse Joints
A transverse joint (full paver \vidth at right angles to the centerline) shall be constructed when
mixture placement operations are suspended. The forward end of the freshly laid strip shall be thoroughly
compacted by rolling before the rni,<ture has cooled. When work is resumed, the end shall be cut vertically for the
full depth of the layer unless a formed edge is constructed as approved by the Engineer.
F2
Longitudinal Joints
Longitudinal joints between strips shall be parallel to the centerline. In multiple lift construction,
the longitudinal joints between strips in each lift shall be constructed not less than 150 rnm [6 inches] measured
transversely from the longitudinal joints in the previously placed lift. When the wearing course is constructed in an
even number of strips, one longitudinal joint shall be on the centerline of the road. When it is constructed in an odd
number of strips, the centerline of one strip shall be on the centerline of the road, provided that no joint is located in
the wheel path area of a traffic lane. Longitudinal joints in multiple lift construction over Portland cement concrete
pavements may be aligned directly over the concrete pavement longitudinal joints at the discretion of the Engineer.
At longitudinal joints formed by placing multiple strips, the adjoining surface being laid shall,
after final compacting, be slightly higher (but not to exceed 3 rnm [1/8 inch]) than the previously placed strip.
When constructing a strip adjoining a previously placed strip or a concrete pavement, any fresh mixture that
overlaps a previously placed strip or pavement shall be removed (to the longitudinal joint line) before any rolling is
done.
G
Asphalt Mixture Production (FOB Department Owner Trucks)
For asphalt mixture production, the Contractor shall, in addition to the asphalt mixture required on
the Project, produce and deliver asphalt mixture to the Depar1:rnent Owner. The mixture shall be the mixture being
produced and shall be loaded on Department Owner furnished trucks at the mixing plant at a time agreed on by the
Engineer and Contractor. The Engineer will notify the Contractor of the total quantity of mixture desired not less
than 2 weeks prior to completion of the wearing course construction. The Engineer will not accept the asphalt
mixture if it is inappropriate for the Department's Owner's intended use.
H
Small Quantity HlVL<\. Paving
Unless otherwise indicated in the Special Provisions, the following provision for a small quantity
of asphalt mixture shall apply.
Page 35 of 48
2360/2350 Combined Specification
December 1, 2004
A Mixture Design Report is not required for planned proj ect quantities less than 191,200 m2 rnrn
[9,000 square yard inches [4,500 square yards per 2 inch thickness, etc]) or 450 metric tons [500 tons].
However, the Contractor shall verify in writing the asphalt mixture delivered to the project meets the requirements
of Table 2360.3-B2a and Table 2360.3B2b. The Department O\vner will obtain samples, as determined by the
Engineer, to verify percent design air voids and gradation. These results will be used for material acceptance. Air
voids will be subject to the requirements of Section 2360AL1 b for isolated air voids and a gradation falling outside
the requirements of Table 2360.2-E will be subject to payment as indicated in Table 2360A-L2b.
2360.6
PAVEMENT DENSITY
A
General
All pavements will be compacted in accordance with the Maximum Density Method unless
otherwise specified in the Contract special provisions or as noted in Section 2360.6C.
B
Maximum Density Method
All courses or layers of plant mixed asphalt mixtures for which the Maximum Density Method is
used shall be compacted to a density not less than the percentage shown in the Table of Required Density, Table
2360.6-B2, for the applicable mixture and course.
Bl
Maximum Density Determination
The Density requirements listed in Table 2360.6B2 are percent of maximum specific gravity
(G~ based on the individual lot. The Maximum specific gravity value used to calculate the percentage density for
the lot shall be the average value obtained from the maximum gravity results from production tests taken during that
days paving. If only one or two maximum specific gravity values were obtained that day, then the moving average
value (at that test point) shall be used. If three or more maximum specific gravity values are obtained that day, then
the average of those tests alone shall be used as indicated above.
Bla
Pavement Density Determination
The density of each lot shall be expressed as a percentage of the maximum specific gravity
(% Grnm) obtained by dividing the average bulk specific gravity for the lot by the maximum specific gravity
multiplied by 100, (maximum specific gravity basis is the average Grnm of QC tests done on the day that the
individual lot was paved as described above). Determination of the bulk specific gravity of the cores shall be in
accordance with AASHTO T-166, Mn/DOT modified. For coarse graded mixtures the Engineer may require
determination of bulk specific gravity of the cores be in accordance with ASTM Dl188, Mn/DOT modified. ASTM
D6752 Mn/DOT modified (Corelok) is also allowed for determination of bulk specific gravity of coarse graded
mixtures. Selection of the test method to determine coarse graded mixture bulk specific gravity shall be agreed upon
at the time of mix design submittal. Both the Contractor and ~,1:nrnOT Owner shall use the same test method to
determine bulk specific gravity. The detennination of coarse and fme graded mixtures will be based on the
percentage of material passing the 2.365 rom sieve [#8] as defmed in Table 2360.3-B2c.
Compaction operations shall be completed within 8 hours of mixture placement and before core
samples are obtained for density determination. Only pneumatic tired or static steel rollers are permitted for any
compactive effort performed between 6 and 8 hours after mixture placement.
Compacted mixtures represented by samples or tests having deficient densities shall not be re-
rolled. The Contractor shall not operate below the specified minimum density on a continuing basis. A continual
basis shall be defmed as all lots in a day's production failing to meet minimum density or more than 50% of lots on
multiple days which fail to meet minimum density requirements. Production shall be stopped until the source of the
problem is determined and corrective action is taken to bring the work into compliance with specified minimum
required density.
Page 36 of 48
2360/2350 Combined Specification
December 1, 2004
B2
Required Density
Minimum density requirements for both gyratory (SP) and Marshall designed mixtures are listed
in Table 2360.6-B2.
Unless otherwise indicated in the Plans or Special Provisions, shoulders wider than 1.8 meters
[6 feet] paved shall be compacted by the Maximum Density Method. When shoulders are required to be compacted
by the Maximum Density Method and are paved in a separate operation or have a different required minimum
density than the driving lane, the lot tonnage placed on the shoulder shall be delineated in separate lots from the
driving lanes for the day paving was conducted.
Unless otherwise indicated in the Plans or Special Provisions a narrow shoulder, 1.8 meter [6 feet]
or less wide, that is paved in the same pass as a driving lane or that is paved separately will be compacted by the
Ordinary Compaction Method. Mixture compacted under Ordinary Compaction is excluded from lot density
requirements and that tonnage is also excluded from incentive/disincentive payment.
If the Plans or Special Provisions indicate a narrow shoulder is to be compacted by the Maximum
Density Method, the minimum required density is listed in Table 2360.6-B2. If the minimum required density of the
shoulder is different than the driving lane, the tonnage placed on the shoulder shall be delineated in separate lots
from the driving lane.
Echelon paving (two pavers running next to each other in adjacent lanes) shall be considered
separate operations.
Table 2360.6-B2
Reouired Minimum Density
SP Wear and All MY SP Nonwear (1)(2) SP Shoulders (1)(2)
and L Y Mixtures (1)(2)
Location from ~ 100 mrn [4 inch]** > 100 mrn [4 inch]** Designed at Designed at
surface * 3% voids 4% voids
% Gmrn 92.0 93.0 93.0 92.0
1)
2)
* SP Mixtures only
** Ifless than 25% of a layer is within 100 mrn [ 4 inches] of the surface, the layer may be
considered to be below 100 mrn [4 inches] for mix design purposes.
Minimum reduced by one percent on the fIrst lift constructed over PCC pavements.
Minimum reduced by one percent for the first lift constructed on aggregate base (mainline and
shoulder), reclaimed or cold inplace recycled base courses and fIrst lift of an overlay on a roadway
with a 6.35 metric ton [7 ton] or less spring load restriction (roadway includes shoulders).
B2a
Lots & Core Locations
Table 2360.6-B2a
Lot Determination
Daily Production
Metric (ton) [English (Ton)] Lots
270* - 545 . [300* - 600] 1
546 - 910 [601 - 1,000] 2
911 - 1,455 [1,001 -1,600] 3
1,456 - 3,275 [1,601 - 3,600] 4
3,276 - 4,545 [3,601 - 5,000] 5
4,546 + [5,001 +] 6
*When mix production is less than 270 metric tons [300 tons], establish 1st lot when accumulative
tonnage exceeds 270 metric tons [300 tons].
Page 37 of 48
2360/2350 Combined Specification
December 1, 2004
Divide the days production into equal lots as shown in Table 2360.6-B2a. The Engineer may
require additional density lots be established to isolate areas affected by equipment malfunctionlbreakdown, heavy
rain, or other factors that may affect the normal compaction operations. Obtain three cores in each lot. Two cores
will be taken from random locations selected by the Engineer. The third core, a companion core, shall be taken
within 0.3 meters [1 foot] longitudinally from either of the fIrst two cores. The companion cores shall be given to
the Department Owners Street Inspector immediately upon completion of coring and sawing. The random locations
will be determined by the Engineer using statistically derived stratified random number tables or other approved
methods of random number generation. These will also be used for partial lots. Both transverse and longitudinal
joints are subject to maximum density requirements. If the random core location falls on an unsupported joint, at the
time of compaction, (the edge of the mat being placed does not butt up against another mat, pavement surface, etc.)
cut the core with the outer edge of the core barrel 0.3 meters [1 foot] away (laterally) from the edge of the top of the
mat (joint). If the random core location falls on a confmed joint (edge of the mat being placed butts up against
another mat, pavement surface, curb and gutter, or fixed face), cut with the outer edge of the core barrel 150 rnrn::l::
12.5 rnrn [6 inches::l:: 0.5 inch] from the edge ofthe top of the mat (ex. center of 100 rnrn [4 inch] core barrel
200 nun::l:: 12.5 nun [8::1:: 0.5 inches] from the edge of the top of the mat). Cores will not be taken \vithin 300 rnrn
[1 foot] of any unsupported edge The Contractor shall be responsible for maintenance of traffic, coring, patching the
core holes, and sa\ving the cores if necessary to the proper thickness prior to density testing.
B3
Core Testing
Cores will be taken and tested by the Contractor. Core locations will be determined and marked
by the Engineer. The Contractor shall schedule the approximate time of testing during normal project work hours so
that the Engineer may observe and record the saturated surface dry and immersed weight of the cores.
Density determination will be made by the end of the next working day after placement and
compaction. If multiple layers are placed in a single day, cores shall be sawn and separated for each layer, tested
and reported by the end of the next working day.
The Contractor will cut pavement samples from the completed work with power equipment, and
restore the surface by the end of the next working day with new, well compacted mixture without additional
compensation. Failure to restore the surface within 24 hours of coring shall subject the Contractor to a fme of $1 00
per working day, per lot, until the core holes are restored. Cores shall be cut using a 100 nun [4 inch] minimum
outer diameter coring device. All samples shall be marked with the lot number and core number or letter. The cores
shall be transported to the laboratory as soon as possible to prevent damage due to improper handling or exposure to
heat. These companion cores may be tested by the Inspector on Department scales or transported to the
Department's Field Laboratory or District ~,1aterials Engineer's Laboratory.
Measure each core three times for thickness prior to saw cutting, report the average lift thickness
on the core sheet. These average thickness will contribute to thickness compliance as described in Section 2360.7A
If the Department Owner companion core test result for bulk specific gravity (Gmb) deviates
beyond the allowable tolerance of 0.030, substitute Department Ovvner companion result for Contractor's core result
and then average the Department Owner result \\'ith the non-companion result for the lot density acceptance. If,
through analysis of data, it is determined there is a bias in the test results, the Engineer will determine which results
are appropriate and shall govern.
If the Gmb tolerance fails in more than 2 lots in a day of either consistently high or low differences
between the companion cores then an investigation to determine the source of errors shall be conducted.
Companion cores samples shall be increased to two per lot and tested until investigation is complete and tolerances
are met.
The Engineer may allow recoring of a sample only when the core has been damaged through no
fault of the Contractor, either during the coring process or in transit to the laboratory.
Page 38 of 48
2360/2350 Combined Specification
December 1,2004
B4
Maximum Density Acceptance and Payment Schedule
The density of compacted mixture shall be accepted by pavement cores on a lot basis.
The Contractor's cores will be used for acceptance if the determined bulk specific gravity Gmb
from AASHTO T -166, 1'1nIDOT modified or ASTM D 1188 is within.:t 0.030 of the state Owner companion Gmb
value. Payment for lot densities of compacted mixture shall be determined from Table 2360.6-B4 or 2360.6-B4A.
Incentive and disincentive payments are for both wearing and non-wearing courses.
"Vhen the density requirement has been reduced by one percent, per Table 2360.6-B2, footnote 1
& 2, payment adjustments for lot densities will be made as specified in Table 2360.6-B4A. Incentive payments are
excluded when the minimum density has been reduced. However, at the Contractors request and with approval of
the Engineer, the reduced density requirement may be waived and density evaluated under Table 2360.6-B4,
including incentives, for first lift constructed on aggregate base, reclaimed or cold inplace recycled base courses and
first lift of an overlay on a roadway with a 6.35 metric ton [7 ton] or less spring load restriction (reduced density
shall not be waived for the fIrst lift constructed on PCC pavements). The request and approval shall be made after
the fIrst days paving and before the third days paving begins. Once the request has been approved, evaluation of
density \vill be in accordance \vith Table 2360.6-B2 (excluding footnote 2) and Table 2360.6-B4, and will remain in
effect for the duration of mixture placement on that lift. The Contractor will also be responsible for compliance with
any construction requirements on subsequent lifts.
Table 2360.6-B4
Payment Schedule for Maximum Density
Percent of Max Specific Gravity (-) Percent of Max Specific Gravity (2) Percent
SP Wear (:0;100 rnm [4 inches] from Surface) SP Non-Wear (>100 rnm [4 inches] from Surface) Payment
All MV & LV , SP Shld (4% Void) SP Shoulders (3% Void)
93.6 and above 94.6 and above 104 (~)
93.1 - 93.5 94.1 - 94.5 102 (J)
92.0 - 93.0 93.0 - 94.0 100
91.0-91.9 92.0- 92.9 98
90.5 - 90.9 91.5 - 91.9 95
90.0 - 90.4 91.0-91.4 91
89.5 - 89.9 90.5 - 90.9 85
89.0 - 89.4 90.0 - 90.4 70
Less than 89.0 (4) Less than 90.0 (4)
Table 2360.6-B4A (1)
1 % Reduced Table
Percent of Max Specific Gravity (i) Percent of Max Specific Gravity (2) Percent
SP Wear (:0;100 rnm [4 inches] from Surface) SP Non-Wear (>100 rnm [4 inches] from Surface) Payment
All MV & LV , SP Shld (4% Void) SP Shoulders (3% Void)
91. 0 and above 92.0 and above 100
90.0 - 90.9 91.0- 91.9 98
89.7 - 89.9 90.5 - 90.9 95
89.4 - 89.6 90.0 - 90.4 91
89.2 - 89.3 89.5 -89.9 85
89.0 - 89.1 89.0 - 89.4 70
Less than 89.0 (4) Less than 89.0 (4)
(1) Minimum reduced by one percent for the fIrst lift constructed on aggregate base (mainline and
shoulder), reclaimed or cold inplace recycled base courses and fIrst lift of an overlay on a roadway
with a 6.35 metric ton [7 ton] or less spring load restriction (roadway includes shoulders).
Minimum reduced by one percent on the fIrst lift constructed on PCC pavements (reduced density
cannot be waived).
Page 39 of 48
2360/2350 Combined Specification
December 1,2004
(2) In calculating the percent of maximum specific gravity, report to the nearest tenth.
(3) The payment in this portion of the specification shall apply only if the day's weighted average
individual production air voids are within - 0.5 percent of the target air void value. The weighted
average air voids shall be based on all the mixture production tests (2360.4e) for the corresponding
day and shall be weighted by the tons the corresponding test represents.
(4) The HJ.\1A material represented by the lot shall be paid at a 70% pay factor, unless a single core
density is less than 87.0% of the maximum specific gravity (Grnrn). Ifa single core density is less
than 87.0% of Gmm, the material shall be removed and replaced by the Contractor at their expense
\vith mixture that meets the density requirements; or the Engineer may permit the unacceptable
material to remain inplace with a 50% pay factor. The limits of the area to be removed will be
determined by additional core samples. These additional core samples shall be taken at the same
offset from centerline as the original core; unless the original low density core was taken within
0.45 m [1.5 feet] of an edge of the paver pass. In that case, the additional cores shall be taken
0.45 m [1.5 feet] from the edge of the paver pass. The densities shall be determined at 15 m
[50 foot] intervals, both ahead and back of the point of unacceptable core density (less than 87.0%
of Grnrn), until a point of acceptable core density (87.0% of Grnrn or greater) is found. If the
incremental core density testing extends into a previously accepted lot, removal of the
unacceptable material will be required; however, the results of these tests shall not be used to
recalculate the previously accepted lot density. All costs incurred from additional coring and
testing, resulting from unacceptable core density, will be paid by the Contractor. The
unacceptable pavement area is to be computed as the product of the longitudinallirnits so
determined by the 15 m [50 foot] cores and the full width of the paver pass, laying in the traffic
lane or lanes. Shoulders shall be exempt from this calculation unless density failure occurred in
the shoulder area.
After the unacceptable material (core density less than 87.0% of Grnrn) has been removed and
replaced, the density of the replacement material will be determined by the average of two cores.
Payment for the replacement material will be in accordance with Tables 2360.6-B4 or
2360.6-B4A, whichever applies. There will be no payment for the material removed. The
remainder of the original lot shall have a 70% pay factor.
c
Ordinary Compaction Method
Ordinary compaction shall be used for layers identified in the typical sections with a minimum
planned thiclmess ofless than 40 rnrn [11/2 inches], thin lift leveling, wedging layers, patching layers, driveways,
areas which cannot be compacted with standard highway construction equipment. Unless otherwise indicated in the
Plans or Special Provisions recreational trails shall also be compacted by ordinary compaction. The ordinary
compaction method shall not be used on mainline, ramp, or loop paving, unless otherwise designated in the plans or
special provisions. When density is evaluated by the ordinary compaction method a control strip shall be used to
establish a rolling pattern. This shall be used by the Contractor for the compaction of the asphalt mixture for the
layer on which the control strip is constructed, or until a new control strip is constructed. The control strip
requirement may be waived by the Engineer in small localized areas or other areas not conducive to its
establishment.
A control strip shall be constructed at the beginning of the work on each lift of each course. Each
control strip shall have an area of at least 330 m2 [395 square yards] and shall be of the same thiclmess as the lift it
represents. The subgrade or pavement course upon which a control strip is to be constructed shall have the prior
approval of the Engineer. The control strips shall remain in place and become part of the completed work.
The materials used in the construction of the control strips shall conform to the specified
requirements for the course. The materials used in the control strip shall be from the same source and of the same
type as the materials used in the remainder of the course that the control strip represents.
Page 40 of 48
2360/2350 Combined Specification
December 1, 2004
The equipment used in the construction of the control strips shall be approved by the Engineer and
shall be the same type and mass used on the remainder of the pavement course represented by the control strip. A
minimum of two rollers shall be required. A rolling pattern shall be established for each roller. A pneumatic-tired
roller shall be available for compaction operations within 24 hours after request by the Engineer. The fInal rolling
shall be performed with a tandem steel-wheeled roller. Areas that are inaccessible to the conventional type rolling
equipment shall be compacted to the required density by using trench rollers or mechanical tampers.
Construction of the control strips will be as directed by the Engineer. Compaction shall
commence as soon as possible after the mixture has been spread to the desired thickness and shall continue until no
appreciable increase in density can be obtained by additional roller's coverages. Densities will be determined by
means of a portable nuclear testing device or suitable approved alternate and a growth curve shall be developed to
determine the optimum rolling pattern. The Contractor shall furnish documentation of the growth curve to the
Engineer.
To determine when no appreciable increase in density can be obtained, two test points shall be
established in the control strip on a random basis and the density at each point shall be measured by a portable
nuclear device or suitable approved alternate after each roller pass. Rolling shall be suspended when testing shows
either a decline of more than 2% of the maximum specific gravity or when additional roller passes fail to increase
the density.
After said testing is accomplished, rolling on the remainder of that course shall be done in
accordance with the pattern developed in the test strip for that roller. A separate rolling pattern and time interval
shall be established for each roller.
A new control strip shall be ordered by the Engineer when:
(a) A change in the JMF is made, or
(b) A change in the source of material is made or a change in the material from the same
source is observed.
A new control strip may be ordered by the Engineer or requested by the Contractor when:
(a) Ten days of production have been accepted without construction of a new control strip, or
(b) There are other reasons to believe that a control strip density is not representative of the
HMA mixture being placed.
The nuclear testing device shall be furnished and operated by the Contractor. The furnishing of
the testing device and the operator will be considered incidental to the furnishing and placement of the HMA
mixture and shall not be compensated for separately. The device shall be calibrated according to procedures
described in the Mn/DOT Bituminous Manual.
Each course shall be uniformly compacted until there is no further evidence of consolidation and
all roller marks are eliminated. When this method is employed, and the quantity of mixture placed by the paver
exceeds 100 metric tons [11 0 tons] per hour, at least two rollers are required for compacting the mixture placed by
each paver.
CI
Rollers
The following requirements for rollers apply only when compaction is obtained by the ordinary
compaction method.
Page 41 of 48
2360/2350 Combined Specification
December 1, 2004
i
C2
Steel-Wheeled Rollers
Steel-wheeled rollers shall be self-propelled and has a minimum total mass on.3 metric tons
[8 tons], or as otherwise specified in the Contract. When vibratory rollers are used, they shall produce 45 kN per
meter [3,085 lbf per foot] of width. The frequency should be at least 2400 vpm and amplitude setting low. The
roller shall be capable of reversing without backlash and shall be equipped with spray attachments for moistening all
rollers on both sets of wheels.
C3
Pneumatic-Tired Rollers
The pneumatic-tired roller shall have a compacting width of 1.5 m [5 feet] or more. It shall be so
constructed that the gross wheel load force shall be a minimum of 13 kL'\T [3,000 pounds] per wheel for LV and MY
mixtures and SP Level 2-3 mixtures and 22 kL'\T [5,000 pounds] per wheel for SP Level 4-6 mixtures and can be
varied as directed by the Engineer. The tire arrangement shall be such that full compaction \vill be obtained over the
full width with each pass of the roller.
The roller may be self propelled or provided with suitable tractive equipment, unless otherwise
specified in the Contract. If more than one roller is propelled by a single tractive unit, then that combination \vill be
counted as a single roller unit.
C4
Trench Rollers
Trench rollers shall be self propelled and have a mass of not less than 4 400 kg per meter
[2,960 pounds per foot] of width.
C5
Mixture Temperature Controls
If compaction is obtained by the ordinary compaction method, the minimum 1aydown temperature
in all courses (as measured behind the paver or spreading machine) of the asphalt mL"\.ture shall be in accordance
with the temperature requirements of Table 2360.6-C5. Unless directed by the Engineer in writing, no paving is
allowed under the Ordinary Compaction Method when the air temperature is below OOC [320F].
lxture emperature ontro
Air Compacted Mat Thickness, mm (A)
Temperature
oc [OF] 25 mID [1 inch] 40 mID [1-1/2 inch] 50 mm [2 inch] >75 mID [3 inch]
+0-5 [32-40] -- 129 (<>) [265] 124 [255] 121 [250]
+ 6-10 [41-50] 130 (l:l) [270] 127 [260] 121 [250] 118 [245]
+ 11-15 [51-60] 127 (l:l) [260] 124 [255] 118 [245] 115 [240]
+ 16-21 [61-70] 121(<>) [250] 118 [245] 115 [240] 113 [235]
+ 22-27 [71-80] 118 [245] 115 [240] 113 [235] 113 [235]
+ 28-32 [81-90] 113 [235] 110 [230] 110 [230] 11 0 [230]
+ 33 [91+] 110 [230] 110 [230] 110 [230] 107 [225]
Table 2360.6-C5
M' T C
(A) Based on approved or specified compacted lift thickness.
(B) A minimum of one pneumatic-tire roller shall be used for intermediate rolling unless otherwise
directed by the Engineer. The Engineer may specify or modify in \witing (with concurrence from
the Department Bituminous Engineer) a minimum laydown temperature.
Page 42 of 48
2360/2350 Combined Specification
December 1, 2004
2360.7
THICKNESS AND SURFACE SMOOTHNESS REQUIREl\tIENTS
A
Thickness
After compaction the thickness of each lift shall be within a tolerance of 6 mID [114 inch] of the
thickness shown in the Plans, except that, if automatic grade controls are used, this thickness requirement will not
apply to the first lift placed. This thickness requirement will not apply to a leveling lift whether or not automatic
grade controls are required. The Engineer may require removal and replacement, at the Contractor's expense, of any
part of any lift that is constructed to less than the minimum required thickness.
Cores taken for density determination shall be measured for thickness also. Each core shall be
measured 3 times for thickness prior to sawing. Report the average of these three measurements. Each lot's average
core thickness shall be documented and submitted to the Engineer. If the average of the two Contractor cores
exceed the specified tolerance, an additional two cores may be taken in the lot in question. The average of all core
thickness measurements per day per lift will be used to determine daily compliance with thickness specifications.
On that portion of any lift constructed to more than the maximum permissible thickness, the
materials used in the excess mixture above that required to construct that portion of the lift to the Plan thickness plus
6 mID [114 inch] may be excluded from the pay quantities and at the discretion of the Engineer and at the
Contractor's expense may be required to be removed and replaced.
B
Surface Requirements
After compaction, the finished surface of each lift shall be reasonably free of segregated, open and
torn sections, and shall be smooth and true to the grade and cross section shown on the Plans with the following
tolerances:
(1) Where a leveling lift is specified, it shall be constructed to \vithin a tolerance of 15 mID [112 inch]
of the elevations and grades established by the Engineer. This requirement shall also apply to the
fIrst lift placed other than leveling when automatic controls are used.
(2) The surface of the fInal two lifts placed shall show no variation greater than 6 mID [114 inch] from
the edge of a 3 m [10 foot] straightedge laid parallel to or at right angles to the centerline.
Shoulder surfacing and surfacing on temporary connections and bypasses shall show no variations
greater than 6 mID [114 inch] from the edge of a 3 m [10 foot] straightedge laid parallel to the
centerline.
(3) After fInal compaction, all final lift asphalt wearing surfaces adjacent to concrete pavements shall
be slightly higher (but not to exceed 6 mID [114 inch] than the concrete surface.
After fInal compaction, all asphalt surfaces adjacent to gutters, manholes, pavement headers, or
other fixed struchrres shall be slightly higher (but not to exceed 6 mID [114 inch] than the surface
of the struchrre.
(4) Transverse joints (construction joints), at the beginning and end of a project, at paving
exceptions, or caused by suspension of daily paving operations, shall show no variation greater
than 6 mID [114 inch] from the edge of a 3 m [10 foot] straightedge centered longitudinally across
the transverse joint. The Engineer may require correction by diamond grinding when material is
placed outside the above described limitations.
(5) The transverse slope of the surface of each lift, exclusive of the shoulder wearing lift, shall not
vary from the slope shown in the Plans by more than 0.4 percent.
Page 43 of 48
2360/2350 Combined Specification
December 1, 2004
(6) The distance between the edge of each lift and the established centerline shall be no less than the
Plan distance nor more than 75 mrn [3 inches] greater than the Plan distance. In addition, the edge
alignment of the wearing lift on tangent sections and on curve sections on degrees or less shall
not deviate from the established alignment by more than 25 mrn [1 inch] in any 7.5 m [25 foot]
section.
(7) The fInished surface of each lift shall be reasonably free of segregated and open and torn sections.
Any material placed outside the above described limitations shall be removed and replaced after
being cut or sawed at no expense to the Department Owner or with the approval of the Engineer, allowed to remain
inplace at a reduced cost calculated at $12 per square meter [$10 per square yard].
C
Pavement Smoothness
Cl
General
Pavement smoothness will be evaluated on the [mal mainline pavement surface using a California
type profi10graph or Inertial Pro filer (IP) with a 5 mrn [0.2 inch] blanking band. Unless otherwise authorized by the
Engineer, all smoothness testing shall be performed in the presence of the Engineer. The Engineer and the
Contractor shall mutually agree upon scheduling of smoothness testing so that testing can be observed. Any testing
performed without the Engineer's presence, unless otherwise authorized, may be ordered retested at the Contractors
expense. The following table shows pavement surfaces, which are excluded from profilograph testing, but subject to
Section 2360.7B surface requirements.
ro I ograpl estmg xc USlOns
Pavement Surfaces Excluded From Profilograph Testing
Ramps, Loops, Climbing Lanes
Side Streets, Side Connections
Turn Lanes, Storage Lanes, Crossovers, Bypass Lanes
Shoulders
Acceleration, Deceleration Lanes
Intersections constructed under traffic - Begin and end the exclusion 30.5 m [100 feet] from the intersection
radius
Sections less than 15.24 m [50 feet] in length
Projects less than 300 m [1000 feet] in length
Mainline paving where the normally posted regulatory speed is less than or equal to 70 km/hr [45 miles per hour]
-- Begin the exclusion at the sign
Single lift overlays over concrete.
Horizontal Curv~s with a radius less than 289.6 m [950 feet]. Horizontal Curves with a degree of curvature
greater than or equal to 60.
Vertical Curves - Absolute value of grade change is 2 % or more and curve length is 91.4 m [300 feet] or less.
Vertical Curves - Absolute value of grade change is 3 % or more and curve length is 121.9 m [400 feet] or less.
Vertical Curves - Absolute value of grade change is 4 % or more and curve length is 182.8 m [600 feet] or less.
Vertical Curves - Absolute value of grade change is 8 % or more and curve length is 213.4 m [700 feet] or less.
