Imp. Proj. #691
COUNCIL
~m
WHO
REQUEST FOR ACTION
Originating Department
Public Works
Approved for Agenda
Agenda Section
June 25, 2001
Consent
By: Guy Johnson
By: D
(
MOTION TO ACCEPT PUBLIC WORKS STORM WATER IMPROVEMENT PROJECT (PROJECT NO. 691) AND TO
AUTHORIZE FINAL PAYMENT OF $19,015.24 TO G. L. CONTRACTING
Item No.
6.11
REQUESTED ACTION
Staff recommends that Council approve a motion accepting the Public Works Storm Water Improvement Project (Project
691) and authorizing the final payment of $19,015.24 to G. L. Contracting.
BACKGROUND
The Public Works Storm Water Improvement Project involved the installation of catch basins and storm sewer pipe in
the parking area of the Public Works Facility. Also included with the project was the construction of a new water
quality pond directly east of the Public Works Facility.
G. L. Contracting's original bid for the construction of the project was $101 t550.32. During the project it became
necessary to do additional earthwork for the pond excavation and to reconstruct slightly more parking lot curb and gutter.
This is work that was called out in the specifications and for which unit costs had already been assigned. These changes
brought the final contract amount to $115,479.75. The extra work on the excavation and embankment for the pond
construction allowed for the required pond volume to be constructed from a water quality perspective. The replacement of
additional pavement and curb and gutter was necessary because of poor soil conditions in parts of the parking area.
Construction of the pond was mandated by the Shingle Creek Watershed Management Commission. The timing of
the project was fortunate as proposed new legislation would require more stringent methods of treatment of run off
from road salt storage sites. City staff is well pleased with the project and comfortable that it meets all of the
Watershed requirements.
FUNDING
Revenue sources for this project are the City's Storm Water Utility Fund (Water Quality Pond) and the Central Garage
Replacement Fund (Storm Sewer/Parking Lot).
ATTACHMENTS
The Request for Payment and the Engineer's letter recommending final payment are attached.
MOTION BY f""_/):2:{/rL
TO: tf_IYL--nlI7/~
1 I
SECOND BY
(? pjlA//1 ~
I: Rfa\Pubworks\691 Final
. f1 ~ Bonestroo
g Rosene
"" Anderlik &
. \J . Associates
Engineers & Architects
Bonestroo. Rosene, Anderlik and Associates. Inc. is an Affirmative Action/Equal Opportunity
Employer and Employee Owned
Principals: Otto G. Bonestroo. FE. · Marvin L. Sorvala. rE. · Glenn R. Cook. P.E. ·
Raben G. Schunicht. P.E. · Jerry A. Bourdon. P.E.
Senior Consultants: Robert W. Rosene. P.E. · Joseph C. Anderlik. p.E. · Richard E. Turner. P.E. ·
Susan M. Eberlin. C.P.A.
Associate Principals: Howard A. Sanford. P.E. . Keith A. Gordon. P.E. · Roqert R. Pfefferle. RE. ·
Richard W. Foster. P.E. · David O. Loskota. P.E. · Robert C. Russek. A.I.A. · Mark A. Hanson. P.E. ·
Michael T. Rautmann, P.E. · Ted K.Field. RE. · Kenneth P. Anderson. P.E. · Mark R. Rolfs. PE. ·
David A. Bonestroo. M.B.A. . Sidney P. Williamson, P.E.. L.S. · Agnes M. Ring. M.B.A. · Allan Rick Schmidt. P.E.
Offices: St. Paul, St. Cloud. Rochester and WiJlmar. MN · Milwaukee. \1')1
MEMO
Website: www.bonestroo.com
TO: Guy Johnson
FROl\1: Vince Vander Top
DATE: June 12,2001
SUBJECT: Public Warks Storm Water Improvements
City Project No. 69/
Our File No: 34-00-125
The Public Warks storm water improvements have been completed. This \vork \vas
completed such that the Public Warks site and the vacant lot east of Public Warks (the
~'Care Break" lot) \vill meet water quality treatlnent standards per the City's Surface
Water Management Plan and Watershed requirements. The-City also replaced failing
pavement, curb and gutter, and a water service in conjunction v.,rith the project.
The original contract amount for the project was $101,550.32. The final amount for the
work constructed is $115,479.75 or $13,929.43 over the original anlount. All work will
be paid by bid unit prices.
The primary reason for the overage Vlas additional excavation and embankn1ent for the
pond construction. Additional soil was moved than included in the original plan StIch
that the required pond volume from a water quality perspective would be constnlcted.
The cost of the additional excavation was $9,597.80. The total spent for the pond
construction \vas $51,314.96.
An additional $4,331.63 was spent on the reconstruction of the parking lot. Additional
pavement and curb and gutter in poor condition was ren10ved and replaced. The total
spent for the parking lot and curb and gutter reconstruction and site storm se\ver
construction was $60,619.79.
A total of $3,545.00 was spent on a water service in the Public Works yard.
It is reconlmended that final payment be ll1ade to G.L. Contracting in the anlount of
$19,015.24. Final payment should not be Inade until the IC-134 forms have been
received.
cc: TOlTI Schuster
Dale Reed
Mark Hanson
2335 West Highway 36 II St. Paul, MN 55113. 651-636-4600 · Fax: 651-636-1311
. j A' Bonestroo
II Rosene
n Anderlik &
1 ~, Associates
Engineers & Architects
Date:
June 6, 2001
2 AND FINAL
Owner: Ci
For Period: 10/17/2000 to 6/6/2001
Contractor: G L Contractin Inc., 4300 Willow Dr., Medina,MN 55340
Re uest No:
CONTRACTOR'S REQUEST FOR PAYMENT
PUBLIC WORKS STORM WATER IMPROVEMENTS
BRA FILE NO. 34-00-125
CITY PROJECT NO. 691
SUMMARY
1 Original Contract Amount $ 101,550.32
2 Change Order - Addition $ 0.00
3 Change Order - Deduction $ 0.00
4 Revised Contract Amount $ 101,550.32
5 Value Completed to Date $ 115j479.75
6 Material on Hand $ 0.00
7 Amount Earned $ 115,479.75
8 Less Retainage 00/0 $ 0.00
9 Subtotal $ 115,479.75
10 Less Amount Paid Previously $ 96,464.51
11 Liquidated damages - $ 0.00
12 AMOUNT DUE THIS REQUEST FOR PAYMENT NO. 2 AND FINAL $ 19.015.24
Recommended for Approval by:
BONESTROO, ROSENE, ANDERLIK & ASSOCIATES, INC.
~~~
Approved by Owner:
CITY OF NEW HOPE
Specified Contract Completion Date:
October 6, 2000
Date:
Request #2FinaLxls
Contract Unit Quantity Amount
No. Item Unit Quantity Price to Date to Date
Part 1 .. Parking Lot and Storm Sewer
1 Sawing Bituminous Pavement LF 600 3.10 674 $2,089.40
2 Remove bituminous pavement SY 200 2.00 200 $400.00
3 Remove concrete pavement Sy 95 8.10 115 $931.50
4 Remove concrete curb and gutter LF 310 3.00 315 S945.00
5 Salvage and Reinstall chain link fence LF 30 15.20 30 $456.00
6 Remove and Replace Concrete Gutters at Roof
Drains EA 2 278.00 2 $556.00
7 Reclaim bituminous pavement SY 1300 1.30 1430 $1,859.00
8 Common excavation (CV) Cy 300 10.10 300 $3,030.00
9 Topsoil borrow (LV) Cy 10 8.60 10 $86.00
10 12" storm sewer LF 75 21.10 75 S 1,582.50
11 15" storm sewer LF 338 25.70 338 $8,686.60
12 6" roof drain LF 180 12.80 201 $2,572.80
13 4' diameter storm CBMH EA 2 1562.00 2 $3,124.00
14 Connect to existing catch basin EA 1 400.40 1 $400.40
15 27" Diameter catch basin EA 1 785.50 1 $785.50
16 Aggregate base, Class 5 TN 100 16.20 375.2 $6,078.24
17 Salvage Aggregate Base, Class 5 Cy 440 4.90 225 $1,102.50
18 Bituminous base course, Type 31 B TN 250 43.80 224.67 $9,840.55
19 Bituminous wear course, Type 41 A TN 125 54.90 125 $6,862.50
20 8612 concrete curb and gutter LF 320 16.70 372 $6,212.40
21 7" concrete driveway pavement SF 450 4.70 450 $2,115.00
22 4" concrete sidewalk SF 100 3.90 115 S448.50
23 Bollard EA 2 151.80 3 $455.40
Total Part 1 - Parking Lot and Storm Sewer $60,619.79
Part 2 - Pond and Outlet Structure
24 Remove Fence and Install Gate LS 1 774.00 1 $774.00
25 Clear and Grub LS 1 4048.00 1 $4,048.00
26 Common excavation (P) LS 1 23994.50 1.4 $33,592.30
27 Topsoil borrow (L V) Cy 250 8.60 125 $1,075.00
28 Bulkhead existing storm sewer EA 2 64.10 2 $128.20
29 Skimmer structure EA 1 1928.10 1 $1,928.10
30 Connect to existing storm manhole EA 1 400.40 1 $400.40
31 15" storm sewer LF 46 35.40 46 $1,628.40
32 4' diameter storm CBMH EA 1 1942.80 1 $1,942.80
33 Class II random riprap Cy 12 68.00 12 $816.00
34 MnDOT Seed Mix 28A AC 0.6 3113.60 0.6 $1,868.16
35 MnDOT Seed Mix 30A AC 0.6 3113.60 1 $3,113.60
Total Part 2 - Pond and Outlet Structure $51,314.96
Alternate #1 .. Water Service
36 Sawing Bituminous Pavement LF 300 3.10 300 $930.00
37 Remove bituminous pavement Sy 85 2.00 85 $170.00
38 3" HOPE water service IF 150 16.30 150 $2,445.00
Total Alternate #1 .. Water Service $3,545.00
Total Part 1 - Parking Lot and Storm Sewer
Total Part 2 .. Pond and Outlet Structure
Total Alternate #1 .. Water Service
$60,619.79
S51,314.96
$3,545.00
Total Work Completed To Date
$115,4]9.75
Request #2FinaJ.xls
PROJECT PAYMENT STATUS
OWNER CITY OF NEW HOPE
BRA FILE NO. 34-00-125
CONTRACTOR G L CONTRACTING INC
CHANGE ORDERS
No.
Date
Description
Amount
Total Change Orders
PAYMENT SUMMARY
No. From
To
Payment
Retainage
Completed
1 07/15/2000 10/16/00 96,464.51 5,077.08 101,541.59
2 AND FINAL 10/17/2000 06/06/01 19,015.24 115,479.75
Material on Hand
Total Payment to Date $115,479.75 Original Contract $101,550.32
RetainaQe Pay No. 2 AND FINAL Change Orders
Total Amount Earned $115,479.75 Revised Contract $101,550.32
Request #2Final.xls
/ / 1 9 I ~J ,j 9. 2 0 C 1 ~l 9: 3 3 PI M~ 2350
GL CONTRAC'flNG l!'\t:.
No,0494 ~P. 2/7
J.==~~"'\ % - ~"'
lvlINNESOTA Departiment of Revenue
VJit~hQlding Affidavit for Contractors .
Tills a ffi clB, 'Iii musf be appro'r'ed by the Minnf;$O(~ Deps<1ment of Revenue before the SIBle of
Minnesou1j-ior any of /Is subdivIsions cen make finel payrnent 10 conlr~ctors.
Ie.., 34
Please typ4' or prinl eJe,)rly. . This wJli b'e your ma;/ing label (or re:l:.Jt71ing Ihe comp1tred form. .
['1t~: "':-p;;;; n~e -.:- - - - - - - ~ - - - -"\ O~;rT>. PhQfl6
t::i[~.: I b .lj, \ Con+,A.C-+lNf9: . I r--r.':} 78-Cj5'';J4
ff,~..:. I Adur953 ' I TOk'!1 comleel ilmlXiOl
~;; I L\3oo WI \\'i)vJ ~ I $ ~53. 'I S
l7:~.: I CIty , Slille lip Cod~ . I Amout'l! sri I dI:a . .
r::0,~;' '- - jY\e.dHJ 'b:: _ _ (Y\ 1\1 __ _ 5 S3 L{ 0_ ./ $;2 '0, r 8~ . ~ 01-
I MitltlUOli W~hol;~;~ rtJ!nbet"
MonU"1/'ye~~ wor~ ~9aj1
'b--eO
I MOMttl/'yez::r wor~; ended
, Cb.~o' t
, . O~t- ~ ASo:;t'~
, "'{ ;,,--, -:-,
ti~~;~.;"~~, I>r e:jeCI nurn b ~ [ -. --" ,n , Prqfecl ~ eet Ion
fi;;:';,:~. .. '.. -.' ... ~'9 ( N ~ Ho €- lcCfI S-hn-m WeL~" -.:t:Jh ~lIeA'l')~,J i:... .
r.ii ~'E Prqjec: Ownwr . Adc:ll~ll ' Cny
i~;:. CJ~\;~ 0"," i\}€u)' >t\Cp-e. Y.4o I X Iff ON. Ave. Nl
~~t-~!5: DId you hoe"i emptoye~~i work on thIs prqJeC1? ~ rEii 0 No If no. who 01(1 U'lt,work7
f)~;i~t1
S;t'>19
vY\N
ZIp cod;
~r-
I~J DChecSk~J: :oOnXt't.r~:~_'~oerscrlbes your InvOlvemenl In the prQjecl and 'Win all Information reqUested.
r1......fl. h l. Clot w
~~~[~~ 0 Subeonlract":r
I ::5:1 conlract~.~ hrr.d you
~'i'l~~~' ,g): PrIme contra.ctor-lf you 5ubconlrllcled out any work on this prqiecl, .all or your subcontractors must filii Ihelr own
" :~~~~'~i~'~;2:~ a~;~:~:l~:~:r~~~;:~~ ~~I~:~:~:~:c~r :~~~~~t::~~es~~~~:a~:~;,:~~~;;i~:~~ J~~.~~~:u
~~.-,;,~ Bu!tnt~ nllme . Addrsss CN:ner IOlfi,~r
[;:~J ./ ~o..Ko-to.: R.f\)C;; IsCf 5'3 _ 6i5C~I\re. Av-e.. R~mOurJi-) ,n,J
t4~ ../ --i:LQ..\(:~s\\)ehL ' tl.J..lf'7o Qu.iran; Dr-i\J'l",.R~sJ fhN _
I:,~:~.J ~)"'nN 51-6J~ ~rb .q Gt.l.+k.r b~O I W. 150-r"'~ , J Appl ~ \lullf'l (n~
wl~if'- '/\'1le~' ',:'~blorV 1~~50 2erv;1-h ~S, BUrr.JSuill-e. 'I'i\N
~1!~~;
~~~:i
f~(_}~ ..,\~'
!f~ .G,~~~
~!~~~~ .
I dfJc{IJle Ihlll nU Inlorl':'ltl'IDn I have IlIIsd In on Ihls fgrm Is Iwe aM cCJ.71plli!a lalhe t>CSi or my Ilr.owllld..e BnCl t>;;/jal. I authoriZo the Dt!lU'lfmDnl or
Flevenue /0 dI5CI()~ p5r1~ lent imOI'lTlel/on re~ling Ie /hIs pt'Cj~r:I, including S~r1ing wple; of /hi! form. 10 Ill, primo eorur"c/or If I 8m a sutx:om11li:/or,
ana to any svttcontrscloH I{ 18m a prlmo C"ontrsctor, tJ.nd to rho ~onlrDctm9 B9f1ncy,
ContrllClor's ~.tt:_lure " _ ..lWe OllIe
. J' I ~ - c;, -'1-
Mall to: MN Depl. of i;.evenue, WllhholcHnSi} DivisIon, Mllil Stsllol1 6610. St. Paul, M
Certificate ofComprianc&
Based on H,cords or the M'nt~asd.a Department or Revenue, I certl'y thaI the conlr.!clor Who has signed Ihis cerliflCZlle hes
fulfIlled Blithe requlremelw, or M/nnaSOle SlZltLl18S 290.92 llnd 290.97 concerning Ihe Wilhholdlng of Minnesota income lall:
from wag~s paId lo emplo.i:Jees rel~ling to COh\recl se~jces vvith the Slate of Minnssote end/or its subdivisions.
II Depll!'lmc:nr oJ Revenuo "pprov~ Ii' J; G 9 Oilla
. I/~ L)~.. ' 2001
J
>i':it). No. ~OC013'(
(fh:i'. l' /95)
1\f~C"~ on "'C":-'Clrx,: pOD-t:r willi I O~ ~tj"CQ!"I\J""lt' w~.\t' lJ!llng "oy~t)~~ I~,
o 7 I 1 9 / ~ ,j u 1 . is. 2 0 0 1~) O.;j~. f. lit 2 :; 5 0
_ 0 6, _ p _ _ _ _ ...... _ 1 ..\.~ ~ 1.1. t": l~t~ 0 4 2 ~ 6 0
: :
GL CONTRACTING INC.
GL CONTRACTING.INC,
I,! r) . 0 L1 q L ~~I 7 / i
hv ,v,~u(:. I I
~~.
MINNESOTA Dep~lrtment of Revenue
Wi~\hho;ding Affidavit for Contractors
This Sf(idlJvtl m4f5J t?6 lJ,oprovsd by Ihe MIo'tnfi$Ole DBpFitlmenf Of Revel1.JB Defore th~ 'slate of
. Minr'lef.tHo t)r eny of {Is 5ubdiv;1!ons can rrwke final peyment 10 comr8crOfS.
10- 1 34
i):. """_,:' ' ~IE Ef./i ryp; 0,. ptJi'. C1iJ&:[Y, 'Trtfl Y~'J lX you: m.amn~ 1&bt7 tor ;'M~g tts rO.'T~~ fprn.
U,.~:~..:. I'r---~._._-----------,
~.:';~~':" I Company nll~ i. . . t?tot.'r.\e phoM
ta~: I . fr"~1ni:) En,s;oN IJ f'/54GQ -It; h
I:.i~.~.:.~':;.r~~l Ad OJ e 1:1; !. .' . Tl')i.,l ~ortr.6: f & l"!\O!Jr~
:.i.:~...'.l;.~~ .'. '.l~5,l:O "be:!JI'Tff 4ve.. ..1 s . ':33,'50
.:,~:~..'.\I CtL,y 11 ~, sw~ Zip Co~ I Amo;..R'l', Jr:H Cut
tJili6 ,_JiU,Ql!,.sl!lLL~..Lh1J_ ~~32-~ $ 505,50
I . Oct-;taoo
t.t.oel!\/)"Mr wo" 'n~d '
9t:..jJl ~{~~'1
It.~...r~~.!,'f .....'~..'._.::.
-';k.~',:'~> .
. ~ . '4 ~:..
~ ...~, ..~ ~ . .
.,:~~
'~i:"'.';'
. W~~l';..\'i:~
.~l \. ~ ~ J ,
Pi~Pt:\ f1\]1T',t),;:, .. I p~~ I~liqh' '.:. '
J ~SO~;~i. N WJ ~Of~ Cc ., l
PlqJgr:i.~h" .' ,";:-''''' - .:' '- 'U_ Aaa;.~s . ',' .... .
c:\~ d.~ :fu~' "'Ore., .
01:1 yt)1,1 hCW'l eltJ;2~Yfm: wn en InlJ'Pf<vtc\'f ~ "II 0 No . ~ no, whtl did thi w:tflt'?
'3.r+Or trt ~Ct-~,...
c~ ~
. ..
-:t:"r'n'~ ~ IJ ~ ~~
!latt ~J.p 'O;i~u,' ,'" ... ,
':"'--'"" .
~~~~~);; Ch&ck the bo~JtJlrser.d~erlp,s yaur Involvamsrll/n the DrqJ6a ana (1I11~ all }riormlitlot1 requeJted\
.~f 0 S~e'cor:~a~\Or
~~i{ ~ J\lbcgnt~eotor
~~~ir~ lIJ.ma of ;:'we<l,r """'.0 "ired you , .
,~<i.)~1 i__ ~ ,l . ,~..\vtU' ~ \ ~
~~~. AlIl1l11l1: . ~. M J' " fh,J 5'5;'; 4 0
~;~~. ~':!';J' 6'~;;;;~-'~~~~~~rf'y;~~~~~~~:}!~~};~ ~ ~: .~: ~oJect, ellO;YC~~:eon~actor5 tnV&\ fil, ~81r own
>€'~~~J", ' ", , .1:;,:1 :?ip..1 "l.d.~:~~..~,,~Jil~ .tJ:'~r:! ~!U~!cl by ~11..a ,~~~Brlr\'le-nl or ReV!! nua before yO\.! C8 n file )'OlIl sllld'lV!t.. For !llil~
.I'_~._.';-. '(~;.;.": $U,.beCinU'l~c~or 1)'OiJ had. fin in the info,rmatfon ""6erow-t;~(I.8Uec'fY's"\.topy' Of1n!cli 'WtiOOntr&t:tar:!-:C.rL1.fi9'd.lfe""~4'1<1l' you u."",
.J::' \~ need tOOfll ~pl'lee, ISlech tl t>>aparCfe fiihMt. . ~ .,.
~. . ~t:";': ,:'r' i\ ~~ l.::-:,~'.:,\;~\!: :J.:::I.~;'.~'; .
'kj:fi'~. . ..6~:':min ~t1.ill-- _. . . ~Qd:,~~ ~l" ,\O\\~r/Offll:1l! ~
!~~;,~i, ',. ' l' :,:-1.' ~ n~. ~..: . :.. :~; ;~:'... " :"~' :,' .f.;":~;ij. :.....!~. ... .'. -). -.!" · LO:-' J /!. ." ", . . . T .' :;.~ .'.' ';; ,Hlt'"\ '. ~ .: ' ,;' ;' .: ,';T'
~.-....w T" ':'." ... ..~"J '1' ·
!!~~~.:,.'. . l'~' ,.... ' · '" ',' "
~}'Y':'~"~ . --+-- .' , ,.;..,' .:
i~i '~;','
~'l":-=~-:
&~ '.;~~
. ,.' I. ''Ie'
i~~.. .~~\.:
t\~ ~::;
w~;~'.;
, ~.- .' - ' ,...'. '~..".' .,' '. .~. . .,
, t1te'~rB m~( QI. InfQr;rlffJOn 't !1Dve 'f'Hlid In QM thJllorrn 1$ truG ~nc.1 eomp.ili<f 10 il't8 t~1 of mykrs"Wftdgc. ~",:i b7iil, , ,U1I1~.iJ~.IM .o(1p~rtm~l"';t r:f
Rfi Yf1nf.."# b dbc'~. ~ po ~!'t{nc!nr. 1~,tprmaItO" re1al/.'1g ro 'llHi ~qjfCI; Irt{;fiJ01ne tfmdfni eopl~J '" If1i i form, t'1 .th. p,'pr~ ~ CI'\![6~iOf .If j :JTM 5 el...'tcPtllt, cfi:':",
G"a to Cf"I)' !l YfJV-:Jj~O!'5 if 118m' pdmQ 'onf(l}~~orl 1M to fM: tcr,tfocfln9 sgt~t:j',
Q r ~Ol' '\ tl'~ atJ1' t . / <<' ,I,
J
?
MaH to; MN . ept. or R.ven\J5I, Withholding .OlvbiQ;.'lJM~lI Su!lion &510, St.' Pel.Jl.MN 5S14S.,eEI1 0
;1 I
. .
~8rtl(lc8te .oJ C::omplia~o.e "
:lj:'1-ased on ri:tTdo~bf ,.,,~~ t\.'irme~e Oepsf"trrli'rtl oTRevenu!1 I c.ertlfy 'hat \he eOrltr'actoi Wl"IO hes siOn@d \hl, ce'fHf1ceitc has
:l~:-: (lJlrdl~d !lli lhe";e:fjlrem,.rrt~ Of MInnesota S{ahi.e's 290,92' ancj 290.97. conc&r'nin9 the wtthhO~dtn9 -or.Mlnntsota ~-nel.CX .
'i;.t}rfm weg-:e'}?:~Jo t~:t~!!l,~I.~te~S, r-e1~~~t3. ~..~~!~~ ~~.:vic~~ ~Ji~,~ ,~_~, ~'~to of Mlnne)ole. andl~r t~ 5~bdl~jltOnl. .
;~' itf!y(}T . ani'R,r'~cV~ri~~V"m. ~\:e!. ^ JU. . .f.......'i;,.,~ 'g' ~ ,.'/ ........,... ..........-- _.... .... 'D.ftc'" ,......~.I;1':.;~:!~J.:f;~;;-C- -.'~ ...... . "
)J.......:.".~ ~(}r~ 1 a q ...t,,,,;.,.... ~,. ,'.. ~/,~' ....~ t~f . . L-. 20ni
. "f1;A,/ ~(f4t+.;: :""..:. - -~. :;~.~. It li;;1 j;';)' (. .:~:' :,,:: ~.~ ~ ~r-,~', ..,! . ~b, " ',' ," ."",,' '. ",:.'. " .:. ,.,.. . ..".. , · ., .,.' .,.
~~X\~ ;
~iCO N~ iQQ'O):fs
(~1t", ,"\ Ir~~:; ~~'~.;:
~:.;:iF(~:~~
?: ..~/ rY
~if~~~j:~?)
~{.:~~ ~ :.~ ~.~ l L
U .';:~~ ~:;;, ~.:t;~~~:;~~~::,; ;'/:;:. i\;;, !'~~:.~ ~:,~~:\ ~i ' ~S;.~:.~~ ~;' . ~:~:~;'L i;~~;:~;2;~ ~;~ ~~ ~ .1:. 'i" ~~~~; f;::,~;:~~~:c ll}~:;~ ~~~. ~;:~. ~~~~:;, .
t'?1!';It'C' 8'n.,,,,,~ye~C',i P1lP-llr;lt\4v...'O~IP::al':P!"'t"b"'IO'_Wl'\H~.rtll~~y"b!~~~.1l1l., . . ,,,... , ,.
~...:'~t: ~ ~l." 41, ~:i _.. ~ _. .....~~ . ..\.r_< :~..,."..;;','.i,~. . ..... ~.~ ~.;_: '.'.::..:....',:'. '';..f;..., .~ ',(' ~.'!:,:;;:'r,.,~I~;:'" ,'u" fJ</~~~~'~ F';\'~~ .::~:""'" ;,E;, ~~:~ t::: u. ,. . - ·
, : .' ~ ~ .' . _ ' ..' ""');:;:~:':-""" _ ,.... ... ,," .. ._-~: ~.:.. . .. .. _. .' h~' "
...~l'~'~ · t,..~:.. ~ ....... '"~''' t"..~'"r ." ~"l ~ to.
. ~
.~ '.. l...
/18. -' F ;;: 3 ,L,1'!042350
j/07(~UUl U~:~'f ~^A t~~4Q42350
j\)'~ :!::~~'
MINNESOTA Depar:::m'ent of Revenu'e
.Witl1holding ffidavit- for Con~ractors,
ThIs affid.II,lt musf be approved by th8 Minnesota Department of R~ve"ue b~rore fhe slafe of
Minnesou"or eny 01 Its svbcJivlsJoni can'm4ke final payment to conlr,aclors.
~~.~';r~ CMek lha box Iha~Il1B5ctibes your InvolvamerU In the project end (III In ell Informl1t1of1 requested,
~~~jf~, D sore 6anlfaC1tor ~\
f~~; 8 Sub~ntraC{i)r
i,'W Name or l:onlrl3di4'r wTtll hire:! you I"" L r~ _ __ ~
~ '~I _ 4' '.~~dTzr(!A"'1\k1r
~,Add'SSll .4300 W\\\o~ ~\. m~J.it'Jo-(l1"" 55'340
r.;.l.iI..;'.'.i_.F.;........~,..~.:.~.:...~.';...:.~.:.;,;.,~~.~.~.~.~,....1...~.. lJ Prim!! CO"t'~C1oJ-.l1 you !Ubconlr~eled out any work On thIs I'rqJg~: all or your $ubCOnlr.!clo~ muSl fllB their own ~
il:.:~~:.. fC'134 artida-.J!ts 2ind have fhGfIi cerlified by .he ,D~pEnm~nt of Re\tsnus beforft )'eu can fllQyour llffldevll.' For sach
~~~L\'i' s\Jbe.on'raC:lor~fOU h&d,; Iln In lnB Information belOw and ~H8Ch B copy of each iubconlrectorr5 cetllfied JC-134. If you
ra:~~' \leeCl more spllce, attach Cl separate sheel.
f*iil 6u.Ihl!!'I\Ilt"e. Addle.!
~~~. .' f)~ .~. Lfa si }~.\a
~~.;.T} .j
"..--.--' - -.-1-- -,.' ,-- -c. ,- -- - ,- n_ .... ''', .. ...~. ~ -- - .,
, f" '\".4\1'
L~~'~fi'~'
~~l~}~!;~
~{'Q
~~,l~..;';{,~.
.H~'!;:~:.~." J...~:
.~3e;{ :
'Q.r
~~, ~~~
~~~~~ ':l"!
.~;.~. '.1.1. :~I, i ,
K~;r.~ '<
li;w ~v
t~:~i;~~i,:
..-----'----: -" ~i"
~7r.>~..:
~, ~ 1.:i....~f:I \
Ir"",._..~. '~;;~.'
='1 ;"
~ " .~
w.;..~ -I~~ "
~,~tJ~::
. _'1';;.'Jj''''''~'
l;..r~::l >c\
'-;"'"
""
~~J.$l;l~
F. ~ ~.~ '*. - '. \1:. .
,~,.~r\~
~~i;f~.,} .
~:I ::(':
tT ',..
\1-.. ,/..~(
., ~~a. ...~~ ~r,.
GL CONTRACTING iNC.
GL CONTRACTI~G INC.
· [: 4 {j 4
,~
IC..1 :S4
Plf:5St?: type .or prini e16:!,tly. This w!J1 be yo;.r ",.,Wng lef>e! (or rell1rn1ng In!: tompleted form.
~---~-------------~
Comp~ny nr,rn! '. Daytrm! ph.one
I .()o...\<.9~ ~~~ I (65)1-423-3995
I, Addr."l. · . r Jolal to.....ubCl OfTlOlJ:hl _
I , 5 q .5: \3 i $ C'"-'i ..Ie. f\v-tL I. s I~a 9!':gr5':".~ . .-
, - . -'.. .-."f:'^<
I CIty . CJ . . Stf't~. Zip Cod" . t ~rn~~r'l.l.!JI!I.t!~e ",...,~.~, ',~'. .
\....:.. ~~~~~2~_ rr)::__~5 o~a _"i- '>'l$.f:~f 85, -:" '. >~;
J MIM~!Cd:e 1tftlhl"tok'ing'l'''' ID mli1lber
357-8845.
Month/year wen.: began
"9'-5-00 .
Monthl ~Br W~K endE1cJ
6-~3-01
~MO~b~~ ... t~~~UQ.~IID<1::t\J'~
f'rC1Je::;t ov\lner Addrs,s
. ~ C.1'i
Did you htl""- Gmploy~'~ork' on lhlt. prQitC\?
~~r"~~~;:" W~4-e.r ~Mivtnt~'--
Cfty SIAlo ZIp c:.od>>
O\rYnW / J:l H j cqr
f dii:::larc thaI elllnfor:riQlion I oovo tilled In em InJJ ;orm Is l!l~ end l:omp/erG to lhe beFI cf ~ knoWiaC1~11 .nrS tJ.fUill. I "Ull'101Izerhe D~"m{;nl of
Revenue 10 dljCI,,~ p..l/llnttnf informatfon re)olln9 fo tn's ptqj({Ct, if1cJLldfl'l~ Stndittg coplei of IhIll farm, fO thaprirne c:onlrar:.tor If I 6.."TJ , .5Ubconlr8C10r,
OJ"a "" ~ny '(}bcomt~,,~l)rs f1 / bm' 0 prim~ ~ortt((lelcr, and to fh<' C'ontt"lIi1'l9 ~g~~y,
CQ~V et r'$ s.'9n~tLl(' ...... '" . Title 1'\
' . 'tlf.t'A1 tLhm
lthhQldlng O.'v'iSioJ'lf fy'cll SLbll~n6B 10. St. Paul, MN 551 ~ 61 ~
Dafe
6/?Io,
,
t. ~ t
Ce:rtiflc(Jte of. Compilsn'ce
Ba~e.d on record! of l"tf 1.,/tinnesots Depanment of Reven\.Je, 1 'etiif~ Ihnt th@ con\r1D.ctor who has signed this ter1Hicate hs~
fulrlHed at! the requirem.eJt\s of MinnfSsola SllltLJtes 290,92 anc1 290.97 concerning thi withholding ~r Mlnne!io'~ lncorne tax
from "','ages paId 10 em1:)loyees relaUng to cC?nlrZJc1 ~ervi~~ whh the SltJ'i cf Minnesot(i and/or it$ subdiv;sions.
D.. . "Pl.r1gum. t of ~. ~rt'l'r^Pf'~~ l' . .'" 01: Ie
I/~~ v~., JUL.1B
""!'
~~nr.l No. 50001.).4
~HiJ'. 1 ~ I 9i)
f'n r"\ t:~ Ct\ r ~ ;r l.l e-C pZl. p let ,-w!.., "l O"X" ~O+l.oC:Dml.rn' L"~ w nl1C; v).h ~ ")C,Y.I'HI v.-~ mt,
-_......~,.,.....~ ""-..~'-"'II ........~_~~-...-.~~_ _~__~_____.._-.
tl f'Ar.J r
S'I~: t:E:-.5ING c..~O_,_U_-r ~ 4, ool '
~ 'Jl':DJO, -runs: ~~ PM
.-~\W.B~~
Mf~WE5OLA Pepartment of Revenue .. ~S' \ LoBc.o -, 300
"athh ing .d~1t for C 't, ars
This ~t mU$r "Q "PPf'bwC by t."A Mln~ D~r11'1'1~tt,.F ~nue ~fol'<1 tll~ .stDk' J
Mlnne~ or ~DY QE lis ~bdM&iDlI& ccn ~~ ~fl.Ol pgymflm f(J (I;(ltrr;.ctQn.
j ;.
t..... 1.Ito,"
L tJ l.
i<~ . .:' ':' ,l, ~ J
,,' . \) ,.) l"'i Ili
I
~2jl~OOl 16:35 6867300
Pn.1m; a~ ~ &5~~ 'Yc..: J~
~'..,'.~..,r.;.,.'."~.:J:.:..:....."..., ~l=" ~~. ~~ ~Jr 't1t~~ ~~'~ ~_(p,_~1i tI~ ~l<<l kIm.
~)~11 1 CPr.'\14?Y .~~ P ~IJ~
I~~""'~~'~':"';'~"".,:. ~~L~~i "'~ Y__J L- I 5.') d~-37q5
'--f:j.: \ . _I I ",I'" oCAl'I~ ,"",,,,,n]
~ J L.cCC;> ~ b, " 0. ~ ~-re 2..6Z..!:ij ..1 s: 5"
~J~~'~U J G1~ ~ 2Jp ~ ~ . I AlI'!:,W')' ari
t~":f':~~ '" ",,"'''' L.....~~ r""';- s:::6.Z.-, .-.-... -~ J $ J 9~? ,SS-
. _ ..... !....~'.J..~--~~~....". --- .-
f1! b lic' V.Jr')tkS -
Cf~
4/7
,. t:i.l.F lIS .-, "
--
Ic;.a J 34
JJ~{)). ~~
,~* ~t
(:~ tho ~ t/j:J1 dBaer1bcs your 1tw~/~nf /71 I1ls proSed a"d flil (ll tall Jaflll~ ~lM~.
CJ loJe ~t
~~
~A'T'.D ._'"~ 'Jt'~u hl:t,. y~
CJ II,.. l\~ you svh.=n1~ I:l.IJI on)' wcrk on thJs pro[liICt, cdl t:lf your .5UbcantJtIdcro ml15t. la ,~rr CWtl
lea' 34 C!m~1'l ~ h~Q thOi'll esrtlfiad by me Oap:1l1tna1lt of ~8in'''' c..rcw you ~" fils "ilJllr QIf',dav t. Po reach
subsa.n1r$tOr yo:r f,Qc;!, filiI" rho rhl'l\CllJoll ~ GIld D!lt:dl Q c:gpy of ecdJ ~lJ~r' ~ 4Q r1lfl=J I .13.4. II. Y"IJ
Mad rnQI$ .:Ip;I>=S. l:lfJgd} C1oUJp::1'01JJ ~0IiI1.
~Itl'""" f1"m<<I .6..J,&m \. ~ /9~""p !
~
.....
I ~r: ~ a!! r,,~l17'O"',1 J ;.- ~1bG in.b't this .:- illl!Je l)IId U>$\p/tm 10 1M ~ tlf (flY ~lJ/J oM bwlie? I CliWJt~ d+ Ps;?'l 11I\"I151l I d
~hIIll Jl:l.~ ~rl/1.B1!1lnfgrms~1I ~ Ite IW p~~, 1tJdudJnQ ~19 aJ~ GJ Jill: fsnn, 1ft Iho: prtro. c:=ail ec:n-' If j '" tllIIor/1:;t; 1'l:Z-W.
.r.dIo~~(l~If'ClIl\.pnMe~'~CI~~~' :
. I .. . /' '" ~ tHe I aro
, _ e:e:n_ . fth9j!" 7- ]q.,Of
I 'f\J1lhhol6l'1B Di~ClIl, Mo:>~ ~ 1 ~;~1. ~. gS~~10 I
Cartm~ G4 C8mpliance
Based r;n ~ of m.e ~ift~ 0e~8,.r Df ~u.o, , ceniiv thot Ihp ~ ~ ROB alsllll1d ltill ~1~ !;os
fulfIlled "U ft14t. ~Jf'flffjSn~..ef Ml~/::I SJtilUhl~ 290,9'2 i::t.d 290.97 ~nmmrns Ihl! wr!hhoidlus cf MlMe~;.uC;Qrna ~
fiei'll ~, paUt 10 .l'l'lp~ rQi~iTl6 10 c:cnlt(ICt lIoD~ W'ilt\ Ills lte/lil r:;f MI~rg tJltd/o' ff6 subdrv%~ Vi
~." ..~/.,..' f.$#c1~Z1~Pf" .... . . . JUL 192001 Dt:III '~''<)''~:'-!
( ./u!Jlr~"" r..t;d' 1 " ." '
"", ..,~ . ),
S~~ ~=l:M
~ J~ '~~t~'1If!l;B___aos~~~~t.ldL
V2'dllnl96~ONnN ?~:I.rl Lil. ALIIO . ~'f??l~?c
~lOS3NNIW ~O 3~N3~ ~lO~~a
~~~~
,~ " ~
I \1 '. ~~
," I ' r
..,. \,.,' I
.,. \' :
9NIS\f31 :!::!V,LS
W~92:8 J002.6t'lnr
I J i .j .
-. ~ v v ~ \ I 1'\ {}. \.J J. ..L L' \".: J. n \.... .
t:, n 'I~! i ~ 0' t) / f:. H H8,HIJDR 1 VE.$ ..;. G:+ L '
L i~l.) ! V ' v.or I llli ,
No,0494
n ~,/7)4
N( · . :~:~ I P001/001
'i't;~4e~2J:5ra
GL CO~7RACTING INC,
_98/20/2001 .1.0146 FAX 7e:l40~;..2350
JGJ002/002
...-. '" ~,~, -.-
MINNESOTA DepartrIlent of Revenue.
Wit.hKclding Affidavit for ,Contractors
This "fl1d$vJt.:;rm&; l7il spprovel3 oy lrut' tv4iM~or~ OQpal1m"l1f tJfR.-wf1l.Hl bQ'~the Etal~ of
M(nnesars &i" ett1y or Us SUbC1ivlslol'1J t:lin miJkfJ /if\B1.psyrrutn! IOco"1r8Clor,~ '
~"..~J ill,
1;,'/ ILl:
.".~, "
f}~\1!' ,~ · :
Jl~t: A.,.
l:''!'' . :
~~'l'i. ~..;'t.'
"l{" /....
~i.~t ' ,.}
;/~~.::,
· 1'10 t'" . , \I
i~'ti ;';~1::~
If~"L!
~~i~:~!:~;
-~. ~g:.
~~;;
~~~ ~~
t~~f.!1111~
.( t,"1,-/l)' ...~,
DII)I;'1:""~
~,'. ~l, 1~11
~;~fj
;t i~~~ ~
~~~~...l:
f.l~:~' 0
, ,I~:l;"
.:R,~.~
~I~;~:~ .
h, ;:.~;,
lit.:.~;'
~J' 1.1.'."
R: ~~}~~:
!' . 11~ .
r.~,:,'~~: , .
~ . . ~ ...
~I " '.;. ~.,
~ tot "\., .
r J fl' .
J '. ~l:"
~ 'i: -;.J 'i
~:~;' ,:
j.;: ;,
:~. ~;. ..
i: if.}
-
IC.134
PJ.S~.i2 type tJ! pr;o/ cJ"f{I::'; Tn!: t'rHI bJ5 j'~~ ~rHr19 1~tl'f:1 tg:" r~J.nf)J!lfJ lite ~"hp!el~ tonn.
r:. - """- - -- --, ------____-=z;z_,
CQmpan1 nl'm;: ,
I. l:to-r~!:"f"\\'~ I
J AdUtft,... I
I 1~tf,7'i t;JuIl'tfl.n( h! - I
ICY~ ~\I! Z/4)~ I
\. - -o:.~ ~ -:., -. J/!!__ -~:3I_ _./
..
.P.twv_~ n~B' ~' 'I fnV'~ ~uon .", .
- H "S9et~;:~ ,"Vew \!QfQ.. Cc,q. ~ """0 (-' 'A-k.r ~'f""O\I'emt~
l>1'l!bcll!tlNt.., AdQ/tW CIti!lt$lil :'1.. C:~e
c.:;~ ct:':.a Neu,) \J.c;:)~ LlLfol '>1y/~('I'Ptv~ rJ
Oid you f'ui"." .m~~ ~r'C1\'.", l~f~ J)~' 0 VIJJ 0 No l1 no.. w~ dId ,,.. ~.,.
. II
Cneck .he 120)( ,har '\~(IN$ ~ur tnvolveflfrmr In the 'prqJlICIsnd fill in all fnformal/on '1lQ1Je5fed,
o 8oJe3ent...a"/~r
S S~beon'r.ct~!?
Nvi'T'B CI' . Ot'1!ra ctO' L 'W'ho hI te<1 }' otJ
G · L. ~"rf'~r..,-t.\ ~ · ~
Y.:30Q \,.\ i \\2~ br ~ IY\eJ\ "'~ Vl'\f\I " SS>3t;:Q
Primo C;gntt~lor-tf you Sl1!:>OOnI1~ oul any WQrlnm Itlls projl3Cl. .!III Of your 8ubwnlrac!ol" ml.l&l file liielr Own,
IC.134 ilffidavll ~ and hays IMllm eertUlOd by ths O$psrllflen! of Rsve~ Defore you can 'lie YC18 artldsvll. Far eaCl'i
wbt:ol1lreaor ~')LI flatS. fill In Ihlll Inform,rion b/JIQW a"d SlIoIIIch Ii c;cPy or each wbc:ol'ltl'Octor's t;Ilf'tlfh:~g Ie, 34, If you
need more ,p~ne. &l\lJch ~ ie;:>Eara~'~heeL .