Note: Begin and end the exclusion at the PC (PVe) and PT (PVT), respectively
Table 2360.7-Cl
P fil hT E I
Cl A
Smoothness Requirements
Pavement smoothness requirements will be evaluated by Table 2360.7-C6A, 2360.7-C6B, or
2360.7-C6C. The pavement smoothness table will be identified in the Special Provisions of the proposal.
Page 44 of 48
2360/2350 Combined Specification
December 1, 2004
C2
Measurement
Smoothness will be measured with a 7.62 m [25 foot] California type profIlograph or an Inertial
ProfIler (IP), which produces a profilogram (profile trace of the surface tested). Either type of device must be
certified according to the procedure on fIle in the Bituminous Office. One pass will be made in each lane, 2.74 m
[9 feet] from centerline. The profIlograph or IP shall be in the direction the traffic will be moving. Each lane will
be tested and evaluated separately. The Engineer will determine the length in kilometers [miles] for each mainline
traffic lane. The profilograph will be operated at a speed no greater than a normal walk, no greater than 6 krn/br
[4 miles per hour]. Motive power may be provided manually or by the use ofa propulsion unit approved by the
Engineer. The IP will be operated at the optimum speed as defined by the manufacturer.
C3
Profilograph testing
The Contractor will furnish a properly calibrated, documented, and certified 7.62 m [25 foot]
California type profIlograph or IP. The profIlograph or IP shall be equipped with automatic data reduction
capabilities unless otherwise authorized by the Engineer. Certification documentation shall be provided to the
Engineer on the first day the profilograph or IP is used on the project. User selected profilograph or IP settings are
on fIle in the Bituminous Office. The Contractor will furnish a competent operator, trained in the operation and
evaluation of the 7.62 m [25 foot] California profi10graph or IP.
All objects and foreign material on the pavement surface will be removed by the Contractor prior
to testing. The pavement surface will be divided into sections which represent continuous placement. A section will
terminate or begin 15.24 m [50 feet] before or after a bridge approach panel, bridge surface, manhole or similar
interruption. These 15.24 m [50 foot] sections, including the transverse joint, will be evaluated under Section
2360.7B, Surface Requirements. A day's work joint will be included in the trace with no special consideration. A
section \vill be separated into segments of 0.1 krn [0.1 mile). A segment will be in only one traffic lane.
A profilogram will be made for each segment of 15.24 m [50 feet] or more. The profi10gram will
include the 7.62 m [25 foot] at the ends of the section only when the Contractor is responsible for the adjoining
surface.
End of run areas not included in the profIlograph trace and any sections of pavement less than
15.24 m [50 feet] in length shall be checked longitudinally with a 3.028 m [10 foot] straight edge and the surface
shall not deviate from a straight line by more than 6 mm in 3.028 m [1/4 inch in 10 feet). Transverse joints shall be
evaluated by centering the straightedge longitudinally across the transverse joint.
The profIle trace and index for each segment of pavement must be furnished to the Engineer
\vithin 48 hours after each days run. Identification of all bumps and dips, with signature of the Operator shall be
included with the submitted trace.
The Contractor will submit a final evaluation generated from approved software, to the Engineer
\Vithin five days after all mainline pavement placement. Software is available from the Mn/DOT Bituminous Office
at www.mrr.dot.state.rnn.us/pavementJbituminouslbituminous.asp. The evaluation submitted shall be in tabular
form, with each 0.1 krn [0.1 mile] segment occupying a row. Each row shall include the beginning and ending
station for the segment, the length of the segment, the profIle index for the segment, the profile index
incentive/disincentive in dollars for the segment, and the deductions for bumps in dollars for the segment. Each
continuous run will occupy a separate table and each table will have a header that includes the following: the project
number, the roadway number or designation, the specified ride table, a lane designation, the mix. type of the final
lift, the PG binder of the final lift, the date of the profi10graph run, and the beginning and ending station of the
continuous run. Each table will have a summary at the bottom that includes the following: a subtotal for the profile
index incentive/disincentive, a subtotal for the bump deductions, and a total for incentive/disincentive for both
profIle index and bumps.
The Contractor will be responsible for all traffic control associated with the smoothness testing.
Page 45 of 48
2360/2350 Combined Specification
December 1,2004
Any portion of the proj ect may be retested if the Engineer determines that the Contractor's test
results are in question. If results are found to be inaccurate, the Contractor will be charged at a rate of $155 .34 per
lane Ian [$250 per lane mile] that is retested, with a minimum charge of$500.00. If the results are found to be
accurate, the Dcpartrnent Owner will be paying the Contractor at arate of$155.34 per lane Ian [$250 per lane mile]
that is retested, with a minimum charge of $500.00.
C4
Profile Index
The profIlograph or IF shall be equipped with automatic data reduction capabilities for
determining the profile index (PI) unless otherwise authorized by the Engineer. The profilograph trace will be
evaluated for the profile index (PI) and bumps in accordance with California Method 526 on file with the
Department Bituminous Engineer. The original trace shall be provided to the Engineer
A profile index shall be calculated for each segment. If an IF is used the corresponding
International Roughness Index (00) for each segment shall be submitted to the Bituminous Office Owner. The
index will be determined by summing the vertical deviations outside either a 5 mm [0.2 inch] blanking band or
outside a zero blanking band depending on the number oflifts in the construction. The units of this index are mm
per Ian [inch per mile]. When there is a segment of76.2 m [250 feet] or less in length, the profilograph or IP
measurements for that segment shall be added to and included in the evaluation of the adjacent section to that
segment.
Bumps and dips equal to or exceeding 10.2 mm in a 7.62 m [0.4 inch in a 25 foot] span shall be
identified separately. When the profile trace shows a successive, uninterrup~ed bump, dip; or dip, bump
combination (up to a maximum on alternating trace deviations that relate to one bump or dip on the roadway),
identify and evaluate these occurrences as one event.
C5
Surface Correction
All areas represented by deviations of28 mm [1.1 inch] or more, as measured by the 7.62 m
[25 foot] profi10graph or IF, will be corrected by the Contractor.
The Contractor may elect to correct pavement segments having no more than two events or two
individual bumps or dips ,vith a vertical deviation of 10.2 to 25 mm [0.4 to 1.0 inch] in a 7.62 m [25 foot] span.
Correction of segments ,vith more than two events or two individual bumps or dips, as defined above, will be
allowed only when approved by the Engineer. The Contractor will be assessed a penalty for dips or bumps of 10.2
to 25 mm [0.4 to 1.0 inch] that are not corrected. Bumps and dips not corrected will also be included in the
evaluation for the segment smoothness. Corrected dips or bumps will be considered satisfactory when the
profilogram shows the dips or bumps are less than 10.2 mm in a 7.62 m [0.4 inch in a 25 foot] span.
Bump, dip, and smoothness correction work shall be for the entire traffic lane width. Pavement
cross slope shall be maintained through corrective areas.
Corrective work shall be made by diamond grinding unless other methods are approved by the
Engineer. Other methods may include; overlaying the area, or replacing the area by milling and inlaying. Any
corrective actions by milling and inlay or overlay shall meet the specifications for ride quality over the entire length
of the correction, including the first and last 15 m [50 feet]. Bumps or dips in excess of 10.2 mm [0.4 inches] at
transverse joints at areas of corrective actions utilizing overlay or milling and inlay, shall be removed by diamond
grinding. The Contractor shall notify the Engineer prior to commencement of the corrective action If the surface is
corrected by overlay, inlay or replacement, the surface correction shall begin and end with a transverse saw cut.
If the smoothness evaluation indicates that corrective work is necessary for more than 50% of a
segment, surface correction \vill be limited to mill and inlay (40 mm [11/2 inch] min).
All corrective work shall be subject to the approval of the Engineer. After all required correction
work is completed, a final profile index shall be determined. Corrective work and re-eva1uation ,viII be at the
Contractor's expense.
Page 46 of 48
2360/2350 Combined Specification
December 1, 2004
C6
Payment
The cost of certified smoothness testing and associated traffic control will be incidental to the cost
of the Wear Course Mixture.
The Contractor may receive an incentive payment or be assessed a penalty based on the number of
segments and the initial profile index. The total ride incentive shall not exceed 10% of the total mix price for
pavement smoothness evaluated under Table 2360.7-C6A, 5% of the total mix price for pavement smoothness
evaluated under Table 2360.7-C6B, or 5% of the total mix price for pavement smoothness evaluated under Table
2360.7-C6C. The maximum allowable net incentive (total incentive minus disincentive) payment shall be calculated
by multiplying the total tons paved by the mixture price by the appropriate incentive cap. Pay adjustments for
incentives will only be based on the initial Profile Index before any corrective work has been performed. Pavement
that contains corrective action for profile or bumps is not eligible for incentive pay. These payments or assessments
will be based on the following schedules.
The Contractor will not receive a net incentive payment for ride if more than 25% of all density
lots for the project fail to meet minimum density requirements.
For each traffic lane, a penalty will be assessed for each bump or dip of 10.2 to 25 mID [0.4 to 1.0
inch] that is not corrected. Penalties, based on the table the profile index is evaluated under, are as follows:
Table 2360.7-C6A: $900
Table 2360.7-C6B: $675
Table 2360.7-C6C: $450
Bumps or dips resulting from a construction joint will be assessed a $900 penalty, regardless of
the table used for evaluation of pavement smoothness.
The Engineer may, at his discretion, assess a penalty in lieu of requiring the Contractor to take
corrective action when the profile index for a segment indicates corrective action is necessary.
Penalties, based on the table the profile index is evaluated under, are as follows:
Table 2360.7-C6A:
Table 2360.7-C6B:
Table 2360.7-C6C:
$560 per 0.1 Ian [$900 per 0.1 mile]
$420 per 0.1 Ian [$675 per 0.1 mile]
$280 per 0.1 Ian [$450 per 0.1 mile]
...
mm per km [Inches per mile] Dollars per Segment Dollars per Segment
per 0.1 km segment [per 0.1 mile sel!ment] (Metric) [English]
0- 13.4 [0.0 - 0.8] 210 [335]
13.5 - 25.3 [0.9 - 1.6] 145 [225]
25.4 - 38.7 [1.7 - 2.4] 80 [115]
38.8 - 78.9 [2.5 - 5.0] 0 [0]
79.0 - 92.3 [5.1 - 5.8] (80) [(115)]
92.4 - 105.7 [5.9 - 6.7] (145) [(225)]
105.8 - 118.3 [6.8 - 7.5] (210) [(335)]
Over 118.3 [Over 7.5] Corrective Action Corrective Action
Table 2360.7-C6A *
Initial Profile Index for 5mm [0 2 inch] blankinu band
* Typically, 3-lift minimum construction
Page 47 of 48
2360/2350 Combined Specification
December 1,2004
m la ro I e n ex or ::lmm mc an ng an
mm per km [Inches per mile] Dollars per Segment Dollars per Segment
per 0.1 kIn segment [per 0.1 mile segment] (Metric) [English]
o - 15.8 [0.0 - 1.0] 145 [225]
15.9 - 31.6 [1.1 - 2.0] 100 [150]
31.7- 47.3 [2.1 - 3.0] 55 [75]
47.4 - 110.5 [3.1 - 7.0] 0 [0]
11 0.6 - 126.3 [7.1 - 8.0] (55) [(75) ]
126.4 - 142.0 [8.1 - 9.0] (100) [(150) ]
142.1 - 157.8 [9.1-10.0] (145) [(225) ]
Over 157.8 [Over 10.0] Corrective Action Corrective Action
Table 2360.7-C6B *
I 'f I P fil I d f [0 2' h] bl ki b d
* Typically, 2-lift construction
.,.,
mm per km [Inches per mile] Dollars per Segment Dollars per Segment
per 0.1 kIn segment [per 0.1 mile segment] (Metric) [English]
0-31.6 [0.0 - 2.0] 95 [150]
31.7 - 47.4 [2.1 - 3.0] 65 [100]
47.5 - 79.0 [3.1 - 5.0] 35 [50]
79.1 - 158.0 [5.1 -10.0] 0 [0]
158.1 - 189.6 [10.1 -12.0] (35) [ (50) ]
189.7 - 221.2 [12.1 - 14.0] (65) [ (100) ]
221.3 - 252.8 [14.1-16.0] (95) [ (150)]
Over (252.8) [Over 16.0] Corrective Action Corrective Action
Table 2360.7-C6C *
Initial Profile Index for 5mm [0 2 inch] blankin<T band
* Typically, single lift construction
2360.8
METHOD OF J\tIEASUREMENT
A
Asphalt Mixture
Asphalt mixture of each type will be measured separately by mass, based on the total quantity of
material hauled from the mixing plant, \vith no deductions being made for the asphalt materials.
B
Blank
C
Asphalt Mixtures Measured by the Square Meter [Square Yard] per Specified (mm [inch])
and for Mixtures Measured by the [Square Yard inch]
Asphalt mixture of each type and for each specific lift will be measured separately by area and by
thickness on the basis of actual fInal dimensions placed. The constructed thickness shall meet tolerances set forth in
Sections 2360.7A.
Page 48 of 48
SECTION 02766
PAVEMENT MARKINGS
PART I-GENERAL
1.01 SECTION INCLUDES
A. Furnishing and applying pavement markirIgs for control and guidance of traffic.
1.02 RELATED SECTIONS
A. Section 02740 - Plant Mixed Asphalt Pavement.
1.03 REFERENCES
A. Minnesota Department of Transportation "Standard Specifications for
Construction," 2000 Edition (MnDOT Spec.):
1. The Application Specification for Conventional Pavement Marking
Materials, 3 Minute Dry Alkyd and High Solids Latex.
2. High Solids Water Based Traffic Paint.
3. Epoxy Resin Pavement Markings.
4. Improved Patterned Polymer Pavement Marking Tape for Lines and
Selected Symbols and Legends.
5. High Durability Preformed Pavement Markings.
6. Drop-On Glass Beads.
7. 3354 - Preformed Plastic Markings for Permanent Traffic Lane
Delineation and Legends.
1.04 SUBMITTALS
A. 1 copy of the chosen paint lot or batch formulation.
B. Pavement Marking Contractor Qualifications/Certifications.
C. MnDOT Certification approvals.
1.05 SEQUENCING AND SCHEDULING
A. As per MnDOT Specifications.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02766-1
PAVEMENT MARKINGS
PART 2 - PRODUCTS
2.0 1 MATERIALS
A. Paint:
1. High Solids Water Based:
a. Free of toxic heavy metals, including lead, mercury, and cadmiu..1Jl.
b. Track Free Time - 3 minutes or less.
c. Yellow Prime Pigment - Colour Index Pigment Yellow #65 or
#75.
d. White Color - Flat white.
e. Yellow Color - Color #33538 of Federal Standard 595.
2. Three Minute Dry Alkyd:
a. Free of toxic heavy metals, including lead, mercury, and cadmium.
b. Track Free Time - 3 minutes or less.
c. Yellow Prime Pigment - Color Index Pigment Yellow #65 or #75.
d. White Color - Flat white.
e. Yellow Color - Color #33538 of Federal Standard 595.
2.02 EQUIPMENT
A. General:
1. Vehicles used shall be deployed and equipped with traffic control devices
set forth in the "Minnesota Manual on Uniform Traffic Control Devices,
Field Manual."
2. Shadow vehicle with truck-mounted attenuator shall be used on streets
with posted speed equal to or greater than 40 m.p.h. or ADT greater than
1500 vehicles per day.
3. Equipment used for spray applications shall be capable of applying glass
beads by a pressurized system at a rate of at least 25 Ibs/gal.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02766-2
PAVEMENT MARKINGS
4. Capable of accumulating footage applied per gun.
5. Stainless steel components in the delivery system required for water-based
materials.
PART 3 - EXECUTION
3.01 GENERAL
A. The pavement marking crew shall include at least 1 technical expert
knowledgeable in each of the following areas:
1. Equipment operation.
2. Application techniques.
3. Traffic control.
4. Safety regulations.
B. The filling of tanks, pouring of materials, or cleanirIg of equipment shall not be
performed on unprotected pavement surfaces, unless adequate provisions are
made to prevent spillage of material.
3.02 SCHEDULE
A. Paint Pavement Markings:
1. Place following completion of bituminous wear course:
a. No sooner than 24 hours after placement of bituminous.
b. Within 5 working days of completion of bituminous placement
unless otherwise directed by Engineer.
3.03 PREPARATION
A. Locations:
1. In general accordance with the Drawings:
a. Location of marking designating no passing zones to be
coordinated with corresponding traffic signs.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02766-3
PAVEMENT MARKINGS
2. The Engineer will place necessary "Spotting" at appropriate points:
a. Horizontal controL
b. Starting and stopping points.
c. Broken line intervals will not be marked.
d. Longitudinal joints, pavement edges, and existing markings shall
serve as horizontal control when so directed.
e. Contractor shall notify Engineer at least 48 hours in advance when
requesting spotting locations.
3. Edge lines and lane lines are to be broken only at intersections with public
roads and at private entrances if they are controlled by a yield sign, stop
sign, or traffic signal.
4. The break point is to be at the start of the radius for the intersection or at
marked stop lines or crosswalks.
B. Street Surface:
1. Engineer may direct cleaning of surface as necessary immediately prior to
marking application:
a. Brushing with non-metallic rotary broom.
b. Other cleaning method approved by Engineer.
c. Air blast following cleaning.
2. Surface must be dry.
3. Minimum surface temperature is 500 F.
3.04 APPLICATION
A. General:
1. Tolerance:
a. Width: A tolerance of 1/4 inch under or 1/4 inch over the specified
width will be allowed for striping provided the variation is gradual
and does not detract from the general appearance.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Ander1ik & Associates, Inc.
02766-4
PAVEMENT MARKINGS
b. Length: Broken line segments may vary up to 2-3/4 inches from
the specified lengths provided the over and under variations are
reasonably compensatory.
c. Alignment: Deviations from the control guide shall not exceed
2 inches.
d. Establishment of application tolerances shall not relieve the
Contractor of his responsibility to comply as closely as practicable
with the planned dimensions.
2. Material shall not be applied over longitudinal joints.
3. 4 inch broken line consists of 10 feet of paint and 40 feet space (1 cycle).
4. If same equipment used for different color material with change in color,
an amount of material equal to fifteen (15) 10 foot long stripes shall be
wasted prior to beginning application with the new color.
5. Conditions:
a. Markings shall not be applied when wind or other conditions cause
a film of dust to be deposited on the pavement surface after
cleaning and before the marking material can be applied.
b. Except when used as a temporary marking, pavement markings
shall only be applied in se~sonable weather when air temperature is
500 F. or higher.
B. Paint:
1. Minimum thickness 15 mil.
2. In accordance with the appropriate MnDOT Spec.
C. Glass Beads:
1. Shall be applied immediately after application of paint markings.
2. Rate of application shall be 8 lbs. per gallon.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02766-5
PAVEMENT MARKiNGS
3.05 CORRECTION OF DEFECTS
A. All pavement markings not conforming to the requirements of the Specifications
shall be removed and replaced, or otherwise repaired to the satisfaction of the
Engineer.
B. Where yield computations show a deficiency in material usage of not more than
20 percent, Owner may require satisfactory repair or may accept the work at a
reduced Bid Unit Price that is in direct proportion to the percent of the deficiency.
C. Where yield computations show a deficiency in material usage in excess of 20
percent, Owner will require removal and replacement to the satisfaction of the
Engineer, unless other means are approved by the Engineer.
D. If removal and replacement is required, at least 90 percent of the deficient line
shall be removed.
E. Width of removal shall be 1 inch wider on all sides than the nominal width of the
marking to be removed.
F. Removal of unacceptable work shall be accomplished with suitable blasting or
grinding equipment, unless other means are authorized by the Engineer.
Bituminous street surfacing shall not be damaged by the removal operation.
3.06 MEASUREMENT AND PAYMENT
A. Lines:
1. Lines shall be measured by the lineal foot on the basis of length actually
applied:
a. Separate measurement made on the basis of color and nominal
width.
B. Messages:
1. Messages shall be measured on the basis of each applied:
a. Separate measurement will be made for each type of message.
b. Separate measurement will be made for paint messages and poly
pre-form messages.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02766-6
PAVEMENT MARKlNGS
C. Bid Items for Pavement Markings of each type are provided. Payment of each
Bid Item shall be compensation in full for all costs incidental thereto, including
but not limited to surface preparation, traffic control measures, maintaining the
work, removal of temporary pavement markers, together with any other expenses
incurred in completing the work that are not specifically included for payment
under the Contract Bid Items.
D. All other work and costs of this Section shall be incidental to the Project and
included in the TOTAL BASE BID.
END OF SECTION
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02766-7
PAVEMENT MARKINGS
SECTION 02770
CONCRETE CURB AND GUTTER
PART I-GENERAL
1.01 SECTION INCLUDES
A. Construction of cast-in-place concrete curbs, and concrete curb and gutter.
1.02 RELATED SECTIONS
A. Section 02720 - Aggregate Base Course.
B. Section 02740 - Plant Mixed Asphalt Pavement.
1.03 REFERENCES
A. American Society of Testing Materials (ASTM):
1. C260 - Air-Entraining Admixtures for Concrete.
B. Minnesota Department of Transportation "Standard Specifications for
Construction," 2000 Edition (MnDOT Spec.):
1. 2461 - Structural Concrete.
2. 2531 - Concrete Curbing.
3. 3101-Portland Cement.
4. 3702 - Preformed Joint Fillers.
5. 3754 - Membrane Curing Compound.
1.04 SUBMITTALS
A. Submit one (1) 7 day and two (2) 28 day concrete cylinder test results for all
concrete pours in any given day.
B. Submit design mix for each concrete mix designation used.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02770-1
CONCREIE CURB AND GUTTER
1.05 SEQUENCING AND SCHEDULING
A. Install concrete curb and gutter within 1 week after aggregate base has been
completed and approved.
B. Concrete curb and gutter construction precedes installation of pavement.
C. Play Area Curb to be installed in 2 Phases:
1. Phase 1 - Install curb abutting bituminous trail prior to trail installation:
a. Consult Engineer to determine limits of Phase 1.
2. Phase 2 - Install remaining curb after completion of play equipment
installation:
a. Anticipated date for Phase 2 is mid-late June 2005.
b. Alignment and quantity of curb shown on plan is subject to change
for Phase 2 curb.
PART 2 - PRODUCTS
2.01 MATERIALS:
A. Concrete to Conform to MnDOT Spec. 2461, except as modified herein:
1. Portland Cement: Conform to MnDOT Spec. 3101:
a. Type 3 air-entraining concrete produced by using Type IA Air-
Entraining Portland Cement.
2. Air-Entraining Admixtures:
a. Conforming to ASTM C260.
b. Not to be added to the concrete mixtures in the field without
approval from Engineer.
3. Mix Designation and Classification for Concrete Curb and Gutter:
a. Manual Placement Mix No. 3A32C.
b. Slip Form Placement Mix No. 3A22C.
B. Pre-Formed Joint Filler: Conform to MnDOT Spec. 3702.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Ander1ik & Associates, Inc.
02770-2
CONCREIE CURB AND GUTTER
C. Curing Compound: Conform to MnDOT Spec. 3754:
1. Curing compound shall contain a fugitive dye.
PART 3 - EXECUTION
3.01 GENERAL
A. Provide copies of batch tickets for concrete mix at the time of material delivery to
Project Site.
B. Construct concrete curb and gutter at the locations and elevations indicated on the
Drawings.
C. Construct the style or type of curb and gutter as shown on the Drawings.
D. Construct intersection curb radii and transitions sections to conform to Drawings.
E. Construct concrete curb ramp depressions to conform to the detail on the
Drawings.
F. Construct curb transitions for driveways to conform to the detail on the Drawings.
Locations to be verified by Engineer at the time of construction.
G. The completed concrete work shall give the appearance of uniformity in surface
contour and texture, and shall be accurately constructed to line and grade. The
required joints, edges, and flow lines shall show neat workmanship.
H. Retempering of the concrete which has partially hardened with or without
additional materials or water is prohibited.
3.02 FOUNDATION PREPARATIONS
A. Support on a compacted aggregate base:
1. Conform to typical sections listed on the Drawings.
2. Conform to Section 02720 - Aggregate Base Course.
3.03 FORMS
A. Conform to MnDOT Spec. 2531.3B.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Ander1ik & Associates, Inc.
02770-3
CONCRETE CURB AND GUTTER
3.04 JOINT CONSTRUCTION
A. Conform to MnDOT Spec. 2531.3C, except as modified herein:
1. Maximum spacing of expansion joints for slip formed shall be 200 feet.
3.05 METAL REINFORCEMENT
A. Conform to MnDOT Spec. 2531.3D, except as modified herein:
1. Where required, install two (2) #4 steel reinforcing rods in lower portion
of the curb section with a minimum of2 inches coverage on all sides:
a. Placement at catch basins conform to the details on the Drawings.
3.06 PLACING AND FINISHING
A. Conform to MnDOT Spec. 2531.3E and 2531.3F, except as modified herein:
1. The top surface of the curb and gutter shall have a brush finish at right
angles to the curb line.
2. Play Area Curbing is to be finished on both the front and back sides as
both sides will be exposed and visible.
3.07 CONCRETE CURING AND PROTECTION
A. Conform to MnDOT Spec. 2531.3G and 2531.3G2 (Membrane Curing Method),
except as modified herein:
1. All surfaces shall be coated with membrane curing compound within 30
minutes after finishing at the specified rate.
2. The membrane-curing compound must be applied in 2 different directions
perpendicular to each other.
3. A second application of membrane curing compound shall be applied 4 to
8 hours after the first application at the specified rate.
4. Cold weather curing when temperatures fall below 400 during placement
or within the following 24 hours shall conform to MnDOT Spec.
2531.3G 1 blanket curing method or method approved by the Engineer.
5. The freshly finished surface shall be protected, surfaces pitted by rain will
be considered unacceptable.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02770-4
CONCRETE CURB AND GUTTER
6. Removal and replacement of any curb section damaged by traffic, rain,
cold weather, or other causes occurring prior to final acceptance shall be
the responsibility of the Contractor.
3.08 BACKFILLING
A. Conform to MnDOT Spec. 2531.3J, except as modified herein:
1. Initial Backfilling:
a. Follow the 72 hour curing period with completion within 6 days of
original placement.
b. Tolerance within 0.3 feet to the top of curb elevation.
2. Curb damaged during backfilling is the responsibility of the Contractor.
3.09 WORKMANSHIP AND FINISH
A. Conform to MnDOT Spec. 2531.3K, except as modified herein:
1. Any deviation in the design curvature of concrete edges in excess of 3/8 of
an inch, measured with a 10 foot straight edge, will be considered
unacceptable.
2. Acceptance of work by price reduction will not be allowed.
3.10 MEASUREMENT AND PAYMENT
A. Bid Items have been provided for Concrete Curb and Gutter and Play Area
Curbing. Measurement of curb and gutter shall be by the lineal foot measured
along the face of the curb at the gutter line for each type. Payment shall include
materials, preparation, placement, finishing, curing, protection, reinforcement,
and backfilling.
B. No separate measurement or payment for modifications at curb ramps, transition
sections, or B618 curb installed at catch basins and radii.
C. All other work and costs of this Section shall be incidental to the Project and
included in the TOTAL BASE BID.
END OF SECTION
000034-04159-0
@ 2005 Bonestroo, Rosene,
Ander1ik & Associates, Inc.
02770-5
CONCRETE CURB At'lD GUTTER
SECTION 02775
CONCRETE WALKS, MEDIANS, AND DRIVEWAYS
PART I-GENERAL
1.01 SECTION INCLUDES
A. Cast-in-place concrete walkways, medians, driveways, and valley gutters.
1.02 RELATED SECTIONS
A. Section 02315 - Excavation and Fill.
B. Section 02720 - Aggregate Base Course.
C. Section 02770 - Concrete Curb and Gutter.
D. Section 02740 - Plant Mixed Asphalt Pavement.
1.03 REFERENCES
A. American Society of Testing Materials (ASTM):
1. C260 - Air-Entraining Admixtures for Concrete.
B. Minnesota Department of Transportation "Standard Specifications for
Construction," 2000 Edition (MnDOT Spec.):
1. 2211 - Aggregate Base.
2. 2461 - Structural Concrete.
3. 2521 - Walks.
4. 2531 - Concrete Curbing.
5. 3702 - Preformed Joint Filers.
6. 3754 - Membrane Cunng Compound.
1.04 SUBMITTALS
A. Submit design mix for each concrete mix used.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02775-1
CONCREIE WALKS,
MEDIANS, AND DRIVEWAYS
PART 2 - PRODUCTS
2.01 MATERIALS
A. Concrete to conform to MnDOT Spec. 2461, except as modified herein:
."
1. Portland Cement: Conform to MnDOT Spec. 3101:
a. Type 3 air-entraining concrete produced by using Type IA Air-
Entraining Portland Cement.
2. Air-Entraining Admixtures: conform to MnDOT Spec. 3113:
a. Conforming to ASTM C260.
b. Not to be added to the concrete mixtures in the field without
approval from Engineer.
3. Mix Designation and Classification:
a. Manual Placement Mix No. 3Y32C.
b. Slip Form Placement Mix No. 3Y22C.
B. Preformed Joint Filler: Conform to MnDOT Spec. 3702.
c. Curing Compound: Conform to MnDOT Spec. 3754.
D. Sub-Grade Base Material:
1. Aggregated Base: Conforming to Section 02720 - Aggregate Base
Course.
P ART 3 - EXECUTION
3.01 GENERAL
A. Provide copies of batch tickets for concrete mix at the time of material delivery.
B. Construct concrete walkway and driveways at the locations indicated on the
Drawings.
C. Verify locations with Engineer in the field prior to construction.
D. The completed concrete work shall give the appearance of uniformity in surface
contour and texture, and shall be accurately constructed to line and grade. The
required joints, edges, and flow lines shall show neat workmanship.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02775-2
CONCREIE WALKS,
MEDIANS, AND DRIVEWAYS
E. Retempering of concrete which has partially hardened with or without additional
materials or water is prohibited.
3.02 FOUNDATION PREPARATIONS
A. Placement of the aggregate base or granular material to support the concrete work
shall conform to Section 02720 - Aggregate Base Course or Section 02318 -
Sub grade Preparation. Compaction of sub grade base shall conform to MnDOT
Spec. 2211.3C 1.
B. The foundation shall be approved by the Engineer prior to placement of concrete
material.
3.03 FORMS
A. Conform to MnDOT Spec. 2521.3B.
3.04 JOINT CONSTRUCTION
A. Conform to MnDOT Spec. 2521.3C2, except as modified herein:
1. Maximum spacing of expansion joints for walkways shall be 60 feet.
2. Match joints of adjacent concrete work.
3.05 METAL REINFORCEMENT
A. Conform to MnDOT Spec. 2531.3D.
3.06 PLACING AND FINISHING
A. Conform to MnDOT Spec. 2521.3Cl and 2531.3F for slip form or 2531.3K for
manual placement, except as modified herein:
1. Any deviation in the design curvature of concrete edges in excess of 3/8 of
an inch, measured with a 10 foot straight edge, will be considered
unacceptab Ie.
2. Any surface area allowing the entrapment of water at a depth 1/8 inch or
greater will be considered unacceptable.
3. Unacceptable work shall be removed and replaced with acceptable work
as directed by the Engineer. Acceptance of work by price reduction will
not be allowed.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02775-3
CONCRETE WALKS,
MEDIANS, AND DRlVEW A YS
3.07 CONCRETE CURING AND PROTECTION
A. Conform to MnDOT Spec. 2521.3C3 and 2521.3C3b (Membrane Curing
Method), except as modified herein: .
,.
1.
Coat all surfaces with membrane curing compound within 30 minutes after
finishing at the specified rate.
2. The membrane-curing compound must contain a fugitive dye and be
applied at 2 different directions perpendicular to each other.
3. A second application of membrane curing compound shall be applied 4 to
8 hours after the first application at the specified rate.
4. Cold weather curing, when temperatures fall below 400 F. during
placement or within the following 24 hours, shall conform to MnDOT .
Spec. 2521.3C3a blanket curing method, or method approved by the
Engineer.
5. The freshly finished surface shall be protected, surfaces pitted by rain will
be considered unacceptable.
6. Removal and replacement of any concrete section damaged by traffic,
rain, cold weather, or other causes occurring prior to final acceptance shall
be the responsibility of the Contractor.
3.08 BACKFILLING
A. Conform to MnDOT Spec.2521.3E, except as modified herein:
1. Perform backfilling to protect the concrete no sooner than 72 hours after
placement of the concrete.
3.09 MEASUREMENT AND PAYMENT
A Bid Item for 4 Inch Concrete Sidewalk has been included in the Bid Form.
Measurement shall be on the basis of in-place square foot:
1. Payment of the Bid Item shall include the following:
a. Concrete materials.
b. Subgrade and base preparation.
c. Placement of materials.
d. Finishing.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02775-4
CONCRETE WALKS,
MEDIANS, AND DRIVEWAYS
e. Curing and protection.
f. Reinforcement
g. Backfilling.
2. Aggregate base beneath concrete sidewalk shall be measured and
compensated per Section 02720 - Aggregate Base Course.
B. A Bid Item for 6 Inch Concrete Driveway Pavement has been included in the Bid
Form. Measurement shall be on the basis of in-place square foot:
1. Payment of the Bid Item shall include the following:
a. Concrete materials.
b. Sub grade and base preparation.
c. Placement of materials.
d. Finishing.
e. Curing and protection.
f. Reinforcement (keyway substitution)
g. Backfilling.
2. Aggregate base beneath concrete driveway apron shall be measured and
compensated per Section 02720'- A:ggregate Base Course.
C. All other work and costs of this Section shall be incidental to the Project and
included in the TOTAL BASE BID.
END OF SECTION
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik.& Associates, Inc.
02775-5
CONCRETE WALKS,
MEDIANS, AND DRNEW A YS
SECTION 02870
SITE FURNISHINGS
PART 1- GENERAL
1.01 SECTION INCLUDES
A. Furnish and Install the Following Items:
1. Water Fountain.
1.02 SUBMITTALS
A. Submit catalog cut of Project Site furnishings to be installed for approval.
B. Color charts shall also be submitted so that colors for the site furnishings can be
selected.
P ART 2 - PRODUCTS
2.01 MANUFACTURED UNITS
A. Drinking Fountain shall be HAWS Model 3376, or approved equal.
PART 3 - EXECUTION
3.01 DRINKlNG FOUNTAIN
A. Install new drinking fountain at location indicated on the Drawings:
1. Install new water service from adjacent 6 inch main, including:
a. 1 inch copper service (3/4 inch minimum).
b. Corporation stop.
c. Install stop box on Main side ofthe blow offline on the water supply
line.
d. 3/4 inch copper blow-offline to ground surface - install ball valve at
end of copper approximately 4 inches below finished grade ground
surface. Owner will install access/enclosure container.
2. Install water service according to requirements of Section 02515 - Water
Services.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02870-1
SITE FURNISHINGS
3. Construct a "French Drain-Type" facility for waste line.
a. Create a drainage "hole" to serve as waste line drainage area.
b. Fill with approx 2 CY of 1-112 inches - 3 inches clear rock. Cover
with geotextile fabric prior to filling above.
c. Consult with Engineer on specifics of waste drainage.
3.02 MEASUREMENT AND PAYMENT
A. A Bid Item has been provided for 6 Foot Bench with Concrete Pad. Measurement
will be based on units of each. The price shall include the concrete pad furnished in
accordance with the bench detail.
B. A Bid Item has been provided for Furnish and Install Drinking Fountain, Including
"French Drain" and Blow off V alve. Measurement will be per each fountain installed
and include all work and materials to install the fountain, the French drain, the blow
off valve assembly, concrete pad, and make all associated connections.
C. All other work and costs of this Section shall be incidental to the Project and
included in the TOTAL BASE BID.
END OF SECTION
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02870-2
SITE FURNISHINGS
SECTION 02920
LAWNS AND GRASSES
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. Restoration of construction area by installation of topsoil, seed, sod, soil
amendments, mulch, and erosion control.
1.02 RELATED SECTIONS
A. Section 01570 - Temporary Erosion and Sediment Control.
B. Section 02315 - Excavation and Fill.
C. Section 02318 - Sub grade Preparation.
1.03 REFERENCES
A.
Minnesota Department of Transportation "Standard Specifications for Construction,"
2000 Edition (MnDOT Spec.):
1. 2575 - Turf Establishment.
2. 3876 - Seed.
3. 3877 - Topsoil Borrow.
4. 3878 - Sod.
5. 3881 - Commercial Fertilizer.
6. 3882 - Mulch Material.
B.
"Minnesota Department of Transportation Seeding Manual 2000," (MnDOT Seeding
Manual).
1.04
SUBMITTALS
A.
Provide source and invoice for seed to be used for this Project.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02920-1
LAWNS AND GRASSES
1.05 QUALITY ASSURANCE
A. At the conclusion of the establishment period, which will be 1 year following initial
installation, a fmal inspection of planting will be made to determine the conditions of
areas specified for seeding. All areas with insufficient plant establishment as
determined by the Engineer will be noted. This material shall be re-supplied and
planted in the next growing season at no additional cost to the Owner. Evaluation of
plantings shall be done in accordance with Early Maintenance. and Evaluation of
Plantings, MnDOT Seeding Manual 2000, and with MnDOT Spec. 2575.3.
1.06 FIELD QUALITY CONTROL
A. Provide Engineer with bags and tags of seed used for identification purposes.
PART 2 - PRODUCTS
2.01 MATERIALS
A. Topsoil: Topsoil Borrow conforming to MnDOT Spec. 3877.2A.
B. Soil Amendments: Conform to MnDOT Spec. 3881 and 3879. Fertilizer shall be
complete fertilizer containing 8 percent nitrogen, 16 percent phosphoric acid, and 8
percent potash.
C. Sod: Conform to MnDOT Spec. 3878.
D. Seed Mix Tabulations: Conform to MnDOT Seeding Manual:
1. Lawn Mix: Conform to MnDOT Seeding Manual Mixture 60A.
2. Ditch Mix: Conform to MnDOT Seeding Manual Mixture 80A.
E. Mulch: Conform to MnDOT Spec. 3882.
PART 3 - EXECUTION
3.01 EXAMINATION
A. Review restoration areas with the Engineer. Determine locations for seed or sod.
Schedule for restoration of areas may be revised to fit field conditions.
B. Notify the Engineer at least 3 days in advance of hauling topsoil borrow on Project
Site so the Engineer may visually inspect and sample for testing if deemed necessary.
C. Finish grades are to be inspected and approved by the Engineer prior to start of
restoration.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02920-2
LAWNS AND GRASSES
3.02 PREPARATION
A. General: Conform to MnDOT Spec. 2575.3A.
B. Soil Preparation: Conform to MnDOT Spec. 2575.3B.
C. Fertilizers and Conditioners: Conform to MnDOT Spec. 2575.3C:
1. Apply fertilizer at a rate of 450 lbs. per acre (10 Ibs.ll000 sq. ft.).
2. Where soil pH is lower than 5.5, apply ground limestone at 3 tons per acre
(140 Ibs.ll000 sq. ft.).
3.03 SOWING SEED
A. Seeding Dates: Conform to MnDOT Seeding Manual for the mixes specified.
B. Seeding Rates: Conform to MnDOT Seeding Manual for the mixes specified.
C. Applying Mulch: Conform to MnDOT Spec. 2575.3 and apply at a rate of2 tons per
acre (90 Ibs.ll000 sq. ft.).
D. Sowing Seed: Conform to MnDOT Spec. 2757.3.
3.04 PLACING SOD
A. Conform to MnDOT Spec. 2575.3J.
3.05 FIELD QUALITY CONTROL
A. Maintain restored areas in accordance with MnDOT Spec. 2575.3L.
B. Restored areas that have been satisfactorily completed and are disturbed by additional
construction activity required by the timing and sequencing of the work shall be
restored over to the same requirements of the original work.
C. Any sod that does not show definite growth and establishment 30 days after laying
shall be replaced and established at the proper season by the Contractor at his
expense.
D. Seed maintenance and evaluation of successful establishment of seed shall be done in
accordance with the MnDOT Seeding Manual 2000 - Early Maintenance and
Evaluation ofPlantings.
E. Watering of seeded and sodded areas shall be done for a period of 30 days from
installation sufficient to ensure establishment of permanent yegetation.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02920-3
LAWNS ANTI GRASSES
3.06 MEASUREMENT AND PAYMENT
A. A Bid Item has been provided for Sodding. Measurement will be based upon units of
square yards of sod installed complete in place as specified, including installing
topsoil; soil amendments; furnishing and installing sod; preparation of surface
maintenance; and all incidental items associated with the work. The actual quantity
installed multiplied by the appropriate Bid Unit Price will be considered payment in
full for all work and costs of this Bid Item.
B. Bid Items have been provided for Seeding MnDOT Mix 60A and 80A. Measurement
will be based upon units of acres of 60A and 80A seed installed complete in place as
specified, including installing topsoil; preparation of seedbed; seed; and mulch and
all correlated activity. The actual quantity installed multiplied by the appropriate Bid
Unit Price will be considered payment in full for all work and costs of these Bid
Items.
C. All other work and costs of this Section shall be incidental to the Project and
included in the TOTAL BASE BID.
END OF SECTION
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02920-4
LAWNS AND GRASSES
SECTION 02930
TREES, SCRUBS, AND PERENNIAL PLANTS
PART 1- GENERAL
1.01 SECTION INCLUDES
A. Bed preparation, plant pits, pruning, planting, supplements, backfill, wrapping,
protection, and maintenance.
1.02 REFERENCES
A. Minnesota Department ofTransportajion "Standard Specifications for Construction,"
2000 Edition (MnDOT Spec.):
1. 2571 - Plant Installation.
2. 2575 - Turf Establishment.
3. 3861 - Plant Stock.
4. 3877 - Topsoil Borrow.
5. 3880 - Peat Moss.
6. 3881 - Commercial Fertilizer.
7. 3882 - Mulch Material.
1.03 DEFINITIONS
A. Weeds: For the purpose of this Project, a weed is a plant that inhibits the
establishment of species listed in article MATERIALS. Weeds may include but are
not limited to: Jimsonweed, quackgrass, morning glory, mustard, lambsquarter,
chickweed, cress, crabgrass, canada thistle, tansy ragwort, bermuda grass, ragweed,
pigweed, johnson grass, bindweed, bentgrass, wild garlic, smooth brome grass,
european buckthorn, glossy buckthorn, tatarian honeysuckle, black locust, and
spotted knapweed, siberian elm.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02930-1
TREES, SHRUBS AND
PERENNIAL PLANTS
1.04 SUBMITTALS
A. Submit the following items consistent:
1. Product Data: Provide all nursery stock submittal materials in accordance
with MnDOT Spec. 2571.A2.
B. Quality Assurance:
1. Nursery Experience: List of completed past projects.
2. Installer Experience: List of completed past projects.
3. Fertilizer Manufacturers Certificate of Compliance.
1.05 QUALITY ASSURANCE
A. Qualifications:
1. Nursery: Company specializing in growing and cultivating the specified
plants with documented experience as represented by a list of completed past
projects.
2. Installer: Company specializing in installing and planting the specified plants
with a minimum on years documented experience as represented by a list of
completed past projects.
B. Fertilizer Manufacturer's Certificate of Compliance: Written documentation
verifying compliance with chemical analysis of fertilizer furnished. Submit to
Engineer 5 days prior to bulk delivery.
1.06 REGULATORY REQUIREMENTS
A. Comply with regulatory agency requirements for fertilizer and herbicide
compositions.
1.07 DELIVERY, STORAGE, AND HANDLING
A. Nursery Stock:
1. Deliver all materials in accordance with MnDOT Spec. 3861.2.
2. Deliver stock after planting preparations have been completed and plant
immediately.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02930-2
TREES, SHRUBS AND
PERENNIAL PLANTS
B. Fertilizer:
1. Deliver small quantities in waterproof bags showing weight, chemical
analysis, and name of manufacturer. Advance approval by the Engineer is
required prior to bulk delivery in containers or by truckload.
1.08 PROJECT/SITE CONDITIONS
A. When excavation is required for planting, locate and protect all adj acent underground
utilities.
B. Protect established turf areas during planting operations.
1.09 SEQUENCING AND SCHEDULING
A. Planting Seasons:
1. Spring: April 15 to June 15.
2. Fall: August 20 to October 1.
3. Other Dates: At the approval of the Engineer.
PART 2 - PRODUCTS
2.01 MATERIALS
A. Topsoil:
1. Salvaged from onsite excavations, stockpiled, and reused. Remove rocks over
1 inch in size.
2. Topsoil Borrow: Conform to MnDOT Spec. 3877.2B.
B. Mulch:
1. Conform to MnDOT Spec. 3882.
2. Type 6 - Wood Chips.
C. Fertilizer:
1. Conform to MnDOT Spec. 3881.
2. Complete Fertilizer: 50 percent ofthe nitrogen derived from natural organic
sources or ureaform.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02930-3
TREES, SHRUBS AND
PERENNIAL PLANTS
3. Spring Planting: 8 percent nitrogen, 16 percent phosphoric acid, and 8 percent
potash.
4. Fall Planting: 10 percent nitrogen, 8 percent phosphoric acid, and 6 percent
potash introduced the following spring.
D. Plant and Nursery Stock: Conform to MnDOT Spec. 2571 and 3861 as follows:
1. Pruned and shaped prior to digging and balling.
2. Prune all bare roots and basal sprouts.
3. Remove all dead, rubbing, damaged, or diseased branches.
4. Prune trees to give tree a uniform and symmetrical shape.
5. Leave leaders intact while removing all stubs.
6. Trees and Shrubs to be provided as shown on the planting schedule:
Symbol Common Name Scientific name Size Spacing Quantity
Trees
AR Northwood Maple Acre rubrum "Northwood" 2" B&B 20-30' 3
TOTAL TREES 3
E. Peat Humus: FS Q-P-166 decomposed peat with no identifiable fibers, pH range
suitable for intended use.
2.02 ACCESSORIES
A. Tree Wrapping: 2 ply asphalt cemented crepe paper furnished in strips.
B. Soil Amendments: Porous ceramics and hydrophilic absorbing polymers used to
modify the physical characteristics of poor soils by balancing or managing water and
oxygen in the soil will be reviewed for approval based on the information provided
by the product label and the manufacturer's recommendations.
C. Water: Non-deleterious to plants or animals.
D. Rodent Protection: Conform to MnDOT Spec. 2571.2C4.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02930-4
TREES, SHRUBS AND
PERENNIAL PLANTS
PART 3 - EXECUTION
3.01 PLANT INSTALLATION
A. Layout:
1. Layout individual tree locations and areas for multiple plantings.
2. Stake locations and outline areas. Center holes at staked locations.
3. Do not start planting work until layout is approved by the Engineer.
4. Make minor adjustments as required.
B. Preparing Plant Holes:
1. Do not begin work on plant holes until after finish grading has been
completed.
2. Identify root flare on trees as described in MnDOT Spec. 2571.3F.
3. Cultivate planting holes and beds by thoroughly loosening and tilling the soil
to a depth that will allow the bottom of root ball to sit on undisturbed soil and
root flare will be at finished grade elevation of the soil as described in
Drawing Details and MnDOT Spec. 2570.3F. Planting holes should be 2 to 5
times the width ofthe root ball. (Most soils need holes 2-3 times the width of
the root ball, heavily compacted soils will need holes 3-5 times the width of
the root ball.)
4. Thoroughly incorporate and mix the required soil amendments into the
loosened soil to the planting depth.
5. Prepare the Soil in the Following Proportions:
a. Topsoil: 4 parts select borrow by volume.
b. Peat Humus: 1 part by volume.
c. Fertilizer: 3 pounds per cubic yard of soil.
d. Mix until thoroughly blended.
6. Loosen planting areas until compaction tester readings are less than 1400
kPa.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02930-5
TREES, SHRUBS AND
PERENNIAL PLANTS
7. Remove foreign materials and undesirable plants and their roots. Do not bury
foreign material beneath areas to be landscaped or restored. Remove
contaminated subsoil.
8. Rototil or aerate any planting soil compacted by operations.
C. Pruning: Prune immediately prior to planting to remove stock damaged during
transport and movement.
D. Placement:
1. Balled and Burlapped:
a. Set balled and burlapped (B&B) stock on undisturbed soil at bottom
of planting hole or on layer of compacted planting soil mixture,
plumb, and in center of pit or trench so that the root flare will be at
finished grade elevation of the soil as described in Drawing Details
andMnDOT Spec. 2571.F.
b. Remove all burlap and nails to expose at least the top third ofthe soil
ball or remove at least the top 2 horizontal rings on wire baskets if
used instead of burlap. Remove all twine and rope.
c. When set, place additional backfill around base and sides of ball, and
work each layer to settle backfill and eliminate voids and air pockets.
d. When excavation is approximately 2/3 full, water thoroughly before
placing remainder of backfill.
e. Repeat watering until no more is absorbed.
f. Water again after placing final layer of backfill.
E. Remove surplus subsoil and topsoil from Project Site.
3.02 WATERING
A. Water each plant within 2 hours of planting.
B. Water to thoroughly saturate all planting soil.
C. Bring planting soil to specified level within 5 days of initial watering and saturate
additional soil.
D.
Water all plants thoroughly as soil moisture is depleted (at least once per week during
periods of average rainfall) until the work is accepted.
02930-6
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
TREES, SHRUBS AND
PERENNIAL PLANTS
3.03 MULCHING
A. Place mulch material as described on details within 48 hours ofthe second watering,
unless otherwise approved by Engineer. Dish top of backfill to allow for mulching.
B. Mulch (Type 6): For trees, provide not less than 4 inch thickness ofmulch and work
into top of backfill and finish to maintain dish or level with adjacent finish grades as
shown in the Drawings. For other plants, provide mulch depth as indicated on
details.
3.04 PROTECTION
A. General:
1. Protect landscape work and materials from damage due to landscape
operations, operation by other contractors, trades, and trespassers.
2. Maintain protection during installation and maintenance periods.
B. Trees:
I. Inspect tree trunks for injury, improper pruning, and insect infestation/disease
and take corrective measures before wrapping.
2. Wrap trees at end of growing season and remove prior to following growing
season. Wrap all trees from the ground to the first maj or branch.
3. Install rodent protection.
3.05 CLEANUP AND RESTORATION
A. During landscape work keep pavements clean and work area in an orderly condition.
B. Treat, restore, or replace in kind turf, sod, plantings, or other facilities damaged by
Contractor's operations.
C. Remove all excess excavated soils from plant holes from the Project Site.
D. Collect and dispose of all excess materials, packaging, and containers.
3.06 MAINTENANCE
A. Begin maintenance immediately after planting.
B.
Maintain plant life for 3 months after acceptance by the Engineer.
02930-7
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
TREES, SHRUBS AND
PERENNIAL PLANTS
C. Trees
1. Trim, prune, remove clippings and dead or broken branches, treat pruned
areas and other wounds.
2. Cultivate and weed as required for healthy groWth, including plant beds and
tree pits.
3. Restore planting saucers.
4. Tighten, repair, or replace stakes, turnbuckles, and guy supports. Reset trees
and shrubs to proper grades or vertical position as required.
5. Restore or replace damaged wrappings.
6. Treat stock with appropriate pest control measures as required to keep trees
and shrubs free of insects and disease.
7. Irrigate to moisten root system and maintain healthy growth.
D. Application of Herbicides and Pesticides:
1. Apply pesticides for weed, insect, and pest control in accordance with
manufacturer's instructions.
2. Remedy damage resulting from pesticide use.
3.07 INSPECTION AND ACCEPTANCE
A. Landscape work will be inspected for acceptance in parts agreeable to the Engineer,
provided work offered for inspection is complete, including maintenance.
B. At the conclusion ofthe establishment period, which will be 1 year following initial
installation, a final inspection of planting will be made.
C. When inspected landscape work does not comply with requirements, replace rejected
work and continue specified maintenance until.re-inspected by Engineer and found to
be acceptable. Remove rejected plants and materials from the Project Site.
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02930-8
TREES, SHRUBS AND
PERENNIAL PLANTS
3.08 MEASUREMENT AND PAYMENT
A. For Trees: Measurement will be each for Trees, for species, variety, and size range,
furnished and planted in accordance with the Drawings. Payment will constitute
compensation in full for all work and costs to furnish and install material in place.
B. For Mulching: Measurement will be in tons, in accordance with the Drawings.
Payment will constitute compensation in full for all work and costs to furnish and
install material in place.
C. For Fertilizer: Measurement will be by weight in pounds of material furnished and
applied in accordance with this Section. Payment will constitute compensation in full
for all work and costs to furnish and install material in place.
D. All other work and costs of this Section shall be incidental to the Project and
included in the TOTAL BASE BID.
END OF SECTION
000034-04159-0
@ 2005 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02930-9
TREES, SHRUBS AND
PERENNIAL PLANTS
This document has important legal consequences: consultation with an attorney is encouraged with respect to its use or
modification. This document should be adapted to the particular circumstances of the contemplated Project and the
Controlling Law.
STANDARD
GENERAL CONDITIONS
OF THE
CONSTRUCTION CONTRACT
Prepared by
ENGINEERS JOINT CONTRACT DOCUMENTS COMMITTEE
and
Issued and Published Jointly By
-----------.
ACEC
National Society of
Professional
Professional Engineers in Privale Practice
..tc!."ri.::i!;; 5;J~iotl'i,;i Cn'ii{(T.';";:::<<!'~
i:~.'-. '.; 1.'< U.h ~~'.'
PROFESSIONAL ENGINeERS IN PRIVATE PRACTICE
Cl practice division of the
NATIONAL SOCIETY OF PROFESSIONf\L ENGINEERS
AivIERICAN COUNCIL OF ENGINEERING COlvIPANIES
AMERICAN SOCIETY OF CIVIL ENGINEERS
This document has been approved and endorsed by
u.,,,....~,
~~
The Associated General Contractors of America
~ ~~d ~ .' ."f~~C:~,,:-,g
'V It'l''''.....Uil\_,I...r...r.'I''~r'l
Construction Specifications Institute
EJCDC C-700 Standard General Conditions of the Construction Contract.
Copyright @ 2002 National Society of' Professional Engineers for EJCDC All rights reserved.
00700- 1
Copyright @2002
National Society of Professional Engineers
1420 King Street, Alexandria, VA 22314
American Council of Engineering Companies
101515th Street, N.W., Washington, DC 20005
American Society of Civil Engineers
1801 Alexander Bell Drive, Reston, V A 20191-4400
These General Conditions have been prepared for use with the Suggested Forms of Agreement Between Owner and
Contractor Nos. C-520 or C-525 (2002 Editions). Their provisions are interrelated and a change in one may necessitate a
change in the other. Comments concerning their usage are contained in the E.lCDC Construction Documents. General and
Instructions (No. C-OO 1) (2002 Edition). For guidance in the preparation of Supplementary Conditions, see Guide to the
Preparation of Supplementary Conditions (No. C-800) (2002 Edition).
E.JCDC C-700 Standard Gcncral Conditions of thc Construction Contract.
Copyright @ 2002 National Socicty of Profcssional Enginccrs for E.JCDC. AJI rights rcscrvcd.
TABLE OF CONTENTS
ARTICLE 1 - DEFINITIONS AND TERMINOLOGY ..............................................................................................................6
1.01 Defined Terms.............................................................................................. ...... ................................. ..................... 6
1.02 Terminology................. ........................... .......... ..... ............................... .................................... ............. .... ..............8
ARTICLE 2 - PRELIMINARY MATTERS. ............................. .................. ....... ...... ......... ........................................ ..................9
2.01 Delivery of Bonds and Evidence of Insurance .........................................................................................................9
2.02 Copies of Documents.......... ............................. ......................................... ...... ...................... ......... ......... ................. 9
2.03 Commencement of Contract Times; Notice to Proceed ...........................................................................................9
2.04 Starting the Work............... .... ............................................. ........ ........... ................ ................................ .................. 9
2.05 Before Starting Construction .................... ........... ................... ................................. .................................. .............. 9
2.06 P reconstruct ion Conference.................................................................................................................... .................9
2.07 Initial Acceptance of Schedules............... .......................................... ...................... ............................. ...................9
ARTICLE 3 - CONTR/\CT DOCUMENTS: INTENT. AlvIENDING, REUSE......................................................................I0
3.01 Illlelll ......................... ............................................. ..................................................... ...........................................10
3.02 Reference Standards.......................... ................................................................................................. ... ...... ..........10
3.03 Reporting and Resolving Discrepancies ................................................................................................................10
3.04 Amending and Supplementing Contract Documents ..............................................................................................11
3.05 Reuse of Documents..... ............. .......... ........................................ ................................... ........... ............. ................ II
3.06 Electronic Data ........................................................................................................ .............................................. II
ARTICLE 4 - AVAILABILITY OF LANDS; SUBSURFACE AND PHYSICAL CONDITIONS; HAZARDOUS
ENVIRONMENTAL CONDITIONS; REFERENCE POINTS ................................................................................................11
4.01 A vailability of Lands .............................................................................................................................................. II
4.02 Subslllj"ace and Physical Conditions............................................................ .......................................... ......... ...... .12
4.03 Differing SubslIIface or Physical Conditions.........................................................................................................12
4.04 Underg round Facilities...... ..................... ................ ............................................................................................... I3
4.05 Reference Points....... ...................................................................................... ........................... .......................... ..13
4.06 Hazardous Environmental Condition ([[ Site .........................................................................................................13
ARTICLE 5 - BONDS Al"TD INSURANCE .............................................................................................................................14
5.01 Pelfomwnce, Payment, and Other Bonds..............................................................................................................14
5.02 Licensed Sureties and Insurers .............................................................................................................................. IS
5.03 CertifIcates of" Insurance......................................................... ................................ ............................................... ] 5
5.04 COlllractor '.I' Liability Insurance................................. ............ ............................................................................... 15
5.05 Owner' .I' Liabilitv Insurance.................................................................................................................................. I6
5 .06 Property Insurance .................... ....................................... ................................. .......................... ............. ........... ..16
5.07 Waive r of Rights................. ............................................................................ .......... ................................. ............. I7
5.08 Receipt and Application of Insurance Proceeds ....................................................................................................17
5.09 Acceptance of Bonds and Insurance; Option to Replace .......................................................................................17
5.10 Partial Utilization, Acknmvledgmem of Property Insurer .....................................................................................18
i\RTICLE 6 - CONTRACTOR'S RESPONSIBILITIES ..........................................................................................................18
6.01 Supervision and Superintendence ....... ...................................................................................................................18
6.02 Labor; vVorking Hours.......................................................................................................................................... .18
6.03 Services, Materials, and Equipment.......................................................................................................................18
6.04 Prog ress Schedule..................... ............................................................................ ................................................. 18
6.05 Substitutes and " Or-Equals" .................................................. .............................. ................................................. 19
6.06 Concerning Subcontractors. Suppliers, and Others................................. .... .......................................................... 20
6.07 Patelll Fees and Royalties ......................................................................................................................................21
6.08 Permits
6.09 Laws and Regulations.................................................................................... ........................................................21
6. 10 Taxes.................................................... ................................................................................................................. 22
6.11 Use of Site and Other AreaL.............. ..................................................................................................................22
6.12 Record Doculllents ............................................... .................................................................................................. 22
6.13 Safety and Protection ... ..........................................................................................................................................22
6.14 Safety Representative........................................................................... ..................................... ............................. 23
6.15 Hazard COlllllllln ication P rog rallls ........................................................................................................... ............. 23
E.JCDC C-700 Standard General Conditions of the Construction Contract.