6uJ'~u ~fm~ . Addre~! .-.-0-.-- Ow~~!r:'e'f
Arldl'. pt;
--
laS<C!Of 6 tn Dt ell j'1(;,.( (l1 U; o/"J f ha \of ~ fill, d I'll pn l#<tlJ fOrm iJ. I'V\') 8fU1 C otrrp flit ~ 10 &1)0 l>-e SI 0' my ;'00 'fit""" e /'Jrr:i bell eJ. J bLJflrof ize f /-to tJt.pa'lmMl C'
RtJ"'VflWEJ to cil".fOK: /i}"I:t ~!nMf It':/afTn,,,IOl'l r.!.arrng fa fll', pro}flCf, 'f'lChIOI"l] IOndh'tg c1!Jple1. I)r thl' form.. ttI fhs pt/.1't# eO!R'f8etr1r J/ I emo &vb&OI1lflJt:1or.
~~tO 0'''\Y $fl~lIIJC' in " J I;fTi " ptlmf c:c.'"1fIQ(U:J1',fI"''')o ,I'M! tDf'>traCJirrg tJe<<-"1'C'y~ .
lt~c:tcr'. 'tpn'lV(C r;:>- . 'Tn'l
'(!fV1WL/ I!IT~ ~,
Mrutl for M Oept. et:>Rg enlll, Wirhhaldlno Olvtllot1, MbU St&11QtY 6510. $\j. Pi1ul.MN S~146-6510
...... OiJte
'7-- /7-0/
C.rtificate of Compliance
Bl!!,eCl 0'1 recoro!O' 'he .""'ntfSs.OlO Deplif"VTlen.' of Revenue, t c;ertHy 01~{ ~ho t;Qntna.c:\Qf who ha=-sJgnad thUs ccnJl.e8ilc: hat!
fulfilled ell ,he teqvirem..~b; of Mll"H'Hi50ltl S.uatwte$ 290, g2' and 2eO, 97concarnlna lha withholding Of MlnftflQl.1:la 1ncome tJ3:(
fro", wage~ P~\Cf '0 IImpib)CPE"- reJtJtI"g 10 COnltiJd sarvh;ei wlln lhe Jilale ol fvUnn~ots 8~/or Un wbdivj,lo~.
~~.~fr>~RD"WI!J~ -JUL 19 2001 ~H)
"".
';)IOU, Nr.,~onD'~'"
lOf~:t/. 1 '/il~J
I"rH'ftf"t't IIn '04)r'elpod }7f'Ipm oJ n~ ~O~ ~lc~~'d" '"'~,~.. lri.~ w,,,,J,u~.c-rt Ihll
u 7/~ ~ 9..1... ~ ~~19 : :3 L iLJ/~J ~J 5 p." ~ v
06/201 "VUJ, J.U: 4.0 llll 763 -3 Cit 2350
MINNESOTA Depr~;rtment of Revenue
Wi1~hholdina Affidavit for Contractors .
Th/2 efr~;tavjl must bEl tJpp:~ by the M{nM8~ DliPsnmerlI of #4rl1tJllUe ~fore ~ /tlellt of
M/nnl!!~<fra or eny of its !ilbr1lvlslchs ca,., m~lte tiMI &layman! to comrae/Qrs,
I
~:}? ;-~
~"''''''l.
r:;~ '
1"',",0,,, r:, '
~:,;r
'll~
~~g, '
H~,
. ',~~bb, '
!? . {.~
(J~ ,
...'7-. ,II.
",l,~',!,I" '
111, ",t:,c
'... f:j 1
.:r~~~
~,',",f, '.
~.--t),
,~~
It:~~,l_"i
~ ~.!~ /
I, ~.'" :' \ ,\
, ~.t!s~
, · dJ~\~
Y;f"1,~;'
~~t..\;:~
'~":~t.
~.~
";:~,f' ',;.r.,
~j~i
,~,~,~,,!.J::1!'
l,7 :.i~'
~ ~~:;.'
~~~
,~;)~ '
I,~J(Z," .?~ l
;~ ' ':i~
, "f
T\, -":, ~~:
~~: ,,', .,~
~, ".I, "(.~'~, " " ,~
~~}
8:~r:1.'!}
r:~~~~:
1(/' '"
f'r
r:'~~~/.
~t.~~,
t~ .. I ...
f, ..
\ '..'.l ·
~4t'i~1~
Gl:61~ "
f:;;Ii'-~~
~~t...
c.-~',,,.
~~. . ,'I
j....-' J. ':'
GL CONTRAC'rlNG INC.
^ Y 1'\ J.fIH.... R At:,t<'J. L .
GL CON'l'tl<c\CTING INC,
ip .:.. . c~ J002
14]002
kit '"'\/0/
.. f.:i LCD 1\r.;1 J ' \.' ~."~ ,"'r
:;-
fOil 1 :sa
FluS{: ~ ~ fJflr'l !.;Jasrll" 1M wRi bll YOllr mlJlUng laboi f()r fS1JpT/lflJ,! t~ Ctlmp!eieo Toml.
/:.. - ......--1:.-----__ -._-.___'"
c.omp.e"y ~IM :" DlYIlfllt phon"
I 0')1\1 q~~ Cu.. h .. ~-H~ r- I, ).er.
I A.dd l'9U "-. . . ,. 'fellll ('()Ill! MI. tnl>:IIll
I ": 14598 GALAXfe AVE.. I s g 8
j City A~U; V~f. MN m~o I
\... - - -... -- I,! - - - - - -..... _ _ 4\llIItI:::a _ _ _ J $
00'"'"
'/"r Prq[ecl foalllon N ~ H.o~
'A,ddrc"
b'l,
S~~ t.cJcL'i{,.., :t:1Tlp~ve/Y)ew-t.
ell)'
StBle Zip ~c"
NQ I! PD. ~ cr~ tis wort?
~!
C h r:ck the 00)( lir,. t desaibllS ,yo LIi ftrvOlvemel1lln the pl'Qiecl and rill In arI infot1r12J/Jon requer.tld.
o 501., conU:i;sctor
~. 11...... """
.sa SUbcont.f~~ ·
Na;;. CJI Clllnr .1~o r I.W> nlr~ ~\I
.. 8 .L. ~-\-r:a.~.'H~er
AdM!l !,:,: u -: " ~ ' \\ "" \;.II
..-; ~ ~ W ( OuJur-i " ~
~ ".rr:-
fnN
5'~ 3l..f ()
o Prltne cD~Hrnr;:lor-.lr )IOU &llbccnlr,o!:1.d OUl any WOlf( ClI1 thIs prqJed.. all or your !L1bcontrec:tQri mus~ rue Ihelr own'
Ie., 34 alflcjltvils and have them certified by the Depanm."t or RBvehUe befD~ YCl.l C8t'l file your aMCl8Vil. For each
51.1boonLI"lI~f r you Imd. nil 1M Lh e I nforma lIOn below aM aile el1 a copy Dr.l\!l ch sub eonlraClOf s cen med IC.13 4, 'f you
need more *~IIt:$" attach 2J separate :JhGltlt,
iV$ln:i~ Mmr,...j~i.. Aoare!:
Owr<.ttr /Oft! Cl!r
l'
, il'
I'
----.--J 1
: ~
l~
I a(teJiilr(: tIlll/ .11 ~MziJIOn. I no vt nUa.:f In on 1111.: fOrm 4- 'rLlD l;ni1 QOmpl..~ to Ihft be!! of "'lY IuJoWI~~fi and bel/ef. l--"o~ file ~nr or
litalorl.,..., to cf"~ Id~n!!11t /nforTmt11C1l ~irrg " Ihrt pn:decI. 1~1t1d1llJl11....uling r>>plfld af IbI4; tbrm. ro IhlP Fn ~lcr IT I am D ~fllr II C:JOr.
/!h;1 /t:t srJ)' lll.rbcontA~II;:'r2 If f 1m II FRn~ wrnmo te C:>r.lfii::l~ agency. .
Contril=lO/"', slgllal ') ~ I b1- 6 Oa z.tJ:' '0 I
Mat! ~: MN De.., 1~r ~l>Vlel!lJ6. W1thtlot lon, Mflll StatiO" 6510, SI, Pll!J1, MN 5514 &<661 0
, .,.J ,
'Certlficale of Compllarace
B~eo Ol"i recOl'd& g1 rtl::fMirmesoLQ D&PJi!r\m&1l1 or RswenU1:l, I can)()' lheL Lhl ct>nlr~CIQT whol'll!lll Ilgll&d ~ ~.nlncale has
fulfilled all lT1Q rEQUlret(~I'1l11! c1 Mtrml!l901.1l Stawlo", 2g0.51~ onCJ ZaO:97 eoncernfng~. WILhhOJOing 01 Mmn\lllQt:, Incl:lme II!'lX
from wages I"QId to C:r1;J!l:10Y:C:; re1at1n9 10 COmr21Cl Sen/lc&~ With tn. SUstll of Minne50W 2lnd/Qr 11$ SUDdlVl&lonll. .
,'t'~PJA" '''''''''',C-fll gf Rc"Yt;nue sp;~'w;r( Oi.Jk:
t/~ 'I.. JUl 19 2001
$tor;)t Na, .s. 0001 3..,
fh,.. 1" In&-; 'Ptl~ c.j\ '1l':l-,)":J1Xli pb~ ~;l" 1QXs pt19~"\ff: ,..-c=JQ U-:'lr'l~ JIilrb..)l;r'C Iflt.
CA fi
pe ifications for
Storm Water Improvements
City of ew Hope
July, 2000
City Project 0.. 691
File 00 34s00EJ 125
Bonestroo
Rosene
Anderlik&
Associates
Engineers & Architects
PUBLIC WORKS
STORM WATER Th1PROVEMENTS
CITY PROJECT NO. 691
Fll..E NO. 34-00-125
NEW HOPE, MINNESOTA
2000
Index
Advertisement for Bids
Information to Bidders
Proposal
01010.
01030.
01040.
01310.
01330.
01400.
01570.
02108.
02225.
02230.
02280.
02312.
02315.
02320.
02515.
02630.
02720.
02740.
02770.
02775.
02830.
02930.
16050.
Summary of Wark
Alternates
Coordination
Project Meetings
Submittals
Quality Control
Erosion and Sediment Control
Full Depth Reclamation
Removals
Site Clearing
Adjust Miscellaneous Structures
Subgrade Preparation
Excavation and Fill
Trench Excavation and Backfill
Water Services.
Storm Drainage
Aggregate Base Course
Plant Mixed Bituminous Pavements
Concrete Curb and Gutter
Concrete Paving
Fence and Bollards
Seeding
Basic Electrical Materials and Methods
Conditions of the Contract
34-00-125
<9 2000 Bonestroo, Rosene,
Anderlik & Associates. Inc.
PROFESSIONAL CERTIFICATION
I-I
INDEX
PROFESSIONAL CERTIFICATION
I hereby certify that this plan, specification, or report was
prepared by me or under my direct supervision and that I am
a dul)l Licensed Professional Engineer under the laws of the
State of Minnesota.
%' r- --;;;-- ~~
Vincent T. Vander Top, . .
Date: July 5~ 2000
34-00~ 125
@ 2000 Bonestroo, Rosene,
Anderlik & Associates, Inc.
1-2
Reg. No. 25770
INDEX
ADVERTISEMENT FOR BIDS
Sealed bids \vill be received by the City of New Hope, Minnesota at the City Hall, at 4401 Xylon
Avenue, until!! :00 A.M., C.D.S.T., on Monday, July 17, 2000, at which time they will be publicly
opened and read aloud for the furnishing of all labor and materials and all else necessary for the
following:
Public Works Storm Water Improvements. City Project No. 691
1,800 SY
300 TN
150 TN
1000 TN
360 LF
850 SF
4,500 CY
650 LF
Remove Bituminous Pavement
Bituminous Base Course Paving
Bituminous Wear Course Paving
Aggregate Base (Salvaged and Ne\v)
B612 Curb and Gutter
Concrete Apron and Sidewalk
Common Excavation for Pond
Storm Sewer and Drain Pipe
Miscellaneous site improvements including grading, restoration, storm sewer structures, and
fencing.
Plans and specifications, proposal forms and contract documents may be seen at the office of the City
Clerk, Ne\v Hope, Minnesota, and at the office of Bonestroo, Rosene, A11derlik & Associates, Inc.,
ConSlllting Engineers, 2335 W. Trunk Highway 36, St Paul, MN 55113, (651) 636-4600.
Each bid shall be accompanied by a bidder's bond naming the City of New Hope as obligee, certified
check payable to the Clerk of the City of New Hope or a cash deposit equal to at least fi ve percent
(50/0) of the amount of the bid, vvhich shall be forfeited to the City in the event that the bidder fails to
enter into a contract.
The City Council reserves the right to retain the deposits of the three lowest bidders for a period not
to exceed 45 days after the date and time set for the opening of bids. No bids may be vvithdrawn for
a period of forty-five (45) days after the date and time set for the opening of bids.
Payment for the work will be by cash or check.
Contractors desiring a copy of the plans and specifications and proposal forms may obtain them from
the office of Bonestroo, Roselle, Anderlik & Associates, Inc., upon payment of a non-refundable fee
of $35.00. See "Information to Bidders" for plan/specificatioll fee policy.
The City Council reserves the right to reject aI1Y and all bids, to waive irregularities and informalities
therein and further reserves the right to a\vard the contract to the best interests of the City.
34-00-125
<92000 Bonestroo. Rosene,
Anderli.k & Associates. Inc.
Daniel Donahue, City Manager
City of New Hope, Minnesota
ADVERTISEIvlENT FOR BIDS
INFOR.t\1A TION TO BIDDERS
1. BID PROPOSAL~ Each planholder has been furnished a specification, plan set and one extra
proposal Bids shall be submitted on the separate Proposal Form designate;dUBID COPY". The
Proposal containing the bid shall be submitted in a sealed envelope.
Requests for Plans and Specifications should clearly state the name of the project beine
bid.
2. BRA PLAN AND SPECIFICATION POLICY:
1) Plans and specifications shall only be available ona non-refund.able~ per plan basis,
with all contractors and vendors being charged the same. Planholders may obtain
more than one set of plans and specifications for the stipu.lated amount, however, all
are non-refundable.
2) The amount for the bid package will be stated in the Advertisement for Bids,
3. INDIVIDUAL DRAWINGS ANTI SPECIFICATION SHEETS: Individual drawings and
specifications sheets may be purchased at the rate of Five Dollars ($5.00) per sheet of drawings
and Twenty-five cents ($0,25) per sheet of specifications for which no reftmd will be made.
4. BID TABULATION: Planholders submitting a bid will be mailed a Bid Tabulation.
Plan.holders not submitting a bid may purchase a copy of the Bid Tabulation for Five
Dollars (55.00).
E1\r:D OF SECTION
1: \bradocs\general\lnfonl'lation to Bidders...99
4/98
~ :r:,:roo Bidder: r;. L. C~ ,f ~" <--t I n
R Anderlik & Address: J c....<-, LV I II LA LV
~ ~ 1 Assodates
Engineers & Architects
--c ~ \. <-
() ;~
14; tL .~r ] y'(l
,)1-
Total Base Bid: /L"C '-i ~---[:' -
Tele hone No. 76 1-<{7F --C( ~27
Fax No. 71:: 1 ~fc y -;;. 1. C-C
PROPOSAL
PUBLIC WORKS STORM WATER IMPROVEMENTS
FILE NO. 34-00-125
NEW HOPE, IvllNNESOTA
2000
Opening Time: 11:00 A.M., C.D.S.T.
Opening Date: Mondav. Julv 17. 2000
Honorable City Council
City of New Hope
4401 Xylon Ave North
New Hope, NIN 55428-4898
Dear Council Members:
The undersigned, being familiar with your local conditions, having made the field inspection and investigations deemed
necessary, having studied the drawings and specifications for the work including Addenda Nos. -----
and being familiar with all factors and other conditions affecting the work and cost thereof, hereby proposes to furnish
all labor, tools, materials, skills, equipment, and all else necessary to completely construct the project in accordance
with the drawings and specifications on file with you and Bonestroo, Rosene, Anderlik & Associates, Inc., 2335 West
Highway 36, St Paul, Minnesota 55113, as follows:
No.
2
3
4
5
6
3400 125pro.xls
Item Units Qty Unit Price Total Price
Part 1 · Parking Lot and Storm Sewer J~ 1,'8'" 6 0 eO
-
Sawing Bituminous Pavement LF 600 $ $
j e-=.. t:'O
Remove bituminous pavement SY 200 $ $ 1j DO --
Remove concrete pavement Sy 95 $ <i['3- $ 7f.Cj ~
qJO C:(:!
f!),e -
Remove concrete curb and gutter LF 310 $ J- $
) r'.:z~ Lf t;: 6 ~~
Salvage and reinstall chain link fence LF 30 $ ~- $
,J 7 ~ a~ DC
Remove and Replace Concrete Gutters at EA 2$ $ S-S6 ---
Roof Drains
PoOl
No. Item Units Qty Unit Price Total Price
;-IS- <::'1'
/ ~?Cl -
7 Reclaim bituminous pavement ~ n6,- $ I C"'
Sy 1,300 $ ~ ;;. I L~ 6 c:
I . (.
/0 Ire"' ]~ c,~
8 Common excavation (CV) Cy 300 $ It' -~ $ -
9 Topsoil borrow (LV) CY 10 $ ~G~ $ r6 c~
~ ~
10 12" stonn sewer LF 75 $ ~ J ,..!:- $ I, ~;2--
f.;Jr-7~ Ge
11 15ft stonn sewer LF 338 $ $ ~I 6 ~ 6 --
,
12 611 roof drain LF 180 $ 1;1 ye $ ;} I 1 C'I./- to ~
13 4' diameter storm CBMH EA 2$ J, -S- 6' d. <:-.=: $ 3 J;}V o.!.
I
14 Connect to existing catch basin EA 1 $ 4 (Jo &.fO $ 4 Do 4 E.
15 27" Diameter catch basin EA 1 $ 7Y~~ $ --, F-~ ~
62c eo
16 Aggregate base, Class 5 TN 100 $ / - $ /, 6;).D ~
1jCf!- 6JJ 1S-6 c!)c
17 Salvage Aggregate Base, Class 5 Cy 440$ -
$
'-I J~~ ce;/Oq
18 Bituminous base course, Type 31B ~8'l ;- /' .~'C
TN 250 $ .. $ _m. ) 8([.~
~_r:'f~ 0 27=117 :s:~ llc 6( 't'6;L :
19 Bituminous wear course, Type 41A TN 125 $ ~-ij ~C $
20 B612 concrete curb and gutter LF 320 $ I 6 7-=: $ ~ J tj'l c,.::.
21 7" concrete driveway pavement SF 450 $ II 73- $ .a II ~ e~
/
22 4 II concrete sidewalk SF 100 $ JC!.!- $ :J1 t:; o~
23 Bollard EA 2$ 1 ~/lf:'- $ ;JOJ 63-
61 S-C~ ::::- :)~2 ~e
24 Loop detector LS 1 $ --
$
Total Part 1 ... Parking Lot and Stonn Sewer $~ ()G~
,
#Si?' q 0200
/ ---
Part 2 · Pond and Outlet Structure
00 7/Lf~
25 Remove Fence and Install Gate LS 1 $ 7 7Y --- $
26 Clear and Grub LS 1 $ if L'LJ 0 d~ 1-/ () <<-(6" :::-
I $
3400 12Spro.x.ls
P-2
No. Item Units Qty Unit Price Total Price
S-0 -2J, c11y ~
27 Common excavation (P) LS 1 $ ,;1 5/ ci11f -$
'!~~ OJ'r-(' ec....
28 Topsoil borrow (L V) Cy 250 $ ---
$
29 Bulkhead existing storm sewer EA 2$ ? tj~ '3- $ J ;) ~ :z--=.
30 Skimmer structure EA 1 $ I, 1;2 ~1Q.. $ /} Cj J Y' l :-
31 Connect to existing manhole EA 1 $ L) tx:J 'i ~ $ 1f /lo '-13-
32 15" stann sewer LF 46 $ :5:~ ~ $ /, 6)'% ::-
33 41 diameter storm CBNrH EA 1 $ Iq~:J 'i~ $ /; 1<-/,) 15~
34 Class II random riprap Cy 12 $ 6 g- 0 :::.. $ ~ / /:. tS:::...
b" !,~6g'b
35 MnDOT Seed Mix 28A AC 0.6 $ .J1 II,] - $
36 MnDOT Seed Mix 30A AC 0.6 $ S, /I,) ~ $ ! I "'F 6 "g !.!-
$ 4 I, :it{- 6 ,2-
Total Part 2 - Pond and Outlet Structure ---.
~
Total Part 1 - Parking Lot and Storm Sewer $ r g--/1 ():J bO
Total Part 2 - Pond and Outlet Structure $ .L/ ~ s <-;6 /2-
Total Base Bid $ ! DO, 'f:s;D ~
Alternate #1 · Water Service
10 91. eo
37 Sawing Bituminous Pavement LF 300 $ ~1 -- $ _ C] -.
.. t;:' c /70 t:"'C-
38 Remove bituminous pavement Sy 85 $ ;)- $ -
Ie II S-CJ / S-c
39 Bituminous base course, Type 31B TN 15 $ / {)c; - -
$
40 Bituminous wear course, Type 41A TN 7$ 1]3~ $ Cl'S<3 ~~
If~ -r-Ct 0
41 311 HOPE water service LF 150 $ $ j, l.f '-} -
Total Alternate #1 - Water Service $ ~9FOJ-=-
3400 I 25pro.xls
P..3
I
The final amount of the contract shall be determined by multiplying the final measured quantities of the various items
actually constructed and installed by the unit prices therefor, in the manner prescribed in the specifications. However,
the low bidder shall be detennined by adding the sums resulting from multiplying the quantities stated by the unit
prices bid therefor.
Accomp~ bid is a bidder's bond, certified check, or cash deposit in the amount of
$ , which is at least five percent (5%) of the amount of my/our bid made payable to the
Owner, and the same is subject to forfeiture in the event of default on the part of the undersigned or failure on the part
of the undersigned to execute the prescribed contract and bond within fifteen (15) days after its submittal to melus.
In submitting this bid, it is understood that the Owner retains the right to reject any and all bids and to waive
irregularities and information therein and to award the contract to the best interests of the Owner.
In submitting this bid, it is understood that payment will be by cash or check.
It is understood that bids may not be withdrawn for a period of 45 days after the date and time set for the opening
of bids. It is understood that the Owner reserves the right to retain the certified check or bond on the three'
lowest bidders as determined by the Owner for a period not to exceed 45 days after the date set for the opening
of bids.
Respectfully submitted,
(A Corporation)
(An Individual)
(A Partnership)
p~
Title
~~L'~[) ~/~~~~6VU
Printed Name of Signer
3400125 pro.xIs
P..4
SECTION 01010
SUMMARY OF WORK
PART 1 - GENERAL
1.01 PROJECT DESCRIPTION
A. Contractor shall supply all labor, materials, transportation, apparatus, equipment and
services required to provide the general c.onstruction for all items described in the
plans and specifications.
B. The project is located at 5500 International Parkway in New Hope, Minnesota.
C. Requirements of sections in Division 0 and Division 1 extend and apply to all work
and material supplied by contractor, subcontractors, material Sllppliers and shall be
included as a part of each section of this specification.
1.02 DIVISION OF CONTRACT
A. The general contractor shall be the prime coordinator of the work and their schedule
and progress shall govern the work of other contractors and subcontractors. The
general contractor shall notify their subcontractors and other contractors \vit11in a
reasonable time of phases or items of the work requiring the incorporation of their
work. The subcontractors and other contractors shall, after SllCh notification and
within a reasonable time, proceed with the furnishing, installation, laying Ollt or
incorporation of their work~ so as not to .delay or ilnpede the general contractor or job
progress.
1.03 \VORK UNDER SEPARATE CONTRACTS
A. The Owner retains the option of issuing separate contracts for other work 111
connection with the project.
1.04 OWNER
A. The City of New Hope is designated as the Owner.
1.05 ENGlNEER
A. Bonestroo, Rosene, Anderlik & Associates, Inc., 18 designated as the
Engineer / Archi teet.
34-00-125
@ 2000 Bonestroo. Rosene,
Anderlik & Associates, Inc.
01010-1
SUivlMAR Y OF V\'ORK
B. Contact Person: Vince Vander Top, Phone No. 651-604-4790
Pager No. 612-510-3681
Cellular No. 612-805-8255
1.06 LAYOUT
A. The general contractor shall lay out all work. This layout shall be for the use of all
trades. Each subcontractor shall then layout their own work and be responsible for
any damages to their work or that of others occasioned by their errors or failure to
check properly alld verify all measurements.
B. Subcontractors for all phases of the work are responsible for layout of t11eir work,
and they shall base their layout on the \vork lines established by the general
contractor,
1.07 EXAMINATION OF THE SITE
A. It is required and expected that each contractor, before submitting a proposal for
\vork required under this specification, shall visit the site, make a thorough
examination of existing conditions, take all necessary measurements, and thoroughly
familiarize hinlself \vith all existing conditions and all of the limitations pertaining to
tile work herein contemplated.
B. No additional compensation will be allowed because of the contractor's
misunderstanding as to the amount of work involved or their lack of knowledge of
any of the conditions pertainillg to the work based on their failure to make
examination of the site.
C. The submission of a proposal shall be considered assurance that the contractor has
visited the site and made a thorough examination of conditions and limitations.
1.08 EX..A.l\1INATIONOF THE DOCUMENTS
A. Extent of specifications and dra\vings defining \vork to be performed under this
project are listed in the Table of Contents and List of Dra\vings, respectively, and any
addenda subseqllently issued amending those sections. It is the bidder's sole
responsibility to verify that they have received all sheets of drawings and
specifications. No claim for additional compensation will be allowed due to lack of
complete information at time of bid.
B. It is expected that in the event that any of these specifications are not clear or if there
are any discrepancies, these will be brought tothe attention of the Engineer prior to
submission of bids and a decision in writing will be rendered as soon as possible.
34.00.125
@ 2000 Bonestroo~ Rosene,
Allderlik & Associates. Inc.
01010-2
SUMMARY OF \VORK
C. The Divisions 2 through 16 primarily apply to the various trade divisions, but
contractor and all subcontractors shall be bound to the information and requirements
of the complete set of specifications. Mention or indication of extent of work under
any \vork Division or Specification Section is done only for the convenience of
contractor and shall not be construed as describing all work required under that
Division or Section, nor establishing any trade or jurisdictional requirements.
1.09 CONTRACT PERIOD
A. Award Date: The City Council \vill consider bids at the July 24, 2000 Council
meeting. The Contract could be awarded at the July 24 meeting.
B. Start Date: The Contractor shall not commence work until the Owner has issued a
"Notice to Proceed". This notice shall be issued \vhen execution of the contract
documents has been completed. The Contractor can aSSUlne that they will have
copies of the contract documents within three days after the c.ontract avvard. The
Contractor shall have no more than five working days to complete tlleir processing of
the contract documents. The City attorney's office review of the contract documents
shall take no more than t\VO days.
1. The pond construction can begin inlmediately after the contracts are approved
and a preconstruction meeting is held.
2. The parking lot construction must be coordinated \vith improvements inside the
Public \Varks garage. The improvelnents will be constructed by others. Refer to
section 01040. The Contractor should assume an early start date of i\.ugust 7,
2000 for the parking lot and storm sewer construction.
C. Completion Date: All \vork including seeding and restoration must be completed by
October 6, 2000.
1.10 LIQlJIDATED DAMAGES
A. If completion dates are not met, liquidated damages, as specified in the
Supplementary Conditions, shall be as follo\vs. Refer also to Sections 3 and 11.4 of
the "Conditions of the Contract".
1. One Hundred Dollars ($100.00) per calendar day for each completion date
missed.
2. Liquidated damages will remain in effect for each con1pletion date until t11e
work under the respective phase is completed.
1.11 SEQlJENCE OF WORK/OWNER occup At"\JCY
A. The general sequence of \vork shall be at the option of the contractors, except as
outlined in Section 01040 and subject to the approval of the Engineer and the Owner.
34-00-125
@ 2000 Bonestroo, Rosene,
Anderlik & Associates. Ine.
01010-3
SU!\1I'v1ARY OF \VORK
However, \\lork shall be carried on simultaneously at as man)' points as will, in the
judgement of the Engineer and Owner, enable the work to be completed within the
prescribed timea
1.12 ",TORKING HOURS
A. All \;york shall be accomplished between the hours of 7:00 A.M. and 9:00 P.M.
Monday through Friday, and 9:00 A.M. to 7:00 P.M. on Saturday. No construction
activity will be permitted on Sundays or Holidays unless necessitated by an
emergency or authorized in writing by the Owner or its representative. The
Contractor Inust comply with all City ordinances to construct this project.
1.13 COLD WEATHER CONSTRUCTION
A. Specific items such as concrete and bituminous have temperature constraints for
constluction. Any heating or protection required for construction shall be incidental
to the project No additional payment will be made by the Owner.
PART 2 - PRODUCTS
Not Used.
PART 3 -EXECUTION
3.01 MEASURElVIENT AND PAYMENT
Not Used.
END OF SECTION
34-00-125
@ 2000 Bonestroo, Rosene,
Anderlik & Associates. Inc.
01010-4
SUrvUvlARY OF \VORK
SECTION 01040
COORDINATION
PART 1 - GENERAL
1.01 SECTION INCLUDES
A.General requirements for overall project coordination.
1.02 RELATED SECTIONS
A. General Conditions, Supplemental Conditions, Conditions of the Contract and
Division 1 sections apply to the vlork of this section.
1.03 SlJBMITTALS
A. List of Subcontractors.
B. Construction sclledule.
1.04 GENERAL
A. Coordinate work with the Owner's operating personnel to minimize interruptions to
tIle Public \V orksoperation.
B. Do not operate valves or eqllipn1ent vvithout OVvner's permission.
C. Coordinate all \vork and Subcontractors to avoid delays in construction progress.
1.05 COORDINATION WITH OTHER PROJECTS
A. The City of Nevv Hope recently awarded a contract for improvements to the Public
Works Building. The improvements include an addition on the south side of the
building and improvements inside the building/garage.
B. City vehicles CUITently access the "Backyard" (the east side of the property) and the
"Garage" at the south side of the building. The vehicles exit the Backyard and
Garage at the north side of the building. Public Warks vehicles access the property
during normal working hours except during emergency. Police Department vehicles
access the property for fuel during all hOllrs.
C. It is anticipated that improvements under this project and under the Building Project
'Vvill restrict access to the building as follovvs:
34-00-125
@ 2000 Bonestroo. Rosene,
Anderlik & Associates, Inc.
01040-1
COORDINATION
1. Both ingress and egress traffic to the property wi}l be restricted to one side at
a time during construction. The other side will be closed for construction
activity.
2. The north garage door and north gate to the backyard will be closed to traffic
from August 7,2000 to September 5,2000.
a. When the north garage door and north gate are closed, the
Contractor \vill be able to occupy the site and complete removals,
storm se\ver, and aggregate improvements.
b. During this period others will complete improvements inside the
building by the north garage door including the replacement of the
garage floor. .L~ccess will be required by this contractor for
removals and deliveries such as ready-nux trucks.
3. It is anticipated that the interior improvements by the north door will be
completed by September 5, 2000. At that time interior improvements by
others \vill begin by the south garage door. Access to the garage and
backyard will then be required on the north side. September 5, 2000 is the
anticipated date for the access s\vitch; however, if interior improvements are
completed prior to this time, access may be switched earlier. If interior
improvements are completed after this time access \\'ill be switched later.
4. During periods when access is required on the north side, the Contractor shall
be responsible for lnaintaining access. Access may be closed for short
periods for the construction of bitumi110Us pavement. The timing of these
periods Inust be coordinate with the City Representati ve~
1.05 UTILITIES
A. Verify location of all existing utilities prior to construction.
B. All kno\vn existing utilities are shown on the plan in a general way only and the
O\vner does not warrant the exact location. It s11a11 be the contractor's responsibility
to verify all existing utilities and to check \vith utility companies prior to starting
work. The Contractor shall also be responsible for taking all necessary precautions to
prevent damage to existing utility lines. The crossing, relocation, removal, shoring,
compaction and other protective procedures necessary to protect the utilities shall be
considered incidental to the project.
c. All utility construction costs incurred by private Owners (NSP, Minnegasco, US
West, Media One) which are the responsibility of the City of New Hope shall be
billed directly to the City without mark-up by the Contractor.
34-00-125
@ 2000 BonestroQ, Rosene,
Anderlik & Associates, Inc.
01040-2
COORDINATION
1.06 CONSTRUCTION INSPECTION
A. The Contractor is hereby informed that a construction inspector will be made
available to the project. The construction inspector will be a liaison bet\:veen the
E-ngineer and the Contractor. The constluction i11spector will assist the Project
Engineer in confirming that the project is completed in accordance with approved
plans, specifications and the contract documents.
B. The construction inspector will generally be present at the project site during
significant construction activity and/or installations. The construction inspector will
be authorized to inspect each part or all of the work completed and all of the
materiais supplied or furnished for the project
C. The construction inspector will notify the project engineer, and document in writing,
failures of work or materials to conform with approved plans and specifications. The
inspector will have the authority to reject unacceptable materials, and will make
recommendations to the project engineer regarding the rejectio11 of any work
determined to be unacceptable. The Engineer or hislher agent shall be allowed access
to all parts of the work, and shall be furnished \vith such information and assistance
frOITI tIle Contractor to make inspections.
D. Contractor shall notify Engineer at least 24 hours prior to significant construction
activity and/or installations to allow scheduling of construction inspector.
PART 2 - PRODUCTS
NOT USED
PART 3 - EXECUTION
NOT USED
END OF SECTION
34-00-125
@ 2000 Bonestroo, Rose.ne.
Al1derlik & Associates. Inc.
01040-3
COORD1'JA TION
SECTION 01310
PROJECT MEETINGS
PART 1 - GE:N~RAL
1.01 PRECONSTRUCTION MEETING
A. A preconstluction meeting will be scheduled within five days after receipt of signed
contract documents.
B. Attendance by Contractor's authorized representatives and all major subcontractors
will be required. The Engineer, Inspector, and Owner's Representative 'A-,ill attend.
c. The Contractor shall submit a written \vork schedule at the preconstluction meeting.
1.02 PROGRESS MEETINGS
A. Progress meetings may be scheduled by the Engineer. Attendance by the Contractor
and key Subcontractors will be required. A minimum 24 hour notice \vill be given
for all meetings.
B. Persons designated by the Contractor to attend and participate in the project meetings
shall have all required authority to commit the Contractor to solutions agreed upon in
the project meetings.
c. Subcontractors, material suppliers, and others may be invited to attend project
meetings in vlhich their aspects of work are involved.
END OF SECTION
34~OO~ 125
@ 2000 Bonestroo, Rosene,
Anderlik & Associates~ Inc.
PROJECT !vlEETINGS
SECTION 01330
SUBMITT ALS
p ART 1 - GEl\TERAL
1.01 PROGRESS SCHEDULE
A. Prepare and Sllblnit an estimated progress schedule for the work prior to the
preconstruction meeting.
B. Maintain one copy of the progress schedule at the job site.
C. During construction revise the progress schedule as necessary to conform to the
current staulS of the \-vork. Submit revised copies of the progress schedule, as
required.
1.02 SlJBCONTRACTOR LIST
A. Prepare and submit a complete list of all subcontractors. Include tIle subcontractors
l1ame, address, telephone number, and contact person. Submit after award of contract
and before preconstruction meeting.
1.03 SUBMITTi\L LIST
A. Prepare and sublnit a complete and comprehensive schedule of all submittals
anticipated to be made during the project.
B. Include a list of eac11 item for \vhich contractors drawings, shop drawings, product
data, samples, gllarantees,or other types of submittals are required.
1.04 SHOP DRAvVINGS Ai"\TD PRODUCT D.t\TA
A. Submit fi ve copies of shop drawings and product data required. Three copies \vill be
retained and t\VO copies will be returned to the contractor. Sllbmit a reproducible
sepia of all drawings larger than 11" x 17".
B. Shop drawings and product data shall be submitted with the contractor's stamp of
approval. Shop dra\vings and product data submitted without this st31np will not be
reviewed and will be returned to the contractor for their approval and resubmission.
C. Shop drawings and product data shall be clearly identified as to project, contractor,
manufacturer, specification section and item submitted. Any Sllbstitutions or
deviations from the requirements of the contract dOCllments shall be noted in \vriting.
34-00-125
@ 2000 Bonestroo, Rosenel
Anderlik & Associates. Inc.
01330-1
SUB ivlIIT ALS
D. Make all shop drawings accurately to a scale sufficiently large to show all pertinent
aspects of the item and its method of connection to the work.
E. Clearly mark each copy of product data to identify information being sllbmitted and
delete information which does not apply. Suppiement standard information as
necessary. Show dimensions and other selected characteristics.
F. Maintain one copy of approved shop drawings and product data at the site with the
record drawings.
1.05 TEST REPORTS
A. Submit three copies of all inspections, tests and approvals required in the contract
documents~
1.06 PAYMENT
A. Payment for all submittals shall be incidental to the cost of the project
END OF SECTION
34-00-125
@ 2000 Bonestroo. Rosene,
Anderlik & Associates. Inc.
01330-2
SUB!\1ITI ALS
SECTION 01400
QUALITY CONTROL
PART 1- GENERAL
1.01 TESTING LABORATORY SERVICES
A. Cooperate with the O\vner's selected testing laboratory and all others responsible for
testing and inspecting the work.
B. The Owner \vill pay for initial testing services.
c. When the initial tests indicate noncompliance \vith the contract dOClilnents, all
subsequent retesting shall be perforll1ed by the same testing agency and the costs for
retestiI1g shall be paid by the contractor.
1.02 TESTING STANDARDS
A. Tests shall be provided and accomplished in accordance vvith the standard used as the
reference for the particular material or product, llnless other test methods or criterion
are specified. ill the absence of a reference standard, tests shall be accolnplished in
accordance with applicable ASTM Standards of Test Methods.
1.03 QU_ALIFICATION TESTING
A. In addition to tests specified, should the contractor propose a product, material,
method of assembl)! that is of unkno\vn quality to the Engineer, the Engineer may
require and order suitable tests to establish a basis for acceptance or rejection. Such
tests \vill be paid for by the contractor, or by the subcontractor requesting approval.
11 Standard 11 test reports or reports on "similar" material will not be accepted.
B. The Owner and Engineer reserve the right to require certification or ot11er proof that
the material, assembly, equipnlent or other product proposed to be furnished for this
project is in compliance with any test or standard called for. The certificate shall be
signed by a representative of the independent testing laboratory or a responsible
official of the firm supplying the product, as acceptable to the Owner and Engineer.
The certificate shall be a s\vorn statement and s11a11 be notarized.
c. Any tests required to qualify the contractor or any of their workmen for any phase of
the work, and any test of a n1ethod, system or equipment that may be required by
specification or law to qualify the item lIse, shall be made or talcen without cost to the
Owner or Engineer.
34-00~ 125
@ 2000 Bonestroo, Rosene.
Anderlik & Associates. Inc.
01400-1
QUALITY CONTROL
1.04 INSPECTIONS
A. Should specifications, Engineer1s instructions, laws, ordinances, or any public
authority require any work to be inspected or approved, contractor shall give timely
notice of its readiness for inspection and a reasonable date fixed for such inspection.
If any work should be covered up without appro"val or consent of approving agency,
or Engineer, it must be uncovered for examination at contractor's expense.
EI\TD OF SECTION
34-00-125
@ 2000 Bonestroo. Rosene.
Anderlik & Associates, Inc.
01400-2
QUALITY CONTROL
SECTION 01570
EROSION AND SEDIMENT CONTROL
PART 1 - GENERAL
1.01 SECTION INCLlJDES
A. This work shall consist of temporary measures to control soil erosion and
sedimentation throughout the duration of all phases of work in accordance ,vith the
design and details indicated on the plans and approved in the C011tract.
1.02 REFERENCES
A. Minnesota Department of Transportation "Standard Specifications for Construction;
1988 Edition and the Sllpplemental Specification dated May 2, 1994 (MllDOT Spec):
1. Section 2573 - Telnporary Erosion ControL
B. American Society for Testing and J.\.1aterials (ASTIvl):
1. ASTM D4355 - Test I\1ethod for Deterioration of Geotextiles from Exposure
to Ultra.
2. AST1vl D4491 - Test Methods for y\T ater Pelmeability of Geotextiles by
Permrnitivity.
3. ASTM D4632 - Test Method for Grab Breaking Load and Elongatioll of
Geotextiles.
1.03 SYSTEM DESCRIPTION
A. T'his v.;ork shall consist of temporary measures to control soil erosion and
sedimentation throughout the duration of all phases of \vork in accordance \vith the
design and details indicated on the plans and approved in the contract.
B. Temporary erosion controls are short lived devices such as straw bale structures, silt
curtains, sediment traps or other means to temporarily protect the over-all work prior
to the installation of permanent erosion COlltrols or to supplement the permanent
measures.
C. It shall include furnishing, installing and Inaintaining erosion or sediment control
devices as required in the Plans or as directed by the Engineer.
D. Dl.lst control may be required to prevent dust from drifting to adjacent areas. Use
\vater to control dust if requested by the Engineer orO\vner.
34-00-125
@ 2000 Bonestroo, Rosene.
Anderlik & Associates, Inc.
01570-1
EROSION AND SEDL.\-IENT CONTROL
1.04 MAINTENANCE
A. Contractor is responsible for clean up of any erosion of sediment that may occur -
including street sweeping of mud and debris tracked from the site.
B. Contractor is responsible for the maintenance and cleaning of all temporary erosion
control devices.
C. Contractor shall inspect all silt fences imme.diately after each runoff event and at least
daily during prolonged rainfall. Any required repairs shall be made immediately.
When sediment deposits reach approximately one-half the height of the silt fence, the
sediment shall either be replaced or a second silt fence installed.
D. The Contractor shall inspect and repair any general washouts that occur as a result of
the grading or construction. Restoration shall consist of both grade repair and turt
reestablishment.
. E. The Contractor shall inspect pipe crossings or slope drains after each rainfall that
produces runoff. Any needed repairs shall be made promptly. The slope drain shall
not be crossed by construction equipmellt. The apron shall be inspected periodically
to check for scour. Any needed repairs shall be made promptly to prevent further
damage.
F. The Contractor shall inspect installed diversion mounds after all significant runoff
events. Any damage shall be repaired promptly. Sediment shall be relTIoved frOIn
the channel and restoration lllade as necessary.