Copyright @ 2002 National Society of Professional Engineers for E.JCDC. All rights reseI'Ved.
00700 - 3
6.16 Emergencies................... ......... ......................................... ... ............................................. .......................... ............23
6.17 Shop Drawings and Samples..................................................................................................................................23
6.18 COllfinu ing the Work ........................................................... .......... ................ ........ ........... ..................................... .24-
6.19 Contractor's General \VarrallfY and Guarallfee ....................................................................................................24-
6.20 Indemn iJication ............... ........................................................................................................................... ........... .24-
6.21 Delegation of Professional Design Services ..........................................................................................................25
ARTICLE 7 - OTHER WORK AT THE SITE .........................................................................................................................25
7.0 I Related Work at Site. ..............................................................................................................................................25
7.02 Coordination. ............ ................................................................... ................................... ......... ......... ......... ......... ...26
7.03 Legal Relationships............................................................ ...... ....................................... ............ .......... ................ .26
ARTICLE 8 - OWl\TER'S RESPONSIBILITIES ......................................................................................................................26
8.0 I Communications to Contractor..... ........................................................ ................................................................ .26
8.02 Replacement of Eng ineer .... .............................................................. ........ ........ .............. ....................... .... ........... .26
8.03 Furnish Data........ .......................................................................... ....... ............................ .... ...... ........................ ...26
8.04- Pay When Due................... ..... ..... ....... ..... ............................. ................. .............. .............. .................................. ...26
8.05 Lands and Easements: Reports and Tests ..............................................................................................................26
8.06 Insurance...................................................................................................................... ..........................................26
8.07 Change Orders... ....... ............................................................................ .......................... ...... ................. ............... .26
8.08 Inspections, Tests, and Approvals...... ....................................... ...................................... .......... ........... ................. .26
8.09 Limitations on Owner's Responsibililies........................................................................... ......... ........................... .27
8.10 Undisclosed Hazardous Environmental Condilion ................................................................................................27
8.11 Evidence of Financial Arrangements.................................................................................................................... .27
ARTICLE 9 - ENGINEER'S STATUS DURING CONSTRUCTION.....................................................................................27
9.01 Owner's Representative..... ..................................................... .................................... ........................................ ...27
9.02 Visits to Site....... .................. .............................. ................................................................................... ............... ...27
9.03 P rojecl Representative........................ ................. ................................................................................. .................27
9.04- A whorized Variations in Work.......................... ............. .............. ..... .............................. .................................... ...27
9.05 Rejecting Defective Work.......... ..................................... ......... ....................... .......................... .............. ............. ...27
9.06 Shop Drawings, Change Orders and Paymellfs .....................................................................................................28
9.07 Determinations for Unit Price Work ......................................................................................................................28
9.08 Decisions on Requiremellfs ofContracr Documellls and Acceptability of Work ...................................................28
9.09 Limitations on Engineer's Awhority and Responsibilities .....................................................................................28
ARTICLE 10 - CHANGES IN THE WORK: CLAIMS ...........................................................................................................28
10.01 A wllOrized Changes in [he Work.................... ..................... ............. ................................................................... ...28
10.02 Unauthorized Changes in the \Vork .................................................................................................................... ...29
10.03 Execution of Change Orders ........................................................................................................................ ..........29
10.04- Notification to Surety.......................................................................................................................................... ...29
10.05 Claims........... ...................................................................................................................................................... ...29
ARTICLE 11 - COST OF THE WORK: ALLOWANCES; UNIT PRICE WORK..................................................................30
11.0 I Cost of the Work................................................................... .................................................................. ................30
11.02 Allowances................................................................... .......................................................................................... 31
11.03 Unit Price Work .............................................................................................................. .......................................31
ARTICLE 12 - CHANGE OF CONTRACT PRICE; CHA1'iGE OF CONTRACT TIMES .....................................................32
12.01 Change of COllfraCI Price..................................................... .................................... .............................................32
12.02 Change of Contracl Times.................................................................................................................................. ...3 3
12.03 Delays................................................................................................................................................... ............... ..33
ARTICLE 13 - TESTS ANTI INSPECTIONS: CORRECTION. REMOV AL OR ACCEPTANCE OF DEFECTIVE WORK.......33
13.01 Notice of Defecls .................................................................................................................................................. ..33
13.02 Access to Work................................................................................................................. .................................... ..33
13.03 Tests and Inspections.......................................................... ............................................. .................................... ..33
13.04- Uncovering Work ................................................................................................................................................. ..34-
13.05 Owner iVIa)' SlOp the Work ............................................................................. ........................................................34-
13.06 Correclion or Removal of Defeclive \Vork .............................................................................................................34-
13.07 Correclion Period................................................................ .................................................................................. 34-
13.08 Acceptance of Defective Work........................................................................................................................... .... 35
13.09 Owner iV/ay Correct Defeclive Work......................................................................................................................35
ARTICLE 14- - PAYMENTS TO CONTRACTOR AND COlvIPLETION...............................................................................36
14-.01 Schedule of Values............................................................... .................................................................................. 36
14-.02 P rag ress Paymenls.......................... ................................................... ................. ............ ....................................... 36
14-.03 Contractor's 'rVarmnty of Tiile ............................................ ........................................................................ ..........37
14-.04- Substantial Completion........................................................ ..... ......... .......................................................... .......... 37
E.JCDC C-700 Standard General Conditions of the Construction Contract.
Copyright @ 2002 National Society of Professional Engineers for E.JCDC. All rights reserved.
00700 -.j
14.05 Parried Utili::.ation ...... ........................................................................ ....................................................................3 8
14.06 Final Inspection .................... .................................................................................................................................3 8
14.07 Final Paymelll....... .... ........ ......................................................................................................... ............................38
14.08 Finol Completion Deloyed .................. ............................ ..................................... ........................... ..................... ..39
14.09 \Vaive r of Claims............... ................................................................................ ............................................ ....... ..39
ARTICLE 15 - SUSPENSION OF WORK AND TERivIlNATION ........................................................................................39
15.01 Owner lvIay Suspend Work .....................................................................................................................................39
15.02 Owner May Terminate for Couse ............................................. ..............................................................................39
15.03 Olvne!' /v10y Terminate For Convenience ...............................................................................................................40
15.04 Contractor /v10y SlOp Work or Terminate ..............................................................................................................40
ARTICLE 16 - DISPUTE RESOLUTION ..............................................................................................................................At
16.01 Methods and Procedures ...................................... .................................................................................................41
ARTICLE 17 - MISCELLANEOUS .........................................................................................................................................41
17.01 Giving Notice ......................................................................................................................... ................................41
17.02 Computation of Times .......... ....... ................... ................. ........ ............... .................................... ..... ..................... At
17.03 Cumulative Remedies....... ............................. .................. ................... ........... ....... ...................... ... ................... .... ..41
17.04 Survival of Obligotions .. ..... .............................................................. .............. .......... ............. ............. ...................41
17.05 COlllrolling Lmv .................. ...... ................... ..... ........ ........................... ....... ..................................... ............... .......4t
17 .06 Headings........... ................................. ......................... ................................. ..........................................................41
E.JCDC C-700 Standard General Conditions of the Construction Contract.
Copyright @ 2002 National Society of Professional Engineers for E.JCDC. All rights reserved.
GENERAL CONDITIONS
ARTICLE 1 - DEFINITIONS AND TERMINOLOGY
1.01 Defined Terms
A. Wherever used in the Bidding Requirements
or Contract Documents and printed with initial capital
letters, the terms listed below \vill have the meanings
indicated which are applicable to both the singular and
plural thereof. In addition to terms specifically defined,
terms with initial capital letters in the Contract
Documents include references to identified articles and
paragraphs, and the titles of other documents or forms.
I. Addenda-- Written or graphic instruments
issued prior to the opening of Bids which clarify, correct
or change the Bidding Requirements or the proposed
Contract Documents.
2. Agreemelll--The written instrument which is
evidence of the agreement between Owner and Contractor
covering the Work.
3. Applicarionfor PaYlllenl--The form acceptable
to Engineer which is to be used by Contractor during the
course of the Work in requesting progress or final
payments and which is to be accompanied by such
supporting documentation as is required by the Contract
Documents.
4. Asbeslos--Any material that contains more
than one percent asbestos and is friable or is releasing
asbestos fibers into the air above current action levels
established by the United States Occupational Safety and
Health Administration.
5. Bid--The offer or proposal of a Bidder
submitted on the prescribed form setting forth the prices
for the Work to be performed.
6. Bidder--The individual or entity who submits
a Bid directly to Owner.
7. Bidding
Requirements and the
(including all Addenda).
Doclllllenls-- The Bidding
proposed Contract Documents
8. Bidding Reqllirelllenls--The Advertisement or
Invitation to Bid, Instructions to Bidders, bid security of
acceptable form, if any. and the Bid Form with any
supplements.
9. Change Order--A document recommended by
Engineer which is signed by Contractor and Owner and
authorizes an addition, deletion, or revision in the \Vork
or an adjustment in the Contract Price or the Contract
Times. issued on or after the Effective Date of the
Agreement.
10. Clailll--A demand or assertion by Owner or
Contractor seeking an adjustment of Contract Price or
Contract Times, or both, or other relief \vith respect to the
terms of the Contract A demand for money or services by
a third party is not a Claim.
11. COlllracl--The entire and integrated written
agreement between the Owner and Contractor concerning
the \Vork. The Contract supersedes prior negotiations.
representations, or agreements, whether written or oral.
12. Conlracl DoclIlllents-- Those items so
designated in the Agreement. Only printed or hard copies
of the items listed in the Agreement are Contract
Documents. Approved Shop Drawings, other Contractor's
submittals, and the reports and drawings of subsurface
and physical conditions are not Contract Documents.
13. Contracl Price--The moneys payable by
Owner to Contractor for completion of the Work in
accordance with the Contract Documents as stated in the
Agreement (subject to the provisions of Paragraph 11.03
in the case of Unit Price Work).
14. Contract Times-- The number of days or the
dates stated in the Agreement to: (i) achieve i\'lilestones, if
any, (ii) achieve Substantial Completion; and (iii) com-
plete the Work so that it is ready for final payment as
evidenced by Engineer's written recommendation of final
payment.
15. COlllraclor--The individual or entitv with
whom Owner has entered into the Agreement.
16. Cost of the \Vork--See Paragraph 11.0 I.A for
definition.
17. Drawings--That part of the Contract
Documents prepared or approved by Engineer which
graphically shows the scope, extent. and character of the
Work to be performed by Contractor. Shop Drawings and
other Contractor submittals are not Drawings as so
deri ned.
18. Effective Date of the Agreclllent--The date
indicated in the Agreement on which it becomes effective.
but if no sllch elate is indicated. it means the date on
which the Agreement is signed and delivered by the last
of the two parties to sign and deliver.
19. Engincer-- The individual or entitv named as
such in the Agreement.
EJCDC C-700 Standard Gcncral Conditions of thc Construction Contract.
Copyright @ 2002 National Socicty of Profcssional Enginccrs for E.JCDC. All rights rcscrved.
00700 - 6
20. Field Onler--A written order issued by
Engineer which requires minor changes in the Work but
which does not involve a change in the Contract Price or
the Contract Times.
21. Gelleral Requirelllellfs--Sections of Division
1 of the Specifications. The General Requirements pertain
to all sections of the Specifications.
22. Hm:ardous Ellvirollmellfal COlldifiolln The
presence at the Site of Asbestos, PCBs, Petroleum.
Hazardous Waste. or Radioactive i'vlaterial in such
quantities or circumstances that may present a substantial
danger to persons or property exposed thereto in
connection with the Work.
23. Hazardous Wasfe--The term Hazardous
Waste shall have the meaning provided in Section 1004 of
the Solid Waste Disposal Act (42 USC Section 6903) as
amended from time to time.
24. Laws alld Regulafions; Laws or Regulatiolls-
-Any and all applicable laws, rules, regulations, ordinanc-
es. codes, and orders of any and all governmental bodies.
agencies, authorities, and courts having jurisdiction.
25. Liens--Charges,
encumbrances upon Project
personal property.
security interests. or
funds. real property, or
26. Milesfone--A principal event specified in the
Contract Documents relating to an intermediate comple-
tion date or time prior to Substantial Completion of all the
Work.
27. NOfice 0/ A wardn The written notice by
Owner to the Successful Bidder stating that upon timely
compliance by the Successful Bidder with the conditions
precedent listed therein, Owner will sign and deliver the
Agreement.
28. Norice fO Proceed--A written notice given by
Owner to Contractor fixing the date on which the Con-
tract Times will commence to run and on which
Contractor shall start to perform the Work under the
Contract Documents.
29. OWller--The individual or entity with whom
Contractor has entered into the Agreement and for whom
the Work is to be performed.
30. PCBs--Polychlorinated biphenyls.
31. Pefroleum--Petroleum. including crude oil or
anY' fraction thereof vvhich is liquid at standard conditions
of temperature and pressure (60 degrees Fahrenheit and
14.7 pounds per square inch absolute), such as oiL
petroleum, fuel oiL oil sludge, oil refuse, gasoline,
kerosene. and oil mixed with other non-I-Iazardous Waste
and crude oils.
32. Progress SchedulenA schedule, prepared and
maintained by Contractor, describing the sequence and
duration of the activities comprising the Contractor's plan
to accomplish the Work within the Contract Times.
33. Projecf--The total construction of which the
'Nork to be performed under the Contract Documents may
be the whole. or a part.
34. Projecf l'vlanual--The bound documentary
information prepared for bidding and constructing the
Work. A listing of the contents of the Project ManuaL
which may be bound in one or more volumes. is
contained in the table(s) of contents.
35. Radioactive i'yfaterial--Source, special nucle-
ar, or byproduct material as defined by the Atomic Energy
Act of 1954 (42 USC Section 2011 et seq.) as amended
from time to time.
36. Relafed Emit), -- An officer, director, partner,
employee, agent, consultant, or subcontractor.
37. Resident Project Representative--The autho-
rized representative of Engineer who may be assigned to
the Site or any part thereof.
38. Somples--Physical examples of materials,
equipment, or workmanship that are representative of
some portion of the Work and which establish the
standards by which such portion of the Work will be
i ud "ed.
39. Schedule ofSubmitwls--A schedule, prepared
and maintained by Contractor, of required submittals and
the time requirements to support scheduled performance
of related construction activities.
40. Schedule of \ialues--A schedule, prepared
and maintained by Contractor, allocating portions of the
Contract Price to various portions of the \V ork and used
as the basis for reviewing Contractor's Applications for
Payment.
41. Shop Drawings--AlI drawings, diagrams,
illustrations. schedules, and other data or information
which are specifically prepared or assembled by or for
Contractor and submitted by Contractor to illustrate some
portion of the Work.
42. Sire--Lands or areas indicated in the Contract
Documents as being furnished by Owner upon which the
Work is to be performed, including rights-of-way and
easements for access thereto. and such other lands
furnished by Owner which are designated for the use of
Contractor.
43. Specific{l[ions--That part of the Contract
Documents consisting of written requirements for
materials. equipment systems, standards and
workmanship as applied to the Work. and certain
EJCDC C-700 Standard Gcncral Conditions of thc Construction Contract.
Copyright @ 2002 National Socicty of Professional Enginccrs for EJ CDC. All rights rcscrvcd.
,7
administrative requirements and procedural matters
applicable thereto.
44. SubconrractoruAn individual or entity
having a direct contract with Contractor or with any other
Subcontractor for the performance of a part of the Work
at the Site.
45. Substantial COlllpletion--The time at which
the Work (or a specified part thereof) has progressed to
the point where. in the opinion of Engineer, the Work (or
a specified part thereof) is sufficiently complete, in
accordance with the Contract Documents, so that the
Work (or a specified part thereof) can be utilized for the
purposes for which it is intended. The terms "substantially
complete" and "substantially completed" as applied to all
or part of the Work refer to Substantial Completion
thereof.
46. Successjitl Bidder-- The Bidder submitting a
responsive Bid to whom Owner makes an award.
47. Supplemenrary ConditionsuThat part of the
Contract Documents which amends or supplements these
General Conditions.
48. Supplier--A manufacturer, fabricator, suppli-
er. distributor. materialman. or vendor having a direct
contract with Contractor or with any Subcontractor to
furnish materials or equipment to be incorporated in the
Work by Contractor or any Subcontractor.
49. Underground Facilities--All underground
pipelines, conduits, ducts, cables, wires, manholes, vaults,
tanks. tunnels, or other such facilities or attachments, and
any encasements containing such facilities. including
those that convey electricity. gases, steam, liquid
petroleum products, telephone or other communications,
cable television. water. wastewater. storm water. other
liquids or chemicals, or traffic or other control systems.
SO. Unit Price Ie\lork--Work to be paid for on the
basis of unit prices.
51. Work-- The entire construction or the various
separately identifiable parts thereof required to be
provided under the Contract Documents. Work incl udes
and is the result of performing or providing all labor.
services, and documentation necessary to produce such
construction, and furnishing, installing. and incorporating
all materials and equipment into such construction, all as
required by the Contract Documents.
but is evidence that the parties expect that the change
ordered or documented by a Work Change Directive will
be incorporated in a subsequently issued Change Order
following negotiations by the parties as to its effect. if
any. on the Contract Price or Contract Times.
1.02
Terminolooy
0.
A. The following words or terms are not defined
but. when used in the Bidding Requirements or Contract
Documents, have the following meaning.
B. lnrent of Certain Terms or A.djectives
1. The Contract Documents include the terms "as
allowed," "as approved," "as ordered", "as directed" or
terms of like effect or import to authorize an exercise of
professional judgment by Engineer. In addition, the
adjecti ves "reasonable." "suitable," "acceptable,"
"proper." "satisfactory," or adjectives of like effect or
import are used to describe an action or determination of
Engineer as to the Work. It is intended that such exercise
of professional judgment, action or determination will be
solely to evaluate, in general, the Work for compliance
with the requirements of and information in the Contract
Documents and conformance with the design concept of
the completed Project as a functioning whole as shown or
indicated in the Contract Documents (unless there is a
specific statement indicating otherwise). The use of any
such term or adjective is not intended to and shall not be
effective to assign to Engineer any duty or authority to
supervise or direct the performance of the Work or any
duty or authority to undertake responsibility contrary to
the provisions of Paragraph 9.09 or any other provision of
the Contract Documents.
C.Day
1. The word "day" means a calendar day
of 24 hours measured from midnight to the next midnight.
D. Defective
1. The word "defective." when modifying the
word "Work." refers to Work that is unsatisfactory,
faulty. or deficient in that it:
a. does not conform to the Contract Documents.
or
b. does not meet the requirements of any
applicable inspection, reference standard, test. or
approval referred to in the Contract Documents,
or
52. Ie\lork Change Directive--A written statement
to Contractor issued on or after the Effecti ve Date of the
Agreement and signed by Owner and recommended by
Engineer ordering an addition. deletion. or revision in the
Work, or responding to differing or unforeseen subsurface
or physical conditions under which the Work is to be
performed or to emergencies. A Work Change Directive
\vill not change the Contract Price or the Contract Times
E.JCDC C-700 Standard General Conditions of the Construction Contract.
Copyright @ 2002 National Society of Professional Engineers for E.JCDC. All rights reserved.
c. has been damaged prior to Engineer's -
recommendation of final payment (unless
responsibility for the protection thereof has been
assumed by Owner at Substantial Completion in
accordance with Paragraph 14.04 or 14.05).
E. FUrJlish, Install, PeJjCirlll. Provide
I. The word "furnish." when used in connection
with services, materials. or equipment. shall mean to
supply and deliver said services, materials, or equipment
to the Site (or some other specified location) ready for use
or installation and in usable or operable condition.
2. The word "install." when used in connection
with services, materials, or equipment. shall mean to put
into use or place in final position said services, materials,
or equipment complete and ready for intended use.
3. The words "perform" or "provide," when used
in connection with services, materials, or equipment. shall
mean to furnish and install said services. materials. or
equipment complete and ready for intended use.
4. When "furnish," "install." "perform," or "pro-
vide" is not used in connection with services. materials. or
equipment in a context clearly requiring an obligation of
Contractor, "provide" is implied.
F. Unless stated otherwise in the Contract Docu-
ments. words or phrases which have a well-known
technical or construction industry or trade meaning are
used in the Contract Documents in accordance with such
recognized meaning.
ARTICLE 2 PRELIMINARY MATTERS
2.0 I Delivery of Bonds ([nd Evidence of Insurance
A. When Contractor delivers the executed
counterparts of the Agreement to Owner, Contractor shall
also deliver to Owner such bonds as Contractor may be
required to furnish.
B. E\'idence of Insurance: Before any Work at
the Site is started. Contractor and Owner shall each
deliver to the other, with copies to each additional insured
identified in the Supplementary Conditions, certificates of
insurance (and other evidence of insurance which either
of them or any additional insured may reasonably request)
which Contractor and Owner respectively are required to
purchase and maintain in accordance with Article 5.
2.02
Copies of Documents
A. Owner shall furnish to Contractor up to ten
printed or hard copies of the Drawings and Project
Manual. Additional copies will be furnished upon request
at the cost of reproduction.
2.03 Commencement of Contract Times: Notice to
Proceed
A. The Contract Times will commence to run on
the thirtieth day after the Effective Date of the Agreement
or, if a Notice to Proceed is given. on the day indicated in
the Notice to Proceed. A Notice to Proceed may be given
at any time within 30 days after the Effective Date of the
Agreement. In no event will the Contract Times com-
mence to run later than the sixtieth day after the day of
Bid opening or the thirtieth day after the Effective Date of
the Agreement. whichever date is earlier.
2.04 Starling the yVork
A. Contractor shall start to perform the Work on
the date when the Contract Times commence to run. No
Work shall be done at the Site prior to the date on which
the Contract Times commence to run.
2.05 Before Starting Construction
A. Preliminary Schedules: Within 10 days after
the Effective Date of the Agreement (unless otherwise
specified in the General Requirements). Contractor shall
submit to Engineer for timely review:
I. a preliminary Progress Schedule; indicating
the times (numbers of days or dates) for starting and
completing the various stages of the Work, including any
Milestones specified in the Contract Documents;
2. a preliminary Schedule of Submittals; and
3. a preliminary Schedule of Values for all of the
Work which includes quantities and prices of items which
when added together equal the Contract Price and subdi-
vicks the Work into component parts in sufficient detail to
serve as the basis for progress payments during
performance of the Work. Such prices will include an
appropriate amount of overhead and profit applicable to
each item of Work.
2.06 Preconstruction Conference
A. Before any Work at the Site is started. a
conference attended by Owner, Contractor, Engineer, and
others as appropriate will be held to establish a working
understanding among the parties as to the \Vork and to
discuss the schedules referred to in Paragraph 2.05.A.
procedures for handling Shop Drawings and other
submittals, processing Applications for Payment. and
maintaining required records.
2.07
Initial Acceptance of Schedules
A. At least 10 days before submission of the first
Application for Payment a conference attended by
Contractor, Engi neer, and others as appropriate will be
held to review for acceptability to Engineer as provided
below the schedules submitted in accordance with
Paragraph 2.05.A. Contractor shall have an additional 10
days to make corrections and adjustments and to complete
and resubmit the schedules. No progress payment shall be
made to Contractor until acceptable schedules are
submitted to Engineer.
EJCDC C-700 Standard General Conditions of the Construction Contract.
Copyright @ 2002 National Society of Professional Engineers for EJCDC. All rights reserved.
00700 - 9
4.02 Sub.I'ulface and Physical Conditions
A. Reporrs and Drawings: The Supplementary
Conditions identify:
1. those reports of explorations and tests of
subsurface conditions at or contiguous to the Site that
Engineer has used in preparing the Contract Documents;
and
2. those drawings of physical conditions in or
relating to existing surface or subsurface structures at or
contiguous to the Site (except Underground Facilities)
that Engineer has used in preparing the Contract
Documents.
B. Limited Reliance by ContraclOr on Technical
Data Authorized: Contractor may rely upon the general
accuracy of the "technical data" contained in such reports
and dra wi ngs, but such reports and dril\vi ngs are not
Contract Documents. Such "technical data" is identified
in the Supplementary Conditions. Except for such reliance
on such "technical data," Contractor may not rely upon or
make any claim against Owner or Engineer. or any of
their Related Entities \vith respect to:
1. the completeness of such reports and drawings
for Contractor's purposes, including, but not limited to,
any aspects of the means. methods. techniques,
sequences. and procedures of construction to be employed
by Contractor. and safety precautions and programs
incident thereto: or
2. other data. interpretations, opinions, and
information contained in such reports or shown or
indicated in such dra wings; or
3. any Contractor interpretation of or conclusion
drawn from any "technical data" or any such other data.
interpretations, opinions, or information.
4.03
Differing SUbslll}(lce or Physical Conditions
A. Notice: If Contractor believes that any subsur-
face or physical condition at or contiguous to the Site that
is uncovered or revealed either:
1. is of such a nature as to establish that any
"technical data" on which Contractor is entitled to rely as
provided in Paragraph 4.02 is materially inaccurate; or
2. is of such a nature as to require a change in the
Contract Documents; or
3. differs materially from that shown or indicated
in the Contract Documents: or
4. is of an unusual nature. and differs materially
from conditions ordinarily encountered and generally
recognized as inherent in work of the character provided
for in the Contract Documents;
then Contractor shall. promptly after becoming aware
thereof and before further disturbing the subsurface or
physical conditions or performing any Work in connec-
tion therewith (except in an emergency as required by
Paragraph 6.I6.A), notify Owner and Engineer in writing
about such condition. Contractor shall not further disturb
such condition or perform any Work in connection
therewith (except as aforesaid) until receipt of written
order to do so.
B. Engineer's Re\'iew: After receipt of written
notice as required by Paragraph 4.03.A, Engineer will
promptly review the pertinent condition, determine the
necessity of Owner's obtaining additional exploration or
tests with respect thereto, and advise Owner in writing
(with a copy to Contractor) of Engineer'S findings and
concl usions.
C. Possible Price and Times Adjustments
1. The Contract Price or the Contract Times. or
both. will be equitably adjusted to the extent that the
existence of such differing subsurface or physical
condition causes an increase or decrease in Contractor's
cost of, or time required for, performance of the \V ork;
subject, however, to the following:
a. such condition must meet anyone or more of
the categories described in Paragraph 4.03.A;
and
b. with respect to Work that is paid for on a Unit
Price Basis, any adjustment in Contract Price
will be subject to the provisions of Paragraphs
9.07 and 11.03.
2. Contractor shall not be entitled to any
adjustment in the Contract Price or Contract Times if:
a. Contractor knew of the existence of such
conditions at the time Contractor made a final
commitment to Owner with respect to Contract
Price and Contract Times by the submission of a
Bid or becoming bound under a negotiated
contract: or
b. the existence of such condition could
reasonably have been discovered or revealed as a
result of any examination, investigation, explo-
ration. test. or study of the Site and contiguous
areas required by the Bidding Requirements or
Contract Documents to be conducted by or for
Contractor prior to Contractor's making such
final commitment: or
EJCDC C-700 Standard General Conditions of the Construction Contract.
Copyright @ 2002 National Society of Professional Engineers for E.JCDC. All rights reserved.
00700 - 12
c. Contractor failed to give the written notice as
required by Paragraph 4.03.A.
3. If Owner and Contractor are unable to agree
on entitlement to or on the amount or extent. if any. of
any adjustment in the Contract Price or Contract Times,
or both, a Claim may be made therefor as provided in
Paragraph 10.05. However, Owner and Engineer, and any
of their Related Entities shall not be liable to Contractor
for any claims, costs, losses, or damages (including but
not limited to all fees and charges of engineers, architects,
attorneys, and other professionals and all court or
arbitration or other dispute resolution costs) sustained by
Contractor on or in connection \vith any other project or
anticipated project.
4.04 Underground Facilities
A. Shown or Indicated: The information and data
shown or indicated in the Contract Documents with
respect to existing Underground Facilities at or
contiguous to the Site is based on information and data
furnished to Owner or Engineer by the owners of such
Underground Facilities, including Owner, or by others.
Unless it is otherwise expressly provided in the Sup-
plementary Conditions:
1. Owner and Engineer shall not be responsible
for the accuracy or completeness of any such information
or data; and
2. the cost of all of the following will be
included in the Contract Price. and Contractor shall have
full responsibility for:
a. revtewmg and checking all such information
and data.
b. locating all Underground Facilities shown or
indicated in the Contract Documents.
c. coordination of the Work with the owners of
such Underground Facilities. including Owner,
during construction. and
d. the safety and protection of all such U nder-
ground Facilities and repairing any damage
thereto resulting from the Work.
B. Not ShoH'n or Indicated
promptly review the Underground Facility and determine
the extent, if any, to which a change is required in the
Contract Documents to retlect and document the
consequences of the existence or location of the Under-
ground Facility. During such time. Contractor shall be
responsible for the safety and protection of such
Underground Facility.
2. If Engineer concludes that a change in the
Contract Documents is required. a Work Change
Directive or a Change Order will be issued to retlect and
document such consequences. An equitable adjustment
shall be made in the Contract Price or Contract Times, or
both. to the extent that they are attributable to the
existence or location of any Underground Facility that
was not shown or indicated or not shown or indicated
with reasonable accuracy in the Contract Documents and
that Contractor did not know of and could not reasonably
have been expected to be aware of or to have anticipated.
If Owner and Contractor are unable to agree on
entitlement to or on the amount or extent. if any. of any
such adjustment in Contract Price or Contract Times,
Owner or Contractor may make a Claim therefor as
provided in Paragraph 10.05.
4.05 Reference Poillls
A. Owner shall provide engmeering surveys to
establish reference points for construction which in
Engineer'S judgment are necessary to enable Contractor
to proceed with the Work. Contractor shall be responsible
for laying out the Work. shall protect and preserve the
established reference points and property monuments, and
shall make no changes or relocations without the prior
written approval of Owner. Contractor shall report to
Engineer whenever any reference point or property
monument is lost or destroyed or requires relocation
because of necessary changes in grades or locations. and
shall be responsible for the accurate replacement or
relocation of such reference points or property
monuments by professionally qualified personnel.
4.06
Hazardous Environmental Condition at Site
A. Reports and Drmvings: Reference is made to
the Supplementary Conditions for the identification of
those reports and drawings relating to a Hazardous
Environmental Condition identified at the Site. if any. that
have been utilized by the Engineer in the preparation of
the Contract Documents.
B. Limited Reliance by COlllraclor 011 Technical
Data Authorized: Contractor may rely upon the general
accuracy of the "technical data" contained in such reports
and drawings. but such reports and drawings are not
Contract Documents. Such "technical data" is identified
in the Supplementary Conditions. Except for such reliance
on such "technical data," Contractor may not rely upon or
make any claim against Owner or Engineer, or any of
their Related Entities with respect to:
1. If an Underground Facility is uncovered or
revealed at or contiguous to the Site which was not shown
or indicated. or not shown or indicated with reasonable
accuracy in the Contract Documents. Contractor shall.
promptly after becoming aware thereof and before further
disturbing conditions affected thereby or performing any
Work in connection therewith (except in an emergency as
required by Paragraph 6.16./\), identify the owner of such
Underground Facility and give written notice to that
owner and to Owner and Engineer, Engineer will
E.JCDC C-700 Standard General Conditions of the Construetion Contract.
Copyright @ 2002 National Society or Proressional Engineers for EJCDC. All rights reserved.
1. the completeness of such reports and drawings
for Contractor's purposes, including, but not limited to,
any aspects of the means, methods, techniques, sequences
and procedures of construction to be employed by
Contractor and safety precautions and programs incident
thereto; or
2. other data, interpretations. opinions and
information contained in such reports or shown or
indicated in such drawings; or
3. any Contractor interpretation of or conclusion
drawn from any "technical data" or any such other data,
interpretations, opinions or information.
C. Contractor shall not be responsible for any
Hazardous Environmental Condition uncovered or re-
vealed at the Site which was not shown or indicated in
Drawings or Specifications or identified in the Contract
Documents to be within the scope of the Work.
Contractor shall be responsible for a Hazardous
Environmental Condition created with any materials
brought to the Site by Contractor. Subcontractors,
Suppliers, or anyone else for whom Contractor is
responsible.
D. If Contractor encounters a Hazardous
Environmental Condition or if Contractor or anyone for
whom Contractor is responsible creates a Hazardous
Environmental Condition, Contractor shall immediately:
(i) secure or otherwise isolate such condition; (ii) stop all
Work in connection with such condition and in any area
affected thereby (except in an emergency as required by
Paragraph 6.16.A); and (iii) notify Owner and Engineer
(and promptly thereafter confirm such notice in writing).
Owner shall promptly consult with Engineer concerning
the necessity f~)f Owner to retain a quali fied expert to
evaluate such condition or take corrective action, if any.
E. Contractor shall not be required to resume
Work in connection with such condition or in any affected
area until after Owner has obtained any required permits
related thereto and delivered to Contractor written notice:
(i) specifying that such condition and any affected area is
or has been rendered safe for the resumption of Work: or
(ii) specifying any special conditions unclCr which such
Work may be resumed safely. If Owner and Contractor
cannot agree as to entitlement to or on the amount or
extent, if any, of any adjustment in Contract Price or
Contract Times, or both, as a result of such \Vork stop-
page or such special conditions under which Work is
agreed to be resumed by Contractor, either party may
make a Claim therefor as provided in Paragraph 10.05.
entitlement to or on the amount or extent. if any. of an
adjustment in Contract Price or Contract Times as a result
of deleting such portion of the Work. then either party
may make a Claim therefor as provided in Paragraph
10.05. Owner may have such deleted portion of the Work
performed by Owner's own forces or others in accordance
with A.rticle 7.
G. To the fullest extent permitted by Laws and
Regulations, Owner shall indemnify and hold harmless
Contractor. Subcontractors, and Engineer. and the
officers. directors. partners, employees, agents,
consultants, and subcontractors of each and any of them
from and against all claims. costs, losses, and damages
(including but not limited to all fees and charges of
engineers, architects, attorneys. and other professionals
and all court or arbitration or other dispute resolution
costs) arising out of or relating to a Hazardous
Environmental Condition, provided that such Hazardous
Environmental Condition: (i) was not shown or indicated
in the Drawings or Specifications or identified in the
Contract Documents to be included within the scope of
the Work. and (ii) was not created by Contractor or by
anyone for whom Contractor is responsible. Nothing in
this Paragraph 4.06. G shall obligate Owner to indemnify
any individual or entity from and against the conse-
quences of that individual's or entity's own negligence.
H. To the fullest extent permitted by Laws and
Regulations, Contractor shall indemnify and hold
harmless Owner and Engineer. and the officers. directors.
partners, employees. agents. consultants. and
subcontractors of each and any of them from and against
all claims, costs. losses, and damages (including but not
limited to all fees and charges of engineers. architects,
attorneys, and other professionals and all court or
arbitration or other dispute resolution costs) arising out of
or relating to a Hazardous Environmental Condition
created by Contractor or by anyone for whom Contractor
is responsible. Nothing in this Paragraph 4.06.H shall
obligate Contractor to indemnify any individual or entity
from and against the consequences of that individual's or
entity's own negligence.
1. The provisions of Paragraphs 4.02, 4.03. and
4.04 do not apply to a Hazardous Environmental
Condition uncovered or revealed at the Site.
ARTICLE 5 BONDS Al.'JD INSUI<.ANCE
5.01 PCljor/1/ance, Payment. and Other Bonds
F. If after receipt of such written notice A. Contractor shall furnish performance and
Contractor does not agree to resume such Work based on payment bonds, each in an amount at least equal to the
a reasonable belief it is unsafe. or does not agree to Contract Price as security for the faithful performance and
resume such Work under such special conditions, then payment of all of Contractor's obligations under the
Owner may order the portion of the Work that is in the Contract Documents. These bonds shall remain in effect
area affected by such condition to be deleted from the until one year after the date when final payment becomes
Work. If Owner and Contractor cannot agree as to due or until completion of the correction period specified
EJCDC C-700 Standard General Conditions of the Construction Contract.
Copyright @ 2002 National Society of Professional Engineers for EJ CDC. All rights reserved.
00700 - 14
in Paragraph 13.07, whichever is later, except as provided
otherwise by Laws or Regulations or by the Contract
Documents. Contractor shall also furnish such other
bonds as are required by the Contract Documents.
B. All bonds shall be in the form prescribed by
the Contract Documents except as provided otherwise by
Laws or Regulations. and shall be executed by such
sureties as are named in the current list of "Companies
Holding Certificates of Authority as Acceptable Sureties
on Federal Bonds and as Acceptable Reinsuring Compa-
nies" as published in Circular 570 (amended) by the
Financial Management Service. Surety Bond Branch. U.S.
Department of the Treasury. All bonds signed by an agent
must be accompanied by a certified copy of the agent's
authority to act.
C. If the surety on any bond furnished by
Contractor is declared bankrupt or becomes insolvent or
its right to do business is terminated in any state where
any part of the Project is located or it ceases to meet the
requirements of Paragraph 5.0I.B, Contractor' shall
promptly notify Owner and Engineer and shall, within 20
days after the event giving rise to such notification.
provide another bond and surety, both of which shall
comply with the requirements of Paragraphs 5.01.B and
5.02.
5.02 Licensed Sureties and Insurers
A. All bonds and insurance req uired by the
Contract Documents to be purchased and maintained by
Owner or Contractor shall be obtained from surety or
insurance companies that are duly licensed or authorized
in the jurisdiction in which the Project is Iocated to issue
bonds or insurance policies for the limits and coverages
so required. Such surety and insurance companies shall
also meet such additional requirements and qualifications
as may be provided in the Supplementary Conditions.
5.03
Cernficaies of Insurance
A. Contractor shall deli vel' to Owner, with copies
to each additional insured identi fied in the Supplementary
Conditions, certificates of insurance (and other evidence
of insurance requested by Owner or any other additional
insured) which Contractor is required to purchase and
maintain.
B. Owner shall deliver to Contractor, with copies
to each additional insured identified in the Supplementary
Conditions. certificates of insurance (and other evidence
of insurance requested by Contractor or any other
additional insured) which Owner is required to purchase
and maintain.
5.04 ContraClor's Liabiliry Insurance
from claims set forth below which may arise out of or
result from Contractor's performance of the Work and
Contractor's other obligations under the Contract
Documents, whether it is to be performed by Contractor,
any Subcontractor or Supplier, or by anyone directly or
indirectly employed by any of them to perform any of the
Work. or by anyone for whose acts any of them may be
liable:
1. claims under workers' compensation.
disability benefits. and other similar employee benefit
acts;
2. claims for damages because of bodily injury,
occupational sickness or disease, or death of Contractor's
employees;
3. claims for damages because of bodily injury,
sickness or disease. or death of any person other than
Contractor's employees;
4. claims for damages insured by reasonably
available personal injury liability coverage which are sus-
tained:
a. by any person as a result of an offense directly
or indirectly related to the employment of such
person by Contractor, or
b. by any other person for any other reason;
5. c1ai ms for damages, other than to the Work
itself. because of injury to or destruction of tangible
property wherever located, including loss of use resulting
therefrom; and
6. claims for damages because of bodily injury or
death of any person or property damage arising out of the
ownership, maintenance or use of any motor vehicle.
B. The policies of insurance required by this
Paragraph 5.04 shall:
1. with respect to insurance required by
Paragraphs 5.04.A.3 through 5.04.A.6 inclusive, include
as additional insured (subject to any customary exclusion
regarding professional liability) Owner and Engineer, and
any other individuals or entities identified in the Supple-
mentary Conditions. all of whom shall be listed as addi-
tional insureds, and inc I ude coverage for the respecti ve
officers. directors. partners. employees, agents.
consultants and subcontractors of each and any of all such
additional insureds. and the insurance afforded to these
additional insureds shall provide primary coverage for all
claims covered thereby:
2. include at least the specific coverages and be
written for not less than the limits of liability provided in
the Supplementary Conditions or required by Laws or
Regulations. whichever is greater:
A Contractor shall purchase and maintain such
liability and other insurance as is appropriate for the
Work being performed and as will provide protection
EJCDC C-700 Standard General Conditions of the Construction Contract.
Copyright @ 2002 National Society of Professional Engineers for EJCDC. All rights reserved.
00700 - 15
3. include completed operations insurance:
4. incl ude contractual
covering Contractor's indemnity
Paragraphs 6.11 and 6.20;
liability insurance
obligations under
5. contain a provision or endorsement that the
coverage afforded will not be canceled, materially
changed or renewal refused unti I at least 30 days prior
written notice has been given to Owner and Contractor
and to each other additional insured identified in the
Supplementary Conditions to whom a certificate of
insurance has been issued (and the certificates of
insurance furnished by the Contractor pursuant to
Paragraph 5.03 will so provide);
6. remain in effect at least until final payment
and at all times thereafter when Contractor may be
correcting, removing, or replacing defecti ve Work in
accordance with Paragraph 13.07; and
7. with respect to completed operations insur-
ance, and any insurance coverage written on a claims-
made basis, remain in effect for at least two years after
final payment.
a. Contractor shall furnish Owner and each other
additional insured identified in the Supple-
mentary Conditions. to whom a certificate of
insurance has been issued. evidence satisfactory
to Owner and any such additional insured of
continuation of such insurance at final payment
and one year thereafter.
5.05 Owner's Liabilily Insurance
A. In addition to the insurance required to be
provided by Contractor under Paragraph 5.04, Owner, at
Owner's option, may purchase and maintain at Owner's
expense Owner's own liability insurance as will protect
Owner against claims which may arise from operations
under the Contract Documents.
5.06 Properry Insurance
A. Unless otherwise provided in the Supple-
mentary Conditions, Owner shall purchase and maintain
property insurance upon the Work at the Site in the
amount of the full replacement cost thereof (subject to
such deductible amounts as may be provided in the
Supplementary Conditions or required by Laws and
Regulations). This insurance shall:
1. include the interests of Owner. Contractor.
Subcontractors, and Engineer. and any other individuals
or entities identified in the Supplementary Conditions,
and the officers, directors. partners, employees, agents,
consultants and subcontractors of each and any of them.
each of whom is deemed to have an insurable interest and
shall be listed as an insured or additional insured:
2. be written on a Builder's Risk "all-risk" or
open peril or special causes of loss policy form that shall
at least include insurance for physical loss or damage to
the Work. temporary buildings, false work, and materials
and equipment in transit, and shall insure against at least
the following perils or causes of loss: fire, lightning.
extended coverage, theft, vandalism and malicious
mischief, earthquake, collapse, debris removal.
demolition occasioned by enforcement of Laws and
Regulations, water damage, (other than caused by flood)
and such other perils or causes of loss as may be specifi-
cally required by the Supplementary Conditions;
3. include expenses incurred in the repair or
replacement of any insured property (including but not
limited to fees and charges of engineers and architects);
4. cover materials and equipment stored at the
Site or at another Iocation that was agreed to in writing by
Owner prior to being incorporated in the Work. provided
that such materials and equipment have been included in
an Application for Payment recommended by Engineer;
5. allow for partial utilization of the Work by
Owner;
6. include testing and startup; and
7. be maintained in effect until final payment is
made unless otherwise agreed to in writing by Owner.
Contractor, and Engineer with 30 days written notice to
each other additional insured to whom a certificate of
insurance has been issued.
B. Owner shall purchase and maintain such
boiler and machinery insurance or additional property
insurance as may be required by the Supplementary
Conditions or Laws and Regulations which will include
the interests of Owner. Contractor. Subcontractors. and
Engineer. and any other individuals or entities identified
in the Supplementary Conditions, and the officers,
directors, partners, employees, agents, consultants and
subcontractors of each and any of them. each of whom is
deemed to have an insurable interest and shall be listed as
an insured or additional insured.
C. All the policies of insurance (and the certifi-
cates or other evidence thereol) required to be purchased
and maintained in accordance with Paragraph 5.06 will
contain a provision or endorsement that the coverage
afforded will not be canceled or materially changed or
renewal refused until at least 30 days prior written notice
has been gi ven to Owner and Contractor and to each other
additional insured to whom a certificate of insurance has
been issued and will contain waiver provisions in accor-
dance with Paragraph 5.07.
D. Owner shall not be responsible for purchasing
and maintaining any property insurance specified in this
Paragraph 5.06 to protect the interests of Contractor,
Subcontractors. or others in the \Vork to the extent of any
EJCDC C-700 Standard General Conditions of the Construction Contract.
Copyright @ 2002 National Society of Professional Engineers for EJCDC. All I'ights reserved.
00700 - 16
deductible amounts that are identified in the Supple-
mentary Conditions. The risk of loss within such
identified deductible amount will be borne by Contractor.
Subcontractors, or others suffering any such loss, and if
any of them wishes property insurance coverage within
the limits of such amounts, each may purchase and
maintain it at the purchaser's own expense.
E. If Contractor requests in writing that other
special insurance be included in the property insurance
policies provided under Paragraph 5.06. Owner shall, if
possible, include such insurance, and the cost thereof will
be charged to Contractor by appropriate Change Order.
Prior to commencement of the Work at the Site, Owner
shall in \vriting ad vise Contractor whether or not such
other insurance has been procured by Owner.
5.07 Waiver of Rigllls
A. Owner and Contractor intend that all policies
purchased in accordance with Paragraph 5.06 will protect
Owner, Contractor. Subcontractors, and Engineer, and all
other individuals or entities identi fied in the Supple-
mentary Conditions to be listed as insureds or additional
insureds (and the officers, directors, partners, employees,
agents, consultants and subcontractors of each and any of
them) in such policies and will provide primary coverage
for all losses and damages caused by the perils or causes
of loss covered thereby. All such policies shall contain
provisions to the effect that in the event of payment of
any loss or damage the insurers will have no rights of
recovery against any of the insureds or additional insureds
thereunder. Owner and Contractor wai ve all rights against
each other and their respective officers. directors,
partners, employees, agents. consultants and
subcontractors of each and any of them for all losses and
damages caused by, arising out of or resulting from any of
the perils or causes of loss covered by such policies and
any other property insurance applicable to the Work; and.
in addition, waive all such rights against Subcontractors,
and Engineer. and all other individuals or entities
identified in the Supplementary Conditions to be listed as
insured or additional insured (and the officers, directors,
partners, employees, agents. consultants and
subcontractors of each and any of them) under such
policies for losses and damages so caused. None of the
above waivers shall extend to the rights that any party
making such waiver may have to the proceeds of
insurance held by Owner as trustee or otherwise payable
under any policy so issued.
B. Owner waives all rights against Contractor.
Subcontractors. and Engineer. and the officers. directors.
partners, employees, agents. consultants and
subcontractors of each and any of them for:
1. loss due to business interruption, loss of' use.
or other consequential loss extending beyond direct
physical loss or damage to Owner's property or the Work
caused by. arising out of. or resulting from fire or other
perils whether or not insured by Owner: and
2. loss or damage to the completed Project or
part thereof caused by. arising out of. or resulting from
fire or other insured peril or cause of loss covered by any
property insurance maintained on the completed Project
or part thereof by Owner during partial utilization
pursuant to Paragraph 14.05, after Substantial Completion
pursuant to Paragraph 14.04, or after final payment
pursuant to Paragraph 14.07.
C. Any insurance policy maintained by Owner
covering any loss, damage or consequential loss referred
to in Paragraph 5.07.B shall contain provisions to the
effect that in the event of payment of any such loss,
damage, or consequential loss, the insurers will have no
rights of recovery against Contractor, Subcontractors, or
Engi neer, and the officers, directors. partners, employees,
agents. consultants and subcontractors of each and any of
them.
5.08 ReceipT and ApplicaTion of Insurance Proceeds
A. Any insured loss under the policies of
insurance required by Paragraph 5.06 will be adjusted
with Owner and made payable to Owner as fiduciary for
the insureds, as their interests may appear, subject to the
requirements of any applicable mortgage clause and of
Paragraph 5.08.B. Owner shall deposit in a separate
account any money so received and shall distribute it in
accordance with such agreement as the parties in interest
may reach. If no other special agreement is reached, the
damaged Work shall be repaired or rcplaced, the moncys
so received applied on account thereof. and the Work and
the cost thereof covered by an appropriate Change Order.
B. Owner as fiduciary shall have power to adjust
and settle any loss with the insurers unless one of the
parties in interest shall object in writing within 15 days
after the occurrence of loss to Owner's exercise of this
power. If such objection be made, Owner as fiduciary
shall make settlement with the insurers in accordance with
such agreement as the parties in interest may reach. If no
such agreement among the parties in interest is reached,
Owner as fiduciary shall adjust and settle the loss with the
insurers and, if required in writing by any party in
interest, Owner as fiduciary shall give bond for the proper
performance of such duties.
5.09 Accepwnce of Bonds and Insurance: Option to
Replace
A. If either Owner or Contractor has any
objection to the coverage afforded by or other provisions
of the bonds or insurance required to be purchased and
maintained by the other party in accordance with Article 5
on the basis of non-conformance with the Contract
E.JCDC C-700 Standard General Conditions of' the Construction Contract.
Copyright @ 2002 National Society of Prof'essional Engineers for E.JCDC. All rights reserved.
Documents. the objecting party shall so notify the other
party in writing within 10 days after receipt of the
certificates (or other evidence requested) required by
Paragraph 2.0 I.B. Owner and Contractor shall each
provide to the other such additional information in respect
of insurance provided as the other may reasonably
request. If either party does not purchase or maintain all
of the bonds and insurance required of such party by the
Contract Documents, such party shall notify the other
party in writing of such failure to purchase prior to the
start of the Work, or of such failure to maintain prior to
any change in the required coverage. Without prejudice to
any other right or remedy, the other party may elect to
obtain equi valent bonds or insurance to protect such other
party's interests at the expense of the party who was
required to provide such coverage, and a Change Order
shall be issued to adj ust the Contract Price accordingly.
5.10 Partial Utilization, Acknowledgment of Property
Insurer
A. If Owner finds it necessary to occupy or use a
portion or portions of the Work prior to Substantial
Completion of all the \Vork as provided in Paragraph
14.05, no such use or occupancy shall commence before
the insurers providing the property insurance pursuant to
Paragraph 5.06 have acknowledged notice thereof and in
writing effected any changes in coverage necessitated
thereby. The insurers providing the property insurance
shall consent by endorsement on the policy or policies,
but the property insurance shall not be canceled or
permitted to lapse on account of any such partial use or
occupancy.
ARTICLE 6 - CONTRACTOR'S RESPONSIBILITIES
6.0 I Supervision and Superintendence
A. Contractor shall supervise, inspect. and direct
the Work competently and efficiently, devoting such
attention thereto and applying such skills and expertise as
may be necessary to perform the Work in accordance with
the Contract Documents. Contractor shall be solely
responsible for the means. methods. techniques,
sequences, and procedures of construction. Contractor
shall not be responsible for the negligence of Owner or
Engineer in the design or specification of a specific
means, method, technique, sequence, or procedure of
construction which is shown or indicated in and expressly
required by the Contract Documents.
B. At all times during the progress of the Work.
Contractor shall assign a competent resident superin-
tendent who shall not be replaced without \vritten notice
to Owner and Engineer except under extraordinary
circumstances. The superintendent will be Contractor's
representative at the Site and shall have authority to act on
behalf of Contractor. All communications given to or
received from the superintendent shall be binding on
Contractor.
6.02 Labor; Working Hours
A. Contractor shall provide competent. suitably
qualified personnel to survey and layout the Work and
perform construction as required by the Contract Docu-
ments. Contractor shall at all times maintain good disci-
pline and order at the Site.
B. Except as otherwise required for the safety or
protection of persons or the Work or property at the Site
or adjacent thereto, and except as otherwise stated in the
Contract Documents, all Work at the Site shall be
performed during regular working hours. Contractor will
not permit the performance of Work on a Saturday,
Sunday, or any legal holiday without Owner's written
consent (which will not be unreasonably withheld) given
after prior written notice to Engineer.
6.03 Services, Materials. and Equipment
A. Unless otherwise specified in the Contract
Documents, Contractor shall provide and assume full
responsibility for all services, materials, equipment. labor,
transportation, construction equipment and machinery,
tools, appliances, fuel, power. light. heat. telephone,
water. sanitary facilities, temporary facilities, and all other
facilities and incidentals necessary for the performance,
testing, start-up, and completion of the Work.
B. All materials and equipment incorporated into
the Work shall be as specified or, if not specified, shall be
of good quality and new, except as otherwise provided in
the Contract Documents. All special warranties and
guarantees required by the Specifications shall expressly
run to the benefit of Owner. If required by Engineer.
Contractor shall furnish satisfactory evidence (including
reports of required tests) as to the source, kind, and
quality of materials and equipment.
C. All materials and equipment shall be stored.
applied. installed, connected, erected, protected, used,
cleellled. and conditioned in accordance with instructions
of the applicable Supplier. except as otherwise mav be
provided in the Contract Documents.
6.04 Progress Schedule
A. Contractor shall adhere to the Progress
Schedule established in accordance with Paragraph 2.07
as it may be adjusted from time to time as provided
below.
E.JCDC C-700 Standard General Conditions of the Construction Contract.
Copyright @ 2002 National Society of Professional Engineers for EJCDC. All rights reserved.
00700 - 18
I. Contractor shall submit to Engineer for
acceptance (to the extent indicated in Paragraph 2.07)
proposed adjustments in the Progress Schedule that will
not result in changing the Contract Times. Such adjust-
ments will comply with any provisions of the General Re-
quirements applicable thereto.
2) it will conform substantially to the
detailed requirements of the item named in the
Contract Documents.
2. Substitute Items
2. Proposed adjustments Il1 the Progress
Schedule that will change the Contract Times shall be
submitted in accordance with the requirements of Article
12. Adjustments in Contract Times may only be made by
a Change Order.
a. If in Engineer's sole discretion an item of
material or equipment proposed by Contractor
does not qualify as an "or-equal" item under
Paragraph 6.05.A.l, it will be considered a
proposed substitute item.
6.05 Substitllles and" Or-Equals"
b. Contractor shall submit sufficient information
as provided below to allow Engineer to
determine that the item of material or equipment
proposed is essentially equivalent to that named
and an acceptable substitute therefor. Requests
for review of proposed substitute items of
material or equipment will not be accepted by
Engineer from anyone other than Contractor.
A. Whenever an item of material or equipment is
specified or described in the Contract Documents by
using the name of a proprietary item or the name of a
particular Supplier, the specification or description is
intended to establish the type, function, appearance, and
quality required. Unless the specification or description
contains or is followed by \vords reading that no like,
equivalent or "or-equal" item or no substitution is
permitted, other items of material or equipment or
material or equipment of other Suppliers may be
submitted to Engineer for review under the circumstances
described below.
c. The requirements for review by Engineer will
be as set forth in Paragraph 6.05.A.2.d, as
supplemented in the General Requirements and
as Engineer may decide is appropriate under the
circumstances.
1. "Or-Equal" Items: If in Engineer's sole
discretion an item of material or equipment proposed by
Contractor is functionally equal to that named and
sufficiently similar so that no change in related Work will
be required, it may be considered by Engineer as an
"or-equal" item, in which case review and approval of the
proposed item may, in Engineer's sole discretion, be
accomplished without compliance with some or all of the
requirements for approval of proposed substitute items.
For the purposes of this Paragraph 6.05.A.1. a proposed
item of material or equipment will be considered
functionally equal to an item so named if:
d. Contractor shall make written application to
Engineer for review of a proposed substitute item
of material or equipment that Contractor seeks to
furnish or use. The application:
1) shall certify that the proposed substi-
tute item will:
a) perform adequately the functions and
achieve the results called for bv the
general design.
a. in the exercise of reasonable judgment
Engineer determines that:
b) be similar III substance to that
specified, and
1) it is at least equal in materials of
construction, quality, durability. appearance,
strength, and design characteristics:
c) be suited to the same use as that
specified;
2) will state:
2) it will reliably perform at least
equally well the function and achieve the results
imposed by the design concept of the completed
Project as a functioning whole.
a) the extent, if any, to which the use of
the proposed substitute item will preju-
dice Contractor's achievement of
Substantial Completion on time:
3) it has a proven record of performance
and availabiIity of responsive service: and
b) whether or not use of the proposed
substitute item in the Work will require
a change in any of the Contract Docu-
ments (or in the provisions of any other
direct contract with Owner for other
work on the Project) to adapt the design
to the proposed substitute item; and
b. Contractor certifies that. if approved and
incorporated into the Work:
1) there will be no increase in cost to
the Owner or increase in Contract Times. and
EJCDC C-700 Standard General Conditions of the Construction Contract.
Copyright @ 2002 National Society of Professional Engineers for E.JCDC. All rights reserved.
00700 - 19
c) whether or not incorporation or use
of the proposed substitute item in con-
nection with the Work is subject to
payment of any license fee or royalty:
3) will identify:
a) all variations of the proposed
substitute item from that specified, and
b) available engIlleenng, sales.
maintenance, repair, and replacement
serVIces;
4) and shall contain an itemized esti-
mate of all costs or credits that will result
directly or indirectly from use of such substitute
item, including costs of redesign and claims of
other contractors affected by any resulting
change,
B. Substilllte Construction j\1etllOds or Proce-
dures: If a specific means, method, technique, sequence,
or procedure of construction is expressly required by the
Contract Documents, Contractor may furnish or utilize a
substitute means. method. technique, sequence, or
procedure of construction approved by Engineer.
Contractor shall submit sufficient information to allow
Engineer, in Engineer's sole discretion. to determine that
the substitute proposed is equivalent to that expressly
called for by the Contract Documents. The requirements
for review by Engineer will be similar to those provided
in Paragraph 6.05.A.2.
C. Engineer's Evaluation: Engineer will be
allowed a reasonable time within which to evaluate each
proposal or submittal made pursuant to Paragraphs 6.05.A
and 6.05.B. Engineer may require Contractor to furnish
additional data about the proposed substitute item.
Engineer will be the sole judge of acceptability. No "or
equal" or substitute will be ordered. installed or utilized
until Engineer's review' is complete, which will be
evidenced by either a Change Order for a substitute or an
approved Shop Drawing for an "or eq ual." Engineer wi II
advise Contractor in writing of any negative
determination.
D. Special Guarantee: Owner may reqUlre
Contractor to furnish at Contractor's expense a special
performance guarantee or other surety with respect to any
substi tute.
E. Engineer's Cost Reimbursemellt: Engineer
will record Engineer's costs in evaluating a substitute
proposed or submitted by Contractor pursuant to
Paragraphs 6.05.A.2 and 6.05.B Whether or not Engineer
approves a substitute item so proposed or submitted by
Contractor. Contractor shall reimburse Owner for the
charges of Engineer for evaluating each such proposed
substitute. Contractor shall also reimburse Owner for the
charges of Engineer for making changes in the Contract
Documents (or in the provisIons of any other direct
contract with Owner) resulting from the acceptance of
each proposed substitute.
F. Contractor's Expense: Contractor shall
provide all data in support of any proposed substitute or
"or-equal" at Contractor's expense.
6.06 Concerning Subcontractors, Suppliers, and
Orlzers
A. Contractor shall not employ any Subcon-
tractor. Supplier. or other individual or entity (including
those acceptable to Owner as indicated in Paragraph
6.06.B), whether initially or as a replacement against
whom Owner may have reasonable objection. Contractor
shall not be required to employ any Subcontractor,
Supplier. or other individual or entity to furnish or
perform any of the Work against whom Contractor has
reasonable objection.