1.05 SEQUENCThIG Al\TD SCHEDULThIG
A. General:
1. The Contractor shall submit for approval, the plan of operations required for
accomplishing temporary and permanent erosion control.
2. hlstallation of temporary erosion and sedimentation control measures shall be
coordinated with all phases of work. The Contractor shall complete grading,
finishillg, and installation of permanent or temporary erosion controls on a
section-by-section basis. He shall also establish permanent turf in accordance
with Section 02920 - LAWNS AND GRASSES to prevent excessive soil
erosion.
B. Install silt fence and bale checks prior to starting any construction operations, which
might cause any sedimentation or siltation.
c. Silt fence shall be removed, as determined by the Engineer, after the slopes and
ditches have been stabilized and turf developed to the extent that future erosion is
34-00-125
@ 2000 Bonestroo, Rosene.
Anderlik & Associates. Inc.
01570-2
EROSION AND SEDL\1ENT CONTROL
unlikely. IYlaterials remaining after removal shall become the property of the
Contractor and shall be disposed of off the construction site.
PART 2 - PRODUCTS
2.01 SILT FENCE
A. Geotextile Fabric: Either \voven or non-woven polyester, polypropylene, stabilized
nylon, polyethylene or polyvinylidene chioride.
1. C.riteria:
I Property I Test Method I Minimum Requirement I
--
Grab Strength* ASTM-D-4632 100 Ibs
Elongation * ASTM-D-4632 150/0 min. to 50% max. at
45 Ibs
Pennitivity i\STM -D-4491 0.01 see
Equivalent Opening Size CW-02215-77 20 to 50 (coarse soils)**
50 to 140 (fine soils)**
Width 36 inches
Ultraviolet Resistance ASTIvl-D-4355 90%
*
12" per min. strain rate
Coarse soils \vith less than 50 percent of the particles passing through a #200 sieve, fine soils
with greater than 50 percent of the particles passing through a #200 sieve.
**
The Contractor shall furnish the Engineer, at the time of delivery of the
geotextile fabric, a manufacturer's Certificate of Compliance that the
geotextile fabric as furnished meets the above reqllirernents.
2. The geotextile fabric shall be furnished in a wrapping, which will protect the
fabric from ultraviolet radiation and from abrasion due to shipping and
hauling. The geotextile is to be kept dry until installed.
B. Posts: 2-inch by 2-inch diameter wood posts or standard steel fence posts \veighing
not less than 1.33 pounds per lineal foot, with a minimum lengtll of 30 inches plus
burial depth.
34-00-125
@ 2000 Bonestroo. Rosene,
Anderlik & Associates. Inc.
01570-3
EROSION AND SEDI1vlENT CONTROL
PART 3 - EXECUTION
3.01 INSTALLATION
A. Silt Fence:
1. Silt fence shall be erected prior to starting any construction operation, which
might cause any sedimentation or siltation to be carried a\vay from the project
site. Silt fence shall be installed on the contour and constructed so tllat flow
cannot bypass the ends. If the silt fence is longer than 600 feet, it shall be
constructed in separate independent units, with each unit having a length less
than 600 feet.
2. Silt fences may be constructed with or without supporting fences such as
snow fellces or wire mesh fences. If support fences are included, they shall
be strong ellough to withstand the load from ponded water and trapped
sediment. The support posts shall be spaced at 8 feet or less, and shall be
driven at least 2 feet into the ground.
3. When a silt fence is installed without a supporting fence, the posts shall be
spaced at 4 feet or less and be placed or driven at least 30 inches into the
ground.
4. For all installations, the fabric shall be anchored in a trench dug on the up-
slope side of the posts. The trench should be at least 6 inches deep and 6
inches wide. The fabric shall be laid in the trench, which is backfilled and
compacted.
5. The filter fabric shall be furnished in a continuous roll to avoid splices.
When a splice cannot be avoided, it shall be made at a fence post. The fabric
shall be overlapped 6 inches, folded over and securely fastened.
6. All silt fences shall be inspected immediately after each runoff event and at
least daily during prolonged rainfall. Any required repairs shall be Inade
immediately. When sediment deposits reach approximately one-half the
height of t~e silt fence, the sediment sllall either be replaced or a second silt
fence installed.
7. Silt fence shall be removed, as determined by the Engineer, after the slopes
and ditches have been stabilized and turf developed to the extent that future
erosion is unlikely. Materials remaining after removal shall become the
property of the contractor and shall be disposed of off the construction site.
3.04 ME AS URE 1\1E NT AND PAYMENT
A. Payment for silt fence shall be on a lineal foot basis.
END OF SECTION
34-00-125
@ 2000 Bonestroo. Rosene,
Anderlik & Associates. Inc.
01570-4
EROSION AND SEDHvlENT CONTROL
02108. FULL DEPTH RECLAlvIATION
Specific and General Requirements
2108.1. DESCRIPTION: Under these project specifications the existing bituminous sutfacing and a
portion of the existing base material will be reclaimed and the material will be used in the parking lot
reconstruction process as aggregate backfill material.
2108.3. CONSTRUCTION REQUIREMENTS: This work shall consist of the creation of a
stabilized base course composed of a mixture of the existing bituminous pavement and some existillg
subgrade material. The manufacture of the stabilized base course shall be done by reclamation
equipment that pul\'erizes and blends the existing pavement and sub grade materials in place. The
process which results in a stabilized base course, shall be accomplished in accordance \vith these
specifications and conform to the lines and grades shown on the plans as established by the Engineer.
At the time tIle Proposal is submitted for this work the Contractor shall specify the equipment to be
used for the reclamation process. Contractors are required to state make, model and year of the
machine they will use for this process. The equipment used must be hydrostatically driven \vith
pneumatic tires, have cOlnputerized controls, and must be capable of cutting up to a 16 inch depth in
one pass.
The depth of pavelnent to be reclaimed is anticipated to be about 3 to 4 inches. TIle depth of the
existing aggregate is anticipated to be 12 inches. The depth to be reclaimed is anticipated to be 8 to
10 inches.
The pulverized n1aterial shall conform to the following gradation for salvaged reclaimed bitun1inous
material:
Sieve Size
Percent Passing
1.5"
100%
95-1000/0
0-500/0
0-12 %
111
#40
#200
Salvage Aggregate Base Material: Refer to section 02720. Defined as handling of the reclaimed
bituminouslbase material generated from the full depth reclamation operation. This materiai will be
used in the as a base material prior to paving. The Contractor may elect to \vindrow, stockpile or
temporarily compact the reclaimed material in place prior to placement. Material shall be shaped,
graded and compacted to within 0.05' of finished base elevation.
All reclaimed material shall be compacted by the Specified Density Method as outlined in Mn/DOT
Spec. 2211.3. All sections of parking lot where reclaim material is being placed shall be completed
and satisfactorily compacted prior to the end of the \vork day.
34~OO~ 125
@ 2000 Bonestroo1 Rosene,
Anderlik & Associates. Inc.
2108-1
FULL DEPTH RECLAMATION
2108.4. METHOD OF MEASUREMENT: The process of reclamation and placement as described
herein shall be measured on the basis of square yards based on the width and length of parking lot
pavement actually reclaimed.
2108.5. BASIS OF PAYMENT: Full depth reclamation shall be paid for by the square yard.
END OF SECTION
34-00-125
@ 2000 Bonestroo, Rosene,
Anderlik & Associates, Inc.
2108-2
FULL DEPTH RECLA1vlA TION
SECTION 02225
REMOV ALS
PART 1 -GEl\TERAL
1.01 SECTION INCLUDES
A. Removal and Disposal of the Following Items:
1. Pavement.
2. Fencing.
3. Concrete sidewalk, curb al1d gutter.
4. Gutters at roof drains.
5. Storm drainpipe and structures.
6. Water service.
B. Salvaging and Reinstalling of the Following Items:
1. Signs.
2. Fencing.
1.02 REFERENCES
A. Minnesota Department of Transportation, "Standard Specifications for
Construction", 1988 Edition alld the Supplemental Specification dated May 2,
1994 (MnDOT Spec.):
1. Section 2104 - Remo'ling 1vliscellaneous Structures.
1.04 DEFINITIONS
A. Remove: To take away, eliminate or rernove from the project site by any method
selected by the Contractor and to dispose of material.
B. Salvage: To disil1antle, disassemble, or remove carefully and without damage so
the item can be re-assembled, replaced or reused in a workable condition eqllal to
that existing before removal.
34-00~ 125
@ 2000 Bonestroo, Rosene,
Anderlik & Associates, Ll1C.
02225-1
REMOVALS
1.05 REGULATORY REQUIREMENTS
A. MnDOT 2104.3C is modified as follows:
1. All materials designated for removal shall be disposed of outside the
project area at sites to be selected by the Contractor.
2. All materials designated for salvage shall be stockpiled or temporary
stored on sites to be provided by the Contractor.
1.06 SCHEDULING
A. Prior to starting work, SUblnit for review by the Engineer, and approval by the
Owner, a schedule showing the commencement, order, and completion dates of
the various parts of this work.
B. Fill holes or depressions resulting from removal or salvage that occur more than
24 hours prior to utility or street construction.
C. Provide temporary surface restoration for traffic continuity where removal or
salvage operations are cOlnpleted \vithin streets, driveways or parking lots more
than 24 hours in advance of utility or street construction.
PART 2 - PRODUCTS
Not Used
PART 3 - EXECUTION
3.01 GENERAL
A. The Contractor shall be responsible for disposal of all items removed, except for
those items identified to be salvaged or recycled. Said disposal sllall be in
accordance with all laws, regulations, statutes, etc.
B. Denlo1ition shall be performed viithout damage to adjacent retained work. Where
such work is damaged, the Contractor shall patch, repair, or otherwise restore
same to it's original condition, at no expense to the Owner.
C. All demolition debris shall be removed from the area of \vork as often as
necessary, but not less than at least once at the end of each work day. Debris shall
be placed in approved containers to prevent the spread of dust and dirt.
D. Execute the work in a careful and orderly manner, with the least possible
disturbance to the public and occupants of buildings.
34-00-125
@ 2000 BonestroQ, Rosene,
A.nderlik & Associates, Inc.
02225-2
REIvl OV .A.LS
3.02 PROTECTION
A. Take all necessary precautions to adequately protect personnel and public and
private property in the areas of work. All site fencing shall be in place prior to the
start of any removal work.
B. All street signs, traffic control signs, guy \vires, mail boxes, posts, wood fence,
etc. which may interfere with construction shall be removed, stored safely, and
replaced.
C. Approved barriers or warning signs shall be provided as necessary.
D. Provide and maintain temporary protection of existing structures designated to
remain where removal \vork is being done, connections made, materials handled,
or equipment moved.
E. Do not close or obstruct \valkways or roadways. Do not store or place materials
in passageways, or other means of egress. Conduct operations with minimum
traffic interference.
F. Take reasonable precautions to limit damage to existing turf.
G. Holes or depressions created by removals shall not be left open for more than one
day. Any hole within ten (10) feet of side\valks shall be filled, suitably rnarked or
covered immediately.
3.03 DEMOLITION A.t~D REMOVALS
A. Sawing Pavement:
1. Concrete pavement shall be sawn alo11g .the removal line to a full depth of
the thickness of the concrete prior to removal of the pavement
2. Bituminolls pavement shall be sa\vn along the removal line to aminilllUlTI
depth of three i11ches prior to breaking off the pavement
B. Concrete and Bituminous Surfacing, Concrete Curb and Gutter:
1. Remove in accordance with 1vIllDOT Spec. 2104.3B, except as modified
below.
2. SaWcllt bituminous surfacing to full depth at the limits of partial removal,
prior to that renloval, unless otherwise approved by the Engineer.
3. Sawcut concrete pavement and concrete base prior to mechanical
pavelnent removal eqllipment. Remove concrete in such a manner that the
relnaining pavement is not damaged.
34-00-125
@ 2000 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02225-3
REMOVALS
4. Prior to restoring trench areas, the edges of the trench shall be trimmed
back to a vertical face on a straight line, which is parallel with the
centerline of the trench.
5. Avoid disturbance to any material beyond the limits required for new
construction.
6. When removing existing curbing and driveways the Contractor shall not
disturb any material beyond the limits required to form for new
construction (assumed 12" maximum from the back of ne\v work and 6"
beyond the edge of new driveways).
C. Fence:
1. Remove chain linlc fence and posts along the east property lille for the
installation of a new 12-foot gate.
D. Water Service at Public Works Building (Backyard):
1. Remove existing 2 Y2" pve pipe as reqllired to install new service.
2. Remove curb and gutter and concrete pad as required to remove existing
\vater service and install neVl service.
E. Manholes, Catch Basins, and Sections of Existing Storm:
1. Remove all structures and piping as shown on the plans. Remove all
piping required for new construction.
2. Cap all utilities and piping encountered and not removed. Piping left in
place will be allo\ved as directed by the Engineer.
F. Gutter at Roof Drains:
1. Remove Concrete Gutters in the planter below roof drains by the Public
\Varks offices.
2. Gutters will be replaced in the existing configuration after the installation
of 6-inch Roof Drain pipe.
3. New Gutters will incorporate Roof Catchment inlet.
34-00-125
@ 2000 Bonestroo. Rosene,
Anderlik & Associates. Inc.
02225-4
RE!\10V ALS
G. StarIn drain pipe:
1. Remove pipe as required for the construction of new structures and the
connection to existing structures.
2. Bulkhead abandoned pipe.
3.04 SALVAGE AND REIN"STALL
A. Signs:
1. Exercise reasonable care against damage to in place signs during storage
and installation.
B. Fence:
1. Salvage and reinstall chain link fence one west end of parking lot as
required for the installation of the storm sewer and parking lot.
3.05 FIELD QUALITY CONTROL
A. Items damaged during removal or salvaging operations shall be replaced with ne\\'
material of equal type and quality of the damaged item when it was new.
B. Items reinstalled shall be of the saIne shape, dimension, location and quality of
the original item prior to construction.
3.06 MEASUREMENT MTD PAYMENT
A. Bid Items have been provided for relllovaI alld salvage items. Measurement will
be based upon the units as listed below for itellls removed complete as specified.
No measurement will be made of any removals that are not required nor of any
removals that are specifically designated. The actllal quantity rellloved multiplied
by the appropriate Unit Prices will be cOlnpensation in full for all work and costs
of the following items.
1. Remove Concrete Curb and Gutter: Per lineal foot without regard to type.
2. Salvage and Reinstall Fence: Per lineal foot. Bid items are provided for
chain link and split rail fence.
3. Salvage and Reinstall Signs: Incidental to the Total Base Bid.
4. Relnove and Replace Gutters at Roof Drains: Per each.
5. Remove Fence and Install Gate: Refer to Section 02830.
34-00-125
@ 2000 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02225-5
REMOVALS
7. Remove Storm Pipe: Incidental to the Total Base Bid.
8. Remove Bituminous Pavement: Per square yard without regard to
thickness.
9. Sawing bituminous pavement: Per lineal foot.
10. Sawing concrete pavement is incidental to pavement removal.
11. Remove Concrete pavement: Per square foot without regard to thickness.
Includes sidewalk and driveway pavement.
12. Bulkhead pipe: Per each. Includes the removal of existing pipe.
13. Removal of Water Service: Incidental to the installation of the new water
service line. Remo\'al of pavement, curb and gutter, and concrete
pavement as required for the installation of the water main will be paid
under the respective bid items.
E1\TD OF SECTION
34-00-125
@ 2000 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02225-6
REl\1 0 V ALS
SECTION 02230
SITE CLEARING
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. Removing and disposing of trees, brush, stumps, roots, windfalls, and other plant
life.
B. Tree trimming/pruning.
1.02 REFERENCES
A. Minnesota Department of Transportation "Standard Specification for
Constluction", 1998 Edition. and the Supplement Specifications dated May 2,
1994, (MnDOT Spec.)
1. MnDOT Spec. 2101 - Clearing a11d Grubbing.
1.03 DEFINITIONS
A. Brush: All bushes, shrubs, and other vegetation that can be cut with a brush
scythe or mowing Inachine, including small isolated trees having a diameter of 4
inches (100 mm) or less at a point 2 feet (600 mm) above the ground surrace.
B. Clearing: Cutting and removing trees, shrubs, bushes, vvindfalls, and other
vegetation in the designated areas.
C. Grubbing: Removing and disposing of stumps, roots, and other remains in the
designated areas.
1.04 SEQlJENCING AND SCHEDULING
A. Complete before or sufficiently ahead of on-going rough grading, excavation,
backfill, and compacting for utilities.
B. The drawings do not specifically show all trees to be reinoved or trallsplanted.
All trees in the area of the pond excavation and fill must be removed.
C. Protect specimen trees close to work that are designated to remain, but may be
damaged by work.
34-00-125
@ 2000 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02230-1
SITE CLEARING
PART 2 - PRODUCTS
Not Used
PART 3 - EXECUTION
3.01 GENERAL
A. Review removals in the field with the Engineer prior to doing work. Clearing
limits clearly marked by the Engineer.
3.02 CLEARING AJ."\TI) GRUBBIJ\fG
A. As directed by the Engineer, trim and paint trees that are to be saved, but interfere
Vvith the proposed construction. Perform all clearing and gnlbbing in accordance
with MnDOT Spec. 2101.
B. Clearing Trees: Trim and cut into lengths of 6 to 8 feet (1.8 ill to 2.4 m).
1. Including all branches 6 inches (150 mm) in diameter and greater.
C. Clearing Brush: Cut even with the ground surface.
D. Grubbing: Remove stumps and roots and other remains from all cleared areas.
E. All depressions resulting from the grubbing operations shall be backfilled with
suitable material and compacted.
3.03 DISPOSAL
A. Dispose of all timber and debris such as stumps, branches, brush, and roots,
outside the project area at a site selected by the Contractor, except for trees and
logs to be salvaged.
B. Disposal site should be a properly designated landfill area as determined by
appropriate governmental agencies, or lands under direct control of the
Contractor.
3.04 PROTECTION
A. Conduct operations so as not to damage surrounding private property.
B. Protect trees intended to be saved from injury or defacement during operations.
1. Restrict widths of utility trenches.
34-00~ 125
@ 2000 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02230- 2
SITE CLEARING
24 Provide protective bracing, sheeting, or box to insure safe work conditions
as incidental to contract.
C. Exercise care to keep salvaged material as clean as possible during operations.
D. Install temporary fencing at the construction limits prior to any constluction
activities in order to protect vegetation.
3.05 MEASUREMENT AND PAYMENT
A. A bid item has been provided for clearing and grubbing. Measurement will be by
the lump sum for the entire project area. Payment will COllstitute compensation in
full for all removal and disposal costs.
B. WindfalllDeadfall shall be incidental to the project, \vith no direct compensation.
C. Shrubs will not be measured as Clearing and grubbing. Removal and disposal of
bnlsh shall be incidental and be included in the payment for cleari11g and
grubbing.
D. i\ll other \vork and costs of this section shall be incidental to the project.
END OF SECTION
34~OO-125
@ 2000 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02230- 3
SITE CLEARING
SECTION 02280
ADJUST MISCELLANEOUS STRUCTURES
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. Perform Adjllstment of:
1. Manholes.
2. Catch Basins.
3. Miscellaneous Structures.
B. Remove and replace frame and casting.
1.02 REFERENCES
A. American Society of Testing and Materials (ASTM):
1. A48 - Specification for Gray Iron Casting.
2. A240 - Specification for Heat - Resisting Chromium - Nickel Stainless
Steel Plate Sheet, and Strip for Pressure Vessels.
3. C6 - Specification for Normal Finishing Hydrating Lime (Mortar).
4.C141 - Specification for Hydraulic Hydrated Lime for Structural Purposes
(Mortar)
5. C150 - Specification for Portland Cement (Concrete Ril1gs/Mortar).
6.C923 - Specification for Resilient Connectors Between Reinforced
Concrete Manhole Structures, Pipes, and Materials.
7. D1248 - Polyethylene Plastics Molding and Extrusion Materials.
8. F593 - Specification for Stainless steel bolts, Hex Cap Screws, and Studs.
9. F594 - Specification for Stainless Steel Nuts.
B. State of Minnesota Department of Transportation "Standard SpecificatiollS for
Construction", 1988 Edition, and the Supplelnents Specifications dated May 2,
1994 (MnDOT Spec.):
34-00-125
@ 2000 Bonesrroo, Rosene,
Anderlik& Associates, Inc.
02280-1
ADJUST 1vIISCELLAi\TEOUS
STRUCTURES
1. Section 3733 - Geotextiles.
1.03 DEFINITIONS
A. Manhole/Catch Basin Adjustment: l\. change in rilll elevation accomplished
through the addition or removal of adjustment rings only. Adjustment does not
include the addition or removal of sections from the structure.
1.04 SUBMITTALS
A. Product Data: Submit manufacturer's descriptive literature and product
specifications for each product.
B. Submit manufacturer's descriptive literature and product specifications for
substitute castings requested by the Contractor.
1.05 SEQUENCING AND SCHEDULfi\lG
A. The Contractor, Engineer, and Owner shall inspect all existing manholes, catch
basins, and gate valve boxes vvithin the project limits prior to begin11ing
construction.
B. The Owner is responsible for the removal of any foreign material found in the
existing structures prior to construction. The Contractor is responsible for
removing any foreign material that may enter the structLlres during the
construction period.
PART 2 - PRODUCTS
2.01 ADJUSTfi\lG Rfi\lG
A. Concrete:
1. Size to match cone or opening in top slab.
2. Concrete Compressive Strength: Minimum 3000 psi.
3. Reinforcing: Single hoop 8 gauge steel \vire.
4. Thickness: Minimum 2-inch, maximuIll 4-inch.
2.02 ADHESION MATERIALS
A. Rarn-Nek material, or equal.
B. Mortar:
34-00-125
@ 2000 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02280- 2
ADJUST MISCELLANEOUS
STRUCTURES
1. Standard Portland Cement: Type I, AST!\1 elSO.
2. Normal Finishing Hydrated Lime: ASTM C6.
3. Hydraulic Hydrated Lime for Structural Purposes: ASTM C141.
4. Mix Proportions: One part cement to three palts mortar sand; Lime may
be added to mixture: maximum amount 15% by volume.
2.03 CASTINGS
A. Manhole and Catch Basin Frames and Covers:
1. Requirement: ASTM A48.
2. Material: Class 35 cast iror!. Best grade. Free froIn injurious defects and
flaws.
3. Finish: Coal tar pitch varnish.
4. Finish Preparation: Sandblast.
5. Machine cover and frame contact surface for non-rock.ingprotection.
6. Type and Style: As shown on dra\vi11gS. Covers without grate openings
stalnped with HSA1~ITARY SEWER" or "STORM SEWER" as
appropriate. Use 2-inch letters.
2.04 GEOTEXTILE
A. General Requirement: MnDOT Spec. 3733 - Type V.
PART 3 -EXECUTION
3.01 GENERAL
A. The necessary vertical alignment will be determined by the Engineer, and
generally as indicated on the schedule of adjustments.
B. Where existing frame is within 0.10 feet of plan grade, no adjustment is to be
made.
C. The concrete or turf shall be either lowered or raised to put the finished grade and
frame at the same grade.
34-00-125
@ 2000 Bonestroo, Rosene,
Anderlik& Associates. Inc.
02280- 3
ADJUST 1vIISCELLANtOUS
STRUCTURES
3.02 ADJUSTMENT MANHOLE AND CATCH BASm FRAME
A. Remove all dirt, deblls, dust, and other deleterious material from surface prior to
placement of first adjusting ring.
B. Concrete Adjusting Ring:
1. Mortar on top and bottom surfaces of all concrete adjusting rings; between
surface of top slab or cone and bottOITI ring; between surface of top ring
and casting; on entire surface of area of ring with no gaps.
a. Mortar Thickness: 14 to ~-inch.
2. No shims of any material allowed.
3. Required cross slope of casting to be achieved by varying thickness of
mortar.
4. Do not plaster the inside surface of rings.
5. Wipe clean, all excess mortar from the joints inside all rings and frame.
6. Remove all mortar spills from the structure.
7. Minimum of two, rnaxilnum of five adjusting rings allowed.
3.03 FIELD QUALITY CONTROL
A. For adjustments made within bituminous sUlfaced areas, any settlements of the
bitulninous surfacing below the rim of the adjustment structure will require
removal and replacement of the bituminous sUlfacing at the Contractors expense.
B. The Contractor is responsible for the protection of all existing structures during
the course of the work.
c. Secure manholes a11d stluctures immediately after completion or before
suspension of operations at the end of \vorking day with castings or suitable
alternative device.
3.04 METHOD OF MEASUREMENT Ai\fD PAYMENT
A. Ne\v Manhole and Catch Basin Adjustment: Measurement of adjustmellt of new
manholes and frames will not be made. Adjustment of the casting on neVi
stluctures is incidental to the bid unit price for furnishing and installing the
strllcture.
END OF SECTION
34-00-125
@ 2000 Bonestroo, Rosene!
Anderlik & Associates, Inc.
02280-4
ADJUST MISCELLANEOUS
STRUCTURES
SECTION 02312
SUB GRADE PREPARATION
PART I-GENERAL
1.01 SECTION lNCLUDES
A. Final preparation or subgrade preparation, conslstlng of grading, shaping,
compacting of subgrade prior to placing a base or surface course.
B. Finish grading of trench backfill for restoration and landscaping.
1.02 RELATED SECTIONS
A. Section 02315 - Excavation and Fill.
B. Section 02720 - Aggregate Base Course.
C. Section 02770 - Concrete Curb and Gutter.
1.03 REFERENCES
A. Minnesota Department of Transportation "Standard Specifications for
Construction", 1988 Edition, and the Supplemental Specifications dated May 2,
1994, (MnDOT Spec).
1. MuDOT Spec. 2105 - Excavation and Embankment
2. MnDOT Spec. 2111 - Test Rolling.
3. MnDOT.Spec. 2112 - SubgradePreparation.
PART 2 - PRODUCTS
Not Used
PART 3 - EXECUTION
3.01 GENERAL
A. Subgrade preparations shall be performed to produce the required density, grade,
and cross-section.
34-00- 125
@ 2000 Bonestroo~ Rosene,
Anderlik & Associates~ Inc.
02312-1
SUBGRADE PREPARATION
3.02 PREPARATION
A. Inspection of Subgrade by test rolling conforming to MnDOT Spec. 2111 or as
modified herein:
1. The equipment used for test rolling shall be a Tandom Tnlck with a gross
weight of 45,000 pounds.
2. The road bed will be considered unstable if yielding and rutting is greater
than 1 Yz inches.
3.03 COMPACTION
A. Conform to MnDOT Spec. 2105.3G or as modified herein:
1. For the Specified Density Method, the Engineer will sample and test the
soils to determine the Maximum Density and Optimum Nloisture.
2. Density and moisture tests \villbe taken on the compacted subgrade, at the
location and testing rates designated by the Engineer.
3.04 FINISH OPERATIONS
A. Subgrade tolerance shall conform to the following:
1. l~ot vary by more than 0.05 feet above or below the prescribed elevation at
anyone point where a measurement is lnade.
3.05 MEASUREMENT AND PAYMENT
A. Sub grade Preparation shall be incidental to the placement of the aggregate base
and include all work and material to prepare the subgrade prior to the placement
of aggregate.
B. Testing Rolling shall be incidental.
END OF SECTION
34-00-125
@ 2000 Bonesrroo. Rosene.
Anderlik & Associates, Inc.
02312-2
SUBGRADE PREPARATION
SECTION 02315
EXCA V A TION At'\ID FILL
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. Construction of excavations, embankments, and fill materials \vithin the project
area.
1.02 RELATED SECTIONS
A. Section 02312 - Subgrade Preparation.
1.03 REFERENCES
A. Minnesota Department of Transportation "Standard Specifications for
Construction", 1988 Edition and the Supplement Specification dated May 2,
1994, ( MnDOT Spec).
1. MnDOT Spec. 2105 - Excavation and Embankment.
1.04 SITE CONDITIONS
A. Contractors shall make necessary ~ite visits prior to bidding to determine the level
of work required to their satisfaction.
B. Protect existing roads, fences, trees, utilities and other features from damage from
work of this section.
C. In the event of damage, immediately make all repairs and replacements necessary
subject to the approval of the Engineer and at no additional cost to the Owner.
PART 2 - PRODUCTS
2.01 MATERIALS
A. Topsoil: Standard topsoil for general use as a tun growing Inedium, conforming
the requirements of MnDOT Spec. 3877, Type A, Topsoil.
1. Suitable on site material Inay be used for Standard Topsoil, subject to
approval by the Engineer.
34-00-125
@ 2000 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02315-1
EXCA V ATION AND FILL
2. This material shall be used for the following:
a. Minimum 3 inch depth topsoil on all areas which are proposed to
be seeded.
B. Common Excavation: Includes all excavation, elnbankment, grading, and shaping
required to construct elevations and contours as shown on the plans.
1. In the parking area Common Excavation includes all excavation to the
sub grade after Aggregate base is salvaged.
2. In the pond area Common Excavation includes all excavation required to
construct elevations and contours as shown on the plans.
PART 3 - EXECUTION
3.01 TOPSOIL STRIPPING A.ND STOCKPILING
A. Topsoil shall be completely stripped from the entire construction site and
stockpiled at on-site locations approved by the Engineer.
B. Install silt fencing and any other erosion control devices necessary to prevent
eroded materials from entering storm sewer system or adjacent areas.
3~02 SITE GRADmG
A. Site Excavation: Cut, fill and grade site to elevations and contollrs shown on the
plans, with allo\vances for pavements, Class 5 aggregate, topsoil, and structures.
B. Slope grades to insure both temporary and pelmanent drainage.
C. Subgrades beneath all pavement areas shall be graded to a tolerance of 0.05 ft.
The Contractor shall test roll all pavement areas to verify subgrade stability in the
presence of the Engineer. The Contractor shall furnish a loaded dual axle dump
truck for the test rolling operation. Unstable areas shall be corrected by
replacement ~lith aggregate base.
D. Subgrade preparation shall include shaping alld compacting existing lnaterials
prior to placement of granular borrow or aggregate. The final subgrade shall be
approved by the Engineer prior to importing aggregate base or the respreading of
salvaged aggregate base.
34-00-125
@ 2000 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02315-2
EXCA V A TION AND FILL
3.03 ESTIMATED QUANTITIES
A. The proposed earthwork in the parking lot will generate an excess of material,
which must be removed from the project site and transported to a site selected by
the Contractor.
1. The following quantItIes are estimated for the parking lot. Actual
quantities used will be measured by cross-section.
a. Salvage Aggregate Base: 440 CYs
b. Common Excavation to be hallled off site: 300 CYs
2. The follo\ving quantities are estimated for the pond construction.
a. Common Excavation: 4500 CY s. This quantity is not guaranteed
and should be reviewed by the Contractor prior to the bid
according to the contours shown on the plan.
b. Areas of fill \vill be adjusted to balance cuts and fills. The pond
will be excavated to the proposed COlltours.
3.04 MEASUREMENT Al\TD PAYMENT
A. A bid item has been provided for Common Excavation for the parking lot under
Part 1 of the proposal. Measurement alld payment will be b)' volume in cubic
yards of Inaterial in its original position, based on cross sections performed by the
Engineer, and computed by the average end area method using the original and
final cross sections. This item represents payment for Excavation to achieve
design grades and for the disposal of the material off-site.
B. A bid item has been provided for COffilllon Excavation for the pond under Part 2
of the proposal. Measurement and payment will be by the lump sum. This item
represents payment for Excavation to achieve design grades for the entire area
outside of the Public Warks yard (paved area).
B. The salvaging of existing topsoil shall be incidental to the Total Base Bid. Select
Topsoil Borrow shall be measured by the CY (LV). PaYluent will be based on the
CY in place.
END OF SECTION
34-00-125
@ 2000 Bonestroo, Rosene,
Anderlik & Associates. Inc.
02315-3
EXCA V A TION AND FILL
SECTION 02320
TRENCH EXCA V ATION AND BACKFILL
p ART 1 - GEl\;TERAL
1.01 SECTION J1\fCLUDES
A. Trenching requirements for undergroulld pIpIng and appurtenances including
requirements for excavation, backfill and compaction.
1.02 RELATED SECTIONS
A. Section 02630 - Storm Drainage.
B. Section 02315 - Exca\'ation and Fill.
1.03 REFERENCES
A. Minnesota Department of Transportation "Standard Specifications for
Construction", (MnDOT).
1. Section 2105 - Excavation and Embankment.
2. Section 2451 - Stlucture Excavations and Backfills.
B. American Society of Testing 1vIaterials (ASTI\Il):
1. D2321- Recomlnended Practice for Ullderground Installation of Flexible
Tllermoplastic Sewer Pipe.
2. D698 - Standard Moisture Density Relationship of Soil.
1.04 DEFJ1\fITIONS
A. Bedding: The soil material adjacent to the pipe which makes contact with the
pipe foundation, walls of the trench and upper level of backfill. The purpose of
bedding is to secure the pipe to tlue line and grade and to provide structllral
support to the pipe barrel.
B. Foundation: Soil material beneath the pipe bedding.
C. Improved Foundation: FOllndation provided by importing material from sources
outside the project limits. Required when foundation is soft or unstable.
D. Pipe ZOlle: That part of the trench below a distance of one foot above the top of
the pipe.
34-00-125
@ 2000 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02320-1
TRENCH EXCA V A TION AND BACKFILL
1.05 PROJECT CONTIITIONS
A. Known existing underground utilities are sho\vn on the drawings in a general
way. The Owner does not guarantee the locations as shown on the drawings. The
Contractor shall anticipate variations in both the vertical and horizontal locations
of underground 1.1tility lines from those shown on the drawings.
Be Uncover utilities and verify both horizontal and vertical alignments sufficiently in
advance of construction to permit adjustn1ents in the work.
C. Contractor to notify Gopher State OIle Call before starting construction in a given
area, reqllesting utility locations in the field.
1.06 SEQlJENCING Ai'ID SCHEDULING
A. Determine location of existing utilities and identify conflicts before excavating
trench for pipe installation.
B. Uncover utilities and verify both vertical and horizontal alignments sufficiently in
advaIlce of construction to permit adjustments in the work.
C. Backfill and compact all trench excavations promptly after the pipe is laid.
1.07 GUARA.NTEE
A. Trench settlements which occur during the guarantee period that are greater than 1
inch as measured by a 10 foot straight edge will be repaired in a manner that is
acceptable to the Owner at the Contractor's expense.
PART 2 - PRODUCTS
2.01 IMPROVED PIPE FOUT\TDATION
A. Comply \vith MnDOT Spec. 3149.2H Modified.
1. Crushing requirements: Not less than 50% of the material, by weight, that
is retained on the No.4 sieve shall have one or more crushed faces.
PART 3 - EXEClJTION
3.01 EXAMINATION
A. Prior to construction, inspect existing utility structures and surlace features and
document condition.
B. Verify with the Engineer that all permits necessary to do the work are obtained.
34-00-125
@ 2000 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02320-2
TRENCH EXCA.VATION AND BACKFILL
3.02 PREPARATION
A. Call Utility Owners to field mark their utility locations.
B. Protect as necessary surface featllres such as utility poles, trees, structures,
pavement, etc. that are not designated on the plans to be removed.
C. Notify Utility Companies of progress schedule so they can accomplish relocations
and removals that they have agreed to perform.
D. Complete temporary removal or relocation of surface features such as fences,
s11rubs, and signs.
E. Strip off existing topsoil from \vithin the trench excavation limits and stockpile.
Separate vegetative strippings from topsoil and dispose of appropriately.
F. Crossing Under Existing Utility Lines:
1. Use extreme care when excavating in the vicinity of Llnderground utility
lines to avoid damage to protective coatings or surfaces.
2. "'There possible and as authorized by the utility, temporarily remove the
utility line, install the new pipe al1d reinstall the utility line.
3. V/here existing line cannot be removed or is not feasible to remove,
securely support, excavate under, backfilll.lnder and arollnd the utility line
to 100 percent standard Proctor density.
4. Report and repair damaged lines prior to backfilling trench.
3.03 CONSTRUCTION
A. Excavation:
1. Trench Construction:
a. Excavate trench to alignment and grade shown on the dra\vings.
b. The trench \vidth at the surface may vary and depends on the depth
of trench and nature of the excavated material encountered.
Ho\vever, it shall be of ample \vidth to permit the pipe to be laid
and jointed properly and the backfill to be placed and compacted
properl y .
34-00-125
@ 2000 Bonestroo. Rosene,
Anderlik & .A.ssociates, Inc.
c. Correct any part of the trench that is inadvertently excavated below
grade with approved material compacted to 100% of standard
Proctor density.
02320-3
TRENCH EXCA V A TION AND BACKFILL
2.
'),
.,J.
4.
5.
34-00-125
@ 2000 Bonestroo, Rosene,
Anderlik & Associates, Inc.
d. Brace, shore, or sheet trench and provide drainage. Comply \vith
applicable State Regulations relating to industrial safety to a safe
angle of repose. Angle of repose may be no iess than that required
by the Accident Prevention Division of the State Industrial
Commission or the requirements of the OCcllpational Safety and
Health Act (OSHA), whichever is most restrictive.
e. Pile all excavated material in a manner that will not endanger the
work or obstruct sidewalks, driveways, gutters, etc.
f. Segregate soils in the excavated material that are not suitable for
trench backfill and dispose of in a manner that is consistent \vith
the requirements specified herein under "Backfill Above Pipe
Zone 11.
g. Dispose of excess excavated ll1aterials off of right-af-ways and
easements in a suitable site selected by the Contractor.
h. Haul materials, other than natural soil materials that are suitable as
backfill material, to an approved landfill as directed by the
Engineer.
Dewater the ground as necessary to excavate the trench and install the
pipe. All pipe and structures shall be laid in a dry condition prior to
backfill. Maintain groundwater level a minimllm of one foot belo\v the
pipe invert. Measure the rate of flow from dewatering pumps at the
beginning of tIle dewatering operation(s) and once per \tveek there after.
Keep a daily log of hours pumped.
Excavate to a sufficient depth to insure adequate foundation \vhen the
bottom of the trench is soft or where, in the opinion of the Engineer,
unsatisfactory foundation conditions exist. Bring excavation up to pipe
grade with thoroughly compacted granular materials meeting the
requirements of In1proved Pipe Foundation Material.
Provide temporary support, remove, relocate or reconstruct eXIstIng
utilities located within the trench excavation. Utility shall designate
method employed. Use particular care and provide compacted fill or other
stable support for utility crossings to prevent detrimental displacement,
rupture or failure.
Excavate to expose existing utilities that cross in close proximity to the
planned pipe line to determine the utilities' exact location sufficiently
ahead of pipe installation to plan for the avoidance of grade conflict.
Measure to determine the utilities' location relative to the planned pipe line
02320-4
TRENCH EXCAVATION AND BACKFILL
location. A deviation from the alignment, grade and location to avoid
conflict may be ordered by the Engineer.
6. Improved Pipe Foundation: When unsatisfactory foundation conditions
exist, excavate to a depth consisting of solid materials. Fill to pipe grade
with thoroughly compacted granular material.
B. Pipe Bedding:
1. Polyvinyl chloride sewer pIpe: Bed pIpe In accordance with ASTM
D2321.
c. Backfill at Pipe Zone:
1. Backfill immediately after pipe is laid.
2. Backfill placed cOlupletely under pipe haunches In uniform layers not
exceeding 4-inches in depth.
D. Backfill above Pipe Zone:
1. Use suitable materials selected from the excavated lnaterials to the extent
available and practical.
2. Suitable materials are mineral soils free of rubbisl1, stumps, branches,
debris, frozen soil, oversize stone, C011crete and bituminous chunks and
other unsuitable material.
3. Place in uniform depth layers not to exceed 12 inches before cOlnpaction.
Complete the compaction of each layer before placing material for the
succeeding layer.
4. Compact each layer by mechanical means until it meets the requirelnents
of MnDOT Specification 2105.3 Fl "Specified Density Method".
Trenches shall be compacted to a minin1um of 95% except to 100% in the
upper 3 feet. If the moisture content of the backfill materials is greater
than 3% above the optimum moisture, compact the materials to a
minimum density of three pounds/cubic foot less than the standard Proctor
curve at that moisture content, except that minirrlum compaction shall be
850/0 of standard Proctor density.
5. The method and means of placement and type of cOlnpaction equipment
used is at the discretion of the Contractor. However, all portions of the
trench backfill must meet minimum specified compaction requirements.
6. Any deficiency in quantity of backfill material (caused by shrinkage or
settlement) shall be supplied at no additional cost to the City.
34~OO-125
@ 2000 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02320-5
TRENCH EXCAVATION AND BACKFILL
7. Excavated material not suitable or required for backfill shall be disposed
of outside of the project limits.
3.04 FIELD QUALITY CONTROL
A. Density Tests: To be pelformed by an approved soils testing firm at various
locations and depths throughout the project as directed by the Engineer. The
Contractor shall cooperate fully and provide assistance as necessary to complete
these tests.
B. Failed density test areas shall be excavated and recompacted until the density
requirements are met.
3.05 ME.ASURE1vIENT AND PAYMENT
A. Trench Excavation: Excavation and backfilling of trench and associated pipe
bedding shall be included in the price of pipe furnished and installed.
B. Density tests: Passing tests: all costs paid by Owner. Failing tests: all costs
charged to and paid by the Contractor.
C. Dewatering al1d Improved Pipe Foundation: No explicit, direct paYlnent is made
for this \vork. Include the costs in the bid unit prices for the pipe or stnlcture
installed.
END OF SECTION
34~OO~ 125
@ 2000 Bonestroo, Rosene,
Anderlik & Associates~ Inc.
02320-6
TRENCH EXCA V A TJON AND BACKFILL
SECTION 02515
WATER SERVICES
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. Water service pipe and all appurte11ances.
1.02 RELATED SECTIONS
A. Section 02320 - Trench Excavation and Backfill.
PART 2 - PRODUCTS
2.01 MN"\TUFACTURERS OF HIGH DENSITY POLYETHYLENE
A. Phillips Driscopipe, Inc.
B. Polypipe Industries, Inc.
C. Chevron Plexco, Inc.
D. Others which meet the reqllirements of this Section.
2.02 PIPE AND FITTINGS
A. General:
1. Type: Solid, Slll00th \vall.
2. Outside Diameter: Nominal Iron Pipe Size (IPS) llnless othervvise noted.
3. Standard Dimension Ratio (SDR): 11 unless otherwise noted.
4. Pressure Rating: 160 PSI@ 730P.
B. Material:
1. Extra-high density black polyethylene.
2. Properties:
a. Density (gmJcc): 0.955 per ASTM D1505.
34-00-125
@ 2000 Bonestroo, Rosene,
Anderlik & Associates, Ine.