B. If the Supplementary Conditions require the
identity of certain Subcontractors, Suppliers, or other
individuals or entities to be submitted to Owner in
advance for acceptance by Owner by a specified date
prior to the Effective Date of the Agreement, and if
Contractor has submitted a list thereof in accordance with
the Supplementary Conditions. Owner's acceptance
(either in writing or by failing to make written objection
thereto by the date indicated for acceptance or objection
in the Bidding Documents or the Contract Documents) of
any such Subcontractor, Supplier, or other individual or
entity so identified may be revoked on the basis of reason-
able objection after due investigation. Contractor shall
submit an acceptable replacement for the rejected
Subcontractor. Supplier, or other individual or entity, and
the Contract Price will be adjusted by the difference in the
cost occasioned by such replacement, and an appropriate
Change Order will be issued. No acceptance by Owner of
any such Subcontractor, Supplier. or other individual or
entity, whether initially or as a replacement, shall consti-
tute a waiver of any right of Owner or Engineer to reject
defective Work.
C. Contractor shall be fully responsible to Owner
and Engineer for all acts and omissions of the
Subcontractors. Suppliers, and other individuals or
entities performing or furnishing any of the Work just as
Contractor is responsible for Contractor's own acts and
omissions. Nothing in the Contract Documents:
1. shall create for the benefit of any such
Subcontractor, Supplier. or other individual or entity any
contractual relationship between Owner or Engineer and
any such Subcontractor. Supplier or other individual or
entity. nor
') shall anything in the Contract Documents
create any obligation on the part of Owner or
Engineer to payor to see to the payment of any moneys
due any such Subcontractor, Supplier. or other individual
E.JCDC C-700 Standard General Conditions of the Construction Contract.
Copyright @ 2002 National Society of Professional Engineers for E.JCDC. All rights reserved.
00700 - 20
or entity except as may otherwise be required by Laws
and Regulations.
D. Contractor shall be solely responsible for
scheduling and coordinating the Work of Subcontractors.
Suppliers, and other individuals or entities performing or
furnishing any of the Work under a direct or indirect
contract with Contractor.
E. Contractor shall require all Subcontractors,
Suppliers, and such other individuals or entities per-
forming or furnishing any of the Work to communicate
with Engineer through Contractor.
F. The divisions and sections of the Specifica-
tions and the identifications of any Drawings shall not
control Contractor in dividing the Work among Subcon-
tractors or Suppliers or delineating the Work to be
performed by any specific trade.
G. All Work performed for Contractor by a
Subcontractor or Supplier will be pursuant to an appro-
priate agreement between Contractor and the
Subcontractor or Supplier which specifically binds the
Subcontractor or Supplier to the applicable terms and
conditions of the Contract Documents for the benefit of
Owner and Engineer. Whenever any such agreement is
with a Subcontractor or Supplier who is listed as an
additional insured on the property insurance provided in
Paragraph 5.06, the agreement between the Contractor
and the Subcontractor or Supplier will contain provisions
whereby the Subcontractor or Supplier waives all rights
against Owner. Contractor. and Engineer.. and all other
indi viduals or entities identified in the Supplementary
Conditions to be listed as insureds or additional insureds
(and the ofticers, directors, partners, employees, agents,
consultants and subcontractors of each and any of them)
for all losses and damages caused by, arising out of,
relating to, or resulting from any of the perils or causes of
loss covered by such policies and any other property
insurance applicable to the Work. If the insurers on any
such policies require separate waiver forms to be signed
by any Subcontractor or Supplier, Contractor will obtain
the same.
6.07 Patent Fees and Royalties
A. Contractor shall pay all license fees and
royalties and assume all costs incident to the use in the
performance of the Work or the incorporation in the Work
of any invention, design, process. product, or device
which is the subject of patent rights or copyrights held by
others. If a particular invention. design, process, product,
or device is specified in the Contract Documents for use
in the performance of the Work and if to the actual
knowledge of Owner or Engineer its use is subject to
patent rights or copyrights calling for the payment of any
license fee or royalty to others. the existence of such
rights shall be disclosed by Owner in the Contract
Documents.
B. To the fullest extent permitted by Laws and
Regulations. Contractor shall indemnify and hold
harmless Owner and Engineer. and the officers. directors.
partners. employees, agents. consultants and
subcontractors of each and any of them from and against
all claims, costs, losses, and damages (including but not
limited to all fees and charges of engineers. architects.
attorneys, and other professionals and all court or
arbitration or other dispute resolution costs) arising out of
or relating to any infringement of patent rights or
copyrights incident to the use in the performance of the
Work or resulting from the incorporation in the Work of
any invention, design, process, product, or device not
specitied in the Contract Documents.
6.08 Permirs
A. Unless otherwise provided in the Supple-
mentary Conditions, Contractor shall obtain and pay for
all construction permits and licenses. Owner shall assist
Contractor. when necessary, in obtaining such permits
and licenses. Contractor shall pay all governmental
charges and inspection fees necessary for the prosecution
of the Work which are applicable at the time of opening
of Bids, or, if there are no Bids, on the Effective Date of
the Agreement. Owner shall pay all charges of utility
owners for connections for providing permanent service
to the Work.
6.09 Laws Cllld Regulations
A. Contractor shall gi ve all notices required by
and shall comply with all Laws and Regulations applica-
ble to the performance of the Work. Except where
otherwise expressly required by applicable Laws and
Regulations. neither Owner nor Engineer shall be
responsible for monitoring Contractor's compliance with
any Laws or Regulations.
B. If Contractor performs any Work knowing or
having reason to kno\v that it is contrary to Laws or
Regulations. Contractor shall bear all claims, costs,
losses, and damages (including but not limited to all fees
and charges of engineers. architects. attorneys. and other
professionals and all court or arbitration or other dispute
resolution costs) arising out of or relating to such \Vork.
However. it shall not be Contractor's primary
responsibility to make certain that the Specifications and
Drawings are in accordance with Laws and Regulations.
but this shall not relieve Contractor of Contractor's
obligations under Paragraph 3.03.
C. Changes in Laws or Regulations not known at
the time of opening of Bids (or, on the Effective Date of
the Agreement if there were no Bids) having an effect on
the cost or time of performance of the Work shall be the
subject of an adjustment in Contract Price or Contract
Times. If Owner and Contractor are unable to agree on
entitlement to or on the amount or extent. if any. of any
such adjustment, a Claim may be made therefor as
provided in Paragraph 10.05.
EJCDC C- 700 Standard General Conditions of the Construction Contract.
Copyright @ 2002 National Society of Professional Engineers for EJCDC. All rights reserved.
00700 - 21
6.10 Taxes
A. Contractor shall pay all sales, consumer. use,
and other similar taxes required to be paid by Contractor
in accordance with the Laws and Regulations of the place
of the Project which are applicable during the
performance of the Work.
6.11 Use of Site and Other Areas
A Limitation on Use of Site and Other Areas
1. Contractor shall confine construction equip-
ment the storage of materials and equipment and the
operations of workers to the Site and other areas
permitted by Laws and Regulations, and shall not
unreasonably encumber the Site and other areas with
construction equipment or other materials or equipment.
Contractor shall assume full responsibility for any
damage to any such land or area, or to the owner or
occupant thereof, or of any adjacent land or areas
resulting from the performance of the Work.
2. Should any claim be made by any such owner
or occupant because of the performance of the Work,
Contractor shall promptly settle with such other party by
negotiation or otherwise resolve the claim by arbitration
or other dispute resolution proceeding or at law.
3. To the fullest extent permitted by Laws and
Regulations, Contractor shall indemnify and hold
harmless Owner and Engineer, and the officers, directors,
partners, employees, agents. consultants and
subcontractors of each and any of them from and against
all claims, costs, losses, and damages (including but not
limited to all fees and charges of engineers. architects.
attorneys. and other professionals and all court or
arbitration or other dispute resolution costs) arising out of
or relating to any claim or action, legal or equitable,
brought by any such owner or occupant against Owner,
Engineer, or any other party indemnified hereunder to the
extent caused by or based upon Contractor's performance
of the Work.
B. Removal of Debris During Performance of the
Work: During the progress of the Work Contractor shall
keep the Site and other areas free from accumulations of
waste materiaIs. rubbish. and other debris. Removal and
disposal of such waste materials, rubbish, and other debris
shall conform to applicable Laws and Regulations.
C. Cleaning: Prior to Substantial Completion of
the Work Contractor shall clean the Site and the Work
and make it ready for utilization by Owner. At the com-
pletion of the Work Contractor shall remove from the Site
all tools. appliances, construction equipment and
machinery, and surplus materials and shall restore to
original condition all property not designated for
alteration by the Contract Documents.
D. Loading Sirllctures: Contractor shall not load
nor permit any part of any structure to be loaded in any
manner that will endanger the structure. nor shall
Contractor subject any part of the Work or adjacent
property to stresses or pressures that will endanger it.
6.12 Record Documents
A. Contractor shall maintain in a safe place at the
Site one record copy of all Drawings, Specifications.
Addenda, Change Orders, Work Change Directives, Field
Orders, and written interpretations and clarifications in
good order and annotated to show changes made during
construction. These record documents together with all
approved Samples and a counterpart of all approved Shop
Drawings will be available to Engineer for reference.
Upon completion of the Work, these record documents,
Samples, and Shop Dra\vings will be delivered to Engi-
neer for Owner.
6.13 Safety and Protection
A. Contractor shall be solely responsible for
initiating, maintaining and supervising all safety precau-
tions and programs in connection with the Work.
Contractor shall take all necessary precautions for the
safety of. and shall provide the necessary protection to
prevent damage. injury or loss to:
1. all persons on the Site or \vho may be affected
by the Work;
2. all the Work and materials and equipment to
be incorporated therein, whether in storage on or off the
Site: and
3. other property at the Site or adjacent thereto,
including trees. shrubs. lawns. walks, pavements,
roadways. structures. utilities. and Underground Facilities
not designated for removal, relocation, or replacement in
the course of construction.
B. Contractor shall comply with all applicable
Laws and Regulations relating to the safety of persons or
property, or to the protection of persons or property from
damage, injury, or loss: and shall erect and maintain all
necessary safeguards for such safety and protection.
Contractor shall noti fy owners of adjacent property and of
Underground Facilities and other utility owners when
prosecution of the \Vork may affect them, and shall
cooperate with them in the protection, removal.
relocation, and replacement of their property.
C. All damage, injury, or loss to any property
referred to in Paragraph 6.13.A.2 or 6.13.A.3 caused.
directly or indirectly, in whole or in part by Contractor,
any Subcontractor. Supplier, or any other indi vidual or
entity directly or indirectly employed by any of them to
perform any of the Work. or anyone for whose acts any of
them may be liable. shall be remedied by Contractor
(except damage or loss attributable to the fault of Draw-
EJCDC C-700 Standard General Conditions of the Construction Contract.
Copyright @ 2002 National Society of Professional Engineers for E.JCDC. All rights reserved.
00700 - 22
ings or Specifications or to the acts or omissions of
Owner or Engineer or . or anyone employed by any of
them. or anyone for whose acts any of them may be
liable, and not attributable. directly or indirectly, in whole
or in part, to the fault or negligence of Contractor or any
Subcontractor, Supplier, or other individual or entity
directly or indirectly employed by any of them).
D. Contractor's duties and responsibilities for
safety and for protection of the Work shall continue until
such time as all the Work is completed and Engineer has
issued a notice to Owner and Contractor in accordance
with Paragraph I4.07.B that the Work is acceptable
(except as otherwise expressly provided in connection
with Substantial Completion).
6.14 Safety Representative
A. Contractor shall designate a qualified and
experienced safety representative at the Site whose duties
and responsibilities shall be the prevention of accidents
and the maintaining and supervising of safety precautions
and programs.
6.15 Hazard Communication Programs
A. Contractor shall be responsible for cOOI'di-
nating any exchange of material safety data sheets or
other hazard communication information required to be
made available to or exchanged between or among
employers at the Site in accordance with Laws or
Regulations.
6.16
Emergencies
A In emergencies affecting the safety or protec-
tion of persons or the Work or property at the Site or
adjacent thereto, Contractor is obligated to act to prevent
threatened damage, injury. or loss. Contractor shall give
Engineer prompt written notice if Contractor believes that
any significant changes in the Work or variations from the
Contract Documents have been caused thereby or are
required as a result thereof. If Engineer determines that a
change in the Contract Documents is required because of
the action taken by Contractor in response to such an
emergenc y. a Work Change Directive or Change Order
will be issued.
6.17 Shop Drawings and Samples
A. Contractor shall submit Shop Drawings and
Samples to Engineer for review and approval in accor-
dance with the acceptable Schedule of Submittals (as
required by Paragraph 2.07). Each submittal will be
identified as Engineer may require.
I. Shop Drawings
b. Data shown on the Shop Drawings will be
complete with respect to quantities, dimensions,
specified performance and design criteria,
materials, and similar data to show Engineer the
services. materials, and equipment Contractor
proposes to provide and to enable Engineer to
review the information for the limited purposes
required by Paragraph 6.17 .D.
') Samples: Contractor shall also submit
Samples to Engineer for review and approval in accor-
dance with the acceptable schedule of Shop Drawings and
Sample submittals.
a. Submit number of Samples specified in the
Specifications.
b. Clearly identify each Sample as to material,
Supplier, pertinent data such as catalog numbers,
the use for which intended and other data as
Engineer may require to enable Engineer to
review the submittal for the limited purposes
required by Paragraph 6.17 .D.
B. Where a Shop Drawing or Sample is required
by the Contract Documents or the Schedule of Submittals
, any related Work performed prior to Engineer's review
and approval of the pertinent submittal will be at the sole
expense and responsibility of Contractor.
C. Submittal Procedures
l. Before submitting each Shop Drawing or
Sample, Contractor shall have determined and verified:
a. all field measurements. quantities, dimensions,
specified performance and design criteria.
installation requirements. materials. catalog
numbers. and similar information with respect
thereto:
b. the suitability of all materials with re.spect to
intended use, fabrication, shipping, handling,
storage. assembly. and installation pertaining to
the performance 0 f the Work:
c. all information relative to Contractor's
responsibilities for means, methods, techniques.
sequences. and procedures of construction, and
safety precautions and programs incident thereto;
and
d. shall also ha ve reviewed and coordinated each
Shop Drawing or Sample
Drawings and Samples
requirements of the Work
Documents.
with other Shop
and with the
and the Contract
2. Each submittal shall bear a stamp or speci fic
written certi fication that Contractor has satisfied
Contractor's obligations under the Contract Documents
EJCDC C-700 Standard General Conditions of the Construction Contract.
Copyright @ 2002 National Society of Professional Engineers for E.JCDC. All rights reserved.
a. Submit number of copies specified in the
General Requirements.
A. To the fullest extent permitted by Laws and
Regulations. Contractor shall indemnify and hold
harmless Owner and Engineer. and the officers. directors,
partners, employees. agents. consultants and
subcontractors of each and any of them from and against
all claims, costs. losses, and damages (including but not
A. Contractor shall carryon the Work and adhere limited to all fees and charges of engineers, architects.
Progress Schedule during all disputes or attorneys, and other professionals and all court or
E.I CDC C-700 Standard General Conditions of the Construction Contract.
Copyright @ 2002 National Society of Professional Engineers for E.lCDC. All rights reserved.
00700 - 24
with respect to Contractor's review and approval of that
submittal.
3. With each submittal. Contractor shall give
Engineer specific written notice of any variations, that the
Shop Drawing or Sample may have from the requirements
of the Contract Documents. This notice shall be both a
wTitten communication separate from the Shop Drawing's
or Sample Submittal; and, in addition, by a specific
notation made on each Shop Drawing or Sample submit-
ted to Engineer for review and approval of each such
variation.
D. Engineer's Review
I. Engineer will provide timely review of Shop
Drawings and Samples in accordance with the Schedule
of Submittals acceptable to Engineer. Engineer's review
and approval will be only to determine if the items
covered by the submittals will, after installation or
incorporation in the Work, conform to the information
given in the Contract Documents and be compatible with
the design concept of the completed Project as a
functioning whole as indicated by the Contract Docu-
ments.
.., Engineer' s review and approval \vill not
extend to means, methods, techniques, sequences, or
procedures of construction (except where a particular
means, method, technique, sequence, or procedure of con-
struction is specifically and expressly called for by the
Contract Documents) or to safety precautions or programs
incident thereto. The review and approval of a separate
item as such will not indicate approval of the assembly in
which the item functions.
3. Engineer's review and approval shall not
relieve Contractor from responsibility for any variation
from the requirements of the Contract Documents unless
Contractor has complied with the requirements of
Paragraph 6.17.C.3 and Engineer has given written
approval of each such variation by specific written
notation thereof incorporated in or accompanying the
Shop Drawing or Sample. Engineer's review and approval
shall not relieve Contractor from responsibility for
complying with the requirements of Paragraph 6.17.C.1.
E. Resubmitted Procedures
1. Contractor shall make corrections required by
Engineer and shall return the required number of cor-
rected copies of Shop Drawings and submit, as required,
new Samples for review and approval. Contractor shall
direct specific attention in writing to revisions other than
the corrections called for by Engineer on previous
submittals.
6.1 S
COlllinuing the \Vork
to
the
disagreements with Owner. No Work shall be delayed or
postponed pending resolution of any disputes or
disagreements, except as permitted by Paragraph 15.04 or
as Owner and Contractor may otherwise agree in writing.
6.19 Contractor's General Warranty Clnd Guarantee
A. Contractor warrants and guarantees to Owner
that all Work will be in accordance with the Contract
Documents and will not be defective. Engineer and its
Related Entities shall be entitled to rely on representation
of Contractor's warranty and guarantee.
B. Contractor's warranty and guarantee
hereunder excludes defects or damage caused by:
1. abuse. modification. or improper maintenance
or operation by persons other than Contractor, Sub-
contractors, Suppliers, or any other individual or entity for
whom Contractor is responsible; or
2. normal wear and tear under normal usage.
C. Contractor's obligation to perform and
complete the Work in accordance with the Contract
Documents shall be absolute. None of the following will
constitute an acceptance of Work that is not in accordance
with the Contract Documents or a release of Contractor's
obligation to perform the Work in accordance with the
Contract Documents:
1. observations by Engineer;
2. recommendation by Engineer or payment by
Owner of any progress or final payment;
3. the issuance of a certificate of Substantial
Completion by Engineer or any payment related thereto
by Owner:
4. use or occupancy of the \Vork or anv part
thereof by Owner:
5. any review and approval of a Shop Dra\ving or
Sample submittal or the issuance of a notice of acceptabil-
ity by Engineer:
6. any inspection. test, or approval by others: or
7. any correction of defecti ve Work by Owner.
6.20
Inde/llIl ificCltion
arbitration or other dispute resolution costs) arising out of
or relating to the performance of the Work. provided that
any such claim. cost. loss, or damage is attributable to
bodily injury. sickness, disease. or death, or to injury to or
destruction of tangible property (other than the Work
itself), including the loss of use resulting therefrom but
only to the extent caused by any negligent act or omission
of Contractor. any Subcontractor, any Supplier, or any
individual or entity directly or indirectly employed by any
of them to perform any of the Work or anyone for whose
acts any of them may be liable.
B. In any and all claims against Owner or
Engineer or any of their respective consultants, agents,
officers, directors, partners. or employees by any employ-
ee (or the survivor or personal representative of such
employee) of Contractor. any Subcontractor, any
Supplier, or any individual or entity directly or indirectly
employed by any of them to perform any of the Work, or
anyone for whose acts any of them may be liable, the
indemnification obligation under Paragraph 6.20.A shall
not be limited in any way by any limitation on the amount
or type of damages, compensation, or benefits payable by
or for Contractor or any such Subcontractor, Supplier, or
other individual or entity under workers' compensation
acts. disability benefit acts. or other employee benefit
acts.
C. The indemnification obligations of Contractor
under Paragraph 6.20.A shall not extend to the liability of
Engineer and Engineer's officers, directors, partners,
employees, agents, consultants and subcontractors arising
out of:
1. the preparation or approval of, or the failure to
prepare or approve, maps, Drawings. opinions, reports.
surveys, Change Orders, designs, or Specifications; or
2. giving directions or instructions, or failing to
gI\!e them. if that is the primary cause of the injury or
damage.
6.21
Delegation ot'Professional Design Services
A. Contractor will not be required to provide
professional design services unless such services are
specifically required by the Contract Documents for a
portion of the \Vork or unless such services are required
to carry out Contractor's responsibilities for construction
means, methods, techniques, sequences and procedures.
Contractor shall not be required to provide professional
services in violation of applicable law.
shall appear on all drawings. calculations, specifications.
certifications, Shop Drawings and other submittals
prepared by such professional. Shop Drawings and other
submittals related to the Work designed or certified by
such professional, if prepared by others, shall bear such
professional's written approval when submitted to
Engi neer.
C. Owner and Engineer shall be entitled to rely
upon the adequacy. accuracy and completeness of the
services, certi tications or approvals performed by such
design professionals, provided Owner and Engineer have
specitied to Contractor all performance and design criteria
that such services must satisfy.
D. Pursuant to this Paragraph 6.21. Engineer's
review and approval of design calculations and design
drawings will be only for the limited purpose of checking
for conformance with performance and design criteria
given and the design concept expressed in the Contract
Documents. Engineer's review and approval of Shop
Dra wings and other submittals (except design calculations
and design drawings) will be only for the purpose stated
in Paragraph 6.17 .D.I.
E. Contractor shall not be responsible for the
adequacy of the performance or design criteria required
by the Contract Documents.
ARTICLE 7 - OTHER WORK AT THE SITE
7.01 Relmed \Vork a[ Site
A. Owner may perform other work related to the
Project at the Site with Owner's employees, or via other
direct contracts therefor. or have other \vork performed by
utility owners. If such other work is not noted in the Con-
tract Documents. then:
1. written notice thereof will be given to
Contractor prior to starting any such other work: and
2. if Owner and Contractor are unable to agree
on entitlement to or on the amount or extent. if any. of
any adjustment in the Contract Price or Contract Times
that should be allowed as a result of such other work, a
Claim may be made therefor as provided in Paragraph
10.05.
B. Contractor shall afford each other contractor
who is a party to such a direct contract. each utility owner
B. If professional design services or and Owner. if Owner is performing other work with
certifications by a design professional related to systems, Owner's employees, proper and safe access to the Site, a
materials or equipment are specifically required of reasonable opportunity for the introduction and storage of
Contractor by the Contract Documents, Owner and materials and equipment and the execution of such other
Engineer will specify all performance and design criteria work. and shall properly coordinate the Work with theirs.
that such services must satisfy. Contractor shall cause Contractor shall do all cutting, fitting, and patching of the
such services or certifications to be provided by a Work that may be required to properly connect or
properly licensed professional. whose signature and seal otherwise make its several parts come together and
EJCDC C-700 Standard Gencral Conditions 01' the Construction Contract.
Copyright @ 2002 National Society of Professional Engineers for E.JCDC. All rights reserved.
00700 - 25
properly integrate with such other work. Contractor shall
not endanger any work of others by cutting, excavating,
or otherwise altering their work and will only cut or alter
their work with the written consent of Engineer and the
others whose work will be affected. The duties and
responsibilities of Contractor under this Paragraph are for
the benefit of such utility owners and other contractors to
the extent that there are comparable provisions for the
benefit of Contractor in said direct contracts between
Owner and such utility owners and other contractors.
C. If the proper execution or results of any part
of Contractor' s Work depends upon work performed by
others under this Article 7, Contractor shall inspect such
other work and promptly report to Engineer in writing any
delays. defects, or deficiencies in such other work that
render it unavailable or unsuitable for the proper
execution and results of Contractor's Work. Contractor's
failure to so report will constitute an acceptance of such
other work as fit and proper for integration with
Contractor's Work except for latent defects and
deficiencies in such other work.
7.02 Coordination
A. If Owner intends to contract with others for
the performance of other work on the Project at the Site,
the following will be set forth in Supplementary Condi-
tions:
1. the individual or entity who \vill have
authority and responsibility for coordination of the
activities among the various contractors will be identified;
2. the specific matters to be covered by such
authority and responsibility will be itemized; and
3. the extent of such authority and responsibiIi-
ties will be provided.
B. Unless otherwise provided III
Supplementary Conditions, Owner shall have
authority and responsibility for such coordination.
the
sole
7.03
Legal Relationships
A. Paragraphs 7.0 l.A and 7.02 are not appIicable
for utilities not under the control of Owner.
B. Each other direct contract of Owner under
Paragraph 7.0 J A shall provide that the other contractor is
liable to Owner and Contractor for the reasonable direct
delay and disruption costs incurred by Contractor as a
result of the other contractor's actions or inactions.
C. Contractor shall be liable to Owner and any
other contractor for the reasonable direct delay and
disruption costs incurred by such other contractor as a
result of Contractor's action or inactions.
ARTICLE 8 - OWNER'S RESPONSIB lLlTIES
8.01 COl/1mllnications lO ContraClor
A. Except as otherwise provided in these General
Conditions. Owner shall issue all communications to
Contractor through Engineer.
8.02 Replacement of Eng in ee r
A. In case of termination of the employment of
Engineer, Owner shall appoint an engineer to whom
Contractor makes no reasonable objection, whose status
under the Contract Documents shall be that of the former
Engineer.
8.03 Fllrnish Data
A. Owner shall promptly furnish the data
required of Owner under the Contract Documents.
8.04 Pay When Dlle
A. Owner shall make payments to Contractor
when they are due as provided in Paragraphs 14.02.C and
I4.07.C.
8.05 Lands and Easelllellls; Reports and Tests
A. Owner's duties in respect of providing lands
and easements and providing engineering surveys to
establish reference points are set forth in Paragraphs 4.0 I
and 4.05. Paragraph 4.02 refers to Owner's identifying
and making available to Contractor copies of reports of
explorations and tests of subsurface conditions and
drawings of physical conditions in or relating to existing
surface or subsurface structures at or contiguous to the
Site that have been utilized by Engineer in preparing the
Contract Documents.
8.06
Insll rance
A. Owner's responsibilities, if any, in respect to
purchasing and maintaining liability and property insur-
ance are set forth in Article 5.
8.07
Change Orders
A. Owner is obligated to execute Change Orders
as indicated in Paragraph 10.03.
8.08 Inspeclions, Tens. and Approvals
A. Owner's responsibility in respect to certain
inspections, tests, and approvals is set forth in Paragraph
13.03.B.
EJCDC C-700 Standard General Conditions of' the Construction Contract.
Copyright @ 2002 National Society of' Professional Engineers for E.JCDC. All rights reserved.
00700 - 26
8.09
Limitations on Owner's Responsibilities
A. The Owner shall not supervise. direct, or have
control or authority over, nor be responsible for.
Contractor's means, methods, techniques, sequences, or
procedures of construction, or the safety precautions and
programs incident thereto, or for any failure of Contractor
to comply with Laws and Regulations applicable to the
performance of the Work. Owner will not be responsible
for Contractor's failure to perform the Work in
accordance with the Contract Documents.
8.10 Undisclosed
Condition
Hazardous
Environmental
A. Owner's responsibility in respect to an undis-
closed Hazardous Environmental Condition is set forth in
Paragraph 4.06.
8.11 Evidence of Financial Arrangements
A. If and to the extent Owner has agreed to
furnish Contractor reasonable evidence that financial
arrangements have been made to satisfy Owner's
obligations under the Contract Documents, Owner's
responsibility in respect thereof will be as set forth in the
Supplementary Conditions.
ARTICLE 9 ENGINEER'S STATUS DURING
CONSTRUCTION
9.01
Owner's Represelllative
A. Engineer will be Owner's representative
during the construction period. The duties and responsi-
bilities and the limitations of authority of Engineer as
Owner's representative during construction are set forth
in the Contract Documents and will not be changed
without written consent of Owner and Engineer.
9.02
Visits to Site
A. Engineer will make visits to the Site at inter-
vals appropriate to the various stages of construction as
Engineer deems necessary in order to observe as an
experienced and qualified design professional the
progress that has been made and the quality of the various
aspects of Contractor's executed \York. Based on
information obtained during such visits and observations,
Engineer. for the benefit of Owner. \vill determine, in
general, if the Work is proceeding in accordance with the
Contract Documents. Engineer will not be required to
make exhausti ve or continuous inspections on the Site to
check the quality or quantity of the Work. Engineer's
efforts will be directed toward providing for Owner a
greater degree of confidence that the completed Work will
conform generally to the Contract Documents. On the
basis of such visits and observations, Engineer will keep
Owner informed of the progress of the \York and will
endeavor to guard Owner against defective \York.
B. Engineer's visits and observations are subject
to all the limitations on Engineer's authority and
responsibility set forth in Paragraph 9.09. Particularly, but
without limitation, during or as a result of Engineer's
visits or observations of Contractor's Work Engineer will
not supervise, direct, control, or have authority over or be
responsible for Contractor's means, methods, techniques,
sequences, or procedures of construction, or the safety
precautions and programs incident thereto, or for any
failure of Contractor to comply with Laws and
Regulations applicable to the performance of the Work.
9.03 Project Representative
A. If Owner and Engineer agree. Engineer will
furnish a Resident Project Representative to assist
Engineer in providing more extensive observation of the
Work. The authority and responsibilities of any such
Resident Project Representative and assistants will be as
provided in the Supplementary Conditions. and
limitations on the responsibilities thereof will be as
provided in Paragraph 9.09. If Owner designates another
representati ve or agent to represent Owner at the Site who
is not Engineer's consultant, agent or employee, the
responsibilities and authority and limitations thereon of
such other indi vidual or entity will be as provided in the
Supplementary Conditions.