02515-1
\V A TER SERVICES
b. Flex 1v1odulus (psi): 133,000 per ASTMD790.
c. ESCR (Failure/hrs): > 5,000 per ASTM D1693.
d. ESCR (Failure/hrs): > 3,500 per ASTM D1248.
e. Tensile Strength (psi): 3,200 per ASTM D638.
f. Elastic Modulus (psi): 110,000 per ASTM D638.
g. HDB (psi): 73.40F per ASTM D2837.
h. HDB (psi): 800 @ 1400P per AST1\1 D2837.
C. Type Classification: Consistent with ASTI\tl D1248, Type III, Class C, Category
5, Grade P34.
D. Cell Classification: 345434C or 355434C as defined in ASTM 3350.
E. Molecular Weight:
1. 250,000 to 1,500,000.
2. Deterlni11ed by Gel Permeation Chromatography procedure.
F. Fittings:
1. Pressure Rating: Same as connected piping.
2. Outside Diameter: Consistent with ASTM F'714 for same sized pipe.
3. 'vVoll Thickness: Consistent with ASTIvl F714 for same sized pipe.
4. Derating: Consistent \vith the manufacturer's written specifications for
pressure rated fittings, clearly labeled on each fitting as such.
5. Quality Control Label: As approved by the manufacturer on each fitting.
2.03 JOINTS
A. Thermal blltt-fusion in accordance with ASTM D2657.
2.04 FABRICATION
A. Pipe and Fittings:
1. Manufacture consistent \vit11 ASTM F714.
3 4~OO~ 125
@ 2000 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02515-2
\VATER SERVICES
2. By same manufacturer.
3. Bends, Tees and Wyes: By mitered construction and of same
class/pressure rating as pressure pipe.
B. Identification:
1. Continuous permanent print line on pipe displaying the following:
a. Manufacturer's name and location.
b. Date of manufacturer.
C. Lot number.
d. Ra\v material supplier.
e. Production shift.
f. ASTM Standard (ASTM F714).
g. Material Designation (PE3408).
2.05 ACCESSORIES
A. Anchor Weights:
1. Construction: As s11own.
2. Hardware: 316 stainless steel.
3. Protective Pads: 1/8" thick Ethylene Propylene Diene Monomer (EPDlvI)
rubber sheet 2 inches wider than weights.
B. Transitions to Dissimilar Pipe at Water Service Ends: Use fittings recommended
by manufacturers to transition to NPC pve or galvanized pipe.
PART 3 -EXECUTION
3.01 INSTALLATION
A. Governing Code: Minnesota Plumbing Code and any local ordinances that lnay
apply.
B. Run service to from buildi11g to yard hydrant assembly as shown on the drawings.
34~OO-125
@ 2000 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02515-3
\VATER SERVICES
c. Water Service Line:
1. Coordinate connection point at building and behind curb at the yard
hydrant as shown on drawings.
2. Provide NPT fitting on each end for future connection to service and
hydrant The Contractor is not responsible to connect the line to the
service or hydrant. Connections \\Till be done by others.
3. Cap line to keep free of dirt.
4. 4' of cover from finished grade. Provide constant slope from the buildillg
to the hydrant with no high or low points.
5. Terminate both pipe ends 3 feet above finished grade or as directed to
provide efficient connections to existing pipes.
6. Provide long radius bends to bring the pipe to the surface on both ends.
D. All trenches shall be backfilled and cOlnpacted in accordance to Section 02320.
3.02 FlELDQUALITY CONTROL
A. Do not backfill trench until the service has been inspected and approved by the
Engineer.
B. The \vater service will be pressure tested at 150 Ibs for two 11oufs. A drop of 3 Ibs
in a one hour span will constitute failure. Leaks will be corrected and the service
retested.
3.03 MEASUREMENT AND PAYMENT
A. A Bid item for "3" HDPE water service" has been provided on the bid form.
Measurement will be based upon units of lineal feet for furnishing and installing
pipe and fittings. Complete in place as specified, including excavation,
backfilling, aIld compaction.
END OF SECTION
34-00-125
@ 2000 Bonestroo, Rosene.
Anderlik & Associates, Inc.
02515-4
\V A TER SERVICES
SECTION 02630
STORM DRAINAGE
1.01 SECTION INCLUDES
A. Storm sewer pipe, catch basin manholes, catch basins, fittings, and miscellaneolls
appurtenances.
1.02 RELATED SECTIONS
B. Section 02315,- Excavation and Fill.
c. Section 02320 - Trench Excavation and Backfill.
1.03 REFERENCES
A. American Society of Testing and Materials (ASTM):
1. A48 - Specification for Gray Iron Castings.
2. A615- Specification for Deforn1ed and Plain Billet-Steel Bars for Concrete
Reinforcement.
3. C139 - Specification for Concrete Masonr)' Units for Construction of
Catch Basins and Manholes.
4.C150 - Specification for Portland Cement.
5.C206 - Specification for Finishing Hydrated Lime.
6. C478 - Specification for Precast Reinforced Concrete Manhole Sections.
7. D1784 - Specificatio11 for Rigid Poly (Vinyl Chloride) (PVC) Compounds
and Chlorinated Poly (Vinyl Chloride) (CPVC) Compounds.
8. D3034 - Specifications for Type PSM Poly (Vinyl Chloride) (PVe) Sewer
Pipe and Fittings.
9. D3212 - Specification for Joints for Drain and Sewer Plastic Pipe Using
Flexible Elastomeric Seals.
10. F477 - Specifications for Elastomeric Seals (Gaskets) for Joining Plastic
Pipe.
34-00-125
@ 2000 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02630-1
STOR1\.1 DR~-\I1"J"AGE
1.04 SEQUENCING AND SCHEDULING
A. Do not pllfsue work causing shut off of utility service (gas, water, electric,
telephone, TV, etc.) to consumers until the utility owner is contacted and all
consumers are notified of the shut-off schedule.
B. Required inspections and tests must be successfully completed before
commencemellt of aggregate base construction.
1.05 SUBMITTALS
A. Shop drawings.
B. Submit certification report for precast structures fabrication and installation.
PART 2 - PRODUCTS
2.01 MATERIALS
A. Concrete l\1aterials:
1. Use Standard Portland Cement Type 1, clean washed sand and crushed
rock and gravel free from deleterious materials for monolithic concrete
n1anholes and all manhole bases.
2. Portland Cement: Comply with the requirements of ASTM elSO.
3. Design Mix: Subject to the approval of the Engineer. Use proper water-
cement ratio to obtain (4000 psi) in 28 days.
B. Mortar Materials:
1. Celnent: Use Type 1 Standard Portlal1d Cement conforming to ASTIYI
eISO.
2. Lime: Use normal finishing hydrated lime meeting the requirements of
ASTM C206.
3. Mix Proportions:
a. Use one part cement to three parts of suitable plaster sand for
mortar used for plastering the exterior walls of block manholes and
catch basins, adjusting rings and lift holes. Use lime or mortar mix
in the amount necessary to make a suitable mixture for plastering
purposes, but not to exceed 15% by volume.
34-00-125
@ 2000 Bonestroo. Rosene,
.A.nderlik & Associates, Inc.
02630- 2
STOR!\1 DRAINAGE
b. Use one part Portland cenlent to two parts of sand to which lime or
mortar mix may be added but not to exceed 150/0 by volume for
mortar used for laying concrete block.
C. Reinforcing Steel: Comply with the requirements of ASTM A615, Grade 60.
2.02 MAi'WFACTlTRED UNITS
A. Manhole and Catch Basin Frames and Covers:
1. Requirelnent: ASTM A48.
2. Material: Class 35 cast iron. Best grade. Free from injllrious defects and
flaws.
3. Finish: No finish required.
4. 11achine cover and frame contact surface for non-rocking protection.
5. Type and Style: As shown on drawing. Covers without grate openings
shall be stamped "STORM SEWER".
6. Covers with two concealed pick holes of approved design.
B. J\rlanholes and Catch Basins:
1. Requirements: ASTI\tl C478, details on the drawings.
2. Dialneter and special requirements are ShOWll on the drawings.
3~ Structures shall be of precast concrete whenever possible. Segmental
block rnay be used for the lower portion of structures over large pipe.
4. Manhole joints shall be rubber O-ring gasket type lneeting ASTM C443.
5. Segmental Block Manholes: Blocks conform to ASTM C139.
6. Structure bases may be pre-cast or poured in place.
C. Manhole Steps:
1. Manhole steps may be constructed of any of the following Inaterials:
a. Cast Iron Manhole Steps: ASTM C478, minimum tensile strength
35,000 psi. Neenah Foundry Step No. RI98IJ, Badger F-15, or
equal.
34-00-125
@ 2000 Bonestroo, Rosene.
Anderlik & Associates, Inc.
02630-3
STORM DRAlNAGE
b. Polypropylene Coated Manhole Steps: M.A. Industries SP-I-PF,
or equal. Design similar to cast iron specifications.
C. AluminUlTI Manhole Steps: Apex Temalloy No. 5 aluminum alloy
or equal. Design similar to the cast iron steps specified may be
used.
D. Storm Pipe:
1. Pipe shall be Rep Class 5 or pve SDR 26. Pipe nlaterials shall be
consistent throughout the project.
2. PSM Poly (Vinyl Chloride) (PVC) Plastic Pipe and Fittings (4-inch
through I8-inch diameters):
a. General: Pipe and fittings shall conform to ASTM D 3034.
b. Materials: PVC plastics having a minimum cell classification of
1254 B or 12454C or 13364 B as defined in ASTM D 1784. Pipe
materials shall have a minimum hydrostatic design stress of 2,000
psi as certified by the Plastic Pipe Institute. Additives and fillers
including but not limited to stabilizers, antioxidants, lubricants,
colorants, etc., shall not exceed 20 parts by weight per 100 of pve
resin in the compound. Certification of resin compounding shall
be provided by the pipe manufacturer prior to shiplnent to the job
site.
Pipe shall have integral wall bell and spigot joint alld a minimum
wall thickness conforming to SDR 26.
Joints shall conform to ASTM D 3212. Joints shall be push-on
type only \vith the bell-end grooved to receive a gasket.
Elastomeric seal (gasket) shall have a basic polymer of synthetic
rubber conforming to ASTM F 477. Natural rubber gaskets will
not be accepted.
Each pipe shall be identified with the name of the manufacturer or
trademark and code, nominal pipe size in inches, the pve cell
classification and "Specification D3034."
PART 3 - EXECUTION
3.01 PREPARATION
A. See Section 02320 for trench excavation and backfill.
34-00-125
@ 2000 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02630-4
STOR!\.1 DRAIN.A.GE
B. Permanently support, remove, relocate or reconstruct existing utility pipes, cables,
structures or other appurtenances when they obstruct the line, grade or location of
the pipe or appurtenance. Do the work in cooperation with the owner of the
utility. Utility owner vvill determh1e which rnethod is to .be used. The Engineer
may order a deviation in the dra\ving line, grade or location if, in his opinion,
there is an acceptable alternative location for the work.
3.02 INSTALLATION
A. Connect to Existing Structure:
1. Connect to existing structure at location shown on the drawings.
2. Core the hole in the structure, trimming the pipe flush \vith the structure,
trimming the pipe flush with the pipe to seal it within the \vall.
3. Reconstruct manhole bench/invert.
4. Minor repairs to the structure.
B. Installillg Pipe:
1. Lay and maintain pipe appurtenances to the alignment, grade and location
shown on the plan and/or staked in the field. No deviation from the
drawing and/or staked alignment, grade or location is allov./ed unless
approved by the Engineer. Deviation from grade in excess of 0.05 percent
may be cause for removal and relaying pipe at the contractor's expense.
2. General Pipe Installation Procedures:
a. Wipe joints clean; apply the mallufactllrer's recolnmended
lubricant cOlnpound over the ell tire joint surface; Center spigot in
bell and push spigot home; Take care to prevent dirt from e11tering
the joint space; bring pipe to proper line and grade and secure pipe
in place by properly bedding.
3. Lay pipe upgrade with spigot ends pointing in the direction of flow.
4. All joints must be watertight. Repair any leaks discovered.
5. Joints connecting dissimilar pipe materials or where materials or where
cut-ins make it impossible to constnlct a bell and spigot joint shall be
make with a reinforced concrete collar completely surrollnding the joint or
b)T using an approved adapter.
6. Any pipe, which has been disturbed after being laid must be taken up, tIle
joint cleaned and properly relaid as directed by the Engineer.
34-00-125
@ 2000 Bonestroo, Rosene,
Anderlik & .A.ssociates, Inc.
02630-5
STOR~'l DRAINAGE
C. Installing Structures and Appurtenances:
1. Excavate to depth and size as shown in the detail on the plans.
2. Poured in place bases must be acceptably cured before manhole sections
are placed on the hardened slab.
3. In\'erts shaped to the half section of equivalent size pipe conforming the
inlet and outlet pipe so as to allow for a free, uninterrupted flow with all
surfaces sloping to the flo\v line.
4. Preformed inverts and watertight pipe connections for all lines 15" In
diameter of smaller.
5. Preformed inverts not allowed where pipe grades are 2 percent or greater
unless design grade is built through the manhole.
6. All concrete pipes entering manholes must be cut with a power saw
similar to the type used for ductile iron pipe.
7. Steps:
a. Locate on the downstream side except for pipe 36 inches in
diameter or greater. Then place where lnost appropriate to provide
the most suitable access.
b. Secure and neatly mortar in place 15 inch on center spacing.
8. Position vertical wall of the eccentric cone on the downstream side.
9. Use one (1 foot section) immediately belo\\' the slab.
10. Lift holes neatly mortared up.
11. The exterior of all block manholes shall be plastered with one-half inch of
Portland cement mortar.
12. Install adjustment rings and adjust casting.
3.03 RECONSTRUCT MANHOLES AND CATCH BASINS
A. In absence of the O-ring joint, older style manhole joints: sealed using Ram-nck
(or equal) gasket material applied in accordance with manufacturer's
recommendation.
34-00-125
@ 2000 Bonestroo, Rosene,
Anderlik & Associates. Inc.
02630-6
STORNI DRAINAGE
B. Manhole sections removed from a structure and not re-used on the project shall be
properly disposed of at a location off the project site.
C. Excavate around entire structure to the required depth for reconstruction. After
new sections are in place, backfill and ilnpact around structure \vith 12-inch lifts.
3.04 ADJUSTIN"G AND CLEANIN"G
A. Adjusting:
1. Consists of adjusting the final elevation of structure casting to final grade.
2. Applies to structures installed as a part of this work.
3. Consists of setting casting frame to final elevation b)l adding or removing
standard concrete adjustment rings of the same size and shape as the cone
or slab opening. Elevation adjustments to existing structures that cannot
be done by adding or removing rings are not adjustments but are
reconstructions.
4. Place each adjusting ring and frame in full mortar bed. Encase the outside
of the rings and frame in mortar collar (encase catch basins located in
curbs in concrete beillg integral \vith the curb).
5. No shims of any material allowed.
6. Minimum thickness of mortar between rings: 14 inch.
7. Maxilnllffi thickness of mortar bet\veen rings: Y2 inch.
8. \Vipe clean all excess mortar from bet\veen rings and frame on the inside.
9. Set structures 1,4 to Y2 inch lower than adjacent final grade.
B. Cleaning:
1. Clean the pipe and structures.
2. Bailing or flushing method of cleaning pipe is acceptable only if adequate
provisions, acceptable to the Engineer, for keeping dirt and debris out of
the existing sewer system are employed. Otherwise, jetting will be
required.
3. Complete prior to final inspection for acceptance.
34-O0~125
@ 2000 BonestroQ, Rosene,
Anderlik & Associates, Inc.
02630- 7
STORM DRAINAGE
C. Required Tests and Inspections:
1. Infiltration:
a. To determine the amount of ground \vater infiltration into the
se\vers.
b. Test waived if no visible infiltration IS observed during the
lamping inspection.
c. Measurement made by means of 90 degree V -notch weirs placed in
the lines as directed by the Engineer.
d. Measurements taken at the points where, in the Engineer's opinion,
the flow of water in the sewer is greater than the maximum
allowable leakage.
e. Maximum allowable rate of leakage: Not more than 100 gallons
per mile per inch diameter per day.
f. Tests may be taken between individual lnanholes and the
infiltration in any given line must not exceed the specified
maximum allowable rate.
cr Method of Measurement: Measurement of tilne for a
o'
predetermined volull1e of flow to occur.
2. Lamping:
a. Verify installation is to true line and grade.
b. Verify installed pipe is structurally sound.
c. Verify there are no broken or deflective pipe.
d. Verify that joints are all home.
e. Verify stluctures conform to specified requirements.
3.05 PROTECTION
A. Plug all entrances and openings to the system promptly and before suspension of
operations at the end of \vorking day.
B. SeCllre manholes and structures immediately after completion or before
suspension of operations at the end of \vorking day with castings or suitable
alternative device.
34-00-125
@ 2000 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02630-8
STOR!vIDRAINAGE
c. ivlark structure susceptible to being hit by construction or vehicular traffic.
D. Mark each plug location with 4"x4" timbers to above grade to aid in marking the
future connection.
3.06 MEASUREMENT AND PAYIvIENT
A. Bid items for "storm sewer" and "drain pipe" have been provided on the bid
form. Measurement \vill be based upon units of lineal feet for each size and
depth, for furnishing and installing pipe. Complete in place with fittings as
specified, including excavation, backfilling, and compaction. Pipe will be
measured from centerline.
B. A bid item has been provided for 4' diameter storm catch basin manhole.
Measurement will be based upon units of each for furnishing alld installing
structures complete, including manhole frame and casting in place as specified.
C. A bid iteln has been provided for 1.'27" dialneter catch basin. 1\1easurement \vill
be based llpon units of each completed as to shape, size, aI1d depth according to
the drawings. Payment shall include catch basin frame and grating.
D. A bid item has been provided for connect to existing catch basin manhole.
Measurement will be by each. Payment "viII represent compensation for all work
and tnaterials including repair of the manhole invert.
E. A bid item has been provided for skimmer structure. Measurement will be by
each. Payment will represent compensation for all work and materials including
the cover grate.
F. A bid item has been provided for Class II randoln riprap. Measurement "viII be by
the CY. Payment will represent compensation for all work and materials
including filter fabric and granular bedding.
G. No direct measurement and payment will be made for the flared end section. This
structure will be measured and included in the payment for the storm se\ver. It
will paid as lineal feet of pipe.
END OF SECTION
34-00-125
@ 2000 Bonestroo. Rosene.
Anderlik & Associates, Inc.
02630-9
STORM DRAI1\fAGE
SECTION 02720
AGGREGATE BASE COu~SE
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. Requirements for aggregate base course.
1.02 RELATED SECTIONS
A. Section 02108 - Full Depth Reclamation.
B. Section 02312 - Subgrade Preparation.
C. Section 02740 - Plant-Mixed Bituminous Paving.
1.03 REFERENCES
A. Minnesota Department of Transportation Standard Specifications for Construction,
1988 Edition and the Supplemental Specification dated May 2, 1994, (MnDOT
Spec.):
1. MnDOT Spec. 2211 - Aggregate Base.
2. MnDOT Spec 3138 - Aggregate for Surface and Base Courses.
1.04 SUBMITTAL
A. Submit gradation report on sample of aggregate base to be used.
1.04 SEQUENCING AND SCHEDULING
A. Construct aggregate base only after all of the follo\ving have been completed:
1. Subgrade has been corrected for instability problems and successfully passed
a test rolling test, performed by the Contractor and witnessed by the Engineer.
2. Subgrade has been checked for conformance to line and grade tolerances
(s tringline ).
34-00-125
@ 2000 Bonestroo~ Rosene.
Anderlik & Associates, Inc.
02720-1
AGGREGATE BASE COURSE
PART 2 - PRODUCTS
2.01 MATERIALS
A~ Aggregate Base, Class 5: Conform to MnDOT Spec~ 3138, Class 5 aggregate~
B. Salvage Aggregate Base, Class 5: Conform to MnDOT Spec. 3138 Class 5
aggregate.
1. This material will be salvaged after reclamation and stock pi1ed~ It will be
repsread as Aggregate Base, Class 5 after subgrade preparation~
2. This project estilnates 11 inches of reclaimed aggregate base \viII be sal'Jaged~
In areas \vhere bituminous pavement is not reclaimed, it is estimated that 8
inches of reclaimed material will be salvaged.
3~ New Aggregate Base, Class 5 will be imported to meet the design section.
p ART 3 - EXECUTION
3.01 PREPARATION
A. Subgrade to be completed and approved by the Engineer prior to installation of
aggregate base.
3.02 CONSTRUCTION REQUIREMENTS
A. Conform to MnDOT 2211.3:
1. Compact by mechanical means to 1000/0 of Standard Proctor density.
2. Install aggregate base in accordance \vithdetails on plan.
3~ Deliver weight tickets to Engineer daily.
3.03 FIELD QUALITY CONTROL
A. The Contractor shall have an independent testing laboratory sample the aggregate
base materials, determine the moisture/density relationships, and gradation and
perform field moisture/density tests at locations determined by Engineer.
B. Line and Grade Tolerance: the final aggregate base surface \vill be checked for
conformance to specified tolerances by the "stringline" method prior to approval to
pave the surface. Grade shall be :to_05' of grade.
34-O0~ 125
@ 2000 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02720-2
AGGREGA1E BASE COURSE
3.04 PROTECTION
A. Protect aggregate base until it is covered by surface pavement.
B. Keep aggregate base free of ruts and irregularities until covered by surface paving.
C. Place water on aggregate base for dust control as required to eliminate nuisance
conditions for adjacent properties.
3.05 MEASUREMENT AL~ PAYMENT
A. Aggregate Base, Class 5 will be measured by the Ton in place.
B. Salvaged Aggregate Base, Class 5 will be measured by the cubic yard in place.
Measurement will be by cross section. Payment will be by the cubic yard in place.
Payment will be for the salvaging, stockpiling, and final placing of the material.
END OF SECTION
34-00-125
@ 2000 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02720-3
AGGREGATE BASE COURSE
SECTION 02740
PLANT MIXED BITUMlNOUS PAVEMENTS
PART 1 - GENERAL
1.01 SECTION lNCLUDES
A. Plant-mixed, bituminous-aggregate hot mixtures for base, binder, wear course
pavements, and bituminous curb.
B. Bituminous Tack Coat
1.02 REL~i\ TED SECTIONS
A. Section 02770 - Concrete Curb and Gutter.
B. Section 02720 - Aggregate Base Course.
C. Section 02280 - Adjustment of Miscellaneous Structures.
1.03 REFERENCES
A. Minnesota Department of Transportation, "Standard Specifications for Highway
Construction," 1988 Edition and the Sllpplernent SpecificatiollS dated May 2,
1994. (MnDOT Spec.):
1. Spec. 2331 Plant-Mixed Bituminous Pavement.
2. Spec.. 2340 Plant Mixed Bituminous Pavement Quality Assurance (Q/A)
Projects.
3. Spec. 2357 Bituminous Tack Coat.
5. Spec. 3139 Graded Aggregate for Bituminous Mixtures.
1.04 SUBMITTALS
A. Conform to MnDOT Spec. 2331.3E2. - submittal of the Job Mix Formula (IMF).
1.05 SEQUENClNG At"\fD SCHEDULlNG
A. Aggregate base and concrete curb and gutter to be completed and approved by the
Engineer prior to placement of bituminous surfaces.
B. The Contractor shall provide a 48-hour notice for scheduling and noticing of the
residents prior to placement of the final wear course.
34-00-125
@ 2000 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02740-1
PLAl'1T MIXED BITUMINOUS PAVEMENT
c. Adjust structures prior to placement of bituminous wear course.
PART 2 - PRODUCTS
2.01 MATERIALS
A. Hot Mixed Bituminous:
1. Aggregate for Driveway, and Parking Lot: Conform to MnDOT 3139.
a. Confornl to the requirements of 3139 and the gradations for each
type of mix as indicated on Table 3139-1, or more specifically the
following:
Mix Type 31
Mix Type 41
Parking Lot Base Course
Parking Lot Wear Course
Mix Designation
31 BBB 50000
41 WEA 50055
2. Bituminous Material: Conform to MnDOT 3151:
a. Conform to MnDOT "Standard Specifications for Performance
Graded Asphalt".
b. The Perrormance Grade Asphalt Cement: PG 58-28.
B. Bitumill0Us Tack Coat:
1. Bituminous Material Conform to MnDOT 3151.
a. Emulsified Asphalt, Cationic, CSS-I or CSS-2.
PART 3 -EXECUTION
3.01 GENERAL
A. All bituminous Inixtures must be furnished by a Contractor Certified Plant for
Bituminous I\1ixtures, Adhering to MnDOT's certification procedure.
B. The Contractor to review the proposed paving sequence with the Engineer prior to
placement of the wear courses.
C. The proposed sequence shall address the; Longitudinal seams, Compaction,
Traffic control, Hauling routes, Placement of pavement markings, Adequate
sIgnIng.
34-00-125
@ 2000 Bonestroo, Rosene1
Anderlik & Associates, Inc.
02740-2
PLANT ?vEXED BITillvIINOUS PAVEMENT
D. Preparation of Bituminous Base:
1. Final clean up of the bituminous base surlace with the use of a power
pickup broom and front end loader.
2. Final adjustment of structures in accordance with Section 02280.
3.02 RESTRICTIONS
A. Confoflll to MnDOT Section 2331.3B except as modified herein:
1. All street surfaces checked and approved by the Engineer prior to paving.
2. Existillg bituminous surfaces must be dry prior to placelnent of any
bituminous pavements.
3. Wearing course not placed when the air temperature, in the shade and
away from artificial heat, is 50 degrees or less, unless otherwise approved
by the Engineer.
4. DUling the placelnent of the wear course mixtures the Contractor must
provide a minimum of six personnel as follows:
a. One paver operator.
b. Two persons to operate the adjustment scre\vson the back of the
paver.
C. One bituminous finisher (raker).
d. One rubber tire roller operator.
e. One steel drum roller operator.
Compaction operations may require additional roller operators to 'obtain
the required densities.
3.03 EQUIPMENT
.L~. Bituminous Pavers shall be self-contained, power propelled units with automatic
screed control conforming to MnDOT 2331.3C2A, for paving including
pathways.
34~OO-125
@ 2000 Bonestroo, Rosene,
Anderlik & Associates. Inc.
02740-3
PLANT NIIXED BITUl\1INOUS PAVEMENT
3.04 TREATMENT OF SURFACE
A. Bituminous Tack coat shall conform to MnDO'r Spec. 2357 or as modified
herein:
B. Restrictions:
1. The tack coat shall not be applied \rvhen the road surface is wet or when
the weather conditions are unsuitable.
2. The area for tack coat applied shall be limited as directed by the engineer.
3. The contractor shall have sole responsibility of claims of tack coat on
personal property due lack of notification or signage of the area being tack
coated.
C. Equipment:
1. Shall conform to J\rlnDOT Spec. 2321.3Cl.
D. Road Surface Preparation:
1. Shall conform to MnDOT Spec. 2357.3C.
E. Application:
1. At a uniform rate conforming to MnDOT Spec. 2357.3Da, but not greater
than 0.05 gallons per square yard.
2. Along the front edge of the concrete curb and gutter.
3.05 MIX PROPORTIONS
A. Requirements will cOl1fornl to MnDOT Spec. 2340.3E or as modified below.
B. Contractor Trail Mix Design: Bituminous mix designed using the Contractors
trial mix design Specifications 2331.3E2b.
c. Recycled Mixture Requirements: Requirements under MnDO'T Section
2331.3E2e shall apply, except as modified; recycled bituminous Mixture Type 42
and Type 48 can not be substituted for Type 41 and Type 47.
3.06 PLANT OPERATIONS
A. Conform to MnDOT Spec. 2331.3F.
34~OO-] 25
@ 2000 Bonestroo, Rosene,
Anderlik & Associates~ Inc.
02740-4
PLANT 1vlIXED BITUI\1INOUS PAVEMENT
3.07 SPREADING OPERATIONS
A. Conform to MnDOT Spec. 2331.3G.
3.08 COMPACTION OPERATIONS
A. Compaction requirelnents conform to MnDOT Specification 2340.3H2 as
Modified Specified Density Method and as modified below:
B. Vibrating steel drllffi roller and a pneumatic tired roller employed in conjunction
\vith each other during compaction of all wear courses.
3.09 THICKHNESS REQUIREMENTS
A. Conform to MnDOT Spec. 2331.31 or as modified.
1. After construction, the thickness of each course must be within 14 inch of
the thickness shown on the plans.
2. For any course constructed, the material used in excess of the specified
thickness plus lA inch will be excluded from the pay quantities.
3.10 CONSTRUCTION JOIN'TS
A.Conform to MnDOT Spec. 2331.3K.
3.11 MEASUREMENT AflD PAYMENT
A. Bituminous Tack Coat: No measurement of bituminous tack coat will be Inade.
Payment for bituminous materials used for tack coat shall be included in the
payment of bituminous paving. Cleaning of all debris and dirt f1'0111 the previous
bituminous surfaces prior to placement of tack coat is included in the unit price
bid for bituminous paving. Payment for tacking exposed edges of existing
bituminous surfaces and concrete curb and gutter in conjunction with base course
placement is considered incidental to the placelnent of the base course.
B. A bid item has been provided for Bituminous base course, Type 31B, and
Bituminous Wear course, Type 41A. Measurement will be based on units of ton.
Payment for paving shall include work and materials required.
END OF SECTION
34-00-125
@ 2000 Bonestroo. Rosene,
Anderlik & Associates, Inc.
02740-5
PLANT MIXED BITUlvlINOUS P A VElvIENT
SECTION 02770
CONCRETE CURB AND GUTTER
PART 1 - GENbRAL
1.01 SECTION INCLUDES
A. Construction of cast-in-place concrete curbs, curb and gutter and valley gutter.
1.02 RELATED SECTIONS
A. Section 02720 - Aggregate Base.
B. Section 02740 - Plant Mixed Bituminous Pavements.
1.03 REFERENCES
A. American Society of Testing Materials (ASTM):
1. C260 - Air Entraining Admixture for Concrete.
B. Minnesota Department of Transportation "Standard Specification for
Construction", 1998 Ed. And the Supplen1ent Specifications dated May 2, 1994,
(MnDOT Spec.).
1. MnDOT Spec. 2461 - Structural Concrete.
2. MnDOT Spec. 2531 - Concrete Curbi11g.
1.04 SlJBIv1ITTALS
A. Submit one - 7 day and two - 28 day concrete cylinder test results for all concrete
pours in any given day.
B. Submit concrete design mix formulas.
PART 2 - PRODUCTS
2.01 MATERIALS: Concrete to Conform to MnDOT Spec. 2461 Concrete
A. Portland Cement: Type 3 air-entraining concrete produced by using Type IA air-
entraining Portland Cement.
34-00-125
@ 2000 Bonestroo. Rosene,
Anderlik & Associates, Inc.
02770-1
CONCRETE CURB AND GUTTER
B. Air-Entraining Admixtures: Conforming to: ASTM C-260.
1. Not to be added to the concrete mixtures in the field without approval
from Engineer.
C. Mix Designation and Classification for Concrete Curb and Gutter:
1. Manual Placement Mix No. 3A32C.
2. Slip Form Placement Mix No. 3A22C.
D. Pre-Formed Joint Filler: Conform to MnDOT 3702.
E. Curing Compound: Confonn to MnDOT 3754.
PART 3 - EXECUTION
3.01 GENERAL
A. The concrete curb and gutter shall be constructed at the locations and elevations
indicated on the drawings.
B. The style or type of curb and gutter shall conform to shape and size as shown on
the drawings.
C. Construct intersection curb radii and transitions sections to conform to the detail
on the drawings.
D. Construct 10-foot transition sections at ill1et structures to conform to the detail on
the drawings.
E. Concrete curb ralnp depressions shall be constructed to conform to the detail on
the drawings.
F. Construct curb transitions for driveways per the detail on the dra\vings.
G. The completed concrete \vork shall give the appearffilce of unifomtity in surface
contour and texture, and shall be accurately constructed to line a11d grade. The
required joints, edges, and flo\v lines shall show neat workmanship.
H. Retempering of the concrete, which has partially hardened, with or without
additionallnaterials or water, is prohibited.
34-00-125
@ 2000 Bonestroo, Rosene.
Anderlik&Associates. Inc.
02770-2
CONCRETE CURB A.ND GUTTER
3.02 FOU1\TDATION PREPARATIONS
A. Support on a compacted aggregate base extending 1 foot behind the back of curb
conforming to Section 02720 - Aggregate Base and MnDOT Spec. 2211.3C 1
(100% Maximum Density).
3.03 FORMS
A. Conform to MnDOT Spec. 2531.3B.
3.04 JOmT CONSTRUCTION
A. Conform to 11nDOT Spec. 2531.3C except as modified herein:
1. Maximum spacing of expansion joints for slip fOlmed shall be 200 feet.
3.05 PLACmO AND FINISHING
A. Conform to MnDOT Spec. 2531.3E and 2531.3F except as modified herein.
1. The top surface of the curb and gutter shall ha\'e a brush finish at right
angles to the curb line.
3.06 CONCRETE CURING AND PROTECTION
A. Conform to MnDOT Spec. 2531.3G and 2531.3G2 (Membrane Curing Method)
except as modified herein.
B. All surfaces shall be coated with membrane curing compoulld within 30 Ininutes
after finishing.
1. The membrane curing compound lTIUst contain a fllgitive dye.
2. A second heavy coat of membrane curing compound shall be applied 4 to
8 hours after the first coat.
3. Cold weather curing, when temperatllres fall belo\v 40 degrees during
placement or within the following 24 hOllfS, shall conform to 2531.3G 1
blanket curing method, or method approved by the Engineer.
4. The freshly finished surface shall be protected, surfaces pitted by rain will
be considered unacceptable.
5. Removal and replacemellt any curb section damaged by traffic, rain, cold
weather, or other causes occurring prior to the 72 hOllf curing period or
final acceptance shall the responsibility of the Contractor.
34-00-125
@ 2000 Bonestroo, Rosene,
Anderlik & Associates. Inc.
02770-3
CONCRETE CURB AND GUTTER
3.07 BACKFILLING
A. Conform to MnDOT Spec.2531.3J except as modified herein.
1. The initial curb backfill and boulevard grading shall follow the 72-hour
curing period, with completion within 6 days of original placement.
2. The curb backfilling shall be completed with the adjacent boulevard
material.
3~ The tolerance for the backfill and grading shall be within 0.3 feet In
relationship to the top of curb elevation.
3.08 WORKi\1A.NSHIP AND FINISH
A. Confolm to MnDOT Spec. 2351.3K except as lTIodified herein.
1. Any deviation in the design curvature, concrete edges and surfaces
designed to straight lines or grades in excess of 3/8 of an inch, measured
with a lO-foot straight edge, will be considered unacceptable.
3.09 :MEASUREMENT Al\TD PAYMENT
A. A bid item has been provided tor concrete curb and gutter. Measurement of curb
and gutter shall be measured along the face of the curb at the gutter line, by length
in lineal feet and by type of curb. No separate measurement or pa)Tment for
modifications at curb ramps, transition sections or curb installed at catch basins
and radii.
END OF SECTION
34~OO-125
@ 2000 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02770-4
CONCRETE CURB AND GUTTER
SECTION 02775
CONCRETE PA VJNG
PART 1 - GENERAL
1.01 SECTION IN"CLUDES
A. Concrete \valks and driveways.
1.02 RELATED SECTIONS
Not Used
1.03 REFERENCES
A. Minnesota Department of Transportation Standard Specification for Construction,
1988 Edition, a11d the Supplement Specifications dated May 2, 1994 (Mn/DOT
Spec.):
1. MnlDOT Spec. 2521 - Walks.
2. Mn/DOT Spec. 3149 -Granular Material.
1.04 SEQUENCING AND SCHEDULING
A. Do not pour concrete pads until base has been approved by Engineer.
PART 2 - PRODUCTS
2.01 CONCRETE
A. Concrete shall have a minimum 28 day compressive strength of 3900 psi.
B. Concrete shall have entrained air content of 5% to 7%.
PART 3 - EXECUTION
3.01 INSTALLATION
A. Concrete pads shall be given a light broom finish. Brooming shall be at a 900 angle
to normal traffic flow direction.
34-00-125
@ 2000 Bonestroo. Rosene,
Anderlik & Associates, Inc.
02775-1
CONCRETE PAVING
3.02 FORtVIS
A. Form\vork shall conform to MnJDOT Spec. 2521.
3.03 JOINT CONSTRUCTION
A. Provide contraction and expansion joints in accordance with Mn/DOT Spec. 2521.
3.04 CURING
A. Provide tile Blanket Curing Method in accordance with MnlDOT Spec. 2521.
3.05 MEASUREMENT AND PAYMENT
A. Concrete \-valks will be measured by the square foot. Payment shall include all \vork
and materials including 4 inches (min.) of granular base and wire mesh
reinforcement.
B. Concrete driveway will be measured by the square foot. Payment shall include all
vvork and materials, including 8 inches of aggregate base and \vire 111esh
reinforcement.
END OF SECTION
34~OO-125
@ 2000 B onestroo. Rosene,
Anderlik & Associates. Inc.
02775-2
CON CRETE PAVING
SECTION 02830
FENCE AND BOLLARDS
P AR T 1 - GEI\TERAL
1.01 SECTION lNCLUDES
A. Chain link fence and steel bollards
1.02 SUBMITTALS
A. Submit typical layout, elevation, and section drawings for fences, and gates. Sho\v
installation details for all end, corner, and line posts.
PART 2 - PRODUCTS
2.01 FENCWG MATERIALS:
A. Fabric: Fabric shall be No. 9 gauge steel \vire, as shown on the plan details.
Aluminized fabric shall be coated before weavi11g with a minimum of 0.4 ounces per
square foot of surface area in accordance with ASTM A-491. The steel wire and
coating shall conform with ASTM A-817. Fabric shall have knuckled top and
bottom edges. Width of fabric shall be as sho\vn on the plan details. Mesh size shall
be 1-3/4 inch.
B. Fence Posts: All posts shall be hot-dipped galvanized, schedule 40 steel pipe and
shall conform to the latest ASTM designation or ~80 oz. aluminum per square foot,
total both sides. Post sizes (O.D.) and weight shall be as listed below:
Post Type
Diameter (Min)
Weight (Mill) Burv Depth
(Min)
FOllndation
Size (Mill)
6' to 8' Fence Line Post 2Yz" 3.65 lb/ft.
3'-0"
10" dia. x 31_ 3"
6' to 8' Fence End, Corner,
& Gate Post 3" 5.79 lb/ft.
4'-Otl
12 l! di a. x 4' - 3 II
c. Rails: Rail to be hot-dipped galvanized, Schedule 40 steel pipe 1-5/8 inch O.D. (2.27
#/ft.)~ Provide with expansion sleeve couplings. Top rail is to pass through base of
post cap and is to securely fasten to end, gate and corner posts. Bottom and mid rails
are required as shown on plan details.
34-00-125
@ 2000 Bonestroo, Rosene.
Anderlik & Associates. Inc.
02830-1
FENCE
D. Gates: Gate frames shall be 2 inch O.D. hot dipped galvanized steel pipe (2.72 #/ft.).
Gates shall have all bracing shown on plans and as recommended by tIle
manufacturer and shall include positive type latching devices \vith padlock
provisions.
E. Ties: Ties shall be No.9 gauge wire at 12 inches o.c. on posts and rails.
F. Fittings: To be of malleable iron, hot-dip galvanized after fabrication. Provide caps
for all posts.
2.02 CONCRETE MIX
A. ASTM C-94 Portland cement concrete \vith maximum 3/4 t! aggregate 11aving a
minimun1 compressive strength of 3,000 psi at 28 days.
2.03 BOLLARDS
A. Fabricate from Schedule 80 steel pipe.
B. Leave top open. Fabricate to shape indicated on drawings.
C. Paint - High solids, lead-free, rust-inhibitive alkyd primer. Acceptable Products: 10-
99 or 10-1009, TnemecCompany Ine or X -60 Rust-Oleum Corporation or approved
equal. Finish color to be selected by O\vner.
PART 3 - EXECUTION
3.01 INSTALLATION
A. Post Setting: Set posts plumb in concrete footings. Top affooting will be at grade,
with the concrete rising above grade towards the post to shed water. Maximum post
spacing shall be 10ft. on center. Concrete footing shall be belo\v decking where
applicable. "Box outs" in decking will not be allowed.
B. Top Rail: Install through line post caps connecting sections \vith sleeves to form a
continuous rail between terminal posts.
C. Fabric: Pull fabric taut with bottom selvage 1 I' above grade. Fasten to tenninal posts
with tension bars threaded through mesh and secured with tension bands at maximum
15" intervals. Tie to line posts and rails \vith tie wires spaced at maxilllum 12lT.
D. The Fence shall follow the slope of the pavement. Fence installer shall coordinate
with paving contractor to verify that final grades are established prior to fence
ins tallati on.
34~OO-125
@ 2000 Bonestroo, Rosene,
Anderlik & Associates, Inc.
02830-2
FENCE
E. Remove Fence and posts and install new posts and gates as required to install a 12
foot gate according to the specifications.
F. Verify bollard location with Engineer prior to placement.
3.02 MEASUREMENT AND PAYMENT
A. A bid item "Remove Fence and Install Gate" has been provided for all work and
materials required to install a gate as described herein.
B. A bid item "Bollard" has been provided for all work and materials required to install
as described herein and in the plans. Ivleasurement will be by each and represent
compensation for all work and materials required.
END OF SECTION
34-00-125
@ 2000 Bonestroo. Rosene,
Anderlik & Associates. Inc.
02830-3
FENCE
SECTION 02930
SEEDING
02930.1. DESCRlPTION
A. This work consists of seeding that takes place on disturbed areas around the pond
as identified on the plan. Black dirt and seeding will also be required behind curb
and gutter replaced at the parking lot.
B. Definitions:
1. Weeds: For the purpose of this project, a weed is a plant that illhibits the
establishment of species listed in tuaterials (Section 02930.2). Weeds may
include but are not limited to: quackgrass, canada thistle, ragweed,
pigweed, bentgrass, ellropean buckthorn, glossy buckthorn, tatarian
honeysuckle, black locust, and spotted knapweed, reed canary grass, and
kentucky bluegrass.
C. Submittals:
1. Product Data: Provide nursery source al1d invoice for seed to be purchased
for this project.
2. Qualifications:
a. Nursery: Company specializing in growing and cultivating the
specified plallts with documented experience as represented by a
list of completed past projects.
3. Producer's certificate of compliance - Written document verifying
compliance of mixture of seed furnished. Submit to the property owner 5
days prior to delivery. Include percentage of variolls seed species mix,
year of production, net weight, date of packaging and location of
packaging, seed bags/tags (gerlnination rate, weed seed content), and copy
of seed dealer's invoice.
D. Delivery, Storage and Handling:
1. Seed:
a. Deliver seed mixture in sealed, undamaged containers.
b. Protect seed from moisture prior to use.
34-00-125
@ 2000 Bonestroo1 Rosene,
Anerlik & Associates, Inc.
02930-1
SEEDING
02930.2. MATERIALS:
A. Topsoil: Select Topsoil BOITOW conforming to MnJDOT Section 3877.2A.
B. Native Seed Mixtures: Tabulations for the seed mixture contain the standard rates
as per Table 2575-1 of the Standard Specifications for Construction Manual,
which are based on seed being broadcast or hydroseeded and are listed in the
following tabulation under "broadcast" rates. Also included are recommended
rates for drill seeding using a Truax-type native grass drill. Drill rates are
approximately 600/0 of the broadcast/hydroseeding rates. When standard
(broadcast) rates are used with a drill, more than one pass should be made over
the site to get all of the seed into the ground.
1. General Requirements:
a. Requirements for production, origin, definition of wild-type, and
treatments shall be adhered to as outlined in "Mn/DOT Seeding
Manual 2000".
b. Approved Vendors/Sources: All native grass and forb seed shall
be purchased from an Approved Vendor or Source for native
seeds. All bags of seed shall be labeled with the species, C011tents
by weight and mixture number (where appropriate) and the vendor
from which it was purchased.
c. Native grass mixtures to be seed in locations identified on plal1:
Mixture 28A Modified (28B) - General Purpose Native Ditch
Common Name Botanical Name 0/0 of lVlix
Bluestem, big Andropogon gerardi 6.0
Milkweed~ marsh Asclepias incarnata 0.17
Brome~ fringed BrOJ1lUS ciliata 4.0
Prairie clover, purple Dalea pUJpu.relun 0.17
Tic-trefoil, showy DeSlllodiufn canadense 0.17
Wheatgrass, slender Elynuls trachycaulus 10.0
Wild-rye, Virginia ElYlnus virginicus 10.0
Sunflower, early Heliopsisi helianthoides 0.17
Rye-grass, annual Loliran italicUlll 8.0
ReGreen NA 40.0
S witchgrass Panicu111 virgattun 3.0
Bluegrass, fowl Poa palustris 12.0
Black-eyed Susan Rudbeckia hirta 0.17
Indian grass Sorghastrulll nutans 6.0
Vervain, blue Verbena hastata 0.17
Total: 100.00
Rate: 40 Ibs/acre (44 kg/ha).
Description: Mesic/\vet native grass ditch mix. Reaches a height of
approximately 36 inches. General purpose mix for use in roadisde ditches that
range from wet to dry.
34-00-125
@ 2000 Bonestroo, Rosene.
Anerlik & Associates, Inc.
02930-2
SEEDING
I\lixture 30A Modified (30B) - Urban Prairie
Common Name Botanical Name 0/0 of lVlix
Grama, sideoars Bouteloua curtipendula 8.0
Grama, blue Bouteloua gracilis 6.0
Prairie clover, purple Dalea purpureu111 2.0
Wild rye, Canada Elyrnus canadensis 4.0
\Vheat grass, slender Elyrnus trachycaulus 6.0
Rye grass, annual Lolhun italicunl 8.0
ReGreen NA 26.0
Blue grass, Canada Poa cOllzpressa 12.0
Alkali grass Puccinella distans 16.0
B luestem, little Schizachyriufn scoparirun 10.0
Dropseed, sand Sporobolus cryptandrus 2.0
Total: 100.0
Rate: 60 lbs/acre (66 kglha).
Description: COlnbination native and turf mix. Reaches a height of
approximately 18 inches. For use in urban areas where conditions may be
saline, droughty, & generally poor soils.
02930.3. CONSTRUCTION REQUIREMENTS:
A. Sequencing and Scheduling:
1. Planting Seasons:
a. Spring: April 15 to June 15.
b. Fall: August 20 to October 1.
B. Seeding:
1. Seeding locations are shown on the attac11ed planting plan. Also seed
behind replaced curb and gutter.
2. Remove foreign materials, undesirable plants, and their roots. Do not bllry
foreign material beneath areas to be landscaped or restored. Remove
contalninated subsoil.
3. I11stallation :Lvlethods for Seeded Areas:
a. Site Preparation - The site ShOtlld be prepared by loosening topsoil
to a minimum depth of 2 Y2 inches.
34-00-125
@ 2000 Bonesrroo, Rosene, ·
Anerlik & Associates, Inc.
02930-3
SEEDING
b. Seed Installation - Seed should be installed with a seed drill that
will accurately meter the types of seed to be planted and keep all
seeds uniformly mixed during the drilling (Truax-type). The drill
should contain a minimUlTI of two seed boxes; a fine seed box and
a box for large/fluffy seeds, and should be equipped with disc
furro\v openers and packer assembly to compact the soil directly
over the drill rows. I\1aximum row spacing should be 8 inches.
Fine seed should drop seed onto the ground surface from the fine
seed box. This can be accomplished by pulling out the plastic
tubes feeding seed into the drill fUITOWS. Large/fluffy seed should
be placed to obtain a final planting depth of 6mm. All drill seeding
should be done at a right angle to surface drainage.
C. Seed Rates - The seeding rate shall be split in half and two passes
shall be made over the entire site.
d. Harrowing - The site should be lightly harrowed or raked
following seeding.
e. Paclcing - Pack the site follo\ving harrowing to insure a firm seed
bed.
C. Mulch
1. Use l\1nJDOT Type 1 (clean straw) mulch at a rate of 2.0 tons per acre.
02930.4. NIEASUREMENT AI\TD PAYMENT:
A. Bid items have been provided for the MI1DOT seed mixes around the pond area.
The bid unit price per acre shall be cOlnpensation for all work alld materials
including seed, fertilizers, and mulch.
B. The Contractor is responsible to place (min. or 4"), tolerance, and prepare topsoil
for seediIlg behind replaced curb and gutter. Seeding in these areas will be
completed by others.
END OF SECTION
34-00-125
@ 2000 Bonestfoo, Rosene,
Anerlik & Associates, Inc.
02930-4
SEEDING
SECTION 16050
RA,"Tr RT ,FJ~TRTrAT, MATRRTAT ^~ A1\Tf) METHODS
PART 1 - GF,NRRAT J
1.01 SECTION IN"CLIJDES
A. Raceways.
B. Wires and cables.
C. Inductive Loop Control for Overhead Doors
1.02 REFERENCES
A. NECA - National Electrical Contractors Association.
1. NECA - Standards of Installation.
B. NEMA - National Electrical Manufacturers Association.
C. NFP A - National Fire Protection Association.
1. NW A 70 - National Electrical Code.
D.OSHi\ - Occupational Safety and Health Administration
E. UL - Undervvriters Laboratories, Inc.
1.04 REGIJLATORYREQUIREMENTS
A. All work performed under this Contract shall conform to the latest editions of the
National Electrical Code (NFPA70), the National Electrical Safety Code (~~SI
C2), the Minnesota State Building Code, and the Wisconsin Administrative Code.
B. Unless specifically noted otherwise, all equipment and Inaterials shall be new and
shall bear the Underwriters Laboratories (1JL) label if such products are listed by
UL.
1.05 IN"STRUCTIONS AND PARTS LITERATURE
A. Instruction and parts literature is generally packed with electrical equipment and
devices. Contractor shall remove this literature from the packing container or
equipment enclosure, identify the literature with the equipment to \vhich it applies,
and provide this information to the Owner upon completion of the job.
34-00-125
@ 2000 Bonestroo, Rosene
Anderlik & Associates. Inc.
1 hO"O-l
BASIC ELECTRIC.AJ..
1\1 A TERlALS AND :METHODS
PART 2 - PRODTTrTS
2.01 CONDUIT AND RACEWAY.
A. pve 1/2" Electrical Non-Metallic Tubing or approved equal.
1. Crush Resistance:
2. Tensile Strength:
3. Temperature, Operating Range:
4. Dimension, Outside, Max:
To 1000 Ibs.
To 200 Ibs.
To 900C
0.82 in.
B. EPC-40-PVC and EPC-80-PVC
1. Sunlight resistant.
2. Approved for:
1. Direct burial.
2. Concrete encasement.
3. Above grollnd and exposed applications.
3. NEMA TC2.
4. NFPA 70 Article 347.
5. lJL-651.
6. UL listed.
7. Carlon, CertainTeed, or equal.
C. RIGID 1v1ET AL CONDUIT
1. Steel:
1. Galva11ized inside and outside.
2. NFP A 70, Article 346.
3. UL-6.
4. UL listed.
34-00-125
@ 2000 Bonestroo, Rosene
Anderlik & Associates, Inc.
1 nO~O-?
BASIC ELECTRICAL
1vlATERIALS AND METHODS
2.02 WIRES Ai'.TD CABLES
A. 600V THW, THWN or THHN for panel wiring.
B. Cable for the vehicle detection loops shall be a preformed pave-over loop.
1. Installation to be done as recommended by manufacturer.
2. Size of cabling and number of turns shall be as per the
manufacturers specifications unless other\vise specified.
4. Joints at "T" to be chemically bonded perrnanufacturers
specifications.
5. T Box to be Carlon #E983D or approved equal.
6. T to be filled with 100% rubber sealant providing watertight seal wi
50 year life.
7. Loop wire to be 18 Ga. 5 conductor unshielded type eM 75 C 800,
style 2464 or approved equal.
8. Lead-in to be 18 Ga., THHNrrHWN, t\visted 12 turns per foot.
9. Lead-In to be protected \vith ENT conduit to pull box, chemically
bonded to T Box by manufacturer to ma11ufacturers specifications.
10. Loop inductance, Operating range: 75 to 750 Jih
11. Pave over loop shall be LIS #E-NLXX-18!XX or approved equal.
2.03 INDUCTIVE LOOP CONTROLLER FOR OVERHEAD DOOR
A. Loop Detector Controller:
1. Single (1) channel.
2. 1IDV Supply
3. Minimum of six (6) levels of sensitivity available betwee11 0.02 percent and
1.28 percent change in total loop inductance.
4. Peek Traffic-Sarasota 625X series, or equal.
34~OO,;.125
@ 2000 Bonestroo, Rosene
Anderlik & Associates, Inc.
1 h0'10- i
BASIC ELECTRICAL
tv1A TERlALS AND rvIETHODS
B. Vehicle detection inductive loop cable shall be a specified in Paragraph 2.02.
C. Provide all necessary mating connections for a complete loop control system as
specified herein.
D. Loop shall be 60" x 120" located 60" from the door, or as specified by
manufacturer.
2.04 DUCT SEALING COMPOUND
A. Soft, fibrous, slightly tacky, non-hardening and easily applied by hand at all \vorking
temperatures.
B. Clean and non-staining.
C. J.M. Clipper Corp. Duxseal, O-Z/Gedney DUX, or equal.
PART i - RXFJ'~TTTTON
3.01 mSTALLATION
A. The overhead door as designated on the dra\vings shall be controlled with the
il1ductive loop vehicle detector system specified in article 2.02 and 2.03 above.
COlnponents shall be installed as described belo\v:
1. Vellicle detection control llnit shall be installed in existing \vall mounted
enclosure that also houses the existing controller for the inside detector.
Contractor shall install unit wiring al1d any additional control components,
such as relays or timers, as needed to conform to the specified sequence of
operation. Terminal strips shall be used to connect the systenl leads to the
pin connector supplied with the unit.
2. Install t\vo-position keyed selector s\vitch on vehicle detection Ullit control
panel, adjacent to existing toggle s\vitch for inside vehicle detector. When
in the manual position, the selector switch shall disable the output of the
vehicle detection unit, so that the doors are controlled by the pushbutton
stations only. In the auto position, the vehicle detector Olltput shall be
enabled so that the door loop control works in cOl1junction with the
pushbutton stations.
3. Installation shall conform to manufacturer's instructions.
34-00-125
@ 2000 Bonestroo, Rosene
Anderlik & Associates, Inc.
160'=;0-4
BASIC ELECTRICAL
MA TERL<\LS ANDrvlETHODS
4. Vehicle detection system shall operate the door designated on the plans in
such way that upon approach of a vehicle to the door, acti\'ation of the loop
shall cause the door to open. After the vehicle enters or exits the garage, the
door shall reclose after an adjustable tinle period rrom zero to 30 seconds.
TIle vehicle detection system shall be interlocked with the existing photoeye
system in such a way the doors \vill not close if a vehicle or person is
detected underneath the doorway.
B. All conduit shall be kept dry and free of water or debris.
C. Where the conduit goes through the exterior of the building, it shall be at least 1811
above the level of the garage floor, and shall be sealed internally at the wall \vith
duct sealing compollnd.
D. All exposed conduit shall be schedule 80 PVC or Rigid Metal Conduit.
3.02 IVIEASUREMENT A1~TI PA Y1\1ENT
A. .L~ bid item "Loop Detector" has been provided on the proposal. Measurement \vill
be by the lump sum and include all work and materials reqllired to install the
overhead door loop detector system as described herein.
E~TI OF SECTIOl'J
34-00-125
@ 2000 Bonestroo, Rosene
Anderlik & Associates, Inc.
1 f\0')0- ~
BASIC ELECTRICAL
:VIA TERIALS AND !v1ETHODS
CONDITIONS OF THE CONTRACT
INDEX
PAGE NO-1-
SECTION 1 DEFINITIONS
1.
SECTION 2 BIDDING REQUlREI\tlENTS
5.
SECTION 3 AWARD AND EXECUTION OF CONTRACT, PROGRESS
AND COMPLETION OF ""ORK
7.
SECTION 4 CONTRACT DOCUMENTS: INTENT AND REUSE
9.
SECTION 5 AVAILABILITY OF LANDS; PHYSICAL CONDITIONS;
REFERENCE POil'ITS
11.
SECTION 6 INSURANCE AND BONDS, LEGAL RESPONSIBILITY AND
SAFETY
13.
SECTION 7 ENGI1\TEER..OWNER-CONTRACTOR RELATIONS, ARBITRATION
Al'lD INDEMNIFICATION
18.
SECTION 8 MATERIALS, EQUIPMENT, INSPECTION AND WORKMANSHIP
25.
SECTION 9 MEASUREMENT, PAYMENT AND PROJECT ACCEPTANCE
34.
SECTION 10 CHA1\fGES IN THE WORK
40.
SECTION 11 CHANGES OF CONTRACT PRICE AND CONTRACT TIME
42.
SECTION 12 SUSPENSION OF WORK Ai"TD TERlvfINATlON
46.
SECTION 13 MISCELLANEOUS
.dO
. o.
FORM OF AGREEMENT
PERFORMANCE BOND
LABOR AN'D PAYMENT BOND
GenerallSpecs/Condtns.gen
@ 1996 Bonestroo, Rosene,
Anderlik & Associates, Inc.
TABLE OF CONTENTS
CONDITIONS OF THE Co~rrRACT
SECTION 1 - DEFINITIONS
1.1 ACTS OF GOD
1.2 ADDENDA
1.3 AGREEMENT
1.4 BID SECURITY
1.5 BIDDER
1.6 CONTRACT
1.7 CONTRACT DOCUMENTS
1.8 CONTRACT PRICE
1.9 CONTRACTOR
1.10 CHANGE ORDER
1.11 DAY
1.12 DEFECTIVE
1.13 DRAWINGS
1.14 ENGINEER
1.15 FIELD ORDER
1.16 FINAL COMPLETION
1.17 MODIFICATION
1.18 NOTICE OF AWARD
1.19 NOTICE TO PROCEED
1.20 O\Vi'H3R
1.21 PERFORMANCE AND PAYMENT BONDS
1.22 PROJECT
1.23 PROPOSAL
1.24 RESIDENT PROJECT REPRESENTATIVE
1.25 SHOP DRA WINOS
1.26 SPECIFICA TrONS
1.27 SUBCONTRACTOR
1.28 SUBSTANTIAL COMPLETION
1.29 SURETY
1.30 WRITfEN NOTICE
1.31 WORK
GeneraVSpecs/Condtns.gen
@ 1996 Bonestroo, Rosene,
Anderlik & Associates. Inc.
- 1 ..
TABLE OF CONTENTS (CONT1D)
SECTION 2 .. BIDDING REOUIREMENTS
2.1 PROPOSAL FORMS
2.2 INTERPRETATION OF QUANTITY ESTIM:A TES
2.3 EXAMINATION OF PLANS, SPECIFICATIONS AND WORK SITE
2.4 ADDENDA
2.5 PREPARATION OF BID
2.6 RESERVATIONS AND/OR EXCEPTIONS
2.7 BID SECURITY
2.8 DELNERY OF PROPOSAL
2.9 OPENING OF PROPOSALS
2.10 EVALUATION OF PROPOSALS
2.11 CERTIFICATION OF INDEPENDENT PRICE DETERMINATION
SECTION 3 .. AWARD AND EXECUTION OF COl\TTRACT. PROGRESS & CO:rvfPLETION OF WORI(
3.1 AWARD OF CONTRACT
3.2 EXECUTION OF AGREEMENT
3.3 FAILURE TO EXECUTE AGREE1\.1ENT
3.4 RETURN OF BID SECURlTY
3.5 NOTICE TO PROCEED
3.6 CONTRACT TIME
3.7 SCHEDULE OF COMPLETION
3.8 COMPUTATION OF Tllv1E
3.9 LIQUIDATED DAMAGES
SECTION 4 - CONTRACT DOCUMENTS: INlENT AJ\TD REUSE
4.1 INTENT OF CONTRACT DOCUMENTS
4.2 ORDER OF PRECEDENCE
4.3 DISCREPANCIES
4.4 ADDITIONAL INSTRUCTIONS
4.5 DRAWll'-TGS AND SPECIFICATIONS AtJOB SITE
4.6 OWNERSHIP OF DRAWINGS AND SPECIFICATIONS AND REUSE
4.7 DIMENSIONS
GenerallSpecslCond tns.gen
@ 1996 Bonestroot Rosene,
AnderlUc & Associates, Inc.
- 2 -
TABLE OF CONTENTS (CONT'D)
SECTION 5 - A V AILABILITY OF LANDS: PHYSICAL CONDITIONS: REFERENCE POII\TTS
5.1 AVAILABILITY OF LANDS
5.2 PRIV ATE PROPERTY
5.3 SURVEYS
5.4 UTILITIES
5.5 INVESTIGATIONS
5.6 UNFORESEEN PHYSICAL CONDITIONS
SECTION 6 - INSURANCE AND BONDS~ LEGAL RESPONSIBILITY AND PUBLIC SAFETY
6.1 INSURANCE
6.2 PERFORlYIANCE AND OTHER BO~1)S
6.3 PATEI\TTS, FEES AND ROYALTIES
6.4 PERMITS AND LICENSES
6.5 LAWS, REGULATIONS AND SAFETY
6.6 WARNING SIGNS AND BARRICADES
SECTION 7 - ENGINEER-OWl\TER-CONTRACTOR RELATIONS. ARBITRATION & INDElvfNIFICATION
7.1 ENGINEER'S STATUS AND AUTHORITY
7.2 COl'ITRACTORIS RESPONSIBILITIES
7.3 O\VNERIS RESPONSIBILITIES
7.4 ASSIGNMENT OF CONTRACT
7.5 RIGHTS OF VARIOUS INTERESTS
7 .6 SEPARATE CONTRACTS
7.7 SUBCONTRACTS
7_8 ORAL AGREEMENTS
7 .9 NON-DISCRIMINATION IN EMPLOYME1\11'
7.10 DECISIONS ON DISAGREEMENTS
7.11 ARBITRATION
7.12 INDEMNIFICATION
GeneraliS pecs/Condtns.gen
@ 1996 Bonestroo, Rosene;
Anderlik & Associates, Inc.
- 3 -
TABLE OF CONTE~TTS (COf'..TTID)
SECTION 8.. MATERIALS. EOUIPM"ENT. INSPECTION AND WORKMANSHIP
8.1 MATERIALS AND EQUIP1\1ENT FURNISHED BY CONTRACTOR
8.2 EQUlV ALENT MATERIALS AND EQUIPMENT
8.3 MATERIALS FURNISHED BY O\VNcR
8.4 STORAGE OF MATERIALS
8.5 SAMPLES
8.6 FURNISHING OF PRODUCT DATA
8.7 QUALITY OF EQUIPMENT AND MATERIALS
8.8 SHOP DRAWINGS
8.9 ACCESS TO AND OBSERVATION OF \VORI(
8.10 TESTS AND INSPECTIONS
8.11 UNCOVERING THE WORK
8.12 CUTTING AND PATCHING
8.13 WARRANTY AND GUARANTEE
8.14 CORRECTION PERIOD
8.15 CORRECTION OR REMOVAL OF DEFECTIVE \VORK
8.16 ACCEPTANCE OF DEFECTIVE WORK
8.17 O\VNER MAY STOP WORK
8.18 OWNER MAY CORRECT DEFECTIVE WORK
GeneraliS pecs/Condtns .gen
@ 1996 Bonestroo, Rosene,
Anderlik & Associates, Inc.
- 4 -
T ABLE OF CONTENTS (CONTtD)
SECTION 9 - MEASUREMENT. PAYMENT AND PROJECT ACCEPTANCE
9.1 DETAILED BREAKDOWN OF CONTRACT AMOUNT
9.2 REQUEST FOR PAYMENT
9.3 ENGINEER'S ACTION ON A REQUEST FOR P A YMEi\TT
9.4 OWNERtS ACTION ON AN APPROVED REQUEST FOR PAYMENT
9.5 OWNER'S RIGHT TO \VITHHOLD PAYMENT
9.6 CONTRACTOR'S WARRANTY OF TITLE
9.7 SUBSTANTIAL COMPLETION
9.8 PARTIAL UTILIZA TI ON
9.9 FINAL INSPECTION
9.10 FINAL APPLICATION FOR PAYMENT
9.11 FINAL PAYMENT AND ACCEPTANCE
9.12 CONTRACTORtS CONTINUING OBLIGATION
9.13 WAIVER OF CLAIMS
SECTION 10 - CHANGES IN THE WORK
10.1 CHANGE ORDERS
10.2 FIELD ORDERS
10.3 UNAUTHORIZED WORK
10.4 ENGINEER RECOMMENDATIONS
10.5 NOTICE OF CHANGE TO SURETY
10.6 CLAIMS FOR ADDITIONAL COSTS
10.7 WORK DURING AN ElvIERGENCY
SECTION 11 - CHANGE OF C01\VfRACT PRICE AND CONTRACT TTh1E
11.1 CONTRACT PRICE
11.2 CHANGE IN CONTRACT PRICE
11.3 BASIS OF CHANGE
11.4 CHANGE OF CONTRACT TIME
GeneraliS pee s/Condtns .gen
@ 1996 Bonestroo, Rosene,
Anderlik & Associates. Inc.
- 5 -
TABLE OF CONTENTS (CONT'D)
SECTION 12 - SUSPENSION OF WORK AND TERMINATION
12.1 OWNER MAY SUSPEND WORK
12.2 OWNERMAYTERMINATE
12.3 CONVENIENCE TERMINATION BY THE O~ffiR
12.4 CONTRACTOR MAY STOP WORK OR TERMINATE
SECTION 13 - MISCELLANEOUS
13.1 LIMITATION OF LIABILITY
13.2 REMEDIES
13.3 PUBLIC CONVENIENCE
13.4 CROSSING UTILITIES, ETC.
13.5 SANITA..RY PROVISIONS
13.6 PRESERV ATIONOF HISTORICAL OBJECTS
13.7 USE OF PREMISES
FORM OF AGREEMEl\TT
PERFORMANCE BOND
LABOR AND MATERIAL PAYMENT BOND
GeneraliS ~...cslCondtns .gen
@ 1996 Bonestroo, Rosene.
Anderlik & Associates, Inc.
- 6 -
CONDITIONS OF THE CONTRACT
SECTlor~ 1
DEFWITIONS
1.1 ACTS OF GOD
An Act of God is an unusual, extraordinary and sudden manifestation of the forces of nature,
uncontrolled and uninfluenced by the power of man and without human intervention, that could not
under normal circumstances have been anticipated or expected. Ordinary weather conditions of
normal intensity for the locality shall not be considered as an Act of God.
1.2 ADDENDA
Written or graphic instruments issued prior to the opening of Bids which clarify, correct or change
the bidding documents or the Contract Documents.
1.3 AGREEMENT
The Agreement is the written document executed by the Owner and Contractor covering the
performance of the Work described in the Contract Documents.
1.4 BID SECURITY
The Bid Security, where required by the Advertisement or Information to Bidders, is a cashierls or
certified check, cash or Bid Bond accompanying the Proposal submitted by the bidder, pledging that
the bidder will enter into an Agreement vvith the Owner for the carrying out of the \Vark, should the
contract for the Work be awarded to him.
1.5 BIDDER
A Bidder is an individual or other entity submitting a Proposal for the advertised Wark.
1.6 CONTRACT
The Contract Documents form the Contract. The Contract represents the entire and integrated
agreement between the parties hereto and supersedes all prior negotiations, representations, or
agreements, either written or oral.
GenerallSpecs/Condtns.gen
@ 1996 Bonestroo, Rosene,
Anderlik & Associates, Inc.
- 1 -
l.7 ,C01\1TF~i\C:T' DOCUI\1ENTS
The Contract Documents consist of the follo\ving~ including an Addenda issued prior to the opening
of bids, Field Orders, Change Orders or oIher Modifications issued after execution of the Agreement:
(a) Dra\vings.
(b) Specifications:
(1) Bid DOCUD1ents (A..dvertisenlent, Addenda, Information to Bidders, Proposal and Bid
Security);
(2) Special Provisions;
(3) General and Specific Requirements;
(4) Conditions of the Contract (General and other conditions);
(5) Performance Bond and Labor and Ivlaterial Payment Bond;.
(6) Form of AgreelTI.ent;
(7) Detail Plates and other dra\vings attached to specifications;
1.8 CONTRACT PRICE
The n10neys payable by O\vner to Contractor under the Contract Documents as stated in the
Agreement.
1.9CONTRACT'OR
The Contractor is the person or entity or authorized representative thereof 11amed in the Contract
Documents.
1.10 CHANGE ORDER
A \vritten order to Contractor signed byO\vner authorizing an addition, deletion or revision in the
\Vork, or an adjustment in the Contract Price or the-Contract Time issued after the effective date of
the Agreement.
1.11 DAY
A calendar day of t\venty..four hours measured from midnight to the next midnight.
GeneraliS pee siC and EnS .gen
~l 1996 Bonesiroo. Rosene.
Anderlik & Associmes, Inc.
- L. -
1.12 DEFECTNE
Refers to Work that is unsatisfactory, damaged, faulty or deficient, does not conform to the Contract
Documents or does not meet the requirements of any inspection, test or approval referred to in the
Contract" Documents.
1.13 DRAWINGS
The Drawings are all plans, drawings (including revisions thereto) or reproductions thereof issued
by the Engineer pertaining to the Work provided for in the Contract Documents.
1.14 ENGINEER
The Engineer is the person or entity or authorized representative thereof named in the Contract
Documents.
1.15 FJELD ORDER
A written order issued by Engineer which orders minor changes in the Wark in accordance with
Paragraph 10.2, but which does not involve a change in the Contract Price or the Contract Time.
1.16 FlNAL COMPLETION
The W ork~ including any punch list items, has been completed in all respects in accordance \vith the
Contract Documents.
1.17 l\IIODIFICA TION
(a) A written amendment of the Contract Documents signed by both parties, (b) a Change Order, or
(c) a Field Order.
1.18 NOTICE OF AWARD
The written notice by Owner to the apparent succ.essful Bidder stating that upon compliance by the
apparent successful Bidder with the conditions precedent enumerated therein, within the time
specified, Owner will sign and deliver the Agreement.
1.19 NOTICE TO PROCEED
A written notice given by Owner to Contractor (with a copy to Engineer) fixing the date on which
the Contract Time will commence to run and on which Contractor shall start to perform his
obligation under the Contract Documents.
Genera1JS pecslCondtns .gen
@ 1996 Bonestroo. Rosene.
Anderlik & Associates, Inc.
.. 3 ..
1.20 OWNER
The Owner is the person or entity.or authorized representative thereof named in the Contract
Documents.
1.21 PERFORMANCE AND PAYMENT BONDS
The Perfonnance and Payment Bonds are the approved form of security furnished by the Contractor
and a Surety prior to the execution of the Agreement as a pledge of good faith on the pfu-t of the
Contractor and the Surety in the event of the Contractor1sdefault, covering the Contractor's faithful
performance under the Contract Documents and the payment of all obligations arising thereunder.
1.22 PROJECT
The total construction of which the Work to be provided under the Contract Documents may be the
whole, or a part as indicated elsewhere in the Contract Documents.
1.23 PROPOSAL
The Proposal is the offer of a bidder to perform the Work described in the Bid Documents.when
made out and submitted on the prescribed Proposal form, properly signed and secured.
1.24 RESIDENT PROJECT REPRESENT.lA.TNE
The authorized representative of the Engineer who is assigned to the site or any part thereof.
1.25 SHOP DRAWINGS
All drawings, diagrams, illustrations, schedules and other data which are specifically prepared by
Contractor, a Subcontractor, manufacturer, fabricator, supplier or distributor to illustrate some
portion of the Work and all illustrations, brochures, stfuldard schedules, performance charts,
instructions, diagrams and other information prepared by a manufacturer, fabricator, supplier or
distributor and submitted by Contractor to illustrate material or equipment for some portion of the
Work.
1.26 SPECIFICATIONS
That portion of the Contract Document generally bound in booklet form and consisting of the
documents identified in Paragraph 1.7 (b) of the Conditions of the Contract.
1.27 SUBCONTRACTOR
The Subcontractor is the person or other entity having a direct contract with the Contractor and acts
for or on behalf of the Contractor in executing any part of the Contract, but does not include any
separate Contractor or his Subcontractor or any material suppliers.
GeneraliS pecs/Condtns.gen
<9 1996 Bonestroo, Rosene,
AnderJik & Associates, Inc.
.. 4 ..
1.28 SUBSTANTIAL COMPLETION
The Work (or a specified part thereot) has progressed to the point where, in the opinion of Engineer
as evidenced by his certificate of Substantial Completion, it is sufficiently complete, in accordance
with the Contract Documents, so that the Work (or specified part) can be utilized for the purposes
for which it was intended; or if there be no such certificate issued, when final payment is due in
accordance with Paragraph 9.10 and 9.11. The tenns "substantially complete" and Ifsubstantially
completed" as applied to any Work refer to Substantial Completion thereof.
1.29 SURETY
A Surety is the person or other entity executing the Contractorrs Bid, Performance and Payment
Bonds.
1.30 WRITTEN NOTICE
Written Notice shall be deemed to have been served if delivered in person or sent by registered or
certified mail to the individual or other entity or to the last known business address of such
individual or entity. It shall be the duty of each party to advise the other parties to the Agreement
as to any change in the business address until completion and acceptance of the Work.
1.31 WORK
The entire completed construction or the various separately identifiable parts thereof required to be
furnished under the Contract Documents. Wark is the result of performing services, furnishing labor
and furnishing and incorporating materials and equipment into the construction, all as required by
the Contract Documents.
SECTION 2
BIDDmG REQUIREMENTS
2.1 PROPOSAL FORMS
The Owner will furnish Proposal Fonns to any qualified Bidder upon request.
2.2 INTERPRET A TION OF au ANTITY ESTIMATES
The schedule quantities as listed in the Proposal are to be considered approximate only and may be
increased, decreased or omitted as necessary to complete the Work as described in the Contract
Documents.
GeneraliS ~...csJCondtns .gen
@ 1996 Bonestroo, Rosene,
Anderlik & Associates, Inc.
- 5 -
2.3 EXAMlNA TION OF PLANS, SPECIFICATIONS AND WORK SITE
Each Bidder is required to examine carefully the site of the Work, the Proposal Forms, Specifications
and Plans. Sub;mission of a Proposal constitutes a representation by the Bidder that he has made
such examination, has familiarized himself with the conditions to be encountered, the. character,
quality and quantity of work to be performed and material to be furnished and has correlated his
observations with the requirements of these Contract Documents.
2.4 ADDENDA
Any Addenda issued prior to the time of receipt of Proposals shall be included in the Proposal and
shall be made part of the Contract Documents. Receipt of each Addendum shall be acknowledged
by the Bidder in his Proposal.
2.5 PREP ARA TION OF BID
The bidder shall submit his Proposal on the Proposal Form provided by the Owner. All blank spaces
in the Proposal must be filled in clearly and correctly in ink or typewritten. Any interlineation,
alteration or erasure must be initialed by the signer of the ProposaL The Proposal shall be signed
in ink by the individual or authorized representative making the Proposal.
2.6 RESERVATIONS AND/OR EXCEPTIONS
Reservations or exceptions shall be clearly stated in writing and attached to the Proposal. They \vill
be deemed to be a part of and incorporated into the Proposal. Bidders are advised that if -such
reservations or exceptions constitute a substantial deviation from the advertised terms and
conditions, their Proposals may be rendered non-responsive. The Bidder shall make no additional
stipulations on the Proposal nor qualify it in any other manner.
2.7 BID SECURITY
If so stipulated in the Advertisement for Bids, or Information to Bidders, each Proposal shail be
accompanied by a Bid Security in the required form and amount pledging that the Bidder will enter
into a Contract with the Owner on the terms stated in his Proposal and will, if required,fumish bonds
as described hereunder in Section 6 covering the faithful performance of the Contract and the
payment of all obligations arising thereunder. Should the Bidder refuse to enter into such Contract
or fail to furnish such bonds, if required, the amount of the Bid Security shall be forfeited to the
Owner as liquidated damages, not as a penalty. The Owner will have the right to retain the Bid
Security of Bidders until either (a) the Agreement has been executed and bonds, if required, have
been furnished by the Contractor to whom an award has been made or (b) the specified time has
elapsed so that unaccepted Proposals may be withdrawn, or (c) all Proposals have been rejected~
GeneraliS pecs/Condtns .gen
@ 1996 Bonestroo, Rosene.
Anderlik & Associates. Inc.
. - 6 -
2.8 DELIVERY OF PROPOSAL
Each Proposal shall b,e placed in an opaque envelope and securely sealed. The envelope shall be so
marked as to indicate the name and address of the Bidder, the type of work and the Project
Designation. If mailed, the sealed envelope shall be enclosed in a separate mailing envelope with
the notation "PROPOSAL ENCLOSED" on the face thereof. All Proposals shall be in the office of
the designated recipient before the time set for bid opening.
2.9 OPENING OF PROPOSALS
Proposals will be opened publicly and read aloud at the time, date and place designated in the
Advertisement.
2.10 EV ALVA TION OF PROPOSALS
The Owner reserves the right to reject any Proposal if it shows any omissions, alterations,
irregularities, is submitted subsequent to the time established in the Advertisement for Bids for
receipt of bids, or is unaccompanied by any required Bid Security. The Bidder further acknowledges
the right of the Owner to reject all Proposals and readvertise with the same or different Bid
Documents. In any event, the Owner reserves the right to waive any informalities, irregularities or
. minor deviations in the Proposal. On unit price Proposals, comparison of Proposals will be made
on the basis of the stated unit prices and unit prices will control in the event of a discrepancy
between the unit price and the extension or summation thereof. On fixed or lump sum price
Proposals, comparison of Proposals will be made on the basis of the lowest price that is responsive
to the Advertisement.
2.11 CERTIFICATION OF INDEPENDENT PRICE DETERMINATION
By submission of a Proposal, each Bidder certifies that:
(a) The prices in the Proposal have been arrived at independently, with
out consultation, communication or agreement as to any matters relating to such prices with
any other bidder or with any competitor for the purpose of restricting competition;
(b) The prices in the.Proposal have not been or will not be knowingly disclosed to any other
bidder or competitor prior to the Owner's opening of the Proposals;
(c) No attempt has been made or will be made by the Bidder to induce any other person or firm
to submit or not to submit a Proposal for the purpose of restricting competition.
GeneraVS pecs/Condtns .gen
@ 1996 Bonestroo, Rosene.
Anderlik & Associates. Inc.
_ ..7..
SECTION 3
AWARD AND EXECUTION OF CONTRACT4 PROGRESS &
COMPLETION OF WORK
3.1 AWARD OF CONTRACT
When the lowest responsive Proposal of the lowest responsible bidder is accepted and. within the
time limit established in the Advertisement for Bids, the Owner \vilI send him the necessary
Contract Documents and a Notice that the contract has been awarded to him, subject to the
furnishing of a Performance and Payment Bond, where required.
3.2 EXECUTION OF AGREEMENT
The lowest responsible bidder shall, \vithin 15 days after receiving the Notice of A\\/ard and Contract
Documents, sign the Agreement contained in the Contract Documents and return the signed
Agreement and such Bonds and Insurance forms as the successful Bidder may be required to furnish
to the Owner.
3.3 FAILURE TO EXECUTE AGREEMENT
Upon the failure of the lowest responsible bidder to furnish an acceptable Bond, where required, or
to execute the Agreement within the time above specified, the Owner may have the option to annul
the award and retain the Bid Security accompanying the Bid as liquidated damages and not as a
penalty. This shall not be the sole remedy of the Owner but upon default by the Bidder the Owner
may adopt any legal remedy which it may see fit to adopt.
3.4 RETURi~ OF BID SECURITY
All Bid Securities, except that of the lowest responsible bidder, will be returned within 45 days after
the date of the opening of Proposals unless stated otherwise in the Special Provisions. The Bid
Security of the lowest responsible bidder viill be returned upon receipt of the properly executed
Agreement and Bond.
3.5 NOTICE TO PROCEED
The date of commencement of the Work is the date set forth in the Notice to Proceed. Thereupon,
the Contractor shall begin and shall prosecute the Work regularly and \vithout interruption, unless
otherwise directed in writing by the Owner, with such manpower and equipment as is necessary to
complete the Work within the time stated in the Contract Documents.
GeneraliS pecs/Condtns.gen
@ 1996 Bonestroo, Rosene,
Anderlik & Associates, Inc.
- 8-
3.6 CONTRACT TTh1E
The Contractor shall complete, in an acceptable manner, all of the Work contracted for in the time
stated in the Contract Documents, subject only to extension for unforeseeable delays above and
beyond the control of the Contractor and his Subcontractors and without their fault or negligence.
Written notice of the Contractor's claim for such extension shall be given within ten (10) days of the
occurrence of the event giving rise to the claim; otherwise the claim shall be waived.
3.7 SCHEDULE OF COMPLETION
The Contractor shall submit, at such time as may reasonably be requested by the Engineer, schedules
which shall show the order in which the Contractor proposes to carry on the Work, with dates at
which the Contractor will start the several parts or the Wark and estimated dates of completion of
the several parts.
3.8 COMPUTATION OF TIME
When any period of time is referred to in the Contract Documents by days, it shall be computed to
exclude the first and include the last day of such period. If the last day of any such period falls on
a Saturday or Sunday or on a day made a legal holiday by the law of the applicable jurisdiction, such
day shall be omitted from the computation.
3.9 LIQUIDATED DAMAGES
3.9.1 Time is the essence of the contract. The Contractor thereby agrees that the OVvner v/iI1 be
entitled to liquidated damages for failure on the part of the Contractor to complete the Vv'ork within
the time limits provided for in the Contract Documents.
3.9.2 Should the Contractor fail to complete the project on or before the specified date, liquidated
damages in the amount specified in the Special Pro\'isions shall be deducted from any monies due
or coming due to the Contractor or shall be paid to the O\vner not as a penalty but as liquidated
damages for each and every calendar day that the contract shall remain uncompleted after the
specified date for Completion. Liquidated damages are specified herein because of the extreme
difficulty of ascertaining and establishing the actual damages which the Owner would sustain.
SECTION 4
C01\TTRACT DOCUMENTS: INTENT AND REUSE
4.1 INTENT OF CONTRACT DOCUMENTS
4.1.1 The Contract Documents comprise the entire Agreement between Owner and Contractor
concerning the Work. They may be altered only by a written Change Order.
GenerallSpecslCondtns.gen
@ 1996 Bonestroo, Rosene~
Anderlik & Associates, Inc.
.... - ..9..
4.1.2 The Contract Documents are complementary; \vhat is called for by one is binding as if called
for by all. If, during the performance of the Work, the Contractor finds a conflict, ambiguity or
discrepancy in the Contract Documents, he shall report it to engineer in writing at once and before
proceeding with the Work affected thereby~ however, Contractor shall not be liable to Owner or
Engineer for failure to report any conflict, ambiguity or discrepancy in the Contract Documents
unless Contractor had actual knowledge thereof or should reasonably have known thereof.
4.1.3 It is the intent of the Specifications and Drawings to describe a complete project (or part
thereof) to be constructed in accordance with the Contract Documents. Any Wark that may
reasonably be inferred from the Specifications or Drawings as being required to produce the intended
result shall be supplied whether or not it is specifically called for. When words which have a well-
known technical or trade meaning are used to describe Work, materials or equipment, such words
shall be interpreted in accordance with such meaning. Reference to standard specifications, manuals
or codes of any technical society, organization or association, or to the code of any governmental
authority, whether such reference be specific or by implication, shall mean the latest standard
specification, manual or code ineffe.ct at the time of opening of Bids (Of, on the. effective date of the
Agreement if there were no Bids), except as maybe otherwise specifically stated. However, no
provision of any referenced standard specification, manual or code (whether or Il0t specifically
incorporated by reference in the Contract Documents) shall change the duties and responsibilities
ofO\vner,Contractor or Engineer, or any of their agents or employees from those set forth. in the
Contract Documents. Clarifications and interpretations of the Contract Documents shall be issued
by Engineer as provided for in Paragraph 4.4.
4.1.4 The Contract Documents shall be governed by the law of the place of the Project.
4.2 ORDER OF PRECEDENCE
If there be a conflict between or among any of the terms or provisions of the Contract Documents,
which conflict cannot be reconciled by resorting to the intent of the Contract Documents under
Paragraph 4.1, the conflict shall be resolved by applying the following Order of Precedence:
(a) Agreement;
(b) Conditions of the Contract;
(c) Special Provisions;
(d) Specific Requirements;
(e) General Requirements;
(f) Drawings.
GeneraliS pecslCond tns. gen
@ 1996 Bonestroo, Rosene,
Anderlik & Associates, Inc.
- 10 ..
4.3 DISCREPANCIES
Any conflict, ambiguity or discrepancy in the Contract Documents, no matter how seemingly
insignificant to the Contractor, shall be brought immediately to the attention of the Engineer ror
clarification. Any Contractor who fails to bring any conflict, ambiguity or discrepancy to the
attention of the Engineer of which it was or should have been aware, shall assume the risk of loss
arising out of any such conflict, ambiguity, or discrepancy.
4.4 ADDITIONAL mSTRUCTIONS
Further or additional instructions may be issued by the Engineer during the progress of the Work by
the use of Dravvings or other means to clarify the intent of the Contract Documents or to explain or
illustrate Changes in the Work or Field Orders.
4.5 DRAV\lINGS AND SPECIFICATIONS AT JOB SITE
Contractor shall keep one record copy of all Specifications, Drawings, Addenda, Modifications,
Shop Drawings and samples at the site, in good order and annotated to show all changes made during
the construction process. These shall be available to Engineer for examination and shall be delivered
to Engineer for Owner upon completion of the Work.