9.04 AllIlzorized Variations in Work
A. Engineer may authorize minor variations in
the Work from the requirements of the Contract
Documents which do not involve an adjustment in the
Contract Price or the Contract Times and are compatible
with the design concept of the completed Project as a
functioning whole as indicated by the Contract Docu-
ments. These may be accomplished by a Field Order and
wil I be binding on Owner and also on Contractor. who
shall perform the Work involved promptly. If Owner or
Contractor believes that a Field Order justifies an
adjustment in the Contract Price or Contract Times, or
both, and the parties are unable to agree on entitlement to
or on the amount or extent, if any, of any such adjustment
, a Claim may be made therefor as provided in Paragraph
10.05.
9.05
Rejecting DefeCTive \Vork
A. Engineer will have authority to reject Work
which Engineer believes to be defective, or that Engineer
believes will not produce a completed Project that
conforms to the Contract Documents or that will prejudice
the integrity of the design concept of the completed
Project as a functioning whole as indicated by the
Contract Documents. Engineer will also have authority to
require special inspection or testing of the Work as
provided in Paragraph 13.04, whether or not the Work is
fabricated, installed. or completed.
E.JCDC C-700 Standard General Conditions of the Construction Contract.
Copyright @ 2002 National Society of Professional Engineers for E.JCDC. All rights reserved.
00700 - 27
9.06
Shop Drawings, Change Orders and Payments
A. In connection with Engineer's authority. and
limitations thereof. as to Shop Drawings and Samples, see
Paragraph 6.17.
B. In connection with Engineer's authority. and
limitations thereof. as to design calculations and design
drawings submitted in response to a delegation of
professional design services, if any. see Paragraph 6.21.
C. In connection with Engineer's authority as to
Change Orders. see Articles 10, 1 Land 12.
D. In connection with Engineer's authority as to
Applications for Payment, see Article 14.
9.07 Delernzinationsjor Unit Price IYork
A. Engineer will determine the actual quantities
and classifications of Unit Price Work performed by
Contractor. Engineer will review with Contractor the
Engineer's preliminary determinations on such matters
before rendering a written decision thereon (by
recommendation of an Application for Payment or
otherwise). Engineer's written decision thereon will be
final and binding (except as modified by Engineer to
retlect changed factual conditions or more accurate data)
upon Owner and Contractor, subject to the provisions of
Paragraph 10.05.
9.08 Decisions on Requiremellls or Contract
Documents and Acceptability of Work
A. Engineer will be the initial interpreter of the
requirements of the Contract Documents and judge of the
acceptability of the Work thereunder. All matters in
question and other matters between Owner and Contractor
arising prior to the date final payment is due relating to
the acceptability of the Work. and the interpretation of the
requirements of the Contract Documents pertaining to the
performance of the Work, will be referred initially to
Engineer in writing within 30 days of the event giving rise
to the question
B. Engineer will, with reasonable promptness.
render a written decision on the issue referred. If Owner
or Contractor believe that any such decision entitles them
to an adjustment in the Contract Price or Contract Times
or both, a Claim may be made under Paragraph 10.05.
The date of Engineer's decision shall be the date of the
event gi ving rise to the issues referenced for tbe purposes
ofParagrapb 10.05.B.
C. Engineer's written decision on the issue
referred will be final and binding on Owner and
Contractor, subject to the provisions of Paragraph 10.05.
partiality to Owner or Contractor and will not be liable in
connection with any interpretation or decision rendered in
good faith in sucb capacity.
9.09 Limitarions on Engineer's Alltizoritv and
RespOlzsibilities
A. Neither Engineer's authority or responsibility
under this Article 9 or under any other provision of the
Contract Documents nor any decision made by Engineer
in good faith either to exercise or not exercise such
authority or responsibility or the undertaking, exercise, or
performance of any authority or responsibility by
Engineer shall create, impose, or give rise to any duty in
contract, tort or otherwise owed by Engineer to
Contractor, any Subcontractor, any Supplier, any other
individual or entity, or to any surety for or employee or
agent of any of them.
B. Engineer will not supervise, direct control, or
have authority over or be responsible for Contractor's
means, methods, techniques, sequences, or procedures of
construction, or the safety precautions and programs
incident thereto. or for any failure of Contractor to
comply with Laws and Regulations applicable to the
performance 0 l' the Work. Engi neeI' wi II not be respon-
sible for Contractor's failure to perform the Work in
accordance with the Contract Documents.
C. Engineer will not be responsible for the acts
or omissions of Contractor or of any Subcontractor. any
Supplier, or of any other individual or entity performing
any of tbe Work.
D. Engineer's review of the final Application for
Payment and accompanying documentation and all
maintenance and operating instructions. schedules.
guarantees. bonds. certificates of inspection, tests and
approvals, and other documentation required to be
delivered by Paragraph 14.07.A will only be to determine
generally that their content complies with the require-
ments of. and in the case of certificates of inspections,
tests, and approvals that the results certified indicate
compliance with the Contract Documents.
E. The limitations upon authority and responsI-
bility set forth in this Paragraph 9.09 shall also apply to,
the Resident Project Representati ve, i l' any, and assistants,
if any.
ARTICLE 10 CHANGES IN THE \VORK; CLAIMS
10.01 AlIIllOri;:.ed Changes in the Work
A. Without invalidating the Contract and without
notice to any surety. Owner may. at any time or from time
to time. order additions. deletions. or revisions in the
D. When functioning as interpreter and judge Work by a Change Order. or a Work Change Directive.
under this Paragraph 9.08, Engineer will not show Upon receipt of any such document Contractor shall
EJCDC C-700 Standard General Conditions or the Construction Contract.
Copyright @ 2002 National Society of Professional Engineers for E.JCDC. All rights reserved.
00700 -
promptly proceed with the Work involved which will be
performed under the applicable conditions of the Contract
Documents (except as otherwise specifically provided).
B. If Owncr and Contractor are unable to agree
on entitlement to. or on the amount or extent if any, of an
adjustment in the Contract Price or Contract Times, or
both. that should be allowed as a result of a Work Change
Directivc, a Claim may be made therefor as provided ll1
Paragraph 10.05.
10.02 Unauthoriz.ed Changes in the Work
A.Contractor shall not be entitled to an increase
in the Contract Price or an extension of the Contract
Times with respect to any work performed that is not
required by the Contract Documents as amended,
modified, or supplemented as provided in Paragraph 3.04,
except in the case of an emergency as provided III
Paragraph 6.16 or in the case of uncovering Work as
provided in Paragraph 13.04.B.
10.03 ExecwiolZ of Change Orders
A. Owner and Contractor shall execute appropri-
ate Change Orders recommended by Engineer covering:
1. changes in the Work which are: (i) ordered by
Owner pursuant to Paragraph 10.0 l.A, (ii) required
because of acceptance of defective Work under Paragraph
13.08.A or Owner's correction of defective Work under
Paragraph 13.09, or (iii) agreed to by the parties:
2. changes in the Contract Price or Contract
Times which are agreed to by the parties, including any
undisputed sum or amount of time for Work actually
performed in accordance \vith a Work Change Directive;
and
3. changes in the Contract Price or Contract
Times which embody the substance of any written
decision rendered by Engineer pursuant to Paragraph
10.05; provided that, in lieu of executing any such
Change Order. an appeal may be taken from any such
decision in accordance with the provisions of the Contract
Documents and applicable Laws and Regulations, but
during any such appeal, Contractor shall carryon the
Work and adhere to the Progress Schedule as provided in
Paragraph 6.18.A.
10.04 Notification to Surery
A. If notice of any change affecting the general
scope of the Work or the provisions of the Contract
Documents (including, but not limited to, Contract Price
or Contract Times) is required by the provisions of any
bond to be given to a surety, the giving of any such notice
will be Contractor's responsibility. The amount of each
applicable bond will be adjusted to ref1ect the effect of
any such change.
10.05 Claims
A. Engineer's Decision Required: All Claims,
except those waived pursuant to Paragraph 14.09, shall be
referred to the Engineer for decision. A decision by
Engineer shall be required as a condition precedent to any
exercise by Owner or Contractor of any rights or remedies
either may otherwise have under the Contract Documents
or by Laws and Regulations in respect of such Claims.
B. Notice: Written notice stating the general
nature of each Claim. shall be delivered by the claimant to
Engineer and the other party to the Contract promptly (but
in no event later than 30 days) after the start of the event
giving rise thereto. The responsibility to substantiate a
Claim shall rest with the party making the Claim. Notice
of the amount or extent of the Claim, with supporting data
shall be delivered to the Engineer and the other party to
the Contract within 60 days after the start of such event
(unless EnS!ineer allows additional time for claimant to
submit additional or more accurate data in support of such
Claim). A Claim for an adjustment in Contract Price shall
be prepared in accordance with the provisions of
Paragraph 12.01.B. A Claim for an adjustment in Contract
Time shall be prepared in accordance with the provisions
of Paragraph 12.02.B. Each Claim shall be accompanied
by claimant's written statement that the adjustment
claimed is the entire adjustment to which the claimant
believes it is entitled as a result of said event. The
opposing party shall submit any response to Engineer and
the claimant within 30 days after receipt of the claimant's
last submittal (unless Engineer allows additional time).
C. Engineer's Action: Engineer will review each
Claim and. within 30 days after receipt of the last
submittal of the claimant or the last submittal of the
opposing party. if any. take one of the following actions
in writing:
1. deny the Claim in whole or in part
2. approve the Claim, or
3. notify the parties that the Engineer is unable to
resolve the Claim if. in the Engineer's sole discretion, it
would be inappropriate for the Engineer to do so. For
purposes of further resolution of the Claim. such notice
shall be deemed a denial.
D. In the event that Engineer does not take action
on a Claim within said 30 days. the Claim shall be
deemed denied.
E. Engineer's written action under Paragraph
1O.05.C or denial pursuant to Paragraphs 10.05.C.3 or
1O.05.D will be final and binding upon Owner and
Contractor. unless Owner or Contractor invoke the
dispute resolution procedure set forth in Article 16 within
30 days of such action or denial.
E.JCDC C-700 Standard General Conditions of' the Construction Contract.
Copyright @ 2002 National Society of Professional Engineers for E.JCDC. All rights rescrvcd.
F. No Claim for an adjustment in Contract Price
or Contract Times will be valid if not submitted in
accordance with this Paragraph 10.05.
ARTICLE 11 COST OF THE
ALLOWANCES; UNIT PRICE WORK
WORK:
11.01 COS{ of the Work
A. Costs Included: The term Cost of the Work
means the sum of all costs, except those excluded in
Paragraph 11.0 1.B, necessarily incurred and paid by
Contractor in the proper performance of the Work. When
the value of any Work covered by a Change Order or
when a Claim for an adjustment in Contract Price is
determined on the basis of Cost of the Work. the costs to
be reimbursed to Contractor will be only those additional
or incremental costs required because of the change in the
Work or because of the event giving rise to the Claim.
Except as otherwise may be agreed to in writing by
Owner, such costs shall be in amounts no higher than
those prevailing in the locality of the Project, shall include
only the following items, and shall not include any of the
costs itemized in Paragraph 11.0 I.B.
1. Payroll costs for employees in the direct
employ of Contractor in the performance of the Work
under schedules of job classifications agreed upon by
Owner and Contractor. Such employees shall include,
without limitation, superintendents, foremen, and other
personnel employed full time at the Site. Payroll costs for
employees not employed full time on the Work shall be
apportioned on the basis of their time spent on the Work.
Payroll costs shall include, but not be limited to. salaries
and wages plus the cost of fringe benefits, which shall
include social security contributions, unemployment,
excise, and payroll taxes, workers' compensation, health
and retirement benefits, bonuses, sick leave, vacation and
holiday pay applicable thereto. The expenses of
performing Work outside of regular working hours. on
Saturday, Sunday, or legal holidays, shall be included in
the above to the extent authorized by Owner.
2. Cost of all materials and equipment furnished
and incorporated in the Work, including costs of
transportation and storage thereof, and Suppliers' field
services required in connection therewith. All cash
discounts shall accrue to Contractor unless OViner
deposits funds with Contractor with which to make pay-
ments, in which case the cash discounts shall accrue to
Owner. All trade discounts. rebates and refunds and
returns from sale of surplus materials and equipment shall
accrue to Owner, and Contractor shall make provisions so
that they may be obtained.
Contractor and shall deliver such bids to Owner. who will
then determine. with the advice of Engineer. which bids.
if any, will be acceptable. If any subcontract provides that
the Subcontractor is to be paid on the basis of Cost of the
Work plus a fee, the Subcontractor's Cost of the Work
and fee shall be determined in the same manner as
Contractor's Cost of the Work and fee as provided in this
Paragraph 11.0 I.
4. Costs of special consultants (including but not
limited to Engineers. architects, testing laboratories,
surveyors, attorney's, and accountants) employed for
services specifically related to the Work,
5. Supplemental costs including the f()llowing:
a. The proportion of necessary transportation.
travel, and subsistence expenses of Contractor's
employees incurred in discharge of duties
connected with the Work.
b. Cost. including transportation and mainte-
nance, of all materials, supplies, equipment,
machinery. appliances, office. and temporary
facilities at the Site, and hand tools not owned by
the workers. which are consumed in the perfor-
mance of the Work, and cost. less market value.
of such items used but not consumed which
remain the property of Contractor.
c. Rentals of all construction equipment and
machinery, and the parts thereof whether rented
from Contractor or others in accordance with
rental agreements approved by Owner with the
advice of Engineer. and the costs of
transportation, loading, unloading, assembly,
dismantling, and removal thereof. All such costs
shall be in accordance with the terms of said
rental agreements. The rental of any such equip-
ment. machinery, or parts shall cease when the
use thereof is no longer necessary for the Work.
d. Sales, consumer. use, and other similar taxes
related to the Work, and for which Contractor is
liable, imposed by La ws and Regulations.
e. Deposits lost for causes other than negligence
of Contractor, any Subcontractor. or anyone
directly or indirectly employed by any of them or
for whose acts any of them may be liable. and
royalty payments and fees for permits and
licenses.
f. Losses and damages (and related expenses)
caused by damage to the Work, not compensated
by insurance or otherwise. sustained by
Contractor in connection with the performance
3. Payments made by Contractor to of the Work (except losses and damages within
Subcontractors for Work performed by Subcontractors. If the deductible amounts of property insurance
required by Owner. Contractor shall obtain competitive established tn accordance with Paragraph
bids from subcontractors acceptable to Owner and 5.06.D), provided such losses and damages have
E.JCDC C-700 Standard General Conditions of the ConstrnctioIl Contract.
Copyright @ 2002 National Society of Professional Engineers for E.JCDC. All rights reserved.
00700 - 30
resulted from causes other than the negligence of
Contractor. an\' Subcontractor. or anyone
directly or indirectly employed by any of them or
for whose acts any of them may be liable. Such
losses shall include settlements made with the
written consent and approval of Owner. No such
losses, damages, and expenses shall be included
in the Cost of the Work for the purpose of
determining Contractor's fee.
g. The cost of utilities. fuel. and sanitary
facilities at the Site.
h. Minor expenses such as telegrams. long
distance telephone calls, telephone service at the
Site, expresses, and similar petty cash items in
connection with the Work.
i. The costs of premiums for all bonds and
insurance Contractor is required by the Contract
Documents to purchase and maintain.
B. Costs Excluded: The term Cost of the Work
shall not include any of the following items:
1. Payroll costs and other compensation of
Contractor's officers. executives, principals (of
partnerships and sole proprietorships). general managers,
safety managers, engineers. architects, estimators, attor-
neys, auditors, accountants, purchasing and contracting
agents. expediters, timekeepers, clerks, and other
personnel employed by Contractor, whether at the Site or
in Contractor's principal or branch office for general
administration of the Work and not specifically included
in the agreed upon schedule of job classifications referred
to in Paragraph 11.01.A.l or specifically covered by
Paragraph l1.01.A.4, all of which are to be considered
administrati ve costs covered by the Contractor's fee.
2. Expenses of Contractor's principal and branch
offices other than Contractor's office at the Site.
3. Any part of Contractor's capital expenses,
including interest on Contractor's capital employed for
the Work and charges against Contractor for delinquent
payments.
4. Costs due to the negligence of Contractor. any
Subcontractor. or anyone directly or indirectly employed
by any of them or for whose acts any of them may be
liable. including but not limited to. the correction of
defective Work, disposal of materials or equipment
wrongly supplied. and making good anv damage to
property.
5. Other overhead or general expense costs of
anv kind and the costs of any item not specifically and
expressly included in Paragraphs 11.01.A andl1.0l.B.
C. Contractor's Fee: When all the Work is
performed on the basis of cost-plus, Contractor's fee shall
be determined as set forth in the Agreement. When the
value of any Work covered by a Change Order or when a
Claim for an adjustment in Contract Price is determined
on the basis of Cost of the Work. Contractor's fee shall be
determined as set forth in Paragraph 12.01.C.
D. Documentation: Whenever the Cost of the
\V ork for any purpose is to be determined pursuant to
Paragraphs 11.0 l.A and 11.0 1.B, Contractor will establish
and maintain records thereof in accordance with generally
accepted accounting practices and submit in a form
acceptable to Engineer an itemized cost breakdown
together with supporting data.
11.02 AllolVances
A. It is understood that Contractor has included
in the Contract Price all allowances so named in the
Contract Documents and shall cause the \Y ork so covered
to be performed for such sums and by such persons or
entities as may be acceptable to Owner and Engineer.
B. Cash AllolVances
1. Contractor agrees that:
a. the cash allowances include the cost to
Contractor (less any applicable trade discounts)
of materials and equipment required by the
allowances to be delivered at the Site. and all
applicable taxes; and
b. Contractor's costs for unloading and handling
on the Site. labor. installation. overhead, profit,
and other expenses contemplated for the cash
allowances have been included in the Contract
Price and not in the allowances. and no demand
for additional payment on account of any of the
foregoing will be valid.
C. Contingency Allowance
1. Contractor agrees
allowance. if any. is for the sole
unanticipated costs.
that a contingency
use of Owner to cover
D. Prior to final payment an appropriate Change
Order will be issued as recommended by Engineer to
retlect actual amounts due Contractor on account of Work
covered by allowances. and the Contract Price shall be
correspondingly adjusted.
11.03 Unit Price Work
A. Where the Contract Documents provide that
all or part of the Work is to be Unit Price Work. initially
the Contract Price will be deemed to include for all Unit
Price \York an amount equal to the sum of the unit price
for each separately identified item of Unit Price Work
times the estimated quantity of each item as indicated in
the Agreement.
EJCDC C-700 Standard General Conditions of the Construction Contract.
Copyright @ 2002 National Society of Professional Engineers for EJCDC. All rights reserved.
00700 - 31
B. The estimated quantities of items of Unit
Price Work are not guaranteed and are solely for the
purpose of comparison of Bids and determining an initial
Contract Price. Determinations of the actual quantities
and classifications of Unit Price Work performed by
Contractor will be made by Engineer subject to the
provisions of Paragraph 9.07.
C. Each unit price will be deemed to include an
amount considered by Contractor to be adequate to cover
Contractor's overhead and profit for each separately
identified item.
D. Owner or Contractor may make a Claim for
an adjustment in the Contract Price in accordance with
Paragraph 10.05 if:
1. the quantity of any item of Unit Price Work
performed by Contractor differs materially and signifi-
cantly from the estimated quantity of such item indicated
in the Agreement; and
2. there is no corresponding adj ustment with
respect any other item of Work; and
3. Contractor believes that Contractor is entitled
to an increase in Contract Price as a result of having
incurred additional expense or Owner believes that Owner
is entitled to a decrease in Contract Price and the parties
are unable to agree as to the amount of any such increase
or decrease.
ARTICLE 12 - CHANGE OF CONTRACT PRICE:
CHANGE OF CONTRACT TIMES
12.01 Change of COil tract Price
A The Contract Price may only be changed by a
Change Order. Any Claim for an adjustment in the
Contract Price shall be based on written notice submitted
by the party making the Claim to the Engineer and the
other party to the Contract in accordance with the
provisions of Paragraph 10.05.
B. The value of any Work covered by a Change
Order or of any Claim for an adj ustment in the Contract
Price will be determined as follows:
1. where the Work involved is covered by unit
prices contained in the Contract Documents, by applica-
tion of such unit prices to the quantities of the items
involved (subject to the provisions of Paragraph 11.03):
or
2. where the Work involved is not covered by
unit prices contained in the Contract Documents. by a
mutually agreed lump sum (which may include an
allowance for overhead and profit not necessarily In
accordance with Paragraph 12.01.C.2); or
3. where the Work involved is not covered by
unit prices contained in the Contract Documents and
agreement to a lump sum is not reached under Paragraph
12.01.B.2, on the basis of the Cost of the Work
(determined as provided in Paragraph 11.01) plus a
Contractor's fee for overhead and profit (determined as
provided in Paragraph 12.01.C).
C. CO/llractor's Fee: The Contractor's fee for
overhead and profit shall be determined as follows:
1. a mutually acceptable fixed fee; or
2. if a fixed fee is not agreed upon, then a fee
based on the following percentages of the various portions
of the Cost of the Work:
a. for costs incurred under Paragraphs 1 LOLA. 1
and 11.01.A.2. the Contractor's fee shall be 15
percent;
b. for costs incurred under Paragraph 11.01.A.3.
the Contractor's fee shall be fi ve percent;
c. where one or more tiers of subcontracts are on
the basis of Cost of the Work plus a fee and no
lixed fee is agreed upon, the intent of Paragraph
12.01.C.2.a is that the Subcontractor who
actually performs tbe Work, at whatever tiel', will
be paid a fee of 15 percent of tbe costs incurred
by such Subcontractor under Paragraphs
1 LOLA. 1 and 11.0 L'\.2 and that any higher tier
Subcontractor and Contractor will each be paid a
fee of live percent of the amount paid to the next
lower tier Subcontractor:
d. no fee shall be payable on the basis of costs
itemized under Paragraphs 11.01.A4. 11.0 1.A.5.
and 11.0 1.B:
e. the amount of credit to be allowed by
Contractor to Owner for any change which
results in a net decrease in cost will be the
amount of the actual net decrease in cost plus a
deduction in Contractor's fee by an amount equal
to Ii ve percent of such net decrease; and
f. when both additions and credits are involved
1I1 anyone change. the adjustment in
Contractor's fee shall be computed on the basis
of the net change in accordance with Paragraphs
12.01.C.2.a through 12.01.C.2.e. inclusive.
12.02
Change c~r ContraC[ Times
A. The Contract Times may only be changed by
a Change Order. Any Claim for an adjustment in the
Contract Times shall be based on written notice submitted
E.JCDC C-700 Standard General Conditions of the Constrnction Contract.
Copyright @ 2002 National Society of Prol'essional Engineers for E.JCDC. All rights reserved.
00700 - 32
by the party making the Claim to the Engineer and the
other party to the Contract in accordance with the
provisions of Paragraph 10.05.
B. Any adjustment of the Contract Times
covered by a Change Order or any Claim for an
adjustment in the Contract Times will be determined II1
accordance with the provisions of this Article 12.
12.03 Delays
A. Where Contractor is prevented from
completing any part of the Work within the Contract
Times due to delay beyond the control of Contractor. the
Contract Times will be extended in an amount equal to
the time lost due to such delay if a Claim is made therefor
as provided in Paragraph 12.02.A. Delays beyond the
control of Contractor shall include, but not be limited to,
acts or neglect by Owner. acts or neglect of utility owners
or other contractors performing other work as contemplat-
ed by Article 7. fires, floods, epidemics, abnormal
weather conditions. or acts of God.
B. If Owner, Engineer. or other contractors or
utility owners performing other work for Owner as
contemplated by Article 7, or anyone for whom Owner is
responsible, delays, disrupts, or interferes with the
performance or progress of the Work, then Contractor
shall be entitled to an equitable adjustment in the Contract
Price or the Contract Times . or both. Contractor's
entitlement to an adjustment of the Contract Times is
conditioned on such adjustment being essential to
Contractor's ability to complete the Work within the
Contract Times.
C If Contractor is delayed in the performance or
progress of the Work by fire, flood, epidemic, abnormal
weather conditions. acts of God. acts or failures to act of
utility O\vners not under the control of Owner, or other
causes not the fault of and beyond control of Owner and
Contractor. then Contractor shall be entitled to an
equitable adjustment in Contract Times. if such
adjustment is essential to Contractor's ability to complete
the Work within the Contract Times. Such an adjustment
shall be Contractor's sole and exclusive remedy for the
delays described in this Paragraph 12.03.C.
D. Owner. Engineer and the Related Entities of
each of them shall not be liable to Contractor for any
claims. costs, losses, or damages (including but not
limited to all fees and charges of Engineers. architects,
attorneys, and other professionals and all court or
arbitration or other dispute resolution costs) sustained by
Contractor on or in connection with any other project or
anticipated project.
ARTICLE 13 TESTS AND INSPECTIONS:
CORRECTION. REMOVAL OR ACCEPTANCE OF
DEFECTIVE WORK
13.01 Notice(~rDcfects
A. Prompt notice of all defecti ve Work of which
Owner or Engineer has actual knowledge will be given to
Contractor. All defective Work may be rejected,
corrected, or accepted as provided in this Article 13.
13.02 Access to Work
A. Owner. Engineer, their consultants and other
representati ves and personnel of Ovmer. independent
testing laboratories, and governmental agencies with
jurisdictional interests will have access to the Site and the
Work at reasonable times for their observation.
inspecting. and testing. Contractor shall provide them
proper and safe conditions for such access and advise
them of Contractor's Site safety procedures and programs
so that they may comply therewith as applicable.
13.03 Tests and InspeCTions
A. Contractor shall give Engineer timely notice
01 readiness of the Work for all required inspections,
tests, or approvals and shall cooperate with inspection and
testing personnel to facilitate required inspections or tests.
B. Owner shall employ and pay for the services
of an independent testing laboratory to perform all
inspections, tests, or approvals required by the Contract
Documents except:
1. for inspections, tests, or approvals covered by
Paragraphs I3.03.C and 13.03.D below:
2. that costs incurred in connection with tests or
inspections conducted pursuant to Paragraph 13.04.B
shall be paid as provided in said Paragraph 13.cl4.C: and
3. as otherwise specifically provided in the Con-
tract Documents.
C. If Laws or Regulations of any public body
having jurisdiction require any Work (or part thereof)
specifically to be inspected. tested. or approved by an
employee or other representative of such public body,
Contractor shall assume full responsibility for arranging
and obtaining such inspections, tests. or approvals, pay all
costs in connection therewith, and furnish Engineer the
required certificates of inspection or approval.
E. Contractor shall not be entitled to an
adjustment in Contract Price or Contract Times for delays D. Contractor shall be responsible for arrangmg
within the control of Contractor. Delays attributable to and obtaining and shall pay all costs in connection with
and within the control of a Subcontractor or Supplier shall any inspections, tests, or approvals required for Owner's
be deemed to be delays within the control of Contractor. and Engineer's acceptance of materials or equipment to
EJCDC C-7()O Standard General Conditions of the Construction Contract.
Copyright @ 2002 National Society of Professional Engineers for E.JCDC. All rights reserved.
00700 - 33
be incorporated in the Work; or acceptance of materials,
mix designs, or equipment submitted for approval prior to
Contractor's purchase thereof for incorporation in the
Work. Such inspections, tests, or approvals shall be
performed by organizations acceptable to Owner and
Engineer.
E. If any Work (or the work of others) that is to
be inspected, tested. or approved is covered by Contractor
without written concurrence of Engineer, it must. if
requested by Engineer, be uncovered for observation.
F. Uncovering Work as provided in Paragraph
13.03.E shall be at Contractor's expense unless
Contractor has given Engineer timely notice of
Contractor's intention to cover the same and Engineer has
not acted with reasonable promptness in response to such
notice.
13.04
Uncovering \Vork
A. If any Work is covered contrary to the written
request of Engineer, it must, if requested by Engineer, be
uncovered for Engineer's observation and replaced at
Contractor's expense.
B. If Engineer considers it necessary or advisable
that covered Work be observed by Engineer or inspected
or tested by others, Contractor, at Engineer's request,
shall uncover, expose, or otherwise make available for
observation, inspection, or testing as Engineer may
require, that portion of the Work in question, furnishing
all necessary labor, material, and equipment.
C. If it is found that the uncovered Work is
defective, Contractor shall pay all claims, costs, losses,
and damages (including but not limited to all fees and
charges of engineers, architects, attorneys. and other
professionals and all court or arbitration or other dispute
resolution costs) arising out of or relating to such
uncovering. exposure, observation. inspection, and
testing, and of satisfactory replacement or reconstruction
(including but not limited to all costs of repair or
replacement of work of others); and Owner shall be
entitled to an appropriate decrease in the Contract Price. If
the parties are unable to agree as to the amount thereof,
Owner may make a Claim therefor as provided in
Paragraph 10.05.
D. If, the uncovered Work is not found to be
defecti ve, Contractor shall be allowed an increase in the
Contract Price or an extension of the Contract Times. or
both, directly attributable to such uncovering, exposure,
observation. inspection, testing. replacement, and
reconstruction. If the parties are unable to agree as to the
amount or extent thereof, Contractor may make a Claim
therefor as provided in Paragraph 10.05.
13.05
OH'ner Ivlay SlOp the Work
A. If the Work is defective. or Contractor fails to
supply sufficient skilled workers or suitable materials or
equipment, or fails to perform the \Vork in such a way
that the completed Work will conform to the Contract
Documents. Owner may order Contractor to stop the
Work, or any portion thereof, until the cause for such
order has been eliminated: however, this right of Owner
to stop the Work shall not give rise to any duty on the part
of Owner to exercise this right for the benefit of
Contractor, any Subcontractor, any Supplier, any other
individual or entity. or any surety for, or employee or
agent of any of them.