4.6 OWNERSHIP OF DRAWINGS AND SPECIFICATION AND REUSE
All original Drawings and Specifications and other data furnished by the Engineer are and shail
remain his property. Copies thereof will be furnished to O\vner and are to be used only with respect
to this Project and are not to be used on any other project or extensions of this Project \vithout the
prior written consent of Engineer. Submission or distribution to meet official regulatory
requirements or for other purposes in connection with the Project are not to be construed as
publication in derogation of the Engineer's common law copyright or other reserved rights.
4.7 DIMENSIONS
Figured dimensions on the plans will be used in preference to scaling the Dra\vings. Any conflicts,
ambiguity, or discrepancy, shall be immediately brought to the attention of the Engineer before
proceeding with the affected Wark. Contractor shall assume the risk of loss for failure to bring to
the attention of the Engineer such conflict, ambiguity, or discrepancy.
GeneraliS pecslCondtns .gen
@ 1996 Bonestroo, Rosene,
Anderlik & Associates, Inc.
- 11 ..
SECTION 5
AVAILABILITY OF LANDS: PHYSICAL
CONDITIONS: REFERENCE POmTS
5.1 A V AlLABILITY OF LANDS
5.1.1 Owner shall furnish, as indicated in the Contract Documents, the lands upon which the Work
is to be perfonned, rights-of-way for access thereto, and such other lands which are designated for
the use of Contractor. Easements for permanent structures or permanent changes in existing
facilities will be obtained and paid for by Owner, unless otherwise provided in the Contract
Documents.
5.1.2 Contractor shall, at his expense, provide for all additional lands and access thereto that may
be required for temporary construction facilities or storage of materials and equipment. Contractor
shall confine his machinery and equipment, storage of materials and operation of workmen to those
areas described in the Contract Documents and such additional areas which he may provide at his
expense.
5.2 PRIVATE PROPERTY
The Contractor shall not enter upon private property for any purpose without obtaining written
permission from the owner thereof, and he shall be responsible for the preservation of ail property,
trees, monuments, etc., along and adjacent to the street and/or right-of-way, and shall use every
precaution necessary to prevent damage or injury thereto. He shall protect carefully from disturbance
or damage all monuments and property markers until an authorized agent has witnessed or otherwise
referenced their location and shall not remove them until directed.
5.3 SURVEYS
Unless otherwise specified, the Owner shall establish all base lines for the location of the principal
component parts of the Wark together with a suitable number of bench marks adjacent to the \V ork.
Based upon the information provided by the Owner, the Contractor shall develop and make all detail
surveys necessary for construction, including batter boards, stakes for pile locations and other
working points, lines and elevations. The Contractor shall be responsible for carefully preserving
bench marks, reference points and stakes, and, in the case of destruction thereof resulting from his
negligence or otherwise, the Contractor shall be charged with the expense and damage resulting
therefrom and shall be responsible for any mistakes that may be caused by the unnecessary loss or
disturbance of such bench marks, reference points and stakes.
GeneraUS pecsJCondtns.gen
@ 1996 Bonestroo, Rosene.
Anderlik & Associates, Inc.
. - 12 ..
5.4 UTILITIES
The Contractor shall be solely responsible for verifying the exact location of all utilities, whether or
not shown on the Drawings or referenced in the Specifications. Prior to the start or any construction,
the Contractor shall notify all utility companies having utilities in the Project area. The Contractor
shall have sole responsibility for providing temporary support and for protecting and maintaining
all existing utilities in the Project area during the entire period of construction, including but not
limited to the period of excavation, backfill and compaction. In carrying out this responsibility, the
Contractor shall exercise particular care, whenever gas mains or other utility lines are crossed, to
provide compacted backfill or other stable support for such lines to prevent any detrimental
displacement, rupture or other failure.
5.5 mVESTIGA TIONS
Reference is made to the Contract Documents for identification or those reports of investigations and
tests of subsurface or latent physical conditions at the site or otherwise affecting cost, progress or
performance of the Wark which have been relied upon by Engineer in preparation of the Drawings
and Specifications. Such reports or tests are not guaranteed as to accuracy or completeness and if
incorporated into the Contract Documents, they shall be for general information only. Contractor
shall be responsible for verifying site and subsurface conditions to his satisfaction prior to submitting
a bid on the project.
5.6 UNFORESEEN PHYSICAL CONDITIONS
Contractor shall immediately notify Owner and Engineer in writing of any subsurface or latent
physical conditions at the site or in an existing structure differing materially from those indicated or
referred to in the Contract Documents. Engineer v/ill promptly review those conditions and advise
Owner in writing if further investigation or tests are necessary. Promptly thereafter, Owner shall
obtain the necessary additional investigations and tests and furnish copies to Engineer and
Contractor. If Engineer finds that the results of such investigations or tests indicate that there are
subsurface or latent physical conditions which differ materially fron1 those intended in tb.e Contract
Documents, and which could not reasonably have been anticipated by Contractor, a Cl1ange Order
shall be issued incorporating the necessary revisions.
SECTION 6
mSURANCE. AND BONDS~
LEGAL RESPONSIBILITY A.ND PUBLIC SAFETY
6.1 mSURANCE
6.1.1 General: The Contractor shall not commence \vorlc under this contract until he has obtained
all insurance required under this Section and shall have filed the certificate of insurance or the
certified copy of the insurance policy with the Owner and Engineer. The Contractor shall not allow
any Subcontractor to commence work on his subcontract until all insurance required for the
Subcontractor has been obtained. Each insurance policy shall contain a clause providing that it shall
not be canceled by tpe insurance company without thirty (30) days written notice to the Owner and
Engineer of intent to cancel.
GeneraliS pe.cs/Condtns.gen
@ 1996 Bon-estroo, Rosene.
Anderlik & Associates, Inc.
-13..
Certificates of insurance shall be submitted on Standard Form C.I.C.C.-701 or ACORD 25 forms
and shall specifically note the clause providing for 30 day written notice to the Owner and Engineer
of intent to cancel. This clause shall read as follows:
"Should any of the above described policies be cancelled before the expiration date thereof, the
issuing company will mail 30 days written notice to the certificate holder named to the left. t1
6.1.2 Workman's Compensation & Emplover Liabilitv Insurance: The Contractor shall secure and
maintain during the life of this Contract, Workman's Compensation and Employer's Liability
Insurance as required by law for all his employees to be engaged directly or indirectly in the work
on the project under this Contract. In case any work is sublet, the Contractor shall require the
Subcontractor to similarly provide Workmen's Compensation and Employer's Liability Insurance for
all the latter's employees to be engaged directly or indire-ctly in such work. The Contractor shall also
maintain insurance required under any other Employee Benefit Acts in force or required by law at
the site of construction.
6.1.3 Contractor Comprehensive General & Automobile Liability: The Contractor shall procure and
maintain during the life of this Contract, Contractor's Comprehensive General and A~utomobile
Liability Insurance which shall protect him from claims for damages for personal injury, including
accidental death, as well as from claims for property damage which may arise from operations under
this contract, whether such operations be by himself or by any Subcontractor ,or by anyone directly
or indirectly employed by either of them. The insurance shall be in amounts listed below and shall
provide coverage under the following hazards:
1. Operations of Contractor.
2. Operations of Subcontractor (Contingent).
3. Products, including completed operations. This insurance is to be carried fora period of
one year after completion or acceptance of the work.
4. Contractual Liability (See Section 6.1.5).
. 5. Property Damage.
6. Broad Form Property Damage.
7. All Owned, Non-Owned and Hired Vehicles.
Minimum Limits - General Liability
1. Bodily inju,ry
$500,000.00 each occurrence
$500,000.00 completed operations
GeneraLIS pecslCondtns .gen
@ 1996 Bonestroo~ Rosene.
Anderlik & Associates I Inc;.
- 14 -
2. Property damage $100,000.0'0 each occurrence
$200,000.00 aggregate
Minimum Limits - Automobile Liability
1. Bodily injury
$250,000.00 each person
$500,000.00 each occurrence
2. Property damage $100,000.00 each occurrence
$200,000.00 aggregate
It is required that basic exclusions for damage caused by explosion, collapse and damage to
underground facilities, commonly knovJn as X, C, U exclusions, be removed fron1 the policies and
so indicated as covered in the declaration and on certificates of insurance. This provision of the
Conditions of the Contract will be waived on above ground projects where hazards of explosion
and/or collapse do not exist. The exclusion of explosion will be al10vled on underground projects
where blasting is not required.
In addition to all of the listed coverages, the Contractor shall procure and maintain an Uinbrel1a
Excess Liability Policy in a minimum limit of $1,000,000.00. Any Umbrella Excess Liability policy
in excess of $1,00'0,000 may be utilized to meet the above listed basic coverages.
6.1.4 Builder's Risk Insurance: Before commencement of the Wark, the Contractor shall provide
Builder's Risk Insurance on a multiple peril form in the full amount of the total construction and
material contract. Such insurance shall contain an appropriate rider to include as Additional Named
Insureds, the Owner, the Engineer and his consultants, and each of their officers, employees and
agents, all Subcontractors, the equipment Contractors and alloT their Subcontractors on the
construction premises. Such insurance may have a deductible clause but the deductible amount shall
be borne by the Contractor and shall not exceed $1,000.00.
The Builder's Risk Insurance required herein shall apply to projects involving construction of
structures and building only. The requirements of this section shall be waived on projects involving
only underground utilities, grading, street improvements and similar construction \vork~ but any
damage or loss to property shall be the sole responsibility of the Contractor until final acceptance
of the Work.
If the Owner finds it necessary to occupy or use a portion or portions of the Wark prior to substantial
completion thereof, such occupancy shall not commence prior to a time mutually agreed to by the
Owner and Contractor and to which the insurance company or companies providing the property
insurance have consented by endorsement to the policy or policies. This insurance shall not be
cancelled or lapsed on account of such partial occupancy. Consent of the Contractor and of the
insurance company or companies to such occupancy or use shall not be unreasonably withheld.
GeneraliS pecslCondtns .gen
(Q 1996 Bonestroo, Rosene.
Anderlik & Associat'es, Inc.
. .. 15 ..
The Owner and Contractor waive all rights against each other and the Subcontractors and their agents
and employees and against the Engineer and separate Contractors (if any) and their Subcontractors1
agents and employees, for damages caused by fire or other perils to the extent covered by insurance
provided under this section or any other property insurance applicable to the work.
6.1.5 Contractural Liability Insurance: To the fullest extent permitted by law, the Contractor shall
indemnify and hold harmless the Owner and the Engineer and their agents and employees from and
against all claims, damages, losses and expenses, including but not limited to attorneys' fees arising
out of or resulting from the performance of Work provided that any such claim, damage, loss or
expense (1) is attributable to bodily injury, sickness, disease or death, or to injury to or destruction
of tangible property (other than the Work itself) including the loss of use resulting therefrom, and
(2) is caused in whole or in part by any negligent act or omission of the Contractor, any
Subcontractor, anyone directly or indirectly employed by any of them or anyone for whose acts any
of them may be liable, regardless of \vhether or not it is caused in part by a party indemnified
hereunder. Such obligation shall not be construed to negate, abridge or otherwise reduce any other
right or obligation of indemnity which would otherwise exist as to any party or person described in
this Section.
In any and all claims against the Owner or the Engineer or any of their agents or employees by arty
employee of the Contractor, any Subcontractor, anyone directly or indirectly employed by any of
them or anyone for whose acts any of them may be liable, the indemnification obligation under this
Section shall not be limited in any way by any limitation on the amount or type of darn ages,
compensation or benefits payable by or for the Contractor or any Subcontractor under worker1s or
workmen's compensation acts, disability benefit acts or other employee benefit acts.
6.1.6 Minimum Insurance Requirements: Losses other than those covered by insurance shall be the
sole responsibility of the Contractors. The insurance requirements as set forth herein shall be
considered to be minimum requirements only. Any other insurance that may be necessary to provide
adequate coverage must be provided by the Contractors and shall be their sole responsibility.
6.1.7 Boiler Insurance: If a permanent boiler is to be installed as part of the project, the Owner will
be responsible for maintaining all boiler and machinery coverage. This coverage vv'ill be placed in
effect when the equipment is ready for inspection and operation. This coverage shall include..the
interests of the Owner, the Contractor, Subcontractors and Sub-Subcontractors.
6.2 PERFORMANCE AND OTHER BONDS
6.2.1 Contractor shall furnish Performance and Payment Bonds; each in an amount at least equal
to the Contract Price as security for the faithful performance and payment of all Contractor's
obligations under the Contract Documents. These Bonds shall remain in effect at least until one year
after the date of final payment, except asother\vise provided by la\v. Contractor shall also furnish
such other Bonds as are required by the Contract Documents. All Bonds shall be in the forms
prescribed by the Contract Documents and be executed by such Sureties as (A) are licens.ed to
conduct business in the state where the Project is located, and (B) are.named in the current list of
"Companies Holding Certificates of Authority as Acceptable Sureties on Federal Bonds and as
Acceptable Reinsuring Companies" as published in Circular 570 (amended) by the Audit Staff
Bureau of Accounts, U.S. Treasury Department. All Bonds signed by an agent must be accompanied
by a certified copy of the authority to act.
GeneraVS pecslCondtns.gen
@ 1996 Bonestroo, Rosene,
Anderlik & Associates, Inc.
. -16-
6.2.2 If the Surety on any Bond furnished by Contractor is declared bankrupt or becomes insolvent
or its right to do business is terminated in any state where any part of the Project is located or it
ceases to meet the requirements of clauses (A) and (B) of Paragraph 6.2.1, Contractor shall within
five days thereafter substitute another Bond and Surety, both of which shall be acceptable to Owner.
6.3 PATENTS. FEES AND ROYALTIES
Contractor shall pay all license fees and royalties and assume all costs incident to the use in the
performance of the 'Nark of any invention, design, process, product or device \vhich is the subject
of patent rights or copyrights held by others. If a particular invention, design, process, product or
device is specified in the Contract Documents for use in the performance of the Vlork and if to the
actual knowledge of Owner or Engineer its use is subject to patent rights or copyrights calling for
the payment of any license fee or royalty to others, the existence of such rights shall be disclosed by
Owner in the Contract Documents. Contractor shall indemnify and hold harmless Owner and
Engineer and anyone directly or indirectly employed by either of them from and against all claims,
damages, losses and expenses (including attorneys' fees) arising out of any infringement of patent
rights or copyrights incident to the use in the performance of the Wark or resulting from the
incorporation in the Work of any invention, design, process, product or device not specified in the
Contract Documents, and shall defend all such claims in connection with any alleged infringement
of such rights.
6.4 PERMITS AND LICENSES
All pennits and licenses necessary for the prosecution of the Wark shall be secured by the Contractor
prior to the commencement of the Wark. Contractor shall also pay all public utility charges,
governmental charges and inspection fees.
6.5 LA\VS~ REGULATIONS AND SAFETY
6.5.1 Contractor shall give all notices and comply with all laws, ordinances, rules and regulations
applicable to the Wark. If Contractor observes that the Specifications or Drawings are at variance
therewith, he shall give Engineer prompt written notice thereof, and any necessary changes shall be
adjusted by an appropriate Change Order or other Modification. If Contractor performs any Wark
knowing or being in a position to know it to be contrary to such la\vs, ordinances, rules and
regulations, and without such notice to Engineer, he shall b'ear all costs arising therefrom; however,
it shall not be his primary responsibility to make certain that the Specifications and Drawings are in
accordance with such laws, ordinances, rules and reguiations.
6.5.2 Contractor shall be responsible for initiating, maintaining and supervlsing all safety
precautions and programs in connection with the Work. He shall take all necessary precautions for
the safety of, and shall provide the necessary protection to prevent damage, injury or loss to:
(a) All employees on the Work and other persons who may be affected thereby;
GenerallSpecslCond tns.gen
@ 1996 Bonestroo, Rosene.
Anderlik & Associates, Inc.
.-. . - 17 -
(b) All the Wark and all materials or equipment to be incorporated therein, \vhether in
storage on or off the site; and
(c) Other property at the site or adjacent thereto, including trees, shrubs, lawns, \valks~
pavements, roadways, structures and utilities not designated for removal, relocation or
replacement in the course of construction.
6.5.3 Contractor shall comply with all applicable laws, ordinances, rules, regulations and orders of
any public body having jurisdiction for the safety of persons or property or to protect them from
damage, injury or loss. He shall erect and maintain, as required by the conditions (hId progress of
the Wark, all necessary safeguards for its safety and protection. He shall notify owners of adjacent
utilities when prosecution of the Work may affect them. All damage, injury or loss to any property
referred to in Section 6.5.2(b) and (c) caused, directly or indirectly, in whole or in part, by
Contractor, any Subcontractor or any directly or indirectly employed by any of them or anyone for
whose acts any of them may be liable, shail be remedied by Contractor. Contractor's duties and
responsibilities for the safety and protection of the Work shall continue until such time as all the
Wark is completed and Engineer has issued a notice to Ov/ner and Contractor that Work is
acceptable.
6.5.4 Contractor shall designate a responsible member of his organization at the site whose duty
shall be the prevention of accidents. This person shall be Contractor's superintendent unless
otherwise designated in \vriting by Contractor to O\vner.
6.5.5 Contractor agrees to indemnify the Owner and Engineer and their agents and employees
against all claims, demands, losses, damages and expenses (including attorneys' fees) arising out of
or resulting from the Contractor1s violation of any safety law, regulation or code (including without
limitation OSHA) or any other prudent precaution.
6.6 W ARNmG SIGNS AND BARRICADES
The Contractor shall provide adequate signs, barricades, colored lights and/or watchmen and take
all necessary precautions for the protection of the V/ork and the safety of the public. All barricades
and obstructions shall be protected at night by colored signal lights which shall be kept in operation
from sunset to sunrise.
SECTION 7
ENGINEER-OWNER-CONTRACTOR RELATIONS:
ARBITRATION: INDEMNlFICA TION
7.1 ENGINEER'S STATUS AND AUTHORITY
7.1.1 Engineer will b.e Owner1s representative during the construction period. The duties and
responsibilities and the limitations of authority of Engineer as Owner1srepresentative during
construction are set forth in the Contract Documents and shall not be extended without written
consent of Owner and Engineer.
GeneraJiS pecs/Condtns .gen
@ 1996 Bonestroo, Rosene,
Anderlik & Associates, Inc.
," 1 8 --
7.1.2 Engineer will make visits to the site at intervals appropriate to the various stages of
construction to observe the progress and quality of the executed Wark and to determine, in general,
if the Work is. proceeding in accordance with the Contract Documents. Engineer is not required to
make exhaustive or continuous on-site inspections to check the quality or quantity of the Work. On
the basis of such visits and on-site observations, Engineer will keep Owner informed of the progress
of the Work and will endeavor to guard Owner against defects and deficiencies in the Work.
7.1.3 If Owner and Engineer agree, Engineer will furnish a resident project representative to assist
Engineer in observing the performance of the Work. The Resident Project Representative shall work
under the authority and direction or the Engineer. The duties and responsibilities of the Resident
Project Representative shall not exceed those duties and responsibilities of the Engineer as set forth
in the Contract. It shall be to the discretion of the Engineer to delegate to the Resident Project
Representative those duties and tasks that are vvithin the authority of the Engineer to perform. Ln
general, the duties of the Resident Project Representative may consist of, but shall not be limited to,
the follo\ving:
1. General contract administration.
2. Periodic observation of the work.
3. Unit price quantity and record plan measuren1ents.
4. Schedule, perform and verify tests and inspections.
5. Monitor Contractor's progress performance.
6. Provide information for the Engineer's revie\v and decision concerning disputes and
defective work.
7.1.4 Engineer will issue with reasonable promptness such \vritten clarifications or interpretations
or the Contract Documents (in the form or Drawings or other\vise) as Engineer may determine
necessary, which shall be consistent with or reasonably inferable from the overall intent of the
Contract Documents. If Contractor believes that a \vritten clarification or interpretation justifies an
increase in the Contract Price or Contract Time, Contractor may make a claim therefor as provided
in Section 10 or Section 11.
7.1.5 Engineer will have authority to disapprove or reject Wark \vhich is defective, and will also
have authority to require special inspection or testing of the Work as provided in Paragraph 8.10,
whether or not the Work is fabricated, installed or completed. The Engineer shall not have charge
of or control over the Vl orkand shall have no authority to stop the \Ai ork.
GeneraliS pecs/Condtns .gen
(g 1996 Bonestroo, Rosene,
Anderlik & Associates~ Inc.
..19..
7.1.6 Neither Engineer's authority to act under this Section 70r elsewhere in the Contract
Do~uments nor any decision made by Engineer in good faith either to exercise or not exercise such
authority shall give rise to any duty or responsibility of Engineer to Contractor, any Subcontractor,
any manufacturer, fabricator, supplier or distributor, or any of their agents or employees or allY other
person performing any of the Work.
7.1.7 If a Resident Project Representative is assigned to the project, the purpose of his efforts shall
be to provide a greater degree of assurance to theO\vner that the Work is constructed in conformance
to the requirements of the Contract. The Resident Project Representative's efforts are for the benefit
of the Owner alone. Neither his authority to act nor his decision to exercise or not exercise such
authority shall give rise to any duty or responsibility to the Contractor, any Subcontractor, .any
manufacturer, fabricator, supplier or distributor, or any of their agents or employees or any other
person performing any of the Work. The Resident Project Representatives authority shall not exceed
limitations on Engineer's authority as set forth in the Contract Documents nor shall the Resident
Project Representative undertake any of the responsibilities or Contractor, Subcontractors, or
Contractor's Superintendent.
7.1.8 Whenever in the Contract Documents the terms ltasorderedH, Has directed", Has requiredH, lias
allowed", or terms of like effect or import are used, or the adjectives 'treasonable", "suitablell,
"acceptableH, ITproper", or "satisfactory", or adjectives of like effect or import are used to describe
requirements, direction, review or judgment of Engineer as to the Work, it is intended th'at such
requirements, direction, rev i e'W' or judgment will be solely to evaluate the Work for compliance with
the Contract Documents. The use of any such term or adjective never indicates that Engineer shall
have authority to supervise or direct perfonnance of the Wark or authority to undertake responsibility
contrary to the provisions of Paragraphs 7.1.9 or 7.1.10.
7.1.9 Engineer "viII not be responsible for Contractor's means, methods, techniques, sequences or
procedures of construction, or the safety precautions and programs incident thereto, and Engineer
will not be responsible forContractor1s failure to perfonn the Work in accordance \vith the Contract
Documents.
7 .1.1 0 Engineer will not be responsible for the acts or omissions of Contractor or of any
Subcontractors, or of the agents or employees of any Contractor or Subcontractor, or of any other
persons at the site of otherwise performing any of the Work.
7.2. CONTRACTOR'S RESPONSIB~ITIES
7.2.1. The Contractor shall supervise and directt~e work competently and efficiently, devoting such
attention thereto and applying such skills and expertise as may be necessary to perform the work in
accordance with the Contract Documents. The Contractor shall b-e solely resp.onsible for the means,
methods, techniques, quality of workmanship, sequences and procedures of construction. The
Contractor shall be responsible to see that the finished work complies accurately with the Contract
Documents.
GeneraliS paves/Condtns. gen
@ 1996 Bonestroo, Rosene.
Anderlik & Associates, Inc.
. .. 20 ..
A competent superintendent, who is acceptable to the Owner, shall be maintained on the Work site
and give efficient supervision to the Wark until its completion. The superintendent shall have full
authority to act on behalf of the Contractor, and all communications given to the superintendent shall
be as binding as if given to the Contractor. It shall be the responsibility of the Contractor's
superintendent to coordinate the work of all the Subcontractors. When required, the superintendent
shall be present on the site to perform adequate supervision and coordination.
Contractor shall provide competent, suitably qualified personnel to survey and layout the Work and
perform construction as required by the Contract Documents. Contractor shall at all times maintain
good discipline and order at the site.
The Contractor shall at all times be responsible for the conduct and discipline of his employees
and/or any Subcontractors. All workmen must have sufficient knowledge, skill and experience to
perform properly the worl( assigned to them. Any foreman and workrr!an employed by the
Contractor or Subcontractor who does not perform his \vork in a skillful manner, or appears to be
incompetent or to act in a disorderly or intemperate manner shall be removed immediately and shall
not be employed again in any portion of the Work.
7.2.2. The Contractor's duties with respect to materials, equipment, inspection and workmanship
are set forth in Section 8.
7.2.3. The Contractor's duties with respect to progress of the work are set forth in Section 3,
paragraphs 3.6, 3.7, 3.8 and 3.9.
7.2.4. The Contractor' duties with res.pect to insurance and bonds,.legal responsibility and safety are
set forth in Section 6.
7.3. OWNER'S RESPONSIBILITIES
7.3.1. The Owner shall issue all communications to the Contractor through the Engineer.
7.3.2. The O\vner shall furnish the data required of the Owner under the Contract Documents
promptly and shall make payments as provided to the Contractor promptly after they are due.
7.3.3. The O\vner's duties in respect of providing lands and easements and providing' engineering
surveys to estabiish reference points are set forth in paragraph 5.1 and 5.3. TheO\vner shall make
available to the Contractor copies of reports of investigations and tests of subsurface and latent
physical conditions. at the site or otheIVIise affecting perforrnanceof the work which have been relied
upon by the Engineer in preparing the drawings and sp.ecifications. Such reports are not guaranteed
as to accuracy or completeness and are not part of the Contract Documents.
7.3.4. In connection with the Owner's rights to request changes in the \vork in accordance \vith
Section 10, the Owner (especially in certain instances as provided in paragraph 10.4) is obligated to
execute Change Orders.
GeneraVS pecs/Condtns. gen
<9 1996 Bonestroo. Rosene.
Anderlik & Associates. Inc.
- 21 -
7.3.5. The Owner's responsibility in respect of certain inspections, tests and approvals is set forth
in paragraph 8.10.2.
7.3.6. In connection with Owner1s right to stop work or suspend work, see paragraphs 8.17 and 12.1.
Paragraph 12.2 deals with the Owner1s right to terminate services of the Contractor under certain
circumstances.
7.4 ASSIGNMENT OF COI\TTRACT
The Contractor shall neither sublet, sell, transfer, assignor otherwise dispose of the Contractor any
portion thereof, or of his right, title or interest therein, or his obligations thereunder, nor, if this
Contractor is a corporate entity, sublet, sell, transfer or assign a majority of the outstanding shares
of stock in the corporation, without prior written consent of the Owner. In case written consent is
given, the Contractor will be pennitted to sublet a portion of the contract or corporate stock thereof,
but shall perform, with his own organization, Wark amounting to not less than 50 percent of the total
original contract price. No subcontracts or transfer of contract or corporate stock shall release the
Contractor of his liability under the Contract or Bonds.
7.5 RIGHTS OF VARIOUS INTERESTS
Wherever Work being done by the Owner's forces or by other Contractors is contiguous to Work
covered by this Contract, the respective rights of the various interests involved shall be established
by agreement to secure the completion of the various portions of the Work in general harmony.
7.6 SEPARATE CONTRACTS
The Owner may let other contracts in connection \vith the Worlc of the Contractor. The Contractor
shall cooperate with other Contractors with regard to storage of materials and execution of their
Wark. It shall be the Contractor's responsibility to inspect all work by other Contractors affecting
his Work and to report to the Engineer any irregularities which will not permit him to commence or
complete his work in a satisfactory manner. His failure to notify the Engineer of such irregularities
shall indicate the work of other Contractors has been satisfactorily completed to receive his Work.
The Contractor shall not be responsible for defects of which he could not have known through
reasonable inspection thereof, which develop in the Work of others after the Work is completed. It
shall be the responsibility of the Contractor to measure the completed work in place and report to
the Engineer immediately any difference bet\veen completed work by others and the Drawings.
GeneraliS pecs/Condtns.gen
@ 1996 Bonestroo. Rosene,
Anderlik & Associates, Inc.
- - 22 -
7.7 SUBC01\TTRACTS
Nothing herein shall create any legal relationship between the Owner or Engineer and any
Subcontractor, and no Subcontractor shall have any rights under this Contractor's agreement with
the Owner. The Contractor's award of subcontracts shall be subject to the following:
7.7.1 Unless otherwise specified in the Contract Documents, the Contractor shall, upon receipt of
the executed Contract Documents, submit in writing to the Owner the names of the Subcontractors
proposed for the Work. Subcontractors may not be changed except at the request or with the consent
of the Owner. Contractor shall not employ any Subcontractor or other person or organization
(including those who are to furnish the principal items of materials or equipment), whether initially
or as a substitute against whom Owner or Engineer may have reasonable objection. A Subcontractor
or other person or organization identified in writing to Owner and Engineer by Contractor prior to
the Notice of Award and not objected to in writing by Owner or Engineer prior to the Notice of
Award will be deemed acceptable to O\vner and Engineer. Acceptance of any Subcontractor, other
person or organization by Owner or Engineer shall not constitute a waiver of any right of Owner or
Engineer to reject defective Worl(. If Owner or Engineer after due investigation has reasonable
objection to any Subcontractor, other person or organization proposed by Contractor after the Notice
of Award, Contractor shall submit another acceptable Subcontractor at no change in the Contract
Price. Contractor shall not be required to employ any Subcontractor, other person or organization
against whom Contractor has reasonable objection.
7.7.2 Contractor shall be fully responsible for all acts and omissions of his Subcontractors and of
persons and organizations directly or indirectly employed by them and of persons and organizations
for whose acts any of them may be liable to the same extent that Contractor is responsible for the acts
andonlissions of persons directly employed by Contractor. Nothing in the Contract Documents shall
create any contractual relationship between Owner or Engineer and any Subcontractor or other
person or organization having a direct contract with Contractor, nor shall it create any obligation on
the part of O\vner or Engineer to payor to see to the payment of any moneys due any Subcontractor
or other personar organization, except as may otherwise be required by la\v . Owner or Engineer
may furnish to any Subcontractor or other person or organization, to the extent practicable, evidence
of amounts paid to Contractor on account of specific Work done.
7.7.3 The divisions and sections of the Specifications and the identifications of any Drawings shall
not control Contractor in dividing the Work among Subcontractors or delineating the Work to be
performed by any specific trade.
7.7.4 All Work performed for Contractor by a Subcontractor will be pursuant to an appropriate
agreement between Contractor and the Subcontractor which specifically binds the Subcontractor to
the applicable terms and conditions of the Contract Documents for the benefit of Owner and
Engineer and contains. waiver provisions as required by paragraph 6.1.4. Contractor shall pay each
Subcontractor a just share of any insurance moneys received by Contractor on account of losses
under policies issued pursuant to paragraph 6.1.4.
GeneraJJS pecslCondtns.gen
@ 1996 Bonestroo, Rosene.
Anderlik & Associates, Inc.
.. 23 ..
7.8 ORAL AGREEMENTS
No oral order, objection, claim or notice by any party to the others shall affect or modify any of the
terms or obligations contained in any of the Contract Documents, and none of the provisions of the
Contract Documents shall be held to be waived or modified by reason of any act whatsoever, other
than by a definitely agreed upon waiver or modification thereof in writing, and no evidence shall be
introduced in any proceeding of any other waiver or modification.
7.9 NONDISCRIMINATION IN EMPLOYMENT
For Work under these Contract Documents, the Contractor agrees:
(a) That in the hiring of common or skilled labor for the performance of any \vork under this
Contract or any subcontract hereunder, no.Contractor,material supplier or vendor shall, by
reason of race, creed, color or national origin, discriminate against the person or persons who
are qualified and available to perform the Wark to which such employment relates;
(b) That no Contractor, material supplier or vendor shall, in any manner, discriminate against
or intimidate or prevent the employment of any person or persons, or on being hired, prevent
or conspire to prevent any person or persons from the performance of the Work under this
Contract on account of race, creed, color or national origin.
(c) Violation of t11is section shall be cause for cancellation or termination of the ..Agreement
bet\veen Owner and Contractor.
7.10 DECISIONS ON DISAGREEMENTS
7.10.1 Claims, disputes, disagreements, or other matters in question bet\tveen the Contractor and the
Owner relating to the execution or progress of the Work or the interpretation of the Contract
Documents shall be referred initially to the Engineer for decision which he will render in writing
within a reasonable time.
7.10.2 Any claim, dispute, disagreement or other matter that has been referred to the Engineer,
except any which has been waived by the making or acceptance of final payment, shall be subject
to arbitration under Paragraph 7.11 below upon the written demand of either party. However,no
demand for arbitration of any such claim, dispute or other matter may be made until the earlier of
the date on which the Engineer has rendered his written decision,or the tenth day after the parties
have presented their evidence to the Engineer or have been given a reasonable opportunity to do so,
if the Engineer has not rendered his written decisio~ by that, date.
GenerallSpecslCondtns.gen
@ 1996 Bonestroo, Rosene,
Anderlik & Associates. Inc.
- 24-
7.10.3 If a decision of the Engineer is made in writing and states that it is final but subject to appeal,
no demand for arbitration of a claim, dispute or other matter covered by such decision may be made
later than thirty days after the date on which the party making the demand received the decision. The
failure to demand arbitration within said thirtydayst period will result in the Engineer's decision
becoming final and binding upon the Owner and the Contractor. If the Engineer renders a decision
after arbitration proceedings have been initiated, such decision may be entered as evidence but \viiI
not supersede any arbitration proceedings unless the decision is acceptable to the parties concerned.
7.11 ARBITRATION
7.11.1 All claims, disputes and other matters in question arising out of, or relating to, the Contract
Documents or the breach thereof, except for claims which have been waived by the making or
acceptance of final payment, or barred by failure to demand arbitration within the time limits
specified, shall be decided by arbitration in accordance with the Construction Industry Arbitration
Ruies of the American Arbitration Association then obtaining unless the parties mutually agree
otherwise. Pre-arbitration discovery shall be conducted in accordance with Rules 26 through 37 of
the Federal Rules of Civil Procedure. No arbitration relating to the Contract Documents shall
include by consolidation, joinder or othenvise, any person or entity (including the Engineer), not a
party to this Agreement without the written consent of such other person or entity. This agreement
to arbitrate shall be specifically enforceable under the prevailing arbitration la\v. The a\vard rendered
by the arbitrators shall be final, and judgment may be entered upon it in accordance with applicable
law in any court having jurisdiction.
7.11.2 Notice of the demand for arbitration shall be filed in \vriting with the other party to the
Contract and with the American Arbitration Association, and a copy shall be filed with the Engineer.
The demand for arbitration shall be made within the time limits specified and in all other cases
within a reasonable time after the claim, dispute or other mattf.r in question has arisen, and in no
event shall it be made after the date when institution of legal or equitable proceedings based on such
claim, dispute, or other matter in question would be barred by the applicable statute or limitations.
7.11.3 The Contractor shall carryon the Wark and maintain the progress schedule during any
arbitration or other legal proceedings, unless otherwise agreed by him and the Owner in \vriting.
7.12 INDEMNIFICA T!ON
To the fullest extent pennitted by law, the Contractor shall indemnify and hold harrrJess the Owner
and the Engineer and their agents and employees from and against all claims, damages, losses and
expenses, including but not limited to attorneys' fees arising out of or resulting from the performance
of Work provided that any such claim, damage, loss or expense (1) is attributable to bodily injury,
sickness, disease or death, or to injury to or destruction of tangible property (other than the Work
itself) including the loss of use resulting therefrom~ and (2) is caused in whole or in part by any
negligent act or omission of the Contractor, any Subcontractor, anyone directly or indirectly
employed by any of them or anyone for whose acts any of them may be liable, regardless of whether
or not it is caused in part by a party indemnified hereunder. Such obligation shall not be construed
to negate, abridge or otherwise reduce any other right or obligation of indemnity which \vould
otherwise exist as to any party or person described in this Section.
GeneraliS pecsJCondtns.gen
@ 1996 Bonestroo, Rosene.
Anderlik & Associates, Inc.
. - 25 -
In any and all claims against the Owner or the Engineer or any of their agents or employees by any
employee of the Contractor, any Subcontractor, anyone directly or indirectly employed by any of
them or anyone for whose acts any of them may be liable, the indemnification obligation under this
Section shall not be limited in any way by any limitation on the amount or type of damages,
compensation or benefits payable by or for the Contractor or any Subcontractor under worker's or
workmenls compensation acts, disability benefit acts or other employee benefit acts.
SECTION 8
MATERIALS~ EOUIPMENT~ INSPECTIONANDWORKMft3.NSHIP
8.1 MATERIALS AND EOUIPMENT FURNISHED BY CONTRACTOR
8.1.1 Contiactor shall furnish all materials, equipment, labor, transportation, construction equipment
and machinery, tools, appliances, fuel~ power, light, heat, telephone, water and sanitary facilities and
all other facilities and incidentals necessary for the execution, testing, illitial operation and
completion of the Wark.
8.1.2 All materials used in the Wark shall be of good quality , new unless otherwise provided for in
the Contract Documents, shall meet the requiren1ents of the Specifications, and shall not be
incorporated into the Work until reviewed by the Engineer. If required by Engineer, Contractor shall
furnish satisfactory evidence (including reports of required tests) as to the kind and quality of
materials and equipment.
8.1.3 All materials and equipment shal1.be applied, installed, connected, erected, used~ cleaned and
conditioned in accordance \vith the instructions. of the applicable manufacturer, fabricator, supplier
or distributor, except as otherwise provided in the Contract Documents.
8.2 EOUrv ALENT MATERIALS p.~ND EOUJPMEI\TT
Whenever materials or equipment are specified or described in the Drawings or Specifications by
using the name of a proprietary item or the name of a particular manufacturer, fabricator, supplier
or distributor, the naming of the item is intended to establish the type, function and quality required.
Unless the name is followed by words indicating that no substitution is permitted, materials or
equipment of other manufacturers, fabricators, suppliers or distributors may be accepted by Engineer
if sufficient information is submitted by Contractor to a11o~~ Engineer to determine that the material
orequipment proposed is equivalent to that named. The procedure for review by Engineer will be
as set forth in paragraphs 8.2.1 and 8.2.2 below as supplemented in the General and Specific
Requirements.
GeneraVS pecslCondtns.gen
@ 1996 Bonestrooy Rosene.
Anderlik& Associates, Inc.
:. 26 -
8.2.1 Requests for review of substitute items of material and equipment will not be accepted by
Engineer from anyone other than Contractor. If Contractor wishes to furnish or use a substitute item
of. material or equipment Contractor shall make written application to Engineer for acceptance
thereof, certifying that the proposed substitute will perform adequately the functions called for by
the general design, be similar and of equal substance to that specified and be suited to the same use
and capable of performing the same function as that specified. The application will state whether
or not acceptance of the substitute for use in the Wark will require a change in the Drawings or
Specifications to adapt the design to the substitute and whether or not incorporation or use of the
substitute in connection with ~he Work is subject to payment of any license fee or royalty. All
variations of the proposed substitute from that specified shall be identified in the application and
available maintenance~ repair and replacement service will be indicated. The application will also
contain an itemized estimate of all costs that will result directly or indirectly from acceptance of such
substitute, including costs of redesign and claims of other Contractors affected by the resulting
change, all of which shall be considered by Engineer in evaluating the proposed substitute. Engineer
may require Contractor to furnish at Contractor's expense additional data about the proposed
substitute. Engineer will be the sole judge of acceptability, and no substitute \vill be ordered or
installed without Engineer's prior written acceptance. Owner may require Contractor to furnish at
Contractor's expense a special performance guarantee or other surety \vith respect to any substitute.
8..2.2 Engineer \-viII record time required by Engineer and Engineerfs consultants in evaluating
substitutions proposed by Contractor and in making changes in the Drawings or Specifications
occasioned thereby. Whether or not Engineer accepts a proposed substitute, Contractor shall
reimburse Owner for the charges of Engineer and Engineerts consultants for evaluating any proposed
substitute.
8.3 MATERIALS FURNISheD BY O\VNER
8.3.1 Materials specifically indicated shall be fumishe-d by the Owner. Before incorporating any of
the materials into the Work, the Contractor shall inspect the materials so furnished by' the Owner.
If the Contractor discovers any patent defects in material furnished by the Owner, he shall notify the
Engineer.
8.3.2 Unless otherwise noted or specifically stated, materials furnished by the Owner are considered
to be f.o.b. the nearest railroad station or truclc line. The Contractor shall transport the materials to
the job site, unload and properly protect all such materials from damage or loss. The Contractor
shall be responsible for material loss or damage after receipt of materials at the point of delivery.
8.4 STORAGE OF MATERIALS
Materials shall be so stored by the Contractor as to insure the preservation of their quality and fitness
for the Work. When considered necessary, they shall be placed on wooden platforms or other hard,
clean surfaces, and/or they shall be placed under cover and not on the ground. Stored materials shall
be located so as to facilitate prompt inspection. Private property shall not be used for storage
purposes without the \vritten permission of the Owner or lessee thereof.
GeneraVSpecslCondtns.gen
@ 1996 Bonestroot Rosene.
Anderlik & Associates, Inc.
- 27 ..
8.5 SAMPLES
All samples called for in the Specifications or required by the Engineer shall be furnished by the
Contractor and shall be submitted to the Engineer for his review. Samples shall be furnished so as
not to delay the commencement or completion of the Project. The Contractor shall furnish such
samples of material as may be required for examination and testing. All materiaisand workmanship
shall be in accordance \vith approved samples. All samples of materials for tests shall be ta!(en
according to methods provided for in the Specifications.
8.6 FURNISHING OF PRODUCT DATA
Product Data are illustrations, standard schedules, performance charts, instructions, brochures,
diagrams and other infonnati on furnished by the Contractor to iliustrate a material,. product or system
for some portion of the Wark.
8.6.1 The Contractor shall furnish one copy, or such additional copies as may be required .by the
Special Provisions, of complete Product Data for every manufactured item of equipment and all
components to be used in the Work, including specific performance data, material description, rating}
capacity, working pressure, material gage or thick.l~ess, brand name, catalog number and general t)rpe.
8.6.2 This data shall be compiled by the Contractor and reviewed by the Engineer before any of the
equipment is ordered.
8.6.3 All data shall be indexed according to specification section and paragraph for easy reference.
8.6.4 After revievv, this data shall become a part of the Contract, and may not be deviated from
except upon written approval of the Engineer.
8.6.5 Product Data for equipment reviewed by the Engineer does not in .any case supersede the
Contract Documents. The review by the Engineer shall not relieve the Contractor from responsibility
for deviations from Drawings or Specifications unless he has in \vriting called the Engineer's
attention to such deviations at the time of furnishing said data. Nor shall such review relieve the
Contractor from responsi~ility for errors of any sort in the items furnished. TheContractof shall
check the W orkdescribed by the Product Data with the Contract Documents for deviations and
errors.
8.6.6 It shall be the responsibility of the Contractor to insure that items to be furnished fit the space
available. He shall make necessary field measurements to ascertain space requirements, including
those for connections, and shall order such sizes and shapes or equipment thai the final installation
shall suit the intent and meaning of the Drawings and Specifications.
8.6.7 Where equipment requiring different aITangementofconnections from those shown is allowed,
it shali be the responsibility of the Contractor to instali the equipment so as to allow for proper
operation and in harmony \vith the intent of the Drawings and Specifications, and to make all
changes in the work required.by the different arrangement of connections.