13.06 Correction or Removal of Defective Work
A. Promptly after receipt of notice, Contractor
shall correct all defective Work. whether or not
fabricated, installed, or completed, or, if the Work has
been rejected by Engineer, remove it from the Project and
replace it with Work that is not defective. Contractor shall
pay all claims, costs, losses, and damages (including but
not limited to all fees and charges of engineers, architects,
attorneys, and other professionals and all court or
arbitration or other dispute resolution costs) arising out of
or relating to such correction or removal (including but
not limited to all costs of repair or replacement of work of
others).
B. When correcting defective Work under the
terms of this Paragraph 13.06 or Paragraph 13.07,
Contractor shall take no action that would void or
otherwise impair Owner's special warranty and guarantee,
if any, on said Work.
13.07 Correction Period
A. If within one year after the date of Substantial
Completion (or such longer period of time as may be
prescribed by the terms of any applicable special
guarantee required by the Contract Documents) or by any
specific provision of the Contract Documents, any Work
is found to be defecti ve, or if the repair of any damages to
the land or areas made available for Contractor's use by
Owner or permitted by Laws and Regulations as
contemplated in Paragraph 6.Il.A is found to be
defective. Contractor shall promptly without cost to
Owner and In accordance with Owner's written
instructions:
1. repair such defective land or areas: or
2. correct such defective Work: or
3. if the defective Work has been rejected by
Owner. remove it from the Project and replace it with
Work that is not defecti ve. and
4. satisfactorily correct or repair or remove and
replace any damage to other Work. to the work of others
or other land or areas resulting therefrom.
EJCDC C-700 Standard General Conditions of the Construction Contract.
Copyright @ 2002 National Society of Professional Engineers for E.JCDC. All rights reserved.
00700 - 34
B. If Contractor does not promptly comply with
the terms of Owner's written instructions. or in an
emergency where delay would cause serious risk of loss
or damage, Owner may have the defective Work
corrected or repaired or may have the rejected Work re-
moved and replaced. All claims, costs, losses, and
damages (including but not limited to all fees and charges
of engineers, architects, attorneys, and other professionals
and all court or arbitration or other dispute resolution
costs) arising out of or relating to such correction or repair
or such removal and replacement (including but not
limited to all costs of repair or replacement of work of
others) will be paid by Contractor.
C. In special circumstances where a particular
item of equipment is placed in continuous service before
Substantial Completion of all the Work, the correction
period for that item may start to run from an earlier date if
so provided in the Specifications.
D. Where defective Work (and damage to other
Work resulting therefrom) has been corrected or removed
and replaced under this Paragraph 13.07, the correction
period hereunder with respect to such Work will be
extended for an additional period of one year after such
correction or removal and replacement has been
satisfactorily completed.
E. Contractor's obligations under this Paragraph
13.07 are in addition to any other obligation or warranty.
The provisions of this Paragraph 13.07 shall not be
construed as a substitute for or a waiver of the provisions
of any applicable statute of limitation or repose.
13.08 Acceptallce of Defective Work
A. If. instead of requiring correction or removal
and replacement of defective Work, Owner (and, prior to
Engineer's recommendation of final payment Engineer)
prefers to accept it, Owner may do so. Contractor shall
pay all claims. costs, losses, and damages (including but
not limited to all fees and charges of engineers, architects,
attorneys, and other professionals and all court or
arbitration or other dispute resolution costs) attributable to
Owner's evaluation of and determination to accept such
defective Work (such costs to be approved by Engineer as
to reasonableness) and the diminished value of the Work
to the extent not otherwise paid by Contractor pursuant to
this sentence. If any such acceptance occurs prior to
Engineer's recommendation of final payment a Change
Order wi Il be issued incorporating the necessary revisions
in the Contract Documents with respect to the Work. and
Owner shall be entitled to an appropriate decrease in the
Contract Price. retlecting the diminished value of Work
so accepted. If the parties are unable to agree as to the
amount thereof. Owner may make a Claim therefor as
provided in Paragraph 10.05. If the acceptance occurs
after such recommendation. an appropriate amount will be
paid by Contractor to Owner.
13.09 Owner May Correct Defective Work
A. If Contractor fails within a reasonable time
after written notice from Engineer to correct defective
Work or to remove and replace rejected Work as required
by Engineer in accordance with Paragraph I3.06.A, or if
Contractor fails to perform the Work in accordance with
the Contract Documents. or if Contractor fails to comply
with any other provision of the Contract Documents,
Owner may. after seven days written notice to Contractor.
correct or remedy any such deficiency.
B. In exercising the rights and remedies under
this Paragraph 13.09, Owner shall proceed expeditiously.
In connection with such corrective or remedial action.
Owner may exclude Contractor from all or part of the
Site, take possession of all or part of the Work and
suspend Contractor's services related thereto, take posses-
sion of Contractor's tools. appliances, construction
equipment and machinery at the Site, and incorporate in
the Work all materials and equipment stored at the Site or
for which Owner has paid Contractor but which are stored
elsewhere. Contractor shall allow Owner. Owner's
representatives, agents and employees, Owner's other
contractors. and Engineer and Engineer's consultants
access to the Site to enable Owner to exercise the rights
and remedies under this Paragraph.
C. All claims. costs. losses. and damages
(including but not limited to all fees and charges of'
engineers, architects, attorneys, and other professionals
and all court or arbitration or other dispute resolution
costs) incurred or sustained by Owner in exercising the
rights and remedies under this Paragraph 13.09 will be
charged against Contractor. and a Change Order will be
issued incorporating the necessary revisions in the
Contract Documents with respect to the Work: and Owner
shall be entitled to an appropriate decrease in the Contract
Price. If the parties are unable to agree as to the amount of
the adjustment. Owner may make a Claim therefor as
provided in Paragraph 10.05. Such claims, costs, losses
and damages will include but not be limited to all costs of
repair. or replacement of work of others destroyed or
damaged by correction. removal. or replacement of
Contractor's defecti ve Work.
D. Contractor shall not be allowed an extension
of the Contract Times because of any delay in the
performance of the Work attributable to the exercise by
Owner of Owner's rights and remedies under this
Paragraph 13.09.
ARTICLE 14 - PAYMENTS TO CONTRACTOR AND
COMPLETION
14.0 I Schedule of Values
A. The Schedule of Values established as provid-
ed in Paragraph 2.07.A will serve as the basis for progress
EJCDC C-700 Standard General Conditions of the Construction Contract.
Copyright @ 2002 National Soeiety of Professional Engineers for EJ CDC. All rights reserved.
00700 .. 35
payments and will be incorporated into a form of Applica-
tion for Payment acceptable to Engineer. Progress
payments on account of Unit Price Work will be based on
the number of units completed.
14.02 Progress Payments
A. Applications for Payments
1. At least 20 days before the date established in
the Agreement for each progress payment (but not more
often than once a month), Contractor shall submit to
Engineer for review an Application for Payment filled out
and signed by Contractor covering the Work completed as
of the date of the Application and accompanied by such
supporting documentation as is required by the Contract
Documents. If payment is requested on the basis of
materials and equipment not incorporated in the Work but
delivered and suitably stored at the Site or at another
location agreed to in writing, the Application for Payment
shall also be accompanied by a bill of sale, invoice, or
other documentation warranting that Owner has received
the materials and equipment free and clear of all Liens
and evidence that the materials and equipment are
covered by appropriate property insurance or other
arrangements to protect Owner's interest therein. all of
which must be satisfactory to Owner.
2. Beginning with the second Application for
Payment, each Application shall include an affidavit of
Contractor stating that all previous progress payments
received on account of the Work have been applied on
account to discharge Contractor's legitimate obIigations
associated with prior Applications for Payment.
3. The amount of retainage with respect to
progress payments will be as stipulated in the Agreement.
B. ReviClv ofApplicatiol1s
1. Engineer will, within 10 days after receipt of
each Application for Payment, either indicate in writing a
recommendation of payment and present the Application
to Owner or return the Application to Contractor
indicating in writing Engineer's reasons for refusing to
recommend payment. In the latter case, Contractor may
make the necessary corrections and resubmit the
Application.
2. Engineer's recommendation of any payment
requested in an Application for Payment will constitute a
representation by Engineer to Owner, based on Engineer's
observations on the Site of the executed Work as an
experienced and qualified design professional and on
Engineer's review of the Application for Payment and the
accompanying data and schedules, that to the best of
Engineer's knowledge, information and belief:
b. the quality of the Work is generally in accor-
dance with the Contract DocLlments (subject to
an evaluation of the Work as a functioning whole
prior to or upon Substantial Completion, to the
results of any subsequent tests called for in the
Contract Documents, to a final determination of
quantities and classifications for Unit Price Work
under Paragraph 9.07. and to any other
qualifications stated in the recommendation); and
c. the conditions precedent to Contractor's being
entitled to such payment appear to
fulfilled tn so far as it is
responsibility to observe the Work.
have been
Engineer's
3. By recommending any such payment Engineer
will not thereby be deemed to have represented that:
a. inspections made to check the quality or the
quantity of the Work as it has been performed
have been exhaustive. extended to every aspect
of the Work in progress, or involved detailed
inspections of the Work beyond the responsi-
bilities specifically assigned to Engineer in the
Contract Documents; or
b. that there may not be other matters or issues
between the parties that might entitle Contractor
to be paid additionally by Owner or entitle
Owner to withhold payment to Contractor.
4. Neither Engineer's review of Contractor's
Work for the purposes of recommending payments nor
Engineer's recommendation of any payment, including
final payment. will impose responsibility on Engineer:
a. to supervise, direct, or control the Work, or
b. for the means. methods. techniques,
sequences, or procedures of construction, or the
safety precautions and programs incident thereto,
or
c. for Contractor's failure to comply with Laws
and Regulations applicable to Contractor's
performance of the Work, or
d. to make any examination to ascertain how or
for what purposes Contractor has used the
moneys paid on account of the Contract Price, or
e. to determine that title to any of the Work,
materials, or equipment has passed to Owner free
and clear of any Liens.
5. Engineer may refuse to recommend the whole
or any part of any payment if, in Engineer's opinion, it
would be incorrect to make the representations to Owner
stated in Paragraph l4.02.B.2. Engineer may also refuse
to recommend any such payment or, because of subse-
quently discovered evidence or the results of subsequent
E.JCDC C-700 Standard General Conditions of the Construction Contract.
Copyright @ 2002 National Society or Proressional Engineers for EJCDC. All rights reserved.
n0700 -.36
a. the Work has progressed to the point indicat-
ed:
inspections or tests, revise or revoke any such payment
recommendation previously made, to such extent as may
be necessary in Engineer's opinion to protect Owner from
loss because:
a. the Work is defective. or completed Work has
been damaged. requiring correction or replace-
ment:
b. the Contract Price has been reduced by
Change Orders:
c. Owner has been required to correct defective
Work or complete Work in accordance with
Paragraph 13.09; or
d. Engineer has actual knowledge of the
occurrence of any of the events enumerated in
Paragraph 15.02.A.
C. Paymenr Becomes Due
l. Ten days after presentation of the Application
for Payment to Owner with Engineer's recommendation,
the amount recommended will (subject to the provisions
of Paragraph 14.02.D) become due, and when due will be
paid by Owner to Contractor.
D. Reduction in Paymenr
1. Owner may refuse to make payment of the full
amount recommended by Engineer because:
a. claims have been made against Owner on
account of Contractor's performance or furnish-
ing of the Work:
b. Liens have been filed in connection with the
Work, except where Contractor has delivered a
specific bond satisfactory to Owner to secure the
satisfaction and discharge of such Liens;
c. there are other items entitling Owner to a
set-off against the amount recommended: or
d. Owner has actual knowledge of the occurrence
of any of the events enumerated in Paragraphs
14.02.B.5.a through 14.02.B.5.c or Paragraph
15.02A
2. If Owner refuses to make payment of the full
amount recommended by Engineer, Owner will give
Contractor immediate written notice (with a copy to
Engineer) stating the reasons for such action and promptly
pay Contractor any amount remaining after deduction of
the amount so withheld. Owner shall promptly pay
Contractor the amount so withheld, or any adjustment
thereto agreed to by Owner and Contractor. when
Contractor corrects to Owner's satisfaction the reasons for
suc h action.
3. If it is subsequently determined that Owner's
refusal of payment was not j usti fied. the amount
wrongfully withheld shall be treated as an amount due as
determined by Paragraph 14.02.C.1.
14.03 Contractor's Warranty olTitle
A. Contractor warrants and guarantees that title
to all Work, materials, and equipment covered by any
Application for Payment. whether incorporated in the
Project or not, will pass to Owner no later than the time of
payment free and clear of all Liens.
14.04 Substantial Completion
A. When Contractor considers the entire Work
ready for its intended use Contractor shall notify Owner
and Engineer in writing that the entire Work is
substantially complete (except for items specifically listed
by Contractor as incomplete) and request that Engineer
issue a certificate of Substantial Completion.
B. Promptly after Contractor's notification,
Owner. Contractor. and Engineer shall make an
inspection of the Work to determine the status of
completion. If Engineer does not consider the Work
substantially complete, Engineer will notify Contractor in
writing gi ving the reasons therefor.
C. If Engineer considers the Work substantially
complete, Engineer will deliver to Owner a tentative
certificate of Substantial Completion which shall fix the
date of Substantial Completion. There shall be attached to
the certificate a tentative list of items to be completed or
corrected before final payment. Owner shall have seven
days after receipt of the tentative certificate during which
to make written objection to Engineer as to any provisions
of the certificate or attached list. If. after considering such
objections, Engineer concludes that the Work is not
substantially complete. Engineer will within 14 days after
submission of the tentative certificate to Owner notify
Contractor in writing. stating the reasons therefor. If, after
consideration of Owner's objections. Engineer considers
the Work substantially complete, Engineer will within
said 14 davs execute and deliver to OViI1er and Contractor
a definitive certificate of Substantial Completion (with a
revised tentative list of items to be completed or correct-
ed) reflecting such changes from the tentative certificate
as Engineer believes justified al'ter consideration of any
objections from Owner.
D. At the time of delivery of the tentative
certificate of Substantial Completion, Engineer will
deliver to Owner and Contractor a written recommen-
dation as to division of responsibilities pending final
payment between Owner and Contractor with respect to
security, operation, safety, and protection of the Work.
maintenance. heat. utilities. insurance. and warranties and
guarantees. Unless Owner and Contractor agree otherwise
in writing and so inform Engineer in writing prior to
Engineer's issuing the definitive certificate of Substantial
EJCDC C-700 Standard General Conditions of the Construction Contract.
Copyright @ 20tl2 National Society of Professional Enginecrs for E.JCDC. All rights reserved.
00700 - 37
Completion. Engineer's aforesaid recommendation will
be binding on Owner and Contractor until final payment.
E. Owner shall have the right to excl ude
Contractor from the Site after the date of Substantial
Completion subject to allowing Contractor reasonable
access to complete or correct items on the tentati ve list.
14.05 Parried Utilization
A. Prior to Substantial Completion of all the
Work. Owner may use or occupy any substantially
completed part of the Work which has specifically been
identified in the Contract Documents, or which Owner,
Engineer, and Contractor agree constitutes a separately
functioning and usable part of the Work that can be used
by Owner for its intended purpose without significant
interference with Contractor's performance of the
remainder of the Work, subject to the follo\ving condi-
tions.
1. Owner at any time may request Contractor in
writing to permit Owner to use or occupy any such part of
the Work which Owner believes to be ready for its
intended use and substantially complete. If and when
Contractor agrees that such part of the Work is
substantially complete, Contractor will certify to Owner
and Engineer that such part of the Work is substantially
complete and request Engineer to issue a certificate of
Substantial Completion for that part of the Work.
2. Contractor at any time may notify Owner and
Engineer in writing that Contractor considers any such
part of the Work ready for its intended use and substan-
tially complete and request Engineer to issue a certificate
of Substantial Completion for that part of the Work.
3. Within a reasonable time after either such
request Owner, Contractor, and Engineer shall make an
inspection of that part of the Work to determine its status
of completion. If Engineer does not consider that part of
the Work to be substantially complete, Engineer will
notify O\vner and Contractor in writing gi ving the reasons
therefor. If Engineer considers that part of the Work to be
substantially complete, the provisions of Paragraph 14.04
will apply with respect to certification of Substantial
Completion of that part of the Work and the division of
responsibility in respect thereof and access thereto.
4. No use or occupancy or separate operation of
part of the Work may occur prior to compliance with the
requirements of Paragraph 5.10 regarding property
Insurance.
14.06 Final Inspection
that the Work is incomplete or defective. Contractor shall
immediately take such measures as are necessary to
complete such Work or remedy such deficiencies.
14.07 Final Payment
A. Application for Payment
I. After Contractor has. in the opIIllon of
Engineer. satisfactorily completed all corrections
identified during the final inspection and has delivered, in
accordance with the Contract Documents, all maintenance
and operating instructions, schedules, guarantees, bonds.
certificates or other evidence of insurance certificates of
inspection, marked-up record documents (as provided in
Paragraph 6.12), and other documents, Contractor may
make application for final payment following the
procedure for progress payments.
2. The final Application for Payment shall be
accompanied (except as previously deli vered) by:
a. all documentation called for in the Contract
Documents. including but not limited to the
evidence of insurance required by Paragraph
5.04.B.7:
b. consent of the surety, if any, to final payment;
c. a list of all Claims against Owner that
Contractor believes are unsettled; and
d. complete and legally effective releases or
wai vel'S (satisfactory to Owner) of all Lien rights
arising out of or Liens filed in connection with
the Work.
3. In lieu of the releases or waivers of Liens
specified in Paragraph 14.07.A2 and as approved by
Owner, Contractor may furnish receipts or releases in full
and an affidavit of Contractor that: (i) the releases and
receipts include all labor, services, material, and
equipment for which a Lien could be filed; and (ii) all
payrolls, material and equipment bills. and other
indebtedness connected with the Work for which Owner
or Owner's property might in any way be responsible have
been paid or otherwise satisfied. If any Subcontractor or
Supplier fails to furnish such a release or receipt in full,
Contractor may furnish a bond or other collateral
satisfactory to Owner to indemnify Owner against anv
Lien.
B. Engineer's Re\'icH' of Application and
Acceptance
1. If. on the basis of Engineer's observation of
A. Upon written notice from Contractor that the the Work during construction and final inspection, and
entire Work or an agreed portion thereof is complete. Engineer's review of the final Application for Payment
Engineer will promptly make a final inspection with and accompanying documentation as required by the
Owner and Contractor and will notify Contractor in Contract Documents. Engineer is satisfied that the Work
writing of all particulars in which this inspection reveals has been completed and Contractor's other obligations
EJCDC C-700 Standard General Conditions of the Constrllction Contract.
Copyright @ 2002 National Society of Professional Engineers for EJCDC. All rights reserved.
00700 - 38
under the Contract Documents have been fulfilled,
Engineer wilL within ten days after receipt of the final
Application for Payment. indicate in writing Engineer's
recommendation of payment and present the Application
1'01' Payment to Owner for payment. At the same time
Engineer will also give written notice to Owner and
Contractor that the Work is acceptable subject to the
provisions of Paragraph 14.09. Otherwise, Engineer will
return the Application for Payment to Contractor, indicat-
ing in writing the reasons for refusing to recommend final
payment in which case Contractor shall make the
necessary corrections and resubmit the Application for
Pavment.
C. Payment Becomes Due
1. Thirty days after the presentation to Owner of
the Application for Payment and accompanying docu-
mentation, the amount recommended by Engineer, less
any sum Owner is entitled to set off against Engineer's
recommendation, including but not limited to liquidated
damages, will become due and, will be paid by Owner to
Contractor.
14.08 Final Completion Delayed
A. If. through no fault of Contractor. final
completion of the \Vork is significantly delayed, and if
Engineer so confirms, Owner shalL upon receipt of
Contractor's final Application for Payment (for Work
fully completed and accepted) and recommendation of
Engineer, and without terminating the Contract, make
payment of the balance due for that portion of the Work
fully completed and accepted. If the remaining balance to
be held by Owner for Work not fully completed or
corrected is less than the retainage stipulated in the
Agreement, and if bonds have been furnished as required
in Paragraph 5.0 l. the written consent of the surety to the
payment of the balance due for that portion of the Work
fully completed and accepted shall be submitted by
Contractor to Engineer with the Application for such
payment. Such payment shall be made under the terms
and conditions governing final payment, except that it
shall not constitute a waiver of Claims.
14.09
Waiver of Claims
A. The making and acceptance of final payment
will constitute:
1. a waiver of all Claims by Owner against
Contractor. except Claims arising from unsettled Liens,
from defective Work appearing after final inspection
pursuant to Paragraph 14.06, from failure to comply with
the Contract Documents or the terms of any special
guarantees specified therein. or from Contractor's
continuing obligations under the Contract Documents:
and
with the requirements herein and expressly acknowledged
by Owner in writing as still unsettled.
ARTICLE 15 - SUSPENSION OF WORK AND
TEIUvIINATION
15.01 Owner May Suspend IVork
A. At any time and without cause, Owner may
suspend the Work or any portion thereof for a period of
not more than 90 consecutive days by notice in writing to
Contractor and Engineer which wi II fix the date on which
Work will be resumed. Contractor shall resume the Work
on the date so fixed. Contractor shall be granted an adjust-
ment in the Contract Price or an extension of the Contract
Times. or both. directly attributable to any such
suspension if Contractor makes a Claim therefor as
provided in Paragraph 10.05.
15.02 Owner May Terminate for Cause
A. The occurrence of anyone or more of the
following events will justify termination for cause:
1. Contractor's persistent failure to perform the
Work in accordance with the Contract Documents
(including, but not limited to, failure to supply sufficient
skilled workers or suitable materials or equipment or
failure to adhere to the Progress Schedule established
under Paragraph 2.07 as adjusted from time to time
pursuant to Paragraph 6.04):
2. Contractor's disregard of Laws or Regulations
of any public body having jurisdiction:
3. Contractor's disregard of the authority of
Engineer: or
4. Contractor's violation in any substantial way
of any provisions of the Contract Documents.
B. If one or more of the events identified in
Paragraph 15.02.A occur. Owner may. after giving
Contractor (and surety) seven days written notice of its
intent to terminate the services of Contractor:
1. exclude Contractor from the Site, and take
possession of the Work and of all Contractor's tools,
appliances, construction equipment, and machinery at the
Site. and use the same to the full extent they could be
used by Contractor (without liability to Contractor for
trespass or conversion).
2. incorporate in the Work all materials and
equipment stored at the Site or for which Owner has paid
Contractor but which are stored elsewhere. and
2. a waiver of all Claims by Contractor against
Owner other than those previously made in accordance
E.JCDC C-700 Standard General Conditions of the Construction Contract.
Copyright @ 2002 National Society of Professional Enginecrs for EJCDC. Ail rights reserved.
3. complete the Work as Owner mav deem
expedient.
C. If Owner proceeds as provided in Paragraph
15.02.B, Contractor shall not be entitled to receive anv
further payment until the Work is completed. If the
unpaid balance of the Contract Price exceeds all claims,
costs, losses, and damages (including but not limited to all
fees and charges of engineers, architects, attorneys, and
other professionals and all court or arbitration or other
dispute resolution costs) sustained by Owner arising out
of or relating to completing the Work, such excess will be
paid to Contractor. If such claims, costs, losses, and
damages exceed such unpaid balance, Contractor shall
pay the difference to Owner. Such claims, costs, losses,
and damages incurred by Owner will be reviewed by
Engineer as to their reasonableness and, when so
approved by Engineer, incorporated in a Change Order.
When exercising any rights or remedies under this
Paragraph Owner shall not be required to obtain the
100vest price for the Work performed.
D. Notwithstanding Paragraphs 15.02.B and
15.02.C. Contractor's services will not be terminated if
Contractor begins within seven days of receipt of notice
of intent to terminate to correct its failure to perform and
proceeds diligently to cure such failure within no more
than 30 days of receipt of said notice.
E. Where Contractor's services have been so
terminated by Owner. the termination will not affect any
rights or remedies of Owner against Contractor then
existing or which may thereal'ter accrue. Any retention or
payment of moneys due Contractor by Owner will not
release Contractor from liability.
F. If and to the extent that Contractor has
provided a performance bond under the provisions of
Paragraph 5.0 lA, the termination procedures of that bond
shall supersede the provisions of Paragraphs 15.02.B. and
15.02.C.
15.03 Owner lvlay Terminate For Convenience
A. Upon seven days written notice to Contractor
and Engineer. Owner may. without cause and without
prejudice to any other right or remedy of Owner.
terminate the Contract. In such case. Contractor shall be
paid For (without duplication of any items):
1. completed and acceptable Work executed in
accordance with the Contract Documents prior to the
effective date of termination. including fair and
reasonable sums for overhead and profit on such Work:
2. expenses sustained prior to the effective date
of termination in performing services and furnishing
labor. materials, or equipment as required by the Contract
Documents in connection with uncompleted Work, plus
fair and reasonable sums for overhead and profit on such
expenses;
3. all claims. costs. losses, and damages
(including but not limited to all fees and charges of
engineers, architects, attorneys, and other professionals
and all court or arbitration or other dispute resolution
costs) incurred in settlement of terminated contracts with
Subcontractors, Suppliers, and others: and
4. reasonable expenses directly attributable to
termination.
B. Contractor shall not be paid on account of loss
of anticipated profits or revenue or other economic loss
arising out of or resulting from such termination.
15.04 COllfraclOr May Stop Work or Terminate
A. If, through no act or fault of Contractor, (i)
the Work is suspended for more than 90 consecutive days
by Owner or under an order of court or other public
authority, or (ii) Engineer fails to act on any Application
for Payment within 30 days after it is submitted, or (iii)
Owner fails for 30 days to pay Contractor any sum finally
determined to be due, then Contractor may, upon seven
days written notice to Owner and Engineer. and provided
Owner or Engineer do not remedy such suspension or
failure within that time. terminate the Contract and
recover from Owner payment on the same terms as
provided in Paragraph 15.03.
B. In lieu of terminating the Contract and
without prejudice to any other right or remedy, if
Engineer has failed to act on an Application for Payment
within 30 days after it is submitted. or Owner has failed
for 30 days to pay Contractor any sum finally determined
to be due, Contractor may, seven days after written notice
to Owner and Engineer, stop the Work until payment is
made of all such amounts due Contractor, including
interest thereon. The provisions of this Paragraph 15.04
are not intended to preclude Contractor from making a
Claim under Paragraph 10.05 for an adjustment in
Contract Price or Contract Times or otherwise for
expenses or damage directly attributable to Contractor's
stopping the Work as permitted by this Paragraph.
AJUrCLE 16 DISPUTE RESOLUTION
16.01 Mer/zods and Procedures
A. Either Owner or Contractor may request
mediation of any Claim submitted to Engineer for a
decision under Paragraph 10.05 before such decision
becomes final and binding. The mediation will be
EJCDC C-700 Standard General Conditions of the Construction Contract.
Copyright @ 2002 National Society of Professional Engineers for E.fCDC. All rights reserved.
00700 - 40
governed by the Construction Industry Mediation Rules
of the American Arbitration Association in effect as of the
Effective Date of the Agreement. The request for
mediation shall be submitted in writing to the American
Arbitration Association and the other party to the
Contract. Timely submission of the request shall stay the
effect of Paragraph 10.OS.E.
B. Owner and Contractor shall participate in the
mediation process in good faith. The process shall be
concluded within 60 days of filing of the request. The
date of termination of the mediation shall be determined
by application of the mediation rules referenced above.
C. If the Claim is not resolved by mediation,
Engineer's action under Paragraph 10.05.C or a denial
pursuant to Paragraphs 10.05.C.3 or 1O.05.D shall become
final and binding 30 days after termination of the
mediation unless. within that time period, Owner or
Contractor:
1. elects in writing to invoke any dispute
resolution process provided for in the Supplementary
Conditions. or
2. agrees with the other party to submit the
Claim to another dispute resolution process, or
3. gi ves wri tten notice to the other party 0 f tbeir
intent to submit the Claim to a court of competent
jurisdiction.
ARTICLE 17 - MlSCELLA1\JEOUS
17.0 I Giving NOlice
A. \Yhenever any provision of the Contract
Documents requires the giving of \vritten notice, it will be
deemed to have been validly given if:
1. delivered in person to the individual or to a
member of the firm or to an officer of the corporation for
whom it is intended. or
2. delivered at or sent by registered or certified
mail, postage prepaid, to the last business address known
to the gi vel' of the notice.
17.02 Compu[{[lion of Times
A. When any period of time is referred to in the
Contract Documents by days, it will be computed to
exclude tbe first and include the last day of such period. If
the last day of any such period falls on a Saturday or
Sunday or on a day made a legal holiday by the la w of the
applicable jurisdiction, such day will be omitted from the
computation.
17.03 CUlllulative Remedies
A. The duties and obligations imposed by these
General Conditions and the rights and remedies available
hereunder to the parties hereto are in addition to, and are
not to be construed in any \vay as a limitation of. any
rights and remedies available to any or all of them which
are otherwise imposed or available by Laws or Regula-
tions, by special warranty or guarantee. or by other
provisions of the Contract Documents. The provisions of
this Paragraph will be as effective as if repeated
specifically in the Contract Documents in connection with
each particular duty, obligation. right. and remedy to
which they apply.
17.04 Survival of Obligations
A. All representations, indemnifications, warran-
ties, and guarantees made in, required by, or given in
accordance with the Contract Documents. as well as all
continuing obligations indicated in the Contract Docu-
ments. will survive final payment, completion, and
acceptance of the \York or termination or completion of
the Contract or termination of the services of Contractor.
17.05 Controlling Lcm
A. This Contract is to be governed by the law of
the state in which the Project is located.
17.06 Headings
A. Article and paragraph headings are inserted
for convenience only and do not constitute parts
of these General Conditions.
EJCDC C-700 Standard General Conditions or the Construction Contract.
Copyright @ 2002 National Society or Proressional Engineers for EJCDC. All rights reserved.