GeneraVSpecsfCondtns .gen
@ 1996 Bonestfoo, Rosene.
Anderlik & Associates, Inc.
_ - 28 -
8.6.8 Product Data shall be promptly submitted by the Contractor after he has reviewed, checked
and approved the data to determine if they are in harmony with the requirements of the Project and
with the provisions of the Contract Documents and after he has verified all field measurements and
construction criteria, materials, catalog numbers and similar data. In submitting the Product Data,
the Contractor certifies that the work represented by the data has been coordinated with the Contract
Documents and all relevant field conditions.
8.7 QUALITY OF EOUIPlVIENT AND I\1ATERIALS
8.7.1 In order to establish standards of quality, the Engineer, in the Specifications, has referred to
certain products by name and catalog number. This procedure is not to be construed as eliminating
from competition other products of equal or better quality by other manufacturers where fully
suitable in design unlessotheryvise specificaliy stated in the Specifications (see Section 8.2 for
substitution procedure). If a product referenced by catalogue name or number is no longer available,
Contractor shall recommend to Owner and Engineer another product of comparable quality.
8.7.2 The Contractor shall furnish the complete list of proposed desired substitutions prior to
executing the Agreement, together with such engineering and Product Data as the Engineer may
require.
8.7.3 The Contractor shall abide by the Engineer1s recommendation when proposed substitute
materials or items of equipment are not recommended for installation and shall furnish the specified
material or item of equipment in such case. All proposals for substitutions shall be submitted in
writing by the General Contractor and not by individual trades or material suppliers. The Engineer
will revie\v proposed substitutions and make his recommendation in writing v.;ithin a reasonable
time.
8.8 SHOP DRAWINGS
8.8.1 The Contractor shall provide Shop Drawings, settings, schedules and such other drawings as
may be necessary for the prosecution of the Wark in the shop and in the field as required by the
Drawings, Specifications or Engineer's instructions. Deviations from the Drawings and
Specifications shall be called to the attention of the Engineer at the time of the first submission of
Shop Drawings and other drawings for approval. The Engineer's review of any drawings shall not
release the Contractor from responsibility for such deviations.
8.8.2 Shop Drawings shall be promptly submitted by the Contractor after he has revievved, checked
and approved the data to determine that they are in harmony with the requirements of the Project and
with the provisions of the Contract Documents and after he has verified all field measurements and
construction criteria, materials, catalog numbers and similar data. By submitting the Shop Drav/ings,
the Contractor certifies that the work represented by the Shop Drawings has been coordinated with
the Contract Documents and all relevant field conditions.
GenerdlS pecs/Condtns .gen
@ 1996 Bonestroo, Rosene.
Anderlik & Associates, Inc.
- 29-
8.8.3 Shop Drawings shall be submitted according to the following schedule:
(a) Not less than three copies or such other number of copies as may be required by the Special
Provisions shall be submitted \vith reasonable promptness and in such sequence as to. prevent delay
of the Wark.
(b) The Engineer shall, within fourteen (14) days of the submittal of any Shop Drawings, return
one copy to the Contractor marked with Engineer's comments.
(c) The Contractor shall then promptly make any necessary corrections or changes.to the Shop
Drawings to conform to the comments made by the Engineer.
(d) Following completion of such corrections or changes, the Contractor shall promptly
resubmit to the Engineer the required number of copies of the revised Shop Drawings.
8.8.4 Engineer will review with reasonable promptness Shop Drawings and samples, but Engineer1s
review shall be only for conformance with the design concept of the Project and for compliance with
the information given in the Contract Documents and shall not extend to means, methods, sequences,
techniques or procedures of construction or to safety precautions or programs incident thereto. The
review of a separate item as such will not indicate review of the assembly in which the item
functions. Contractor shall make any corrections required by Engineer and shall retum.the required
number of corrected copies of Shop Drawings and resubmit ne\v samples for review. Contractor
shall direct specific attention in \vriting to revisions other than the corrections called for by Engineer
on previous submittals. Contractor's stamp of approval on any Shop Drawing or sample shall
constitute a representation to Owner and Engineer that Contractor has either determined at,d verified
all quantities, dimensions, field construction criteria, materials, catalog numbers, and similar data
or assumes full responsibility for doing so, and that Contractor has reviewed or coordinated each
Shop Dravving or sample\vith the requirements of the Vlark and the Contract Documerlts~
8.8.5 Where a Shop Drawing or sample is required by the Specifications, no related Work shall be
commenced until the submittal has been reviewed by Engineer.
8.8.6 Engineer1s review of Shop Drawings or samples shall not relieve Contractor from
responsibility for any deviations from the Contract Documents unless Contractor .has in writing
called Engineer's attention to such deviation at the time or submission and Engineer has given
written concurrence with the specific deviation, nor shall any concurrence by Engineer relieve
Contractor from responsibility for errors or omission,s in the Shop Dra\vings.
8.9 ACCESS TO AND OBSERVATION OF WORK
8.9.1 Engineer and Engineer's representatives, other representatives of Owner, testing agencies and
governmental agencies with jurisdictional interests will have access to the Work at reasonable times
for their observation, inspection and testing. Contractor shall provide proper and safe conditions for
such access.
GeneraVSpecslCond tns. gen
@ i 996 Bonestroo, Rosene.
Anderlik & Associates. Inc.
- 30-
8.9.2 All materials and equipment and each part or detail of the. Wark shall be subject at all times
to observation by the Engineer and the Owner, and the Contractor \vill be responsible for strict
adherence to the intent of the Contract Documents in regard to quality of materials, workmanship,
and the diligent execution of the Work. Such observations may include mill, plant, or shop
inspection, and any material furnished under these Specifications is subject to such observation. The
Engineer and Owner shall be allowed access to all parts of the Work and shall be furnished with such
information and assistance by the Contractor as is required to make such observations.
8.10 TESTS AND mSPECTIONS
8.10.1 Contractor shall give Engineer timely notice of readiness of the Work for all required
inspections, tests or approvals.
8.10.2 If any law, ordinance, rule, regulation, code, or order of any public body having jurisdiction
requires any Work (or part thereof) to specifically be inspected, tested, or approved~ Contractor shall
assume full responsibility therefor, pay all costs in connection therewith and furnish Engineer the
required certificates of inspection, testing or approval. Contractor shall also be responsible for and
shall pay all costs in connection with any inspection or testing required in connection with Owner's
or Engineer1s acceptance of a manufacturer, fabricator, supplier or distributor of materials or
equipment proposed to be incorporated in the Wark, or of materials or equipment submitted for
approval prior toContractorfs purchase thereof for incorporation in the Work. The cost of all other
inspections, tests and approvals required by the Contract Documents shall be paid by Owner (unless
otherwise specified).
8.10.3 All inspections, tests or approvals other than those required by law, ordinance, rule,
regulation, code or order of any public body having jurisdiction shall be performed by organizations
selected by or acceptable toO~/ner or Engineer.
8.10.4 If any Wark that is to be inspected, tested or approved is covered vvithout \vritten concurrence
of Engineer, it must, if requested by Engineer, be uncovered for observation. Such uncovering shall
be at Contractor's expense unless Contractor has given Engineer timely notice of Contractor's
intention to cover such Wark and Engineer has not acted with reasonable promptness in response
to such notice.
8.10.5 Neither observations by Engineer nor inspections, tests or approvals by others shall relieve
Contractor from his obligations to perform the "Vork in accordance with the Contract Documents.
GeneraliS pecslCondtns. gen
<9 1996 Bonestroo, Rosene,
Anderlik & Associates, Inc.
- 31 -
8.11 UNCOVERThTG WORK
If any Work is covered contrary to the wiitten request or Engineer, it must, if requested by Engineer,
be uncovered for Engineer's observation and replaced at Contractor's expense. If Engineer considers
it necessary or advisable that covered W orkbe visually examined by Engineer or inspected ortested
by others, Contractor, at Engineer's request, shall uncover, expose or otherwise makea\~ailabie for
observation, inspection or testing as Engineer may require, that portion of the \V ork in question,
furnishing all necessary labor, materiai and eql.l:~pment. If it is fou-ndthat such Workisdef~ctive,
Contractor shall bear all the expenses of such uncovering, exposure, observation, inspection and
testing and of satisfactory reconstruction, including compensation for additional professional
services, and an appropriate deductive Change Order shall be issued. If, however, such Work is not
found to be defective, Contractor shall be allowed an increase in the Contract Price cran extension
of the Contract Time, or both, directly attributable to such uncovering,exposure, observ.ation,
inspection, testing and reconstruction if he makes a claim therefor as provided herein.
8.12 CUTTmG AND PATCHING
The Contractor shall do all necessary cutting, fixing or patching of the Work that may be required
to make its several parts fit together properly, or to properly receive the W orkof the various trades,
or, as required by the Drawings and Sp-ecifications, to complete the Work. He shall restore all. such
cut or patched \vork as approved by the Engineer. Cutting of existing structure that shall endanger
the Work, adjacent property, workmen or the public shall notb,edone.
8.13 WARRANTY AND GUARANTEE
Contractor warrants and guarantees to Owner and Engineer. that all vVork~ including materials and
equipment, will be in accordance \vith the Contract Documents and will not be faulty or defective.
Prompt notice of all defects shall be given to Contractor upon discovery. All defective Work,
whether or not in place, may be rejected, corrected or accepted as provided in paragraph 8.15 and
8.16. This warranty and guarantee shall be in addition to and notin limitation or any other warranty
or guarantee required by lav/ or by these Contract Documents, including the provisions of paragraph
8.14.
8.14 TVlO YEAR CORRECTIOI~ PERIOD
If within two years after the date of final acceptance of the project by the Owner or such longer
period of time as may be prescribed by law or by L~e terms of any applicable special guarantee
required by the Contract Documents or by any specific provision of the Contract Documents, fuiY
Work is found to be defective, Contractor shall promptly, without cost to Ov/ner and in accordance
with Ownerts written instructions, either correct such defective Work, or, if it has been rejected by
Owner, remove it from the site and replace it with non-defective Work. If Contractor does not
promptly comply with the terms of such instructions, or in an emergency where delay would cause
serious risk of loss or damage, Owner may have the defective Work corrected or the rejected Work
removed and replaced, and all direct and indirect costs of such removal and replacement, including
compensation for additional professional services, of Engineer or others, shall be paid by Contractor.
This obligation shall survive any termination of the Agreement between Owner and Contractor.
GenerallSpecs/Condtns .gen
@ 1996 Bonestroo, Rosene,
Anderlik & Associates. Inc.
- 32 -
8.15 CORRECTION OR REIvl0V AL OF DEFECTIVE WORK
If required by Engineer, Contractor shall promptly, without cost to O\vner and as specified by
Engineer, either correct any defective Work, whether or not fabricated, installed or completed, Of,
if the Wark has been rejected by Engineer, remove it from the site and replace it with non-defective
Wark.
8.16 ACCEPTANCE OF DEFECTIVE WORK
If, instead of requiring correction or removal and replacement of defective Work, Owner (and, prior
to Engineer's recommendation of final payment, also Engineer) prefers to accept it, Owner may do
so. In such case, if acceptance occurs prior to Engineer's recommendation of final payment, a
Change Order shall be issued incorporating the necessary revisions in the Contract Documents,
including appropriate reduction in the 'Contract Price; Of, if the acceptance occurs after such
recommendation, an appropriate amount shall be paid by Contractor to Owner.
8.17 O-WNER MAY STOP THE WORK
If the Work is defective, or Contractor fails to supply sufficient skilled workmen or suitable materials
or equipment, OVJner may order Contractor tastop the \V ork, or any portion thereof, until the cause
for such order has been eliminated; however, this right of Owner to stop the Work shall not give rise
to any duty on the part of Owner to exercise this right for the benefit of Contractor or any other party.
8.18 OWNER MAY CORRECT DEFECTIVE WORK
If Contractor fails within a reasonable time after written notice of Engineer to proceed to correct the
defective Work or to remove and replace rejected Work as required by Engineer in accordance \vith
Paragraph 8.15, or if Contractor fails to perfonn the Work in accordance with the Contract
Documents (including any requirements of the progress schedule), Owner may, after seven days'
written notice to Contractor, and Contractor's Surety, correct and remedy any such deficiency. In
exercising its rights under this paragraph, OV/ner shall proceed expeditiously. To the extent
necessary to complete corrective and remedial action, Owner may exclude Contractor from all or part
of the site, take possession .of all or part of the V/ork, and suspend Contractor's services related
thereto, take possession of Contractor's tools, appliances, construction equipment and machinery at
the site and incorporate in the Wark all materials and equipment stored at the site or for which
Owner has paid Contractor but which are stored elsewhere. Contractor shall allow Owner, Owner's
representatives, agents and employees such access to the site as may be necessary to enable Owner
to exercise its rights under this paragraph. All direct and indirect costs of Owner in exercising such
rights shall be charged against Contractor in an amount reviewed by Engineer, and such amounts
shall be deducted from the Contract Price. Such direct and indirect costs shall include, in particular
but without limitation, compensation for additional professional services required and all costs of
repair and replacement of work of others destroyed or damaged by correction, removal or
replacement of Contractor's defective Work. Contractor shall not be allowed an extension of the
Contract Time because of any delay in performance of the Wark attributable to the exercise by
Owner of Owner's rights hereunder.
GeneraliS pecslCondtns.gen
@ 1996 Bonestroo, Rosene.
Anderlik & Associates, Inc.
- 33 -
SECTION 9
rvIEASUREMENT~ PAYMENT AND PROJECT ACCEPTANCE
9.1 DETA~ED BREAKDOWN OF CONTRACT AMOUNT
Except in cases where unit prices form the basis for payment under the Contract Documents, the
Contractor shall, within ten (10) days of receipt of the Contract Documents, submit an itemized
b~e*down of the Contract Amount having the value, including an allowance for profit and overhead,
assigned to each part of the Work. Unless the breakdown of the Contract Amount is objected to by
the Owner, it shall be used as the basis for all Requests for Payment.
9.2 REOUEST FOR PAYMENT
The Contractor may submit periodically, but not more than once each month, a Request for PaymeIlt
for Worl( done and materials delivered and stored on the site. Payment for materials stored on the
site will be conditioned on the following:
(a) The Contractor shall submit evidence to establish the Ov/nerls title to such materials.
(b) Acceptable provisions have been made for storage.
(c) The Contractor shall provide and maintain insurance against all loss, theft, vandalism,
damage and similar peril for the full value of the stored material. The insurance on the stored
material shall name the Owner as insured~
Each Request for Payment shall be itemized and computed from the Work completed on all items
listed on the Detailed Breakdown of Contract Amount. Where unit prices are specified, the Request
for Payment shall be based on the quantities completed. The Owner shall pay to tl1eContractor an
amount not to exceed 950/0 of the amount earned under the Contract subject to the approval outline~d
in Section 9.3 and the provisions of Section 9.4 and 9.5. However, \\Then the "Vork required under
the Contract is 950/0 or more completed, upon recommendation of the Engineer, such portions of the
retained money shall be released as the Owner determines are not required to be retained to protect
the Owner's interest in satisfactory completion of the Contract.
At the option of the Contractor, retainage shall be paid to the Contractor in accordance wit.n the
follo\ving:
The Contractor may deposit bonds or securities with the Owner or in any bank or trust company
to be. held in lieu of cash retainage for the benefit of the Owner. In that event, the Owner shaH
reduce the retainage in an amount equal to the value of the bonds and securities and pay the
amount of the reduction to the Contractor. The interest on the bonds or securities shall be payable
to the Contractor as it accrues. Bonds and securities deposited or acquired in lieu of retainage
shall be of a character approved by the state treasurer including, but not limited to:
a. Bills, certificates, notes or bonds of United States;
b. Other obligations of the United States or its agencies;
GeneraVS pecs/Condtns .gen
@ 1996 Bonestroo, Rosene,
Anderlik & Associates, Inc.
. - 34 ..
c. Obligations of any corporation wholly owned by the federal government; and
d. Indebtedness of the Federal and National Mortgage Association.
If the Owner incurs additional costs as the result of the exercise of the option described in this.
paragraph, the Owner may recover the costs from the Contractor by reducing the final payment
due under the contract. As work on the contract progresses, the Owner shall, upon demand,
inform the Contractor of all accrued costs.
9.3 ENGINEER'S ACTION ON A REQUEST FOR PAYMENT
Within ten (10) days of submission of any Request for Payment by the Contractor, the Engineer shall
recommend to Owner:
(a) Approval of the Request for Payment as submitted; or,
(b) Approval of such other amount as Engineer shall consider is due the Contractor,
infonning the Contractor in \vriting of his reasons for recommending approval of the modified
amount; or,
(c) Withholding of the Request for Payment, informing the Contractor in writing of his
reasons for recommending withholding of the Request.
9.4 OWNER'S ACTION ON AN APPROVED REOUEST FOR PAYMENT
Within thirty (30) days from the date of recommending approval of a Request for Payment by the
Engineer, the Owner shall:
(a) Pay the Request for Payment as recommended by the Engineer.
(b) Pay such other amount in accordance with Section 9.5 as Owner shall decide is due
the Contractor, informing the Contractor and the Engineer in writing of the reasons for paying
the modified amount.
(c) Withholding payment in accordance with Section 9.5 informing the Contractor and the
Engineer in writing of O\vner's reasons for \vithholding payment.
9.5 OWNER'S RIGHT TO WITHHOLD PAYMENT
9.5.1 The Owner rnaywithhold payment in whole or in part to the extent necessary to protect itself
from loss on account of any of the following causes:
(a) Violation of any of the terms of the Contract DOCUITlents.
(b) Defective work not ren1edied, or completed work which has been damaged.
(c) Reasonable evidence indicating potential filing of claims by other parties against the
Contractor or Owner.
GeneraliS pn-....csICondtns.gen
@ 1996 Bonestroo, Rosene.
Anderiik & Associates. Inc.
, - 35 -
(d) Failure of the Contractor to make payments to Subcontractors, materialmen or
suppliers.
(e) Damage to the Owner or any other person.
(f) Contractor's unsatisfactory prosecution of the work.
9.5.2 When any of the above grounds for which payment is being withheld is remo,ved, payment
shall be made for the amount withheld.
9.5.3 Should the Owner fail to pay a Request for Payment within 30 days from the date of
recommendation of approval by the Engineer and should he fail to inform the Engineer and
Contractor in writing of the reasons for withholding payment, the Owner shall pay to the Contractor
simple interest on the past due amount at an annuai rate equal to the monthly index of long tenn
United States bond yields for the month prior to the month in which the obligation is incurred plus
an additional one percent p,er annum.
9.6 CONTRACTOR'S WARRANTY OF TITLE
Contractor warrants and guarantees that title to all Wark, materials and equipment co.vered by any
Application for Payment, whether incorporated in the Project or not, v/ill pass to Owner at the time
of payment free and clear of all liens, clairns, security interests and encumbrances (hereafter in these
Conditions of the Contract referred to as "Lienslf).
9.7 SUBSTANTIAL COMPLETION
9.7.1 When Contractor considers the entire \Vark ready for. its intended use Contractor shall, in
writing to Owner and Engineer, certify that the entire Work is substantially complete and request that
Engineer issue a proposed Certificate of Substantial Completion. Viithin a reasonable time
thereafter, Owner, Contractor and Engineer shall make an inspection of the Work to determine the
status of completion. If Engineer does not consider the Wark substantially complete, Engineer \vill
notify Contractor in writing giving his reasons therefor. If Engineer considers the \Vork substantially
complete, Engineer will prepare and deliver toOvvner a proposed Certificate of Substantial
Completion v"hich shall fix the date of Substantial Completion~ There shall be attached to the
proposed Certificate a list of items C1punch lisf') to be completed or corrected before final payment.
9.7.2 Owner shall have seven days after receipt of tile Certificate during \vhich he may make written
objection to Engineer as to any provisions of the Certificate or attached list. If, after considering
such objections, Engineer concludes that the Wark is not substantially complete, Engineer will
within fourteen days after submission of the proposed Certificate to Owner notify Contractor in
writing, stating his reasons therefor. If, after consideration of Owner's objections, Engineer considers
the Wark substantially complete, Engineer will within said fourteen days execute and deliver to
Owner and Contractor a final Certificate of Substantial Completion (with any revised list of -items
to be completed or corrected) reflecting such changes from the proposed Certificate as he believes
justified after consideration of any objections from Owner. At the time of delivery of the proposed
Certificate of Substantial Completion Engineer \\'i11 deliver to Owner and Contractor a written
recommendation as to division of responsibilities pending final payment between Owner and
Contractor with respect to security~ operation, safety, maintenance, heat, utiiities and insurance.
GenerallSpecslCondtns4gen
@ 1996 Bonestroo, Rosene,
Anderlik & Associates, Inc.
- 36 ..
Unless Owner and Contractor agree otherwise in writing and so inform Engineer prior to his issuing
the final C-ertificate of Substantial Completion, Engineer's aforesaid recommendation will be binding
on Owner and Contractor until final payment. Owner shall have the right to exclude Contractor from
the Work after the date of Substantial Completion, but Owner shall allow Contractor reasonable
access to complete or correct items on the list of items to be completed or corrected.
9.8 PARTIAL UTILIZATIOl~
Use by Owner of completed portions of the work may be accomplished prior to Substantial
Completion of all the Work subject to the following:
9.8.1 Owner at any time may request Contractor in writing to permit Owner to use any part of the
Wark which Owner believes to be substantially complete and which may be so used without
significant interference with construction of the other parts of the Work. If Contractor agrees,
Contractor will certify to Owner and Engineer that said part of the Wark is substantially complete
and request Engineer to issue a proposed Certificate of Substantial Completion for that part of the
Work.
9.8.2 Within a reasonable time thereafter Owner, Contractor and Engineer shall make an inspection
of that part of the Wark to determine its status of completion. If Engineer does not consider that part
of the Wark to be substantially complete, Engineer vvilI notify Owner and Contractor in writing
giving his reasons therefor. If Engineer considers that part of the Wark to be substantially complete,
Engineer will execute and deliver to Owner and. Contractor a proposed Certificate' t<Ylhat effect,
fixing the date of Substantial Completion as to that part of the Wark, attaching thereto a list of items
to be completed or corrected before final payment.
9.8.3 Prior to issuing a Certificate of Substantial Completion as to part of the Work, Engineer "viII
deliver to Owner and Contractor a written recommendation as to the division of responsibilities
pending final payment between Owner and Contractor with respect to security, operation, safety,
maintenance, utilities and insurance for that part of the Work which shall become binding upon
Owner and Contractor at the time of issuing the final Certificate of Substantial Completion as to that
part of the Work unless Owner and Contractor shall have otherwise agreed in writing and so
informed Engineer. Owner shall have the right to exclude Contractor from any part of the Work
which Engineer has so certified to be substantially complete, but Owner shall allow Contractor
reasonable access to complete or correct items on the list of items to be completed or corrected.
9.8.4 In lieu of the issuance of a Certificate of Substantial completion as to part of the Work, Owner
may take over operation of a facility constituting part of the Work whether or not it is substantially
complete if such facility is functionally and separately usable; provided, that prior to any such
takeover, Owner and Contractor have agreed as to the division of responsibilities between O\\'TIer
and Contractor for security, operation, safety~ maintenance, correction period, heat, utilities and
insurance with respect of such facility.
9.8.5 No occupancy of _part of the Work or taking over of operations of a facility will be
accomplished prior to compliance with the requirements of Section 6.1.4, Paragraph 3, in respect of
property insurance.
GeneraliS pecslCondtns. gen
@ 1996 Bonestroo, Rosene,
Anderlik & Associates, Inc.
.-. , - 37 -
9.9 FINAL INSPECTION
Upon written notice from Contractor that the Work is complete, Engineer will make a final
inspection with Owner and Contractor and will notify Contractor in writing of all particulars in
which this inspection reveals that the Work is incomplete or defective. Contractor shall immediately
take such measures as are necessary to remedy such deficiencies.
9.10 FINAL APPLICATION FOR PAYMENT
After Contractor has completed all items to be completed or corrected to the satisfaction of Engineer
and delivered all maintenance and operating instructions, schedules, guarantees, bonds, certificates
of inspection, marked-up record documents and other documents --all as required by the Contract
Documents, and after Engineer has indicated that the Wark is acceptable (subject to the provisions
of Section 9.12), Contractor may make Application for Final Payment following the procedure for
progress payments. The Final Application for Payment shall be accompanied by all documentation
called for in the Contract Documents and such other data and schedujes as Engineer may reasonably
require, together with complete and legally effective releases or \vaivers (satisfactory to Owner) of
all Liens arising out of or filed in connection \vith the \Jlork. In lieu thereof and as approved by
OV/ner, Contractor may furnish receipts or releases in full; an affidavit of Contractor that the releases
and receipts include all labor, services, material and equipment for which a Lien .could be filed; a
representation that all payrolls, material and equipment bills, and other indebtedness connected\vith
the Wark for which Owner or his property might in any way be responsible, have been paid or
otherwise satisfied; and, consent of the Surety, if any, to final payment. If any Subcontractor,
manufacturer, fabricator, supplier or distributor fails to furnish a release or receipt in full, Contractor
shall furnish a Bond or other collateral satisfactory to OV/ner to indemnify Owner against any Lien.
9.11 FINAL PAYMENT AND ACCEPTANCE
9.11.1 If, on the basis of Engineer's observation of the VI orkduring construction and final
inspection, and Engineer's review of the Final Application for Payment and accompanying
documentation, all as required by the Contract Documents, Engineer is satisfied that tIle Work has
been completed and Contractor has fulfilled all of his obligations under the Contract Documents,
Engineer will, within ten days after receipt of the Final Application for Payment, indicate in writing
his recommendation of payment and present the application to Owner for payment. Thereupon
Engineer will give written notice to Owner and Contractor that the Work is acceptable subject to all
applicable provisions of the Contract Documents. Other\vise, Engineer will return the Application
to Contractor, indicating in \vriting the reasons for refusing to recornnlend final payment, in which
case Contractor shall make the necessary corrections and resubmit the Application.
GeneraliS pecs/Condtns .gen
@ 1996 Bonestroo~ Rosene.
Anderlik & Associates, Inc.
- 38 --
9.11.2 If the Application and accompanying documentation are appropriate as to form and
substance, Owner shall, within thirty days after receipt thereof pay Contractor the amount
recommended by Engineer. If, through no fault of Contractor, final completion of the \Vork is
significantly delayed thereof and if Engineer so confirms, Owner shall, upon receipt of Contractor's
Final Application for Payment and recommendation of Engineer, and without terminating the
Agreement, make payment of the balance due for that portion of the Wark fully completed and
accepted.
9.11.3 If any remaining balance to be held by Owner for Work not fully completed or corrected is
less than the retainage stipulated in the Agreement, and if Bonds have been furnished as required
herein, the written consent of the Surety to the payment or the balance due for that portion of tbe
Work fully completed and accepted shall be submitted by Contractor to Engineer with the
Application for such payment. Such payment shall be made under the terms and conditions
governing final payment, except that it shall not constitute a waiver of claims.
9.12 CONTRACTOR'S CONTINUING OBLIGATION
Contractor's obligation to perfonn and complete the Work in accordance ~vvith the Contract
Documents shall be absolute. Neither recommendation of any progress or final payment by
Engineer, nor the issuance of a Certificate of Substantial Completion, nor any payment by Owner
to Contractor under the Contract Documents, nor any use or occupancy or the Work or any part
thereof by Owner, nor any act of acceptance by Ov/ner nor any failure to do so, nor the issuance of
a notice of acceptability by Engineer pursuant to Sections 9.10 or 9.11, nor any correction of
defective Worle by Owner shall constitute an acceptance of Work not in accordance \vith the Contract
Documents or a release of Contractor's obligation to nerform the \\'ork in accordance \vith the
'-' J.
Contract Documents.
9.13 WANEROFCLAIMS
The making and acceptance of final payment shall constitute:
9.13.1 A waiver of all claims by Owner against Contractor, except claims arising from unsettled
Liens, from defective work appearing after final inspection pursuant to Section 9.9 or from failure
to comply with the Contract Documents or the terms of any special warranties or guarantees
specified therein; however, it shall not constitute a \vaiver by Owner of any rights in respect to
Contractor's continuing obligations under the Contract Documents; and
9.13.2 A waiver of all claims by Contractor against Owner other than those previously made in
writing and still unsettled.
GeneraliS pecslCond tns.gen
@ 1996 Bonestroo, Rosene.
Anderlik & Associates. Inc.
.. 39 -
SECTION 10
CHANGES IN THE WORK
10.1 CHANGE ORDERS
Without invalidating the Agreement, Owner may, at any time or from time to time, order additions,
deletions or revisions in the Work; these vlill be authorized by Change Orders. Upon receipt of a
Change Order, Contractor shall proceed with the Work involved. All such Work shall be executed
under the applicable conditions of the Contract Documents. If any Change Order causes an increase
ordecrease in the Contract Price or an extension or shortening of the Contract time, an equitable
adjustment will be made as provided in Section 10 or Section 11 on the basis. of a claim made by
either party.
10.2 rlliLDORDERS
Engineer may authorize minor changes in the Work not involving an adjustment in the Contract
Price or the Contract Time, which are consistent \vith the overall intent of the Contract Documents.
These may be accomplished by a Field Order and shall b.e binding on Owner, and also on Contractor
who shall perform the change promptly. If Contractor b.elieves that a Field Order justifies an
increase in the Contract Price or Contract Time, Contractor may make a claim therefor .as provided
herein.
1 0.3 UNAUTHORIZED WORK
Additional Work perfoITI1ed \vithout authorization of a Change Order will not entitle Contractor to
an increase in the Contract Price or an extension of the Contract Time, except in the case of an
emergency.
10.4 ENGWEER RECOMMENDATIONS
Owner shail execute appropriate Change Orders prepared by Engineer covering changes in the V\T ark
which are required by Owner, or required b-ecause of unforeseen physical conditions or emergencies,
or because of uncovering Work found not to .bedefective, or because of an)' other claim of
Contractor for a change in the Contract Time or the Contract Price which is recommended by
Engineer.
10y5 NOTICE OF CHANGE TO SURETY
If notice of any change affecting the general scope of the W orkor change in the Contract Price is
required by the provisions of any Bond to be given to the Surety, it will be Contractor's responsibility
to so notify the Surety, and the amount of each applicable Bond shall be adjusted accordingly.
Contractor shall furnish proof of such adjustment to Owner.
GeneraliS pecs/Condtns.gen
@ 1996 Bonestroo, Rosenet
Anderlik & Associates, Inc.
< - 40 -
10.6 CLAIIVIS FOR ADDillONALCOSTS
If the Contractor wishes to make a claim for an increase in the Contract Sum, he shall give the
Engineer written notice thereof within ten (10) days after the occurrence of the event giving rise to
such claim. This notice shall be given by the Contractor before proceeding to execute the Work,
except in an emergency endangering life or property in which.case the Contractor shall proceed in
accordance with Paragraph 10.7. No such claim shall be valid unless so made. If the Owner and t.l-}e
Contractor cannot agree on the amount of the adjustment in the Contract Sum, it shall be referred
to the Engineer in accordance with Paragraph 7.8. Any change in the Contract Sum resulting from
such claim shall be authorized by Change Order.
If the Contractor claims that additional cost is involved because of but not limited to (1) any written
interpretation of the engineer, (2) any order by the Owner to stop the Work where the Contractor was
not at fault, (3) any written order for a minor change in the Wark or (4) failure of payment by the
Owner, Contractor shall make such claim as provided in this Subparagraph.
10.7 WORK DURING AN EMERGENCY
10.7.1 In any emergency affecting the safety of persons or property, the Contractor shall act to
prevent threatened damage, injury or loss. In all cases he shall, as soon as practicable, notify the
Owner of the emergency and he shall not wait for the instructions before proceeding to protect both
life and property.
10.7.2 Any additional compensation or extension of time claimed by the Contractor on account of
said emergency work shall be determined under Paragraph 10.6.
SECTION 11
CHANGE OF CONTRACT PRICE A-NDC01'1TRACT TIME
11.1 CONTRACT PRICE
The Corltract Price constitutes the total compensation (subject to authorized adjustments) payable
to Contractor for performing the Work. All duties, responsibilities and obligations assigned to or
undertaken by Contractor shall be at his expense without change in the Contract Price.
GenerallS pecslCondtns. gen
@ 1996 Bonestroo, Rosene,
Anderlik & Associates, Inc.
..41..
11.2 CHANGE IN CONTRACT PRICE
11.2.1 Except where u it prices form the basis for payment under the Contract Documents, the
Contract Price may only be changed by a Change Order. Any claim for an increase in the Contract
Price shall be based on written notice delivered to Owner and Engineer \vithin ten (10) days of the
occurrence of the event giving rise to the claim. Notice of the amount of the claim with supporting
data shall be delivered v.lithin thirty (30) days of such occurrence unless Engineer . allows an
additional period of time to ascertain accurate cost data. All claims for adjustment in the Contract
Price shall be determined by Engineer if Owner and Contractor cannot otherwise agree on the
amount involved. Any change in the Contract Price resulting from any such claim shall be
incorporated in a Change Order.
11.2.2 Where unit prices form the basis of payment and the quantity of any item of Work as.given
in ~he Proposal is increased or decreased, payment for such item will be made on the basis of actual
quantity completed, at the contract unit price for such item.
11.3 BASIS OF CHA~GE
The method of determining the cost or credit to the Owner resulting from a change in the work shall
be determined and mutually agreed upon by Owner and Contractor in advance of performance of the
change in \vorl( in one or more of the following ways:
11.3.1 By mutual acceptance of a lump sum pioperly itemized,
11.3.2 By unit prices stated in the Contract Documents or subsequently agreed upon (unitprices
shall include an allowance for Contiactor's main office expense~ overhead, profit and bond), or
11.3.3 By actual cost of the changed work, plus an allo\vance for overhead, supervision and profit,
as defined as follows:
1. The !leost of the changed work'. shall r.oean costs necessarily incurred in the proper
performance of the changed work and paid by Contractor at rates not higher than the standard paid
in the ioeality of the worl( (except with prior consent of theO\vner) as more specifically defined as
follovY's:
a. The cost of the changed work shall include:
(1) Wages paid for labor in the direct employ of Contractor in the performance of.the
changed work in the field or in the fabrication shop .under applicable collective bargaining
agreements or under a salary or wage schedule agreed upon by Contractor and Owner, plus
a payroll markup of 40 percent to cover all overhead items applicable to payroil, such as
insurance, taxes,F.I~C.A., workmen's compensation, unemployment taxes, and union
benefits.
(2) Cost of all materials, supplies and equipment incorporated in the changed \vork.
GeneraVSpecslCondtns.gen
<9 1996 Bonestroo, Rosenet
Anderlik & Associates, Inc.
- 42-
(3) Cost, including maintenance of all materials, supplies, equipment, temporary faciiities
and hand tools owned by workmen, which are consumed in the perlorrnance of the
changed work, and cost less salvage value on such items used but not consumed which
remain the property of the Contractor.
(4) Rental charges of all necessary machinery and equipment, exclusive of hand tools,
used in performing the changed work, including installation, minor repairs and
replacements, dismantling, removal, transportation and delivery costs thereof at rental
charges consistent \vith those prevailing in the area.
(5) Cost of additional premiums for all bonds and insurance which the Contractor is
required by the Owner or contract documents to purchase and maintain and which is
incurred as a result of performing the changed work.
(6) Sales, use or similar taxes, related to the changed work and for \vhich the Contractor
is liable, imposed by any governmental authority.
(7) Permit fees, royalties, damages for infringement of patents and costs of defending suits
therefore, and deposits lost for causes other than the Contractor1s negligence.
(8) Losses and expenses, not compensated by insurance or other\vise sustained by the
Contractor in connection with the changed work provided they have resulted from causes
other than the sole or joint fault or neglect of the Contractor, any Subcontractor, anyone
directly or indirectly employed by any of them, or for whose acts any of them may be
liable. Such losses shall include settlements made with the written consent and approval
of the Ovvner. No such losses and expenses shall be included in the cost of the changed
work for the purpose of determining the Contractor's fees thereon. If, however, such loss
requires reconstruction and the Contractor is placed in charge thereof, he shall be paid for
his services an additional fee computed in proportion to the sum stated above for the
original changed work.
(9) Cost of "drayage,1I exclusive of any drayage between shop and jobsite, only when
Contractor must hire an independent trucking firm and driver to perform special drayage
services in p,erformance of the changed work for which Contractor's skills, manpower and
vehicles are inadequate. "Drayage" does not include transportation performed or which
could have been performed by Contractor's drivers or vehicles but for their use on another
project.
(10) Costs incurred due to an emergency arising out of the charlged work affecting the
safety of persons and property.
( 11) Other costs incurred in the performance of the changed work if and to the extent
approved in advance in writing by the O\vner.
GeneraliS pecs/Condtns .gen
@ 1996 Bonestroo. Rosene,
Anderlik & Associates, Inc.
, -.43-
(12) Cost of Subcontractors in perfonning theContractorls work as changed shall be
computed in accordance with this paragraph 11.3.3, computed in accordance with clauses
11.3.1, .2, or .3.
b. The cost of the changed \vork shall exclude:
(1) Salaries or other cOlllpensation for Contractor's officers, executive, general managers,
project managers, estimators, engineers, timekeepers, surveyors, mechanics,
\varehousemen, auditors, accountants, purchasing and contracting agents, draftsmen
(except sheetmetal draftsmen), stenographers, receptionists, and other staff employees,
whether or not employed at Contractor's principal office, branch, office or field office at
the job site.
(2) Expenses of Contractor's principal office, branch office or job site field office,
including without limitation the expense for pickup trucks, office trailers, storage trailers,
rental of office or storage space, telephone, heat, lights, etc.
(3) Ownership cost of maintenance expenses for Contractor-o\vnedequipment, including
without limitation all construction equipment, trucks fuld vehicles, machines and all other
o\vned equipment required for Contractor's performance of the Work.
(4) Cost for purchas~ and maintena~ce of.lo91s,materials, supplies and facilities not
consumed during construction or incorporated In the work.
(5) Contractor's capital expense,. including interest onContractorts capital employed for
the work.
(6) Overhead or general e.xpenses of any kind, including but 110t limited to office or
fabrication shop overhead or drafting and printing costs, except as may be expressly
included in clause 11.3.3.1a above.
(7) Costs due to the negligence of Contractor, any Subcontractor, anyone directly or
indirectly employed by any of them, or for \vhose acts any of them may be liable, including
but not limited to injury or damage to persons or property, the correction of defective
work, disposal of materials and equipment wrongly supplied, or making good any damage
to property.
(8) The cost of any item not specifically and expressly included in the terms described in
clause 11.3.3.1 a above.
GenerallSpecs/Condtns. gen
@ 1996 Bonestroo, Rosene,
Anderlik & Associates, Inc.
. - 44-
2. Allowances for profit, overhead and nonreimbursable costs shall be computed as follows:
a. For the Contractor:
(1) A minimum of 5% up to a maximum of 15% (the actual rate dependent of the
Contractor's performance and assumed risks as determined in the sole discretion of the
Owner) of all reimbursable costs defined in clauses 11.3.3.1a (1) through (12) above, and
(2) A minimum of 30/0 up to a maximum of 70/0 (as determined at the sole reasonable
discretion of the Owner) for the work of Subcontractors supervised by the Contractor as
computed in accordance with clause 11.3.3. No fee \vill be allowed on Subcontractor
work not supervised by the Contractor.
(3) For first, second, and other tier Subcontractors claiming compensation for changed
work under clause 11.3.3.1(a) (12), their allowances shall be determined at the sole
reasonable discretion of theOv/ner consistent with percentages in subclause (2) directly
above.
(4) The Owner shall have the right to examine, inspect, copy and audit the books and
records of any Contractor or Subcontractor making claim for reimbursement for costs arid
allowances hereunder in order to verify the accuracy, correctness, completeness and
propriety of all costs and allowances claimed.
11.4 CH~ANGE OF CONTRACT TIIvIE
11.4.1 The Contract Time may only be changed by a Change Order. i\ny claim for an
extension in the Contract Time shall be based on written notice delivered to O\vner and
Engineer within ten (10) days of the occurrence of the event giving rise, to the claim. I'lotice
of the extent of the claim with supporting data shall be delivered within thirty (30) days of
such occurrence unless Engineer allows an additional period of time to ascertain more
accurate data. All claims for adjustment in the Contract Time shall be determined by Engineer
if Ovvner and Contractor cannot otherwise agree. An)' change in the Contract Time resuiting
from any such claim shall be incorporated in a Change Order.
11.4.2 The Contract Time will be extended in an amount equal to time lost due to delays
beyond the control of Contractor if a claim is made therefor as provided in paragraph 11.4.1.
Such delays shall include, but not be limited to, acts or neglect by Owner, or to fires, floods,
labor disputes~ epidemics, abnormal weather conditions, or acts of God.
11.4.3 All time limits stated in the Contract Documents are of the essence of the Agreement.
The provisions of this paragraph 11.4 shall not exclude recovery for damages (including
compensation for additional professional services) for delay by either party.
GenerallSpecslCondtns .gen
@ 1996 Bonestroo, Rosene.
Anderlik & AssOCiates, Inc.
. - 45 ..
SECTION 12
SUSPENSION OF WORK AND TERMIl'rATIOr~
12.1 OWNER MAY SUSPEND WORK
Owner may, at any time and without cause, suspend the Work or any portion thereof for a period of
not more than ninety days by notice in writing to Contractor and Engineer which shall fix the date
on which Work shall be resumed. Contractor shall resume the Work on the date so fixed.
Contractor will be allowed an increase in the Contract Price or an extension of the Contract Time,
or both, directly attributable to any suspension if he makes a claim therefor as provided in Sections
10 and 11.
12.2 OWNER MAY TERMlNATE
12.2.1 Upon the occurrence of anyone or nlore of the following events:
(a) If Contractor is adjudged a bankrupt or insolvent,
(b) If Contractor makes a general assignment for the- benefit of creditors,
........
(c) If a trustee or receiver is appointed for Contractor or for any of Contractor IS prGperty~
(d) If Contractor files a petition to take advantage of any debtorls act, or to reorganize under
the bankruptcy or similar la\vs,
(e) If Contractor repeatedly fails to supply sufficient skilled \vorkmen or suitable materials
or equipment,
(f) If Contractor repeatedly fails to make prompt payments to Subcontractors or for labor,
materials or equipment,
(g) If Contractor disregards lavy's, ordinances, rules, regulations or orders of any public body
having jurisdiction,
(h) If Contractor disregards the authority of Engineer, or
(I) If Contractorother\vise violates in any substantial way any provisions of the Contract
Documents,
GeneraliS pecs/Condtns.gen
@ 1996 Bonestroo, Rosene,
Anderlik & Associates, Inc.
. - 46 ..
Owner may after giving Contractor and his Surety seven days' written notice, terminate the services
on Contractor, exclude Contractor from the site and take possession of the ~Work and or all
Contractor's tools, appliances, construction equipment and machinery at the site and use the same
to the full extent they could be used by Contractor (without liability to Contractor ror trespass or
conversion), incorporate in the Work all materials and equipment stored at the site or for which
Owner has paid Contractor but which are stored else\vhere, and finish the Work as OVv'ner may deen1
expedient. In such case Contractor shall not be entitled to receive any further payment until the
Work is finished. If the unpaid balance of the Contract Price exceeds the direct and indirect costs
of completing the Wark, including compensation for additional professional services, such excess
shall be paid to Contractor. If such costs exceed such unpaid balance, Contractor shall pay the
difference to Owner. Such costs incurred by Owner shall be verified by Engineer and incorporated
in a Change Order, but in finishing the Work, Owner shall not be required to obtain the lowest figure
for the Wark performed.
12.2.2 Where Contractor's services have been so terminated by O\vner, the tennination shaH not
affect any rights of Owner against Contractor then existing or which may thereafter acc.rue. ..Any
retention or payment of moneys due Contractor by Owner will not release Contractor from liability.
12.2.3 Upon seven days I written notice to Contractor and Engineer, OVvner may, \vithout cause and
without prejudice to any other right or remedy, elect to abandon the Work and terminate the
Agreement. In such case, Contractor shall be paid for all Work executed and any expense sustained
plus reasonable termination expenses.
12.2.4 If, after notice or termination for failure to fulfill contract obligations, it is deteI1T\ined that
the Contractor has not defaulted, the termination shall be deemed to have been effected ror the
convenience .of the Owner and the Contractor shall be paid in accordance \vith paragraph 12.3.
12.3 CONVENlENCE TERMINATION BY THE OWNER
The Owner reserves the right to terminate the Work under this contract in whole, or from tilne to
time in part, and said tennination for convenience shall not be construed as a breach of the Contract.
If the Contract is terminated for convenience, the Owner shall give the Contractor written notice
specifying the extent the W orkof the Contract that is being terminated and the effective date of said
termination. Upon receipt of the notice of termination, the Contractor shall stop vvork on the date
and to the extent specified.
The Contractor shall place no further orders nor incur any further costs for the terminated parts of
the Work. The Contractor shall further terminate all orders and subcontracts relating to the
terminated part of the Wark. The Owner shall pay the Contractor for the value of the Wark
terminated as completed to the termination date together with a reasonable profit on the completed
Work, but no damages or costs or lost profits. Disposition of the completed parts of the terminated
work, materials, equipment and other tangible property shall be made as agreed upon by the Owner
and Contractor. The title to any property and materials retained by the Owner shall accrue to the
Owner immediately upon payment by the Owner to the Contractor.
GeneraliS pecs/Condtns .gen
@ 1996 Bonestroo, Rosene,
Anderlik & Associates, Inc.
. .. 47 ..
12.4 CONTRACTOR MAY STOP WORK OR TERMThTA TE
If, through no act or fault of Contractor, the Wark is suspended for a period of more tl1an ninety d.ays
by Owner or under an order of court or other public authority ~ or Engineer fails to act on any
Application for Payment within thirty days to pay Contractor any sum finally determined. to be due,
the Contractor may, upon seven daysl written notice to Owner and Engineer, terminate the
Agreement and recover from Owner payment for all Wark executed and any expense sustained plus
reasonable termination expenses. In addition and in lieu of terminating the Agreement, if Engineer
has failed to act on an Application for Payment or Owner has failed to ma..1(e any payment as
aforesaid, Contractor may upon seven days' notice to Owner and Engineer stop the Work until
payment of all amounts then due. The provisions of this paragraph shall not relieve Contractor of
his obligations to carry on the Work in accordance with the progress schedule and without delay
during disputes and disagreements with Owner.
SECTION 13
MISCELLANEOUS
13.1 LTh1IT A TION OF LIABILITY
In no event, either as a result of breach of contract, negligence, or otherwise, shall theOw~eror
Engineer or their agents or Employees be liable for damages or loss of profits, loss of use, loss of
revenue, loss of bonding capacity ,or any other special, indirect or consequential damages of any
kind. To the extent the Contract Documents allow any liability to be imposed, the total liability of
the Owner and Engineer for any loss, claim, or damage arising out of this agreement or the
performance or breach thereof, shall be limited to the value or the work performed.
13.2 REMEDIES
The duties and obligations imposed by these General Conditions and the rights and remedies
available hereunder to the parties hereto, and, in particular but without limitation, the warranties,
guarantees and obligations imposed upon Contractor herein and all of the rights and remedies
available to Owner and Engineer thereunder, shall be in addition to, and shall not be construed in
any way as a limitation of, any rights and remedies available to any or all of them \vhich are
otherwise imposed or available by law or contract, by special warranty or guarantee or by other
provisions of the Contract Documents, and the provisions of this paragraph shall be as effective as
if repeated specifically in the Contract Documents in connection with each particular duty,
obligation, right and remedy to which they apply. All representations, warranties and guarantees
made in the Contract Documents shall survive final payment and tennination or completion of this
Agreement.
GeneraliS pecslCondtns.gen
<9 1996 Bonestroo. Rosene,
Anderlik & Associates. Inc.
- 48 -
13.3 PUBLICCONVENlENCE
The Contractor shall at all times so conduct his work as to insure the least possible obstruction to
traffic and inconvenience to the general public and the residents in the vicinity of the Work, and to
insure the protection of persons and property. No road or street shall be closed to the public except
with the permission of the O\\'ner and proper governmental authority. Fire hydrants on or adjacent
to the Work shall be kept accessible to fire-fighting equipment at all times. Temporary provisions
shall be made by the Contractor to insure the use of sidewalks and the proper functioning of all
gutters, sewer inlets, drainage ditches and irrigation ditches, which shall not be obstructed.
13.4 CROSSmG UTILITIES. ETC.
Where the prosecution of tl1e -Work results in the crossing of high\vays, railroads, streets or utilities
under the jurisdiction of state, county, city or other public or private entities, the Contractor shall
secure written permission frail1 the proper authority to cross said highway, railroad, street or utility
before further prosecuting the Work. A copy of the written document granting permission shall be
filed with the Owner and Engineer before any Work is done. The Contractor shall be required to
obtain a written release from the applicable authority upon completion of the Vv" ark. A copy of this
written release shall be filed with the Owner and Engineer before final acceptance of the Vvork is
granted.
13.5 SANITARY PROVISIONS
The Contractor shall provide and maintain such sanitary facilities for the use of his employees and
those of his Subcontractors as may be necessary to comply with ~he la\vs, rules or regulations of the
Federal, State and local governments, or agencies or departments thereof.
13.6 PRESERVATION OF HISTORICAL OBJECTS
13.6.1 Where historical objects of potential archeological or paleontological nature are discovered
within the areas on which the Contractor's operations are in progress, the Contractor shall restrict or
suspend his operations in the immediate area of the discovery as may be necessary to preserve the
discovered objects until the Owner has made arrangements ror their disposition or has recorded the
desired data relative thereto.
13.6.2 The Contractor shall immediately notify the Owner of any historical objects he may discover
or become aware of as the Work is being prosecuted, and shall aid in the preservation and salvage
program decided upon, as may be requested or ordered by the Owner. No VVork which the
Contractor considers to be Extra Wark shall be performed without the written authorization of the
Owner.
GeneralJSpecs/Condms. gen
@ 1996 Bonestroo, Rosene.
Anderlik & Associates, Inc.
. - 49-
13.6.3 The Owner shall have the right to restrict or suspend the Contiactorts operations in the
immediate area where historical objects are discovered for a period not to exceed 72 hours, withollt
claim being made by the Contractor for any damages he might suffer asa re~,ttlt thereof. Any
restrictions imposed shall not remain in effect for a period exceeding 72 houFs'unless mutually
agreed to in writing.
13.7 USE OF PREMISES
Contractor shall confine construction equipment, the storage of Inaterialsandequipment and the
operations or workmen to areas permitted by law, oidinances,permits or the requirements of the
Contract Documents, and shall not unreasonably encumber the premises with construction
equipment or other materials or equipment.
GeneraliS pecs/Condtns. gen
@ 1996 Bonestroo, Rosene,
Anderlik & Associates, Inc.
. ~ 50 -
FORM OF AGREEMENT
THIS AGREEMENT, made and signed this 26th day of July
, 2000, by and
between City of New Hope, hereinafter called the "Owner", and G L Contracting Ine hereinafter
called the "Contractor".
THIS AGREEMENT WITNESSETH, that the Owner and the Contractor, for the
consideration hereinafter stated, agree as follows:
ARTICLE I. The Contractor hereby covenants and agrees to perform and execute all the
provisions of the drawings and specifications as prepared by Bonestroo, Rosene, Anderlik &
Associates, Inc., of St. Paul, Minnesota, and indicated below under ARTICLE IV, as provided by the
Owner for:
Storm Water Improvements, City Project No. 691, BRA File No. 34-00-125
and to do everything required by this Agreement and the Contract Documents.
ARTICLE II. The Contractor agrees that the Work contemplated by this Contract shall be
fully and satisfactorily completed on or before the completion date(s) as specified.
ARTICLE III. The Owner agrees to pay and the Contractor agrees to receive and accept
payment in accordance with the prices bid for the unit or lump sum items as set forth in the
conformed copy of Proposal Form hereto attached, which prices shall conform to those in the
accepted Contractor's Proposal on file, the aggregate of which prices, based on the approximate
schedule of quantities, is estimated to be $101,493.32 or One hundred one thousand four hundred
ninety-three and 32/100 Dollars.
The contract is awarded on the Base Bid plus Alternate 1 minus Item Nos. 24, 39, & 40.
ARTICLE IV. The Contract Documents shall consist of the following component parts:
(a) Drawings
(b) Specifications:
(1) Bid Documents (Advertisement, Addenda, Information to Bidders, Proposal
and Bid Security);
(2) Special Provisions;
(3) General and Specific Requirements;
(4) Conditions of the Contract (General and other conditions);
(5) Performance and Payment Bond;
(6) Agreement;
(7) Detail Plates and other drawings attached to specifications
@ 2000 Bonestroo, Rosene,
Anderlik & Associates, Inc. 51
I: \34\3400 125\ W ord\Specifications\Con tract_ Condi tions\p51-61.doc "
General Construction Contract
Between Owner & Contractor
This Agreement, together with the document hereinabove mentioned, form the Contract and all
documents are as fully a part of the Contract as if attached hereto or herein repeated.
IN WITNESS WHEREOF, the parties to this Agreement have hereunto set their hands and seals
as of the day and year first above written.
Attest:
The
City of New Hope
(Seal)
~"r" (
l",-, _' ' ,.'f-'/
Il,('.' 1, If/} j-I [', I) [ ,::"1..---, r- ,r'
vC~,,'-vCX-,< /-fU-'i / lJL-
By
By
OWNER
//~:<:......
In the,}1resence of:
~=,=(:S
G ~ Conttactinglnc
CONTRACTOR
By /"::\Z,~/~~,""-<'-'~:.' '<~r(_L, ",~ ______________
.... :<i,:.\
J-,,,:' .'
.~ ....:~.....~... ....~....;::;..........~~....,......_~:.:..:.::... ....,,;.. .............~
TITLE
.....:/'...,
CERTIFICATE OF ACKNOWLEDGEMENT
State of Minnesota )
","< . . ) S S .
County 0 f\_lJLlL:;LfL/Ai},
On this day, t'~4~j_,f.iLi fj l , 2000, before me personally appeared
Ii .1, f:tllcY"ilcf":- , to meUpersonally known, being by me duly sworn, did say that he is the
Representative of the City of New Hope, that the seal affixed to the foregoing instrument is the seal
of said City of New Hope, and that said instrument was executed on behalf of the Owner, and said
,D,fji"?<]~/r-:r7 ,/ acknowledged the instrument to be the free act and deed of said
CitY of New Hope.
, // ./' r /. .' ..'
(~_/':l'7/&~IP./~.'->:::)G-Lj-ta--({J/&f'
(Notarial Seal) Signature of Notary Public t/
@ 2000 Bonestroo, Rosene,
Anderlik & Associates, Inc. 52
1:\34\3400 125\ W ord\Specifications\Contract_ Conditions\pS l..{). Ldoc-
General Construction Contract
Between Owner & Contractor
CERTIFICATE OF ACKNOWLEDGMENT
(For use where Contractor is individual or partnership)
State of Minnesota )
) SS.
County of )
On this day of , 2000, before me personally appeared
, to me personally known to be the person described in and who
executed the foregoing instrument and acknowledged that _he executed the same as the free act and
deed of the individual.
(Notarial Seal)
Signature of Notary Public
CERTIFICATE OF ACKNOWLEDGMENT
(For use where Contractor is a corporation)
State of Minnesota )
) SS.
County of 7'/ t/j'v,>_j{,?7 'i'~--)-'
On this 2~ b day of "j , 2000, before me personally appeared
:> jr",,..'iC,,? ~/v ~,4t:?'-"/{,~ .~;",>-" an.d-. , to me personally known who, being by me
duly sworn, each did say that they are respectively the p {:~~ f:;"'~ L '? ~i"~"\_/, aE.,tl~'
of G L Contracting Ine, that the seal affixed to the foregoing instrument is the
corporate seal of said corporation, and that said instrument was executed in behalf of the corporation
by authority o~+~i~~~d2f,,~DiJectors and said and
_ ac~~~~c''''''~~e the free act and deesI of the corporation.
f~'} fi l.Ib~Ot:~ /
I /~~
~
(Not~.rIaTsea~~<~~(:;'~'~~gnature of Notary Public
@ 2000 Bonestroo, Rosene,
Anderlik & Associates, Inc. 53
1:\34\3400 125\ W ord\Spe,cifications\Contract_ Conditions\pSl..61.doc-
General Construction Contract
Between Owner & Contractor
GLeON
;.A.c:;ORD;,...;.GER."'IIElb.lX.fElS:d.eiINSW_liit.r....::i><.. .... ................<.......:<>.;....; DATE (MM/DDNY)
:::':,::, -..'.':':-:':-:< :>>.',', .'...... .. -, . .:??:': ::':'::;: :': ' '<.:::::."> .-::::..=.. :::.:::::.:::::::::. ,.::. ::::'. )>/>:'... .>?_ .. .'::: .:>::::::.' '__ :':,.. ,:-','_ ,<::..:-. .-::.'::', .' . :':':. ,'., <: .::-. '::/: ;.::?;'?/:</:::t:=:::::<:(=:::\t\?< .. - -.. ..-c,:,::::::';:,,:'.:.:.':',"':, .,.'.... . 0 7 / 2 6 / 0 0
PRODUCER THIS CERTIFICATE IS ISSUED AS A MA ITER OF INFORMATION
Cedarleaf I Cedarleaf &Cedarleaf ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE
360 W Larpenteur Ave HOLDER. THIS CERTIFICATE DOES NOT AMEND, EXTEND OR
POBox 6471 7 ALTER THE COVERAGE AFFORDED BY THE POLICIES BELOW.
5 516 4 COMPANIES AFFORDING COVERAGE
Saint Paul, MN
G L Contracting,
4300 Willow Drive
Medinal MN 55340
Inc
COMPANY
ACNA
I COM~~Y
COMPANY
C
I COM~ANY
Insurance Companies
INSURED
THIS IS TO CERTIFY THAT THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD
INDICATED. NOTWITHSTANDING ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS
CERTIFICATE MAY BE ISSUED OR MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS,
EXCLUSIONS AND CONDITIONS OF SUCH POLICIES. LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS.
08t I TYPE OF INSURANCE I
A I GENERAL LlABIUlY I
X COMMERCIAL GENERAL LIABILITY
I_I CLAIMS MADE [XJ OCCUR i
_ OWNER'S & CONTRACTOR'S PROT
X Prol ect Aqq
1-
A I AUTOMOBILE LIABILITY
fXl ANY AUTO
~ ALL OWNED AUTOS
SCHEDULED AUTOS
LxJ HIRED AUTOS
H NON-OWNED AUTOS
~RAGe LIABILITY
R ANY AUTO
A I EXCESS LIABIUTY
fXl UMBRELLA FORM
n OTHER THAN UMBRELLA FORM
A WORKERS COMPENSATION AND
EMPLOYERS'llABILlTY
POUCY NUMBER
1 POLICY EFFECTIVE I POUCY EXPIRA nON I
1 DATE (MM/DDIYY) DATE (MM/DDNY)
04./01/00 104/01/01 I GENERAL AGGREGATE
PRODUCTS..cOMP/OP AGG
UMITS
C135059047
1$2,000 000
IS1, 000,000
PERSONAL & ADV INJURY I sl ,- 0 0 0 , 0 0 0
I EACH OCCURRENCE Is1 , 000 I 000
FIRE DAMAGE (Anyone fire) Is 100 I 000
I MED EXP (Anyone person) Is 5 , 000
104/01/00 04/01/011 I
,COMBINED SINGLE LIMIT $1, 000 I 000
Is
Is
Is
Is
1-;;::::=-::,::>,:-:,.:-:.:.: ,'.' .,...
EACH ACCIDENT 1$
AGGREGATE Is
o 4 / 0 1 / 0 0 0 4 / 0 1 / 0 1 I EACH OCCURRENCE 1 $5 1 0 0 0 I 0 0 0
I AGGREGATE Is5 1 000 , 000
Is
04 / 01/ 0 0 04/ 0 1/ 01 X I STATUTORY LIMITS LH))::.rtH(}':::}:}:\)':(:::::::::/
EACH ACCIDENT Isla 0 I 0 0 0
I DISEASE.POLlCY LIMIT 1 $5 0 0 , 0 0 0
o ISEASE- EACH EM PLOYEE 1$10 0 I 0 0 0
BODILY INJURY
(Per person)
C117587219
CI017587222
BODILY INJURY
(Per accident)
I PROPERTY DAMAGE
I AUTO ONl Y-EA ACCIDENT
OTHER THAN AUTO ONLY:
WC117587236
THE PROPRIETOR!
PARTNERS/EXECUTNE
OFFICERS ARE:
OTHER
RI INCL
EXCL
DESCRIPTION OF OPERA T10NS/lOCA 110NSNEHICLES/SPECIAL ITEMS
Job: Public Works Storm Water Improvements City Project No 691
SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE THE
EXPIRATION DATE THEREOF. THE ISSUING COMPANY WILL MAIL
3..0.- DAYS WRITTEN NOTICe TO THE CERTIFICATE HOLDER NAMED TO THE LEFT,
City of New Hope
4401 Xylon Ave
New Hope
I MN
55428
.. AUTHO~DR:?J:S€NTA~~CiuL- -. . .... .
ApQRP252~(~/~3jl()fl:m.#M6:939.:::::.::i;:::::\;::::::[rit:::::~;:::tAM::.~A(;6RPOPRPQRA:tIQif1~93
Bond No. 54~113522
PERFORMANCE BOND
KNOW ALL MEN BY THESE PRESENTS: that G L Contracting Ine as Principal (hereinafter
called
Contractor)
and,
~On1ted Fire & C.asu.al ty Company
as Surety (hereinafter called Surety) are held and firmly
bound unto City of New Hope as Obligee (hereinafter called Obligee) in the amount of $101,493.32
or One hundred one thousand four hundred ninety-three and 32/100 Dollars for the payment
whereof Contractor and Surety bind themselves, their heirs, executors, administrators, successors
and assigns, jointly and severally, firmly by these presents.
The contract is awarded on the Base Bid plus Alternate 1 minus Item Nos. 24, 39, & 40.
.,- -; _ r);{"
WHEREAS, Contractor has by written agreement dated JULy LO , 2000, entered into
a contract with the Obligee for construction of Storm Water Improvements, City Project No. 691,
BRA File No. 34-00-125 in accordance with Drawings and Specifications prepared by Bonestroo9
Rosene9 Anderlik & Assoc., Inc. which contract is by reference made a part hereof: and is
hereinafter referred to as the Contract.
NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION is such that, if Contractor
shall promptly and faithfully perform said Contract in conformance with the Contract Documents,
and all guaranty, indemnity and warranty obligations specified therein, and shall promptly and
faithfully remedy any breach of its obligations under the Contract Documents discovered within the
time limits set by statute for commencement of actions, and shall pay any damages for unexcused
late completion, then this obligation shall be null and void; otherwise it shall remain in full force and
effect.
The Surety hereby waives notice of any alteration, changes or extension of time made by the
Obligee.
Whenever the Contractor shall be, and declared by the Obligee to be in default under the
Contract, the Surety may promptly remedy the default, or shall promptly:
(1) Complete the Contract in accordance with its terms and conditions, or if appropriate,
@ 2000 Bonestroo, Rosene,
Anderlik & Associates, Inc. 54
1:\34\3400 125\ W ord\Specifications\Contract_ Conditions\p51-6 Ldoc-
General Construction Contract
Between Owner & Contractor
2) Obtain a bid or bids for completing the Contract in accordance with its terms and
conditions, and upon determination by the Obligee and the Surety jointly of the lowest responsible
bidder, arrange for a contract between such bidder and Surety, and Surety shall pay such bidder
pursuant to such contract, while the Obligee shall pay the Surety the cost of completion, up to but
not exceeding the balance of the contract price. The term "balance of the contract price," as used in
this paragraph, shall mean the total amount payable by the Obligee to Contractor under the Contract
and any amendments thereto, less the amount paid by the Obligee to Contractor, of if appropriate,
(3) Promptly pay such sums to the Obligee as the Obligee may be entitled from the
Contractor under the Contract Documents, or for the breach thereof, but not exceeding the amount
set forth in the first paragraph hereof:
The surety agrees to be bound by any award granted to the Obligee against the Contractor in
arbitration or judicial proceedings commenced pursuant to the Contract Documents.
No right of action shall accrue on this bond to or for the use of any person or corporation
other than the Obligee named herein or the successors of the Obligee.
Signed and sealed this 26tb. day of
July.
, 2000.
G Ir Contr;lcting Ine
, :". . ,
By
Contractor
.Ii
f>:C:..~.... .~:.~..:."..~" ~;.,_>"....//i::~ ~
" ~'. . ...."'.., ---..,.. --
Signature
n;~\ri{1 g~ St0"S.11RO"n
(Typed or Printed name of Signer)
.-"^"....-;;:::...::.-..~-
I
!
Title
Presiclent
C::;~;;"''i,'?~-
Witness
By
Signature
(Typed or Printed name of Signer)
Title
@ 2000 Bonestroo, Rosene,
Anderlik & Associates, Inc. 55
1:\34\3400 125\ W ord\Speci fications\Con tract_ Condi tions\p51..61.;doc.
General Construction Contract
Between Owner & Contractor
(If the Contractor is a partnership or joint venture, all
partners or co-venturers must execute this Bond.)
UNITED FIRE & CASUAL TYCOEfPMrf
Surety
~Sl 00 BO:2S: 73909~Ced..ar Rapids9 L\. 52407
Address
C JJ ~
. Afl} /1..,./) /
..../ .j .'./1 ./ .f"'-
Witness
J!.".... l
O. . ,,;-:7. '.-"."'" ..
. ,~v ~,c,"l,7
1-800=343="9130
Phone No.
~
R~~~":~~' ,~~/(?~,~L:/~
,,.,,,,,.'f,e 4' / / . _m
/// Sign~ture
'/
/' ,/"
Jack Cedarleai""/II
//,.....
(Typed or Printed name of Signer)
Title Attorln,e'y~..in""'"fac.t
360 ~r~ Larpen.teu!: A"ile f:
St~ Paul, l<1.N 55113
(Local Address & Telephone Number)
(The attorney-in-fact shall attach hereto a copy of his
power of attorney or other documents which authorizes
him to act on behalf of and to bind the surety.)
@ 2000 Bonestroo, Rosene,
Anderlik & Associates, Inc. 56
1:\34\3400 125\ W ord'8pecifications\Contract_ Condi tions\p51..{il.doc-
General Construction Contract
Between Owner & Contractor
CERTIFICATE OF ACKNOWLEDGMENT BY PRINCIPAL
(For use where Contractor is individual or partnership)
State of Minnesota )
) SS.
County of )
On this day of , 2000, before me personally appeared
, to me known to be the person described in and who executed the
foregoing bond, and acknowledged that _he executed the same as the free act and deed of the
individual.
(Notarial Seal)
Signature of Notary Public
CERTIFICATE OF ACKNOWLEDGMENT
(For use where Contractor is a corporation)
State of Minnesota )
) SS.
County of )
On this 26th day of July . 2000, before me personally appeared
afitf DavidGe S'J7anson , to me personally known who, being by me duly sworn, did
say that they are respectively the President Stp~ , ofG L Contracting
Ine that the seal affixed to the foregoing instrument is the corporate seal of said corporation, and that
said instrument was executed in behalf of the corporation by authority of its Board of Directors, and
said Ilavj.~.:::^~:~o S ~ ,-,>-"~.>::~;?;,~ acknowledged the instrument to be the free
act and deed corporation. ~ "1//;, :~7
." t~ .^~-,
.~;;S~~} .",,~~~,J------. </ -'
(Notarial Seal)
Signature of Notary Public
!JDTITED FIPili &C,ASUltT.JTt COt1PP:,.rrY,f) Po 00 BOX 73909,SJ CEDllli RAPIDS;I U\ 52l!:07
Full Name & Address of Surety Company's Home Office
JACI<CED~~J-IRA.F II;: CEDp.J?iliEl1F, CED.AllI.lEl\F I; CEDAPJ.JE1~F, I~NCo, 360 ~:Jc LAlk~'!~lTEUR Av~c
Full Name, Address, Phone, and Contact Person of Local Bond Agency
St Q Paul.., rit.~:
,., J..J~3
If this bond is executed outside of the State of Minnesota, it must be countersigned on the
Performance Bond by a Minnesota resident agent of the Surety Company.
Name & Address of Agent Affixing Countersignature
MEMORANDUM: Affix here Power of Attorney and Acknowledgment of Corporate Surety.
@ 2000 Bonestro-o, Rosene,
Anderlik & Associates, Inc. 57
1:\34\3400 125\ W ord'tSpecitications\Contract_ Conditions\pS 1-61':doc'
General Construction Contract
Between Owner & Contractor
UNITED FIRE & CASUALTY COMPANY
HOME OFFICE -> CEDAR RAPIDS, IOWA
CERTIFIED ..COPY OF POWER OF ATTORNEY
(Original on file at Home Office of Company - See Certification)
KNOW ALL MEN BY THESE PRESENTS, That the UNITED FIRE & CASUAL TV COMPANY, a corporation duly organized and existing
under the laws of the State of. Iowa, and having its .principal office in Cedar Rapids, State of Iowa,. does make, constitute and
appoint D. R. DOUGHERTY, OR JACK CEDARLEAF II, ORR. J. LARSEN, OR E . LANGE,
OR CHRISTINEM. HANSEN, ORKURTC. LUNDBLAD, OR C. A. HOUSH,
ALL INDIVIDUALLY
of POBOX 64717 ST PAUL MN 55164
its true and lawful AttorneY(s)-in-Factwithpower and authority hereby conferred to sign, seal and execute in its behalf all
lawful bonds, undertakings and other obligatory instruments of similar nature as follows: ANY AN DA L L BONDS
and to bind UNITED FIRE&.CASUAL TY<COMPANY thereby asfullyahd to the same extent as if such instruments Were signed by
the duly authorized officers of UNITED FIRE & CASUAL TV COMPANY and all the acts of said Attorney, pursuant to the authority
hereby given are herebY ratified and confirmed..
The Authority hereby<grantedshall expire J ANUARY8 th 2002 unless sooner revoked.
This Power of Attorney is made and executed pursuant to and by authority of the following By-Law duly adoPted by the
Board of Directors of the Company on April 18, 1973.
"Article V - Surety Bonds and Undertakings."
Section 2,AppointmentofAttorney..in..Fact. "The President or any Vice President, or any other officer of the Company, may, from time to time,appoint
by written certificates attorneys.in..fact to act in behalf of the Company in the execution of policies of insurance, bonds, undertakings and other
obligatory instruments of like nature. The signature of any officer authorized hereby, and the Corporate seal, may be. affixed by facsimile .. to any
powerof attorney or special power of attorney or certification of either authorized hereby; such signature and seal. when so used, being adopted by the
Company as the original signature of such officer and the original seal of the Company, to be valid and binding upon the Company with the same force
and effect as though manually affixed. Such attorneys..in.fact, subject to the limitations set forth in their respective certificates of authority shall have
full power to bind the Company by their signature and execution of any such instruments and to attach the seal of the Company thereto. The f>resident
or any Vice President, the Board of Directors or any other officer of the Company may at any time revoke all power and authority previously given to
any attorney-in-fact.
IN WITNESS WHEREOF, the UNITED FIRE & CASUAL TV COMPANY has caused. these presents
to be signed by its assistant vice President and its corporate seal to be hereto affixed this
8th day of JANUARY ,A.D. 2000
State of Iowa, County of Linn, 5S:
UNITED FIRE & CASUAL1:Y COMPAfi "-
By ~Aga~tSce ~~
Onthis 8th day of JANUARY 2000, before me personally came JEFFREY A. CHAPIN
tome known, who being by me dulY sworn, did dePose and say: that he resides in Cedar RaPidst State of Iowa; that he is an
Assistant Vice President of the UNITED FIRE & CASUALTY COMPANY, the corporation described in and which executed the
above instrument; that he knows the seal of said corPoration; that the seal affixed to the said instrument is such corporated
seal; that it was so affixed pursuant to authority given.. by the Boatd of Directors of said corporation and that he signed his
name thereto pursuant to like authority. arid acknowledges same to be the act..~ and ~).:;.id co ora 'on.
~q- Notary Public
My commission expires 11-10-01
CERTIFICATION
I, the undersigned officer of the UNITED FIRE & CASUAL TYCOMPANY, do hereby certify that I have comPared the foregoing
copy of the Power of Attorney and affidavit, and the copy of the Section of the By-Laws of said Company as set forth in said
Power of. Attorney, with the ORIGINALS ON FILE IN THE HOME.. OFFICE OF SAID COMPANY, and that the same. are correct
transcripts thereof, and of the whole of the said originals, and that the said Power of AttorneY has nof been revoked and is
now infulf force and effect.
~""''''''l In testimony whereof I have hereunto subscribed my name
~#~....~. ..~.............. . ~~.~ Company this~ I-t, day of .:Jt.t/y ~ a-tJ 00
;COIPOIATE ~,( {
'i _0... f
~ SilL ..$
C"'s' ~~$
~ .",,"\,'\~
"'UIIS),"\
the
Secretary
Bond No. 54-113522
LABOR AND MATERIAL PAYlVIENT BOND
KNOW ALL MEN BY THESE PRESENTS: that G L Contracting Inc as Principal, (hereinafter
called Contractor) and,
United Fire & Casualt)~ Compan.y as Surety (hereinafter called Surety) are held and
firmly bound unto City of New Hope as Obligee (hereinafter called Obligee) for the use and benefit
of claimants as hereinbelow defined, in the amount of $101,493.32 or One hundred one thousand
four hundred ninety-three and 32/100 Dollars, for the payment whereof Contractor and Surety
bind themselves, their heirs, executors, administrators, successors and assigns, jointly and severally,
firmly by these presents.
The contract is awarded on the Base Bid plus Alternate 1 minus Item Nos. 24, 39, & 40..
WHEREAS, Contractor has by written agreement datedJ"uly 26 ~ 2000 , entered into a contract
with Obligee for construction of Storm Water Improvements, City Project No. 691, BRA File
No. 34-00-125 in accordance with Drawings and Specifications prepared by Bonestroo, Rosene,
Anderlik & Associates, fuc. which contract is by reference made a part hereof, and is hereinafter
referred to as the Contract.
NOW~ THEREFORE, THE CONDITION OF THIS OBLIGATION is such that, if Contractor
shall promptly make payment to all claimants as hereinafter defined, for all labor and material used
or reasonably required for use in the performance of the Contract and shall keep the Project free and
clear of all liens as provided in the Contract, then this obligation shall be void; othenvise it shall
remain in full force and effect, subject, however, to the following conditions:
1. Claimant is defined as one permitted by applicable law to file a Public Contractor's Bond
claim for labor, material, or both, used or reasonably required for use in the performance of the
Contract, labor and material being construed to include without limitation that part of water, gas,
power, light, heat, oil, gasoline, telephone service, rental of equipment, insurance premiums, taxes,
and any items for which a claim or lien may be filed against the Obligee under the applicable law.
2. The above named Contractor and Surety hereby jointly and severally agree with the Obligee
that every claimant as herein defined, who has not been paid in full may sue on this bond for the use
of such claimant, prosecute the suit to final judgment for such sums as may be justly due claimant,
and have execution thereon. The Obligee shall not be liable for the payment of any costs or expenses
of any such suit.
@ 2000 Bonestroo, Rosene,
Anderlik & Associates, Inc. 58
1:\34\3400 125\ W ord\Specifications\Contract_ Conditions\pSl-6 Ldoc
General Construction Contract
Between Owner & Contractor
3. No suit or action shall be commenced hereunder by any claimant:
(a) Unless claimant shall have filed a public contractors bond claim in the form and
within the time provided under applicable law, or
(b) After expiration of time for enforcement of a public Contractors bond claim by legal
action.
4. The amount of this bond shall be reduced by and to the extent of any payment or payments
made in good faith hereunder.
5. The Contractor and Surety shall keep the Project free and clear of liens and shall promptly
remove any and all liens filed against the Project by claimants.
6. The Obligee's right of action on this bond, or for the breach thereot: shall not be limited by
the conditions set forth in paragraphs 1 through 3 above.
/~'
G L <;ontract~ In"c
" ,/
By
Contractor
xl
/"" "
".,//
~/' '" _/"
;<.----~.':'.... /
:.._.." .<...........v. ....._
.,',....------...,-----..................---~.., '
\ ;;... <'..''-[f .~"-Z )\
\i Signature
David Go Swanson
(Typed or Printed name of Signer)
~.::~'
.<:/~,,:;. .;::
Title
]?resid'ent
: ,,/ t,.. /
('---i--~''''---
Witness
By
Signature
(Typed or Printed name of Signer)
Title
(If the Contractor is a partnership or Joint venture, all
partners or co-venturers must execute this Bond.)
@ 2000 Bonestroo, Rosene,
Anderlik & Associates, Inc. 59
1:\34\3400 125\ W orcMpecifications\Contract_ Conditions\pSl-61 ~doc
General Construction Contract
Between Owner & Contractor
(If the Contractor is a partnership or joint venture, all
partners or co-venturers must execute this Bond.)
ImITED FIRE & CASUALTY CO~~A1ri
Surety
PoOi) B01:; 739:(91) Cedar Rapids, IA 52407
Address
1'"0800- 343 ~9130
Phone No.
I~i j): '.
I 111/7;,,/'} ,..
\..- ~//f j/ VL/'..,;;.~/
Witness
~ J / ,
XI ~~2e/l"-uf
__''----/"/ . /")~? ~7/
B~~%_/ /~;E~2/j&;~
///' / -, Signature:,';'/
// . " k """"Co ~ -~, '""', +: T/~//
Jac_ C_daL__aL __
(Typed or Printed name of Signer)
Title
360 w~
1:1-;; e 0
Ste
55113
(Local Address & Telephone Number)
1-651-4a8~ ,6666
(The attorney-in-fact shall attach hereto a copy of his
power of attorney or other documents which authorizes
him to act on behalf of and to bind the surety.)
@ 2000 Bonestroo, Rosene,
Anderlik & Associates, Inc. 60
1:\34\3400125\ W ordlSpecifications\Contract_ Condi tions\pS 1...(), l':doc
General Construction Contract
Between Owner & Contractor
ACKNOWLEDGMENT OF SURETY
STATE OF: Minnesota
COUNTY OF: Ramsey
On this day, July 26, 2000, before me personally come(s)
Jack Cedarleaf II, to me personally known, who being by me duly sworn,
did say that he is the aforesaid officer or attorney-in-fact of the United
Fire & Casualty Company a corporation; that the seal affixed to the foregoing
instrument is the corporate seal of said corporation, and that said
instrument was signed and sealed in behalf of said corporation by the
aforesaid officer, by authority of its board of directors; and the aforesaid
officer acknowledged said instrument to be the free act and deed of said
corporation.
~~,o
{'1 ,~"",~~.iJ
~Q ~;(~~
'r
~,~'
CHRISTINE M. HANSEN'
NOTARY PUBLIC. MINNESOTA
My Commission Expires Jan. 31, 2005
CA~ j}1~ 1a~~,J
Notary Public
.""""" "'-. . ~ ....
CHI 84964
UNITED FIRE & CASUALTY COMPANY
HOME OFFICi: - CEDAR RAPIDS, IOWA
CERTIFIED ..COPY OF POWER OF ATTORNEY
(Original on file at Home Office of Company - See Certification)
KNOW ALL MEN BY THESE PRESENTS, That the UNITED FIRE & CASUALTY COMPANY. a corporation duly organized and existing
under the laws of the State of Iowa, and having its Principal office in Cedar Rapids, . State of>lowa, does make, constitute and
appoint D. R. DOUGHERTY, OR JACK CEDARLEAF II, ORR. J. LARSEN, OR E. LANGE,
OR CHRISTINEM. HANSEN, OR>KURT C. LUNDBLAD, OR C. A. HOUSH,
ALL INDIVIDUALLY
of POBOX 64717 STPAUL MN 55164
its true and lawful Attorney(s)-in-Factwith power> and authority hereby conferred to sign, seal and execute in its behalf all
lawful bonds, undertakings and other obligatory instruments of similar nature as follows: ANY AND AL LB 0 N DS
and to bind UNITED FIRE & CASUAL TYCOMPANY thereby asfullvahd to the same extent as if such instruments were signed by
the duly authorized officers of UNITED FIRE & CASUAL TV COMPANY and all the acts of said Attorney, pursuant to the authority
herebY given are herebY ratified and confirmed.
The Authority hereby granted shall expire J A N UA RY 8 t h 20 0 2 unless sooner revoked.
This power of Attorney is made and executed pursuant to and by authority of the following By-Law duly adoPted by the
Board of Directors of the Company on April 18, 1973.
"Article V - Surety Bonds and Undertakings."
Section 2, Appointmentot Attorney-in-Fact. "The President or any Vice President, or any other officer of the Company, may, from time totime,appoint
by written certificates attorneys-in~fact to act in behalf of the Company in the execution of policies of insurance, bonds, undertakings and other
obligatory instruments of like nature. The signature of any officer authorized hereby, and the Corporate seal, may be affixed by facsimile to any
powerof attorney or special power of attorney or certification of either authorized hereby; such signature and seal, when so used, being adopted by the
Company as the original signature of such officer and the original seal of the Company, to be valid and binding upon the Company with the same force
and effect as though manually affixed. Such attorneys~in.fact, subject to the limitations set forth in their respective certificates of authority shall have
full power to bind the Company by their signature and execution of any such instruments and to attach the seal of the Company thereto. The President
or any Vice President, the Board of Directors or any other officer of the Company may at any time revoke all power and authority previously given to
any attorney~in~fact.
IN WITNESS WHEREOF, the UNITED FIRE & CASUALTY COMPANY has caused these presents
to be signed by its assistant vice president and its corporate seal to be hereto affixed this
8th day of JANUARY ,A.D. 2000
State of Iowa, County of Linn, 55:
UNITED FIRE & CASUALTY COMPA~ "'-
By ~Aga~t~ce ~:~
Onthis 8 th day of J AN UA R Y 2 0 00, before me personally came JEFFREY A. CHAPIN
to me known, who being by me duly sworn, did depose and say: that he resides in Cedar Rapids, State of Iowa; thafhe is an
Assistant Vice President of the UNITED FIRE & CASUALTY COMPANY, the corporation described in and which executed the
above instrument; that he knows the seal of said corp,oration; that the seal affixed to the said instrument is such corporated
seal; that it was so affixed pursuant to authority given by the Board of Directors of said corporation and that he signed his
name thereto pursuant to like authority, and acknowledges same to be the act... aa~n.d ~.. ~id co ora. 'on.
~t Notary Public
My commission exPires 11-10.....01
CERTIFICATION
I, the undersigned officer of the UNITED FIRE & CASUAL TYCOMPANY, do hereby certify that I have comPared the foregoing
copy of the Power of Attorney and affidavit, and the copy of the Section of the By-Laws of said Company as set forth in said
Power of Attorney, with the ORIGINALS ON FILE IN THE HOME OFFICE OF SAID COMPANY, and that the same are correct
transcripts thereof, and of the whole of the said originals, and that the said Power of Attorne'i has not been revoked and is
now infuH force and effect.
~"Ut"l7l In testimonywherebfl have hereunto subscribed my name
~~i~;~~il Company thisoL "f~ day of rJ I.!-/'j ;J-o () "
'::) SIlL -rS
('''a~. ~~$
~~ ..,.\.. \'\~
"'J " 1\\\
the
CERTIFICATE OF ACKNOWLEDGMENT BY PRINCIPAL
(For use where Contractor is individual or partnership)
State of Minnesota )
) SS.
County of )
On this day of , 2000, before me personally appeared
. to me lmown to be the person described in and who executed the
foregoing bond, and aclmowledged that _he executed the same as the free act and deed of the
individual.
(Notarial Seal)
Signature of Notary Public
CERTIFICATE OF ACKNOWLEDGMENT
(For use where Contractor is a corporation)
State of Minnesota )
) SS.
County of )
On this 26th day of July . 2000, before me personally appeared
XX}'" Davl.a .\.;:G Swanson ..
ana. r lJ~iW~.&ersonally lmo~x.who, bemg by me duly sworn, did say
that they are respectively the ana " of G L
Contracting Ine that the seal affixed to the foregoing instrument is the corporate seal of said
corporation, and that said instruIp.~nt, wC;lSexecllted in.behalf of the corporation by authority of its
Board of Directors, and said Dav:Let b.~wanson m aclmowledged
the ins . ...~~ act an4,de~(f id corp~n.
;""'~~l '
I
~;-~::~:~,..,'//..--..--".,./
tTl~ITED FIP~ &CASU~.LTYCO!ilP~l\lY, Po OoBOl{ 13909,CEDl~R ~LLl?IDS~ lA. 52407
Full Name & Address of Surety Company's Home Address
Jp~CK CEDh..RLIt\.F II, CEDARLEAF $ CEDl\P~EAF& CEDAPJ-:EAF, Il'lC Q Z' 3,60 t,;] Q L.4..RPEI'4TEUR. Av~.~
Full Name, Address, Phone & Contact Person of Local Bond Agency
~ 1"0 1: AUIJ $ 1~;J :)j 1.J..,j
If this bond is execute,d outside of the State of Minnesota, it must be countersigned by a Minnesota
resident agent of the Surety Company.
Name & Address of Agent Affixing Countersignature
MEMORANDUM: Affix here Power of Attorney and Aclmowledgment of Corporate Surety.
<9 2000 Bonestroo, Rosene)
Anderlik & Associates, Inc. 61
1: \34\3400 125\ W ord\Specifications\Con trac t_ Cond i tions\pS 1-6 Ldoc
General Construction Contract
Between Owner & Contractor